Punch List

www.GQIS.co.uk

HPC-HINKLEY POINT C-AGGREGATE JETTY-


Customer: Edgen Murray Project Name:
PRELIMINARY STEEL PILE PROJECT

Vendor: ESC GROUP Sub-Vendor: ZHEJIANG CHANKONG STEEL PIPE CO.,LTD

Vendor Address: PUTUO, SHANG HAI, CHINA Sub-Vendor Address: TIANNING, JIASHAN, ZHEJIANG

Purchase Order No: 3568

Punch List Items


Date Raised Current Closed Remark
Item No. Description
Statu Date
s
3568-C05-068 Flexible hose length not conformity with drawing requiremnt 2016-09-01 Closed 2016-09- Confirmed
11 result OK
3568-C03-063 Found three indication at weld seam during perform MT. 2016-09-02 Closed 2016-09- Checked again
02 after repair
3568-C06-058 Lift hole on padeye was irregular, the minumum dimension was 60 that not in line with 2016-09-06 Closed 2016-09- Confirmed
the drawing requirement 74mm. 08 result OK
3568-PS-026 Found two indications at weld seam during perform UT and marked on side, the sub- 2016-09-08 Closed 2016-09- Checked again
vendor state they would totally remove the defect and repir and need inpected again. 09 after repair

1. On 1st September,2016 found flexible hoses length not conformity with drawing requiremnt, later sub-vendor send this batch of flexible hose to the supplier for
modify, on 11th September,2016 checked corrected hoses length and confirmed they were in line with the drawing and result can be acceptable.

2. For pile 3568-C03-063, on 2nd September,2016 found three indications at weld seam during perform MT, sub-vendor remove the defect immediately and
repaired according to approved repair procedure, later checked again by MT and confirm the result was satisfied.

3. For pile 3568-C06-058, on 06th September,2016 found Lift hole on padeye was irregular, the minumum dimension was 60 that not in line with the drawing
requirement of 74mm, later sub-vendor repaired the irregular hole, on 8th September,2016 inspected that dimension was75mm and can be acceptable.

4. For pile 3568-PS-026, on 8th September,2016 found two indications at weld seam during perform UT, later sub-vendor remove the defect and repaired according
to approved repair procedure, on 9th September,2016 checked again by UT and confirm the result was satisfied.
GUI-068-00 (Revision 0) Punch List Dated: 22nd March 2016
Vendor/Sub-Vendor Name: Technical Specialist Name:
Su Jinlong
Vendor/Sub-Vendor Signature: Technical Specialist Signature:
Su Jinlong
Date: Date: 2016-09-13

GUI-035-00 (Revision 0) Inspection Report Dated: 22nd March 2016