Professional Documents
Culture Documents
0 GEOTECHNICAL DEPARTMENT
6.1 AUTHORITY AND GUIDELINES
Below are the essential lists of standards used for civil engineering
design:
1
investigations for general purposes are described in BS 5930, the
methods of investigation for stability of slopes of cuttings and
embankments require additional specialist techniques and
equipment which are described in the present code.
3
useful to the general public, many of whom carry responsibility for
slope maintenance as owners of property.
6.2 Earthwork
The scope of work involve in earthwork are:
i. Determination of proposed ground level as well as cut and
fill process within the site boundary
ii. Cross section of the site plan after the cut and fill works
iii. Typical temporary earth drain and sedimentation basin
design for the surface runoff
5
material and refilling and for the demolition and disposal of any
existing structures or obstructions in accordance with the
specifications given.
6
Removal of existing fill and replacement with imported
compacted fill;
Removal of upper natural soil and replacement with
compacted fill.
Cut slopes
Fill slopes
7
since sound walls and other forms of sound path blockage are less
effective in this geometry. There are a variety of reasons for creating
fills, among them reduction of grade along a route or elevation of
the route above water, swampy ground, or areas where snow drifts
frequently collect. Fills can also be used to cover tree stumps, rocks,
or unstable soil, in which case material with a higher bearing
capacity is placed on top of the obstacle soil, in which case material
with a higher bearing capacity is placed on top of the obstacles in
order to carry the weight of the roadway and reduce differential
settlement.
Purpose of earthwork
Earthworks are required for the purpose of providing ground
gradients that satisfy engineering criteria and level or useable
platform for erection of structure or other purpose for which it is
planned.
8
proposed in order to fulfill the slope condition and to minimize the
cut and fill volume. After analyzes, the suitable platform level is 2.30
m for this construction area.
Compaction of earthwork
Compaction increases the strength characteristics of soils,
thereby increasing the bearing capacity of foundations constructed
over them. Compaction also decreases the amount of undesirable
settlement of structures and increases the stability of slopes of
embankments. Smooth-wheel rollers, sheeps foot rollers, rubber-
tired rollers, and vibratory rollers are generally used in the field for
soil compaction. Vibratory rollers are used mostly for the
densification of granular soils. This chapter discusses the principles
of soil compaction in the laboratory and in the field.
Compaction, in general, is the densification of soil by removal
of air, which requires mechanical energy. The degree of compaction
of a soil is measured in terms of its dry unit weight. When water is
added to the soil during compaction, it acts as a softening agent on
the soil particles. The soil particles slip over each other and move
into a densely packed position.
9
site grading can completely alter the topography, and development
in the neighborhood can alter the hydraulic balance.
h3 h4
Figure 1 : Grid Segment
The figure above shows the sample of the square grid that is
used for the volume calculation of the earthwork. The average
height of the square grid is obtained in order to compute the volume
for the earth work. The volume of the earthwork within the grid can
be calculated as below:
Hmean = (h1+h2+h3+h4)/4
Soil volume, V = (hmean proposed level)x grid area
10
Grid Layout 1
11
15 100.00 2.170 2.30 0.13 13.00
15 63.90 2.380 2.30 0.08 5.11
16 65.57 2.110 2.30 0.19 12.46
17 100.00 2.110 2.30 0.19 19.00
18 100.00 2.080 2.30 0.22 22.00
19 100.00 2.110 2.30 0.19 19.00
20 100.00 2.140 2.30 0.16 16.00
21 100.00 2.130 2.30 0.17 17.00
22 100.00 2.120 2.30 0.18 18.00
23 51.97 2.120 2.30 0.18 9.35
24 78.61 2.080 2.30 0.22 17.29
25 100.00 2.065 2.30 0.24 23.50
26 100.00 2.065 2.30 0.24 23.50
27 100.00 2.080 2.30 0.22 22.00
28 100.00 2.080 2.30 0.22 22.00
29 100.00 2.130 2.30 0.17 17.00
30 100.00 2.130 2.30 0.17 17.00
31 40.02 2.130 2.30 0.17 6.80
32 91.64 2.060 2.30 0.24 21.99
33 100.00 2.060 2.30 0.24 24.00
34 100.00 2.060 2.30 0.24 24.00
35 100.00 2.060 2.30 0.24 24.00
36 100.00 2.105 2.30 0.20 19.50
37 100.00 2.205 2.30 0.09 9.50
38 100.00 2.280 2.30 0.02 2.00
39 28.07 2.280 2.30 0.02 0.56
40 100.00 2.000 2.30 0.30 30.00
41 100.00 2.030 2.30 0.27 27.00
42 100.00 2.060 2.30 0.24 24.00
43 100.00 2.070 2.30 0.23 23.00
44 100.00 2.130 2.30 0.17 17.00
45 100.00 2.205 2.30 0.09 9.50
46 100.00 2.280 2.30 0.02 2.00
47 16.13 2.280 2.30 0.02 0.32
17.72 1.930 2.30 0.37 6.56
49 100.00 1.930 2.30 0.37 37.00
50 100.00 2.000 2.30 0.30 30.00
51 100.00 2.025 2.30 0.28 27.50
52 100.00 2.065 2.30 0.24 23.50
53 100.00 2.105 2.30 0.20 19.50
54 100.00 2.130 2.30 0.17 17.00
55 100.00 2.130 2.30 0.17 17.00
56 30.75 1.900 2.30 0.40 12.30
57 100.00 1.930 2.30 0.37 37.00
58 100.00 1.930 2.30 0.37 37.00
59 100.00 1.903 2.30 0.40 39.70
60 100.00 1.940 2.30 0.36 36.00
61 100.00 2.015 2.30 0.29 28.50
62 100.00 2.340 2.30 0.04 4.00
63 100.00 2.080 2.30 0.22 22.00
64 30.75 1.890 2.30 0.41 12.61
65 100.00 1.890 2.30 0.41 41.00
66 100.00 1.890 2.30 0.41 41.00
12
67 100.00 1.930 2.30 0.37 37.00
68 100.00 1.880 2.30 0.42 42.00
69 100.00 1.860 2.30 0.44 44.00
70 100.00 1.960 2.30 0.34 34.00
71 79.74 1.930 2.30 0.37 29.50
72 43.79 1.930 2.30 0.37 16.20
73 100.00 1.565 2.30 0.74 73.50
74 100.00 1.565 2.30 0.74 73.50
75 100.00 1.200 2.30 1.10 110.00
76 100.00 1.565 2.30 0.74 73.50
77 100.00 1.880 2.30 0.42 42.00
78 100.00 1.910 2.30 0.39 39.00
79 46.62 1.930 2.30 0.37 17.25
80 11.41 1.200 2.30 1.10 12.55
81 24.16 1.220 2.30 1.08 26.09
82 36.91 1.200 2.30 1.10 40.60
83 48.18 1.200 2.30 1.10 52.99
84 54.93 1.200 2.30 1.10 60.42
85 35.36 1.260 2.30 1.04 36.77
27.38 1987.77
13
Figure 6.2 : Cross section A-A
The total cut and fill volume for layout1 is coming in the below
categories:
Amount of cut = 27.38 m3
Amount of fill before compaction = 1987.77 m3
Amount of extra fill required after compaction
= 1987.77 * 20% = 397.55 m3
Total amount of fill required = 2385.32 m3
Soil to be disposed = 2385.32 27.38 = 2357.94m3
14
avoid water accumulate on site which destabilized the soil, surface
soil erosion, prevent damage to slope as well as for safety reason
whiles the construction is ongoing or before the drainage system of
the construction area are built. Drainage should be connected to
existing drainage and the channeled to sedimentation basin or silt
trap for treatment purpose.
During the earthwork stage of construction, the soils top layer
or cover will be removed and this will leave the soil bare. A bare soil
uncovered surface will have a higher surface water runoff compared
to normal grassed surfaces. The function of temporary earth drain is
used to make sure the rain water appropriately directed flow away
without causing unnecessary clogging or flood.
6.3.2 Methodology
Based on MASMA, the general procedure to estimate the peak flow
for a single catchment area using the rational method as below:
15
Select design
ARI
Estimation of
time
concentration,t
c
Determine
rainfall
intensity, yIt
Estimate
runoff
coefficients
Calculate peak
flow rate, Qy
PD = P30 - FD (P60 -
16
ln (RIt) a + b ln(t) + c (ln(t))2 +
d (ln(t))3
(MASMA Eq.13.2)
Where,
(RIt) = the average rainfall intensity (mm/hr) for ARI and duration t
R = average return internal (years)
T = duration (minutes)
a to d = fitting constant depending on ARI (Appendix 13.A)
Peak Flow Estimation, Qpeak
Qy = c. yIt
.A
360
(MASMA, Eq. 14.7)
Where,
Qy = y year ARI peak flow (m3/s)
C = dimensionless runoff coefficient
y
It = y year ARI average rainfall intensity over time of
concentration, tc, (mm/hr)
A = drainage area (ha)
b
The earth drainage design is trapezoidal. The Manning Equation
used to calculate the Q of the flow;
2 1
A R3 S2
Q=
n
17
Where,
n = Mannings roughness coefficient
R = hydraulic radius (m)
S = friction slope (m/m)
A = cross section area (m2)
Hydraulic Radius
Area , A
R=
wetted perimeter , P
18
years, the design storm event is the 5-day 80th percentile for the
design.
6.4.2 Methodology
Calculate sizing of
sediment basin
Determine overland
flow time of
concentration, to
Estimation the
sizing of emergency
spillway
The calculation for design of silt trap are shown in Appendix 6.2
LTWL Spillway
LB
Inflow WTWL WB
Inflow
Y1
1
Y2 2
Appendix 6.2
Typical layout of temporary earth drainage
19
2m
0.8
0.8m
25.32m
0.6 m
1
0.37m 2
0.4m
1.67m
3m
20
The site investigation is done by team of geotechnical laboratory,
Universiti Sains Malaysia,. There are 1 (one) borehole had being
carried out; located at the middle of construction area.
21