You are on page 1of 2

8.1. Names of Designatio Worth (Rs.

in Address
Directors n Lacs.)

Amount As on

Shri Kirit
Bhimjibhai Patel

DIN: 02125246
A 1/3, Chinaibaug Flats,
31.03.1 Behind Law College,
Director 255.00
4 Ellisbridge, Ahmedabad-4

Mr Kirit Patel, aged 62 years is civil engineer and is in charge of Whole India operations of Somat group which
includes getting work/project orders, monitoring and supervision of all projects and improvement of performance
of the company by ensuring smooth transition at all project works.
Mr. Patel has over 30 years of experience in civil engineering. Mr. Patel's responsibilities as a Project Engineer
and/or Project Coordinator include construction monitoring, shop drawing reviews, and inspection of field works.
Additionally, Mr. Patel performs preparation of design calculations, drawings, and reports as well as planning,
coordination, and supervision of geotechnical investigations. Additionally Mr. Patel has experience in
developing single and multifamily home properties.
Job Responsibility Over all overview and operation of Somat Engineering, Inc.s India Subsidiary Somat
Infrastructure India Private Ltd. estimation and bidding for contracts, bid evaluation and selection of sub
consultants, material & equipment procurement, project management, scheduling, progress monitoring,
coordination with owner and engineering consultant, and recruiting staff.
Projects Within India:
1. Construction Managers for 40 Residential schools for Karnataka Residential Project.Project cost Rs.200
cr.
2. Consultancy services for EIA studies and geotechnical investigation for 1320 MW at Gulbarga for Power
Corporation of Karnataka Ltd.
3. Consultancy services for EIA studies and geotechnical investigation for 1320 MW at Ghat-prabha for
Power Corporation of Karnataka Ltd.
4. Construction Managers for 40 schools for Backward class schools.
5. Third party quality inspection for 200 cr. Road projects for Mumbai Municipal Corporation.
6. Construction Managers for up gradation of existing 6 schools for Mumbai Municipal Corporation.
7. Setting up Precast Prestressed Hollow Core plants at different locations with Govt. of India Public sector
undertaking Hindustan Prefeb Limited.
8. Empanelled as Bid Pocess Managers and consultants for Infrastructure Projects coming up at Naya
Raipur Development Authority in the State of Chhattisgarh
9. Construction of air-conditioned indoor domed stadium with the following features - Seating capacity of 7114
persons, 330 feet diameter structural steel dome, 25000 square feet wooden floor, aluminum roof, under deck
insulation, pre-cast concrete panels for outer vertical cladding; flooring and wall panels of marble, granite and
terrazzo tile; Hydropneumatic system for water supply, fire-fighting system, etc..
10. Construction of hostel and community center adjacent to the indoor stadium.
11. Construction of circulating water system for Gujarat Industries Power Supply Company for 250 MW power
project. This project include the following features: hot and cold water pressure tunnels of 1500 meters, open
water channels of 400 meters, pump house, structural steel fabrication for heavy duty pumps & connection to
turbines, etc.
12. Construction of additional two lanes and upgrading of existing two lanes for National Highway # 8 including
construction of new bridges, flyovers, under passes, service roads, retaining walls, toll plaza, landscaping, etc.
Construction activity at site also included soil stabilization of the poor roadbed.
13. Construction of elevated 2150 meters long four-lane flyover, for Surat Municipal Corporation. .
14. Construction of a 600 bed hospital for the city of Surat city with the following features: The project consisted of
5 two floor blocks connected through a 5 meter wide corridor; central out patient department block; reinforced
concrete structure; brick work; flooring of marble, kota, ceramic and terrazzo tiles; doors and windows of teak
wood and aluminum sections; internal and external water supply and drainage system.
15. Approximate built up area: 100,000 square feet.
16. Construction of 470 apartments, for State Reserve Police Group IX, Surat. It consisted of under reamed bored
piles as foundation, load bearing brick walls, reinforced cement concrete slabs, teak wood doors and windows,
all internal and exterior finish and associated civil works.
17. Approximate built up area: 125,000 square feet
18. Construction of Administration Building for Kakarapar Atomic Power Project of Nuclear Power Corporation
(NPC). The project consisted of five two stories blocks, connected with 4 meter wide corridor, reinforced
concrete structure, brick work; flooring of marble, green kota stone, ceramic tiles and terrazzo tiles, doors and
windows of teak wood and aluminum sections, internal and external water supply and drainage system.
Approximate built up area: 45000 square feet.
19. Construction of warehouses for Kakarpar Atomic Power Project. Approximate built up area: 33000 square feet.
20. Construction of 72 apartments and barracks for Kakarapar Atomic Power of NPC. Approximate built up area:
50,000 square feet.
21. Construction of a 1250 metric tones per day capacity sugar factory for Ukai Co-Operative Society.
22. Construction of a fire fighting system including pump house for the Hazira Project of Oil and Natural Gas
Commission (ONGC).
23. Construction of oil rig foundations (bored under reamed piles) for ONGC.
24. Construction of Jain Temple at Ahmedabad.

Projects Outside India:


Projects:
1. Rehabilitation of Bascule Bridge on M-85 (Ford Road) in Detroit.
2. Oakwood CSO Project in Detroit.
3. Upper Rouge CSO Tunnel Project, Detroit.
4. Ambassador Gateway Project, Detroit.
5. Installation of Standby Generators at Wastewater Treatment Plant for DWSD, Detroit.
6. Joy Road Pumping Station, Detroit.
7. Wayne County Parks Holiday Valley Bridge Restorations Project, Detroit .

You might also like