Professional Documents
Culture Documents
AbstractIn utility power system substation design, the created by considering every situation in which the station
breaker-and-a-half topology is frequently used, primarily fails.
because it is considered very reliable. This paper aims to
demonstrate that by adding sectionalizing circuit breakers into The components usually considered include transmission
the busbars of the breaker-and-a-half configuration, the lines, transformers, reactors, buses, circuit breakers, reclosers,
reliability of this substation design can be improved. Using a and switches. Each component has several associated failure
combinatorics-based approach to combining reliability indices states, as applicable, including fault, preventative
of substation component failures, combined with using minimal maintenance, false trip, and stuck. Failures are distinguished
cut sets of reliability graphs to identify failure scenarios, overall as either passive, when they do not trigger the operation of
system failure rates were calculated for various substation adjacent protective devices, and active, when they do. Two
topologies. The results demonstrate that the sectionalized or more component failures occurring in sequence, with the
breaker-and-a-half topology reduces the substations failure rate subsequent failures occurring before the initial failure is
by 70.8% and its total annual downtime by 28.9% compared to repaired, are referred to as second- and higher-order failures.
a typical breaker-and-a-half scheme, although at the cost of Many papers on substation reliability only concern
increasing the mean time to repair of a substation failure by 2.49 themselves with limited types of third- or higher-order failure
hours. events, or neglect them entirely [2], as the likelihood of
failures drops off steeply as the order increases.
Index Terms-- Power Systems, Power System Reliability,
Substations. Reliability indices evaluated usually include failure rate,
average outage duration, and total annual outage time. Each
I. INTRODUCTION component has an associated value for each index, with
average outage duration being a function of the average repair
Reliability studies of utility power system substations time and total outage time being the product of the other two
have often concerned themselves with comparisons of indices. Then each first- and second-order failure event can
different architectures used within the substation to connect be given a set of reliability indices by probabilistically
incoming (source-side) lines to outgoing (load-side) lines. As combining the indices of the components involved in each
substations can potentially supply power to a very large event. Finally, a set of overall substation reliability indices
number of downstream customers, it is very important that can be derived by combining the indices of each failure event
they be very reliable. In most reliability studies, the breaker- that results in substation failure [1].
and-a-half topology is identified as among the most reliable
configurations [1]. A wide variety of approaches to modeling these indices
have been developed, including the use of state enumeration
Many approaches have been developed for the modeling through minimal cut sets [3] or fault tree analysis [4], and
of substation reliability and the derivation of accompanying calculation of reliability indices through combinatorics-based
reliability indices. Of these, most concern themselves probability models [1], [5], Markov chains [2], [6], sequential
primarily with the failure rate of individual components Monte Carlo methods [7], [8], and treating reliability indices
within the substation, identifying which components or as random variables [9]. This paper will utilize a minimal cut
combinations of multiple components failures would cause set approach to enumerating failure states and a
the substation as a whole to fail. In substation reliability, combinatorics-based probability model to calculate reliability
system failure is defined as no paths existing between the indices.
incoming and outgoing lines. Assigning each component a
set of reliability indices, aggregate reliability indices can be
The work presented herein is supported in part by the U.S Office of Naval
Research Contract Number: N0014-08-1-0080.
D. Breaker-and-a-Half
The Breaker-and-a-Half arrangement consists of two
parallel busbars, connected by two lines. Each connecting
line contains three circuit breakers, an incoming line and an
outgoing line (Fig. 4). This configuration contains a
significant amount of redundancy, even more than the ring
bus. However, this increased redundancy also means more
Figure 1. Single Bus, Single Breaker arrangement. components are involved, increasing the number of possible
failure points. Like the ring bus, the breaker-and-a-half
B. Sectionalized Bus arrangement cannot fail due to a first-order failure.
The sectionalized bus arrangement is simply the single
bus, single breaker configuration with the addition of a
sectionalizing circuit breaker on the busbar separating the two
pairs of incoming and outgoing lines (Fig. 2). This adds a
layer of protection, ensuring that if a bus fault occurs, or if
there is a short circuit in one of the line breakers, only one
side of the substation will be taken down, while the other side
remains operational. A short circuit in the bus breaker will
still result in system failure, as will a number of second- and
higher-order failures, but this topology nonetheless represents
an improvement in reliability over the single bus, single
breaker arrangement.
Reliability Index
Substation
Arrangement MTTR Total Downtime Failure Rate
(hours) (hours/year) (#/year)
Single Bus, Single
11.999974 0.768001643 0.06400027
Breaker
Single Bus, Single
Breaker with 11.657036 0.120340567 0.01032343
(a)
Sectionalized Bus
Ring Bus 1.0675151 0.000440691 0.00041282
(b)
(c)
Figure 6. (a) A reliability graph of the Single Bus, Single Breaker with
sectionalized bus topology. (b) A first-order failure, which the substation
survives. (c) A second-order failure, which the substation does not survive.
TABLE II. CALCULATION OF SINGLE BUS, SINGLE BREAKER SUBSTATION RELIABILITY INDICES
Total Downtime Failure Rate
Failure 1 Failure 2 Failure 3 MTTR (hours)
(hours/year) (#/year)
Bus (A) 12 0.288 0.024
CB1 (A) 12 0.12 0.01
CB2 (A) 12 0.12 0.01
CB3 (A) 12 0.12 0.01
CB4 (A) 12 0.12 0.01
CB1 (P) CB2 (P) 6 8.21355E-07 1.36893E-07
CB3 (P) CB4 (P) 6 8.21355E-07 1.36893E-07
TOTAL 11.99997433 0.768001643 0.064000274
of the five substations, though it fails more often than either of The sectionalized breaker-and-a-half topology, then,
the Breaker-and-a-Half configurations. This is due to the fact would be most useful in a situation where one is trying to
that the majority of the failure scenarios in a Ring Bus minimize the number of failures that occur, regardless of their
substation involve stuck breakers. Stuck breaker conditions duration. The traditional breaker-and-a-half topology
occur more frequently than overlapping active or passive represents a middle ground between the ring bus and
failures, but can be repaired much more quickly, as can be sectionalized breaker-and-a-half.
seen in Table I. Therefore the ring bus may be preferable in
situations in which the loads being served can sustain a greater V. CONCLUSIONS
number of short failures better than a lesser number of failures A minimal cut set approach to failure state enumeration
of a greater duration. The low MTTR of a ring bus topology and a combinatorics-based probability model of reliability
as compared to a breaker-and-a-half arrangement has been indices leads to the conclusion that the Breaker-and-a-Half
observed in previous studies [1], [6]. substation topology can be made more reliable by including
sectionalizing circuit breakers in the busbars. This
configuration has a lower failure rate and total annual
downtime than the four other topologies modeled, though it
has a higher mean time to repair than the ring bus and the
breaker-and-a-half scheme without sectionalized busbars. Of
these three topologies, the ring bus has the lowest MTTR and
the highest failure rate and total annual downtime, with the
traditional breaker-and-a-half falling between the other two
topologies in all three indices.
In the future, the comparison made here between the
sectionalized breaker-and-a-half topology and other substation
arrangements can be corroborated and refined though the use
of other established approaches to reliability modeling. The
Figure 8. Substation Mean Times to Repair. comparison can be further refined though the inclusion of
economic concerns or comparisons against other, more
complex substation arrangements.
REFERENCES
[1] M. S. Grover, R. Billinton, A Computerized Approach to Substation
and Switching Station Reliability Evaluation, IEEE PES, November
1973.
[2] X. F. Wang, X. L. Wang, Generalized Outage Table Approach to
Reliability Study of Power Stations Bus Schemes, IEEE Trans. PD,
Vol. 12, No. 4, October 1997.
[3] R.N. Allan, M.F. de Oliveira, Reliability Modeling and Evaluation of
Transmission and Distribution Systems, PROC. IEEE, Vol. 124, No.
6, June 1977.
[4] Z. Liu, Reliability Analysis of Breaker Arrangements in High Voltage
Stations: A Fault Tree Analysis, Chalmers University of Technology,
Goteborg, Sweden, 2008.
Figure 9. Substation Total Annual Downtimes. [5] Z. Dong, D. O. Koval, J. E. Propst, Reliability of Various Industrial
Substations, IEEE Trans. IA, Vol. 40, No. 4, August 2004.
[6] J. J. Meeuwsen, W. L. Kling, Substation Reliability Evaluation
The results demonstrate a higher level of reliability in both including Switching Actions with Redundant Components, IEEE
failure rate and total annual downtime in the sectionalized Trans. PD, Vol. 12, No. 4, October 1997.
breaker-and-a-half configuration as compared to the [7] R. Billinton, G. Lian, Monte Carlo approach to substation reliability
arrangement without sectionalizing breakers. The downside evaluation, IEEE Proc.-C, Vol. 140, No. 2, March 1993.
of this change can be seen in Fig. 8, as the failures of the [8] C. J. Zapata, A. Alzate, M. A. Rios, Reliability Assessment of
sectionalized arrangement take, on average, longer to repair Substations using Stochastic Point Processes and Monte Carlo
Simulation, IEEE PES, July 2010.
than those in the standard version. This is because most of the [9] R. Billinton, R. Goel, An Analytical Approach to Evaluate Probability
failure scenarios for the standard breaker-and-a-half Distributions Associated with the Reliability Indices of Electric
configuration that are prevented by the sectionalized busbars Distribution Systems, IEEE Trans. PD, Vol. PWRD-1, No. 3, July
involve stuck breakers. As mentioned above, these failures, 1986.
while being relatively frequent compared to active or passive [10] R. N. Allen, J. R. Ochoa, "Modeling and Assessment of Station
Originated Outages for Composite Systems Reliability Evaluation",
circuit breaker failures, also can be repaired much quicker. IEEE Trans. PS, February 1988.
However, this increase in MTTR is more than offset by the
reduced failure rate, as can be seen in Fig. 9.