You are on page 1of 8

providing insights for todays hvac system designer

Engineers Newsletter volume 39 3

ASHRAE Standard 90.1-2010


Updates to mechanical system mandatory and prescriptive requirements

ASHRAE Standard 90.1-2010 is


The 2010 version of ASHRAE simply 90.1-2007, with the Equipment Efficiency
Standard 90.1, Energy Standard incorporation of more than 100 Changes
for Buildings Except Low-Rise approved addenda, 52 of which
Residential Buildings, will be
published this fall. Significantly, the
affect mechanical systems and will The following is a summary of
goal of ASHRAE Standard be the focus of this article. updates to the equipment efficiencies
90.1-2010 was to achieve 30 required by 90.1-2010.
percent energy-cost savings Other significant changes were
compared to 90.1-2004 made to the scope, lighting, building
(aggregated across 16 building Air conditioners and heat pumps.
envelope and modeling sections of
types in 17 climate zones). Efficiencies for air conditioners and
the standard, which will affect load
heat pumps have been improved
This newsletter provides an calculations and equipment sizing.
substantially in recent years. In fact,
overview of the mechanical
changes that pertain to heating, The addenda that affect mechanical when compared to the 1989 standard,
ventilation and air-conditioning. systems can be roughly grouped there is approximately a 17 percent
into the following areas: Energy Efficiency Ratio (EER)
improvement in the larger sizes and
Equipment efficiency 30 percent in the 5- to 20-ton
System design and control category. For small, less than 5-ton,
requirements equipment the change is
approximately 34 percent Seasonal
Waterside Energy Efficiency Ratio (SEER)
Outdoor air improvement.

Airside Equipment schedules now


incorporate a new term called
These changes are outlined in the Integrated Energy Efficiency Ratio
following sections. (IEER). This new metric was
developed for unitary products to
replace Integrated Part Load Value
(IPLV) and encourage designs that
have better part-load performance.
(Addendum S)

2010 Trane, a business of Ingersoll Rand. All rights reserved. 1


Single-zone VAV. As of January 1, efficiency levels vary by application full-load kW/ton requirement. Each
2012, unitary equipment 110,000 Btuh (such as water source, ground water path has both a full-load and a part-load
(9.2 tons) or larger serving a single source, ground source) to correspond metric to meet. (Addendum M)
zone must provide means to reduce with the rating temperatures typical for
fan speed to two-thirds or less at loads those applications. (Addendum BG) Glycol or brine in chillers. Other
below 50 percent. This can be changes to the chiller section targeted
accomplished by two-speed or Computer room air conditioners bringing more chillers under the scope
variable-speed fans. (CRAC). The scope of 90.1 has been of the standard. The first is how to
expanded to include systems used in consider the performance and
Chilled-water air-handling units have a
commercial process cooling compliance of chillers with glycol for
similar requirement (effective January
applications. (Addendum AQ) freeze protection that operate at a
2010); see VAV requirements for
normal chilled-water temperature. In
chilled water air-handling units serving As a result, there is a new class of the past, chillers with a freeze point of
a single-zone, p. 7. covered product: computer room air 27F or lower had enough glycol to
conditioners, or CRAC units. ASHRAE exempt them from meeting the
The low-speed airflow can be the larger
127 is the referenced test procedure. standard. In reality, designers add
of the limit stated above or the
The ASHRAE test procedure has glycol to air-cooled chillers in cold
ASHRAE 62.1 ventilation requirement
defined a term called Sensible climates, even though there are no
for the zone. Outdoor air measurement
Coefficient of Performance (SCOP). design changes to the chiller, only a
or a compensating damper will be
SCOP-127 calculates efficiency at performance degradation. The test
necessary for proper ventilation at
conditions more reflective of the procedure AHRI 550/590 uses water
reduced speed. Discharge air
mostly sensible cooling that occurs in during the test. Efficiency levels must
temperature sensors or multiple
data centers and computer rooms. be calculated for these chillers with
stages of compression may be
(Addendum BU) water as the test fluid, and meet the
necessary for proper control of the
unit. (Addendum N) values in Table 6.8.1C.
Variable-refrigerant-flow (VRF)
multi-splits. While minisplits have This change is slightly more nuanced
Water-cooled and evaporatively for centrifugal chillers. When a
been covered by 90.1 for many years
cooled air conditioners and heat centrifugal chiller has glycol in it, heat
and certified to AHRI 210/240, a similar
pumps. New full-load efficiency transfer is degraded. More lift is
class of equipment called a multi-split
requirements are 3 to 5 percent more required of the compressor which
or VRF system was previously not
stringent as of June 2011, with IEER changes the design slightly, and its
covered. This type of split system has
increases of 5 to 13 percent. ability to meet the performance in
multiple indoor DX fan coils sharing a
(Addendum CO) Table 6.8.1C when tested with water.
common compressor and condenser.
The AHRI 1230 test procedure is now The additional efficiency needed to
In addition, two-position valves are overcome losses from an oversized
now required on water-cooled air published and there are efficiency
requirements for these systems. The compressor operating at lower lift must
conditioners as well as on water-loop be compensated for by the chiller
heat pumps. See further discussion in IEER requirements get more stringent
in July 2012. design, which serves to discourage
Waterside, p. 3. (Addendum AK) unnecessary use of glycol and
VRF systems can include heat recovery improves the stringency of the
Packaged terminal air conditioners through a refrigerant-to-water heat standard. (Addendum BL)
and heat pumps (PTAC/PTHP). As of exchanger. There is a special category
October 2012, PTACs and PTHPs will in each size for VRF systems with heat Chiller test procedures. Related
be required to meet new, aggressive recovery. (Addendum CP) interpretations have been issued in
efficiency levels. (Addendum BW) recent years to discuss how to
Note: As we finalized this newsletter, accommodate customer-requested
The definition of non-standard size was AHRI was about to release a deviations from standard test
also added so that standard-sized units certification program for VRF multi- conditions, in particular tolerances and
in new construction must meet a splits. tube fouling. The actual, as built, chiller
different efficiency level than
performance is to be calculated with
replacement units having to fit into
Chillers. Since January 2010, standard tolerance and fouling, before
existing wall sleeves. (Addendum T)
Addendum M has been in effect. The comparing it with the 90.1 required
big change was the addition of an efficiency level to determine
Water-to-water heat pumps. The alternative compliance path for water- compliance. (IC 90.1-2004-14, IC 90.1-
water-to-water heat pump as a heating cooled chillers. One path has a more 2004-15)
or cooling device now falls within the stringent IPLV (part load) requirement,
scope of the standard. The required while the other has a more stringent

2 Trane Engineers Newsletter volume 393 providing insights for todays HVAC system designer
Another interpretation affirmed that Heat rejection. Heat rejection is
the energy metric, both full-load and another area that saw a significant System Design and Control
part-load, are to be measured at the change. There are now limits on the use Requirements
line side of the starter or variable- of centrifugal fans in cooling towers,
frequency drive (VFD). This means that once the tower handles more than 1100 When it comes to energy savings,
starter and drive losses must be gpm. Towers above this flow rate now much of the impact of the mechanical
included in the chiller performance have to meet the more stringent axial section relates to system
data. (IC 90.1-2004-6) fan power level of 38.2 gpm per requirements. The general areas fall
horsepower. There are exceptions for into three categories: waterside,
Chiller scope expansion. Along with site and acoustic restrictions. outdoor air, and airside design and
changes for glycol use, the scope for (Addendum U) control requirements.
positive displacement chillers, both air-
A new tower category was added in
and water-cooled, was expanded to
response to confusion over whether a
include those with a leaving fluid
fluid cooler, or 'closed-circuit cooling Waterside
temperature greater than 32F.
tower', was intended to be covered by
(Addendum BL)
the cooling tower requirements. Closed- Two-position valves in water-cooled
The last change for chillers in 90.1-2010 circuit cooling towers have different test unitary products. Condenser water
is the non-standard centrifugal conditions more reflective of the range flow for unitary systems can only be
equation and the temperatures and and approach. Closed-circuit cooling variable if (at least) a two-position valve
flows that are within the scope. towers equipped with an axial fan have a is included at the unit, to shut off water
Centrifugal chillers are covered by 90.1 more stringent level than those flow when the unit is turned off. Since
if they have: equipped with a centrifugal fan. 2001, water-source heat pumps have
(Addenda A, L) been required to have these valves;
36F or higher evaporator leaving
now this is a requirement for water-
fluid temperature,
Liquid-to-liquid heat exchangers. cooled unitary air conditioners also. For
115F or lower leaving condenser Liquid-to-liquid heat exchangers now water-cooled unitary systems of
fluid temperature, and have a referenced test procedure. This greater than 5 hp, a VFD is required on
20F to 80F of lift (leaving has encouraged heat exchanger the pump motor, or it must have similar
condenser minus leaving manufacturers to submit their products performance. (Addendum AK).
evaporator temperature). to a certification program, which gives
users a common reference for Variable-flow and variable-speed
Roughly 98 percent of centrifugal performance. No target efficiency levels pumping. In hydronic systems other
chillers sold will now be subject to have been set, but could be in the than water-cooled unitary systems, if
meeting 90.1 requirements. For future. (Addendum AD) the system power is greater than 10
example, an 85.1F entering condenser hp, a VFD is required on the pump
water temperature can no longer be Electrical equipment. motor, or it must have similar
used to avoid the 90.1 requirements. Motors. Other changes include federal performance. This is a dramatic
This loophole could not be closed until requirements for integral horsepower change. In the past, at 10 hp for the
a new, non-standard adjustment general purpose motors to be premium system, the system had to have, at
equation was developed. The new efficiency, as defined by the National minimum, two-way valves and ride the
adjustment can apply to more Electrical Manufacturers Association pump curve. At 50 hp per pump, with
combinations of conditions. As chillers (NEMA). Special purpose motors are at least 100' of head, a VFD was
deviate from standard conditions, the exempt from this requirement. Motor required. Now, when individual pumps
90.1 requirement becomes slightly types are defined by NEMA, and an are 5 hp or more, and the system
more stringent than in the past version. excerpt of the definition of a general power is at least 10 hp, VFD-like
purpose motor is included in 90.1 for performance is required. (Addendum
The adjustment is handled by a ease of reference. (Addenda AJ, BK) AK)
polynomial equation, sometimes
referred to as K-adjust or Kadj.
Transformers. Low-voltage, dry-type, Service water booster systems.
(Addendum BT)
distribution transformers are covered by Pumps are often installed in service
All of these changes together made it 90.1-2010 to reflect 2005 federal water systems (aka domestic hot
difficult to keep the non-standard requirements. (Addendum O) water) to boost the pressure at a
adjustment tables for centrifugals specific point in the system.
within the pages of the standard. Downstream of that booster system,
Instead, a spreadsheet tool will be 90.1-2010 prohibits installing a device
included on the User's Manual CD and solely for the purpose of reducing the
examples in the printed version of the pressure of the water flow, except for
User's Manual. safety devices. Pressure must be
measured and pump operation varied
to better follow the load. And pump(s)
must be shut off when no service
water flow is required. (Addendum CV)
providing insights for todays HVAC system designer Trane Engineers Newsletter volume 393 3
Pump pressure optimization. With Pipe insulation. Chilled-water piping 90.1 explicitly states that the threshold
all the new requirements for variable insulation requirements have modest is based on the individual fan and coil.
speed pumping, it follows that 90.1 changes, but hot water and especially For a fan-coil, VRF or zone-based fan
now requires pump pressure steam pipes have significant upgrades. and coil system, 54,000 Btu/h is the
optimization for systems with DDC There are exceptions: for example, largest terminal size before an
controls. There are two main when pipes are in the interior walls economizer is required. This
requirements: the differential pressure between conditioned spaces. And if requirement could be satisfied by
(DP) setpoint can be no more than the non-metallic pipe is used, and it's either a water or air economizer.
DP that corresponds to 110 percent of greater than schedule 80 thickness,
the design flow rate, and the DP you may reduce insulation thickness to One way that more climates were
setpoint has to be reset until one valve an equivalent heat transfer per linear justified is by dropping the exceptions
is nearly wide open. (Addendum AK) foot. There are adjustments for buried for integrated economizing. This
pipe. (Addenda BA, BI) means that the economizer will be the
first stage of cooling, followed by
Maximum flows in nominal pipe mechanical cooling, until the high limit
sizes. The allowances change based shutoff point. The high limit changes
on the annual hours of operation of Outdoor Air by climate zone.
that system, and whether it is variable
flow/variable speed. See Table 1. There are four main topics for outdoor There are 12 exceptions to the
air system design and control: economizer requirement
This change limits the amount of economizers, energy recovery (paraphrased):
frictional loss that the system pumps ventilators, dampers, and ventilation
must overcome. System design delta T 1 climate zones 1a or 1b
controls.
impacts which pipe sizes are 2 fan + coil size 54,000 Btu/h
permitted. For example, if you really (computer rooms use 90.1-2007
Economizers. A sweeping
want 6-inch and not 8-inch pipes, you size limits)
addendum changed economizer
may have to increase the delta T
requirements. That is, economizers are 3 non-particulate air treatment is
(reduce the flow rate).
now economically justified in most required by ASHRAE 62.1
For pipe sizes larger than 12", you climate zones. Two exceptions are
climate zones 1a and 1b, which include 4 percent of air that is humidified to
adhere to a maximum velocity. over 35F dewpoint (75 percent of
(Addenda AF, CC) the areas highlighted in Figure 1 and
other very hot climates worldwide. design airflow for health care, 25
(Addendum CY) percent for process cooling, not
Pump head calculations. Standard applicable to computer rooms)
90.1-2010 requires that pump head Smaller systems will need 5 systems with condenser heat
calculations be performed prior to economizers as well. If the individual recovery of a specific size (see
sizing pumps. This is similar to the fan and coil is 54,000 Btu/h (4.5 tons) below discussion)
requirement for load calculations. or greater, then an economizer is
(Addendum V) required. Some jurisdictions have 6 systems serving residential
interpreted this as applying if the entire spaces with a size < 270,000 Btu/h
system is greater than 4.5 tons, but 7 systems with cooling loads less
than the skin loads at 60F outdoor
temperature
Table 1. Piping System Design Maximum Flow Rate in GPM (IP) (ASHRAE Standard 90.1-2010 Table 6.5.4.5) 8 systems operating < 20 hours per
Operating hours/yr 2000 2000 and 4400 4400 week
hours/yr hours/yr hours/yr
9 systems where outdoor air for
Nominal pipe size Other Variable flow/ Other Variable flow/ Other Variable flow/
cooling would affect open
(in.) Variable speed Variable speed Variable speed
refrigeration cases
2 1/2 120 180 85 130 68 110
3 180 270 140 210 110 170
10 efficiency trade-off
4 350 530 260 400 210 320 You may trade off the economizer
5 410 620 310 470 250 370 with an improvement in equipment
efficiency. The trade-off has been
6 740 1100 570 860 440 680
expanded to include more types of
8 1200 1800 900 1400 700 1100
mechanical cooling equipment,
10 1800 2700 1300 2000 1000 1600 including applied systems, and it
12 2500 3800 1900 2900 1500 2300 applies to the part load metric (or the
Maximum velocity 8.5 fps 13.0 fps 6.5 fps 9.5 fps 5.0 fps 7.5 fps full load metric if a part load metric
for pipes over 12" does not exist.)
size

4 Trane Engineers Newsletter volume 393 providing insights for todays HVAC system designer

Figure 1. Economizer requirements


Table 1. Eliminate Required Economizer for
Comfort Cooling by Increasing Cooling
Efficiency (ASHRAE Standard 90.1-2010 Table Dry (B) Moist (A)
Marine (C)
6.3.2)
Climate Zone Efficiency Improvementa
2a 17%
2b 21%
3a 27%
3b 32%
3c 65%
4a 42%
4b 49%
4c 64%
economizer required if Zone 1 includes
5a 49%
individual fan plus coil Hawaii, Guam,
5b 59% >54,000 Btuh (4.5 tons) Puerto Rico
and Virgin Islands
5c 74%
6a 56%
6b 65% Systems with dedicated outdoor air, 3 the local water authority does not
7 72% such as VRF, water-source heat pumps, allow cooling towers, or
8 77% large fan coils, etc., will have difficulty 4 less than 600,000 Btu/h of
a
meeting the air economizer computer room cooling equipment
If a unit is rated with an IPLV, IEER or SEER then to
eliminate the required air or water economizer, the requirement, because the ductwork is capacity is being added to an
minimum cooling efficiency of the HVAC unit must be
increased by the percentage shown. If the HVAC unit is
not sized to deliver enough air to meet existing building. (Addendum BU)
only rated with a full load metric like EER or COP cooling the full space cooling load. Most of
then these must be increased by the percentage shown
these will fall under the 54,000 Btu/h
threshold, but some will not. These Waterside economizer sizing for
11 data center load threshold (see Data systems can be designed to data centers. For data center
center exceptions for economizers) alternatively include heat recovery designers who prefer water
through water-to-water or refrigerant- economizers, slightly different sizing
12 data centers where 75 percent of the
to-water heat exchangers or water requirements were made to reflect
design load serves an essential facility,
economizers. nearly constant year-round loads.
Tier IV design, Critical Operations
When an economizer is required, the
Power Systems, or pending financial
expected cooling load at 40F dry bulb/
transactions (paraphrased) Data center exceptions for 35F wetbulb must be met with
economizers. If one of the following evaporative water economizers or the
Heat recovery economizer four situations is true, then an expected cooling load at 35F dry bulb
exception. There are a number of economizer is not required for the must be met with dry cooler water
exceptions for required economizers, computer room(s) (data centers): economizers. (Addendum BU).
one of which was expanded. Heat 1 the total design cooling load of all
recovery is often at odds with computer rooms in the building is
economizer operation. This is because less than 3,000,000 Btu/h and the
a number of hours when heating is building is not served by a
needed happens when the cooling load centralized chilled-water plant, or
is being shed by the economizer. You
can't have all of both economizing and 2 the room total design cooling load
condenser heat recovery. is less than 600,000 Btu/h and the
building in which they are located is
served by a centralized chilled-
water plant, or

providing insights for todays HVAC system designer Trane Engineers Newsletter volume 393 5
Table 3. Maximum Damper Leakage (ASHRAE Standard 90.1-2010 Table 6.4.3.4.4)
Ventilation optimization (ventilation
reset). In addition to zone-level
Maximum Damper Leakage (cfm per ft2) at 1.0 in. w.g.
ventilation control, there is a new
Ventilation Air Intake Exhaust Relief requirement for system level ventilation
Climate Zone non-motorized1 motorized non-motorized1 motorized adjustments in multiple-zone systems
1,2 with DDC controls. One exception is that
any height 20 4 20 4 this control is not required if the system
requires an ERV by section 6.5.6.1 (Table
3
4). What is not required, is dynamic
any height 20 10 20 10
recalculation of the critical zone, with the
4, 5b, 5c ability to pop open the critical boxes to
less than 3 stories not allowed 10 20 10 reduce the outdoor-air (OA) fraction and
3 or more stories not allowed 10 not allowed 10 reduce the overall system intake airflow.
5a, 6, 7, 8
This technique is allowed under
exception a2 in 6.5.3.2(a). This is
less than 3 stories not allowed 4 20 4
sometimes referred to as limiting the
3 or more stories not allowed 4 not allowed 4 maximum Z, based on the variable
1 Dampers smaller than 24 in. in either dimension may have leakage of 40 cfm/ft2 assigned to the zone OA fraction in
Standard 62.1. So for those looking to

exceed the minimum requirements, this


Dampers. Outdoor air intake dampers (f) Heating energy recovery in climate is one place to do it.1,2 (Addendum CK)
in climates 5a, 6, 7, 8 must be motorized zones 1 and 2.
(Table 3), low-leak (AMCA Class 1)
dampers. Gravity or backdraft dampers (g) Cooling energy recovery in climate
are permitted for all uses in climates 1 zones 3c, 4c, 5b, 5c, 6b, 7, and 8. Airside
through 3, or for exhaust/relief dampers
in one or two story buildings in climates (h) Where the largest source of air In addition to single-zone VAV, there are
4 through 8. (Addendum CB) exhausted at a single location at the several new or modified requirements
building exterior is less than 75 for airside controls.
percent of the design outdoor airflow
Exhaust air energy recovery. Energy
rate.
recovery ventilators (ERVs) are Supply air reset. A requirement for
justifiable in a lot more situations, now (i) Systems requiring dehumidification supply air temperature (SAT) reset was
that energy costs have risen and the that employ energy recovery in series removed from 90.1 in the 1999 version,
component costs have come down. with the cooling coil. but has returned in the 2010 version. Part
There are three intersecting thresholds: of the ambivalence 90.1 has shown for
climate, a percentage of outdoor air, and (j) Systems expected to operate less this requirement is the overall impact of
the supply airflow rate (see Table 4). than 20 hrs per week at the outdoor increase in fan energy compared to the
There is no ERV requirement, for any air percentage covered by table decrease in reheat energy.
size system in any climate, if below 30 6.5.6.1.
percent outdoor air at full design airflow. The goal is to set up the SAT reset
strategy so that it gradually resets to full
Zone-level demand-controlled reset at a point when most zones have
There are 10 exceptions to the ERV
ventilation (DCV). As of 90.1-2007, minimal cooling loads, and the additional
requirement, related to situations where
zone-level DCV is required for zones with fan energy will not overwhelm the
exhaust heat recovery is not economical
more than 40 people per 1000 square reheat savings. A simple approach for
or practical.
feet (100 in the 2004 version). As doing this was mentioned in a recent
(a) Laboratory systems meeting 6.5.7.2. discussed in an earlier newsletter2, newsletter3. The outdoor air temperature
several techniques are suitable for this based strategy begins resetting the
(b) Systems serving spaces that are not control, depending on the space type supply air setpoint when it is 70F
cooled and that are heated to less and use. outdoors, with 1F of reset per 2F
than 60F. additional reduction in outdoor air
temperature until the maximum reset
(c) Systems exhausting toxic,
supply air setpoint is reached.
flammable, paint, or corrosive fumes
or dust. Table 4. Energy Recovery Requirement (IP) (ASHRAE Standard 90.1-2010 Table 6.5.6.1)
% Outdoor air at full design airflow rate
(d) Commercial kitchen hoods used for
> 30% and > 40% and > 50% and > 60% and > 70% and > 80%
collecting and removing grease Zone
< 40% < 50% < 60% < 70% < 80%
vapors and smoke.
Design Supply Fan airflow rate (cfm)

(e) Where more than 60 percent of the 3B, 3C, 4B, 4C, 5B NR NR NR NR > 5000 > 5000
outdoor air heating energy is 1B, 2B, 5C NR NR > 26000 > 12000 > 5000 > 4000
provided from site-recovered or site 6B > 11000 > 5500 > 4500 > 3500 > 2500 > 1500
solar energy. 1A, 2A, 3A, 4A, 5A, 6A > 5500 > 4500 > 3500 > 2000 > 1000 >0
7, 8 > 2500 > 1000 >0 >0 >0 >0

6 Trane Engineers Newsletter volume 393 providing insights for todays HVAC system designer
Above 70F, the outdoor air provides Figure 2. Dual maximum control option for zone heating
little or no cooling benefit for 100% maximum
economizing, and the cooling load in heating coil (design)
activated primary
most zones is likely high enough that
airflow

discharge air temperature setpoint


reheat is not required to prevent sub-

primary airflow to zone, %


90F
90F
cooling the space. Additionally, the maximum limit discharge
colder supply-air temperature allows temperature
the system to provide sufficiently dry setpoint maximum
50%
primary
air to the zones, improving part-load
heating
dehumidification. airflow

minimum
Dual maximum control on VAV 20%
primary
boxes. This change is aimed at cooling
55F
avoiding the need to increase zone airflow
55F
outdoor airflow due to temperature design space load design
stratification when supplying hot air 0% heating cooling
from ceiling-mounted diffusers and load load
returning through ceiling-mounted
air that can be reheated). This blanket with the requirements (see VAV
grilles. A new option was added for the
exception was removed, and a new control on lab exhaust systems).
maximum amount of air that can be
section on laboratory exhaust specifies
cooled and then reheated (Figure 2).
the effectiveness and control needed to Heat recovery pressure drop
The new control option requires that
make sure that these zones are not adjustments . Within the fan power
primary airflow be reduced to 20
maintained at constant flow when the limitation section there is a new
percent of design cooling airflow, but
air is not needed for pressure control. pressure drop credit equation for ERVs
then allows primary airflow to be
(Addendum AS) that compensates for effectiveness. A
modulated up to a maximum of 50
percent of design airflow for heating. higher pressure drop adjustment is
This allows heating to be accomplished VAV requirements for chilled water allowed for more effective energy
with a lower discharge-air temperature, air-handling units serving a single- recovery, reflecting the balance
which improves zone air-distribution zone. As previously mentioned on between fan energy and heat
effectiveness. (Addendum H) page 2 for packaged systems (effective recovered. Coil runaround loops have
January 2012), and as of January 2010 their own pressure drop adjustment on
You may find the new, dual for chilled water systems, variable-air- the system fan power limit:
maximum control necessary for volume fan control is required for
ERV pressure drop adjustment:
complying with the next requirement. single-zone systems. This applies to
(2.2 x Energy Recovery
A previous engineers newsletter1 chilled-water air handlers with motors
Effectiveness) 0.5 in w.c. for each
explains this control in detail. 5 hp or greater. This change requires
air stream
either two-speed motors or variable-
Overhead heating temperature speed drives on the supply fan(s), and Coil runaround loops are given a
limit. This change limits the zone may invoke the need for discharge air pressure drop adjustment of 0.6 in.
discharge-air temperature to no more temperature sensors and outdoor w.g. per air stream
than 20F above the zone thermostat airflow measurement. (Addendum N)
setpoint (with exceptions for morning
warm-up) when supplying hot air from Fan power limitation. When the Other Changes
diffusers located above the breathing single-zone VAV change occurred, the
zone, and returning through grilles 90.1 committee realized it needed to Several changes to the mechanical
located above the breathing zone. This revise the definition of which allowable section were not explicitly covered in
minimizes temperature stratification fan horsepower applies to VAV systems this newsletter. They relate to:
and short circuiting to increase zone air that don't have zone dampers Elevator lighting and ventilation
distribution effectiveness. increasing the system pressure. Single- (Addendum DF)
zone VAV systems are required to use
The new dual maximum control the more stringent constant volume fan Garage ventilation controls (Add.
stratgey may be used so that airflow power limit. DI)
can be increased in heating mode. Duct leakage class A (Add. CQ)
(Addendum BX) Allowances for exhaust systems were
previously poorly defined. This created Kitchen exhaust hoods (Add. AX)
VAV control on lab exhaust a hardship for several types of buildings Radiant panels (Add. AE)
systems. In the same section as the and specifically laboratories, hospitals,
and vivariums. The blanket exception to Heat pump pool heaters (Add. Y)
dual maximums, there used to be an
exception for spaces like hospitals and the fan power limitation for fume hoods Furnaces & water heating (Add. K,
labs where the pressure control has been removed. Other changes AO)
requirements set the minimum stop on relate to credits for exhaust and return
the VAV box (the maximum amount of systems, provided the system complies

providing insights for todays HVAC system designer Trane Engineers Newsletter volume 393 7
Summary References
Engineers
Newsletter
When the standard is published this 1. Stanke, D. 2008. Potential ASHRAE Standard
fall, it is intended to be adopted directly Conflicts - Indoor Air Quality and Energy
by energy code jurisdictions, and by
reference in IECC, NFPA, and other
Standards. Engineers Newsletter, 37-4.
LIVE!
2. Murphy, J. 2005. CO2-Based Demand- To register, contact your
model codes. Controlled Ventilation with ASHRAE Standard local Trane office.
62.1-2004. Engineers Newsletter, 34-5.
Preliminary results of modeling
performed by Pacific Northwest 3. Murphy, J. 2010. Energy-Saving Control
ASHRAE Standard
National Laboratories (PNNL) were Strategies for Rooftop VAV Systems. Engineers 90.1-2010
shared at the June 2010 annual Newsletter, 39-1. This program will discuss
meeting. Not all approved addenda major envelope, mechanical,
4. American Society of Heating, Refrigerating, and
were included at that time. Air-Conditioning Engineers. 2007. ANSI/ lighting, and modeling addenda
In addition to the changes in 90.1, ASHRAE/IESNA Standard 90.1-2007: Energy that will be incorporated into
there were ventilation rate changes in
Standard for Buildings Except Low-Rise 90.1-2010.
Residential Buildings. Atlanta, GA: ASHRAE.
ASHRAE Standard 62.1. These are
included in the modeling. 5. American Society of Heating, Refrigerating, and
October 2010
Air-Conditioning Engineers. 2010. ANSI/
From a whole building perspective, ASHRAE/IESNA Standard 90.1-2010: Energy
including receptacle loads (for example Standard for Buildings Except Low-Rise
copiers, vending machines, etc.), the Residential Buildings. Atlanta, GA: ASHRAE.
energy cost savings is over 23 percent
New application manuals
and the energy savings is almost 25
percent, when compared to reference now available
buildings meeting 90.1-2004. Trane now offers online
Central Geothermal Design and
Until the change to the Title, Purpose, courses for LEED credential Control. (SYS-APM009-EN,
and Scope made by Addendum AQ, maintenance and AIA April 2010)
the committee could not address loads
from receptacles or processes. If
required learning units at
receptacle thermal loads are included no charge Chilled-Water VAV Systems. (SYS-
in the model, but not their electrical APM008-EN, August 2009)
consumption, the savings estimates Since becoming a U.S. Green Building
rise to almost 29 percent for cost and Council (USGBC) Education Provider in Multiple Chiller System Design and
31 percent for energy. February 2010, Trane has been working Control. (SYS-APM001-EN, May 2009)
to make Leadership in Energy and
In addition, there are a significant Environmental Design (LEED) Visit www.trane.com/bookstore to
number of addenda that have yet to be credential maintenance courses order and view a complete list of
modeled, so the final saving estimates accessible online. The newly resources.
are expected to be even greater. developed course pages allow LEED
Congratulations to all who worked on professionals to more easily complete
90.1-2010. the continuing education required to
maintain credentials and stay
By Susanna Hanson, applications engineer and
competitive in the sustainable building
Jeanne Harshaw, program manager, Trane.
Susanna was a member of the 90.1 Mechanical industry.
Subcommittee throughout the development of
90.1-2010. You can find this and previous issues of The courses were developed and are
the Engineers Newsletter at www.trane.com/ offered free of charge to demonstrate
engineersnewsletter. To comment, e-mail us at Tranes commitment to sustainable
comfort@trane.com.
design. LEED Accredited Professionals
(APs) and AIA members can participate
and earn an average of 1.5 Continuing
Education (CE) hours per program.

Visit www.trane.com/
continuingeducation to view current
courses and details.

Trane, Trane believes the facts and suggestions presented here to be accurate. However, final design and
A business of Ingersoll Rand application decisions are your responsibility. Trane disclaims any responsibility for actions taken on
the material presented.
For more information, contact your local Trane
office or e-mail us at comfort@trane.com

8 Trane Engineers Newsletter volume 393 ADM-APN038-EN (September 2010)

You might also like