Professional Documents
Culture Documents
ARTICLE I
GENERAL PROVISIONS
-1-
Section 2. Guiding Principles Article 6.3 of the PGC and Article 6.3 of
the PDC directed the Grid Owner and the Distributors to conduct transmission and
distribution planning studies for the preparation and evaluation of transmission and
distribution system reinforcement projects and for the preparation of the
transmission and distribution development plans. TransCo is mandated to prepare
the Transmission Development Plan (TDP) for its submission to the DOE for
integration with the Power Development Program (PDP) and the Philippine Energy
Plan (PEP). Similarly, Distribution Utilities are mandated to prepare and submit
their annual 5-year Distribution Development Plans to the DOE. Individual
development projects found within the TDP and the DDP shall be reviewed by the
ERC.
-2-
c) Distribution Development Plan shall refer to the five-year
development plan submitted by the distribution utilities to the DOE not later
than the fifteenth (15th) of March of every year, pursuant to Section 23 of
R.A. No. 9136 and Rule 7, Section 4(p) of its IRR. In the case of electric
cooperatives, such plans shall be submitted through the NEA for review and
consolidation, in preparation of the National Electric Cooperatives
Distribution Development Plan.
g) Economic Zone (EZ) shall refer to the selected areas which are being
developed into agro-industrial, industrial, tourist, recreational, commercial,
banking, investment and financial centers. An EZ may refer to any of the
following: Industrial Estates, Export Processing Zones, Free Trade Zones,
Information Technology Parks and Tourist/Recreational Centers, such as
but not limited to, those managed, administered, or operated by the Bases
Conversion Development Authority (BCDA), Cagayan Economic Zone
Authority (CEZA), Clark Development Corporation (CDC), Subic Energy
Zone (SEZ), Philippine Economic Zone Authority (PEZA), Phividec Industrial
Authority (PIA), and Zamboanga City Economic Zone Authority (ZCEZA).
-3-
k) Grid Code shall have the same meaning as Philippine Grid Code.
m) Grid Owner shall refer to the party that owns the high-voltage
backbone transmission system and is responsible for maintaining adequate
grid capacity in accordance with the provisions of the Grid Code.
o) Person shall refer to a natural or juridical person, as the case may be.
r) Philippine Grid Code (PGC) shall refer to the set of basic rules,
requirements, procedures, and standards that will ensure the safe, reliable,
secured and efficient operation, maintenance, and development of the high-
voltage backbone transmission system in the Philippines. It identifies and
recognizes the responsibilities and obligations of the Grid Owner, System
Operator, and the Market Operator.
-4-
t) Transmission Development Plan (TDP) shall refer to the program for
managing the transmission system through efficient planning for its
expansion, upgrading, rehabilitation, repair, and maintenance, to be
formulated by DOE and implemented by TRANSCO or its buyer or
concessionaire.
a) Major Capital Projects are projects that are larger in scale in terms of
the nature and scope of work and involve several inter-related activities,
including the construction, upgrading, extension or installation of new
and/or of existing major transmission / sub-transmission facilities,
distribution systems and substations; systems control, protection,
metering and communication facilities, that are necessary to improve the
reliability, adequacy and efficiency of the electric transmission and
distribution system, as the case maybe.
Minor Capital Projects shall not require the approval of the ERC but shall
be submitted for monitoring purposes not later than the 30th day of
September of the current year together with the following information: (1)
Project Description; (2) Justification for the Project; (3) Detailed Cost
Estimates; and (4) Proposed Project Schedule.
-5-
c) Emergency Capital Projects are projects that require immediate
action in order to maintain safe, reliable, secured and efficient operation
of the power system.
The Electric Utility shall inform the ERC in writing within 30 calendar
days upon implementation of Major Emergency Capital Projects and
shall include the (a) Project Costs and (b) Project Schedule.
The Electric Utility shall file an application for approval within 30 calendar
days after completion of Major Emergency Capital Projects.
ARTICLE II
-6-
iii. Leverage, Liquidity, Efficiency and Profitability Ratios for the two
most recent 12-month periods (include Return on Equity and
Working Capital Ratio);
iv. Major assumptions used in estimating benefits and expenses to
be obtained and incurred during the lifetime of the project;
7. Front-End Engineering Design and Drawings (sufficient to conduct
bidding);
8. Project Cost Estimates (Equipment, Materials, Installation/Construction,
Testing & Commissioning, Feasibility & Engineering Design);
9. Project Financing Plan (i.e. amount and sources of financing);
10. Proposed Gantt Chart Schedule;
11. Board resolution approving the proposed Project(s);
12. Agency / Instrumentality Approvals (when applicable);
13. Plan for Right-Of-Way Acquisition (when applicable);
14. DOE certification that the proposed projects are consistent with the TDP
/ DDP;
15. Results of the competitive bidding and procurement process conducted
including the proposals of all suppliers and/or contracts (when available)
-7-
Section 3. The Electric Utility shall submit to the ERC a written report,
together with justifications, if it decides to defer or cancel approved Major Capital
Projects.
ARTICLE III
ADMISTRATIVE SANCTIONS
ARTICLE IV
TRANSITORY PROVISIONS
Major Capital Projects that have been completed or have been commenced
shall be submitted for the ERCs approval, within three (3) months from the date of
the effectivity of this Guidelines.
ARTICLE V
FINAL PROVISION
Section 3. EFFECTIVITY - This Guidelines shall take effect fifteen (15) days
upon its publication in a newspaper of nationwide circulation.
-8-
RODOLFO B. ALBANO, JR.
Chairman
-9-