Dynamic Modification Rule:

DMR contains the conditions for the inspection stage change. Inspection stage changes occur on the
basis of the inspection results that are recorded for inspection lots and inspection characteristics
(that is, on the basis of their acceptance or rejection).

You can store DMR rule at one of following place:

1) Insp plan - header level

2) insp plan - char level

3) Material master - Insp type level

With ref to DMR condition system update the quality level, which always reflects the current status.

ex: one ROH material which we receive from one vendor.


Now as per SOP we want to do inspection first time only if it accepts then don't want to do inspection
for next 5 lot otherwise continue inspection.

If we have this kind of req then we can use DMR.

Basic Steps to Create Dynamic Modification Rule

Process:
Quality Management > Inspection Planning> Basic data> Sample > Dynamic modification Rule (QDR1)

DMR is basically used to vary the inspection scope.


DMR can define in 1. Task list at header level
2. Task list at characteristic level
3. Inspection setup of the material master at
inspection type level

E.g:
Normal inspect(5 lots(A*)) > skip(10lots(A*))> Reduced inspect(1 lot(A*))
> skip(10lots(A*))
skip(10lots(R*))> Tighten inspect(5 lot(A*))> Normal
inspect(5 lots(A*))
A Lot Accept
R Any one Lot Reject

Select option Dynamic modification rule is created for usage decision /At lot creation.

Assign stage, required inspection severity, enter short text and tick on Initial Inspection
Stage(ISt) )/Skip stage.
Normal inspection:

Skip Stage:
Max.skip duration is in days :
This field is used in the following ways:
To determine the current inspection stage at sample determination

When the quality level is updated

The system first checks the number of skips and then the skip duration.
Inspection lot creation
At sample determination for a lot, if the number of allowed skips has not yet been
reached, but the maximum skip duration has been reached or exceeded, the next stage
in the sequence for accepted lots is taken as the current stage for the inspection lot. If
this stage is another skip, then the next stage in the sequence for a rejected lot is taken
as the current inspection stage. This means that the current inspection lot is due for
inspection as a result of the maximum skip duration, although the quality level contains
a skip as the next inspection stage.

Update of the quality level


The quality level is updated either at lot creation or when the usage decision is made.
The update occurs independently of sample determination for an inspection lot (even if
dynamic modification takes place at lot creation) and always occurs after the current
inspection stage has been determined for the inspection lot. If the maximum skip
duration has been reached or exceeded, when the quality level is updated, the system
calculates the next inspection stage for the quality level of an accepted lot based on the
same algorithm. This means that the following stage in the sequence for accepted lots
is used as the next inspection stage. If this stage is a skip, the following stage in the
sequence for a rejected lot is taken as the inspection stage for the quality level. Since
this stage usually specifies an inspection, the next inspection lot is to be inspected.

Tighten inspection:

Reduced inspection:
We can assign DMR in
1. Task list at header level
2. Task list at characteristic level
3. Inspection setup of the material master at
inspection type level
We can review/change Quality level for DMR by using T.code QDL1/QDL2/QDL2

other guidance:

1.Create a DMR(Steps Given Below)

Now Lets consider material 123000 there are 2 vendors ABC and XYZ

For Vendor ABC you can create a task list where in Material Assignment you can mension ABC
vendor agaist material and Maintain a DMR(at lot level in Header of inspection Plan) which is Alwaz
skip.

For Vendor XYZ you can create a task list where in Material Assignment you can mension XYZ
vendor agaist material and do not maintain DMR.

Now look at the steps:

1.Go to QDR1

2.Click on At lot level.

3.Go to Next screen

4.Say stage 10 , click on skip ,short text:Skip

5.Next line say 20,Enter seviarity say 4 ,click on seviearity ,Enter short text as say reject

6.select bot lines and click on stage change

No. of skips........999( you can change also)

New insp. stage :10


Rejections 1

New insp. stage:20

for stage 20:

No. of Inspection : 1

New insp. stage :10

Rejections 1

New insp. stage:20

SAVE

Apply this DMR to Inspection plan with vendor ABC


His lots will be alwz skip while do not apply any DMR to XYZ his lots will be under inspection alwz.

You need not to change Quality level manually

DMR: simple words means when you dynamicall want to change the stages of the inspection.that
means you want to reduce the inspection or skip the lots or tighten the inspection.

DMR mainly used for reducing the cost of inspection.

There are many links which are available with example for the same.

DM rule

DMR

Dynamic modification

Dynamic Modification Rule (DMR) at lot creation

DMR - QUALITY LEVEL

DMR @ Char level

DMR inspection stage


https://archive.sap.com/discussions/thread/1661660

You might also like