Why DG PV Hybrid System?
Benefits of DG PV Solution
Grid
Mahindra Advanced
Controller Unit
(MACXTM)
Prevents underloading of DG
Vendor Agnostic
Mahindra DG PV Hybrid Illustration
8 AM LOAD
100 kW
Available: GRID, PV
Case 1: PV < LOAD
SOLAR (100 kW PV) Normal operation
50 kW
Energy Meter
Power line
Energy Flow 50 kW
0 kW DG 125 kVA
Communication
GRID
Control
Mahindra DG PV Hybrid Illustration
11 AM LOAD
40 kW
Available: GRID, PV
SOLAR (100 kW PV) Case 2: PV > LOAD
High SOLAR generation
40 kW
60 PV begins to adjust with LOAD
PV limited to LOAD capacity
No power drawn from GRID
Energy Meter
Power line
Energy Flow 0 kW
0 kW DG 125 kVA
Communication
GRID
Control
Mahindra DG PV Hybrid Illustration
12 PM
LOAD
Available: GRID fails, DG on, PV on 100 kW
Case 3: LOAD = 80% DG
SOLAR (100 kW PV) DG lowered to 50% loading
40 kW
0 kW
Energy Meter
Solar is on
Sun MACXTM SOLAR
DG loading
generation
is
It iskW
100 checked
DG if
reduced to on
present 50% at
100 kW LOAD
higher SOLAR on
80% increased
SOLAR
Saving loading
on fuel
INVERTER generation is
consumption
to 40 kW
possible
Electrical Panel
Power line
Energy Flow 0 kW
100 kW
60 kW DG 125 kVA
Communication
GRID
Control
Mahindra DG PV Hybrid Illustration
1 PM
LOAD
Available: DG, PV 80 kW
Case 4: LOAD < PV +30% DG
SOLAR (100 kW PV) High SOLAR generation
SOLAR begins to reduce
75 kW
42.5 kW DG loading below 30%
SOLAR limited
DG loading brought to 30%
Energy Meter
DG loading
Sun MACXTM SOLAR
changes
High generation
to safe
generation
ofreduced
100 kW to
LOAD
75loading
DG on
kWat 62.5
of
20%
SOLAR onis
INVERTER 30%, kWensuring
on
long life of system
Electrical Panel
Power line
Energy Flow 0 kW
25 kW
37.5 kW DG 125 kVA
Communication
GRID
Control
90 Solar DG Load Solar Generation
80
Without Controller
70
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Increasing intelligence of solar installations
Increase solar penetration With Controller
Reduce diesel consumption 90 Useful Solar Energy DG Consumption Excess Solar Power
80
Integrate remote monitoring facility Solar Generation Load
70
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Installation at Igatpuri