Professional Documents
Culture Documents
lntroduction................................................................................. 6
Safety ............................................................................................... 40
lntroduction ...............................................................................................40
Risk assessment ..................................................................................... 40
Communications & hand signals ............................................................. 44
Personal protective equipment ................................................................ 45
Capacity classification ............................................................................. 45
Sea state (only applicable for offshore applications)............................... 47
Constant tension system ......................................................................... 48
Wave compensator .................................................................................. 48
Loadlradius table ..................................................................................... 49
Overload protection ................................................................................. 49
Commissioning and testing ..................................................................... 52
Taking a crane int0 service ..................................................................... 52
Seafastening of 800 Ts mast crane ......................................................... 53
Precautionary measures ......................................................................... 55
Personnel baskets ................................................................................... 55
Leaving the crane .................................................................................... 56
Summary ................................................................................................. 56
Questions ................................................................................................ 57
APPENDIX
Crane operators exercises on board.............................................. . . . . . 196
The original context of this book was composed by SBW in order to educate and
train offshore crane operators. lt has been extended and reduced in order to
comply with the specific requirements for a Heavy Lift Crane operator on board of
Jumbo Heavy Lift vessels.
The context is still subject to changes. Any recommendations, extra subjects or
alike from crew members are welcome and wil1 be considered for addition in later
issues.
Chapter 2 discusses the types of cranes and derricks most commonly found in use
on Jumbo Heavy Lift vessels. We then move on to definitions and the basic
knowledge that is required for an understanding of the later chapters.
These chapters can be skimmed through if these basic ideas are already familiar
t0 you.
Chapter 3 provides a brief explanation of the main components of the Heavy Lifi
Mast Crane (HLMC) and the terminology used to refer to them.
Chapter 4 deals with safety and the many factors that contribute to it, such as:
personal protective equipment
risk assessment
risk control
maintenance
communications
crane capacity classes
sea state
shock loading factor
offlead and side lead
constant tension
wave compensation.
Chapter 6 deals with lifting equipment: maintenance and inspection and colour
coding used on board Jumbo heavy lift vessels, as wel1 as rejection criteria of wire
ropes
Chapter 7 deals with lifting chains and the associated equipment including:
e Ming hooks
connections
eye bolts
eye nuts
a chain combinations
* chain slings
working Ioad factor.
Chapter 8 is concerned with steel wire ropes, their various terminations and
combinations of wire ropes.
Chapter 12 deals with the safe attachment of loads, and wil1 be useful to slingers
as wel1 as crane operators.
Chapter 14 contains the answers to the questions at the end of each chapter.
In case a large load moment is required (> 10,000 ton meter), the slew ring
diameter increases and therefore the foot ~ r i nof
t the crane.
Pedestal Crane
Radius k4
y l
!
Mast Crane
Radius 4
!
!
!
!
!
!
Load
As the load moment of the HLMC is completely absorbed by the mast and not by
the slew ring hearing (like a pedestal crane), it can be built very slender.
As the winches are placed in a fixed position in the lower part of the vessel below
the mast foot, the slewing range is limited to 2x210' to either side from the .neutral
position
lPropulsion
The HLMC's or Mast Derrick systems on board Jumbo vessels are driven:
e electro-hydraulic high pressure (280 bar)
e electro-hydraulic low pressure (30 bar) (mast derrick systems only)
e fully electrically driven (440 Volt 60 Hz)
We wil1 not discuss in detail the various drive systems of the Jumbo derricks and
mast cranes, as the maintenance and repair of these drive systems fall under the
responsibility of the Chief Engineer on board and are not being repaired or
maintained by the crane operator
lifting capacity
By lifting capacity we mean the mass of the load in relation to the radius, so for
example 400 tonnes at a radius of 18 m. The lifting capacity of a telescopic jib
crane is low in comparison with a crane with a solid-walled or lattice jib.
Lifling a 115 Ts Module on board of a Jumbo Heavy Lift A 300 Ts telescopic crane used to tail-in a reactor vessel
vessel
lifting force
Lifting force is the force necessary to lift the working load. This depends on the line
pull of the runner wire and the number of reevings in the hoist block.
The 800 Ts mast crane is equipped with a hoist block of 7 sheeves (14 parts) and
with a line pull of 67 ts can develop a max. force of 800 ts. Bear in mind that 14x67
ts = 938 ts, but that friction in the sheeves decrease the max. lifting load.
The 800 ts mast crane wil1 be upgraded to 900 ts SWL, by adding an additional
sheave to the main hoist block (8 instead of 7 sheaves). In normal operations, the
crane wil1 be reeved for 800 ts SWL, but can be re-reeved to 16 parts and have a
SWL of 900 ts.
lifting tackle
Lifting tackle is the equipment (2) which is needed to attach the useful load (1).
This includes slings, chains, spreaders and lifting beams. By useful load we mean
solely the load ( l ) , that is, without lifting tackle (2) the crane hook (3), rope bal1 (4),
block (5) and rope (6).
w. l l"",,
4. rope bal1
5. crane block
6 . rope.
useful load
The useful load is the maximum load that can be lifted, minus the lifting tackle.
working load
Working load is the combination of the useful load (1) and the lifting tackle (2).
We make a clear distinction between the working load and the hoisting load.
With cranes, the working load is always less than the hoisting load.
hoisting load
Hoisting load is made up of the working load plus the lifting gear (3, 4, 5, 6)
situated above the hook.
test load
The test load is the load with which the lifting equipment was tested. Testing is
necessary to ensure that the equipment is fit for its task. Testing may take place on
a test bench or with a test weight. The unit for load testing is kN. (kiloNewton)
breaking load
The load at which failure occurs is called the breaking load. There is a difference
between the calculated breaking load and the actual breaking load. The calculated
13 of 197 OSBW & Jumbo A Jumbo Crane Operator Syllabus
- .-., .,.. .- . .
"
breaking load is the theoretica1 limit at which the lifting equipment wil1 fail. If the
load which wil1 break the equipment is determined in practice this is referred to as
actual breaking load. The unit for breaking load is kN.
working coefficien
Of course you must never load lifting equipment so heavily that it fails, and indeed
an ample safety factor must be adopted. The ratio between the breaking force and
the Safe Working Load of an item of Ming equipment is known as the working
coefficient or working factor. A working coefficient of 5 means that the SWL may
not exceed 115 of the breaking force. Since the SWL is a mass it is first converted
to N (Newton). The size of the working coefficient depends on the type of
equipment and in some cases on the SWL. The usual working coefficient for
chains and chain assemblies is 4. The coefficient for steel wire rope is 5, and for
fabric slings it is 7. We wil1 be looking further int0 this in the coming chapters.
Chains =4
Steel wire ropes= 3,33 - 5 (depending on capacity) < 25 ts = 5. > 180 ts = 3.33
Hoisting cables = 3-4
Synthetic slings= 7
Weight as a force is therefore expressed using the Newton as a unit. The weight of
an object with a mass of 100 kg is therefore 100 x 9,8 N = 980 N.
When lifting loads the load is expressed in mass with units of kg or tonne (= 1000
kg). In practice this is equivalent to the weight in the unit N.
If this resultant force crosses the point known as the tipping point, then the
briefcase wil1 fall over. The magnitude of the resultant force 'R' depends on,the
acceleration of the train (here we took 3 m/s2).
The Same theory applies in reverse when the train is stopping. The train's braking
is a deceleration. The Force 'F' wil1 now point in the opposite direction. Again, if the
force 'R' crosses the tipping point then the briefcase wil1 fall over, but this time in
the opposite direction. If you can understand these basics then a lot of the
principles in the transportation, lifting and rigging business wil1 become clear.
The principles outlined above should also explain why we move heavy loads
slowly, and why we avoid abrupt accelerations and decelerations.
The magnitude of the acceleration or deceleration directly affects the forces (in
Newtons, or in the US Poundforces; 1 Poundforce = 4.45 N) on the load.
Returning to the example above, if the acceleration of the train is slow enough then
the resultant force R wil1 remain in front of the tipping line and your briefcase wil1
"
L-..
..... .. - ......
u.
not fall over. Naturally, if the braking is slow enough then the sarne principle
applies.
combining forces
Usually objects are acted upon by more than a single force and the various forces
often vary in direction and size. We are then required to find a force which can be
substituted for those varying forces, but still has the sarne end effect as those other
forces applied in combination. This is referred to as the combination of forces, and
the single substitute force is called the resultant.
Where two forces operate in the sarne line of action and in the Same direction, the
resultant is the addition of both forces. Where two forces operate in the Same line
of action but in opposite directions the resultant is equal to the difference between
the two forces.
Where two forces in a single plane operate at a particular angle with respect to one
another, we can determine the resultant by drawing a so-called "parallelogram of
forces".
We draw the forces to a particular scale (F1 and F2). We then move the forces
along their line of action until they cross at point S. Frorn S we then once again set
out the magnitude of the forces ( F l ' and F2').
By drawing a parallelogram, we can now find the size and direction of the resultant
between the points S and R.
resolution of forces
The resolution of forces is the opposite of
combination of forces. When forces are
resolved, a single force is replaced by several
forces. Taken together, these forces have the
Same effect as that single force. In lifting
operations forces are often resolved. Say for
example you need to lift a case. The weight of
the case creates a force equal to G Newton.
The lifting force G, must exceed G in order to
allow the lift to be performed. The lifting force Gl
can be resolved int0 two forces (Fl and F2)
which operate on the slings used to lift the case.
We can see from the angle drawn that the
forces F, and F2are smaller than the lifting
force G1.
Calculation wil1 show that the forces in the slings and the lifting force are equal
when the angle is 120'. That angle must therefore never exceed 120' for any lifting
operation.
lForces on cargo
Forces are created during the storage of containers, which they must be able to
resist.
The container and or heavy lifts must be of sufficiently robust construction to resist
these forces and must be adequately lashed and secured.
Life can be hard for containers and heavy lifts when there is bad weather at sea.
D rolling
The horizontal force is even greater at the moment the ship begins to rol1 back in
the opposite direction. The container is still trying to move at full tilt in the direction
previously dictated by the rol1 of the ship.
D pitching
Similar forces are created by the pitching of the ship, which is rotation around the
transverse axis of the vessel. The horizontal force created by pitching may reach
17% of Fg. This force is therefore much less powerful than the horizontal force
created by rolling, but it occurs in a different direction, namely along the length of
the container.
Heaving of the vessel occurs as the ship moves from wave crest to wave trough or
vice versa. The movement from wave crest to wave trough creates an upward
force, while the reverse creates a downward force.
Pitching of the vessel results in upward and downward forces on the container
The magnitude of the force is dependent upon the loading of the container and the
speed with which the ship rises and falls. These movements don't occur in
isolation, the motion of a ship is usually a combination of the three main motions.
If the container is not properly secured on deck, there is a risk of it slipping from its
lashings.
wind force
The force of the wind influences the lifting of containers. The wind can exert a
considerable force which can cause the container to swing and roll.
Experiments have shown that the wind force can be calculated using the formula:
P = 0.625 v2
p = wind force in N/m2
v = wind speed in m/s
For example we can calculate the pressure exerted by the wind at Beaufort force
6. At force 6 the wind speed is 10.8 - 13.8 mis, giving a rounded mean of 12 mis.
The wind pressure is then p = 0.625 x 12 x 12 = 90 N/m2
You wil1 see that a quite substantial force is exerted upon the container at wind
force 6.
lAttaching containers
Offshore, containers are usually lifted using the corner fittings. A 4-leg sling is
usually attached to the container. The container's corner fittings are then
horizontally loaded. This is only permitted with 10- foot containers, and the
diagonal included angle of the sling legs may not exceed 60'.
10- foot containers are usually lifted with a 4-leg sling offshore
The 10-foot container is therefore rnuch used offshore. There are 20, 30 and 40-
foot containers which can be lifted with a 4-leg sling, the so-called platform
containers.
The slings are usually connected to the container with a D-Shackle, and the top
link is left hanging over the side of the container.
This makes it easier to attach the hook.
Before attaching a container you must be aware of the inspection criteria.
MP1 is a Magnetic Particle Inspection, which checks for cracks with the aid of
magnetism. Where this test is impractical a penetrant dye test wil1 be carried out.
The object in question is sprayed with a penetrant dyestuff which reveals any
cracks.
D load test
The load test is a test of the load hearing capacity of the container. The inspection
data are shown on a plate. A crane operator can always see whether a container
has been inspected.
DATA 1'1ATE
Ownei-s Name: ("TB 0 1 1 . SERVICES LTO
L l
The most important data on the container, including the inspection details, are shown on the inspection
plate.
D Summary
We have learned about different type of cranes and the principle of the Heavy Lift
Mast crane and derrick systerns. What Safe Werking Load means and something
about masses and forces. Newton, kilogram and the difference between mass and
force and what effect accelerationldeceleration has on masses. Which safety
factors are applied and what it means. We have learned how forces can be
combined and what forces act on cargo on board of a vessel on the high seas.
B Questions
2.1 What is meant by lifting capacity?
2.2 In this lifting situation using a crane, which items are considered
"lifting equipment"?
A Only 2
C 3 , 4 , 5 and 6
D 2, 3,4, 5 and 6
C The maximum force that may be exerted upon the lifting equipment,
,, UMBO%
2.5 What does the abbreviation SWL stand for?
2.7 What are the specific features of the Heavy Lift Mast Crane ?
A. Small foot print and large load moment, one slew bearing,
winches at rear side of mast, high Centre of Gravity
B. Small foot print and large load moment, two slew bearings,
winches in lower part of mast foot, low Centre of Gravity
C. No counter weight needed, small foot print and large load moment,
one slew bearing, winches in upper part of mast
D. Low Centre of Gravity, small foot print and large load moment,
two slew bearings, trolley hoist under jib
A. 360fu11 rotating
D. 1 x 180'
2.9 What is the rnax load moment of the Jumbo 800 tons mast crane?
A. 22400 tonmeter
B. 12400 tonmeter
C. 560 tonmeter
D. 42000 tonmeter
A. 7
B. 4,6
C. 3
D. 5
A. 7
B. 4
C. 3,33
D. 5
A. 7
B. 4
C. 3
D. 5
A 50'.
B 60'.
C 70'.
D 80'.
2.15 What is the resultant force acting on a rnass of 10 tons, when it is subject to
a horizontal acceleration of 4 m/s2 and earth's gravity of 9.81 rn/s2 ?
A. 140 N
B. 107.70 N
C. 105.65 N
D. 10.6 ton
In case a large load moment is required (> 10,000 tonmeter) , the slew ring
diameter increases and therefore the foot print of the crane.
As the load moment of the HLMC is completely absorbed by the mast and not by
the slew ring hearing (like a pedestal crane), it can be built very slender. As the
winches are placed in a fixed position in the lower part of the vessel below the
mast foot, the slewing range is limited to 2x210' to either side from the neutral
position
All other vessels are equipped with HLMC's with the exception of the so called G-
types (mv. Stellanova, Jumbo Spirit and Fairload) which are equipped with a 250 ts
mast derrick system and a 250 ts HLMC. See picture below:
On the larger HLMC's (400 ts and 900 ts HLMC) used on the Jumbo vessels,
there are additionally one or two tugger winches installed for load control.
These extra tugger winches are controlled from a separate transmitter control box
lifting capacityloutreach
Seafastening position
Originally the mast cranes of the J-Class were built as 800 Ts mast cranes. In
2006 both J-Class heavy lift vessels have been upgraded to 900 Ts lift
capacity/crane. Normally both cranes are reeved with 14 falls for 800 Ts lift
capacity and need to be re-reeved to 16 fall in order to reach 900 ts lift capacity.
The crane jib is normally stowed in vertical position against the sea fastening
supports in the masthead. For sea fastening of crane jib and load blocks one
should follow the detailed procedures as specified per crane.
D Jibs
Jibs can be constructed in various ways. We wil1 briefly discuss various jib types:
m Box girder jib
m telescopic jib
m lattice jib.
All jibs on the HLMC's of Jumbo Heavy Lift vessels are of the box girder type.
The jibs on the Sennebogen crawler crane of the J-Type vessels are of the
telescopic type
The 800 tons mast crane with box girder jib assemblee! in the Huisman workshop.
The sliding in and out of the jib sections is referred to as telescoping. The rollers or
wear pads mounted between the sections facilitate smooth telescoping. They must
be regularly lubricated to cut down wear and you must always be careful when
telescoping.
The following guidelines should be kept in mind when telescoping the jib:
o Where possible, avoid telescoping with a load on the hook. The mass of the
load sets up considerable forces, causing extra wear to the rollers and wear
pads
o Raise the jib as high as possible before telescoping. The forces acting on the
rollers and wear pads are noticeable reduced when the jib is fully raised
o Don't work with the jib fully extended, instead withdraw it slightly. In that way the
forces are not always concentrated on the Same points on the jib.
lattice jib
Lattice jibs are constructed of welded angle bars, U-shaped or tubular section of
steel. Tubular sections are more resistant to buckling in any direction than angle
For use offshore, all joints are blasted and welded water-tight to achieve maximal
strength and corrosion resistance. Blasting is a treatment where sand or grit is
driven against the object to be treated by high-pressure air. All corrosion is
removed.
High-grade steel is used in the construction of all components.
Manufacturers of lattice jibs do take int0 account that the pull on the crane rope
may sometimes be on the skew: that is, that lifting is carried out even though the
crane hook is not directly below the jib head. This may be due to the motion of a
ship for example. Weather also affects lattice jibs more than solid jibs. Lattice jib
sections usually have flanges at each end allowing the sections to be assembled
using nuts and bolts. Luffing is by means of a steel rope and drum. Jumbo mast
cranes and derricks are not using lattice jibs. This only applies to offshore cranes
or mobile cranes on land.
Load i
!
!
!
!
Radius
i
The difference between a pedestal crane and a mast crane is that the load
moment (load x radius) is in the pedestal crane absorbed by the two blue forces in
the slew bearing, while the mast crane slew bearing only has to absorb the
pressure force of the jib, the load moment is absorbed by the fixed mast structure.
The mast crane is often refered to as a "Kingpost crane" when applied on an
offshore platform
slewing gear
The slewing gear consists of an internally or externally toothed ring rotating on a
slewring provided with bal1 or roller bearings. The toothed ring is attached to the
pedestal, while the slewring is attached to the crane (pedestal crane) or to the
slewing ring platform (mast crane).
D toothed ring
A smaller gear wheel (pinion) is fitted to the crane to turn the toothed slewing ring.
Turning the pinion turns the crane (pedestal crane) or jib and mast head (mast
crane) : the pinion pulls itself around the toothed slewing ring, taking the crane with
it (pedestal crane) or the slew gear (pinion) is fixed to the mast structure and
moves the slewring platform (mast crane).
400 Ts mast
cranes, driving
the siew platform
Dslewing brake
The slewing brake must be applied when the crane is idle or when it stands still for
a short time with a suspended load, particularly in squally weather or high seas.
32 of 197 OSBW & Jumbo A Jumbo Crane Operator Syllabus
D slewing lock
In general the crane must be prevented from slewing of its own accord when it is
not in use. This may be done by means of a slewing lock if fitted. The lock often
consists of a pin located in a seating in the pedestal. The Jumbo mast cranes are
not equipped with a slewing lock, as the slew gear brakes are automatically
activated when not slewing. When the ship sails, the jib is placed in vertical sea
fastening position and locked to the masthead.
D Crane cabin
All crane movements are controlled and monitored from the cabin or by a remote
control box. Jumbo still has cranes with a cabin, but all recent mast cranes are
outfitted with remote control boxes. The advantage of this control box is that they
do not obstruct cargo as they are small and not fitted to the crane slew platform.
One can easily walk around the ship and on the quay while operating the crane.
The disadvantage is that one gets easily disturbed from the control task which
could lead to dangerous situations. A standard procedure on board of Jumbo
Heavy Lift vessels is that a crane operator, who operates a crane with a remote
control box, must follow instructions from a signa1 man. Both functions should not
be combined, due to safety reasons.
A good overview of the lifting operation and the crane functions can be obtained from the cabin
For application on offshore platforms the cabin must be insulated against noise
and the doors must be capable of watertight closure. Crane cabins are sometimes
over pressured to prevent the ingress of gas. Electrical components in such cabins
are not protected against explosion. Cabins are often air-conditioned.
Looking upwards in
mast structure of 400 ts
mast crane
hoisting drum
The hoisting drum must be provided with over lowering protection to ensure that
three residual turns of rope remain on the drum when the rope is paid out to its
maximum working length. The protection is initiated when three turns of rope
remain on the drum. The motion in the opposite direction, where rope is taken in,
must still be possible. For offshore cranes the over lowering protection must be
capable of being over-ridden by means of an emergency lever.
The main hoisting winch, auxiliary winch and luffing hoist drum of
an offshore crane.
D Block seafastening
On all Jumbo mast cranes the jib is stowed and seafastened in a vertical position
against the masthead of the mast crane. Depending on the vessel the seafastening
procedure varies slightly. Basically the hoist blocks are connected with slings to the
jib and pulled under a certain tension to avoid movement of the hoist blocks during
sailing.
All the parts mentioned are present on this rather older crane
D Summary
This chapter has named and described the components of the Heavy Lift Mast
Crane in particular and some other cranes in general.
A Only l is true
B Only II is true.
3.3 Why can the mast crane not slew a continuous 360' ?
C Hoisting and topping wires are running over sheaves in the mast head
3.4 Why should you try to avoid extension of the jib of a telescopic crane under
load?
B. To avoid excessive wear and tear on rollers and guide pads in jib
slewing gear
jib stop
auxiliary mast
latticework jib.
slewing gear
snatch block
auxiliary mast
fixed jib.
pedestal
A-frame
auxiliary mast
jib.
pedestal
auxiliary mast
fly-jib
jib.
3.6 Why are the winches of the heavy lift mast crane placed in the lower part of
the mast foot?
D Risk assessment
In order to prevent accidents and damage, as wel1 as near misses i l is important
that an assessment be made of the risks involved in a lifting task or rnaintenance
activity.
This approach wil1 produce a wel! thought out working situation taking account of:
safety
o health and welfare
o the environment
o efficiency.
Setting down procedures for different activities is a useful aid in ensuring that these
points are addressed.
Before beginning any lifting task, you should make an assessment of the following
matters:
are the crane and the lifting equipment in good condition?
what is to be lifted, is it all on the quayside or does something need to be lifted
off or onto deck or int0 the hold of the vessel?
what is the allowable deck loading, i.e. the mass per m2?
what are the weather conditions? Is it only the wind that needs to be considered
(because the lift wil1 take place entirely on the vessel), or is the sea state factor
to be included because something needs to be lifted off or onto a supporting
vessel or onto the seabed, or is it the swell in the port which wil1 affect the
loadinglunloading conditions
how many banksmen wil1 be required and who wil1 control them?
what equipment is required to lift the load in question?
is the leading banksman aware of the use to be made of the lifting equipment
and the methods of communication?
is the full lift to be in the view of the crane operator or is part of it out of his
view? This is particularly important in the case of the personnel basket.
For lifting heavy loads onloff Heavy Lift ships we should keep following lifting
tios i n mind:
Inform personnel of planned operation and check
communication equipment
> Always check before lifting that all rigging gear is correctly
connected
Make sure personnel stays in clear area's and can not be hit by
swinging cargo
'r- Make sure stability of vessel has been checked and does meet
the Jumbo standards and that all sea fastening has been
released to lift safely
> In case of heavy lifting, blow horn of vessel and switch on alarm lights to
evacuate unauthorized people from board
> When lifting off or onto trailers make sure brakes are off
In case lifting a load from the quay, make sure vessel has room to adjust itself
in the mooring lines
/f you can't answer the following , please fiil in fhe step-by step'section yes n0
1) are the route and laydown area clear of obstructions?
2) is the laydownllanding area adequate in terms of size and load-bearing ability D D
3) is suitable packing available for protection of the load, lifting equipment, slings etc.
4)are barriers ~ositionedto ~ r e v e nacces
t bv unauthorised nersonnel? D
5) have you confirmed that the laydown area is within the operation limitslradius of the equiprnent D
6) are environmental conditions been considered with regards to the safety of the lifting operation?
7) wil1 the lifting equipment operator be able to see the Banksman throughout the operation, or has
another suitable, risk-assessed rneans of communication been checked and made
available (e.g. radios)?
What is important is that those signals used on board of Jumbo Heavy Lift Vessels
are known t o all crew members and used throughout the fleet.
f ^
% ,
i
T"?
t
l I,
STOP DOG EVERYTHING MOVE SLOWLY
l 11
BLOCK UP BLOCK DOWN USE MAIN HOIST
- SWING LEFTiRIGHT
J 1
M I S E BOOM
AND LOWER BLOCK
LOWER BOOM
AND M I S E BLOCK
A final signa1 system for Jumbo vessels wil1 be developed in due course.
Input from crew mernbers is welcome
D Capacity classification
Various influences may be brought to bear on the crane during work offshore:
impacts
e shocks
offlead and sidelead.
An operating cycle is defined as the whole of the activities commencing with the
raising of the load and concluding at the moment the crane is ready to piek up the
next load. To find the total effective duration of service, the classification of the
crane is first established and used to determine the working coefficient.
The working coefficient (Fd) tor offshore cranes is fixed at Fd = 1.2. If you are
curious about how this figure was arrived at, you might like to consult Lloyds Code
for Lifting Appliances in a Marine Environment (Chapter 3: Cranes and
Submersible Lifting Appliances).
The Dynamic factor for the Jumbo Heavy Lift Mast crane to be used in sheltered
water is Fd = 1. l .
In poor weather the supply ship is often moved further away, to prevent damage to
the platform. This situation greatly increases the likelihood of off-lead (an inclined
force on the rope along the line of extension of the jib). Furthermore, the supply
vessel wil1 not remain in one position in such circumstances, causing side-lead, an
inclined force at an angle to t'he jib.
The Jumbo heavy lift mast cranes are designed with a max. off-lead = 1' and a
max. side-lead of 4'. For all offshore lifts with Jumbo heavy lift mast cranes one
should de-rate the cranes with dynamic factors taken int0 account.
'-*
There are established names for the motions of a ship.
6 3 3 6 1,61
1.8
8 4 4 B 2,07
12 6 6 12 2,73
This table shows the sea state values as applied by Lloyds Register of Shipping.
lWave compensator
A crane fitted with a wave compensator provides
the operator with the means to follow wave
motion automatically, with the crane takinq in and
paying out rope according to the motion of the 15 ts tugger winch on stew patform of 400 ts mast
ship. The system is used only on cranes carried
on ships and is intended for use offshore. The
wave compensator can be disabled as required. Jumbo mast cranes do not have a
wave compensator.
The wave compensator lowers the load in a wave trough and raises it as the wave
rises. It passes raise and lower commands to the rope drum which carries out the
relevant motion. You wil1 never be able to react as quickly to wave movements as
some advanced wave compensation systems now in use. We do not discuss this
matter in detail, as it is only applicable to offshore cranes.
General status
* Alarm list
Huisman logo
The
above figure shows the loadlradius table (LCDdisplay) of the 800 ts mast crane.
The crane can lift a max. load of 800 metric Tons at a radius of 28 m over
Starboard and 800 ts at 32 m radius over a limited slewing area of 45' over
Portside. Since the upgrade in 2006, each crane can now lift 900 Ts at 25 m radius
(when re-reeved to 16 falls).The max. load moment of the 800 ts mast crane is
800x28 = 22400 tonmeter. All cranes and derricks on board of Jumbo vessels
have different loadlradius tables.
D Overload protection
Modern offshore cranes are equipped with a load moment computer, which has
become a vital tooi for the crane operator. The load moment computer sounds an
alarm when the maximum permitted load moment is reached.
The system needs three items of information in order to determine whether the
load can be lifted or not:
e jib angle
e jib length (usually a single value for offshore cranes)
e mass of the load.
A sea state selector wil1 be required where loads are transferred between ships
and fixed installations. The sea state selector effectively provides additional load
tables for the crane, taking account of the dynamic effects produced by the motion
of the supply ship.
All Jumbo offshore lifts wil1 be engineered lifts and clear limitations wil1 be set
before a load can be lifted. There are no sea state selectors on Jumbo mast
cranes.
Be aware that the Jumbo heavy Lift mast crane is designed for its max. load to be
lifted in sheltered water only. For offshore lifts a new max. lift capacity must be
calculated, taken int0 account the new dynamic factors.
In the wind force table the first column shows the Beaufor scala, the second
column shows the average value in nautical mph. 1 nautical mile per hour = 1 knot
= 1852 metres per hour. The third column gives the highest value, the fourth gives
the average value in mis and column five shows the highest value in mls. The
rernaining columns show the different descriptions in various European languages.
This wind force table give the relation between Beaufort and windspeed.
A checklist is frequently used to ensure that these checks are carried out.
The load moment computer must be properly set up before lifting. Points to
consider include the sea state and the number of falls of rope used with the main
or auxiliary hoist.
Most of above points remain valid for the Jumbo mast cranes and derricks.
In addition special attention must be paid to the sea fastening of each individual
crane or derrick. A description of the seafastening system of the 800 ts mast crane
is shown below:
NOTE
Before seafastening of every single movement, hook-on seafastening slings at
the main block andhoist the main block
until the slings are just above the
seafastening yoke. This is to be done
before the boom is seafastened because
once it is, the main block wil1 only be
operable in creeping speed. (hoisting
direction only).
NOTE
Seafastening of the tuggers can only be carried out with the jib in seafastening
position.
The seafastening procedure is to be followed in the order as described
previously, so first the topping hoist and ending with the tuggers
During seafastening every movernent is safeguarded via the inverter for max.
torque. This is a fixed value which rneans that it wil1 stop when this value is
reached. Nevertheless, always keep an eye on the load read-out when
tensioning one of the movernents.
WARNING:
BEFORE OPERATING THE TUGGERS ALWAYS CHECK THAT THE
SEAFASTENING PINS ARE REMOVED! (Refer to page 2-6 tor the location of
the seafastening pin)
Maintenance
During maintenance you should make an assessment of the risks that might be
created. Take for example the greasing of rope sheaves. A "lock, tag, try and clear
procedure" may be introduced to prevent anyone switching the crane on during this
work. Before work begins, all forms of energy are switched off, locked and labelled.
Any stored energy is discharged (for example in hydraulic accumulators and
compressed air tanks). A check is then made to ensure there is no energy present
that might initiate a movement. Once you have actually checked that all sources of
energy have been removed, a safe working permit can be issued.
B Personnel baskets
Depending on the weather conditions and company-internal rules, the transport of
persons by means of personnel baskets may be permitted. The applicable
legislation requires that personnel baskets may be used exclusively for the
transport of persons and their hand luggage. In the illustration, the man at the left
has positioneel his arms incorrectly. The man on the right has his arms wrapped
right around the straps, which is correct.
Due to vessel stability, the aft mast crane jib has been secured in
lowered position
D Summary
In this chapter you have seen
how risks can be reduced by
compliance with regulations and
by the method of approaching
work. The approach to a task
should begin with an assessment
of risks, allowing them to be
more easily controlled.
Communications using hand and
arm signals must be agreed, so
that everyone understands one
another precisely. If a walkie-
talkie is used, the recipient's
name or the name of the vessel
or platform must be used with
every command. You have also
learned what is meant by sea
state and how to set up the crane to match it, and you have also learned about
constant tension. You know what is meant by offlead and sidelead. You are able to
use a loadlradius table and a wind force table. Finally you have learned the
requirements governing the use of personnel baskets.
B Small spare parts as long as their weight is within the limits of the
personnal basket.
4.4 With safety in mind, what should you do before commencing a lifting
operation?
4.5 You need to lubricate the rope sheaves in the jib head. The jib is
already in its rest. What precautions are required?
A Switch off all energy sources and notify the installation manager.
B After switching off, lock the switch and hang up a notice to say
maintenance is in progress.
C You are the only one who uses the crane, so you just need to switch it
off.
A Stop; Boom up
D The shock to the load from the sea and the bouncing ship.
D A slanting force on the rope along the line of extension of the jib.
B Check jib head position and verticality of hoisting tackle, inform crew
members of operation, check stabilizer position when in use
A very important basic rule is that the Centre of Gravity of a freely supported load
(CoG) is always directly vertically underneath the boom head and hoist block.
5.1 . l initial-stability
5.1.2 stability-moment
5.1.3 stability-range
5.1 . l The INITIAL STABILITY must be positive i.e. the cargo has
a righting moment when turned over a small angle.
This requires the CoG of the cargo to be inside triangle AHB ,
see figure 5.1 . l
disturbing moment
Figure 5.1.1 from outside
negative initia1
stability: the load
not come upright
anymore !
5.1.2 The STABILITY MOMENT is the up righting moment [ton-meter] due to the
cargo at a given heeling angle. see fig. 5.1 .Z.
l ^
p-,
Conclusion: ! T B
The stab moment is positive and so is the initial ! j ' /
stabilitv if h > v $3.
or in oiher words if the Co G. of the cargo is inside the A
triangle AHB .
vsina-
h sin a --
Figure 5.1.3
Figure 5.1.4
Larae stabil. ranae Small stabil. ranae
The stability range is defined by the angle where the stability moment becomes
zero; in ether words: when line of force F coincides with line through points GA, or :
- u2 rnax
"B
Figure 5.1.5
Figuur 5.2.1 a
Figuur 5.2.1 .b
Conclusion :
If a spreader- or lifting beam is used (as in fig.5.2.1) the vertical wires D-D"en E-E'
do not contribute to the stability and must be ignored for judging the lifting stability.
Lifling a patrol boat out of the water. Lifling a locomotive using a lifting beam
Note the triangle above the lifling combined with 2 spreaders
beam
Some examples are given in figure 5.2.3, where the lifting systems left are not
stable, and at the right side are stable.
Figure 5.2.3
Figure 5.3.1
In order to keep the load level, one should use different lengths of slings.
The correct sling length can be determined by drafting the load CoG, slings and
hook block.
If all is drawn to scale, one can easily rneasure the sling length with a ruler.
The right length of lifting grommets can also be determined by following formula:
(see fig. 5.3.2) :
Figuur 5.3.2
If it still occurs that the load rernains under an angle, despite ti-ie fact that we have
drawn and calculated everything correctly and in case we are sure that the lift
system is stable, then we know the CoG must be in a different location then
assurned.
A good approach for the realistic shift of CoG ( = tcg) compared to the estimated
CoG can be obtained by following formula:
Figure 5.3.4
When using a single lift spreader bearn while CoG is not in the centre, the beam
wil1 be not level before fixing to the cargo. A counterweight could be used.
In order to establish the correct lifting height one should first draw the lower slings
to check if we clear the load with the lifting beam hanging under an angle.
In order to keep the free hanging load with lifting beam level, the combined GoG of
load and lifting bearn must be vertically under the hook block. See example below:
Question:
How much and which sling
should be lengthened to
make sure that the trafo is
lifted level?
Answer:
With formula
X = d L2 + 2 x tcg.x (b-e) we can calculate
the correct lengthening as follows
In order to check possible overload in slings and shackles, one should calculate
the forces in each individual sling or shackle.
The total force in slings is in general bigger then the total load of the cargo. In other
words: if a load of 100 ton is supported by 2 slings, then the average load in each
sling is in general more then 10012 = 50 ton. This is caused by:
- the lifting wires are not vertically but connected under an angle with the load.
(see fig. 5.4.1)
Figure 5.4.1
100 t
In which
HL = 100 ton = hook load
S = tension force in sling under angle a
Fv = vertical force
t HL = 100 Ton
Figuur 5.4.3
fl- -
-k-
UNI3
,-"--
Calculation of forces in slings of unequal lengths
Be aware that when a load is lifted in two cranes and belly slinged and not lifted
horizontally, a horizontal reaction force wil1 occur and slings may slip away.
When a load is lifted with two cranes and the load is not kept horizontal, the load in
each hook block can very significantly. This depends on the location of the CoG of
the load.
the direction of the pulling force acting on a lifting eye must be in line with
the eye (correct direction)
Correct
Less Correct
Correct
Correct Wrong
Correct
Wrong
that the diameter of the pin of the shackle is not too smal1
and in relation to the hole of the lifting eye, as it wil1 cause higher
pressures and forces in the lifting eye.
A bending moment wil1 act upon the welding and plate of the
lifting eye in case one does not pull in the plain of the lifting eye
plate. (zie fig. 5.5.1 and pictures below)
;"l
: L-.
i
1
1. Deformations ; hair cracks in weids. In case of doubt contact the Jumbo office
for advise.
So check :
- thickness eye plate - in relation to jaw width of shackle
- pin diameter - in relation to pin diameter of shackle
- outside diam. eye plate - in relation to inside height of shackle
+ thickness grommet (be aware of tolerances of shackles)
4. accessibility for safe connection of slings such as but not limited to:
ladders; staircases, platforms; temporarily scaffolding; connection line for "life-belt"
; etc. .
I n case serious defects o n the lifting eyes are detected, one should
immediately:
- notify the merchant
- refuse to start lifting the cargo, even in case this wil1 be done by shore crane or
floating crane.
- give the merchant a written report with a clear description of the defects
- immediately inform the Jumbo head office in Rotterdam.
When lifting a load with two cranes it is crucial that the lifting tackles stay exactly in
a vertical position above the lifting points. This is easily said but not so easyly
done. When a long load is lifted from the quay and must be slewed in between
both cranes in order to be placed on deck, both crane operators have to watch
carefully and control three crane movements such as
slewing, topping or lowering of boom, lifting or lowering
of main block and by doing so keep the lifting tackles
vertical above the lift points and keep the load in
horizontal position.
Avoid lifting with two cranes during night time, when visibility is limited.
5.6.1. Spreader- 1 lifting bearn whereby the lifting wires are connected to the
beam.
The forces in the (inclined) slings from the hook to the spreader can be calculated
as per part 5.4. See fig. 5.6.1 below:
The additional component due to the own weight of the spreader beam is:
2.5 lsin 45' = 3.5 ton, so the total force in S = 74.5 ton.
In this case the force in the lifting sling wil! be the Same every where and equal to
10012 = 50 t.
The forces in the additional slings to support the own weight of the spreader beam
as wel1 as the downward component of the main lift slings can be calculated as
below:
We immediately notice that the total force S fig. 5.6.1 per side in the upper slings
is: 711 + 3.5t =74.5 t, while in fig.5.6.2 (when a and p are 45') this should be 50t +
3.5t = 53.5t.
The missing 21 t should in this case be absorbed by the extra lifting slings that
support the spreader beam.
It is clear that the necessary SWL of the lifting slings do not only depend on the
weight of the spreader beam but greatly depend on the load that is lifted and the
top angle p of the slings.
l / Pressure in spreader
............... Neutral axis
Figure 2.6.3
Fv=50t !
S = Fs = Fv = force in lifting sling below and above spreader bearn are equal
S' = force in sling to support spreader beam
If this is not the case, a bending force in addition to the pressure force wil1 act upon
the spreader beam.
A relatively smal1 bending moment can make the spreader buckle.
One should at al1 times check the design criteria of the spreader beam before use
in relation to:
Figure 5.6.4
Fs
Cross point
of worklines /
/ /7
,-
Correct
spreader
L-- >
\
Neutral axis -- --
FV FS FS Not a Correct
/ spreader
COLOUR CODE
In order to identify the differences in SWL and lengths and to avoid
misunderstandings, Jumbo wil1 adhere as much as possible to the standard colour
codes as defined in "Colour Code Lifting material"
Please do not only pay attention to the size of the lifting equipment.
A 55 Tons SWL Crosby shackle could have the Same dimensions as an 85 tons
SWL Crosby shackle and grommets with the Same diameter could have different
SWL's, depending on the used type of wire rope steel. A 110 Ts Greenpin can
have Same dimensions as an 85 Ts SWL Greenpin.
9 MONTHS INVENTORY
Every 9 months the actual quantity of lifting- and lashing material must be
checked.
The checked quantities with possible remarks must be communicated through a
standard form with the Jumbo head office.
For lifting grommets and slings the safe working load is the breaking strength
divided by a safety factor of 3.333 - 5.000 (depending on lifting capacity)
For polyester lifting slings the safe working load is the breaking strength divided by
a safety factor of 7
Lifting beams are all being tested after fabrication with a test load of 10-100% more
then the actual SWL. The correct proof load can be calculated with the forrnula:
Shackles (and turnbuckles) are all being tested after fabrication with a test load of
2 x SWL . The breaking strength is in most cases 4-6 times the SWL
As the known manufacturers "Greenpin" and "Crosby" do not use standard safety
factors, a stamped L.R. (Lloyds Register) certificate is leading
PAY ATTENTION
In case a grommet or sling leads under full load over sharp edges it can darnage
the steel wire ropes severely and reduce the SWL significantly
In all cases cable protectors ("cable shoes") must be used.
The damage or cutting to polyester lifting slings by sharp edges is even greater
than for steel wire ropes.
SHACKLES
Every 12 'l2years the lifting shackles > 12 Ts are being tested.
These tests wil1 be witnessed by Lloyd's or another approved authority.
Tests wil1 be conducted by the Jumbo head office.
Lies, = 1.22 x WLL + 20, i.e. a 55 ts shackle must be tested with a proof load of
A 180 ts shackle with a proof load of: 180 x 1.22 + 20 = 239.6 Ton
GROMMETS
Before use, slings and grommets must be visually inspected by the Captain or
mate.
Grommets must be inspected every 5 years by Lloyd's or another approved
authority.
A certificate of this inspection must be issued by Lloyd's in two fold.
In case grommets are smaller or equal than 10 m and more then 12 Vi years old,
they need to be replaced.
Old grommets must be destroyed. The out of date certificate together with the
change order form need to be sent to the Jumbo head office
With this information the breaking strength of the grommet can be calculated
From this calculation it can be seen that in case the grommet is used in double
configuration we may use twice the SWL (and not 1.5 times)
The reduction in strength due to the bending of the wire rope over a small radius
has already been accounted for in the breaking strength calculation
When a sling (= one single wire rope with 2 eyes) is used in double configuration
over a small radius, we must take into account the reduction in strength.
Now only 1.5 x SWL may be lifted.
In case they do differ from the standard, then this must be reported by means of a
standard change form to the Jumbo head office.
This all is to avoid that a certain shackle does not fit in a certain lifting eye.
D Summary
This is one of the most important chapters in this syllabus. We have learned that
when we lift a load below the CoG, the stability of the load, when lifted is an
important point to be considered. We now know when a load is stable and when
not. We also have learned about forces in slings under an angle and the relation
between angle and load. A description is given on how the lifting equipment on
board of Jumbo vessels is stored, inspected and used and which safety factor
should be taken into account.
D Questions
5.1 Which is a stable lift
100 Ton
A. 71 kg
B. 58 Ton
C. 71 Ton
D. 100 kg
100 Ton
60 Ton
5.5 When we use this lifting beam, what is the load in S1 and S2?
Ignore own weight of the lifting beam.
i
T 2 0 0 Ton
A. No
B. Yes
C. Check shackle dimensions in relation to lifting lug, check lifting lug for
deformations like hair cracks etc., check correct position of lifting lugs
t 7 Fs
snijpunt
werklijnen
B. Only 2 is correct
C. Only 1 is correct
A. 2 x SWL
B. 4 x SWL
C. 1,5 x SWL
D. 5 x SWL
A. 90 Ton
B. 60 Ton
C. 75 Ton
D. 30 Ton
5.1 1 What load can max. be lifted at the tip of the crowbar when pushing down at
one end with 50 kg?
A. 2 years
B. 4 years
C. 10 years
D. 5 years
A. 2 years
B. 5 years
C. 10 years
D. 4 years
A 2 x S W L = 100Ton
B. 1 , 5 x S W L = 7 5 T o n
5.15 What is the max. load of a 50 tons steel wire rope sling used in double
configuration over a small radius?
A. 2 x SWL = 100Ton
C. 1 , 6 x S W L = 8OTon
5.16 What is the max. test load of a spreaders and lifting beams after fabrication?
5.17 What is the load S in both slings, when lifting a load of 100 Tons?
100 Ton
A. 100 Ton
B. 58 Ton
C. 71 Ton
D. 194 Ton
100 Ton
5.18 What is the load S in both slings, when lifting a load of 80 Tons?
80 Ton
A. 64-8 Ton
B. 58 Ton
C. 46,4 Ton
D. 92,8 Ton
80 Ton
D Machinery Directive
Manufacturers are required to meet certain minimum requirements to promote the
safety of rnachinery. These requirements are set down in the Machinery Directive
which came int0 force on 1 January 1995. Machines which meet the requirements
are given a CE mark. The letters CE stand for the French "Conforrnit
Europenne", rneaning "European Conformity". Machines that satisfy the Directive
are provided with a CE sticker.
x.
lifting clamps
The following information must be shown on lifting clamps:
o Safe Working Load
o serial number
date of last test
e mass, if required
e minimal clamping force.
For lifting equipment the appropriate declaration is HA. This displays the Same
serial number as that applied to the equipment. Declarations of conformity must
always be available for inspection during the work.
The certificate must show the applicable type of EC declaration, which as we have
seen is the HA declaration in the case of lifting equipment. A product description
and the Safe Werking Load wil1 also be stated. These certificates are often
combined with test certificates. These certificates must also be available during the
work. As wel1 as the EC declaration of conformity, manufacturers must also provide
information on operation and maintenance and about situations where it would be
better not to use the product.
Suppliers are required to provide guidance for users in the language of the country
of use. It is permissible to combine the guidance for users of a range of types of
lifting equipment into a catalogue.
B Storage
The useful life of lifting equipment is shortened when it is subject to contamination
and moisture. You must therefore provide a dry and well-ventilated storage space,
without aggressive vapours and fluids. It is a good idea to hang the equipment up
in a systematic manner. You could separate:
e chain assemblies
e wire ropes
lifting strops and fibre ropes
lifting blocks and cable sheaves
special equipment.
rope grease
Good quality rope grease is of mineral
origin and is acid and alkali free. It leaves
behind a firmly adhering lubricant film.
This film wil1 not crack or blister and also
does not form a crust round the rope.
The lubricant should not be sticky where
ropes may come in contact with soil and
sand. Apply a thin but complete coating
to the steel wires. This is better than
smearing the rope with a thick paste that
will only drip or fly off later. That only makes the area around the rope greasy and
dangerously slippery.
Another problem is that cable sheaves may become full of grease When this
hardens as it ages the cable may no longer fit the sheave correctly and it may even
fall out. So clean sheaves regularly, even with moderate greasing of ropes.
User maintenance begins from the moment that the rope is first reeved Lubricate
the rope with a good quality grease when reeving, and repeat periodically
thereafter. The tarry types of grease used on open gear wheels are not suitable.
These greases run off the rope too quickly in summer and provide insufficient
protection in winter.
From time to time you should remove the old layer of grease, along with the
contaminants it has picked up. The period between cleanings wil1 depend on the
circumstances of use. The condition of the core should be checked at the periodic
inspection. Flushing oil and waste oil must never be used to clean wire ropes.
Flushing oil contains chemica1 agents that may damage the rope. Apart from
chemicals, used oil also contains metallic particles which get between the strands,
causing damage.
oil bath
Wire ropes exposed to the weather should first be immersed in an oil bath to
prevent the core drying out. Rope grease is usually applied with a brush, by
spraying or by immersion, and automatic lubrication equipment is also available.
D Inspection
The following points wil1 be dealt with in this section:
e periodic inspection
colour coding
e rejection criteria.
periodic inspection
As wel1 as cleaning and lubrication we also monitor the condition of the lifting
equipment by means of periodic inspections. This is important both for safety and
for control of costs.
The Safe Werking Load of an item of lifting equipment wil1 decline through fatigue,
wear, corrosion and damage. Regular inspections wil1 reveal the condition of the
equipment at a single moment in time and ensure that its safety has not fallen
below an acceptable minimum. The interval between inspections depends on the
conditions of use. In any event the interval must be short enough to prevent any
risk of danger through excessive wear, fatigue or aging.
In other words, before and during its use, the user must ensure that the lifting
equipment is in good condition.
colour coding
Lifting equipment offshore is marked with a colour code, established by the IMO,
the International Maritime Organization and adopted by most other bodies.
The colour code is marked on the equipment with paint and is as follows:
You can carry out a close inspection while you are cleaning and lubricating
equipment. If you detect one or more of the defects mentioned above, report this
immediately. The equipment may not be used further.
In an organisation approved by 1-SZW, the defect wil1 then be further investigated
by a competent person who wil1 decide whether the equipment can be repaired or
whether it has to be rejected. Only the manufacturer or a recognised body may
carry out such repairs.
Visual inspections only reveal external defects. Internal defects can only be
identified by an expert. The competent person not only has the necessary
knowledge but wil1 also have available special equipment like X-ray and ultrasound
apparatus. The competent person carries out his inspections at regular intervals,
which may not exceed two years.
Jumbo uses the colour code as shown below to identify the SWL and lengths of
lifting grommets.
The SWL and working length of grommets and slings are indicated by painted color
codes on the wires as given below. The color codes for the SWL of shackles is the
Same as for the grommets 1 slings.
* = not standard
-
IDENTIFICATION NR. ( EQUIPMENT NR. CERTIFICATE NR.)
W L = Working Length
.-f- -
eter
Usually you the crane driver are the first to identify a defect. You must report this to
the technica1 department in your firm. Take detective equipment out of service
immediately and send it to the responsible person. Below we give rejection criteria
for:
chain and chain assemblies
steel wire ropes.
k Summary
This chapter has dealt with the Machinery Directive. You now know what
requirements lifting equipment is required to meet, and what to look for when
inspecting it. You know how to rnaintain lifting equiprnent and how to store it. You
also know that a colour code exists and that you can expect to see two colours
marked on the equipment. Finally you know the criteria leading to the rejection of
lifting equipment.
6.3 What is the most important information for the crane operator on the
(coloured) label on a lifting strap?
B The CE marking.
A At least a HA certificate.
D Definitions
Chains and chain assemblies are defined as follows.
Chains and chain assemblies are arrangements of interconnected, closed,
identical links. The links are made of round steel.
A chain assembly is an item of lifting tackle made up of separate components in
chain connected mechanically.
chain assemblies
Chain assemblies are permanently connected chains, rings and hooks. All parts
are made in the Same material. We wil1 now discuss mechanically connected chain
assemblies, chain slings and the Working Load Limit. (= WLL = Safe Working Load
= SWL)
Chain assemblies are now mechanically connected where formerly welding was
the norm. This has two advantages:
e they can be assemblee! by the suppliers themselves.
a they are easily modified and repaired.
The shackle connectors can be seen at top left, and the hooks of the left hand
three-leg sling have a shackle connection. Mechanically connected chain
assemblies are made of high quality steel, usually of class T. All components are
made in the same material so that strength and resistance to wear is the Same
throughout. The legs of mechanically connected chain assemblies are usually
identical in length, but different lengths do occur. Single, double, three and four-leg
slings are found. The included angle between the legs of a sling may be no greater
than 120'. Provided account is taken of the applicable Working Load Limit, this wil1
prevent the lifting
tackle being What factor do we use for each chain assembly
overloaded. with a top i gle of 90-12O0?
Chain slings may be run around a load. They can be less damaging than wire rope
or fabric slings. The following illustration shows various chain sling configurations.
0 @
Various mechanically connected chain sling assemblies.
Single leg slings usually have a master link at the top and a flat hook at the bottom.
They are used if the crane hook is too large to take the lifting equipment attached
to the load. They form a connection between the crane hook and the lifting
equipment at the load.
Chain slings are often usedbetween the crane hook and lifting equipment attached to the load
Loads with several points of attachment can be lifted using multi-leg chain slings,
which are called two-leg, three-leg and four-leg slings as appropriate. The top link,
master link or crane hook link is usually oval to provide more room for the crane
hook. The illustration below shows a selection of the very wide range of multi-leg
chain slings available.
@ @ c3
A load with several attachment points rnay be lified using a two, three or four leg chain sling
If you lift a load with a single leg sling, you may load the sling up to the SWL as it
appears on the identification plate. However if you are using a two, three or four-
leg sling, you may not simply multiply the SWL by two, three or four. This is
because the legs of the multi-leg sling wil1 be at an angle to the vertical. The mass
of the load creates a loading on the sling, and this loading is greater when Ihe sling
is at an angle than when it hangs vertically. The force acting on the sling increases
as the angle with the vertical increases. With an included angle between the legs
of 120, the force is equal to the working load.
Angles above 12O0are therefore prohibited to prevent overloading of the lifting
equipment. Since there are different types of lifting equipment and you can attach a
load in different ways, Working Load Limits have been introduced and
standardised. The Working Load Limit varies according to the type of lifting
equipment and its manner of use, and also according to the sling leg angle.
The Working Load Limit depends on the ding leg angle and the manner of attachrn~nl
In order to find the maximum load that may be lifted with a particular item of lifting
equipment, the WLL must be multiplied by the utilisation factor. The WLL and the
utilisation factor are stated on the equipment identification plate
B Material
Chains and chain assemblies are made from steel, and that steel is an alloy. The
proporties of steel can be improved by the addition of certain substances. This
addition is called alloying. The most important alloys used in steel for chains and
chain assemblies are nickel chrome and molybdenum. The addition of these
materials makes steel:
stronger
tougher
more resistant to wear
more resistant to corrosion
o resistant to aging.
The addition of chrome and nickel makes steel corrosion resistant Corrosion in
this context means rust. Steel which wil1 not rust because of the addition of chrome
and nickel is called stainless steel.
p.--.- - . ..-....-
The upper chain is a long-link chain, the lower one is a short-link chain.
A specialised form of short-link chain is the calibrated chain. Here the links are cast
precisely to size in a mould. We wil1 also be discussing tempered and fully killed
steel in this section.
D Quality classifications
Steel exists in so many different forms that chains and chain assemblies are
divided int0 classes. The standards distinguish between 6 quality classes. The
classification rnainly indicates the strength of the steel. The table below shows the
classification. Breaking strength is the lowest tension at which the material wil1
break (the minima1theoretica1 breaking force). The symbol for breaking force is o,
the Greek letter sigma. The unit of breaking force is ~ l m m ' .
Chain and chain assernblies of classes S, T and V are made in alloy steel.
Strength class T is usually used for chain and chain assernblies used in lifting. The
expressions high-grade alloy steel or sirnply alloy steel are often used for chains
and chain assemblies in steel of strength class T.
B Working coefficient
The relationship between the breaking force and the Safe Working Load is known
as the working coefficient. We have dealt with this already in Chapter 5. Chain and
chain assemblies have a working coefficient factor of 4.
B Lifting chains
Chains formed of links are used for lifting work. The internal length of a link is
known as the pitch. The length of a chain is the pitch multiplied by the number of
links.
Chains corne in various formats and may have long or short links. The difference is
in the length of the link. Only short-link chains are used for lifting. The linksof such
chains are short and strong. Lifting chains have the following dimensions in relation
to material diameter (d).
link width
Long-link chains are lighter and cheaper than short-link chains. They are often
found in rigging and tensioning applications. Long-link chains must never be used
for lifting operations.
D Lifting hooks
We wil1 deal with lifting hooks along with chains, although they are also used with
wire ropes and also blocks and sheaves. Hooks can be divided into three groups:
e sling hooks
e special purpose hooks
e crane hooks.
sling hooks
Sling hooks are used to attach to lifting eyes and connections. Various patterns
exist. Common types include:
e flat hooks or eyehooks
latched safety hooks
e safety hooks.
Flat hooks are also known as eyehooks, and are often used with chain and wire
rope assemblies. The dimensions are such that removable connecting links wil1
pass wel! over the throat. Hooks must always be provided with a safety latch to
prevent the load unintentionally corning loose.
These safety hooks are fitted with a latch which is forced against the hook tip when
the hook is loaded. A ratchet then ensures that the latch remains locked. Latched
safety hooks are used when there is a chance of the hook fouling on projections.
Safety hooks have a hook and a gate which hinge together. There is a recess in
the end of the gate which fits over the hook tip. When the hook is loaded, the gate
is pressed against the hook, just as with the latched safety hook. However these
safety hooks are sometimes less safe than latched safety hooks.
D grab hooks
Grab hooks have a jaw which precisely fits the links of a chain. They are made for
chain sizes from 6 to around 18mm. They are used to temporarily shorten chains.
You may for example shorten one leg of a two-leg chain to allow a load to hang
straight.
A shortening clutch is also used to shorten chains. Shortening clutches are found
in use with chain slings.
-
A shorening clutch is handy when shorening chains.
D swivel hook
Normal hooks cannot rotate in chains and ropes. If a load begins to rotate, the
chain or rope wil1 turn with it. In these circumstances a swivel hook can be used.
This has a pivot which turns in a drilling in the base of the eye. It is kept in place by
a nut, and the nut is prevented from coming loose by a weid or a retaining pin.
A variety of hooks are available for lifting drums. The drum hooks shown below are
used for lifting a drum in a horizontal position. The hooks are placed opposite one
another and engage beneath the rims of the drum. The paired drum hooks are
joined with an endless chain and a ring. When the load is taken up the hooks are
pulled tight against the drum.
These hooks are not suitable to lift upright drums or thin walled drums. They
should not be used with drums containing hazardous substances. There is always
the chance that the hooks may slip along the drum rims, which is an unacceptable
risk in the case of hazardous substances.
D drum clamps
Other forms of drum-lifting equipment are far safer. The following illustration shows
a simple type of drum damp with a clamping mechanism. This type is suitable for
drums with a mass up to 1000 kg per set. The damp opens when the button is
pressed.
D single hooks
v.,,
./""
A single hook with block and sheave.
The hook may have a self-closing safety latch. A single hook is ofen used as a
component of a crane block.
D double hook
A double hook is often called a ramshorn hook. This type is used in very heavy
work where the load is held by several slings. Just like the single hook, the double
hook is often used as a component of a crane block.
Y
A double hook can make the use of multiple slings easier.
shackles
Shackles are used to attach a chain or rope to an object. The shackle is closed
with a bolt, enclosing the chain or rope. There are two types:
D-shackles
H-shackles
Shackles are available in other patterns and may be made in a variety of materials.
2 D
screwed into a threaded hole with the Same thread and eye nuts are threaded onto a stud.
F) checking
Eyebolts and nuts have a tough life and need regular inspection. Look at the
condition of the thread and check for wear. Eyebolts and nuts in poor condition
must be replaced.
Eyebolts and eye nuts are unsuitable for lateral forces. Try to load them axially as
much as possible and avoid sideways loading. The maximum permissible angle
with the vertical (1) is 45'.
y
Eyebolts and eye nuts may only be loaded to a maximum of 45' in a lateral direction.
D load rings
Load rings look quite similar to eyebolts and eye nuts. The difference is that the
load ring eye hinges so that it can be swung out of the way, preventing obstruction.
Load rings hinge and sorne can be swung out of the way, preventing obstruction.
lSummary
You have learned how chains are manufactured and from what materials. You
know that short-link chains are used for lifting work and that calibrated chains are
used as hoisting chain in a chain hoist. Chains and chain assemblies are strong
and resistant to wear. If made from unalloyed steel they wil1 need regular heat
treatment and may be brittle in cold conditions. Unalloyed steel lifting chain is no
longer produced. You have also learned about the different types of chain
assemblies, what the utilisation factor is and how to use it.
You know how and when D and H shackles are used, that locked bolts and nuts
are safer, and that eyebolts may be side-loaded only up to a certain angle.
B 1 x the SWL
7.5 What is meant by the working coefficient of quality class T chain work?
B It means that the WLL of the chain is Vs, of the breaking load.
A 45 degrees.
B 60 degrees.
C 75 degrees.
D 120 degrees.
7.7 A two-leg chain sling has an included angle < 90 degrees. The SWL
of a single leg is 10 tonnes. What can be lifted in this situation?
A 7,14 tonnes.
B 14 tonnes.
C 14,3 tonnes.
D 10 tonnes.
7.8 A three-leg chain assembly has an included angle < 90 degrees. The SWL of a
single leg is 12 Tonnes. What can be lifted in this situation?
working b a d limit table tor chains assemblies
A 25.2 tonnes.
B 12 tonnes.
C 16,8 tonnes.
D 18 tonnes.
120 of 197 @SBW & Jumbo A Jumbo Crane Operator Syllabus
Steel wire ropes and steel
wire rope assemblies
D Introduction
Lifting is often carried out with the use of chains, but steel wire ropes are also very
useful for this. Chains and ropes each have their advantages and disadvantages,
and their own fields of application. This chapter is concerned with the different
constructions of steel wire rope. We wil1 confine the discussion to the steel wire
ropes and terminations that are used for lifting slings.
lMaterials
Wire ropes have to meet many requirements, and so they are made from high
quality steel. The steel contains little phosphorus, sulphur or other contaminants
and has a regular structure. The alloy manganese is used to increase resistance to
wear. Wire ropes are made up of steel wires drawn through a drawing plate.
They are then put in bundles and twisted together. The large number of wires
makes wire ropes flexible enough to bend easily and to pass over wheels.
We wil1 discuss the requirements steel wire ropes must fulfil, and how steel wire
rope is to be protected against corrosion.
' requirements
Wire ropes for slings must resist:
high temperatures
acids
a high pressures
corrosion
e rough treatment.
Steel wire ropes have been developed which meet specific requirements in a wide
range of applications.
Wire ropes made frorn galvanised steel wire have a thin coating of zinc.
After drawing, the wires are passed through a zinc bath and the coating of zinc that
is left behind on the surface ensures that no corrosion can occur. The zinc coating
is applied in a hot bath so the process is sometimes called hot dip galvanisation.
The heat of the bath reduces the strength of the steel. Since the zinc coating is
slightly porous and can be damaged, it is wise to lubricate galvanised wire ropes
wel1 with grease.
D Working coefficient
The working coefficient applied to steel wire ropes is the relationship between the
actual breaking load and the Safe Working Load of the equipment. Steel wire
ropes for lifting slings with a SWL up to 25 tonnes have a working coefficient of 5.
With a higher SWL a working coefficient of decreases to 3,33 depending on the
SWL..
The steel wires in the strands surrounding the core can slide easily along the rope
core without wear or damage. The disadvantage is that fibre rope itself is
vulnerable to damage, and ages and even decomposes in rapidly changing
temperatures. The core becomes thinner and its supporting function is lost.
The consequence is rapid wear, or one of the strands may be pushed inwards.
When a rope in this condition is loaded it makes a corkscrewing motion and the
strands are loaded unevenly. The life expectancy such a rope is short.
It was long believed that a fibre rope core would provide internal lubrication, but it
has emerged that this is only the case with new ropes. Compression gradually
forces the grease out of the rope core, and it can then take up water. Water rots
the fibre core and rusts the steel wires.
It has also often been said that a wire rope with a fibre core is more flexible than a
steel cored rope. That is not completely true either. Wire ropes with fibres cores
are initially more flexible, but that flexibility declines rapidly in use.
D core rope
A core rope is really a rope within a rope. The core generally consists of six
strands of seven wires with a core strand of the Same construction at the centre.
Wire ropes generally have six strands of seven wires with a seventh strand at the core.
Eight-strand wire ropes are found in various patterns. The core rope usually
consists of six strands. The centre of the core rope may then be a strand like those
in the other core rope strands. In another pattern, the centre of the core rope is
also a rope, with six strands and another at its centre. The illustration below shows
both types of core in eight-strand rope.
There are also steel wire ropes with a core strand. The core strand is exactly like
the strands in the rope itself. This type is very rarely used for steel wire rope slings
as it makes the rope too stiff.
tensile strength
Steel wire ropes are available in three tensile strengths, 1570, 1770 and 1960
m mm' The 1770 ~ / m m ~ c l a sissmost common. Wire ropes with strength
classification1960 m mm' are used for special purposes. Nowadays even tensile
strengths of 2160 m mm' are available and used by Jumbo in several heavy lift
mast cranes (400 ts and 800 ts mast cranes)
lStrand constructions
The strands of steel wire ropes can be built up in several ways.
0 0
Build-up of strands in the normal construction.
@
To spread the load evenly across all wires, the wires in each layer have the Same
angle of lay.
The following illustration shows what is rneant by an angle of lay
l
Angle of lay, and other dimensions of a rope made by the normal construction.
1, 3, 5, 7 intersection
2 angle of lay
4, 6 pitch
8 angle of lay is the sarne in each layer
9 point contact
0 @
Normally constructed wire ropes are much used for wire rope slings,
parallel construction
The parallel construction is far more cornrnon. This construction is so called
because all wires run parallel to one another in all layers. This creates line contact
rather than the point contact which can be hazardous. This construction is
achieved by using wires of differing diameters. The pitch of all wires is the sarne
and each layer has its own angle of lay. Line contact spreads the forces over a
greater surface, reducing wear.
1 intersection
2 point contact
In the Seale construction the layers of the strand have the Same nurnber of wires.
Wires in the Same layer also have the Same diameter. The wires in the outer layer
are thicker than those in the inner layer. The number in the specification indicates
the number of wires. So a 19 Seale consists of a thick core wire, a layer of nine
thin wires and a layer of nine thick wires. The thick wires of the outer layer reduce
damage and wear.
u
In the Seale construction the layers of the strand have the sarne nurnber of wires
D Warrington construction
In the Warrington construction the core wire and the wire in the first layer have the
Same diameter. The outer layer is known as the Warrington layer and has twice as
many wires as the layer beneath. The Warrington layer consists half of thick and
half of thin wires. The thick wires lie in the grooves between the wires in the layer
below.
w
The Warrington construction has differing nurnbers of wires in each layer
A 19 Warrington rope has a single core wire, with a layer of six wires of the Same
diameter as the core, followed by a final layer of twelve wires. This outer layer
consists of six thick and six thin wires.
Just as in the Seale construction, the strands in the Warrington construction are
resistant to wear and damage. The Warrington construction is more supple
because of the high number of outer wires.
u w
Construction of a 36 WarringtonISeale rope
In the WarringtonISeale construction he inner wires are thicker than the outer wires
and that makes such ropes better resistant to internal fatigue. These are the most
suitable ropes for lifting slings.
D Lays
In describing wire ropes a distinction is made between the type of lay, direction of
lay and pitch (or length of lay). We wil1 discuss these concepts individually below.
We wil1 then look at preformed ropes and a rotation-free construction.
type of lay
The strands of wire ropes can be twisted into a rope in the following ways:
e regular lay
e Lang's lay.
D regular lay
Wire ropes with a regular lay are most common. In the regular lay the direction of
lay of the individual wires is the opposite of that of the strands in the rope. Regular
lay ropes are less inclined to unwind. Only regular lay ropes are used for lifting
slings.
In the regular lay, the direction of lay of the wires is opposed to that of the strands.
The Lang's lay is named after its inventor, the Englishman Lang. In the Lang's lay
the wires and the strands are laid in the same direction.
In the Lang's lay, the direction of lay of the individual wires is the Same as that of the strands
Wire ropes made using Lang's lay are more supple and less sensitive to wear than
regular lay ropes. Their disadvantage is the tendency to unwind. This can be seen
when a free load is taken up and begins to spin. Lang's lay wire ropes are
therefore only suitable for guided loads, for example counterweights, lifts and
rammers. They are not used in lifting slings.
irection of lay
Direction of lay refers to the manner in which the strands are twisted together. The
strands turn to the left in a left-hand lay and to the right in a right-hand lay. The
right-hand lay is most common.
D Pitc
The pitch or length of lay of a rope is the length required for a strand to make a
complete turn around the rope. We are concerned here with the linear length,
measured in a straight line along the rope. The illustration shows a rope with six
strands and indicates the pitch.
pre-forming
Without special treatment, wires and strands have a tendency to resume their
original shape. This characteristic causes internal or twisting tension, but these
tensions can be removed if the rope is pre-formed. In this process the strands are
given the spiral form which they wil1 later have to adopt in the rope.
This makes them easier to handle. The disadvantage is that broken wires are not
seen, because they stay neatly in place instead of springing out as a non-pre-
formed wire would.
non-rotating constructions
Non-rotating wire ropes consist of two or more layers of strands around a fibre or
steel core. The inner layer or layers are laid opposite to the outer layer. When such
wire ropes are loaded, the outer layer tends to open (lengthen) and the inner layers
tend to close (shorten). Under load, a certain balance is achieved between the
inner and outer layer. At the moment equilibrium is reached the internal rotation of
the rope ceases. A non-rotating construction has a higher working coefficient
factor.
terminations
Steel wire rope assemblies, like chain assemblies, are made to length and
supplied with the necessary accessories. To attach loads to wire rope assemblies
they must be fitted with hooks, eyes, thimbles and the like. This is achieved with
the use of terminations.
Two groups of these are distinguished:
e permanent
e temporary.
D talurit
A Talurit connection provides an eye without splicing. A light metal tube is pressed
onto the rope after the eye has been formed.
Prior to pressing the clamping tube is oval. It fits tightly over the cable and the free
end. The end of the cable is cut off with an electric cutting machine. The wires fuse
together during the cut and the rope cannot therefore unwind. The rope is passed
through the damp, the eye is formed and the free end is passed back through the
clamp. The free end should protrude slightly from the damp to ensure that it is
clamped over its full length. The hard, burned-off part is also better placed outside
the damp as this part of the rope is less easily compressed. A thimble is often
used to prevent the bend in the eye becoming excessive.
The thimble also protects the rope from damage. The clamp is then firmly pressed
onto the rope. After pressing the shape of the clamp is almost cylindrical. The
cable and the cable end are pressed together and the clamp fits tightly around
them.
A disadvantage of the Talurit connection is that the force of the clamped part is not
along the centreline of the rope but a little to one side. This reduces the strength of
the connection. A Talurit connection reduces the breaking load of the cable by
10%.
Talurit connections may only be loaded in line with the axis of the rope.
They are not suitable for bending forces as there is a high risk of them coming
open. So be careful with slings in particular that the terminations are not bent
around round sections and corners. Talurit connections are not resistant to rough
handling.
D SuperSplice
D poured socket
The poured socket provides a safe terminal connection. There are closed and
open sockets, all made of forged steel. All poured sockets have a tapered hollow
section int0 which cold-curing resin is poured.
The securing of the cable end is specialist work and rnay only be done in specially
equipped workshops. Synthetic resin is also currently used for this purpose. It
gives a safe connection, resistant to seawater and a variety of chemicals.
Polyester resin is not resistant to acetone and may not be exposed to
temperatures above 115'C.
If all conditions are satisfied and the rope is attached in the correct manner, then
this connection may be subjected to the Same loading as the rope itself
D swaged socket
Swaged sockets are found in use with mooring ropes and also in extending ropes.
The clamping element forms a unit with the eye or shackle, Swaged sockets are
used up to a rope diameter of 65mm.
The most important temporary termination is the wedge socket. Wedge sockets
are used when the rope length requires frequent adjustment, or to connect the
hoisting rope to a lifting block. The wedge socket should be fitted so that the rope
carrying the load is in direct alignment with the eye of the socket clevis pin. A
wedge socket must be given additional security by means of a U-bolt damp,
positioned on the dead part of the rope as shown below.
@
Some examples of wire rope slings.
The sling with two eyes is most common. Sliding hooks do little damage to the
rope. The terminations are often Talurit clarnps, SuperSplice clamps or sometimes
spliced. The endless steel wire rope sling is of spliced construction.
D grommets
A special version of the endless steel wire rope sling is the grommet. Grommets
are made of six or eight strand rope. They have six strands laid up six times over
the core. The core is also a rope and is identical to the other strands.
This construction is called wire rope lay. Grommets are very flexible and are rnuch
used offshore and in the dredging industry.
You can teil from the shape of the gromrnet whether it is under load. Be sure to use
grommets correctly. Check that both strand ends are correctly tucked away.
The area where the ends are is marked with red. No hooks or eyes should be
attached in this region, as that would force the ends outwards, leading to snagging
projections and internal birds-nests. You must
also ensure that the seizing has been carried
out correctly.
~ x m ~ l of
e srope slings
The Working Load Limit is dependent upon the manner of attachment and the included angle
lSummary
Steel wire ropes are made of thin steel wires and are constructed in a variety of
ways. We have learned to recognise the normal and the parallel constructions The
most comrnon construction for lifting slings is the WarringtonISeale. Steel wire ropc
assernblies include single and multi-leg slings. Patterns are similar to those of
chain assernblies. Terminations are needed in constructing steel wire rope
assemblies. Only permanent terminal connections are suitable for use in lifting
work. The most cornmon type of sling has two eyes.
Multi-leg slings are attached to a common eye or link. Finally, the working
coefficient can be adapted to any situation with the use of the table.
8.2 There are three marked areas on a grommet. One red area and two green
areas. What does this rnean?
A The red area is the SWL color. The green areas are the lifting
points.
B The red area is the place of the splice (tuck area). The green
areas correspond with years.
C The red area is the place of the splice (tuck area). The green
areas are the lifting points.
D The red area is the year code. The green areas point to the SWL.
8.3 What is the maximum size of the included (top) angle between diagonally
opposite ropes in a four-leg wire rope sling?
A 60'.
B 90'.
C 120.
D 150'.
8.4 What is the working coefficient for steel wire rope lifting slings with a SWL of
25 ton?
A 4.
B 5.
C 7.
D 9.
* w c t'. C
8.6 The wire rooes shown below have two different lavs. State the lavused in
rope A (leftj and rope B (right).
A A Superloop.
B A splice.
C A Talurit connection.
D A SuperSplice.
lIntroduction
Fabric slings were originally used only for loads without sharp edges, but they are
increasingly being used in stead of chain and wire rope slings, since these can
often cause damage. Fibre rope slings may no longer be used, and in their place
have come fabric slings in man-made fibres. Fibre ropes are no longer used in
lifting, but they are used to guide loads. This chapter wil1 discuss the different
materials from which rope is made and their properties.
lFabric slings
Chain and wire rope slings are heavy and can damage loads, and so fabric slings
from man-made fibres are becoming increasingly common. Fabric slings are light
but still strong. They may be made from polyamide (PA), polyester (PES) or
polypropane (PP). Polyester is most common.
Fabric slings are strong but you can't always teil if they have been weakened in
use. A working coefficient factor of 7 is therefore applied.
properties
Fabric slings are light, strong, inexpensive, they don't rust, don't damage the load
and require virtually no maintenance. A three-metre long sling with a SWL of 5
tonnes weighs only around 1 kg. Fabric slings therefore save a great deal of mass.
Fabric slings do have certain disadvantages. They are less resistant to high
temperatures and aggressive chemicals, although this can be solved to some
extent with the use of a protective sleeve. The sleeve material can be matched to
the chemicals which the sling might come int0 contact with. Some sleeves protect
against temperatures up to 250C.
Plastics are sensitive to the UV rays produced by the sun. The consequence is that
mechanical properties such as strength, elasticity and flexibility may be
significantly reduced. Plastics used for fabric slings therefore have a chemica1
additive which reduces sensitivity to UV rays. This is referred to as UV
stabilisation.
The mechanical properties of the sling are preserved longer through the addition of
a UV stabiliser to the base material.
lManufacture
Fabric slings are produced in two different ways. The man-made fibres may be
woven int0 a flat sling or gathered int0 a round sling. In round slings the fibres lie
side by side and are kept in place by a seamless woven sleeve. Round slings are
always endless.
A distinction is made in the manufacture of lifting slings between:
o woven slings
round slings.
woven siings
Many fabric slings are woven. Weaving the man-made fibres provides strength.
Woven lifting slings are called flat slings. There are two types, single and double,
and we wil1 discuss each of these now.
A single flat fabric sling consists of a single woven layer. These slings are available
in widths of 30mrn upwards. The rnethod of weaving prevents lateral tearing.
This single pattern has two ends with eyes or connectors. Flat endless slings are
als0 found.
The eyes are often reinforced with leather and have a prescribed internal
dimension. The seams at the eyes are stitched with threads of the Same rnan-
made fibre material as the sling. The ends of the sling are trimmed and fused
together. This prevents the ends unravelling.
The terminal eyes may be flat or twisted. Twisted eyes are covered on both sides
and either side can therefore be used, increasing durability. The eyes may be
doubled over, folded in half or to 113 of the breadth, with the advantage that the
eye now presents a greater bearing surface to the crane hook.
round slings
In round slings the man-made fibres are formed int0 endless strands. A round sling
consists of numerous parallel endless strands side by side within a woven
protective sleeve. The sleeve protects the strands and keeps them together. lt has
no effect on the strength of the sling.
The sleeve must be a little longer than the sling itself since the fibres extend a little
under Ioad and an excessive force would otherwise be placed upon a short sleeve.
The stitching would give way and the fibres would be exposed. A sling in that
condition must no longer be used.
A round lifting sling is always endless. To enable it to be attached more easily, the
protective sleeve is sometimes stitched through along its length. This produces
what is known as a Win sling. The ends are left open, creating two eyes at the
ends. These eyes are reinforced with leather or fabric. The Ioad bearing part of a
twin sling is often reinforced with a layer of polyester.
D sling assemblies
Round endless fabric lifting slings can als0 be used as components in sling
assemblies. A plastic sleeve is fitted to the sling, short enough to create eyes at the
ends. The eyes are used to attach connecting links. Master links or hooks may
then be attached. This assembly can then be used as a single leg sling or as part
of a 'wo-leg or four-leg sling. Sling assemblies are sometimes known as sling
combinations.
.
, Wo leg fabric sling, made UD of Wo round E!ndless
slings, cGnnecting liiks, hooki and a master link,
The metalwork in such assemblies must be made of steel which is not sensitive to
ageing. The links and hooks are generally made from refined alloy steel of strength
class T.
colour coding
Fabric lifting slings have a colour coding which indicates the SWL. These codes
are set down in a European standard. Some manufacturers have adopted their
own systems, which makes it unsafe to rely entirely on the colour code. lt is better
to check the details on the label. The following table shows the standardised colour
coding.
SWL coiour
in kg
500 olive
l 2000 l areen l
4000 1 grey
5000
- - - - 1 red
6000 brown
8000 blue
l O000 oranae
u
15000 1 oranae
ll 20000 1 orange
25000 l oranae l
1 30000 1 oranae 1
The colour of the sling indicates the SWL.
D Labels
Fabric slings have a label showing a variety of information.
The colour of the label indicate the material of the fabric sling.
The label of a polyamide (PA) sling is green, polyester (PES) is blue and
polypropeen (PP) is brown. But, read the label! Not every manufacturer of fabric
slings is using colour codes on his labels.
Similarly, it is als0 the case that the working coefficient for fabric slings and sling
combinations differs according to the type of Ming equipment and the manner of
attaching the Ioad. The size of the included angle als0 influences the working
coefficient. The following table shows a working coeficient table for fabric slings
and sling assemblies.
The working coefficient depends on the method of atiachment and the included angle
In order to determine the maxima1 Ioad which may be lifted with a particular piece
of lifting equipment, the SWL must be multiplied by the working coeficient factor.
The SWL and working coefficient are shown on the sling label. The practica1
application of working coefficients and included angles is covered in Chapter 5.
polyester
Polyester (PES) is strong and resists wear well.
Other advantages of polyester are:
e wet and dry strength are identical
8 good resistance to UV rays
8 moderate shrinkage
8 moderate stretching.
applications
F~brerope is more flexible than steel rope and stretches more. Fibre rope is no
longer used for lifting purposes. The rnain reason for that is the aging process,
which makes fibre rope less reliable. But fibre rope is still employed where
flexibility is important, for example:
o in warping lines, mooring and tow ropes in shipping applications
o in guying lines
in tag lines used in lifting operations.
D Summary
Fabric lifting slings are light, economical and prevent damage to the Ioad. They are
usually made from polyester (PES). A colour coding indicates the SWL, but not al1
manufacturers use the Same code. You must therefore always look at the
information on the label. Fabric slings may be flat woven, or round and filled with
bundles of loose strands. Two-leg, three-leg and four-leg slings can be made from
round endless fabric slings. Rope is sometimes made with the natural fibre manilla,
but is more usually in a man-made fibre. When used as a steadying line, that is
often polyester. Fibre ropes may no longer be used for lifting purposes.
A Only l is true.
B Only II IS true.
A 45 degrees.
B 60 degrees.
C 90 degrees.
D 120 degrees. this sling has a smal1 top angle what is the
right way
The working coefficient factor for man-made fibre lifting slings is:
A 3.
B 5.
C 7.
D 10.
9.5 The included angle of the legs of fabric lifting slings is:
A maximally 60 degrees.
C minimally 60 degrees.
D minimally120 degrees.
C Where the lifting tackle may come into contact with chemicals.
D At high temperatures.
D Lifting equipment
Special lifting equipment is taken to include the following:
o lifting beams
o lifting clamps
e special lifting hooks
werking platforms
e gas cylinder racks
e tensioning and guying equipment (not strictly lifting equipment).
b Lifting beams
A lifting beam allows a large number of items to be lifted at the Same time. Lifting
beams can therefore save a lot of time. There are various patterns, including for
example a beam for lifting upright drums. These are not used offshore. Lifting
beams are sometimes called spreaders or levellers.
B Lifting clamps
Special lifting clamps have been designed to lift certain objects. The construction is
such that the load itself assists with the clamping. Such equipment is used for
exarnple with:
o steel plate, either horizontally or vertically
O steel profiles, for example rails.
Clamps with vertical clamping surfaces must hold loads automatically and ensure
that they are not loosened by impact. Clamps intended to move several objects at
once must have a fall prevention device. You must always use the fall prevention
during lifting operations.
Beam clamps are used to hold steel profiles. Two hooks clamp the profile and an
eye is provided for lifting. The clamp is secured for safety with a threaded rod. The
advantage of beam clamps is that they are easily moved allowing speedy
balancing of loads. The Same clamp can often be used for different width profiles.
Beam clamps must not be used to raise a steel profile from a horizontal to a
vertical position.
D Work platforms
Work sometimes needs to be carried out in places that are very difficult to reach
without the use of work platforms. These are cage-like constructions in steel or
aluminium. The base is enclosed while the sides must be provided with guardrails
and toeboards. The toeboard must prevent persons falling beneath the guardrails.
Transporting persons on work platforms is hazardous and is therefore subject to
legislation.
Work platforms must comply with the Machinery Directive.. Since the use of work
platforms is so hazardous it must only be done in exceptional circumstances, for
example with short-term work in difficult locations.
Persons carried in work platforms must wear safety harness and be firmly attached
to the platform.
2. 1 Crane safety
2.1 1 Does the crane conform to the legal
1 requirements?
2.2 1 Has a periodic inspection been carried out
A gas cylinder rack provides the necessary protection for gas cylinders.
turnbuckles
The following equipment may be used to secure a load:
e rapid action turnbuckles with lever action
ratchet lever turnbuckles
e container chains.
Turnbuckles are used to secure all kinds of objects, for example to tie down
objects to be transported in an open container. Container chains are used to
secure containers to the deck.
D working coefficient
A working coefficient factor of 7 is usual with fabric lifting slings in man-made fibre,
but lashings are subject to less wear than lifting equipment so a lower working
coefficient, from 3 to 5 depending on the type, may be employed.
D strength
The strength is indicated on some lashings. Black threads are currently woven int0
the lashing along its length and the number of threads indicates the permissible
tension on the lashing. Each thread represents around 10,000 N of tensile force. If
fabric lashings have been used but show stretching, use lashing chains.
lSummary
Lifting beams are used to carry large loads or several items together. They are
also called spreaders or levellers. Lifting clamps close automatically and hold a
load firmly. All kinds of special hooks are available to lift variously shaped loads.
Work platforms are equipped to transport persons and to allow them to carry out
work. Moving persons on a work platform is hazardous and should only be done
where there is no alternative. The work platform must meet stringent requirements.
Gas cylinders must be carried in a special cage. Loads must be properly secured
to vehicles and vessels, other wise the load may shift. Equipment for this purpose
includes turnbuckles, lashings and lashing chains.
A Pivot.
B Gear segment.
C Bearing face
l Lifting beams can be used to help in lifting long and sagging loads.
A Only l is true.
B Only II is true.
II The checklist must be completed for every job and countersigned by the
crane driver.
A Only l is true.
B Only II is true.
10.4 10 m long flexible pipes are required to be lifted. What lifting equipment
would be most suitable?
A Lifting beam.
B 2-leg sling.
C Lifting clamp.
D Pallet hook.
deflection
The deflection factor affects the rope. The rope continually slides across a sheave
or drum, so that the strands of the rope also slide across one another. This creates
fatigue phenomena and internal wear.
surface pressure
The surface pressure factor affects both ropes and drums and sheaves. With high
surface pressures there is little contact surface between ropes and sheaves or
drums. This leads to external wear of the rope and the bearing surfaces of drums
and sheaves.
With low surface pressure there is greater contact surface between ropes and
sheaves or drums. This leads to less wear of the rope and the bearing surfaces of
drums and sheaves.
The surface pressure on the rope itself is also very important for the extent of
internal wear to the rope. Where there is a large contact surface between the
individual wires there is less internal wear. So a low surface pressure is
advantageous here too.
B Fleeting angle
Account must be taken of the take-off or fleeting angle in the run of rope between
the drum and sheaves. Fleeting is the angle the rope makes with the axis of the
drum or sheave. It changes as the rope is wound off and onto the drum. Where the
fleeting angle is excessive, the rope bears with great force on the flange of the
sheave. This causes increased wear to both sheave and rope. An excessive
fleeting angle creates gaps between the turns on a smooth drum, which may lead
in turn to trapping and damage to the rope when a second layer is put on the drum.
Where the fleeting angle is too small the rope may lie over the previous turn, with a
high probability of rope piling up. This is exceptionally harmful to both rope and
machine.
Maximum and minimum fleeting angles are therefore set down to prevent the
situations described above.
fleeting
angle t00
small
piling up
7
1
The fleeting angle must lie between half a degree (Vao) and one and a half degrees
(1%'). This accords with a distance (l) between sheave and drum axes of minimally
40 x a (a = half drum width) and maximally 115 x a. With grooved drums the
fleeting angle may be a maximum of 2', that is (l = 30 x a).
The rope sheave leads the rope at such an angle that the rope comes onto the drum at the correct
angle.
diameter
The diameter of the sheave is measured at the centre of the rope. The sheave
diameter depends on:
stiffness of the rope
size of the angle of contact between the rope and sheave
the number of times the rope is bent over drums and sheaves.
The sheave diameter (D) in mm is calculated by multiplying the rope diameter (d)
by the tension factor (h,) and reeving factor (hz):
JU
Factors determining the sheave diameter. D = sheave diameter, d = rope diameter
The underlying aim of this approach is to ensure the longest possible life for the
rope and sheave.
163 of 197 @SBW & Jumbo A Jumbo Crane Operator Syllabus
tension factor
The tension factor (hl) takes account of the angle of contact:
e size of the contact surface between the rope and sheave
e radius of the bend in the rope.
The value of the tension factor runs from 14 to 31.5. For the lifting equipment we
are concerned with the tension factor is usually 20.
reeving factor
The reeving factor (hz)takes account of the number of bends made b y the rope.
The reeving factor has a value of:
e 0.89 up to 3 bends
e 1.O0 up to 5 bends
1. l 2 for 6 bends and above.
For machines in our target group the reeving factor used is 1.O0 In summary, we
may assume the following multiplication factor for our purposes
D=20xd
groove profile
As wel1 as the diameter, the form and dimensions of the sheave groove can also
influence the durability of a rope. If a rope is bent the strands and wires of the rope
slide across one another. An excessively narrow groove does nol allow this
movement. This leads to rapid rope wear. Another consequence of a narrow
groove is the breakage of the sheave flange. The sharp broken edge may severely
damage the rope or even cut it off. In an excessively spacious groove the rope wil1
have an extremely small contact surface with the sheave. This leads to a high
surface pressure between rope and sheave, deforming the rope and negatively
affecting durability.
The flange height or groove depth (a) of the rope groove is at least 1% x rope
diameter. This is necessary to prevent the rope falling out of the sheave.
Nevertheless you must still take steps to prevent the rope leaving the groove.
Rope and groove also wear in use. The rope becomes thinner from wear and
stretching. The groove wears down in line with this smaller diameter so the groove
itself becomes smaller.
With wear, the rope becomes thinner and the groove becomes narrower.
If a new rope is placed in a worn groove it wil1 jam as the groove is too narrow. The
durability of the rope is reduced.
D Rope drums
A rope drum is used to pay out and to take in rope. Drums are available in cast and
welded constructions. Cast drums rnay be in iron or steel, welded drums are made
of steel. Rope drums rnay have a smooth or grooved surface. Currently, grooved
drums are most common. A grooved drum supports the rope better and winds the
rope on better.
The following rule applies to offshore cranes: the attachment of the hoisting rope to
the hoisting drum of a deck crane rnay not exceed 10% of the rope's breaking
strain. We wil1 discuss the following aspects of rope drums:
diameter
groove profile
winding onto drums
* rope attachment.
diameter
The loading on a rope on a grooved drum is more favourable to it than when it runs
over a sheave, so a lower rope factor rnay be adopted. The diameter of the drum
rnay therefore be rather smaller than that of a sheave.
The capacity of the drum is also significant in selecting the drum diameter. The
capacity is the length of rope to be held on the drum. Capacity is determined by the
diameter and length of the drum. We need to take account of the maximum
permissible fleeting angle when selecting the length. The diameter of the drum
rnay therefore come out rather larger to obtain sufficient capacity. Smooth drums
have a rather larger diameter than grooved drums. This is due to the less
favourable fleeting and lie of the rope on an smooth drum.
l11
Minimal dimensions of drum grooves.
The height of the drum flange must be at least twice the rope diameter. measured
from the centre of the rope. On drums with several layers of rope we measure from
the centre of the topmost layer.
Underhand winding. The first drum has a right lead, the second has a lefl lead.
Overhand winding. The first drum has a lef lead, the second has a right lead
Drums with more than a single layer of rope often have a raised section to allow a
smooth transition from the first to the second layer of rope. The run of rope
between the drum and sheave is also very important. If the rope leaves from the
top of the drum it must also be lead int0 the top of the sheave (overhand). If the
rope leaves from the bottom of the drum it must also be lead into the bottom of the
sheave (underhand).
I11 IV
Situations l and III are incorrect, the rope must run along either the bottom or the top
This photo shows the end attachment of the hoisting rope to the drum.
The hoisting rope must be capable of being freed from the drum in an ernergency.
The rope is therefore secured with a chain, so that it can easily be pulled free, for
exarnple by a provisioning vessel.
The components of a crane block are made in high grade alloy steel. The hook is
attached to the traverse and can usually be rotated. For heavy loads attached with
several slings, a double or ramshorn crane hook is often used. It provides more
space for the slings. The rope sheaves are made of grey or nodular cast iron, or
plastic. They are provided with sleeve or roller bearings. Grey and nodular cast
iron are resistant to pressure and wear. Plastic is inexpensive and hence easily
replaced. Most blocks use sleeve bearings, but bal1 or roller bearings are used with
heavier blocks or to provide a faster hoisting speed. The number of sheaves, and
therefore the number of parts from which the load is suspended, depends on the
capacity of the crane and the capacity of the drum.
Most cranes have the possibility to reeve the hoisting rope for several times
between the jib and the crane block. The SWL depends on the nurnber of falls of
rope used. More detailed information wil1 be discussed in the next paragraph. The
hoisting speed is decreased by the number of falls of rope used. The hoisting rope
has to be symmetrically divided on the sheaves of the jib and the crane block
according to the operating manual. In the following illustration a jib wil1 be shown
with two topguide sheaves, four guide sheaves under the jib and a crane block with
three sheaves and a becket. When you position the hoisting rope on one side on
the sheaves there wil1 be a rotational force on the jib. Reeving in the wrong way
causes the crane block to rotate under the jib.
In order to calculate the reeving you wil1 need the following information:
the weight of the hoist
e the maximum allowable pull in the hoisting rope.
The photograph shows why you need an operating handbook before you start
reeving.
D Summary
This chapter has dealt with rope sheaves, rope drums, crane blocks and serving
sleeves.
We first considered two factors which influence the durability of steel ropes and
machine components: deflection and surface pressure. We then considered
fleeting angle, the angle at which a rope runs off a drum. The fleeting angle is
important for good winding on and paying out of the rope. A rope is reeved to
spread the load over several ropes. This requires a crane block. Reeving the rope
several times reduces the force required to lift the load.
D Questions
11.l A new rope needs to be reeved in. The top sheave appears as in the
illustration below. What action wil1 you take?
D It doesn't matter, the top sheave doesn't affect the hoisting rope.
11.2 Gaps may appear between the turns when winding the first layer of
rope onto a smooth drum. What is the possible consequence?
11.3 A crane block is reeved in 5 times. The load rises at l m per second.
How fast does the rope go onto the drum?
A 1/51mls.
B 0.5 mis.
C 2 m/s.
D 5 m/s.
11.4 What are the consequences of a rope going over sheaves which are
too small in diameter?
C The sheave wil1 turn too fast because of the small diameter.
D With a greater angle the rope wil1 slip over the sheave.
Hooks must not be allowed to come free, Off centre of Gravity of boiler IS
so they are hooked from inside to outside compensated by using a lifting beam
The lifting points are so positioneel on the load that the centre of gravity is placed
along the axis of the lifting rope before lifting even begins. Where that is not the
case, forces wil1 arise during hoisting which wil1 tip the load and bring the centre of
gravity beneath the hook. But a tipped load is more difficult to set down accurately
than a load hanging straight.
Where the load does not hang level it should therefore be straightened up before
continuing with the lift. You must ensure that the centre of gravity of the load is
directly under the hook. Only then wil1 the load lift straight. See for more details
Chapter 5
It seems obvious to lift the load in the illustration above by attaching the chain sling
directly to one of the tubes. But the load's own weight wil1 cause it to be
unacceptably deformed during the lift.
It might seem better to attach this load using two slings attached to the underside,
but this is no good either, as the load wil1 topple over too easily. The slings must be
used so that they provide a sound support for the load. Lengths of timber are
therefore often used to support the load to be lifted.
The links are subject to damage in the INCORRECT: a hook must never be attached to
situation shown above. the middle of a (chain) ling.
Where a two-leg sling is used you should ask yourself "can the load withstand the
opposing forces set up by the two attachment points?" Difficulties may arise with
loads like long and not very rigid cases, plates or smooth straight objects.
Two or more slings which do not form an angle with one another may be used in
these circumstances. A spreader beam wil1 offer a good solution in such a case.
The centre of gravity rnay also be situated outside the object, as can be the case
with asymmetrical bodies.
When you begin a lift, always make sure the centre of gravity is directly under the
hook. We say then that the load is in balance.
If this is not the case, as the load leaves the ground it wil1 tip and turn until it finds
its own balance. See chapter 5
Imagine that you are raising a load using a two-leg sling. At the moment the load
leaves the ground, the two legs are not both tight. Stop the lift irnmediately.
If the two legs are not equally tight, that indicates that the load is out of balance.
This is a hazardous situation which rnay lead to an accident:
e a tipping and swinging load rnay trap persons or damage objects
e the legs of the sling rnay be overloaded
e if the load is hanging in a sling it rnay shift.
The crane hook must hang above the centre of gravity of the load. otherwise the
hazardous situation shown in the lower drawing wil1 arise.
i-force F1
The load must always be hung straight, so NOT as shown in the illustration above
The symmetrical or asymmetrical distribution of the load has consequences for the
working load on the lifting gear. Where the load is distributed asymmetrically a
lower working load factor is assumed. Asymmetry in a load is apparent in the large
differences in the angles of the legs from the perpendicular.
If the working load is calculated according to the tables, you must rnultiply the
working load factor by the strength of the single parts.
choke hftch
n
ft'
(4%
tipping a load
It may be that you are required to
intentionally tip a load. Such lifts
must be carried out with care to
avoid the crane and the lifting gear
being suddenly subjected to peak
loadings. The turning motion of the
load must also be controlled as
much as possible. Tipping can also
be carried out with two sets of slings.
These are not normal lifting activities
and the advice of the regulatory
agencies should be sought.
When tipping a load one should clearly understand where the CoG is and what
effect it wil1 have when the CoG crosses the tipping line. In the triangular structure
above a shorter extra sling is used to avoid sudden shockload, when tipping.
The principle is shown in sketches below:
Sling 2 gets
tighter and
gradually takes
Structure is over the load All load is now
turning on one from sling 1 in sling 2
All load in sling 1
Sling 1 is longer end
then sling 2
Start lifting
t T
e Is there welding work evident on the hook or chains? If so, discard it and do not
use it. Don't take chances.
e Attach the load as syrnmetrically as possible about the centre of gravity.
e Attachrnent points are often provided on the load itself. Look for syrnbols on the
load or its packaging.
e Long srnooth objects should be prevented from slipping out of the slings.
With pipes, an extra turn can be taken around the load.
e When steel slings are used, place tirnber packing between the sling and the
load.
e Sharp edges on the load may darnage the lifting equipment.
e Timber packing, tyres or sirnilar items may be placed between the load and the
sling to widen the loop formed by the sling.
e
always fall directly below the crane
hook to prevent the load tipping
during the lift.
Aim for an even loading in each leg
o spacer
of a sling.
e Prevent long horizontal loads from
turning, as they may impact with
people, the crane or the structure of
the platform.
Two tailing lines should be attached
to the end of the load. Two persons
can then direct the load.
e Keep long horizontal loads in balance
by using two or more slings.
58 Ton 58 Ton
/
3
2
100 Ton
1 0 0 Ton
The angle with the perpendiculak of each leg of a chain, steel rope or fabric sling assembly must not
exceed 60,giving a maximum permitted included angle of 120.
It is quite easy to determine the included angle in practice. The method is shown in
the illustration below. Measure the distance from the hook to the load.
If the length of one of the legs exceeds twice this measurement you have an
included angle exceeding 120, and you have therefore got it wrong!
If the vertical distance is equal to or less than the distance between the attachment
points, the included angle is 90' or less.
The height of a triangle with this included (top) angle at the top is half of the sloping side
^a:^'^^~~>s!~~"%?^!"a;as?a^^#% "4
Standa rd triangles
D Summary
This chapter has been concerned with the attachment of loads. We have
discussed attachments using the crane hook and using slings. We also discussed
the attachment of mixed loads. We moved on to consider the centre of gravity of a
load. It is vital that the centre of gravity of a load should fall below the crane hook
before the lift takes place. We explained why this is so important. We subsequently
dealt with the intentional tipping of a load, and tipping using two cranes or two sets
of lifting equipment. Finally we listed a series of points which must be taken int0
account before a lift is carried out.
In general, the advice given when attaching loads is to think before you act.
D Questions
12.1 The situation below involves lifting a flat case. What can you say about the
angle B and about the slings?
A Angle B rnay not exceed 30' and the two legs of the sling must have an
adequate capacity.
B Angle B rnay not exceed 60' and all legs of the sling must be equally
loaded.
C Angle B rnay not exceed 90' and the two legs of the ding must have an
adequate capacity.
D Angle B rnay not exceed 120' and the two legs of the sling must have an
adequate capacity.
12.2 When several slings are used for lifting, the included angle must be known in
order to apply the correct working load limit. In the situation depicted below,
the vertical distance from the top ring to the box is half the length of a single
leg. What is the size of angle 2?
A around 30'.
B around 45O.
C around 60'.
D over 60'.
12.3 What problem rnay arise when lifting a tank half-full of liquid?
D It doesn't matter.
12.5 What is the load S in both slings, when lifting a load of 80 Tons?
A. 56.8 Ton
B. 58 Ton
C. 46.4 Ton
D. 92.8 Ton
12.6 What is the load in both slings S, when lifting 100 Tons?
A. 100 Ton
B. 58 Ton
C. 71 Ton
D. 194 Ton
100 Ton
Jumbo has developed certain procedures for lifting heavy loads as well. They
follow in general the procedures described in this Chapter and which mainly
applies to offshore crane operations.
The installation manager is notified before lifting activities commence, and also if
necessary the radio operator. A discussion should then be held with slingers and
anyone else involved in the lift, to ensure that everyone knows what is expected of
them. If a lifting operation is complex and non-routine the preparation of a lifting
plan is advisable. A lifting plan wil1 include a detailed method of work with drawings
and all relevant data on the items to be lifted.
Never walk under a load suspended from the crane hook. Keep the workplace tidy
and safe. Equipment like containers, baskets, tank containers, slings, multi-leg
slings, fastenings, lifting strops and special lifting equipment must be inspected
and certified. Loose items should be placed in a proper container for lifting. Always
check that the SWL is adequate for the load to be lifted.
D Crane operator
The crane may be operated only by persons holding a valid certificate of
competence to operate an offshore crane.
As there is still no certification of ship crane operators, Jumbo has developed this
crane operators manual in order to train and educate the personnel that operates
the cranes on board of the Jumbo heavy lift vessels.
As a crane operator you are responsible for the crane(s), including the
maintenance of the crane book, the completion of inspection reports and the
necessary tests, checks and maintenance activities, including the following:
e cleaning the crane
e following the lubrication schedule and checking oil levels
e testing of safety interlocks and limit switches
e checks on electrical connections
e checks on wiring, rope sheaves and rope terminations
e preparation of inspection reports
reporting damage and defects to the installation manager or other responsible
person.
Safety interlocks must never be defeated or disabled, and any defects must be
reported to the installation manager. As crane operator you wil1 need information
on the loads to be taken for example from a supply ship to the platform, including
documentation such as cargo manifests, load sheets or weighing certificates.
These wil1 show the mass and nature of the load. You should not load and unioad
items in the absence of such information. You may also be given information
verbally. No weighing certificate wil1 accompany a load coming from another
platform.
D Banksmen
As a banksman you must ensure that you can never be trapped by an unforeseen
movement of the load. Banksmen must have taken a course in the safe attachment
of loads. A banksman must be able to assess the quality and reliability of lifting
gear. Before you raise a load, check it over for loose items. Use protection oh
corners and edges. Scaffold boards are not suitable. Use a tag line when needed.
D Lifting tackle
Lifting tackle must comply with national and international standards. You must not
use equipment which lacks identification or test data. The colour code wil1 show
immediately if the lifting tackle can be used. Only two colours may be in use at any
time. Equipment which is past its test date must be taken out of circulation and
sent ashore for inspection. The oil companies usually have their own department
who ensure that lifting equipment is inspected or replaced on time. We wil1 have a
brief look at the following items of lifting tackle:
* lifting chains and chain tackle
wire rope slings
fabric slings.
U-bolts and D-bolts must always be locked. Never use anything other than the
original bolt, and secure it with a corrosion-resistant split pin.
fabric slings
Every new fabric sling bears a blue label showing the following information:
0 SWL
o material in which the sling is made
o length in metres
o supplier'slmanufacturer's name
o recognition code "EN 1492-2 -1994".
It is advisable to hang slings up when out of use. Never use them around sharp
edges and never tie knots in them. If the sling sleeve is damaged, render it
unusable and send it ashore.
lContainers
Check the inspection plate. Every container has one, often on one of the doors.
The plate shows the following information:
permitted gross weight
date of last load test
date of last visual/Magnetic Particle Inspection.
The load test is valid for two years, the visual/MPI inspection for one year. Check
the mechanica1 condition of the container. Look out for damage. In particular look
at the door closure and its seal. Container doors must be locked.
Check the four-leg sling: it must not be distorted. The included angle between
diagonally opposite legs must not exceed 60.If the shackles can be separated
from the sling assembly they must be separately provided with a number and serial
number. They must be provided with bolts locked with split pins. With open
containers, check the drainage holes, which must always be clear. The container
can hold a considerable weight of water. It is better not to stack baskets and
containers, as the four-leg sling may be more easily damaged.
If stacking is necessitated by limited space, take extra care not to damage the
sling. Place protective timber packing between the containers or baskets.
Never open two container doors at the Same time until it is known what is inside.
The contents must be secured, and if chemicals are carried they must not be
allowed to interact. Prevent the risk of explosion, fire and other damage to the
192 of 197 GSBW & Jumbo A Jumbo Crane Operator Syllabus
., .,,...... . . ., .
packaging. Inflatable airbags may be used which are specially designed to secure
loads.
Methanol, diesel, helicopter fuel and water tanks come under the Same regulations
as containers, and are also provided with an identification plate carrying the usual
Load test and MP1 data.
The four-leg sling is tested as a unit with the tank, so it is not permissible to
'borrow" one from another unit. The SWL of a four-leg sling must always be equal
to or greater than the maximum total weight on the tank identification plate.
lWerking platforms
Before using a working platform with a crane you must first establish that there is
no better solution, for example using stagings.
The persons on a working platform must wear a safety belt attached to the
platform. The crane operator must have continuous visual contact with the persons
on the platform, and also good communications. The working platform may be
used in winds of speeds up to 13.8mls (6 Bft). The platform must be accompanied
by a record document and safety checklist.
OK NOK
1. 1 Work platform safety
1 Is the platform CE marked and is their a
certifikate or manufacturer's declaration?
1.2 Has a periodic inspection been carried out by
1a competent person in the last year?
1.2.1 1 Have all defects identified in this inspection
1been rectified?
1.3 1 Is there evidence of unacceptable damage or 1
1deformation to the platform? 1
1.4 1 Is the slinq in use in accordance with the local 1
rulesluser's manual?
1.4.1 Is the sling in good condition?
1.4.2 Is the attachment of the slina to the work
With some cranes, the load must first be placed on deck before the jib can be
lowered using the emergency procedure. Read up on this in your crane manual.
A separate hand pump is sometimes supplied, as with Liebherr cranes. These can
be taken to the required location and connected to the relevant hydraulic control
circuit. The circuit can then be pumped up to
pressure by hand.
1. manometer
2. pump handle
3. hose connection
4. tank
5. tank cap.
The hand
pump used
with a Liebherr
Emergency operations for Jumbo heavy Lift mast cranes and derricks require a
different approach. Above applies to platform cranes offshore.
Lifting machinery and lifting tackle may be damaged in the interim, so you must
check before each use that the equipment is still in order. Emergency procedures
must be carried out precisely in accordance with the crane handbook.
The limitations on crane movements are particularly significant, since protective
systems may not operate in an emergency.
D Questions
15.1 Why do you need to work according to procedures?
A It increases efficiency.
D It is a legal requirement.
15.2 A work platform may not be used without forethought. When may you
use a work platform?
15.3 What needs particular attention when you are placing a load on deck
in an emergency?
D That you should put the load down in a safe place as quickly as
possible.
As loods
EW fncrtasiRgdimen*
slons and weigte
BI& tt more and
more nwsssary t0
consider the we al
tw m more eranes t~
Bft om tod. Such an
operaffan freq~ently
wxpizss the prepara-
of a (ietaite&" m g plan to ckwiy (teler-
mine the iimlts within whfch the i% can be
ered. and can be advantageous 10 tlw !ittin~ Selectlon of niain lift crane: Although the
contractor.irtclude: nitial raising of this column wil he carried out
by meaas of a mam lik crane and taiicrane. the
ginal part of the UK. whcn the column reachcs
metres away fram the Centre of Gravity ("Cof a Other work Ehat caii tic done by the crane on
G) ~ n incaled
d on the centreline o[ the veasel. that speciiicjohsite.
THE S A F E V I E W
The-subjectssf. this artlcle te a prassure wssel (H ing the &ft. Uien there MB be no overhad in any
S2Otomes which has t5 be erect& by mem5 of of the twa mainlift eranes,
two main lift cranes and one tailcrane. The pres- However. it crane A lifts laster then crane B,
sure vessel is as show1 in Figure l . it wlit resuft te sn overlaad of o-aw A,
WewU make me of the technKitiewhich we Depeadtng w the distance oi the m i n Ufti~g
iewed in the previous artictes and which c m trunam to the ?.of 6..&is o<ferioad coalti !x
be su~~narised as: tnstgniflcant or mutd be dangerous. ft is thus
Taft-taads can be reduced by ofkettiag te wcesswy te cdcalate these condltkMts before
tatiicglag. starting the lift-ft is alsoimportant to keepboth
a TaSi4oa((s cm be rerfucat hy positroning %he !n t borfeantaj pEwe dur-
man Uthg trunntons close t@ mg the lilt. Foilowing are som? calculations of
ewtre of gmvfty (C. ofG.). the overload on "A" of "B" when both trunmons
are nat kepk horizontal,
ETORMOJS C S~pposeSas. QW pevrevessel la not Sttisd
The enomom weiekt anti knath of the column eorreetiy ard that c m e "A" ttfts (aster than
mam. %at G c m &uiti b~ neeai& Gram "S'rasultjag in a i dB
0arect ik in asin horizon. Due to this iact-newfth &e horizon &s
d would be t b erection
of thts column by meaas oi a mast g a t r y systesi
(ar GIn Pok). The me ol $ach a tffttog gantiy b
In te%xiwlaads,
amtongS13
tonnes column
iteetet fay tw
~smag re-"w
main I & mmes
and ia Owi'wa
CC-2009
tailcran* at
Finanasli
refinsry
Antwrp.
STEEL S m
agefwg of C o i u m
DETAIL "B"
FIG. 4
the; hor&ootajityof the mals iifttog UuBalon8. s8 oraties trom the job site. It spsxss for itseff, {%s, placed fa non shrink grout, o m test&
The sim i$te nsure that lo ooe swing the tail- that the crane types used in (hls anicte are fust rectmgalar steel sh
erme m,withoat liftmg the column any examples and thac the same principles can be
tx-, stowly gulde the column toto the veilt- applied tor other crane types. 2s O mritlmetres). By mews of a kveb
gag inttraitieot the torizostat dato et allshim-
AUGNMENT OF COLUMN plates is cfeeted.
Once the column h a been placed in the vertkal Wtth a spirit levei ths IwizonaBly of each
position and on its ia:ndation, one has to check IndIviduat shiro-ptateis adjuseedand wben the
@="mum effect m a possi&& overload of crane ;ad, U necessaiy, &fust &e verUcal a l i g ~ m i . shim-plates are fin&@set at the correct &va-
' * w "B". Thfi most critica}part o!the operatton
A devathu md wientation of the column. ft is Eon, the aides of each shte-plate are
fewbthe to 4e swwg tn between essaitid &at the coiams pwkiowd vW- wub grolt (5% Rg. 2 and picture 8. Mak $ure
bath c m e ft is wo& ren~aber- caBy wS&in toleramas determtwd by the mgi- that the surface ei ach shini-ptee te snil
lag, altbug catitraetor. a~mximateiy19 initBnoatrm Ww the ficial
any clips, nozzles or other obstructions alonq ekvaxon. The mxt das wben the grout has
the area of the column's shell thtit is close to lift- &r.ed. tb eievaxon stwM b@&ecW ag&n
engineering c o a t r a a r usually cheeto the mr- and adjustrnents made u p i o the liml required
reet alignment of the basering in reiation to 'he ievation by tneans of separate shim-piates of
centreiina of the coiumn. !n most cases, how- wartaas thictaiasses ( 1 , 2 , 3 , 4 . and 5 mBffme-
ever. ik is normal to find :hal the boitorn of ihe &&fl.
basering &&ates from the horizontal flat ptato
:he olher WAS 82 meirea. Diameters were 4 5 due to welding tensions. It is therefore neces-
mecres and 5.4 metres respectiv y sary to c h c k the verticalityof the column.
36
INTESNATlONAL CRANES M A Y 1993
Dimensions in Millimeters (Wde Body} Weigilt
Cargo handltag, espa- yoa MM be abte to me the crane operator's forces through &hepad eyes of the lifting beaia
cially when cranes standerd beams. However, beyond these nor-- &elf, (m Figures 3, 4 and 5). whereas a
are invulved, often mal weghts and dimensions, special liftingand spreader bearo is nonnaUy used to keep the
requirw t& we of spreader beams are requirecl. iifting sfings at a eertah angle to the ilfttnglugs
special spreader or What consideratioos should we observe on the load itself, The verticai lifting forces are
Uftingbeams. Usually, when using Hfting beams OF spreader frames, not traasfemd through the spreader bemi
stevedores ar crane and how cm we improve efficiency in handilng ttseif; te tmly farces in the spreader are com-
operators have a set these items? In this artfcle we try to answer pressfon brces, eaused by the horizontal com-
of bems &at cm be these questans and at the same tmie provide a ponent of the &ce tn the siing frorn the hook
used for vacious types of cargo. As tong as the suma"y of 'rarioustypes of lifting appiimce. to the spreader. @eeRgwes t and 2.)
cargo weights are nut extreme Qess than 40 First, how do y ~ defae
u the lenm lifting
tonnes), and the dimensions within normal beani and spreader hem? A liftiigbeam,used
s"ies (2-3 metres wide and 8-12 metre? long), ina rigging arrangement. is usuaxy transferring
A Uklag beam or spreader frame is needed
when cargo is being tiftfid by a single hook lift,
and when you have to &ach the Iifxng sings
&otwoomwr. iifting lugs whieh oaly aiiowver*
ticd farces. The only purpose of the beam i s to
ensure that the lifting lugs are dot toaded at sn
unacceptable anale.
Flat piate &e liftiitg iugs eau usually only be
loaded in one plain, parallel to h e plain of the
lifting lug. Futces perpendieuiar to &is plan are
usually utiacceptabte. and in such cases we
have to use aspreader or liftingbeam.
B the task of the Iiiing appliaace is only to
ensure the yerticdity ol &e tifting sBags, thm
a spreader bearo is most appropriate. (See
Figure l). T t e disadvantag@ o6 vsing the
spreader is the loss vl lifting height caused by
the need to take thesiings up to the main lifting
hook at anAMjle af 60 degrem.
The design o[ the spreader beam can be
quitesimple,as tt is only medio keep the stings
under aeettain angte. Because thelfting forces
are not transferred Uirough the spreader ikelf,
you m,in most cases,satisfy the customer
with a stress analysis of the spreader bem.
There is no red need tor a test procedure,
MO aithough yoa have to be
tons reactor careiui t0 mate suie the
with 9 Demag- spreader b e m is used cm-
TG3000 ~ t h rectiy6
22Stsupw'*
using a HE-4008 m o k at tiie
spreader hamforcediagram of a spreader
of firn twgth. beam (See Figure 21, the
A fumace farce 31 in the rnain hook beam itseif. A stras malysis alone is no longer
sectionwitha gjhg is the Same w the sufficient. The b a r n should be tested at its
~ o r n b i n ~ oofn designed Saie Worjdng Load, especially when
force SI underneath the
beam pitis two spreader, Force Si= Force iiiting toads above 100tonnes.
smaller lifting SI,since ik is the same sling. Such teSting cm be an expenswe exercue,
beams. When we work out the bUt once you have a valid test certiiicate, the Sift-
resuttant force of forces SI, we eet force RS1, ing beam can be a very versabteappliance.
which is pointing slightly dowi~%ds.This CU It is theretore wry important to Incorpc-
be split nto a compression farce HSL, in the rate al! practica! and theoretica1 howiedge in
direction of the spreader beam, and a Force the design ofa liting beatn.This &o appifes to
VS1,whteti points vertically downwards. the spreader hem: the design and fabrication
of both shouid be carried out by specialtsts.
TAKE PRECAimONS Soms Important parameters to be consid-
K we do not t&e precatitions, the spreader wed are:
bewiwikl fail down under this vertical force VS1 The lifting beam's own weight -shouldbe as
and under it" seK wigat. It is therefore neces- Iowas possible.
sary to attacti the spreader kam to the main Loss of fifting height should be as little as
lifting hook by rasans of two additionaisiings52.
Be aware that these silngs are &ere not oniy to The lifiing beun shoald be designed for a
support the spreader beam's own welght, bui wide variety ol loads.
ais0 to compensate tor the-vertcalforceVS1. Fitting and handling of the lifting beam
With heavy ioads, the force VS1 has to be should be~traightfarward.
caScuiated. and suttabte hoiding slings used 60 in the case of two identicai tifthg teams
keep the spreader h a m in position. Let us beingfabricated,testing can somemes be done
assume for caiculation purposes that ding S2 using hydraulic jacks as show iaEgure 9.
is at the Same angle to the rnahi hook as sling
51.5ee Figure2.
Force HS1 = SI.Cosa, and force VS1 =
One of the most c o m o n design errors with
HSlflanCf80+a)/2:), $5, force VS1 =
llting beams occurs in the positioning of the
(SI,Cosa)/Tanff90+a)/2). The force in SlingS2 =
fitting pad eyes at the end of the karo.fa many
VSVSina. Therefore, wken. lifting& load of 200
tonnes, the load tn sling SI = 100 tonnes aad WHEN DO YUU USE LtFnNG cases, pad eyes are positioneel as shown in
BWS? Rgure 3. In this case, the working fin* of theBft-
the load in sllag S2 = (Sl.cosEO-'/tanT57/sin6Oq
As explained betere, a lifttng beam does more ing torces has not been observed, resultingin
= 15,47tonnes, whicb cannot be ignored!
than lust spread (he slings. When fitted to tb posstbe overload of the pad eye.
The graat advantage of ustng a spreader
main Uiting hook of the crane, tt acts as an lt cannot be expressed strongly enough:
beam. designed in this method, is that it eau be
extenaionerfthe hook and h a the advantage of teave the design and fabrication of liftiag
a retatively simple H-beam w ptpe th&tcan eas-
allowing the slings to be piaced in positions bqm to specialist febricators who have a
Sly be adapted to the iength required, even tor
which best suit th load's lifting lugs. (See track record and eatensive experience. Foor
big toa&.
FigureS.) design and/or bad vtorhanship can easily
For exampie, a spreads- beam comprising a
As cm be seen fraai Figures 7 and 8, these lead to latdities. Liftin3 beams shouid ~ n l ybe
single HE400 B beam was u& fora 340 tonne, 6
bearns are subject to both hending and shear used uncter lifttag mgles as specified by the
metre diameter reactor. (See picture l.) Only
farces. The pad @yesor liftlag Ininions on the fabricator. altkough ia some cases different
Mo end plees of, say, l metre should be fabri-
lifting beam transfer the forces through the angies are allowable onder reduced koads.
cated. and cornbined with intennedlate sections
Depending O R &pasftton
~ of the liftinglugs,
it is sometjmes possibie h? we a combInation of
lifttag beains or spreaders. A disadvantage hera
is that more Eiftirig bems require rriore lifting
height. K no height is avdlable,A spe&tiy made
liftingbeam mtght be ttusanswer.
CRARETYPES
Bestdes tbs capacity range of a crane,
the user also needs to specify what crane
type he wants. We could, for exampk, &vide l^-
more then one jobiaaday. The $paceand time
needed for riggingfderigging is &o very h-
ited becauss the telescopic boom travels on
the crane and cm be extended fa the fwW
length after the crane has been set on lts out-
negers. Only very large telescopic cranes
sometimes need art auxiliary crane during tig-
ging/deriggiag. The loww mtfage is reiatlvely
short and most of the wheels are steerable.
which makes these cranes ided tor manoeu-
vring int0 narrow locatlans.
CRAWLER CRAWS
The speciflc differente hetween a crawler
crane and other crane types is that the
crawier dees nok travel on rubber U r e hut is
nstead equipped with steef crawler tracks.
The crawier tracks form the baste support
structure of the crane aad spread Uia crime
ioad on the ground, white at the saroe time -
and this is an important dfference - befng
able to move the crane wth Jaad from one
iocaton t6 the other.
The crawkr is usually used on long temcon-
tracts, as mobilisation/demobiiisation ad rig-
gmgAiedgginggenerally readres lar more work
thw 4 t h a. telescopk crane, Depending on the
size o( the crane, you cm @ace&e complete
machine on a towloadw. ar you may have to di-
mantte both crawler tracks, counter we'ightand
boom. In soirie cases, espedally in the USA
where road restrictlon are more strict then in
other countries,the upper and kwer carbody of
the larger crawler eranes m e t &o be spkt aad
transported on separate lowloaders.
Features of owlers which can [Bate hem
ideal for long tenn contracts OR constructton
sites are the wiWoad travel capabili& and the
hil'ityta rdocate oa their own trads. The latest
devdopment in this Held is the PC/CC Type
(Pedestal Crane/Crawler Crane) dsvdoped by
Ven Seumerenand M m s s m m Demag fsee pic-
ture on previ~uspage). Ttxs is tesially a truck
crane, hut cm &o be ptaced on a a w k @a&
as welt as 6n outrtggers, thereby combining the
advantagesof acrawler-and truckerm&
cranes toto the foltowtag braad categoties: by road frorn onejob to another. and had to be
Telescopic AllTerrain Cranes mobilised/demoblllsed by lowloader. In west-
CrawlerCranes ern Europa, rough terrain cranes have in mmy
Lattiee Boom Oraties cases been repiaced by al1 terrain cranes Company's Special Transport
Eacn of these hm tts specik field ai appiication. which can travel both on wad and on rough Division. He has a Mastere Degree ia
terrain. These tetescopic cranes are typicaxy Mechaaical Engineering h m the
used on short terra contracts. Tedmicai Uaiverslty of Delft and
Mobilisation/'demobiUsationi s very easy as was project manager with Van
the mane travels OR its own wheels from job to
Seumeren Holland aatil1989.
job &d usualiy does not requte another crme
to rig it. In roany cases they can beqused on
Befare that he wasmana@ngdirec-
tor of ItrftcBV Holland. He "ias boen
TAB& 2: CAPACITY CHART IN TONNE FOR 60 T UEBHERR LTM-1060BASE0 ON 66 'h4/0 O f TIPPING
r-- ---- --. ,
T H E SAFE VEW.
TRANSPORT CUMBI&ATIOi"^
How do we now calculate the grwnd pressure
underneath a transport combination'^ [f we the average ground ptessure is ificreased. The which gives a smaller sur- The average
take a closer look at the actual pressure of a average gmund pressure ter a foyr axieiine face than what we cakeu- groundloadOf a
rfoubl'~widtb 8-
tyre on the ground. we reajise that the contact platform trailer loafted to its maximum capac- katcd w h e ~tb? tyre laad 1s p,atform
pressure of the tyre wit1 be the Same as the ity of 100tonnes c m bwalculated as follows: spread under 45 desrees. trailer hardty
pressure inside the ! g e (act~ox~s reaction). Qrowd area at a depth of half axieiine dis- The strange thing about exteefitis 5
(Set Figure t .) tance=4~1~55x@+l.SS)=28,21 m2. these load (alculations is tonne/m2.
Depending on the load on the lyre, i t wil$ The averaga ground pressure is the Cross that port authortfaes, who are very concerned
detlect until there is equilibrium between the VehideWesght/Ground Area t 116/28.21 a 4.1 E &bout darnaging their quays, hardly pay any
tyre pressure and the grouad surface pressure tonnwra2. attention to mobile eranes which usually put
undemeath it. With a tyre presswe of 12 In case a fully lmded double width 8 a l e - their eutngoers directiy down on the concrete of
kg/crnz, this results in a contact pressure on line trailer is used, +.he average ground pres- the qua!, r<sultir~qin !ar higher poini !mds ~ttt!!i
the ground surface of 12 ka/cm2. Ii we convert sure = (4&0-(16~~4));(~8~1.35xf6.2-1.?.3)) = 4 82 anyol :ne tyres of a hlly loadec plaiforrn trailer,
this int- a laad per id it wouid ba 12 x 10,000 tonne/k2. (The maximum bad = 400 tonnes, ft is not onSy the load per square metris
cm2=120,000kgm2 s 120tonne/m2. plus own wei& ot trailer v 16 x 4 = 64 tonnes). which should be conssdered. In $ome cases the
We know this is not realistic and that we This aethod s a realistic approach to estab- total Soad placed on the gound sarface a even
should consider the average ground pressure. lish a ground toad of a [oaded traite- Another more importarrt thm the laad/m2. %en a
The average ground pressure is'the pressure factor whicn we should take inio account is transport combtnation is drisen alongside the
undemeath a transport combination ai-adepth tht values given &y cis!! engineers in most bank of a canal or river, particular care should
of half the axieline distance underneath the case? are b a a d on very little settSernent over a ba taken in considering tke effect on the
tyres- %we assume that the contact prassure of long period of time. In the transport business, @mbankment.See Figure 3.
the tyre spreads its b a d under 45 degrees into we do allow settlemem. as the Iaad usuaily
the subsoil. then we can caieufctte the average moves over the surface quickty. When heavy MOBILE CRARES
grourid pressure as shown in Fgure 2, loads are transported on multi-wheeled plat- \f we take, fot ewiple. a 60 tonne hydrauiic
Dw t<s the leed spreadingpp@%rl~atlgle of form trailers, the contractor usualiy oniy takes crane on tour outriggws <own weigSit of crane
45 ijegrees the area which is used to calculate int0 account the projecled m a of the trailer, apprcwmatety 30 tonnes), lifting a load of 10
26
IMTEfiNATiONAL C R A N E S SEPTEMBER 1 9 9 3
the crane upper carbody Ss placed in line with
the centreiin@o i the crane with the mafa boom
positioneel over the rear end of the crane. The
pusltion of the centre of gravily of the com-
ptetefy ngged unloaded erane in hanzontal as
weli as vertical posUon can be calcul.ated front
al1 individual pats. Usually, tbs pasitton of the
centre of gravityof theunkiade(i crane (posikion
A) is somewhereabove the upper carbody (here
taken as 1.8 metres a h m base) and a tittre
khind therotation centre of theupper carbody.
tonnes resulttng fn a poss Qutrigges of a
Ut us assume the rigged crane with coup
vehick wetght fl( 60 tonnes, GemagTC-30Q0
tfane, ptaced on terweight bas a total weight of 160 tonnes,
the lwd per outrigger hlsupport Based on position A, the laad X1 on oubriggers
wouid bea mintmum ol60j4 matsto wead 1 4 can be cakuiaied as:
= 15 tonnes. In most cases the tead.
X1=[16p322)/10= 35.2 tonnes
- theload on theoutriagersat Scw*tme5 pijfn9 Rfispctely, 17.6 tonnes on outrigger l
ihe side we are liftiag would is fequired. and 17.6 tonnes on outrlgger 2. The load on
even be higher. outriggers 3 and 4 is 62.4 tonnes each. M e n
, With outrigger pad3 of only 0.6 x 0.6 0.36 the upper carixxty is nat in line wfth the
:
m*, the outrigger load wil1 in many cases crane's lower carbody,the ealculation isa1Ett.k
exceed the aftowable laad of the quay. bit more complicated, but t)ie saaie principles
However, l have never come across a situation can be appiied.
w h e a~crme outrigger prbtruded through the
concrete slab of a qua?. Average altowable CRANE WITH Lom
gmund loads on concrete berths are in the Let us now see what happens with the outrg- the support mat fe suificient, the awrage
range of S tonne/m2, which in almost alk cases p r loads when the crane lifts a load of 125 grouttd bad can be cafcuiated by
a suffident tu accommodate a tufly loaded tonnes at 12 metres radlus. Weftrst have to cal- 129.96/(7.5xl .S) =.ll.SS tonne/m2.
platform trailer. culate the new kation 8 o( the centre of grav- %ere the laad of each outrigger cannot be
In order to calculate the outrigger load of a ity of the crane with laad. Wth the moment spread sufflcientiy, a solution can te found by
mobiie crane, we need to know the exact loca- eqvawn over lipping line 1-2 we find in hort- drving ples on the oatrtgyx positions of the
tion of the centre of gravity of the untoaded zontal position: crane. faisting foundationscan &lsobe a heip.
crane. As cm be s e n hwn Figitfes 4 and 5, the 160x?.+((125+Mi0]xY)3t25xi2, YsO.88in. in practce, it is usually aot as simple as It
location of the centreof gravtty depends ort the The vertlcai postian of the centre of gravity looks te caJculate outrigger loads of craaes.
type and teagth of main boom as wel[ as the of thecraae W h bad is: The main difflculty is that the erane mmufac-
boom angle with the horizontai. The orrenta- (160x2 9)<325xl8.3> 285itZ,Z=9.654 metres. lurers do not easliy gfve us the exact *tgte
Bon of the upper carbody 01 the crane in reta- PSeasefxsa in mind that the centre of gcav- and locations of the eentres of gravftSas of dl
tion to the outnggers is als0 Important. ity oftfte load must be taken as tf it was glaeed individual m m paris of the crane. $ometiros
To caialate the exatt locatt'on o4 the centre in the centre of the top sheave of the main crane maauiaWims supply outrigger laad
of gravity of the completely rigged crafie, we boom. Becauseof the load of 125tonnes in the tables, but they only show the outrgger ioads
need to kn6w the weights and location of the main hooit, the centre of gravlty of khe crane for some cases. With today's computers and
centre of gravity of sach indivdual part of the with load ha$ moved upwards sgnificantly as spreadsheets it is a. reiatively simpte t&k to
m e . The mam p m s are: wel1 as towards oatriggers 1-2, resultmg i prepare a caiculatbg progrmitie b r outrigger
'MainBooni [ fty jib K applicatie) iticreased loads on outriggefg l md 2. Ths ioads, even tor different siswing mgles of the
A-Pram be calcalatad as bekw: upper car body, provided the manufact
Upper car body C* angle wth centreine) "3.=(28,5.';9.12)/18 = 259 92 tonnes, supplies the essentiaf infonnatt-n.
Lower car body This is equivalent to 12936 tonnes on each
Stay*re$ outrigger l and 2. Usually the outrigger loads
Main had bbck (illfting wires) of heavy cranes are spread on the ground by
To simplify the caiculation, we assume that means of stee! support mats. K the sGBness of President of JuaAo Shipphg
Company's Special Transport
Division. He has a Masters Degree in
Aiechaixcal Engineering trom the
Technical University of Delft and
was project managerwith Van
Semneren HoUsnd mul 1889.
Before that he was managing direc-
tor of Itrec BV Holland. He bas been
27
I N T E R N A T I O N A L CRANE S t P T E M S E 9 1993
Richard Krabbendam * shows hw to save time with a quick boom-clearance culculationprogram
When a tigging pian is
prepared, you usually
start with a plan draw-
ing of the workinffsite
and select a crane
which t- abk to lift a
pattictilar ioad ?t the
requred radius. Using
the plan we eaucheck
&e clearance of the counterwf5ight and A-
frame wlxi swounding foundations or otter
obstacles. Outriggers are alsu shown on the
plan, so Grane orimtation can b@altered unti!
alt eraneparts are clear of obstactes.
Wbether you use a lattice boom or tete-
seopic boom crane. you always have t& g&
through more ar Iess the same routine, That is,
prepare the aerial plan and indicate;
Piek- radius of the load and franc liftmg
capacityat pick-up radius
Setting radius of iaad aftd crane capacity
a Boom leng&kof crane
lndicate space tor boom lay down and rig-
ging posftion of crane
A useful tooi or preparing this top vrew pian is To check this, It is c5mmon to prepw A side 9 Offset @lh a m pivot a i bottorn =A
a set ot'transparent overiays of the man crane vtew (cailed an $ i e d o n ) of the most critical Helght of boom plvot abavebottom = G
body- including outrfgger ar erawier tayouts - crane positron when the load is tifted. However. Boom tenglh = L
at different scates. The t~rnifigradius of Uie A- an easier and quicker w y to check boom clear- Thickness of hoorn in direetion o( lift = E
frame and couaterweigkt should a i s ~ bis indi- ance (Fin R i e is to calculate ft mathemati E Offset of top sbeaw = C
cated on the transparencies. See Raure l. A eally using a programabt- pocket calculator. Radius o( hador obstacte = D
rigging engtoeer shouid always have a set of Height at positton of ciewaace = M
transparencis at various scales in ord&r to POCKETCALCUTION E Radiug odift = R
establish qutckly and quita accuralely the cor- A stmple calcalating procedure using a pro-
reet crane positin on a plan. grarnabie pocket caicutator (Casta, Tandy, late boom dearance, F, by ihe followmg forrnula:
There stUi remairs another very important Hwlett Packard w similar) has been prepared F = (R-A-w(H-G)/Tan(U)))'Sii<lJXE/2)
check to be carried out. Is the selected boom to ailow rapid cataiiatioa o?clearance. By feed- Hew do we enter this te our pocket eom
len@~ sufficient, and does the load stay dear OE ing in rquired radius, liftng capacity, esti- puttr? Read the maoud firsi and make sure you
thema boomorother hei& obstactes on site? mated boom fength and other variables, the have a programmabie pocket computer wfth 8
programme checks the boom clearance wth kilobyte memory or bstter, The program lstlng
eittusr ?he load or ether height obstacles. in which is Bven below i s based on the Casio FX-
addition to swing &{meit can als@impress 95P. Other computers may require $light modi-
ciients byallowing you to select the crane ody tications,but the principie stays the Same.
minutesafter tost seeingthe site plan! Rigging persomel are nat aiways fayniliar
How can yau do this yqurself? Firat,make wth computers, sa the foltowing p r o g r m e
sure you have a programttiable pocket com- description gags int@some depil. Remember
puter. in my own expetienee, a very simpte &at once set up, ft could becomeavery power-
&s&-W99w its equivalent, the Tandy PC- fui tooi fot staif tn the field,
6, is ddeal for we in the Beid; 2s weighs n e a to
nothing and is the Same site. as au dectronic A BASIC PROGBAiMME
diary, The n w e advanced Hewlett Packard F- The following tines' of program - in the BASIC
95 could ais0 be used. computer tanguage - must be typed into the
In order to calculate the boom ctearance,F, pocket computer. Resd &e maau& on how to
you need t@estabikik specfic data of the do this. Each line represent$ a contmand lor the
crane. The data requirments are listex beiow pocket calculator to execute. The calculator
and shown on Fgure2. carries out the commands line by fine In b
T H E S A F E V I E W
Richard Krabbendam * desuibes how spreadsheets can b@@e8to calcuhte tailtoad deaemes.
t o t tanallarwttti computers.
The program listin%is given beiow:
100 PMOT "A1UOA CALCULATOR
10SSETO
110 INPUT TOTAL
36
H T S K M A r i O H A L CSAWS K O V M 8 E R t 2 9 3
..
12 [Boom Clearance F= =(B~-B~-(B~-B~)/(TAN(BI 3*PI()/180))-B7)*SIN(B13*PIO/180)-0.5*B51 Meter
13 l~oomanglewith Horizon = ~ = ( A T A N ( B ~ / B ~ ) + A C O S ( ( B ~ - B ~ ) / S Q R T ( B ~ * B ~ + B ~ * B ~ ) ) )lDegree3
*~~~PI~
treline of the column and at increased lifting shown in Figure 5. Column B is used
angle becomes unstable. Try to avoid this in al1 to convert degrees int0 radians
circurnstances. which are used in the fonnulae in
columns C, D and E.
SPREADSHEETOPTION To illustrate the tailioad calcula-
Nowadays most crane hire contractors make tions even better, you can let the
use of computers for word processing or spreadsheet present the resuits in
accounting. Popular spreadsheets include the fonn of an X-Y graph. See Figure 4,
Lotus123 and Excel 4.0. These spreadsheet pro- where curve l represente an 0.2
orams are very powerful and can do a lot more
metre offset, curve 2 a 5.0 metre off-
than the pocket computer, though are less con- set and curve 3 a 10 metre offset.
venient for field work. A spreadsheet can pre When the spreadsheet is com-
sent the calculations as shown in Figure 4. plete, it is advisabie to protect the
The input data a, b, c and G for three differ- document and lock all cells which are
ent offset cases are entered in columns C, D not subject to change. That is, all cells
and E of rows 2,3,4 a d 5 respectively of the except the ones under C2-C5, D2-D5,
spreadsheet. See Figure S, aithough columns D E2-ES and A&A26. Now you c m easily
and E are not show% The input data can vary calculate the tailload at any lifting
as. much as you xke, provided the values angle and iflustrateit graphicaily:
remain positive. The iiiting angles, vS, are listed
in column A under rows 8 to 32 in steps of 5 BOOM CLEARANCE
degrees up to 70 degrees, and thereafter in The boom clearance calcdation discussed in the boom clearance between load and boom as
steps of 2 degrees. the previous artlcle (JC, October, p43) can als0 shown in the sketch oa Figure 7 is entered in
The formdae for tailioad in an EXCEL 4.0 tie carried out by spreadsheet. The input data cel1 B13 and the fonnuia for the boom angle is
spreadsheet are placed in columns C, D and E A, G, L, E, C, D, H, and R can be entered in cells entered in c d B12. Again, it isadvisableto lock
of rows 8 to 32 respectively. The fonnuiae are B2-B9. See Figure 6. The formula to calcuiate these cells which are not subject to change. An
example of a booin clearance cakulation is
shown as in. Fig. 7.
FiNAL CHECK.
When the programs have been typed in cor-
rectty they should run without diicuity. As a
check, type in thesame data as used in the exam-
pies and checkyou get thesameresalts.
t
*Eic.hard Krabbendam is Vice-
President of Jumbo Shipping
Company's SpecialTransportDivision.
He has a Masters Degree in Mechanica!
Engineering from the Technica1
Ugversity of Delft and was project
manager withVan Seumeren Holland
until1989. Before that he was manag-
ing director of I&ecBV Holland. He
has been in the heavy lift and trans-
portation indnstysince 1973.
Lchard
of Jumbo Shipphg Company's Special
1 Transport Division. He has a Masten
1
lower carbody. As shown in ftgure 5, the com- This is caiculatedss shown te figure 5. That is, negree& MechanicalEngineaw from
b i n d CoG of thecraae is placed in the centre of T.qa) = 745/2%75= 8.2504, giving a theoretlcal the Tecbnical Universityaf Delft and was
tipping angle, a, of ATAN(0.2504)= 14.05 project managerwiih Van %umerea
the 12-&e line platform trailer.The trailer itself Holland anti! 1989. Before &at he was
is set in aa asymmetrical %point suspension degraes. (Here, 745 niilltmtres (s the distance
managing djrectoroItrec BV Holland.
systeni. All d e s areloadd equdy. from the CoG to the tipping Une.) The a ?
He h w been in the heavy lift and mn*
base,A-B, itself dspends on the trailer typeand portation industrystooft1973.
TIPPING UKES is here 1,800mUliinetres.
The tipping lines of the transport combination In a &point suspension aystem, rte area
are defined as the lines comecting the three eoclosed by the tipping lines wouid te a rectan-
suspension points. We eould c o m F e &is to a $e; the distance of the CoG to the tipping line
tabte wfth thrae leas. As tong as the CQG ol the increases to 980 miltimetres, aad, as a result,
toad stays mthin the.tipping tines the trailer the stability of the transport comb'inaton
wit1not tip over. inereases. The advaniage of the %pointsuspen-
One criteria for 3tabUlty is the theoretica1 Sion, howwer, is that it is stattcally deflned,
tipping angte of the transport combinaxon. whereas the four point $Ftera is act. As m
it "i ccoincidenta! but iatroduci~g the i30 9000 standard is to To profeet the parties nvolved, we Md not
perhaps appropriate increase safety and efficiency. What soms do Teveal any names. What is Important B that we
tht th'is, my ihir- not lik about these certKication standards is leam &om the example and do not mate the
teenth article tor The that they often seem to create extra paper Same mtetekes ourselves.
Safe View. Is on the worit without improving efficiency and safety.
subject of atcidents. We should always try to keep reguiations RO-R0 ACCIDEW
In the crane and straightforward: simple m& are easy to The accident in queston occurred more than
transport world, tinderstand and easy to apply. 15 years ago. A Roll-on/Roll-off @o-Ro) vessel
everyone tries to One practica! wayof avoidingacadente is to arrived In port and preparat'ionswere made to
work safety to minimlsethe risk of accdertls. (eam Erom past mistalces, analysing tn detail jack up and rolf-offtwo pressure vessels at 450
Unfortimateiy, accdents do happen and what went wrong and why In my own heavy lift and 365 tonnes weight respecii~ely. 80th
'yiespite our best efforts an accident-free future career I have been formate enough never io columns had to be jacted up to manoeuvre wo
ean never be guaranteed- have been directly involved in a smous accl- double width. 6 axieline platform trader dollies
What we can do, howwer, is train our per- den& but have been called 'm. severat times after underneath a c h transport saddte. The dollies
soanel and esteblisft ruies and r^gulatlons that the went to analyse the causes of accdents. went fitted with bolsters.
are practica) and whch can have a postthre Hare. we wilt look ai an actual accident which The flrst column was jacted LTS metres
tafluence on safety. Qne of the reasons lor combined both trainsportfflion and litting taska. above deck leve! and the dollies manosuvred
started to go wrong. To ,
explalsi what happend &ring roll'oEf we first
have to explain the worfcing pnnciptes of art air
powered brat-ng system.
-
Air b r a k have (wo airlines ooe red and
OM yexow - which are connecte~to the air
supply of the prime mover, The red line feeds
air tnto starage tanks on the ptatfm trailer.
When the pressure in the tank exceeds 7.35
bar. and when the hand brake valve ta
released. the spring powered braking cylinders
ara activated and the brakes reteased.
Altarnatively, if the pressure Is beiow 7.35 bar,
or if there ts rio air "upply at &l! in dl? red air-
line, thw the hrakng cyiinders wii! activate
the braks 2nd the trailer
~acfislfted the caaflotmove,
column to alto*
jmfmg af
'?he ye3kow airhe i$ the
transpo& commantting airkirte and is
rioHies. normally operated frofn the
prime mover's fout pedal. When the peda1 is
depreased. the comrnandia~ air pressure
drops, activating the main system (the red air-
line) which ihen applies the trailer braks. The
requireti brakhg force, which depends on the
Cross Vehicte Weight of the transport combina-
tion. cao be adpisted to tour levets. Thfe level is
set by a handie on the side of the traile- wbich
can als0 be used as a hand brake or to release
the pressure o1 the spring powered brakes.
n=T MISTAKE
Now back to ow case study. The supervisor
want& to move the platlonn trailer and ciuoifl
comblnation a tew melrea towards the Ro-Ro
ramp.Th@red line was conneeted t~ the prime
mover hut the corncnanding H~QW line was left Thngs thea got worse. Ta clear up the wauld change i" Ke m o a The rear of the
mess ft was decided K> use two crawfer eranes the load towards the bow. wiumn
mconnected because the travel distance was
so short wi the brakina power raquired so low to lift the vesse off the damaged trailer, posi- He shout- ais& W e f~~d~ft~$~
- or so thought th+supervis~r.m i s is often the tloned either side of the vessei's ssrt end. The
intention was- to lift at the front dolly and skw
instructed & trailer opera- weids
tor t0 ~ t a d b yn e e to the conoecting the
procedure usedon. stadje, level gmund.)
Cm you guess what happened? When Ehe simuitaneously to albw the trailer and botster hand brake vdve at the bolster &te t*
side of the trailer. ihe traiiw wore-
tramsport combinatton was pulled towards &he to te removed. torn off.
R@&oramp, the shlp's trim aitered, tipping And, of course, te
domwards towards the quay and in turn DUAL LIFT ERROR transgort combination shouid never have been
increasing rhe transport coinbinatton's move- However, duriag the QQeraHOaonly OMcrane movad without conoectmg b o t , air Bnes
ment downwards. The supervisor instructed slewed as pianned* The other reniamed sta- faecause it was resting aft a floatalg vessej aad
the driver to actvate the brates, bul nothing tonary, resultuig m an exmsive $<deforce on oot a tevei, stabie surface. A &@led standard
happened because the y e w iine was not con- the boom, causngil to buckle and fallonto the checklistcov~ruigall these points should have
nected. The cornbinaflon cootinued to rot1 ski& of the pressure vessel The second crane been used, and the supervisor in. charge
towanfe the ramp, inereashg the:deckslope as couldn't hotd the load on its own and its boom assig~b d check the important points.
kt did so. aiso huckteti. To round things off the vessel The faufts In the liting operattoa were simi-
Everyone couid see what was happening, dropped back onto the trailer and caused fur- lady ctear. For exaniple, neither of the crane
but it wss 1 9 0 late to do atlythiag. In a matter of t b r severe damags. operators had preger instructions on b w the
seconds the front dol& rolled of the ramp After ranoval oi the two daaiaged trawlers, lift was to be camed out We taww that in al1
onto the quay. The secood dolly f6M~wedand a single crane was used to shift tne trom dcily circumsta.nces side loads on crane booms
&e saaden transfer of weight off the ship to :he hesner rear end oi the pressure vessel, should be avoided. This could easily have been
ca& the bow to r i s shaqly. As a result the wfth the front end sappofled by a drIH rig accomplished: the prime inover coufd have
raar end of t t e seeond dolly was more or tess dessert bogie fsee picture). In this way the pulled the load slowiy forward a d S both
dumped onto the quay. ship's Rc-Ro ramp was cleared. oanes were in tree swing,ttrey c&uldhave lol-
Nobody was injured Snit the transport com- After the necessary repairs the w o n d lowed the movement of ftie prime #over auto-
binaton was a mess. Tke weids securmg the pressure vessei on board was jacted up and maticaUy. Slight adjustmeats might have been
coiumn's bolster plate to the trailer were torn rolled off properiy and ttaasported safety t0 required forthe increas-eciradius.
oif, causaig the bolster piate to slide fowaid. the job site. Thereafter Uia Brst unit was However, durhg &e slewing operation one
The rear ot tha trailer was stil! partiyresting w retoaderf onto the repaired platform trailer dof- crane was in (ree swing while the other w&$oo
the m~ steeply stopittg %Q-Roramp, and tt had lies and shiftet to s&. controlled swing wd t b r e wss a@ naging
pushed upwards int0 the ski& of the pressure superintendentia charge who couid @veproper
vessei. prodwang a $light denc. The front end tasxructions to tte @@rators.A coaipiiacapra-
of the conibifiatioo W W he back end of xon should be planned in detail and nok be lek
heavtiy overioaded and the trailer to crane opcratars vbo necessartty have a !im-
pushed int0 the quay. pusiis* mtO above you should conlinuously te thinking
~ a x ittie axtes cai b t h
fraters nat been straight it
gzrEofui
resu,-ting in a
eaboi-n ttie consequencesof each of l-hepanned
acttofis.In this exatnple, that nieans the iuper-
wout- have beena totworse. st+ghtdent. visarshout- have forewen that the $hip's trim
ROAD SURVEYS
B the project tavolves the transportation of
targe and heavy items, a detat-ed route survey
trom the landing point to the job site should be TRAILER STAStLITY
cmed out to idenxfyimportant points such as: location of the Ming points oa a heavy pr*
Q Overhead wires. Clearances of dras to the $wevessei can geatly influence the erecfon
loa. Cm these be raised or should they be rnethod and crane typets) required. (See pre6
ren#ued?Arethere any high tension transmis" o m articles on tandemfifts.}
swn Unes inthe transport route which need to Q AIIowabe ground h d oa site. R i s is par-
te$hut off when the ioad passes? ticularty important whea artrernely heavy
O Overfacad obstraetions. C a these obstruc- hads need to bearected. in certain cases piling
tions be renwed or cm a bypass be con- ander the crme outriggers or ringer construc-
structed? In some instances the road can be tion is necessaiy, Altematively, a large number
dug out to tncrease the maximum clearance. Q( laad spreading mats may be suBicieat.
Q bridge^, cuverts etc.What is the m m m O Dfaneasions of loads and location af the
allowable &e line load on the bridges? i f the load's centre af gravity (CoG). The physical-
bridge cannot be crossed cm it be strength- stee and shape of the load as wel1 as the locs e
eaed #rcm a bypass be constrected? tion of the CoG in relatioo to the iifting points
Q Raad pceots in percentage t e m , dimb- c m have an enormous affect on the erection
ing w deseendbig. The required tractivepower method as welI as the type of crane(s) needed.
of the transport cambination cm be calculated a infrastructm-eat &e job site; How good are
i{Ure gradients are knowo. the acces3 roads to the job site? ?s there SU@-
3 Camber of the road. This is an important dent space to assemble the main boom? Can-
point conceming the stabiiity of the ioad oo a crime assembly all be dons at the erwtion
trailer. Trailers wrth hydrauiic suspension cm iocatioci ar at a different spot and then moved
easxy compensate tor road camber sad keep to the sitehilly rigged?
the load kvel at al1times. Hl these quesxons wied an w w e r befere
O Raad-sarfac~tin order to transport heavy .
stiould investigate the following:
you c m prepare a good quotation for the pro-
toa&, the road suriace should be sufflciently ject. Most c m usually be answered by the
compact& to wtthstand the tyre pressure, as Q Ptot plan of foundations. TOidentKy where dient, provfed they are aware of these issues.
weit as the tracx're power ai the prime mover. the cargo can be- moved and how i t can be The aitimate atal must be far ci"entsto pro-
The moother and harder the road surface, the erected or instailedyou needthe layout or piot vide botter RF@ so that contractory eau sub-
s frexou one-cm e x p e t The width o[ the plan. of the foundationsin relation to surrouod- &t bete-quotations.
road at claves as wel1 as atraiahts must be s& ing site roads, strueturesetc.
iicient to cope mth the pSmed transport com- O Elevaiions of foundations. A cross section
bination- of the foundation,as welk as details of the type
o[ foundation, is important In sdecting the Hnal
erection method. A tabfe top foundation
requires in most cases a different rigging plan
trom a foundation st ground level.
Q Details and tecaxoos of li%ng pohts. The
ComputerAidedDesign (CAD} andprojectplanning programs m
mxkeyourbusiness a lot more effici'nt. Richard Krabbendam *
r 'i3W3N
TRANSPORT i& SZEXHJLE OF PREssuRE vEssEf.
ean reach up to more than 90 drawings. US@ casts to specified resourees. The basic use of
these it is eaq to conflgure a side vtew of the these programs c m be learnsd quickiy.
Demag as s h o w 'm. Figure 2. The same applies Ta prepare a bar chart ts fairiy straightfor-
to transport equipment or ships and barges, ward. First split the project M a major actM-
These drawings, wliich should be filed t k ~miled
, *Suiamary task* Cshown In capita!
under designatecl sub-directorie withtn your letters in the example in Figure 3). Then list the
computer titingsystem, are the basic tools used detailed taste in a togical sequence beiow ttie
to compose Lhe rgging and transport studies. smmary taks- Using the esanipk of the trans
Tbt? dewiags are similar to the Setters of the port and erection of a pressure vessel. The
alphabet. Each letter is a drawing. which we can major acxvittes are:
quiddy retrievt; by pushkg the relevant com- Mobiiis~lonand rigging of cranes-
puter key. In Aatocad we ean p r v e as many Transport of pressure vessel.
RGGIHG STUDY drawlngs as we tite, bot have to prepare our Erection of Pressure vesseL
The mafn taste are to eet familiar 4th the pro- o m menu on the keyboard to &e w qui& 9 De-rigging and deniobiBsaxon of eranes.
gram ftself, input all your tooi$ (crane parts acces$ to thesi by means of so-cdled "pull. When preparing a bar chart scheduie for
such as btocks, boom aections, spreaders, down' menu$ w bymeans of a tablet, wtere we this project we have to specify the duration o(
trailers etc.) and create a menu which makes it select which drawingor tooiwe want to use, each defaikd task in dayq of pats OE & ay
easy to acces5 the standard drawings you me- It c m take saveral months &obuilt up p u r (OSd = tel!a day, 3h = 3 beurs). By making the
at@.To mate a riaging study, we must draw a own iibraryof standard drawings for yaur fleet taste dependent on each ofher, the program,
top view and side view of the crane and vary When buying a new eranc yoa can mate life a in this case Microsoft Project 4.0, automax-
the boom lengtti. slewina mgie and counter- lot esiet, and cut down on a lot of work. bv cally caladates at what date and time the o&
, weight cortfiguratton. asking the crane manufacturer t- suppiy gen- task c m start. It aiso altows you to define what
'
Take as an aample a Demag TC-3900 lattice era1 arrangemeat drawinas of the machine on dav of the week and hours of the day are
boom crane, The most efficient way to draw floppy disk. The manirfacturerprobably used worked.
tKis crane te to build it up from essential non- a CAD system to design the c m e so this We cannot here describe dl the details f.
ehangsablepark $uch as: sfiould oot be a probtem. har ia mind that ywi these programs. We c m only advise you to try
Lwer carbody with autrigger base. only need the outline of the structure, not the them and to study the manuals: you wifl dis-
Upper carbody without counierweight. construction details. cover ertonmus possibttities. ff aothiag more,
it wil1 certainly give your bids a professional
PROJECT PLANNING appearanee.
Another very usefu! tooi in project work is a
Planning Program. There is a large variety of
programs avaLla.ble,such as Macrosoit Project,
TimeLioe. On Target etc. Most of these are
operated under Windows and make an ideal
tooi to create Bar Chart Plarming Scheduies or
Netwerk Planning Schedules. Many cao aiso be
used br cost calcuiatioas bv aliocating unit
ofaload is an essentialskil1for any yger.
Richard Krabbendam shows how ii is done.
hom the Ieft hand edgejs thus calculated fmm: culating theweight and C of G of more complex
CoinpositeC of G shapes, such as a pressure vessel. The first
= total mo~iant/toiaIweight thing to do here is calculate the weight of the
= 142/36 vessei, which means we have to know the
a3.944metres&om leftedge of the load materiai used, the plate thickness and the total
The calculation can &o be ased to deter- volume of material.
mine the posftion of the C of G atong the Y-ais The pfate thickness of a column usualiy
@ving the hcight of the C of G) or dong the Z- varies dong its length, depending w the
a i s (into the paper, assuming the object is design. The column basically consists of cylin-
three dimenstonal). ders, conical shaped zones and top and bot-
The Same prtnciples cm be applted in cal- torn ends. The individual weights of these ca11
34
I N T E R N A T I O N A L C R A N E 5 JUHE 1 9 9 3
be calalated bv multipiying the matertal vol-
urnewith its specific density. For the column in
F i i e 2 we would use the followingequations:
Weight of sphdcal head of column
[ " v ~ x ( ~ I ~($-r,?]
@ x XP (=volumexdensity)
Weight of cyndricai part of column
~[iixhx(r~-r~~Jxp
Weight of coTiieal part of column
= 1/3xnxhx(R2-Rf + r/-r;+ (r,xRJ-(r,x
R ~ X P
in which
r outside radius of column or sphericd head
arsmaflest radius of eone(=b)
r, = insde radias of column or spherical head
or smallest radius of cone Wj
R. = outside radlus ("argest sideza) of conical
part
= insideradius (lxgest stde~a)of conkaipart
p = (iensity of matetiai (eg,steel = apprcx 7800
WW^
We eau now calculate the weight of a c h
individuai pact. If the load is symmetrical,theC
of G of eaeh section wlll be on the centreline
and in the middie. The C of G of the sphericai
part {top of column) is Iocated approxiroately
0.4244 xr trom ttie tangent line. (Sec Figure5.1
ff the $kirt of the column bas a w& thick-
nes5 of 20 millimetres, the first cylindtical part
a thicisness of 30 militoetres, the conieal
shaped part 30 millimetres and the top section
15caiilimetres, tben the weights of all sections
eau be calculated as shown io Figures 2 and 3
and Table l.
The C of G location of a tonical shaped transi-
Bon zone Is:
ex= h/3 x ((a + 2b)/(a+b))
roeasawi sway (rooithelargest diameter of the
coae. In thfs fomyla, a = largest diameter of
cone. h = height of coneand b s smallest diame-
ter of the cone. (See Figure 5.) Wfaen we have
calmlated the weight of all sections you cao
calculatethe composlte C of G of thecolumn by
wng the moment fomula a s before. To be
exact we should alm take into account the indi-
vidual we'ightsof the transport saddles a d als0
the liftinglugsat the top tangent lie.As cm be
scan kom Figure 3 and Table l, we have allo
cated 4 tonnes for each transport saddie aad
0.2 tonnes for the WOHfting lugs. M &ere are
any ether accessories atlaehed to the column,
such as nozzles. piping etc, then these s h o M
be taken into account as well. mode, we must ensare that both s h g s are
through the hook. (See FIgure 4 again.) We al1
BENEATH THE HOOK know &is exereise: the load is lifted and does positioneel at equal distances either side of the
Wefl aload is iiftedbya c m e the C of C atw~iys not stay horizontal. Ta make swe that the ioad C of G. We also have to usesHngs that are long
hangs verttcally beneath the hook. K teC of G stays horizontal when lifted, we either change enough to ensure that they cannot slip, and to
is nat unda"the hook whea ft is first tiked.Uien the lift point position of ons of the slings or ensure that the angle with the horizon is
tbdoad wil1tilt untx it is. (s% Figu~4). lengthen or shortea ene CA the slings in such a acceptable Ag& ustng the moment fomula
This can be a usefuf way of locating the C of way that the C of G i s exactly under the hook we cm calculate the load on each transport
G of a load in the field. We huw that the C of G whenwe liftthe load. saddle, that is, 125 tonnes on saddte l and 73
is tocated somewhere along the verticai line K we lift our 188 tonne column in beRy ding tonnes on saddie2. Sec Figure 4.
35
I N T E R N A T I O N A L C R A N E S JUNE 1 9 3 %
This artiele is riot witten to extrerndy sure about what kas happmed &en The.supervisor in charge of cornpany A
show anyonein & bad light. yw are better to settie at a wtdn tmount instructed the trarispartation crew of compaiit
It describes what caused tban to continue with the case and find yuur- B to set the trailer in aso-cdled +oint susperi-
the Bpping over of a 12&e- s& havingto b r alf the cos@. $ton syxiteni, as advisai in the trailer mamita6
line piaxonn trailer loaded turer's manual for loads with high ceatre
with a 208 tonne reactor, fa ISSUES gravin'.
describing the accident, One party, let's cdtbem "A*, had accepted the supervisor also tastniet& E'sJrailer
our mam purpose is to order to transport &e reactor from Belgium fo operator io me a spirit tevel dwing a~ phasei
InBningham, The Sorth Sea erosstog went oi the transport opeiation in order to dosel$
aware of what cm go wrong and what are the smootbly and on a beautiful mornhg fa August monitor the horizontal ievel of the trailer bek
legal consequencesof au acddenL the reactor was relied off from the barge oato during all times and tl necessaq to compen-f
The accident described here happen& in the Ismsxngham Do&. This roll-off operation sate the level of the trailer bed wth
August 1988 and a final verdict as to the c w e and the transport fraai the doch to thejobsite hydraulcsuspension systeia. t,
oi the accident was &en by the High Cotirt, was subcontracted to a local baulage contrac- On the request of lts dient,company~had
Londen, in Marcb 1996, almost eight years tor, company "B". iwred the reactor agafast darnage durtag
later. Fortanately tbere were ao injuries to per- transportation, The insuraace company fom@
sound. oniy damage to the reactor tosalation tbat the wuse of "he accident was operator'$
and Ereproofing. aegligence on the part of compaay B, sa'
daliaeti the cost of the accidentto B.
? Party B rejected the claim and said thy
A 28 metre tong, 5.8 metre diameter reactor, company A's supervisor @d fSvea ?&e wo
weighing 208 tonnes, was loaded on a 3 metre iristructions and tbat the traite- should have
f
wde t2 &e-line Scheuerie platformtrailer and been set in a 3-point suspension systm rather
on its way from the Satmingharo Doch to ts than a 4point suspension $ysteai. Til
final destination at anearbyoii refi~ery, dairaed that the Jevefaess of tbe traileron aT i
The total distance kom the do& to the point suspension system could not he co?
refiner? was ahaast 7.8 kifometres. After In
trofled, thereby causiug the load to tip over.
appruxhaately 6 kikometres the trailer combi- response party A ciaimed fhat the suspension
natlon xpped over while m?goxatmg a. tong system of the trailer Was not the cawe of &e
i
curve witha 2,8egree camber. accident, rather tt was &te fact that the trailer
The cause of the accident was &=&&d as bed was not lerclted when negofia- the $8
degree curve. Party B denied this axssS a B
operator's fault, as the operator had not c m -
ftensated the trafier bed to horizontal whea
negoxating the camber, It almost took B years
court case was bome.
fa order to fully undersmd what had hap-
T
and a court w & t o proef tbis. Tb&sourpartof pen& we shaiild look in more detail at
tt dl was tbat all cos& in addition to the repair hydrauk platform trailers. A platform trailer
woris: and salvage operation of the reactor, in principle consists of a rigid steel frame,in
tacladtag legal fees, teehnlcal experts and which todividual axies are mounted. &h arie
court cos&,were w e d to the party at fauill. is suspentled by a hydrauiic cylinder. (See
It prove8 once agata that tf yoa are nok Pigtn-e S .)Alt these hydraalie eyltnders arema- ff s
TOPVIEW OF TRAILER SUSPENSION SYSTEMS
BOM
f m
4 nected to each other &y mems of hydraulic the Ionger the trailer, the mare difficuit tt As this was close to the strength limitation
lies. becomes to guarantee qua1 ioad distribution of the trailer frame tt was jofafly agreed to dis-
Ey hxng iadnridual suspension cylmders on di &es. This is where the hydraBe plat- conneet &e two centare axie-flnes of &e traiier,
ft is possible to ereate suspension pointe con- fom trailer offers sa !deal soluton. By co* tbereby reduciag the bending moment to the
sisting ol two or more suspension cyltaders. pling individuai trailer units to eaeh other, trailer h m e . In essence, the reactor was
Rgure 2, tor example. shows a Spokt suspen- eittier longitudinaliy or side by side, we eau lmded on a 12 ade-tee trailer but the &e$
sfon system. The tour cyiinders at the front of create platform trailers capable of handling were grouped toto tour pohts, each conshting
the trailer are connecied together as one sus- loads ap to several hundreds a ~ even
d geveral of five asdes (one &.a = 4 tyres = l suspension
pension poiat. white the si%rear cylinders are thousands of tonnes. cyiinder). Sec Egure&.
separate@ int0 two individual suspenston Of course the hydrauk Unes betwam each By using the raomenturn lornula om cm
points aach consistiog of &ree connected trailer must be connected wilh each other and exact& caiculate the load on @achgroq of
cyfindere. a 3- or 4-point suspension system should he axies, and consequently the laad per &e,
Provided the centre of gravity of the load is created by opening and dosing the correct
placed exactiy in the centre of the trailer, each ^&v& in the hyteufic &es. The horizontal
aste wifl have the s a m load (hydra& pres- ievd of the trailer can be adjustecl as w&,
surft in each suspension point is equaT). which comes ta handywhen theroad ha$ a eer- caltipptag angle of the trailer. The trailer wil
Another @at advantageof the hydraulic plat- tain cmber. Each individual suspension point tip over when the combinsd centre of gravlty
fonntrailer is that the trailer cm be raised by can be raised or lowered by mans of the diesel of the trailer and load passes over the
means of a separate &esel (jtrivefl hydraulc driven hydraujicpanp. xppmg h e .
pump. In most cases the maximum stroke is Kext rnoirth we look fa detail at why the
limited to W millimefres. C&SE reactor tipped o w .
Thfe @drauSic: suspension systero means Lete$go back to om case. Th& 203 tonne reac-
the platform cm cope wfth uneven road sur- tor -28.6 metres long and 5 metres in diameter
iaces and stilt guarantee an equal load on each - was loaded on tiie 12 de-Ene Scheuerie
tadividual d e . See Figares l. 2 and 3. trailer. The transport ~addleswere set 12
In noa-hydraulic trailers the same end is metres apart and the saddie loads were acBng
acheved by a spring aystem or by means of on the forward and aft part of the trailer, which
swivelling rocker arms applied to each set of was composed of 2 x 6 d e l i n e s coupled
des- However. the more ades &ere are and togetber longitudi~aiBy.See Figwe 4
38
I N T E R N A T I O N A L C R A M E S OC708EK 7.9'46
n the la& &iele we
were dmMbing how
&e c o i m CBrm t0 i&
of Imperia1measurements. Foundation
oday, people are travehg more fie- dar& and make it mier to exchange plans, parts not changed is that it has such a large domestic
l
n my previous article I explained the differ- apply so-called dynamic
ence between mass (M) and force (F) and the factors, which is a safety
reasons why we need to move heavy loads margin to account for
slowly. The more abrupt a movement starts sudden shock loads.
or stops, the greater the acceleration/decelera- However, these dynarnic factors do not account the crane and ligging industry, the most
tion is, and consequently, the larger the force d for the enormous forces caused by the impact of commonly used units are for weight, volume,
be. A very unfortunate example of this theory an aircraftor a 20-storey section ofa building. b dimension andpressure.
4 factors. Although there are a lot more units, I tem as well as in the Imperial system. F i t we
will not list them al1 and only select those units, convert the area of the load spreading mat into
which are relevant to the lifting industry. I have square ket, being 2.5 m x 4 m = 10 m2 ( l m =
divided these into groups, and listed each in a 3.28 ft) = 32.80 square ket (SF). Now we con-
separate box. vert the 100 t = 100,000 kilogram (kg) into
Knowing the listed conversion factors on 220,264 pounds (Ibs) (l Ibs = 0.454 kg). 100 t
these pages one can easily convert the Imperiai load on 10 m2 = 10 t/m2 = 22,026/32.8 = 671
values into the SI units and vice versa. In the PSF (Poundsper square bot).
crane and rigging industry we are not interested With the above exarnples and conversion
in the last decimal points, so I d round off factors at hand, Imperial units can be converted
some of the units. into SI units. Be aware of mistakes as they
Just as an example, let's convert a 100 t out- are very easily made. I do not pretend to be
ligger load, spread out on a steel load spreading complete, but rather intend to shine some light
matof2.5 m x 4 m = 10m2intotheSIunitsys- on the complex matters of different units.
t
The principles l am describing here do apply for a simple
Making a Rigging Plan rigging study made by hand, as wel1 as fora detailed study
prepared with a sophisticated CAD system or other modern
A rigging plan is a necessity for a safe and wel1 executed techniques.
lifting job. In the Netherlands, the civil Industry has Before we start drawing we must think of what we are going
recognised the importance of a wel1 prepared rigging plan to put on paper and in what format. In other words how do
and has appointed the SBW (Training centre for Infra we make the lay-out of the rigging study. Does the plan view
structure) in Harderwijk, the Netherlands for training crane and side view fit on the Same piece of paper? What scale are
supervisors the basics of how a rigging plan should be we going to use? Will we use the paper in portrait (vertical)
prepared. or in landscape (horizontal) mode? Where do we place the
l realise that with today's computers most of the rigging logo of the drawing, in which we identify the drawing number
studies can be prepared with software packages available on and describe what project we are drawing, as wel1 as the
the market and tailor made to specific crane types. These scale the drawing is made. So, again before we start putting
programs are of great help and there are several packages any line on paper: Think, Think and Think again.
available.
In the field though, a computer is not always available and to The lay-out of the drawing greatly depends on the project we
understand the principles of a rigging plan it is clear that the want to put on paper. l am a great supporter of a Rigging
crane supervisor should at least be able to prepare a simple plan in which we have all relevant information on one sheet
rigging plan himself with a sheet of paper, a ruler and a of paper.
1 pencil. To make things a little easier for you, let me make a list,
Simple lifting jobs do not require a lifting plan, but who are which describes what to my opinion should be in the Rigging
we to decide what a simple rigging job is and where does it plan:
start to be complicated. Pay attention to following points when preparing a
A small lift from a narrow spot at a long radius could be as Rigging plan
complicated as a big lift at a short radius with no obstacles.
LAY-OUT
Probably for a lot of people in the Industry, this article is a * Logo in right hand corner if possible
simple description of what they already know and apply in Side View and Top View on Same paper if
every days business. It is especially for those people who possible
intend to bring their operations on a higher safety level and What scale can you use best
help them in preparing a detailed rigging plan which can help Where do you place the lifting information
the operator and supervisor on the job to set the crane in the
correct position.
structures
Lift load in irorizonial
s l 3 ,
Fig.2
LOGO
,~,- The Logo should preferably be placed in the
---.-.v-
right hand corner and give information about
following points:
Tail crane WEIGHT OF RIGGING GEAR o Name of contractor that executes the job
o Name of dient and Project
o Scale:
Cap. 99.25 ton o Date:
60 Ts Spanlifl Ballast
Rad. 10.5 m; o Drawn by:
Cap. 116.50 Ts o Checked by:
ig. 1 o Drawing No.:
o Revision:
o Drawing paper format
m Of course a lot of other things could be Radius and capacity of tail crane at pick-up and
mentioned in the LOGO. but the most imoortant setting down of the load
points are listed above Length and WLL (Work Load Limit) of slings
used in the lifting project for main crane(s) as
wel1 as tail crane(s)
WLL of shackles used on the project
Lifting lug details (hole diam., trunion size etc) in
relation to shackle and sling dimensions
m Dimensions and WLL of spreader and lifting
beams
INFORMATIONABOUT THE LOAD
Specify in detail:
Weight of load in Metric Tonnes, pounds or
Short Tons
Overall dimensions of load
Location and dimensions of transport
saddleslsupport points in relation to the C. of G.
Location of Centre of Gravity of the load in
relation to the lifting pointslsupport points
Dimensions and location of lifting points in l
relation to the C. of G.
INFORMATIONABOUT THE JOB SITE
Dimensions and Elevation of foundation(s)
Size and location of foundation bolts and shim
plates
l
Fig.3 Location and dimensions of obstacles such as
but not limited to:
DIMENSIONS o Drainage and sewer pipes under gound
Dimensioning of a drawing can be in the International metric o Light and telephone poles
o High tension lines
system (SI) or in the Imperia1system. In the International
system all dimensions are in mm (millimetres; 1000 mm = o Pipe racks and underground pipelines
o Allowable ground pressure
l m ) without specifically stating the units. If other units are
used they should be mentioned. (For more information on o Surrounding structures etc.
units see my previous articles in IC of September and
November 2001). The rigging plans shown are made with Autocad drawing
In a Rigging plan the following dimensions should at least be software and show a lot of details of equipment which is not
specified: always necessary for a correct rigging plan. See Fig.4 as an
Radius and crane lifting capacity at which we example of the same rigging plan but without the details of
piek up the load (for each crane, i.e. main crane the main boom, carbody and spreader beam.
********
as wei1 as tail crane)
Radius and crane lifting capacity at which the
load is set (again for each crane)
Outrigger (crawler) base of crane(s)
Radius of counterweight (or Superlift tray, or
radius of A-frame)
Position of each crane in relation to foundations
or other land marks
Type, model or make of crane that is used
Offset of top sheave, boom length, boom width
etc.
Centre lines of load, foundations, crane(s) etc.
Dimensions and locations of obstacles, which
could interfere with the lifting of the load
Dimensions and details of load spreading mats ll
LIFTING INFORMATION
Specify in detail:
* Radius and capacity of main crane at pick-up
and setting down of the load
Preparation o f Lifting Arrangement
Step by Step
l
Things can always be that little bit better
Offshore Lifts
eave Compensation:
What is it? Who needs it?
GETS YOUR
PROJECT MOVING
Simplicity
The last, or rnaybe the first, criterion is
sirnplicity. A good arrangement is easy to
understand and to execute. Minirnise the
amount of handling: Prepare the site,
assemble all supports, rigging etc. Try to
use single motions (no slewing and hois-
ting at the Same time). Minimise the
arnount of equiprnent. Avoid re-rigging,
flame cutting and welding during the ope-
ration. Space between pins and holes must
contain sufficient rnargin. Lifting procedu-
res should always allow for stopping or
reversing at any time. Figure 4: Loss of stability
They have their own ideas, they are a bit sure of themsel-
ves, even arrogant. But those are the positivo sides of
Huisman-ltrec, based in Schiedam, the Netherlands, one
rid's ieading suppliers of hoist and transportation
systems used by the shipping industry and pipe laying
systems used by the petroleum and natura1 gas indus-
tries. "We know what the client wants, but we also know
that sornetimes it can done just that littie bit better,"
says Petro Walters the chanical Engineering
For offshore lifts the environmental conditions are less wel! controlled than lifts
with land based cranes or even shipboard cranes. Irregular waves and swell lead
t5 reduced control over crane motion. Therefore, the steel structure and drive
system of an offshore crane must be designed for higher dynamic loads than a
land based crane.
greatly reduce wear and corrosion. Lack of crane performs a certain cycle (loaded and
grease has a negative effect on service life. unloaded), a movement pattern could
occur that brings torsion in the rope. This
Twisting of lower tackle wil1 cause spinning after a certain amount
Twisting of lowertacklecouldbe caused by: of cycles. Winding and unwinding the
complete rope from the drum from time to
Improper design of tackle stability. Try time can prevent this.
using a rope with a lower torque factor or
use larger sheave diameter. The twist wil1 Waviness and bird caging
occur with and without load at larger Waviness and bird caging are both caused
tackle lengths. by torsion in the rope, but act in different
directions. Bird caging means the rope
6 Operations that cause torsion on the turns open. Waviness means the rope
lower tackle, for instance if the swivel of turns in. In both situations some strands
the hook does not function properly. The wil1 carry more load than others.
swivel torque should normally not provoke
t00 much torsion. It is important that a swirl is not applied to
the dead end connection of an ordinary
Improper rope manufacturing or instal- rope.This is only allowed for non-spinning
lation. ropes.
Broker) wires by selecting a rope less sensitive t o fati-
If broken wires are found t h e cause very gue (higher product o f strands and wires),
much depends on t h e spot where they or cut and slip practice (so t h a t t h e
occur. damage is spread over a larger piece o f
rope).