You are on page 1of 1

Documentation: Records and Reports 59

the action taken. List any other problems or abnormal of each project can be summarized in a single project report
occurrences that arose during each day, including nota- for each project being monitored.
tions of any particular lack of activity on the part of the
contractor. Note corrective actions taken.
3. Record time and the name of the contractors represen-
SPECIAL FEEDBACK
tative to whom field orders are delivered and the nature REPORTS
of the contents of the field order. Although not generally a contract requirement or even a
4. Note unforeseen conditions observed by the inspector common practice among most architect/engineer offices, a
that may cause a slowdown by the contractor. highly desirable practice would be the establishment of com-
5. Where a contractor is performing extra work because of munications feedback systems between the various field
an unforeseen underground obstruction, make a careful forces and between the field and office. Such communica-
field count of all personnel and equipment at the site tions can minimize the number of repeated errors or field
and how they are occupied. Log the number and craft of problems that often occur as a result of the traditional failure
each person idled by such work, as well as any idle of communication between the construction forces and the
equipment that would otherwise be capable of working. designers of a project.
6. Record the content of all substantive conversations held
with the contractor at the site, as well as any trade-offs, Report of Field Correction
deals, or commitments made by either party. Whenever the need for any corrective change is recognized in
7. Record all field errors made by any party at the site. the field that would require a departure from the plans and
Identify in detail and indicate probable effect. specifications as originally issued, a complete detailed report
8. Show name of the job at the head of every page. should be prepared by the Resident Project Representative and
9. Sign every diary entry and indicate your job title imme- submitted to the project manager for evaluation by the design
diately under the last line of entry on each days report. and specifications departments to see if the problem can be
This will preclude claims that additional wording was prevented in the future by design or specifications changes.
added later. A convenient document for this purpose is illustrated in
Figure 4.9. It provides for the necessary information needed
by the office forces in their evaluations and possible correc-
WHO SHOULD MAINTAIN tions, if merited. The report should be in sufficient detail to
DIARIES AND DAILY allow the engineer or architect to understand the problem,
REPORTS? make a determination, and issue instructions to the field
personnel. This document is intended as a source of infor-
A construction diary should be kept by every individual mation only and must not be used as an authorization to
involved in the project. The Daily Construction Report, by perform work nor as a change order. Wherever changes are
comparison, is prepared and submitted only by the Resident required, the normal procedures for accomplishing such
Project Representative, utilizing the Inspectors Daily Record of changes within the terms of the contract must be observed.
Work Progress reports submitted by each of the inspectors as The document should do the following:
an information source. These interim inspectors reports serve
also as a check of contractor work progress when it becomes 1. Identify the problem. Indicate why originally specified
necessary to review the contractors partial pay request. construction is not recommended.
2. Offer a solution. Describe in detail the recommended
change or changes that are suggested.
DOCUMENTATION OF 3. Indicate whether the case appears to be an isolated one or
INTERMIT TENT INSPECTION whether it appears to be a general condition that could be
Sometimes a project representative is responsible for moni- improved by changing specifications or drawings.
toring the construction of several smaller projects instead of Whether it will facilitate an understanding of the prob-
serving as a Resident Project Representative on a single, large lem or its solution, the Resident Project Representative is
project. In such cases, the project representative usually encouraged to submit sketches along with the Report of
makes intermittent field visits to each project site, as needed, Field Correction.
to meet the individual project requirements. At this point, the Resident Project Representative should
The documentation requirements for construction be cautioned. The foregoing instructions are not meant to imply
progress reporting of multiple projects by the same project that the inspector is to take any corrective action that will result
representative calls for an approach different from the tradi- in a variation from the plans and specifications without the
tional daily report. A more practical approach under the cir- approval of the architect or engineer of record. By definition the
cumstances is to prepare a weekly project report for each architect or engineer of record is that individual whose
project for which the project representative is responsible signature appears on the plans as evidence that he or
(Figure 4.8). In this manner, the activities of the entire week she, either personally or as a representative of a design firm,

You might also like