Date: 28-Sep-2012 Minutes of Meeting


Start Time: 03:15 p.m.
Present:

Mr. Gautam Rekhi


Mr. Mugundan S.
Mr. NK Menon
Mr. Prakash Narayanan
Mr. Rakesh Agarwal
Mr. Dharmendrasinh
Mr. Ashok Karthikeyen
Ms. Savita Iyer
Mr. Sunil Sahu

Some of the important points discussed in todays meeting are as follows:

Exports: Responsibility - Capt. Prakash

Vessel Thor Fortune berthed on 27th Sept at NMPT to load 26 sets of WTGs from Padu
& 4 sets of LM blades from Tuticorin. Out of this 12 Nacelles, 7 Hubs and 7 Nosecones
already loaded in vessel
To inform Mr. Kutty on acquisition of land in Kandla for storage of Blades
Coastal Movements expected 4 sets of SB46 blades from NMPT to Tuticorin next
week

Imports: Responsibility Mr. NK Menon

To follow-up with Mr. Rahul (Singapore) for MTO license on priority - to get Agency
agreement from SE Shipping
To prepare and share list of prospected customers with the below details:
o Expected Revenue
o Expected Profit
o Credit Terms
o Advance Payment Requirement, etc
NBD Update:
o MAIT Contract is in finalisation stage, expected to be awarded by Monday

Quality: Responsibility Mr. Mugundan

Below initiatives are on hold due to fund constraints:


o Plant to Port Mechanical Trailers modification for operational Cost Reduction
o All India Transport to various site Modification of enroute from the plant to
Hubli & carry out the movement directly to the site
Plant-wise Performance Matrix have been shared with the employees of Domestic and
Export team including the HODs

SE Freight & Logistics India Pvt. Ltd. Shrikant Chambers, B Wing, 2nd Floor, VN Purav Marg, Chembur, Mum - 71
Domestic Transportation: Responsibility Mr. Dharmendrasinh

WTGs Transit time specified in the SLA been revised


Penalty clause to be included as an Addendum in SLA 2012-13 which are as follows:
o Damages below 10,000/- to be deducted from vendors invoice where there is
complete negligence by the service provider
o Transportation cost for sending the damaged FGs for repair to the nearest
plant to be borne by the vendor
o Above points are to be conveyed to the transporters
Route survey of priority sites Baroda (Import NBD), Wilturi completed. Modification
not in SEFLI scope

Finance: Responsibility Mr. Rakesh Agarwal

To convey vendors on reconciliation of their accounts as depicted in SEFLI accounts to


avoid backdated entries
To reconfirm with vendors & settle the vendor invoices received with revised (reduced)
rates and book the cost in accounts

New Business Development: Responsibility Mr. Gouranga Basu

Updates:
o EMCO 2 Trafo from Mumbai to Mirza, Assam has been lifted & are in transit
expected to reach Kolkata in last week of October
o GE Power Contract awarded for movement of Transformers for Pan India
from Chennai & Hyderabad. Movement expected in 1st week of Oct.
o EMCO (CORE) 2 Trafo lifted on 26th Sept, one for Punjab and the another for
Burhwal
o Sarika Enterprises 1 movement from Kolkata to Sorang, Material to be
lifted tomorrow
o Voith Rongnichu to Bhasmay, Vehicle to be placed tomorrow
o AREVA T&D RFQ already floated, movement expected in Nov / Dec12

Human Resource: Responsibility Ms. Savita Iyer

To interview & appoint 4 priority vacant positions for Chennai & Hyderabad location by
next week
To start the recruitment process for the following positions in NBD:
o High priority 1 Loading supervisor & 1 Staff at Chennai by next week
o High priority 1 Loading supervisor & 1 Staff at Hyderabad by next week
o A Marketing Manager for Surface Transportation reporting to Mr. Basu
o A dedicated Marketing Manager for Freight Forwarding

Meeting adjourned at 04:00 p.m

Prepared by : Sunil Sahu