You are on page 1of 63

Questions 1-200

1) You have started a hand-made dolls business, Pretty Dolls and hire a team to make your
dolls. You sign a contract to pay them for their costs and in addition, a considerable amount
if they deliver all the dolls before the beginning of the holiday season. The team did deliver
the dolls to your satisfaction but their costs went over the initial estimates by 20%. You
decide the share the overages with the seller.
This is an example of:
A. Cost Plus Fixed Fee Contract
B. Cost Plus Incentive Fee Contract
C. Cost Plus Award Fee Contract
D. Time and Material Contract

2) If for a remodeling project, the estimates are:


Optimistic estimate: 2 days
Pessimistic estimate: 6 days
Most likely estimate: 4 days

What is the expected duration using the triangular distribution?


A. 6 days
B. 2.6 days
C. 2 days
D. None of the above

3) Your company plans to install an employee satisfaction tool to gather employee feedback.
It has the resources it needs to create the tool in-house. As the project manager, you
conduct the make-or-buy analysis. Since the members are assigned to other projects and
are unavailable for the employee satisfaction tool creation you decide to buy.
Which of the following are not true about the buy decision?
A. You may decide to purchase the tool from outside
B. Leasing the tool from outside is a possible option
C. Support costs of purchasing the tool from outside shouldnt be included in the buy
decision as they are indirect costs
D. You may decide to get an external vendor to create the tool for you

4) When looking for contractors for your home remodeling project, you narrowed your list
down to three contractors A, B, and C. You checked online reviews from other customers
and felt that A might be suitable for your project. You called and talked to all the contractors
and finally decided that B would be the best fit based on the information he provided. Which
technique influenced your final decision?
A. Reviewing
B. Meetings
C. Expert judgment
D. Market research

5) Prospective sellers have submitted bids based on your statement of work. You notice that
seller 1 has submitted a bid of $100,000, seller 2 has submitted a bid of $120,000, and
seller 3 has submitted a bid of $90,000. However your estimate of costs was $500,000.
Which of the below cannot be reasons for this huge difference between seller estimates and
your estimate?
A. Procurement statement of work was ambiguous
B. Sellers misunderstood buyers requirements
C. Sellers failed to respond to the entire statement of work
D. Bidder conference was effective in answering suppliers questions

6) Project manager A prepared the stakeholder management plan and published it on the
teams wiki site. One of the stakeholders who was identified as being resistant to the project
came across that information and was upset. Project manager A was not:
A. Aware of the sensitive nature of the stakeholder management plan
B. The confidentiality of the stakeholder management plan
C. Taking appropriate precautions regarding distribution of this information
D. Asking stakeholders to sign a non-disclosure agreement before viewing the stakeholder
management plan

Answer choices:
1. A, B
2. B, C
3. C, D
4. A, C

7) You are a project manager managing a project that automates report creation. Currently,
reports are being manually created by analysts. Your project will create a portal where the
reports will be automatically created. This has created job insecurity in the analysts and
their supervisors who will have to test and approve the reports you create. You identify this
concern and have meetings with the analysts and supervisors, explain the benefits the
project will bring, show some opportunities where the analysts time can be better utilized
by supervisors on alternate analyses, and how the supervisors can present more accurate
data free from human errors to upper management thereby increasing their reliability. After
a few meetings, the analysts and their supervisors like your project and are happy to work
with you on making your project successful. Which of the below have you done?
A. Facilitate consensus toward project objectives
B. Influence people to support the project
C. Negotiate agreements to satisfy the project needs
D. Modify organizational behavior to accept the project outcomes

8) You are managing a time-sensitive project and getting your deliverables from a supplier.
Which of the below is a strategy to manage potential risks to schedule due to supplier
delays/failure to deliver?
A. You draft an agreement with the seller detailing implications on him if theres a delay in
delivering products
B. You have a back-up supplier
C. You buy insurance to compensate for overruns due to delay
D. In the worst case, you plan to drop the project

Answer choices:
1. A
2. B
3. All of the above
4. None of the above

9) One of your test team members identified a defect and confirmed that a report that was
built for one of the customers requirements would not conform to stakeholder expectations.
Which of the following is false about this failure?
A. It involves an internal failure cost
B. The failure cost is called cost of non conformance
C. The failure cost is called cost of poor quality
D. There is no cost associated with a failure identified by the internal project team

10) Car manufacturer ABC manufactured cars which were sold to a lot of customers.
Customers soon started complaining that the sun visors didnt work. ABC promised to fix
this under warranty. The cost incurred by ABC is a:
A. Prevention cost
B. Appraisal cost
C. Internal failure cost
D. External failure cost

11) Customers have complained about support quality. You collect data and put together the
Pareto chart shown below. Resolving which of the below will solve support quality issues
using the Pareto principle?

A. Long wait times, Too many questions before getting to the operator, Impolite customer
service rep
B. Long wait times, Incompetency of staff, Too many questions before getting to the
operator
C. Impolite customer service rep, Poor communication, Call gets dropped during high traffic
times
D. Long wait times, Poor communication, Incompetency of staff

12) During a web applications load test, the following data was collected at each failure:
Time between failure 1 and failure 2=120 seconds
Time between failure 2 and failure 3=90 seconds
Time between failure 3 and failure 4=70 seconds

What is the Mean time between failures?


A. 120 seconds
B. 60 seconds
C. 10 seconds
D. 70 seconds

13) The control chart below indicates that:


A. The process is stable
B. Corrective action should be taken as the process is out of control
C. Variations are in the normal range
D. No corrections are needed to the control parameters

214) You are designing a website that sells cooking books. Which of the below would be the
best technique to show the navigation between web pages when selecting a book, adding to
cart, and placing an order?
A. Storyboard
B. Questionnaire
C. Benchmarking
D. Observation

15) Use the following diagram to answer the question below:

The total float on paths ABCDE and AHIDE is:


A. 6d
B. 0d
C. -6d
D. Cannot be determined with the information provided

16) You are working with a supplier on a fixed price landscaping contract costing $10,000.
Some way through the project, you decide that you really want to add a fountain to your
front lawn. Your contractor agrees but says it will cost an additional $500. This is an
example of:
A. Fixed price contract
B. Time and materials contract
C. Cost reimbursable contract
D. Hybrid contract

17) In the below schedule network diagram, what is the latest finish date for activity A
(assume that there are no holidays)?

The diagrams use the below code:


ES=Early start
EF=Early finish
LS=Late start
LF=Late finish

A. Apr 6
B. Apr 7
C. Apr 10
D. Apr 9

18) Resource A and B are allocated as follows for a 4-day project:


A:
Day 1: 16 hours on task 1
Day 2: 8 hours on task 2
Day 3: 8 hours on task 3
Day 4:
B:
Day 1: 8 hours on task 1
Day 2: 16 hours on task 2
Day 3: 8 hours on task 3
Day 4:

A typical work day is 8 hours.


Which of the below can be done to level resources? Choose the best answer.
A. Allocate resource A for 8 hours on day 1 for task 1, for 8 hours on day 2 for task 1, for 8
hours on day 3 for task 2, and for 8 hours on day 4 for task 3
B. Allocate resource B for 8 hours on day 1 for task 1, for 8 hours on day 2 for task 2, for 8
hours on day 3 for task 2, and for 8 hours on day 4 for task 3
C. Keep current resource allocations and offer day 4 off
D. Do nothing

Answer choices:
1. A and B
2. B
3. A
4. C

19) Your projects duration needs to be shortened. So you ask your team to work weekends
and hire additional resources to help shorten the schedule. This could:
A. Increase risk
B. Increase cost
C. Work only for critical path activities
D. Level resources

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

20) Using the below information, calculate the EAC forecast for ETC work considering both
SPI and CPI factors.
Actual cost=$1000
Earned value=$900
Budget at completion=$1200
Cost performance index=1.2
Schedule performance index=0.9
EAC is:

A. $1000
B. $2944.44
C. $1277.77
D. $700
21) You hire a team to build your website. You offer to pay them for the development,
hosting, and other costs they incur for performing the work and in addition, a considerable
amount.
This is an example of:
A. Cost Plus Fixed Fee Contract
B. Cost Plus Incentive Fee Contract
C. Cost Plus Award Fee Contract
D. Time and Material Contract

22) You have started a hand-made greeting card business, PaperGreet and hire a team to
create your greeting cards. You sign a contract to pay them for their costs and in addition, a
considerable amount if they deliver all the cards before the beginning of the holiday season.
This is an example of:
A. Cost Plus Fixed Fee Contract
B. Cost Plus Incentive Fee Contract
C. Cost Plus Award Fee Contract
D. Time and Material Contract

23) Risk audits:


A. Are the responsibility of the project manager
B. Are conducted only by project manager and his team
C. Can be done during regular project review meetings
D. Examine and document the effectiveness of risk responses in dealing with
identified risks and their root causes

Answer choices:
1. A, B, C
2. B, C, D
3. C, D, A
4. D, A, B

24) You have started a hand-made paper business and hire a team to make paper. You sign
a contract to pay them for their costs and in addition, a considerable amount if they deliver
all the paper rolls before the beginning of the holiday season. The initial estimate of costs is
$5000.
The team did deliver the paper to your satisfaction but their costs went over the initial
estimates by 20%. You decide the share the overages with the seller at a pre-determined
rate of 70/30.
This is an example of:
A. Cost Plus Fixed Fee Contract
B. Cost Plus Incentive Fee Contract
C. Cost Plus Award Fee Contract
D. Time and Material Contract

25) You have started a hand-made paper business and hired a team to make paper. You
sign a contract to pay them for their costs and in addition, an additional $1000 if they
deliver all the paper rolls before the beginning of the holiday season. The initial estimate of
costs is $5000.
The team did deliver the paper to your satisfaction but their costs went over the initial
estimates by 20%. You had also included in the contract a provision to the share the
overages with the seller at a pre-determined rate of 70 (buyer)/30 (seller).
The final amount you have to pay the seller is:
A. $6000
B. $6700
C. $700
D. $5700

26) You have started a hand-made paper business and hired a team to make paper. You
sign a contract to pay them for their costs and in addition, an additional $1000 if they
deliver all the paper rolls before the beginning of the holiday season. The initial estimate of
costs is $5000.
The team did deliver the paper to your satisfaction but their costs went over the initial
estimates by 20%. You had also included in the contract a provision to the share the
overages with the seller at a pre-determined rate of 70 (buyer)/30 (seller).
The amount the seller has to bear for the overage is:
A. $6000
B. $300
C. $700
D. $5700

27) You sign an agreement with a building contractor to build your house. You will
reimburse all his costs but pay the majority of his fee based on subjective determination of
his performance. This is an example of:
A. Cost Plus Fixed Fee Contract
B. Cost Plus Incentive Fee Contract
C. Cost Plus Award Fee Contract
D. Time and Material Contract

28) Which of the following is not true about T&M contracts?


A. Combine aspects of cost-reimbursable and fixed-price contracts
B. Used when a precise statement of work cannot be prescribed quickly
C. Can increase in contract value as if they were cost reimbursable Contracts
D. Unit labor or material rates cannot be preset by the buyer and seller

29) Obtaining seller responses, selecting a seller, and awarding a contract are done in:
A. Plan Procurement Management
B. Conduct Procurements
C. Control Procurements
D. Manage Procurements

30) Your company plans to install an employee satisfaction tool to gather employee
feedback. You as the PM, estimate that there are resources available in-house to create the
tool at a cost $20,000. Alternately the tool could be bought outside for $15,000. But your
project has a budget of only $5000. You are considering leasing as an option. Which
technique are you using?
A. Negotiation
B. Make-or-buy analysis
C. Expert judgment
D. Budgeting

31) As a PM working on a contract document for a supplier, you are asking the legal
department to review the terms and conditions so any gaps can be addressed. Which
technique are you using?
A. Negotiation
B. Make-or-buy analysis
C. Expert judgment
D. Budgeting

32) When looking for contractors for your home remodeling project, you narrowed your list
down to three contractors. You checked online reviews from other customers and finally
decided on one of the contractors. Which technique did you use?
A. Reviewing
B. Make-or-buy analysis
C. Expert judgment
D. Market research

33) Procurement performance reviews, payment systems, and claims administration are
tools and techniques for which of the below?
A. Control procurements
B. Conduct procurements
C. Manage procurements
D. Close procurements

34) Which of the below can be guided in the procurement management plan?
A. Coordinating procurement with other project aspects, such as scheduling and
performance reporting
B. Handling the long lead times to purchase certain items from sellers and coordinating the
extra time needed to procure these items with the development of the project schedule
C. Handling the make-or-buy decisions and linking them into the Estimate Activity
Resources and Develop Schedule processes
D. Procurement metrics to be used to manage contracts and evaluate sellers

35) As a PM, you prepare a document for your resource vendor that lists the number of
resources needed, the work location, and the duration of the contract. Which document are
you preparing?
A. Activity resource requirement
B. Procurement Statement of work
C. Source selection criteria
D. Procurement policy

36) You are managing a road repair project. Budget is set at $100,000 and the supplier
decision will be made based on who bids lowest. You prepare a procurement document to
solicit proposals from prospective sellers. Which of the following are alternate names for the
procurement document?

A. Bid
B. Quotation
C. Tender
D. Proposal

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

37) You are managing a road repair project. Budget is set at $100,000 and the supplier
decision will be made based on who bids lowest. You prepare a procurement document to
solicit which of the below from prospective sellers (choose the best answer)?

A. Bid
B. Quotation
C. Tender
D. Proposal

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

38) You are managing a road repair project. Budget is set at $100,000 and the supplier
decision will be made based on who bids lowest. You prepare a procurement document to
solicit proposals from prospective sellers. Which of the following are possible ways to issue
the procurement request?

A. Publication of the request in public newspapers


B. Publication of the request in trade journals
C. Publication of the request in public registries
D. Publication of the request on the internet

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

39) You are managing a road repair project. Budget is set at $100,000 and the supplier
decision will be made based on who bids lowest for the materials and delivery. Four sellers
bid for the contract and the materials requested are standard and readily available from all
of them.
A. Seller A bids at $80,000 and has a good reputation.
B. Seller B bids at $90,000 and has the best reputation among all bidders.
C. Seller C bids at $95,000 and doesnt have a good reputation.
D. Seller D bids at 77,000 and is a new bidder who has just started his business.
Which of the sellers will you select for awarding the contract?

40) Your prospective seller claims that he has always exceeded performance requirements
and has had only happy clients in the past. But prior customers that verified the sellers
work experience and compliance with contractual requirements did not provide positive
feedback about the seller. Which of the below source selection criteria failed?
A. Warranty
B. Past performance of sellers
C. References
D. History

41) You post an ad inviting ghostwriters to apply for your writing project that involves
writing a book with your ideas. You want to own copyrights for the book. One of the
conditions is that the ghostwriter has to sign a Work for hire agreement which states that
you will pay the writer for their work but they cannot claim any ownership or copyrights of
the work. Out of the writers that applied to your project, only one was willing to sign the
Work for hire agreement. You are covering which of the following source selection criteria?
A. Technical capability
B. Intellectual property rights
C. Proprietary rights
D. History

42) As a PM, you are performing make-or-buy analysis on whether to create a software tool
in-house or procure it from outside. Which of the below do not influence make-or-buy
decisions?
A. Core capabilities of the organization
B. Value delivered by vendors meeting the need
C. Cost-free estimating of vendor capability
D. Capability internally compared with the vendor community

43) As a PM of a construction company, you invite prospective sellers to meet with you and
address their questions before they submit a bid. You collect questions from the bidders and
incorporate responses as amendments to procurement documents. This meeting cannot be
called a:
A. Bidder conference
B. Verbal conference
C. Contractor conference
D. Pre-bid conference
44) Which of the following is/are not true about bidder conferences?
A. They are used to conduct open bidding from prospective sellers to ensure buyer gets the
best offer
B. They are used to clarify prospective seller questions to ensure common understanding of
buyers requirements
C. They are meetings between buyer and prospective sellers after submitting a bid
D. Each prospective sellers question is answered by the buyer and kept confidential

Answer choices:
1. A, B, D
2. B, C, D
3. A, B, C
4. A, C, D

45) Which of the following is not true about agreements?


A. They are informal documents between a buyer and seller
B. They are mutually binding
C. They can be simple or complex
D. They may reflect the simplicity of the effort

46) You are conducting procurements for your project. Which of the below tools and
techniques can you use? Choose the best answer.
A. You meet with prospective sellers to explain your requirements and answer any questions
the sellers may have
B. You ask members of your companys legal team to evaluate sellers proposals
C. Your company has a list of potential sellers. But you post ads online inviting other sellers
D. You hire a professional estimator to estimate costs for your statement of work

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

47) A procurement agreement has been prepared that includes terms and conditions and
other items that the seller has to provide. Whose responsibility is it to ensure that the
agreement meets the needs of the project and abides by the organizations procurement
policies?
A. Project manager
B. Seller
C. Project management team
D. Buyer and seller

48) A procurement agreement can also be called:


A. Understanding
B. Contract
C. Sub contract
D. Purchase order

Answer choices:
1. A
2. B
3. C
4. All of the above

49) Which of the below is not true about a contract?


A. It is a mutually binding legal agreement
B. It is a legal relationship subject to remedy in court
C. Obligates seller to provide specified products and buyer to pay seller
D. Final contract language may not reflect all agreements reached

50) A contract has been prepared between your company (seller) and the client that
includes the options A-D below. Which of these can the buyer not specify in the contract?
A. Payment to you will be made 30 days after you bill the client
B. Your resources will be evaluated every quarter for performance on the project
C. Roles and responsibilities for your resources on the project
D. Selection criteria that was used to choose you for award of contract

51) During procurement award, the buyer specifies that any disputes that arise between you
and the buyer have to be resolved out of court, using arbitration. You agree. You have been
awarded the contract. The arbitration clause gets added to the:
A. Contract
B. Statement of work
C. Risk register
D. Independent estimate

52) During procurement award, the buyer specifies that any disputes that arise between you
and the buyer have to be resolved using alternative dispute resolution. You agree and have
been awarded the contract. Which of the below are examples of not examples of alternative
dispute resolution:
A. Conciliation
B. Remedy in court
C. Arbitration
D. Mediation

53) The project management processes that are applied in Control procurements are:
A. Direct and Manage Project Work
B. Control Quality
C. Perform Integrated Change Control
D. Control Risks

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

54) Which of the following is not true about agreements?


A. Include details on incentives, insurance and performance bonds
B. Can be amended prior to contract closure
C. Amendments are captured in writing
D. Can be amended with consent from buyer or seller

55) Which of the following in a contract can be changed by getting an approved change
request?
A. Terms and conditions
B. Procurement statement of work
C. Pricing
D. Descriptions of the deliverables to be provided

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

56) You are a PM collecting work performance data as part of a contract with a seller. Which
of the following will not be part of the data?
A. Statement of work
B. How far the quality standards set have been satisfied
C. Costs incurred
D. Finding out which invoices from seller have been paid

57) Which of the below is true about quality and grade?


A. A quality level that fails to meet quality requirements is always a problem, a low grade of
quality may not be a problem
B. A quality level that fails to meet quality requirements may not always be a problem, a
low grade of quality is always be a problem
C. A quality level that fails to meet quality requirements is always a problem, a low grade of
quality is always a problem
D. A quality level that fails to meet quality requirements may not always be a problem, a
low grade of quality may not be a problem

58) You spend money on the following activities during the project to avoid failures. Which
of these are costs of conformance?

A. Training costs
B. Equipment costs
C. Costs associated with the time to build the right product
D. Costs associated with documenting the processes

1. A
2. A, B
3. A, B, C

4. A, B, C, D

59) You spend money on the following activities to avoid failures. Which of these are costs
of conformance?

A. Training costs
B. Equipment costs
C. Rework costs
D. Costs for warranty work

1. A
2. A, B
3. A, B, C

4. A, B, C, D

60) Your construction project procures fancy light fixtures from a supplier. Your team
performs quality audits and identifies that the fixtures are of poor quality. The contractor
has also not complied with a labor requirement that was agreed to in the contract. Which of
the below techniques are you using now?
A. Performance Reporting
B. Work Performance Data
C. Procurement Performance Review
D. Work performance information

61) Contested changes are also called:


A. Claims
B. Appeals
C. Disputes
D. Issues

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

62) Claims are preferred to be settled by:


A. Negotiation
B. Mediation
C. Conciliation
D. Legal court

63) Which of the below is not true for early contract terminations?
A. Special case of procurement closure
B. Can result from a mutual agreement by both parties
C. Can result from the default of one party
D. Can be for convenience of the buyer if provided for in the contract

Answer choices:
1. A
2. B
3. C
4. None of the above

64) Which of the below is untrue for Close Procurements?


A. Procurements cannot be closed if there are unresolved claims
B. Addresses each contract applicable to the project or a project phase
C. Ensures that contractual agreements are completed or terminated
D. Involves administrative activities such as finalizing open claims

65) Which is the least desirable option to settle outstanding claims?


A. Negotiation
B. Mediation
C. Litigation in court
D. Alternative dispute resolution

66) The process that identifies people that could impact the project, their
interdependencies, influence, and impact on project success is:
A. Identify Stakeholders
B. Assess Stakeholders
C. Stakeholder analysis
D. Expert judgment

67) The government has initiated a project to build a dam. The houses in the construction
area will be destroyed and the residents relocated. The residents of the area resist this
initiative as they will be displaced from their native place. They:
A. Are project stakeholders
B. Are public whose interests will be affected by the execution of the project
C. Are team members
D. May exert influence over the project and its deliverables

Answer choices:
1. A, B, C
2. A, B, D
3. A, C, D
4. B, C, D

68) Which of the below are stakeholders for a project you will deliver?
A. Project sponsor
B. Your suppliers
C. Customers
D. Your organization

Answer choices:
1. A, B, C
2. A, B, D
3. A, C, D
4. All of the above

69) Which of the below models is used in stakeholder analysis? Choose the best answer.
A. Power/interest grid
B. Power/influence grid
C. Influence/impact grid
D. Salience model

Answer choices:
1. A, C
2. B, D
3. None of the above
4. All of the above

70) If one of your stakeholders has high interest in the project and high power, you should:
A. Keep satisfied
B. Manage closely
C. Keep informed
D. Monitor

71) In a power interest grid, which of the below best describes how stakeholders in the
lower right quadrant should be managed?
A. Keep satisfied
B. Manage closely
C. Keep informed
D. Monitor

72) Project meetings designed to develop an understanding of major project


stakeholders, to exchange and analyze information about roles, interests, knowledge, and
the overall position of each stakeholder facing the project are called:
A. Project team meetings
B. Status meetings
C. Profile analysis meetings
D. Stakeholder reviews

73) The main output of the Identify Stakeholders process is:


A. Stakeholder register
B. Stakeholders
C. Potential stakeholders
D. Stakeholder support

74) Which of the below information about stakeholders will be present in the stakeholder
register?
A. Name
B. Role in project
C. Location
D. Classification (Supporter/neutral/resistor)

Answer choices:
1. A, B, D
2. A, C, D
3. A, B, C
4. All of the above

75) You will be managing a project, the stakeholders of which have already worked on a
different project with Project manager A. Which of the below organizational process assets
will be helpful to you as inputs in planning stakeholder management?
A. Lessons learned database
B. Risk analysis
C. Historical information
D. Classification (Supporter/neutral/resistor)

Answer choices:
1. A, B
2. A, C
3. B, C
4. C, D

76) Which of the below are engagement levels of stakeholders?


A. Unaware
B. Resistant
C. Aware
D. Supportive

Answer choices:
1. A, B, C
2. A, C, D
3. B, C, D
4. A, B, D
77) If one of your stakeholders has low interest and high power you should:
A. Monitor him
B. Keep him satisfied
C. Manage him closely
D. Keep him informed

78) If one of your stakeholders has low interest and low power you should:
A. Monitor him
B. Keep him satisfied
C. Manage him closely
D. Keep him informed

79) Which of the below are present in stakeholder management plan?


A. Scope and impact of change to stakeholders
B. Stakeholder communication requirements for the current project phase
C. Time frame and frequency for the distribution of required information to stakeholders
D. Method for updating and refining the stakeholder management plan as the project
progresses and develops

Answer choices:
1. A, B, C
2. B, C, D
3. C, D, A
4. A, B, C, D

80) Depending upon the application area, a contract can also be called:
A. Agreement
B. Understanding
C. Subcontract
D. Purchase order

Answer choices:
1. A
2. B
3. All of the above
4. None of the above

81) Which of the below is not true about activities involved in managing stakeholder
engagement?
A. Clarifying and resolving issues that have been identified
B. Addressing potential concerns that have not yet become issues
C. Anticipating future problems that may be raised by stakeholders
D. Asking stakeholders to sign a non-disclosure agreement before viewing the stakeholder
management plan

82) Which of the below are interpersonal skills that a project manager applies to manage
stakeholders expectations?
A. Building trust
B. Resolving conflict
C. Active listening
D. Overcoming resistance to change

Answer choices:
1. A
2. A, B
3. A, B, C
4. All of the above

83) Who is responsible to ensure that procurements purchased meet needs of the project?
A. Project manager
B. Risk auditor
C. Project management team
D. Seller

Answer choices:
1. A
2. B
3. C
4. None of the above

84) The ability of stakeholders to influence the project is highest:


A. During the initial stages of the project
B. During the final stages of the project
C. Throughout the project
D. During execution phase of the project

85) Which of the below are management skills that a project manager applies to coordinate
and harmonize the group toward accomplishing the project objectives?
A. Facilitate consensus toward project objectives
B. Influence people to support the project
C. Negotiate agreements to satisfy the project needs
D. Modify organizational behavior to accept the project outcomes

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

86) A web application with many features but no defects is of:


A. Low grade and low quality
B. High grade and low quality
C. High grade and high quality
D. Low grade and high quality

87) The degree to which a set of inherent characteristics fulfill requirements is called:
A. Quality
B. Grade
C. Performance
D. Scope
88) As a design intent, a category assigned to deliverables having the same functional use
but different technical characteristics is called:
A. Quality
B. Grade
C. Performance
D. Scope

89) In the figure below, the maroon dots are considered:

Note: The black spot represents the target value.

A. Precise
B. Accurate
C. Neither precise nor accurate
D. Both precise and accurate

90) In the figure below, the blue dots are considered:

Note: The black spot represents the target value.

A. Precise
B. Accurate
C. Neither precise nor accurate
D. Both precise and accurate

91) Which of the below approaches are examples of Continuous improvement?


A. Plan-do-check-act
B. Total Quality Management
C. Six Sigma
D. Lean Six Sigma

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

92) Which of the below are maturity levels in the Capability Maturity Model Integrated
(CMMI)?
A. Initial, Managed, Defined, Quantitatively Managed, Optimizing
B. Initial, Managed, Developed, Quantitatively Managed, Optimizing
C. Initiate, Managed, Defined, Quantitatively Managed, Optimizing
D. Initial, Managed, Defined, Qualitatively Managed, Optimizing

93) Which of the below are maturity levels in the Organizational Project Management
Maturity Model (OPM3)?
A. Standardize, Measure, Control, Continuously improve
B. Standardize, Measure, Check, Continuously improve
C. Standardize, Manage, Control, Continuously improve
D. Standardize, Measure, Control, Continuously optimize

94) In the Demings cycle shown below, which of the below values best fits the? ?

A. Initiate
B. Prioritize
C. Plan
D. Standardize

95) Act in Demings cycle, belongs to which of the below project management process
groups?
A. Planning
B. Executing
C. Monitoring and controlling
D. Closing

96) Which of the below does Cost of Quality not include?


A. Costs incurred over the life of the product by investment in preventing nonconformance
to requirements
B. Costs of appraising the product or service for conformance to requirements
C. Costs of failing to meet requirements (rework)
D. Cost of the quality step to the expected benefit

97) Depending on the application area, the seller may be identified as which of the below?
A. contractor
B. Subcontractor
C. Vendor
D. Service provider

Answer choices:
1. A
2. B
3. All of the above
4. None of the above

98) Which of the below are costs of conformance?


A. Prevention costs
B. Appraisal costs
C. Internal failure costs
D. External failure costs

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

99) Depending on the buyers position in the project acquisition cycle, the buyer may be
called which of the below?
A. Client
B. Service requestor
C. Prime contractor
D. Acquiring organization

Answer choices:
1. A
2. B
3. All of the above
4. None of the above
100) In the SIPOC model, SIPOC stands for:
A. Supplier, Input, Process, Output, Customer
B. Stakeholder, Input, Process, Output, Customer
C. Supplier, Input, Process, Optimize, Customer
D. Supplier, Input, Process, Output, Customize

101) Which of the below are part of the seven basic quality tools (7QC)?
A. Fishbone diagrams
B. Flowcharts
C. Pareto diagrams
D. Checksheets

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

102) You are trying to decide whether a product should be developed in-house or purchased
from outside. You will do this in which of the below phases?
A. Plan Procurement management
B. Conduct Procurements
C. Independent estimates
D. Proposal Evaluation

Answer choices:
1. A
2. B
3. All of the above
4. None of the above

103) The control chart below indicates that:

A. The process is stable


B. Corrective action should be taken as the process is out of control
C. Variations are in the normal range
D. No corrections are needed to the control parameters

104) The control chart below indicates that:


A. The process is stable
B. Corrective action should be taken as the process is out of control
C. Variations are in the normal range
D. No corrections are needed to the control parameters

105) You are managing a landscaping project. You have received bids from multiple
agencies. Which of the below will you use to determine which bids are reasonable?
A. Agencys timelines
B. Activity cost estimates
C. Contracts
D. Agency reputation

106) Which of the following are not true about scatter diagrams?
A. They are also called correlation charts
B. They seek to explain a change in the independent variable, in relationship to a change
observed in the corresponding dependent variable
C. If correlation can be established between the dependent and independent variable, a
regression line can be calculated
D. A pattern of correlation may not exist between the variables

107) Which of the following is not true about Design of Experiments?


A. It is used to reduce the sensitivity of product performance to sources of variations caused
by environmental or manufacturing differences
B. It provides a statistical framework for systematically changing each of the important
factors, rather than changing all the factors one at a time
C. It plays a role in optimizing products or processes
D. Analysis of the experimental data should provide the optimal conditions for the product
or process, highlight the factors that influence the results, and reveal the presence of
interactions and synergy among the factors

108) 100 light bulbs were chosen from a lot of 10,000 and were tested for life expectancy
and two were found defective. This technique of quality planning is called:
A. Design of experiments
B. Force field analysis
C. Statistical sampling
D. Pareto diagram

109) Architects and engineers can use which of the following techniques to determine which
combination of aesthetics and usability will produce the most liveable home at reasonable
cost?
A. Design of experiments
B. Force field analysis
C. Statistical sampling
D. Pareto diagram

110) You are developing a reporting system for your stakeholders sourcing finance data.
Given the need for accuracy, the stakeholders have mentioned that they want your reporting
system to reconcile with the source systems finance data (revenue $) with an allowable
variation of +/-0.05%. 0.05% is the:
A. Defect frequency
B. Tolerance
C. Measurement
D. Quality metric

111) The below diagram is called:

A. Force field analysis


B. Affinity diagram
C. Process decision program charts
D. Tree diagrams

112) Which of the below are not true of quality audits?


A. They can confirm the implementation of approved change requests
B. They can proactively offer assistance in a positive manner to improve implementation of
processes to help the team raise productivity
C. They may be scheduled or random
D. They may be conducted by only internal auditors

113) As part of your dam construction project you plan to resource some of the work
externally. These components of work can be found in (choose the best answer):
A. RBS
B. WBS
C. Project management plan
D. Project scope statement
Answer choices:
1. A
2. B
3. All of the above
4. None of the above

114) Which of the following are not true about inspections?


A. They can be called peer reviews or walkthroughs
B. They are about keeping errors out of the hands of the customer
C. They cannot be done to validate defect repairs
D. The results of an inspection generally include measurements and may be conducted at a
single activity or final product level

115) Develop Project Charter has the following benefits (Choose the best answer):
A. Well-defined project start
B. Well-defined project boundaries
C. Creation of a formal record of the project
D. Direct way for senior management to formally accept and commit to the project

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

116) Which of the following is not true about a project charter?


A. Used to establish internal agreements within an organization
B. Once approved, formally initiates the project
C. Should be authored by the buying entity
D. Provides the project manager with the authority to plan and execute the project

117) Who from the below does not initiate a project?


A. Project Manager
B. Sponsor
C. Project management office staff
D. Portfolio governing body chairperson

118) Which of the below is not present in a project statement of work (SOW)?
A. Business need
B. Product scope description
C. Strategic plan
D. Request for proposal

119) Which of the below is/are true about tolerance?


A. Is an allowable variation to a metric
B. Is a project attribute
C. Is the same as measurement
D. Can be expressed as a percentage

Answer choices:
1. A, B
2. B, C
3. A, D
4. C, D

120) An organizations business needs can be based on which of the below?


A. Market demand
B. Ecological impacts
C. Legal requirement
D. Social need

Answer choices:
1. A, B, D
2. B, D, A
3. None of the above
4. All of the above

121) Which of the below are true about deliverables?


A. A unique and verifiable product that is required to be produced to complete a process
B. Tangible components completed to meet the project objectives
C. Can include elements of the project management plan
D. Capability to perform a service that is required to be produced to complete a phase

Answer choices:
1. A
2. B
3. C
4. All of the above

122) Which of the below are examples of work performance data?


A. Work completed
B. Key performance indicators
C. Actual costs
D. Number of change requests

Answer choices:
1. A
2. B
3. C
4. All of the above
323) Which of the below could change requests include?
A. Corrective action
B. Preventive action
C. Defect repair
D. Updates

Answer choices:
1. A
2. B
3. C
4. All of the above

124) Which of the below is true about requests for change?


A. They cannot be indirect
B. They cannot be internally initiated
C. They can be contractually mandated
D. They can only be optional

125) Which of the below are functions of the change control board?
A. Review change requests
B. Record change decisions
C. Delay change requests
D. Evaluate change requests

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

126) Identification and selection of a configuration item to provide the basis forwhich the
product configuration is defined and verified, labeling products and documents, managing
changes, and maintaining accountability are all part of which of the below?
A. Configuration audit
B. Configuration status accounting
C. Configuration identification
D. Configuration verification

127) Recording and reporting a list of approved configuration identification, status of


proposed changes to the configuration, and the implementation status of approved changes
is done as part of which of the below?
A. Configuration audit
B. Configuration status accounting
C. Configuration identification
D. Configuration verification
128) Ensuring that the composition of a projects configuration items is correct and that
corresponding changes are registered, assessed, approved, tracked, and correctly
implemented is done as part of which of the below?
A. Configuration setup
B. Configuration status accounting
C. Configuration identification
D. Configuration verification and audit

129) Which of the below is true about project scope and product scope? Choose the best
answer.
A. Completion of the project scope is measured against the project management plan while
completion of the product scope is measured against the product requirements
B. Product scope comprises the features and functions that characterize a product, service,
or result while project scope comprises the work performed to deliver a product, service, or
result with the specified features and functions
C. Project scope is sometimes viewed as including product scope
D. Work of the project should result in delivery of the specified product scope

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

130) Which of the below is not a component of the Project scope management plan?
A. Process that establishes how the WBS will be maintained and approved
B. Process to control how requests for changes to the detailed project scope statement will
be processed
C. Process that specifies how formal acceptance of the completed project deliverables will be
obtained
D. Process for communicating scope to stakeholders

131) Which of the below are components of the requirements management plan?
A. Requirements prioritization process
B. Product metrics
C. Traceability structure
D. Details on how requirements activities will be planned

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

132) Which of the below is not true of requirements?


A. They include capabilities to be met by the project
B. They need not be the foundation of the WBS
C. They include the documented needs of the sponsor
D. They should be recorded in enough detail to be included in the scope baseline

133) Which of the below is not a valid requirement classification?


A. Business requirements
B. Solution requirements
C. Transition requirements
D. Transactional requirements

134) Your project creates reports for your business users to run on a daily basis. The
reports take too long to load and dont satisfy the performance requirement. Which of the
following requirement classifications does performance requirement fall under?
A. Quality requirements
B. Solution requirements
C. Transition requirements
D. Project requirements

135) Your project creates reports for your business users to run on a daily basis. The
reports take too long to load and dont satisfy the performance requirement. Which of the
following requirement classifications does performance requirement fall under?
A. Quality requirements
B. Non-functional requirements
C. Transition requirements
D. Project requirements

136) Your project creates reports for your business users to run on a daily basis. The
reports should display data according to the profile of the user logged in. This security
requirement should be captured as a?
A. Quality requirement
B. Non-functional requirement
C. Transition requirement
D. Project requirement

137) Which of the below is not a tool/technique to collect requirements?


A. Interview
B. Delphi
C. Facilitated workshop
D. Focus group

138) Joint application design/development (JAD) session used in the software industry is an
example of:
A. Interview
B. Delphi
C. Facilitated workshop
D. Focus group
139) Quality function deployment (QFD) used in the manufacturing industry is an example
of:
A. Interview
B. Delphi
C. Facilitated workshop
D. Focus group

140) Short, textual descriptions of required functionality developed during a requirements


workshop are called:
A. User stories
B. User requirements
C. Meeting notes
D. Interviews

141) Which of the below is not true about user stories?


A. They describe the stakeholder who benefits from the feature
B. They describe what the stakeholder needs to accomplish
C. They describe the benefit to the stakeholder
D. They are widely used with waterfall method

142) Which of the below is/are true about facilitated workshops?


A. Help reconcile stakeholder differences
B. Improve communication between participants
C. Help discover issues earlier
D. Might take longer to define cross-functional requirements

Answer choices:
1. A
2. A, B
3. A, B, C
4. All of the above

143) A technique that enhances brainstorming with a voting process used to rank the most
useful ideas for further brainstorming or for prioritization is:
A. Nominal group technique
B. Brainstorming
C. Affinity diagram
D. Idea/mind mapping

144) Which of the below methods is used in reaching a group decision when using the
Delphi technique?
A. Unanimity
B. Majority
C. Plurality
D. Dictatorship
145) Which of the following tools and techniques to collect requirements is most effective
when audiences are varied, geographically dispersed, and where statistical analysis is
appropriate?
A. Workshops
B. Questionnaires and Surveys
C. Interviews
D. Focus groups

146) For your project, you have decided to build a working model of the final product and
revise it based on feedback from stakeholders. The tool/technique you are using is:
A. Storyboard
B. Prototype
C. Benchmarking
D. Observation

147) You are planning to acquire resources from a vendor for your software project. Which
of the below are enterprise environmental factors that can affect the planning?
A. Marketplace conditions
B. There are only few resources who are experts in the technology you plan to implement
C. Suppliers
D. Recent lay-offs

Answer choices:
1. A, C, D
2. A, B, C
3. C, D, A
4. D, B, A

148) You prepare a grid to map requirements to the deliverables adding project objectives,
owner, priority, requirement description, etc. You are preparing the:
A. Storyboard
B. Prototype
C. Requirement traceability matrix
D. Mapping document

149) Which of the below will not be in the project scope statement?
A. Description of what is in the scope of the project
B. Description of what is not in the scope of the project
C. Acceptance criteria
D. Risks

150) You have prepared a WBS but the total of the work at the lowest levels doesnt roll up
correctly to the higher levels. Which of the below rules havent been followed?
A. 100 percent rule
B. Rule of sums
C. Net sum rule
D. Total work rule

151) You are a new PM who has been assigned a project. You are trying to plan out the
schedule for the project and seek help from other members who have been with the
company for a long time and have worked on similar projects in the past. This
tool/technique is called:
A. Expert judgment
B. Historical information
C. Meetings
D. Analytical estimation

152) Which of the following is not true about milestones?


A. A milestone is a significant point or event in a project
B. Milestones can be mandatory or optional
C. Milestones are similar to regular schedule activities with the same structure and
attributes
D. Milestones have finite duration during which the activity is performed

153) Which of the below is not true about mandatory dependencies?


A. Mandatory dependencies are those that are legally or contractually required or inherent
in the nature of the work
B. Mandatory dependencies often involve physical limitations
C. Mandatory dependencies are also sometimes referred to as hard logic or hard
dependencies
D. Technical dependencies are always mandatory

154) Which of the below is not true about discretionary dependencies?


A. The project team determines which dependencies are discretionary during the process of
sequencing the activities
B. Discretionary dependencies are established based on knowledge of best practices within a
particular application area
C. Discretionary dependencies are also referred to as soft logic or preferential logic
D. Discretionary dependencies should be partially documented since they can create
arbitrary total float values and can limit later scheduling options

155) During activity sequencing, you determine that your quality assurance team cannot
test code until your development team completes development. This is:
A. A Mandatory dependency
B. A Discretionary dependency
C. An internal mandatory dependency
D. An internal dependency

156) Which of the below is not true about project schedule network diagrams?
A. It is a graphical representation of the logical relationships, also referred to as
dependencies, among the project schedule activities
B. It is produced manually or by using project management software
C. It can include full project details
D. It can have only one summary activity

157) Which of the below will not be present in a resource calendar?


A. Working days and shifts on which each specific resource is available
B. When identified project resources will be available during the project
C. Staffing policies
D. How long identified project resources will be available during the project

158) Which of the below is not an example of a resource category?


A. Labor
B. Equipment
C. Material
D. Skill level

159) You have to estimate the duration of the design activity for your project. You know that
20 drawings have to be created and it will take the architect 10 hours per drawing. You
estimate that the design activity will take 200 hours. This is an example of:
A. Parametric estimating
B. Analogous estimating
C. Three-point estimating
D. Decision making

160) If for a remodeling project, the estimates are:


Optimistic estimate: 2 days
Pessimistic estimate: 6 days
Most likely estimate: 4 days

What is the expected duration using the triangular distribution?


A. 6 days
B. 4 days
C. 2 days
D. Cannot be determined with the data provided

161) You manage a software project for a company that utilizes vendors to provide
consultants. Your project deliverables are accepted by another company. Which of the below
best describes your company:
A. Buyer
B. Seller
C. Buyer and Seller
D. Procurer

162) If for a remodeling project, the estimates are:


Optimistic estimate: 2 days
Pessimistic estimate: 6 days

What is the expected duration using the triangular distribution?


A. 6 days
B. 4 days
C. 2 days
D. Cannot be determined with the data provided

163) If for a remodeling project, the estimates are:


Optimistic estimate: 2 days
Pessimistic estimate: 6 days
Most likely estimate: 4 days

What is the expected duration using the beta distribution?


A. 6 days
B. 4 days
C. 2 days
D. None of the above

164) If for a remodeling project, the estimates are:


Optimistic estimate: 2 days
Pessimistic estimate: 6 days
Most likely estimate: 4 days

What is the expected duration using the beta distribution?


A. 6 days
B. 3 days
C. 2 days
D. None of the above

165) If for a remodeling project, the estimates are:


Optimistic estimate: 2 days
Pessimistic estimate: 6 days

What is the expected duration using the beta distribution?


A. 6 days
B. 3 days
C. 2 days
D. Cannot be determined with the information provided

166) Use the following diagram to answer the question below:

The projects critical path is:


A. ABCDE
B. AFGCDE
C. AHIDE
D. Cannot be determined with the information provided

167) Use the following diagram to answer the question below:

The projects critical path is:


A. ABCDE and AHIDE
B. AFGCDE
C. AFGCDE and AHIDE
D. Cannot be determined with the information provided

168) You are planning to acquire resources from a vendor for your software project. Your
company has a list of preferred vendors that they always send their requirements to and get
resources from. This list is an example of:
A. Enterprise environmental factor
B. Formal policy
C. Organizational process asset
D. Seller preference

169) Use forward pass calculation for the following diagrams to answer the question below
(assume that there are no holidays).
The diagrams use the below code:

ES=Early start
EF=Early finish
LS=Late start
LF=Late finish

The early start for activity D is:


A. Mar 9
B. Mar 8
C. Mar 10
D. Mar 11

170) In the following diagram, early start date is denoted in the left top corner and early
finish date is denoted in the top right corner.

Using forward pass calculation, the early finish date of activity A is (assume that there are
no holidays):
A. Mar 6
B. Mar 3
C. Mar 7
D. Mar 8

171) In the below schedule network diagram, what is the latest start date for activity C
(assume that there are no holidays)?

The diagrams use the below code:


ES=Early start
EF=Early finish
LS=Late start
LF=Late finish

A. Apr 9
B. Apr 7
C. Apr 10
D. Apr 11

172) You sign a contract with your building contractor and specify the types of materials
that should be used in building the house. The contractors men arent showing up to work
regularly and the work is delayed resulting in increased costs. But he still has to complete
the building by the date you specified in the contract. This is an example of (Choose the
best answer):
A. Fixed price contract
B. Firm Fixed Price Contract
C. Fixed Price Incentive Fee Contract
D. Fixed Price with Economic Price Adjustment Contract

173) The scheduling methods that uses buffers to account for limited resources and project
uncertainty is:
A. Critical path method
B. Critical chain method
C. Buffering method
D. Resource optimization

174) In the critical chain method, the buffer placed at the end of the critical chain is called:
A. Feedback buffer
B. Critical chain buffer
C. Project buffer
D. Resource buffer

175) In the critical chain method, the buffer placed at each point where a chain of
dependent activities that are not on the critical chain feeds into the critical chain is called:
A. Feeding buffer
B. Non-critical chain buffer
C. Project buffer
D. Resource buffer

176) Which of the following is not true about resource leveling?


A. It is a technique in which start and finish dates are adjusted based on resource
constraints with the goal of balancing demand for resources with the available supply
B. It can be used when shared or critically required resources are only available at certain
times, or in limited quantities
C. It can be used to keep resource usage at a constant level
D. It cannot cause the original critical path to increase

177) You sign a contract with your building contractor and specify the types of materials
that should be used in building the house. If the contractor can complete the building before
holiday season, you promise him a bonus. This is an example of (Choose the best answer):
A. Fixed price contract
B. Firm Fixed Price Contract
C. Fixed Price Incentive Fee Contract
D. Fixed Price with Economic Price Adjustment Contract

178) Which of the below is not true about resource smoothing?


A. It is a technique that adjusts the activities of a schedule model such that the
requirements for resources on the project do not exceed certain predefined resource limits
B. The projects critical path is not changed
C. The completion date may not be delayed
D. Resource smoothing fully optimizes all resources

179) Your projects duration needs to be shortened. The quality assurance cycle that is
usually done after development is complete is now planned to be partly done in parallel with
development to help shorten the duration. This is called:
A. Fast tracking
B. Crashing
C. Resource leveling
D. Resource smoothing

180) Your projects duration needs to be shortened. So you ask your team to work
weekends and hire additional resources to help shorten the schedule. This is called:
A. Fast tracking
B. Crashing
C. Resource leveling
D. Resource smoothing

181) Your project is to construct a huge shopping mall at the city center. It is a three year
long project and you want to sign a contract that allows final price adjustments to account
for inflation and changes in materials and labor costs over three years. This is an example of
(Choose the best answer):
A. Fixed price contract
B. Firm Fixed Price Contract
C. Fixed Price Incentive Fee Contract
D. Fixed Price with Economic Price Adjustment Contract

182) Which of the below is true about schedule baseline?


A. It is an approved version of a schedule model that can be changed only through informal
change control procedures
B. Used as a basis for comparison to planned results
C. During monitoring and controlling, the approved baseline dates are compared to the
planned start and finish dates to determine whether variances have occurred
D. It is a part of the project management plan

183) As a project manager, you prepare a schedule presentation for your management. The
presentation shows high-level timelines and is in a summary form. The schedule is called:
A. Master schedule
B. Milestone schedule
C. Detail schedule
D. Project time management plan

Answer choices:
1. A
2. B
3. Both A and B
4. Neither A nor B
184) Which of the below are examples of project schedule network diagrams?
A. Pure logic diagram
B. Logic bar chart
C. Time-scaled logic diagram
D. Milestone chart

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

185) You present your project status to management every Wednesday morning. Your
presentation states that the status of the project is green as of mm/dd/yyyy. In this case,
mm/dd/yyyy is the:
A. Status date
B. As-of date
C. Presentation date
D. Recording date

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

186) Which of the below must schedule data include?


A. Schedule milestones
B. Schedule activities
C. Activity attributes
D. Documentation of all identified assumptions and constraints

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

187) When planning your projects cost, you are referring to the published commercial
information guidelines for resource cost per hour. This is an:
A. Enterprise environmental factor
B. Organizational process asset
C. Financial database
D. Cost-estimating procedure

188) Which of the below is true about the accuracy of a projects estimate?
A. It increases as the project progresses through its life cycle
B. It decreases as the project moves forward
C. It remains the same
D. It can increase or decrease depending on other factors that influence costs

189) Which of the following is not true about analogous cost estimating?
A. It is a gross value estimating approach
B. It is used to estimate a value when there is a limited amount of detailed information
about the project
C. It uses historical information and expert judgment
D. It relies on the actual cost of the current project as the basis to estimate previous,
similar projects

190) Which of the below are required for analogous estimating to be accurate? Choose the
best answer.
A. Previous projects should be similar to current project in fact
B. Project members preparing the estimate should have the required expertise
C. Estimating should be done early in the project
D. Known differences in project complexity should not be accounted for

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

191) Which of the below include supporting details for activity cost estimates?
A. Documentation about how the estimate was arrived at
B. Documentation of assumptions and constraints
C. Indication of the range of possible estimates
D. Indication of the confidence level of the final estimate

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

192) Which of the below does project cost control not include?
A. Ensuring that all change requests are acted on in a timely manner
B. Preventing unapproved changes from being included in the reported cost or resource
usage
C. Informing appropriate stakeholders of all approved changes and associated cost
D. Bringing expected cost overruns within acceptable limits

Answer choices:
1. All of the above
2. None of the above
3. A
4. B

193) Using the below information, calculate the EAC forecast for ETC work performed at the
budgeted rate.
Actual cost: $1000
Earned value=$900
Budget at completion=$1200
EAC is:

A. $1000
B. $1300
C. $1200
D. $700

194) Using the below information, calculate the EAC forecast for ETC work performed at the
present CPI.
Cost performance index=1.2
Budget at completion=$1200
EAC is:

A. $100
B. $1000
C. $1200
D. $700

195) You hire a consultant to help with network setup and security for your online business.
Your site has just launched and you dont know how much your business will grow, how
much the traffic will be, and how much if any, maintenance work is needed. You ask the
consultant to log the hours he works per month and offer to pay him for the number of
hours he has worked based on a fixed amount per hour. This is an example of:
A. Fixed price contract
B. Time and materials contract
C. Cost reimbursable contract
D. Hybrid contract

196) Which of the below is/are true about tolerance?


A. Is an allowable variation to a metric
B. Is a project attribute
C. Is the same as measurement
D. Can be expressed as a percentage

1. A, B
2. B, C
3. A, D

4. C, D

197) Which of the below is not true about program management?


A. Program managers monitor the progress of program components to ensure the overall
goals, schedules, budget, and benefits of the program will be met
B. Program managers develop the overall program plan and create high-level plans to guide
detailed planning at the component level
C. Programs have a larger scope and provide more significant benefits
D. Program managers manage the project staff and the project managers; they provide
vision and overall leadership

198) Which of the below is not true about project management?


A. Projects have defined objectives. Scope is progressively elaborated throughout the
project life cycle
B. Project managers expect change and implement processes to keep change managed and
controlled
C. Project managers monitor the progress of program components to ensure the overall
goals, schedules, budget,
and benefits of the program will be met
D. Success is measured by product and project quality, timeliness, budget compliance, and
degree of customer satisfaction

199) Which of the below is not true about portfolio management?


A. Portfolios have an organizational scope that changes with the strategic objectives of the
organization
B. Portfolio managers create and maintain necessary processes and communication relative
to the aggregate portfolio
C. Portfolio managers may manage or coordinate portfolio management staff, or program
and project staff that may have reporting responsibilities into the aggregate portfolio
D. Portfolio managers monitor strategic changes and aggregate resource allocation,
performance results, and risk of the program

200) Which of the below is not true of a project?


A. A project need not be part of a program
B. Projects within a program may not be related through the common outcome or collective
capability
C. Success is measured by product and project quality, timeliness, budget compliance, and
degree of customer satisfaction
D. Projects have defined objectives. Scope is progressively elaborated throughout the
project life cycle

181) Your project is to construct a huge shopping mall at the city center. It is a three year
long project and you want to sign a contract that allows final price adjustments to account
for inflation and changes in materials and labor costs over three years. This is an example of
(Choose the best answer):
A. Fixed price contract
B. Firm Fixed Price Contract
C. Fixed Price Incentive Fee Contract
D. Fixed Price with Economic Price Adjustment Contract

182) Which of the below is true about schedule baseline?


A. It is an approved version of a schedule model that can be changed only through informal
change control procedures
B. Used as a basis for comparison to planned results
C. During monitoring and controlling, the approved baseline dates are compared to the
planned start and finish dates to determine whether variances have occurred
D. It is a part of the project management plan

183) As a project manager, you prepare a schedule presentation for your management. The
presentation shows high-level timelines and is in a summary form. The schedule is called:
A. Master schedule
B. Milestone schedule
C. Detail schedule
D. Project time management plan

Answer choices:
1. A
2. B
3. Both A and B
4. Neither A nor B

184) Which of the below are examples of project schedule network diagrams?
A. Pure logic diagram
B. Logic bar chart
C. Time-scaled logic diagram
D. Milestone chart

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

185) You present your project status to management every Wednesday morning. Your
presentation states that the status of the project is green as of mm/dd/yyyy. In this case,
mm/dd/yyyy is the:
A. Status date
B. As-of date
C. Presentation date
D. Recording date

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

186) Which of the below must schedule data include?


A. Schedule milestones
B. Schedule activities
C. Activity attributes
D. Documentation of all identified assumptions and constraints

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

187) When planning your projects cost, you are referring to the published commercial
information guidelines for resource cost per hour. This is an:
A. Enterprise environmental factor
B. Organizational process asset
C. Financial database
D. Cost-estimating procedure
188) Which of the below is true about the accuracy of a projects estimate?
A. It increases as the project progresses through its life cycle
B. It decreases as the project moves forward
C. It remains the same
D. It can increase or decrease depending on other factors that influence costs

189) Which of the following is not true about analogous cost estimating?
A. It is a gross value estimating approach
B. It is used to estimate a value when there is a limited amount of detailed information
about the project
C. It uses historical information and expert judgment
D. It relies on the actual cost of the current project as the basis to estimate previous,
similar projects

190) Which of the below are required for analogous estimating to be accurate? Choose the
best answer.
A. Previous projects should be similar to current project in fact
B. Project members preparing the estimate should have the required expertise
C. Estimating should be done early in the project
D. Known differences in project complexity should not be accounted for

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

191) Which of the below include supporting details for activity cost estimates?
A. Documentation about how the estimate was arrived at
B. Documentation of assumptions and constraints
C. Indication of the range of possible estimates
D. Indication of the confidence level of the final estimate

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

192) Which of the below does project cost control not include?
A. Ensuring that all change requests are acted on in a timely manner
B. Preventing unapproved changes from being included in the reported cost or resource
usage
C. Informing appropriate stakeholders of all approved changes and associated cost
D. Bringing expected cost overruns within acceptable limits

Answer choices:
1. All of the above
2. None of the above
3. A
4. B

193) Using the below information, calculate the EAC forecast for ETC work performed at the
budgeted rate.
Actual cost: $1000
Earned value=$900
Budget at completion=$1200
EAC is:

A. $1000
B. $1300
C. $1200
D. $700

194) Using the below information, calculate the EAC forecast for ETC work performed at the
present CPI.
Cost performance index=1.2
Budget at completion=$1200
EAC is:

A. $100
B. $1000
C. $1200
D. $700

195) You hire a consultant to help with network setup and security for your online business.
Your site has just launched and you dont know how much your business will grow, how
much the traffic will be, and how much if any, maintenance work is needed. You ask the
consultant to log the hours he works per month and offer to pay him for the number of
hours he has worked based on a fixed amount per hour. This is an example of:
A. Fixed price contract
B. Time and materials contract
C. Cost reimbursable contract
D. Hybrid contract

196) Which of the below is/are true about tolerance?


A. Is an allowable variation to a metric
B. Is a project attribute
C. Is the same as measurement
D. Can be expressed as a percentage

1. A, B
2. B, C
3. A, D

4. C, D

197) Which of the below is not true about program management?


A. Program managers monitor the progress of program components to ensure the overall
goals, schedules, budget, and benefits of the program will be met
B. Program managers develop the overall program plan and create high-level plans to guide
detailed planning at the component level
C. Programs have a larger scope and provide more significant benefits
D. Program managers manage the project staff and the project managers; they provide
vision and overall leadership

198) Which of the below is not true about project management?


A. Projects have defined objectives. Scope is progressively elaborated throughout the
project life cycle
B. Project managers expect change and implement processes to keep change managed and
controlled
C. Project managers monitor the progress of program components to ensure the overall
goals, schedules, budget,
and benefits of the program will be met
D. Success is measured by product and project quality, timeliness, budget compliance, and
degree of customer satisfaction

199) Which of the below is not true about portfolio management?


A. Portfolios have an organizational scope that changes with the strategic objectives of the
organization
B. Portfolio managers create and maintain necessary processes and communication relative
to the aggregate portfolio
C. Portfolio managers may manage or coordinate portfolio management staff, or program
and project staff that may have reporting responsibilities into the aggregate portfolio
D. Portfolio managers monitor strategic changes and aggregate resource allocation,
performance results, and risk of the program

200) Which of the below is not true of a project?


A. A project need not be part of a program
B. Projects within a program may not be related through the common outcome or collective
capability
C. Success is measured by product and project quality, timeliness, budget compliance, and
degree of customer satisfaction
D. Projects have defined objectives. Scope is progressively elaborated throughout the
project life cycle

Answer Key
1B
Ref: PMBOK guide 5th ed. Page 364.

2D
Ref: PMBOK guide 5th ed. Page 171.
Triangular Distribution Time estimate = (Optimistic time estimate + Most likely time
estimate + Pessimistic time estimate) / 3
(2+6+4)/3=4 which is not an option in the above list.

3C
Ref: PMBOK guide 5th ed. Page 364.

4B
Ref: PMBOK guide 5th ed. Page 366.
5D
Ref: PMBOK guide 5th ed. Page 376.

6- 4(A, C)
Ref: PMBOK guide 5th ed. Page 404.

7B
Ref: PMBOK guide 5th ed. Page 408.

8- 3 (All of the above)

9D
Ref: PMBOK guide 5th ed. Page 235.

10 D
Ref: PMBOK guide 5th ed. Page 235.

11 B
Ref: PMBOK guide 5th ed. Page 237.
Explanation: Pareto principle identifies the key issues that should be fixed to resolve 80% of
the problems. In this case, if the first 3 issues are fixed, that fixes 80% of the support
issues.

12 D
Ref: PMBOK guide 5th ed. Page 250,
https://en.wikipedia.org/wiki/Mean_time_between_failures

13 B
Ref: PMBOK guide 5th ed. Page 238.

14 A
Ref: PMBOK guide 5th ed. Page 116.

15 B
Explanation: The time taken for each of the paths is as follows:
ABCDE?5d+5d+2d+1d=13d
AFGCDE?2d+3d+1d+2d+1d=7d
AHIDE?3d+6d+3d+1d=13d
Since AHIDE and ABCDE take the same time to complete and are the longest paths, they
are the critical paths for this project. Total float is 0 on the critical path.

16 A
Ref: PMBOK guide 5th ed. Page 362.

17 A
18- 1(A and B)
Ref: PMBOK guide 5th ed. Page 179.

19- 3(A, B, C)
Ref: PMBOK guide 5th ed. Page 181.

20 C
Ref: PMBOK guide 5th ed. Page 221.
EAC = AC + [(BAC EV) / (CPI SPI)]
EAC=1000+[(1200-900)/(1.2*0.9)]=$1277.77

21 A
Ref: PMBOK guide 5th ed. Page 364.

22 B
Ref: PMBOK guide 5th ed. Page 364.

23- 3(C, D, A)
Ref: PMBOK guide 5th ed. Page 351.

24 B
Ref: PMBOK guide 5th ed. Page 364.

25 B
Ref: PMBOK guide 5th ed. Page 364.
Explanation:
Initial estimate=$5000
Incentive promised if performance conditions are met=$1000
Overage=20% of $5000=$1000
Agreement between buyer and seller was to share the departure from original estimate at a
pre-determined rate of 70 (buyer)/30 (seller).
70% of overage=$700
Seller to pay=Initial estimate+Incentive+70% of overage =$5000+$1000+$700=$6700

26 B
Ref: PMBOK guide 5th ed. Page 364.
Explanation:
Overage=20% of $5000=$1000
Agreement between buyer and seller was to share the departure from original estimate at a
pre-determined rate of 70 (buyer)/30 (seller).
30% of overage=$300 which seller has to bear.

27 C
Ref: PMBOK guide 5th ed. Page 364.

28 D
Ref: PMBOK guide 5th ed. Page 364.

29 B
Ref: PMBOK guide 5th ed. Page 355.

30 B
Ref: PMBOK guide 5th ed. Page 365.

31 C
Ref: PMBOK guide 5th ed. Page 365.

32 D
Ref: PMBOK guide 5th ed. Page 365.

33 A
Ref: PMBOK guide 5th ed. Page 356.

34- 4(All of the above)


Ref: PMBOK guide 5th ed. Page 366-367.

35 B
Ref: PMBOK guide 5th ed. Page 367.

36- 3(A, B, C)
Ref: PMBOK guide 5th ed. Page 368.

37- 3(A, B, C)
Ref: PMBOK guide 5th ed. Page 368.

38- 4(A, B, C, D)
Ref: PMBOK guide 5th ed. Page 368.
39 D
Ref: PMBOK guide 5th ed. Page 368.

40 C
Ref: PMBOK guide 5th ed. Page 369.

41 B
Ref: PMBOK guide 5th ed. Page 369.
Explanation: Copyright is an intellectual property.

42 C
Ref: PMBOK guide 5th ed. Page 374.

43 A
Ref: PMBOK guide 5th ed. Page 375.

44- 4(A, C, D)
Ref: PMBOK guide 5th ed. Page 375.

45 A
Ref: PMBOK guide 5th ed. Page 357.

46- 4(A, B, C, D)
Ref: PMBOK guide 5th ed. Page 375-376.

47 C
Ref: PMBOK guide 5th ed. Page 377-Agreements.

48- 4(All of the above)


Ref: PMBOK guide 5th ed. Page 377-Agreements.

49 D
Ref: PMBOK guide 5th ed. Page 377-Agreements and Procurement negotiations.

50 D
Ref: PMBOK guide 5th ed. Page 378.

51 A
Ref: PMBOK guide 5th ed. Page 378.

52 B
Explanation: Alternative dispute resolution is a way to solve issues, out of court.
Conciliation, mediation, and arbitration are alternative dispute resolution methods.

53- 4(A, B, C, D)
Ref: PMBOK guide 5th ed. Page 381.

54 D
Ref: PMBOK guide 5th ed. Page 378, 381.

55- 4(A, B, C, D)
Ref: PMBOK guide 5th ed. Page 381.
56 A
Ref: PMBOK guide 5th ed. Page 381.

57 A
Ref: PMBOK guide 5th ed. Page 228.

58- 4 (A,B,C,D)
Ref: PMBOK guide 5th ed. Page 235.

59- 2(A,B)

60 C
Ref: PMBOK guide 5th ed. Page 383.

61- 3(A, B, C)
Ref: PMBOK guide 5th ed. Page 384.

62 A
Ref: PMBOK guide 5th ed. Page 384.

63- 4(None of the above)


Ref: PMBOK guide 5th ed. Page 387.
Explanation: All of the above are true for early contract terminations.

64 A
Ref: PMBOK guide 5th ed. Page 387.

65 C
Ref: PMBOK guide 5th ed. Page 388-Procurement negotiations.

66 A
Ref: PMBOK guide 5th ed. Page 393-Identify Stakeholders.

67- 2(A, B, D)
Ref: PMBOK guide 5th ed. Page 394.
In some cases, residents protest and prevent the dam construction from starting hence
influencing the project.

68- 4(All of the above)


Ref: PMBOK guide 5th ed. Page 394.

69- 4(All of the above)

70 B
Ref: PMBOK guide 5th ed. Page 397.

71 C
Ref: PMBOK guide 5th ed. Page 397.

72 C
Ref: PMBOK guide 5th ed. Page 398.
73 A
Ref: PMBOK guide 5th ed. Page 398.

74-4 (All of the above)


Ref: PMBOK guide 5th ed. Page 398.

75- 2(A, C)
Ref: PMBOK guide 5th ed. Page 401.

76- 4(A, B, D)
Ref: PMBOK guide 5th ed. Page 402.

77 B
Ref: PMBOK guide 5th ed. Page 397.

78 A
Ref: PMBOK guide 5th ed. Page 397.

79- 4(A, B, C, D)
Ref: PMBOK guide 5th ed. Page 403.

80- 3(All of the above)


Ref: PMBOK guide 5th ed. Page 357.

81 D
Ref: PMBOK guide 5th ed. Page 405.

82- 4(All of the above)


Ref: PMBOK guide 5th ed. Page 407.

83- 3(C)
Ref: PMBOK guide 5th ed. Page 357.

84 A
Ref: PMBOK guide 5th ed. Page 406.

85- 4(A, B, C, D)
Ref: PMBOK guide 5th ed. Page 408

86 C
Ref: PMBOK guide 5th ed. Page 228.

87 A
Ref: PMBOK guide 5th ed. Page 228.

88 B
Ref: PMBOK guide 5th ed. Page 228.

89 C
Ref: PMBOK guide 5th ed. Page 228.

90 A
Ref: PMBOK guide 5th ed. Page 228.
91- 4(A, B, C, D)
Ref: PMBOK guide 5th ed. Page 229.

92 A
Ref: Wikipedia

93 A
Ref: Wikipedia

94 C
Ref: PMBOK guide 5th ed. Page 229.

95 C
Ref: PMBOK guide 5th ed. Page 231.

96 D
Ref: PMBOK guide 5th ed. Page 235.

97- 3(All of the above)


Ref: PMBOK guide 5th ed. Page 357

98- 2(A, B)
Ref: PMBOK guide 5th ed. Page 235.

99- 3(All of the above)


Ref: PMBOK guide 5th ed. Page 357

100 A
Ref: PMBOK guide 5th ed. Page 237.

101- 4(A, B, C, D)
Ref: PMBOK guide 5th ed. Page 237.

102 A
Ref: PMBOK guide 5th ed. Page 359

103 B
Ref: PMBOK guide 5th ed. Page 238.

104 B
Ref: PMBOK guide 5th ed. Page 238.

105 B
Ref: PMBOK guide 5th ed. Page 361

106 B
Ref: PMBOK guide 5th ed. Page 238.

107 B
Ref: PMBOK guide 5th ed. Page 239.

108 C
Ref: PMBOK guide 5th ed. Page 240.

109 A
Ref: PMBOK guide 5th ed. Page 240.

110 B
Ref: PMBOK guide 5th ed. Page 242.

111 C
Ref: PMBOK guide 5th ed. Page 245., Google.com results

112 D
Ref: PMBOK guide 5th ed. Page 247.

113 B
Ref: PMBOK guide 5th ed. Page 360

114 C
Ref: PMBOK guide 5th ed. Page 250, 252.

115- 4(A, B, C, D)
Ref: PMBOK guide 5th ed. Page 66.

116 C
Ref: PMBOK guide 5th ed. Page 67.

117 A
Ref: PMBOK guide 5th ed. Page 68.

118 D
Ref: PMBOK guide 5th ed. Page 68.

119- 3(A,D)
Ref: PMBOK guide 5th ed. Page 242.

120- 4(All of the above)


Ref: PMBOK guide 5th ed. Page 68.

121- 4(All of the above)


Ref: PMBOK guide 5th ed. Page 84.

122- 4(All of the above)


Ref: PMBOK guide 5th ed. Page 85.

123- 4(All of the above)


Ref: PMBOK guide 5th ed. Page 85.

124 C
Ref: PMBOK guide 5th ed. Page 85.

125- 4(A, B, C, D)
Ref: PMBOK guide 5th ed. Page 96.
126 C
Ref: PMBOK guide 5th ed. Page 96.

127 B
Ref: PMBOK guide 5th ed. Page 97.

128 D
Ref: PMBOK guide 5th ed. Page 97.

129- 4(A, B, C, D)
Ref: PMBOK guide 5th ed. Page 105-106.

130 D
Ref: PMBOK guide 5th ed. Page 109-110.

131- 4(A, B, C, D)
Ref: PMBOK guide 5th ed. Page 110.

132 B
Ref: PMBOK guide 5th ed. Page 112.

133 D
Ref: PMBOK guide 5th ed. Page 112.

134 B
Ref: PMBOK guide 5th ed. Page 112.

135 B
Ref: PMBOK guide 5th ed. Page 112.

136 B
Ref: PMBOK guide 5th ed. Page 112.

137 B
Ref: PMBOK guide 5th ed. Page 114.

138 C
Ref: PMBOK guide 5th ed. Page 114.

139 C
Ref: PMBOK guide 5th ed. Page 114.

140 A
Ref: PMBOK guide 5th ed. Page 114.

141 D
Ref: PMBOK guide 5th ed. Page 114.

142- 3(A, B, C)
Ref: PMBOK guide 5th ed. Page 114.

143 A
Ref: PMBOK guide 5th ed. Page 115.
144 A
Ref: PMBOK guide 5th ed. Page 115.

145 B
Ref: PMBOK guide 5th ed. Page 115.

146 B
Ref: PMBOK guide 5th ed. Page 116.

147- 2(A, B, C)
Ref: PMBOK guide 5th ed. Page 362

148 C
Ref: PMBOK guide 5th ed. Page 119.

149 D
Ref: PMBOK guide 5th ed. Page 124.

150 A
Ref: PMBOK guide 5th ed. Page 131.

151 A
Ref: PMBOK guide 5th ed. Pg 147

152 D
Ref: PMBOK guide 5th ed. Page 153.

153 D
Ref: PMBOK guide 5th ed. Page 157.

154 D
Ref: PMBOK guide 5th ed. Page 158.

155 C
Ref: PMBOK guide 5th ed. Page 158.

156 D
Ref: PMBOK guide 5th ed. Page 159.

157 C
Ref: PMBOK guide 5th ed. Page 163.

158 D
Ref: PMBOK guide 5th ed. Page 163.

159 A
Ref: PMBOK guide 5th ed. Page 170.

160 B
Ref: PMBOK guide 5th ed. Page 171.
Triangular Distribution time estimate = (Optimistic time estimate + Most likely time
estimate + Pessimistic time estimate) / 3
(2+4+6)/3=4.

161 C
Ref: PMBOK guide 5th ed. Page 355.

162 D
Ref: PMBOK guide 5th ed. Page 171.
Triangular Distribution time estimate = (Optimistic time estimate + Most likely time
estimate + Pessimistic time estimate) / 3
Since the pessimistic estimate is not provided, the expected duration cannot be determined
using the triangular distribution.

163 B
Ref: PMBOK guide 5th ed. Page 171.
Beta Distribution (from the traditional PERT technique) Time estimate = (Optimistic time +
(4*Most likely time) + Pessimistic time) / 6
For the above question, Time estimate=(2+4(4)+6)/6=4.

164 D
Ref: PMBOK guide 5th ed. Page 171.
Beta Distribution (from the traditional PERT technique) Time estimate = (Optimistic time +
(4*Most likely time) + Pessimistic time) / 6
For the above question, Time estimate=(2+4(4)+6)/6=4 which is not an option above.

165 D
Ref: PMBOK guide 5th ed. Page 171.
Beta Distribution (from the traditional PERT technique) Time estimate = (Optimistic time +
(4*Most likely time) + Pessimistic time) / 6
For the above question, the most likely estimate is not provided and hence the expected
duration cannot be calculated using beta distribution.

166 C
Explanation: The time taken for each of the paths is as follows:
ABCDE?5d+5d+2d+1d=13d
AFGCDE?2d+3d+1d+2d+1d=9d
AHIDE?4d+6d+3d+1d=14d
Since AHIDE is the path with the longest duration, it is the critical path for this project.

167 A
Explanation: The time taken for each of the paths is as follows:
ABCDE?5d+5d+2d+1d=13d
AFGCDE?2d+3d+1d+2d+1d=9d
AHIDE?3d+6d+3d+1d=13d
Since AHIDE and ABCDE take the same time to complete and are the longest paths, they
are the critical paths for this project.

168 C
Ref: PMBOK guide 5th ed. Page 362

169 C
Explanation: Both activities B and C have to be completed before activity D can start.
Activity C ends on Mar 8 (EF). Activity B ends on Mar 9 (EF). Since the latest EF is Mar 9, D
can start only on Mar 10.
170 A
Explanation: The duration of activity A is 4 days. If activity A starts on Mar 3, it will finish by
end of day, Mar 6. Hence EF date is Mar 6.

171 A

172 B
Ref: PMBOK guide 5th ed. Page 363.

173 B
Explanation: PMBOK guide 5th ed. Page 178.

174 C
Explanation: PMBOK guide 5th ed. Page 178.

175 A
Explanation: PMBOK guide 5th ed. Page 178.

176 D
Explanation: PMBOK guide 5th ed. Page 179.

177 C
Ref: PMBOK guide 5th ed. Page 363.

178 D
Explanation: PMBOK guide 5th ed. Page 180.

179 A
Explanation: PMBOK guide 5th ed. Page 181.

180 B
Explanation: PMBOK guide 5th ed. Page 181.

181 D
Ref: PMBOK guide 5th ed. Page 363.

182 D
Explanation: PMBOK guide 5th ed. Page 181.

183- 3(Both A and B)


Explanation: PMBOK guide 5th ed. Page 181.

184- 3(A, B, C)
Explanation: PMBOK guide 5th ed. Page 182.

185- 2(A, B)
Explanation: PMBOK guide 5th ed. Page 184.

186- 4(A, B, C, D)
Explanation: PMBOK guide 5th ed. Page 182.

187 A
Explanation: PMBOK guide 5th ed. Page 197.

188 A
Explanation: PMBOK guide 5th ed. Page 201.

189 D
Explanation: PMBOK guide 5th ed. Page 204.

190- 2(A, B)
Explanation: PMBOK guide 5th ed. Page 204-205.

191- 4(A, B, C, D)
Explanation: PMBOK guide 5th ed. Page 208.

192- 2(None of the above)


Explanation: PMBOK guide 5th ed. Page 216.
All of the above are included in project cost control.

193 B
Explanation: PMBOK guide 5th ed. Page 220.
EAC = AC + (BAC EV)
EAC=1000+1200-900=$1300.
194 B
Explanation: PMBOK guide 5th ed. Page 220.
EAC = BAC / CPI
EAC=1200/1.2=$1000

195 B
Ref: PMBOK guide 5th ed. Page 363.

196- 3(A,D)
Ref: PMBOK guide 5th ed. Page 242.

197 D
Explanation: PMBOK guide 5th ed. Page 8.

198 C
Explanation: PMBOK guide 5th ed. Page 8.

199 D
Explanation: PMBOK guide 5th ed. Page 8.

200 B
Explanation: PMBOK guide 5th ed. Page 9.

You might also like