CRONOGRAMA GANTT Y RUTA CRTICA
TING001 - CONSTRUCCION TINGLADO ALTO YURAJ RUMMY
15/Feb/2016 22/Feb/2016 29/Feb/2016 7/Mar/2016 14/Mar/2016 21/Mar/2016 28/Mar/2016 4/Abr/2016 11/Abr/2016 18/Abr/2016 25/Abr/2016 2/May/2016
tem Actividad Das L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D
1. ACTIVIDADES GENERALES 2.00
1 INSTALACION DE FAENAS 2.00
2 REPLANTEO Y CONTROL DE OBRAS 2.00
2. TINGLADO 61.00
3 DEMOLICION DE HORMIGON CICLOPEO 5.00
4 EXCAVACION DE 0_2.5 TERRENO SEMI DURO 5.00
5 HORMIGON POBRE 2.00
6 ZAPATAS DE HA DOSIF: 1:2:3 7.00
7 COLUMNA DE HORMIGON ARMADO 5.00
8 RELLENO Y COMPACTACION CON MATERIAL SELECCIONADO 3.00
9 ANCLAJE PARA COLUMNAS SEGN DISEO 2.00
10 COL. MET C/PERFIL TIPO I 8.00
11 COL. MET C/PERFIL TIPO II 8.00
12 CERCHA METALICA C/PERFIL TIPO 5.00
13 PROV. COLOC. CORREAS PERFIL C80X40X15X2MM 8.00
14 PROV. Y COL. TENSORES 16 MM 3.00
15 CUBIERTA CALAMINA ONDULADA GALVANIZADA N28 PREPIN 7.00
16 CANALETA DE CALAMINA PLANA N 28 3.00
17 BAJANTE RECTANGULAR DE CALAMINA PLANA N28 2.00
18 ILUMINACION CANCHA C/LED DE 150W/220V (PROV. E INS 5.00
4. CANCHA POLIFUNCIONAL 18.00
19 DEMOLICION DE PISO 1.00
20 RELLENO COMUN Y COMPACTADO 3.00
21 PISO CEMENTO FROTACHADO FINO DE 7 CM C/EMPEDRADO 7.00
22 ESTRUCTURA TABLERO SEGUN DISEO 5.00
23 PINTADO TABLERO Y DEMARCADO E PINTADO DE CANCHA 3.00
24 LIMPIEZA Y RETIRO DE ESCOMBROS 2.00
Proyecto: CONSTRUCCION TINGLADO ALTO YURAJ RUMMY Fecha de Inicio: 19/02/2016 Simbologa:
Ubicacin: COCHABAMBA Fecha Conclusin: 07/05/2016 Actividad Crtica:
Cliente: ALTO YURAJ RUMMY Total Das Hbiles: 79.00 Actividad Flotante: