Schedule of Requirements 1
Purchase Agreement
Supply of (Insert Material Name)
THIS PURCHASE AGREEMENT made the _____ day of __________, 20___
between China Railway First Group, CRFG (hereinafter called Purchaser
/CRFG ) of the one part and [name of Supplier] of [city and country of
Supplier] (hereinafter called the Supplier) of the other part.
- Witness:
____________
Signature of the {supplier _______
name} (Name, Title and Address)
______________________
(Seal) ____________________
Signed, Sealed and Delivered in
the presence of:
Section 3. Schedule of Requirements 2
Witness:
Signature of the CRFG/ __________________________
Purchaser (Name, Title and Addres)
_____________________(Seal)
____________________
Section-1: Suppliers Information and Purchase Orders 3
Table of Content
1. Definitions 81............................................................................................................18
284.........................................................................................................................................18
24.................................................................................................. Insurance 89
18
28................................................................................................... Warranty 92
18
2 18
97 18
Supplier Information
[The Supplier shall fill in this Form in accordance with the instructions
indicated below. No alterations to its format shall be permitted and no
substitutions shall be accepted.]
Date: ..
(a) We have examined and have no reservations with the terms and
conditions of this agreement
(b)We have not been suspended nor declared ineligible by any Project.
(c) We offer to supply in conformity with the Project Technical specifications
as attached Annex-A and in accordance with the Delivery Schedules
specified in the Schedule of Requirements the following Materials:
Sr No. Material Supply Name Quantity Rate(Currency)
Related Services
1. Bitumen
2. Steel
3. Etc. In case of multi supplies from the same Supplier
(d)The total agreed price as per material unit rate by both the parties
excluding any discounts offered in item (c1) below is:
In case of only one lot, total price of the supply
In case of multiple lots, total price of all lots (sum of all lots): (insert
currency name & amount)
Section-1: Suppliers Information and Purchase Orders 6
(e) The details of discounts offered & agreed along with the methodology for
their application are:
(i) The discounts are: Specify in detail each (if any)
(ii) The exact method of calculations to determine the net price after
application of discounts is shown below : [Specify in detail the method
that shall be used to apply the discounts];
(f) M/s CRFG shall use his best endeavors in assisting the supplier where
required in obtaining clearance through the customs of material supplies.
(g)This terms & conditions shall remain binding upon both parties till the
supply delivery of final lot as per delivery schedule mentioned above.
(h)We obtain a performance security in accordance within 14 days after
signing of the Material Purchase Agreement with CRFG
(i) We are under obligation to pay all federal & provincial taxes, follow
Contract provisions related to supplies, Project Technical Specifications,
Project & projects country laws and related regulations as are mentioned
in agreement documents.
(j) We understand that this document with its attachments shall constitute a
binding contract between us
(k) We hereby certify that we have taken steps to ensure that no person
acting for us or on our behalf will engage in any type of fraud and
corruption.
Title of the person signing this Doc [insert complete title of the person
signing ]
Currencies:
of ______
1 2 3 4 5 6 7 8
Line Description of Country of Delivery Quantity and Unit price CIP Price per line Price per line item for
Item Materials Origin Date as physical unit item inland transportation
defined CIP [insert place of and other services
N by Agreed destination] (Col. 5x6) required in the
schedule Projects country to
in accordance with convey the Materials
ITB 14.8(b)(i) to their final
destination
[insert [insert name of [insert [insert [insert [insert unit price [insert total CIP [insert the
numbe Material] country of quoted number of CIP per unit] price per line corresponding price
r of origin of Delivery units to be item] per line item]
the the Date] supplied and
item] Material] name of the
physical unit]
Total Amount:
Name of Supplier [insert complete name of Supplier] Signature of Supplier: [signature of Authoriz
Date: [insert date]
Section-1: Suppliers Information and Purchase Orders 10
Line Description of Country Delivery Quantit Unit price Custom Unit Price Price per Price p
Item Materials of Date as y and including Duties and net of line item item
Origin defined physical Custom Import Taxes custom net of inla
N by unit Duties and paid per duties and Custom transpo
Purchase Import unit, [to be import Duties and n and
Order Taxes paid supported by taxes Import serv
schedule documents] Taxes paid, requir
s (Col. 6 the Pro
minus (Col. 58) count
Col.7) conve
Materi
their
destin
[insert [insert name of [insert [insert [insert [insert unit [insert custom [insert unit [ insert price [insert p
number Materials] country quoted number price per duties and price net of per line item per line i
of the of origin Delivery of units unit] taxes paid per custom net of for inland
item] of the Date] to be unit] duties and custom transpor
Material] supplied import duties and and othe
and taxes] import services
name of taxes] required
the Projects
physical country]
unit]
Name of Supplier [insert complete name of Supplier] Signature of Supplier: [signature of Authoriz
[insert date]
* [For previously imported Materials, the price shall be different from the original import value of these Materials declared to
customs and shall include any rebate or mark-up of the local agent or representative and all local costs except import duties and
taxes, which have been and/or have to be paid as per Project provisions.
Section-1: Suppliers Information and Purchase Orders 11
Contents
The objective of the Schedule of Requirements together with the Supplies Price
Schedule, may serve as a basis in the event of quantity variation during
construction execution
The date or period for delivery should be carefully specified, taking into account (a)
the implications of delivery terms stipulated in NHA specifications along and this
Agreement . Supplier pursuant to the Incoterms rules (i.e., EXW, or CIP, FOB, FCA
termsthat delivery takes place when Materials are delivered to the carriers),
and (b) the date prescribed herein from which the CRFGs delivery obligations start.
[inser [insert description of insert insert insert [insert the insert the i
t Materials] quantit physic place of number of number of n
item y of al unit Delivery days days f
No] item to for the following the following the d
be quanti date of BOQ date of o
supplie ty item to be Purchase /
d executed in Order
accordance /targeted
with date
Programme
under SCI
8.3
Place where
Services shall
Servic Description of Service Quantity1 Physical Unit
performed
e
1. If applicable
Section 3. Schedule of Requirements 15
Testing of Material
The TS shall require that all Materials and materials to be incorporated in the
Materials be new, unused, as orders and that they incorporate all recent
improvements in design and materials, in line with NHA Technical
specification for the respective Project.
(b) Detailed tests shall be performed and after The Engineers Approval
delivery order shall be given
Completion:
The agreements shall stand concluded once all the delivery is delivered timely
and all the payments are made to the supplier.
Termination
(a) The Purchaser, by written notice of default sent to the Supplier, may
terminate the agreement
i. if the Supplier fails to deliver any or all of the Goods within the
period as per purchase order and schedule of requirement.
ii. if the Supplier fails to perform any other obligation under this
agreement
(b) In the event, the Purchaser terminates the agreement for the supply
of materials , the Purchaser may procure, upon such terms and in
such manner as it deems appropriate, materials or Related Services
similar to those undelivered or not performed, and the Supplier shall
be liable to the Purchaser for any additional costs for such similar
Goods or Related Services. However, the Supplier shall continue
supplying to the extent not terminated.
ARBITRATION
All disputes or differences which shall at any time arise between the
parties concerning this Agreement shall be referred to a single arbitrator
in accordance with the Pakistan Arbitration Act, 1940. The arbitration
proceedings shall take place at Islamabad and shall be conducted in the
English language. The Award of the Arbitrator shall be final and binding
upon both parties.
Section 3. Schedule of Requirements 18