Professional Documents
Culture Documents
1. INTRODUCTION:-
processed materials above the natural soil sub- grade. The payment
noise pollution. The ultimate aim is to ensure that the transmitted stresses
due to wheel load are sufficiently reduced so that they will not exceed
2. TYPE OF PAVEMENTS:-
granular structure. The flexible pavement, having less flexural strength, acts
of the pavements and the pavements are also available. A thin layer of
Flexible pavements will transmit wheel load stresses to the lower layers by
The wheel load acting on the pavement will be distributed to a wider area,
and the stress decreases with the depth. Taking advantage of these stress
Hence, the design of flexible pavement uses the concept of layered system.
and the top layer has to be of best quality to sustain maximum compressive
stress, in addition to wear and tear. The lower layers will experience lesser
generally found on low volume roads) or, asphalt concrete surface courses
pavement layers reflect the deformation of the lower layers on to the surface
to the surface layer), In the case of flexible pavement, the design is based on
quality expensive materials are placed in the top where stresses are high. aud low
bituminous layers directly on the soil sub-grade. This is more suitable when there
asphalt concrete is placed above the sub-grade will significantly reduce the vertical
course, tack coat, binder course, prime coat, base course, sub-base course,
Seal coat is a thin surface treatment used to water-proof the surface and to
diluted with water. It provides proper bonding between two layers of binder
course and must be thin, uniformly cover the entire surface, and set very
fast.
bonding between two layers. Unlike tack coat, prime coat penetrates into the
layer below, plugs the voids, and forms a water tight surface.
Surface course is the layer directly in contact with traffic loads and generally
dense graded asphalt concrete (AC). The functions and requirements of this
layer are:
it will prevent the entrance of excessive quantities of surface water into the
It must be tough to resist the distortion under traffic and provide a smooth
It must be water proof to protect the entire base and sub-grade from the
This layer provides the bulk of the asphalt concrete structure. Its chief
purpose is to distribute load to the base course. The binder course generally
consists of aggregates having less asphalt and doesnt require quality as high
The base course is the layer of material immediately beneath the surface of
The sub-base course is the layer of material beneath the base course and the
primary functions are to provide structural support, improve drainage, and reduce
the intrusion of fines from the sub-grade in the pavement structure If the base
course is open graded. Then the sub-base course with more fines can serve as filler
between sub-grade and the base dourse A sub-base course is not always needed or
used. For example, a pavement constructed over a high quality, stiff sub- grade
may not need the additional features offered by a sub-base course. In such
2.4.8 Sub-grade
The top soil or sub-grade is a layer of natural soil prepared to receive the
stresses from the layers above. It is essential that at no time soil sub-grade
National Highway No.18 starts from Cuddapah (km 167.750) to Kurnool (km
the corridors taken up for augment the capacity under NHDP Phase III
4. PRELIMINARY INVESTUGATION:
4.1 General
The sub grade provides a foundation for supporting the pavement structure.
From the pavement during its design life will depend largely upon the
Will ensure uniformity of support for the pavement structure and realization
of the maximum strength potential for the particular sub-grade soil type.
The importance of soil and moisture conditions under the pavement cannot
general suitability of the sub grade soils based on classification of the soil,
soil capillarity, topography, rainfall, and drainage conditions also will affect
the future support rendered by the sub grade by increasing its moisture
Highway project The objective of the exploration work was to determine the
probable range of safe bearing capacity for the structure. To fulfil objective,
4.2.1 Alignment
and vertical curves which require geometric corrections and the existing
stretch of the highway where it passes through plain terrain. The existing
Hill Road manual Widening options of this stretch will be studied in detail
environmental impact if hill is cut for widening purpose etc. The existing
embankment.
The alignment of project road passes through number of built-up
sections. The list of built-up areas and locations are shown in the
Table 1.
4.2.2 Climate
The climate along the road is generally hot. Annual rainfall for year 2004-
Table2.
Six state Highways cross/take off from NH: 18. One major junction is at
Nandyal @ km 289.000 with a road to Nandyal and another is with MDR-24
@ panyam(km 303.030).The details of junction are shown in Table4.There is
no signalized junction on this stretch of highway.
4.4.1 Cross-roads
There are number of side roads that take-off/meet NH: 18 from Cuddapah
to Kurnool stretch. The roads include state highways, MDRs, ODRs and
village roads. The details are shown below:
Type of soil along the project road includes red gravely soil, silty sand, BC
soil with gravel and black soil with gravel. Land use along the highway is
predominantly for agriculture. Majority of the land is being used for wet
crops viz. Paddy, Sugarcane etc. There are number of settlements all along
Hospitals, petrol stations etc. Major settlements are close to the existing
292.000
vehicles viz. buses and cars are more than the commercial vehicles & these
vehicles include 2-axle, 3-axle trucks and LCVs. Local traffic is more in the
18.
borings.
and cuts and tests of Both natural and subsurface drainage of the sub grade
must be considered.
(i) Soil
Soil samples from the preliminary borings should be classified and the data
used to prepare soil profiles and to select representative soils for further
explorations should these areas and carried 2 to 4 feet below the anticipated
bases on relevant IRC codes, MORTH & BIS specifications. Details are
lane divided carriageway for symmetrical widening, left / right widening and
In general, IRC standard codes to which the design shall conform to are:
9) IS:1893-1984(Reaffirmed1991):Earthquake loads
per IRC: SP: 42-1994 (guidelines on Road Drainage) and sub surface
improvement in the project road stretch regarding following facilities for safe
standard)
6. MATERIALS SPECIFICATIONS:
Materials specifications to be used in the construction of road and
structures will be based on the MORTH Specifications for road and bridge
6.1 General
mentioned on the drawings, the requirements laid down in this section and
specifications for relevant items of work covered under these specifications.
the work, it shall conform to relevant Indian Standards, if there are any, or
The Contractor shall notify the Engineer of his proposed sources of material
product from any other source proves unacceptable at any time, the
Contractor shall furnish acceptable material from other sources at his own
expense.
6.2.1 Stones
Stones shall be of the type specified. It shall be hard, sound, free from
approved quarry. Stone with round surface shall not be used. The stones,
when immersed in water for 24 hours, shall not absorb water by more than
5 per cent of their dry weight when tested in accordance with IS: I 124.The
length of stones shall not exceed 3 times its height nor shall they be less
than twice its height plus one joint. No stone shall be less in width than the
height and width on the base shall not be greater than three-fourth of the
6.2.2 Cement
Cement to be used in the works shall be any of the following types with the
Cement conforming to IS: 269 shall be used only after ensuring that the
Cement conforming to IS: 8112 and IS: 12269 may be used provided the
shall be used with a certain caution as high early strengths of cement in the
Silicate. In such cements, the further growth of strength beyond say 4weeks
strength tests shall be carried out for 56 and 90 days to fine tune the mix
threshold values as per IS: 456 are sulphate concentration in excess of 0.2
structure is located near the sea coast. chemical factories and agricultural
land using chemical fertilizers and sites where there are effluent discharges
540 kg/cu.m. of concrete .Cement conforming to IS: 8041 shall be used only
Total chloride content in cement shall in no case exceed 0.05 per cent by
mass of cement.
For plain and reinforced cement concrete (PCC and RCC) or pre stressed
material. They shall not consist pieces of disintegrated stones, soft, flaky,
positive alkali-silica reaction shall not be used. All coarse aggregates shall
conform to IS: 383 and tests for conformity shall be carried out as per IS:
2386, Parts Ito Viii. The contractor shall submit for the approval of the
components in PCC, RCC or PSC.The maximum value for flakiness index for
coarse aggregate shall not exceed 35 per cent. The coarse aggregate shall
For masonry work, sand shall conform to the requirements of IS: 2116. For
plain and reinforced cement concrete (PCC and RCC) or pre stressed
concrete (PSC) works, fine aggregate shall consist of clean, hard, strong and
of natural sand, crushed stone or gravel. They shall not contain dust,
used to remove impurities from sand. Fine aggregate having positive alkali-
silica reaction shall not be used. All fine aggregates shall conform to IS: 383
and tests for conformity shall be carried out as per IS :( Parts I to VIII). The
Appendix A of IS: 383. The fineness modulus of fine aggregate shall neither
be less then 2.0 nor greater than 3.5.SandJfine aggregate for structural
6.25 Steel
The use of cast steel shall be limited to bearings and other similar parts.
Steel for castings shall conform to Grade 280-520N of IS: 1030. In case
components, the letter N at the end of the grade designation of the steel
casting shall be replaced by letter W. 0.3 percent to 0.5 per cent copper may
7.1 General
These Specifications shall apply to the construction of embankments
approved material obtained from roadway and drain excavation, borrow pits
any other material approved by the Engineer. Such materials shall be free of
embankment:
and
(f) Material with salts resulting in leaching in the embankment.
shall not be used as a fill material. Where expansively clay with acceptable
free swelling index value is used as a fill material, sub-grade and top 500
exceeding 1.9 grams of sulphate (expressed as SO3) per liter when tested in
accordance with BS: 1377, but using a 2:1 water-soil ratio shall not be
Materials with a total sulphate content (expressed as SO3) exceeding 0.5 per
cent by mass, when tested in accordance with BS: 1377 shall not be
The size of the coarse material in the mixture of earth shall ordinarily not
placed in the sub-grade. However, the Engineer may at his discretion permit
the use of material coarser than this also if he is satisfied that the same will
not present any difficulty as regards the placement of fill material and its
The maximum particle size shall not be more than two-thirds of the
Notes :( 1) this is not applicable for lightweight fill material e.g. cinder, fly
ash etc.
(2) The Engineer may relax these requirements at his discretion taken into
factors.
(3) The material to be used in sub-grade should also satisfy design CBR at
Where the materials are to be obtained from designed borrow areas, the
location, size and shape of these areas shall be as indicated by the Engineer
and the same shall not be opened without his written permission. Where
Engineer, these shall not be dug continuously. Ridges of not less than 8 m
width should be left at not exceeding 300 m. Small drains shall be cut
through the ridges to facilitate drainage. The depth of the pits shall be so
regulated that their bottom does not cut an imaginary line having a slope of
1 vertical to 4 horizontal projected from the edge of the final section of the
bank, the maximum depth in any case being limited to 1.5 m. Also, no pit
shall be dug within the offset width from the toe of the embankment
deposition.
acceptable material from the site to suit his operational procedure, then he
shall make good any consequent deficit of material arising there from. Where
carry out the excavation in such a manner that the acceptable materials are
separately.
The Contractor shall ensure that he does not adversely affect the stability of
borrow areas and have these tested at the size laboratory following a testing
7.3.2 Dewatering
in the opinion of the Engineer it is feasible to remove it, the same shall be
removed by bailing out or pumping, as directed by the Engineer and the area
discharge the drained water so as not to cause damage to the works, crops
or any other property. Due to any negligence on the part of the Contractor,
from all areas of cutting and from all areas to be covered by embankment
foundation shall be stripped the specified depths not exceeding 150 mm and
slopes. Cut slopes and other disturbed areas where re-vegetation is desired.
minimum.
Table. In case where the difference between the sub-grade level (top of the
sub-grade on which pavement rests) and ground level is less than 0.5 m and
less than 97 per cent of dry density as given in Table. Where so directed by
engineer.
moisture content
grader and compacted .The motor grader blade shall have hydraulic control
suitable for initial adjustment and maintain the same so as to achieve the
specific slope and grade. Successive layers shall not be placed until the
embankment.
the same shall be made good. Where water is required to be added in such
variable widths of surface but without any flooding. The water shall be
of the layer.
aeration and exposure to his sun, till the moisture content is acceptable for
layer of soil shall be checked in accordance with IS: 2720 (Part 2), and
accordance with IS: 2720 (Para 7) or IS: 2720 (Para 8) as the case may be.
corresponding to the specified dry density, but on the wet side of the
After adding the required amount of water, the soil shall be processed by
Embankment and other areas of fill shall, unless otherwise required in the
width and their fullest possible extent and the Contractor shall control and
direct construction plant and other vehicular traffic uniformly over them.
good by the Contractor with material having the same characteristics and
with steeper side slopes, or to greater widths than those shown in the
trimming back, 01. To obtain the final profile following any settlement of the
fill and the underlying material. Whenever fill is to be deposited against the
such faces shall be benched immediately before placing the subsequent fill.
considered suitable by the Engineer, the slope or any other method approved
by the Engineer.
7.3.6 Compaction
Smooth wheeled, vibratory, pneumatic tvred, sheep foot or pad foot rollers,
etc of suitable size and capacity as approved by the Engineer shall be used
done with the help of vibratory roller of 80 to 100 KN Static weight with
plain or pad foot drum or heavy pneumatic tyred roller of adequate capacity
these site trials shall first be submitted to the Engineer for approval.
specified in Table Subsequent layers shall be placed only after the finished
layer has been tested according to accepted by the Engineer. The Engineer
gauge used in accordance with agreed procedure and the gauge is calibrated
to provide results identical to that obtained from tests in accordance with IS:
2720 (Part 28). A record of the same shall be maintained by the contractor.
achieved, the material& in the soft areas shall be removed and replaced by
of the Engineer.
7.3.7 Drainage
shall be maintained at such a cross fall (not flatter than that required for
ponding.
The soil in the affected portion shall be removed in such areas as directed by
thc Engineer before next layer is laid and refilled in layers and compacted
with. If the cut is not sufficiently wide for use of required mechanical means
for compaction, the same shall he widened suitably to permit their use for
proper compaction.
damages including widening of the cut, if any, shall be carried out by the
Finishing operations shall include the work of shaping and dressing the
by the Engineer subject to the surface tolerance described .Both the upper
and lower ends of the side slopes shall be rounded off to improve
appearance and to merge the embankment with the adjacent terrain. The
topsoil, removed and conserved earlier shall be spread over the fill slopes as
topsoil in order to provide satisfactory bond. The depth of the topsoil in shall
to 150 mm. Where directed, the slopes shall be surfed with sods in
area shall be cleared of all debris, and ugly scars in the construction area
special Conditions
benches.
Each at least 300 mm wide, shall be cut into the old slope for ensuring
to the work. For wet conditions, benches with slightly inward fall and subsoil
at the lowest point shall be provided as per the drawings. Before the fill is
the cut-fill interface, work on the same shall be carried out in proper
Engineer.
(i) If the existing road surface is of granular or bituminous type and lies
specified, so as to provide ample bond between the old and new material
ensuring that at least 500 portions below the top of new sub-grade level is
(ii) If the existing road surface is of cement concrete type and lies within 1 m
of the new sub- grade level the same shall be removed completely.
(iii) If the level difference between the existing road surface and the new
Unless directed otherwise, the filling around culverts, bridges and other
structures up to a distance of twice the height of the road from the back of
the abutment shall be carried out independent of the work on the main
embankment. The fill material shall not be placed against any abutment or
wing wall, unless permission has been given by the Engineer but in any case
not until the concrete or masonry has been in position for 14 days.
equal layers on each side of the structure to avoid displacement and unequal
pressure. The sequence of work in this regard shall be got approved from the
Engineer.
The material used for backfill shall not be an organic soil or highly plastic
clay having plasticity index and liquid limit more than 20 and 40
Filing behind abutments and wing walls for all structures shall conform to
of the type of material, the extent of backfill, its laying and compaction etc.
required for embankment and sub-grade. Where the provision of any filter
medium is specified behind the abutment, the same shall be laid in layers
simultaneously with the laying requirements for filter medium spelt out in
vibratory roller, plate compactor or power rammer. Care shall be taken to see
that the compaction equipment does not hit or come too close to any
over such ground by the use of lighter or modified equipment after proper
ditching and drainage have been provided where this exception is permitted,
over any area of the Contract will be the responsibility of the Contractor and
particles with maximum particle size not exceeding 75 mm. The material
should be non-plastic having uniformity co-efficient of not less than 10. The
compaction.
In the case of high embankments, the Contractor shall normally use the
material from the specified borrow area. In case he desires to use different
material for his own convenience, he shall have to carry out necessary soil
investigations and redesign the high embankment at his own cost. The
Contractor shall then furnish the soil test data and design of high
embankment for approval of the Engineer, who reserves the right to accept
or reject it. If necessary, stage construction of fills and any controlled rates
of filling shall be carried out in accordance with the Contract including
of fill with approved material for the periods specified in the Contract. If
unacceptable for use in the fill being surcharged, lying below formation level,
PCI. Direction of the Engineer. He shall then bring the resultant level upon
formation level; the Contractor shall remove the unacceptable material and
dispose it as per direction of the Engineer. He shall then bring the resultant
remain in place for the required settlement period before excavating for
piles. The duration of the required settlement period at each location shall
Construction and other vehicular traffic shall not use the prepared surface
Engineer. Any damage arising out of such use shall, however, be made good
Apparatus:
425 Micron IS Sieve-01 no, & l00ml capacity graduated cylinder-02 nos,
Procedure:
1. Take two nos of 10 grams oven dried sample passing through 425 micron
IS Sieve.
2. Take two nos of 100ml capacity graduated cylinder, one filled with
3. Each soil specimen shall he poured in each of the two glass graduated
4. After removal of entrapped air, the soil in both the cylinder shall be
Vd=Volume of soil specimen from the graduated cylinder filled with water.
Vk= Volume of soil specimen from the graduated cylinder filled with
kerosene.
8. SUB-GRADE:-
8.1 SCOPE
with the lines, grades and cross sections shown on the drawings are as
8.2 Materials:
Except when otherwise specified, the sol used for stabilization shall be the
8.2.2 Lime:
Lime for lime-soil stabilization work shall be commercial dry lime slaked at
permitted by Engineer, the lime shall have purity of not less than 70% by
weight of Quicklime (CaO) when tested in accordance with IS: 1514. Lime
that equivalent calcium oxide is incorporated in the work. The mix design
having due regard to the purity of the engineer so that equivalent calcium
oxide is incorporated in the work .The mix design shall be done to arrive3e
purity of lime, the type of soil, the moisture-density relationship, and the
design CBR/UCS value shall be at least 1.5 times the minimum field value
8.2.4 Water
The water to be used for lime stabilization shall be clean and free from
Lime-soil stabilization shall not be done when the air temperature in the
For lime stabilization, the soil before addition of stabilizer shall be pulverized
using agricultural Implements like dis harrows and ratovators to the extent
be permitted only where the width of lying is not adequate for mechanical
approved equipment capable of pulverizing and mixing the soil with additive
and water to specified degree to the full thickness of the layer being
the stabilized material. If so desired by the Engineer, trail runs with the
equipment shall be carried out to establish its suitability for work. The
thickness of any layer to be stabilized shall be not less than 100 mm when
compacted. The maximum thickness shall be 200 mm, provided the plant
Before deploying the equipment, the soil after it is made free of undesirable
employed, the soil shall be lightly rolled at the discretion of the Engineer.
The Equipment used shall either be of single-pass or multiple pass type. The
periodically so that the correct depth of mixing is obtained at all times. With
in relation to the speed that the required degree of mixing, pulverization and
be spread -uniformly and mixing continued with successive passes until the
required depth and uniformity of pressing have been obtained. The mixing
equipment shall be so set that it cuts slightly into the edge of the adjoining
Where manual mixing is permitted, the soil from borrow areas shall first be
freed of all vegetation and other deleterious matter and placed on the
bars, pick axes or other means approved by the Engineer. Water n requisite
similar implements till the whole mass are uniform After adjusting the
moisture content to be within the limits mentioned later, the mixed material
8.3.6Addition of Lime
Lime may be mixed with the prepared material either in slurry form or dry
state at the option of e Contractor with the approval of the Engineer. Dry
lime shall be prevented from blowing by adding water to the lime or other
trenched to receive the lime. The distance to which lime may spread upon
the Engineer. No traffic other than the mixing equipment shall be allowed to
pass over the spread lime until after completion of mixing. Mixing or re-
material is free of any white breaks or pockets of lime and the mixture is
uniform.
Non uniformity of colour reaction, when the treated material is tested with
of inadequate mixing.
The moisture content at compaction checked vide IS: 2720 (Part 2) shall
8.3.8 Rolling
commence at the inner edge and progress towards outer edge. During rolling
the re shall be frequently checked for grade and cross-fall (camber) and any
per cent of the maximum dry density for the material determined in
see that the compaction of lime stabilized material is completed within three
hours of its mixing or such shorter period as may be found necessary in dry
weather. During rolling it shall be ensured that roller does not bear directly
than what may be necessary for achieving the specified compaction at the
joint. The final surface shall be well closed, free from movement under
or otherwise defective areas shall be made good to the full thickness of the
8.3.9 Curing
The sub-base course shall be suitably cured for a minimum period of 7 days
surface from drying out and becoming friable. No traffic of any kind shall ply
8.3.10 Strength
When lime is used for improving the sub-grade, the soil-lime mix shall be
tested for its CBR value. When lime stabilized soil is used in a sub-base, it
of variation from the design CBR!UCS, in situ value being lower, the
pavement design shall be reviewed based on the actual CBR/UCS value sJi1
cubic metres.
97 test pits of size 1.Om x l.0m x 0.75m are dug by the side of existing
These results would be made use in applying corrections to BBD test values.
Maximum dry density (MDD) test is conducted at 20 test pits using sand
replacement method to work out the density of existing sub grade material.
Sub grade sample of approx. 60 kg is collected from each pit for conducting
- Atterberg limits
The test results will be utilized in assessing the quality of existing sub grade
CBR value is used in the preliminary design of flexible pavement. The design
per sqm and to arrive at the construction cost of tjme project road.
Procedure:-
ratio is usually determined for penetration of 2.5 and 5.0mm where the ratio
at 5.0mm is used.
No. of layer :5
allowance for lesser material shall be replacing by 19.0 pass and 4.75mm
retained material &mix thoroughly with water and compacted in CBR mould
layer by layer after compaction this set up shall undisturbed for 96 hours in
water.
Penetration test:- The specimen allowed to drain downwards for 15mm. The
weights the perforated plate and the top filter paper shall be removed and
The plunger shall be seated under a load of four kg. So that full centect is
established between the surface of the specimen and plunger. The gauge
Lord shall be applied to the plunger into the soil @ 1 .25mm/mm, Reading
Of the load shall be taken at penetration of 0.5, 1.0, 1.5, 2.0, 2.5, 4.0, 5.0,
2.5 70 1370
9.1 Scope
lower sub-base and upper sub base (termed as sub base sub base
9.2 Materials
The material to be used for the work shall be natural sand, moorum, gravel,
required. Materials like crushed slag crushed concrete, brick metal and
kankar may be allowed only with the specific approval of the Engineer.
The material shall be free from organic or other deleterious constituents and
conform to one of the three grading given in table below. While the grading
one each for maximum particle size of 75 mm, 53 mm and 26.5 mm.
The corresponding for the coarse-graded materials for each of the three
The materials shall have a10 per cent fines value of 50 km or more (for
sample in soaked condition) when tested in compliance with bs: (812 part
111). The water absorption value of the coarse aggregate shall be determine
as per IS: 2386 (part 3) ; if this value is greater than 2 per cent, the
soundness test shall be carried out on the material delivered to site as per
IS:383. For Grading II and II materials, the CBR shall be determined at the
Note: The Material passing 425 micron (0.425 mm) sieve for all the three
grading when tested according to IS: 2720
(Part 5) shall have liquid limit and plasticity index not more than 25 and 6
on specimens re molded at field dry density and moisture content and any
Immediately prior to the laying of sub base, the sub-grade already finished
extraneous matter, lightly sprinkled with water if necessary and rolled with
on the prepared sub- grade with the help of a motor grader of adequate
capacity, its blade having hydraulic controls suitable for initial adjustment
and for maintaining the required slope and grade during the operation or
The Material to be used for the work shall be natural sand, morum, gravel,
Materials like crushed slag crushed concrete, brick metal and kankar may
be allowed only with the specific approval of the Engineer. The material shall
the three grading given in Table for grading for close-graded granular sub-
granular sub-base materials, one each for maximum particle size of 75 mm,
materials for each of the three maximum particle sizes are given at Table for
the desired degree. If so desired by the Engineer, trial runs with the
equipment shall be carried out to establish its suitability for the work.
IS: 2720 (Part 2) and suitably adjusted by sprinkling additional water from a
truck mounted or trailer mounted water tank and suitable for applying
IS: 2720 (Part 8). While adding water, due allowance shall be made for
evaporation losses. After water has been added, the material shall be
shall start. If the thickness of the compacted layer does not exceed 100 mm,
compacted single layer up to 225 mm the compaction shall be done with the
commence at the lower edge and proceed towards the upper edge
elevation and shall commence at the edges and progress towards the centre
Each pass of the roller shall uniformly overlap not less than one-third of the
track made in the proceeding pass. During rolling, the grade and cross-fall
roller shall not exceed 5 km per hour. Rolling shall be continued till the
density achieved is at least 98 per cent of the maximum dry density for the
material determined as per IS: 2720 (Part 8). The surface of any layer of
material on completion of compaction shall be well closed, free from
meters. The protection of edges of granular sub-base extended over the full
9.4.4 Rate
The Contract unit rate for granular sub-base shall be payment in full for
(i) Making arrangements for traffic to except for initial treatment to verges,
royalties, fees, rents where necessary and all leads and lifts;
(iii) All labour, tools, equipment and incidentals to complete the work to the
Specifications; (iv) Carrying out the work in part widths of road where
directed; and
Apparatus: liquid limit device, plastic limit device, IS 4.75mm Sieve trays.
The plastic limit is determined by rolling out a thread of the fine portion of a
If is plastic, this thread will retain its shape down to a very narrow diameter.
The sample can than be remolded and the test repeated. As the moisture
content falls due to evaporation the thread will begin to break apart at larger
diameter. The plastic limit is defined as the moisture content where the
The liquid limit (LL) is the water content at which a soil changes from plastic
to liquid behavior. The original liquid limit test of Atterbergs involved mixing
A groove was cut through the pat of clay with a spatula and bowl was then
make the measurement more repeatable. Soil is placed into the metal cup
portion of device and a groove is made down its center with a standardized
tool of 13.5mm (0.53 in) width. The cup is repeatedly dropped 10mm onto a
hard rubbed base at a rate of 120 blows per minute, during which the
for the groove to close is recorded. The moisture content at which it takes 25
drops of the cup to cause the groove to se over a distance of 13.5mm (0.53
in) is defined as the liquid limit. The test is normally run several moisture
contents, and the moisture content which requires 25 blows to close the
groove is interpolated from the test results. The liquid limit test is defined by
ASTM standard test method D 4318. The test method also allows running
the test at one moisture content where 2O and 30 blows are required to
close the groove; then a correction factor is applied to obtain the liquid limit
Sieve analysis:-
Procedure:-
typical sieve analysis involves a nested column of sieves with wire mesh
cloth (screen). See the separate mesh (scale) page for details of sieve sizing.
A representative weighed sample is poured into the top sieve which has the
largest screen openings. Each lower sieve in the column has smaller
openings than the one above. At the base is a round pan, called the receiver.
the column, usually for some fixed amount of time. After the shaking is
complete the material on each sieve is weighed. The weight of the sample of
each sieve is then divided by the total weight to give a percentage retained
on each sieve. The size of the average particle on each sieve is then analysed
screen. The results of this test are used to describe the properties of the
purposes such as selecting the appropriate aggregate for concrete mixes and
asphalt mixes as well as sizing of water production well screens. The results
of this test are provided in graphical form to identify the type of gradation of
the aggregate. The complete procedure for this test is outlined in the
American Society for Testing and Materials (ASTM) C136 and the American
A suitable sieve size for the aggregate should be selected and placed in order
should be placed underneath the nest of Sieves to collect the aggregate that
passes through the smallest. The entire nest is then agitated, and the
material whose diameter is smaller than the mesh opening passes through
the sieves. After the aggregate reaches the pan, the amount of material
10.1 Scope
This work shall consist of laying and compacting clean, crushed, graded
shall be laid in one or more layers as necessary to lines, grades and cross-
The thickness of a single compacted Wet Mix Macadam layer shall not be
equipment are used, the compacted depth of a single layer of the sub-base
not less than 90 per cent by weight of the gravel/shingle pieces retained on
4.7mm sieve shall have at least two fractured faces. The aggregates shall
TabIel4. Physical requirements of aggregates for wet mix macadam for sub
base/base courses
weight of flaky stone metal divided by weight of stone sample. Only the
elongated particles are separated out from the remaining (non-flaky) stone
flaky particles. The value of flakiness index and elongation index so found
are added up. If the water absorption value of the coarse aggregate is greater
than 2 per cent, the soundness test shall be carried out on the material
Materials finer than 425 micron shall have Plasticity Index (PT) not
exceeding 6.
The final gradation approved within these limits shall be well graded from
coarse to fine and shall not vary from the low limit on one sieve to the high
While constructing wet mix macadam, arrangement shall be made for the
This shall be done by laying materials in adjoining shoulders along with that
mixing arrangement like pug mill or pan type mixer of concrete batching
plant.
For small quantity of wet mix work, the Engineer may permit the mixing to
size. While adding water, due allowance should be made for evaporation
losses. However, at the time of compaction, water in the wet mix should not
vary from the optimum value by more than agreed limits. The mixed
material should be uniformly wet and no segregation should be permitted.
these are to be laid nor shall their hauling over a partly completed stretch be
permitted. The mix may be spread either by a paver finisher or motor grader.
approved by the Engineer shall be used. The motor grader shall be capable
of spreading the material uniformly all over the surface. Its blade shall have
hydraulic control suitable for initial adjustments and maintaining the same
(ii) The screed shall have tamping and vibrating arrangement for initial
The surface of the aggregate shall be carefully checked with templates and
10.4.4 Compaction
After the mix has been laid to the required thickness, grade and cross
fall/camber the same shall be uniformly compacted, to the full depth with
suitable roller. If the thickness of single compacted layer does not exceed
100 mm, a smooth wheel roller of 80 to 100 KN weight may be used. For a
compacted single layer up to 200 mm, the compaction shall be done with
equivalent capacity roller. The speed of the roller shall not exceed 5 km/h. In
commence from the lower edge and progress gradually towards the upper
edge. Thereafter, roller should progress parallel to the centre line of the road,
uniformly overlapping each preceding track by at least one third width until
from any preceding sop. In portions in camber, rolling should begin at the
edge with the roller running forward and ward until the edges have been
firmly compacted. The roller shall then progress gradually towards the
centre parallel to the centre line of the road uniformly overlapping each of
the reeding tracks by at least one-third width until the entire surface has
and/or removed and made good. Along forms, kerbs. Wal1s or other places
not accessible to the roller, the mixture shall be thoroughly compacted with
scarifying the surface to permit proper bonding of the added material shall
not be permitted. Rolling should not be done when the sub-grade is soft or
yielding or when ii causes a wave-like motion in the sub-base base course
or sub-grade.
uniform surface conforming to the red grade and cross fall. In no case
Rolling shall he continued till the density achieved is at least 98 per cent of e
equipment or any compaction planes, ridges, cracks and loose material. All
Loss, segregated or otherwise defective areas shall be made good to the full
After final compaction of wet mix macadam course, the road shall be allowed
wet mix macadam surface till it has dried and the wearing course laid.
Where the surface irregularity of the wet mix macadam course exceeds the
grade soil getting mixed with the aggregates, the full thickness of the layer
shall be scarified over the affected area, reshaped with added premixed
and recomputed. The area treated in the aforesaid manner shall not be less
10.5.2 Rates
The Contract unit rate for wet mix macadam shall be payment in full for
carrying out the required operations including full compensation for all
components.
Sieve analysis:-
Procedure:-
typical sieve analysis involves a nested column of sieves with wire mesh
cloth (screen). See- the separate mesh (scale) page for details of sieve sizing.
A representative weighed sample is poured into the top sieve which has the
largest screen opening. Each lower sieve in the column has smaller openings
than the one above. At the base is a round pan, called the receiver.
the column, usually for some fixed amount of time. After the shaking is
complete the material on each sieve is weighed. The weight of the sample of
each sieve is then divided by the total weight to give a percentage retained
on each sieve.
The size of the average particle on each sieve is then analysed to get a cut-off
The results of this test are used to describe the properties of the aggregate
selecting the appropriate aggregate for concrete mixes and asphalt mixes as
well as sizing of water production well screens. The results of this test are
The complete procedure for this test is outlined in the American Society for
Testing rd Materials (ASTM) C136 and the American Association and State
A suitable sieve size for the aggregate should be selected and placed in order
should be placed underneath the nest of sieves to collect the aggregate that
passes through the smallest. The entire nest is then agitated, ad the
material whose diameter is smaller than the mesh opening passes through
the sieves. After the aggregate reaches the pan, the amount of material
Procedure:
2. Each fraction is the thus gauged individually for length in a length gauge.
The gauge length is used should be those specified in the table for the
appropriate material.
3. The pieces of aggregate from each fraction tested which could not pass
through the specified language length with its long side are elongated
particles and they are collected separately to find the total weight of
sieves sizes are found W1, W2, W3, and the total weight of sample
determined =W1+ W2+W3=Wg. Also the weight of the material from each
function retained on the specified gauge length are found= X1, x2, x3 and
6. The elongation index is the total weight of the material retained on the
sample gauged.
(X1+x2+x3+-------)
(w1+w2+w3+-----)
Procedure
5. Let the weight of the flaky materials passing the gauge be W1 gm.
Similarly the weights of the fractions passing and retained on the specified
sieves be W1, W2, W3, etc, are weighed and the total weight WI+W2+W3+ =
Wg is found. Also the weights of the materials passing each of the specified
thickness gauge are found =W 1, W2, W3.... And the total weight of the
found.
6. Then the flakiness index is the total weight of the flaky material passing
(w1+w2+w3+----)
(w1+w2+w3+----)
11. 1 Scope
This work shall consist of the application of a single coat of low viscosity
11.2 Materials
11.2.1 Prime
are:
macadam,
The type and viscosity of the primer shall comply with requirements of IS:
The primer shall be bitumen emulsion, complying with IS: 8887 of a type
use of medium curing cutback as per IS: 217 shall be restricted only for
Engineer.
storm or when the weather is foggy, rainy or windy or when the temperature
in the shade is less than 100C. Surfaces which are to receive emulsion
11.3 Construction
11.3.1 Equipment
carefully swept of dust and loose particles, care being taken not to disturb
the interlocked aggregate. This is best achieved when the surface layer is
slightly moist (lightly sprayed with water and the surface allowed to dry) and
accordance with. The method for application of the primer will depend on
type of equipment to be used, size of nozzles, pressure at the spray bar and
A primed surface shall be allowed to cure for at least 24 hours or such other
using the minimum quantity possible. A primer surface shall not be opened
to traffic other than the necessary to lay the next course. A very thin layer of
clean sand may be applied to the surface to lay prevent the primer picking
up under the wheels of the paver and trucks delivery bituminous material to
the paver.
square meters.
11.3.6 Rate
The contract unit rate for prime coat with adjustment as describe in shall
payment in full for carrying out the required operation including full
provision of prime coat at the application rate of 0.6 kg per square meter,
with adjustment, plus or minus, for the variation between this amount and
12.1 Scope
Macadam, (DBM), for use mainly, but not exclusively, in base/binder and
profile corrective courses. DBM is also intended for use as road base
12.2 Materials
12.2.1 Bitumen
Indian Standard Specifications for Paving Bitumen IS: 73, and of the
The coarse aggregates shall consist of crushed rock, crushed gravel or other
hard material retained on the 2.36 mm sieve. They shall be clean, hard, and
durable, of cubical shape, free from dust and soft or friable matter, organic
aggregates have poor affinity for bitumen, as a condition for the approval of
payment. Before approval of the source, the aggregates shall be tested for
stripping.
Table, for dense bituminous macadam. Where crushed gravel is proposed for
retained on the 4.75 mm sieve shall have at least two fractured faces.
and retained on 75 micron sieve. They shall he clean, hard, durable, dry and
free from dust, and soft or friable matter. organic or other deleterious matter.
The fine aggregate shall have a sand equivalent alue of not less than 50
when tested in accordance with the requirement of IS: 2720 (Part 37). The
plasticity index of the fraction passing the 0.425 mm sieve shall not exceed
** The water sensitivity test is only required if the minimum retained coating
12.2.4 Filler
Filler shall consist of finely divided mineral matter such as rock dust,
hydrate lime or cement approved by the engineer. The filler shall be grated
The filler shall be free from organic impurities and have a Plasticity Index
not greater than 4. The Plasticity Index requirement shall not apply if filler is
cement or lime. When the coarse aggregate is gravel, 2 per cent by weight of
not required when the limestone aggregate is used. Where the aggregates fail
coat.
When tested in accordance with IS: 2386 Part 1 (wet sieving method), the
combined grading of the coarse and fire aggregates and added filler for the
particular mixture shall fall within the limits shown in Table 19, for dense
and quality of bitumen, and appropriate thickness, are also indicated for
Note: The combined aggregate grading shall not vary from the low limit on
Apart from conformity with the grading and quality requirement for
individual ingredients, the mixer shall meet requirement set out in Table 20.
Notes: 1. the nominal maximum particle size is one size larger than the firt
mixture set out in Table and the traffic volume specified in the Contract. The
aggregates retained on the 26.5 mm sieve by the aggregates passing the 26.5
stability values in Table shall be multiplied by 2.25 and the minimum flow
shall be 3 mm.
The Contractor shall inform Engineer in writing, at least 20 days before the
start of the work, of the job mix formula proposed for be used in the works,
(iii) A single definite percentage passing each sieve for the mixed aggregate;
(iv) The individual grading of the individual aggregate fractions, and the
Contractor;
(vi) Where the mixer is a batch mixer, the individual weights of each type of
aggregate, and binder per batch, (vii) Test results of physical characteristics
temperature. While establishing the job mix formula, the Contractor shall
materials that will actually be used in the work and that the mixture and its
the mix shall he furnished by the Contractor required by the Engineer. The
approved job mix formula shall remain effective unless and until a revised
Over the laboratory job mix formula is approved, the Contractor shall carry
out plant trials at the mixer to establish that the plant can be set up to
produce a uniform mix conforming to the Base and approved job mix
various ingredients in the actual mix from the job mix formula to be used
Once the plant trials have demonstrated the capability of the plant. And true
trials are approved. The laying operation may commence. Over the period of
the first month of production for laying on the works. the Engineer shall
Once the 1)1 ant trials have been successfully completed and approved, the
Contractor shall carry out laying trials, to demonstrate that the proposed
mix can be successfully laid, and compacted. The laying trial shall be
carried out on a suitable area which is not to form part of the works. unless
specifically approved in writing, by the Engineer. The area of the laying trials
laid.
The Contractor shall previously inform the Engineer of the proposed method
for laying and compacting the material. The plant trials shall then establish
Once the laying trials have been approved, the same plant and methodology
shall be applied to the laying of the material on the project, and no variation
The surface shall be thoroughly swept clean by a mechanical broom, aid the
Engineer.
12.4.2 Rolling
The compaction process shall be carried out by the same plant, and using
the same method, as approved in the laying trials, which may be varied only
The newly laid surface shall not be open to traffic for at least 24 hrs after
Engineer in writing.
Engineer.
12.4.5 Rate
The rate shall include the provision of bitumen, 4.25 per cent by weight of
the total mixture. The variance in actual percentage of bitumen used will be
Marshal test
Procedure:
The test sample consist of aggregate passing 12.5mm sieve and retained on
10mm sieve and dried in an oven for four hours at a temperature 100C to
110C and cooled. Test aggregates are filled up to about one-third full in the
cylindrical measure and tamped 25 times with rounded end of the tamping
cylinder and 25 stocks of the tamping rod are given. The measure is now
filled with the aggregate to over flow, tamped 25 times. The surplus
aggregate are struck off using the tamping rod as straight edge. The net
and this weight of the aggregate is used for carrying out duplicate test on
the sample material. The impact machine is placed with its bottom plate flat
on the floor so that the hammer guide columns arc vertical. The cup is fixed
firmly in position on the base of the machine and the whole of the test
The hammer is raised until its lower face is 380mm above the upper surface
of the aggregate in the cup, and allowed to fall freely on the aggregates. The
interval of not less than one second. The crushed aggregate is then removed
from the cup and the whole of it sieved on the 2.36mm sieve until no further
The fraction passing the sieve is weighted accurate to 0.1gm. The fraction
retained on the sieve is also weighed and if the total weight of the fraction
passing and retained on the sieve is added it should not be less the original
weight is less than the original weight of the specimen by more than one
gram, if the total weight is less than the original by over one gram the result
Marshal Test:-
Apparatus required:
breaking head, loading machine flow meter, thermometers water bath and
oven
Procedure: -
should be proportioned and mixed in such a way that final mix after
3. The compaction mould assembly and rammer are cleaned and kept
trowel.
maintained and then the mix is transferred into the pre-heated mould
used are determined first. The theoretical specific gravity of the mix is
determined.
specimen are noted. The specimens are weighted in air and then in
water.
7. The bulk density value of the specimen if calculated from weight and
volume
to 40 minutes.
9. The specimens are taken out one, placed in the marshal lest and the
11. Five graphs are plotted with values of bitumen content against
the values of density, Marshall Stability, voids in total mix, flow value,
Then the optimum bitumen content for mix design is given by: Bo= (BI
+B2+B3)/3.
13.1 SCOPE
This work shall consist of the application of single coat of low viscosity liquid
13.2 Material
13.2.1 Binder
The binder used for tack coat shall be a bitumen complying with IS : 8887 of
storm or when the weather is foggy, rainy or windy or when the temperature
in the shade is the less than 100c. Where coat is of cutback bitumen, the
13.3 Construction
13.3.1 Equipment
by the engineer.
The surface on the tack coat is to be applied shall be and from dust, dirt
requirements of appropriate.
Immediately before the application of the tack coat the surface shall be
swept clean with a mechanical broom and high pressure air jet or by other
The application of task coat shall be rate specified in the contrite , and shall
contract then it shall be at the rate specified in the below table. The normal
geosynthetic is proposed for use the provisions shall apply. The method of
application of the tack coat will depend of forward movement. The contractor
that has not been subjected to traffic or contaminated by dust a tack coat is
The task coat shall be left to cure until the entire have approved before any
the task coat other than those essential for the construction.
13.3.5 RATE
The contrite unit rate for granular sub-base shall be payment in full for
royalties, fees, rent where necessary and all leads and lifts.
3) All labour tools equipment to completed the work to the specification;
4) Carrying out the work in the part widths of road where directed and;
5) Carrying out the required test for quality.
(1)To (5) and as applicable to the work specified in these specification.
The rate shall cover the provision of task 0.2 kg square meter, with in
14.BITUMINOUS CONCRETE:-
14.1 Scope
14.2 Materials
14.2.1 Bitumen
Bituminous Works.
micron sieve. They shall be clean, hard, durable, dry and free from dust, and
The fine aggregate shall have a sand equivalent value of not less than 50
when tested in accordance with the requirement of IS: 2720 (Part 37). The
plasticity index of the fraction passing the 0.425 mm sieve shall not exceed
14.2.4 Filler
Where the aggregates fail to meet the requirements of the water sensitivity
test in below Table then 2 per cent by total weight of aggregate, of hydrated
When tested in accordance with IS: 2386 Part 1 (wet sieving method), the
combined grading of the coarse and fine aggregates and added filler shall fall
Apart from conformity with the grading and quality requirements for
individual ingredients, the mixture shall meet the requirements set out in
below Table. The requirements for minimum per cent voids in minemal
mixture set Out in below Table and the traffic volume specified in the
Contract. The Marshall method for determining the optimum binder content
by the Engineer.
The procedure for formulating the job mix formula shall be generally and the
sample)
**The water sensitivity test is only required if the minimum retained coating
Note: 1.The combined aggregate grading shall not very from the low limit on
14.3.5 Geosynthetics
aggregates, the hot mix plant shall be calibrated from time to time.
cold feed combined grading is within the grading limits specified for that
bituminous bound material, in the case of a designed job mix, the bitumen
and filler content shall be derived using this combined grading. Further
Bituminous Works.
14.4 Spreading
paving machine. As soon as possible after arrival at site. The materials shall
The rate of delivery of material to the paver shall be regulated to enable the
paver to operate continuously. The travel rate of the paver, and its method of
bituminous material across the screen, free from dragging, tearing, and
mechanical paver cannot be used, the material shall he spread, raked and
levelled with suitable hand tools by experienced staff, and compacted to the
satisfaction of the Engineer.
accordance with the minimum values given in the relevant parts of these
expansion joint of a structure, machine laying shall stop 3mm short of the
joint. The remainder of the pavement up to the joint, and the corresponding
area beyond it, shall be laid by hand, and the joint or joint cavity shall be
against heat damage have been approved by the Engineer. Hand placing of
circumstances:
(1) For laying regulating courses of irregular shape and varying thickness.
(ii) In confined spaces where it is impracticable for a paver to operate. (iii) For
footways.
structures.
(i) At the edges of the layers of materials and at gullies and manholes.
14.5 Rolling
After this, rolling shall commence at the edges and progress towards the
cambered portions, it shall progress from the lower to the upper edge
parallel to the center line of the pavement. Rolling shall continue until all
roller marks have been removed from the surface. All deficiencies in the
surface after laying shall he made good by the attendants behind the paver,
having nine wheels, with a tyre pressure of at least 5.6 kg/sqcm. The finish
The newly laid surface shall not be open to traffic for at least 24 hours after
lying and the completion of compaction, without the express approval of the
Engineer in writing.
Engineer.
14.5.4 Rate
The contract unit rate for Dense Graded Bituminous Macadam shall be
payment in full for carrying out the all required operations as specified, and
shall include, but not necessarily limited to all components. The rate shall
include the provision of bitumen, 4.25 per cent by weight of the total
mixture.
The variance in actual percentage of bitumen used will be assessed and the
include the provision of bitumen at 5.0 per cent, by weight of the total
Marshal test
15.1 Scope
This work shall consist of the application of one coat or two coats of surface
15.2 Materials
15.2.1 Binder
The binder shall have a kinematic viscosity lying in the range 1 x 104 to 7 x
construction site during the period of laying. The type of binder to be used
will be stated in the Contract documents and shall comply with one of the
following:
15.2.2 Aggregates
(i)Coarse aggregates
The coarse aggregates shall consist of crushed rock, crushed gravel or other
hard material retained on the 2,36 mm sieve. They shall be clean, hard, and
durable, of cubicle shape, free from dust and soft or friable matter. organic
aggregates have poor affinity for bitumen, as a condition for the approval of
payment. Before approval of the source, the aggregates shall be tested for
stripping.
cent and they shall have a Polished Stone Value, as measured by the method
given in BS: 812 (Part 114), of not less than 60. The chips shall be single
sized, clean. hard, durable, of cubical shape, free from dus: and soft or
For the purpose of pricing the Bill of Quantities the rates of spread given in
Where the proposed aggregate fails to pass the stripping test then an
approved adhesion agent (Appendix 5 for details) may be added to the binder
before approval by the Engineer. Dust removed in the process shall be blown
coated before they are spread except when the sprayed binder film is a
bitumen emulsion. Pre-coating the chips may be carried out in any one of
(a) Mixing them with 0.75 to 1.0 per cent of paving bitumen by weight of
chips in a suitable mixer, the chips being heated to 1600C and the bitumen
for at least one week or until they become non sticky and can be spread
easily.
(b) Spraying the chips with a light application of creosote. Diesel oil or
surface to be covered, or during rain, fog and dust storms. After rain, the
bituminous surface, prime or tack coat shall be blown off with a high
pressure air jet to remove excess moisture, or the surface left to dry before
laying shall start. Laying of bituminous mixtures shall not be cal Tied out
The base on which the surface dressing is to laid shall be prepared, shaped
and conditioned to the specified lines, grade and cross section in accordance
existing surface shows signs of fatting up, the excess bitumen shall be
by the Engineer. The prepared surface shall be dust free, clean and dry,
(except in the case of cationic emulsion where the surface shall be damp).
The equipment and general procedures shall all be in accordance with the
below Table.
The equipment and general procedures shall all be in accordance with the
application of binder, clean, dry chips (in the case of emulsion binder the
15.3.5 Rolling
roller. Traditional steel wheeled rollers tend to crush the aggregates and if
their use cannot be avoided their weight should be limited to 8 tones. Rolling
shall commence at the edges and progress towards the centre except in
from the lower edge to the higher edge. Each pass of the roller shall
uniformly overlap not less than one-third of the track made in the preceding
continue until all aggregate particles are firmly embedded in the binder and
Where surface dressing in two coats is specified, the second coat should not
be applied until the first coat has been open to traffic for 2 or 3 weeks. The
surface on which the second coat is laid must be clean and free of dust. The
construction operations for the second coat shall be the same as described.
Traffic shall not be permitted to run on any newly surface dressed area until
the following day. In special circumstances, however, the Engineer may allow
the road to be opened to traffic immediately after rolling, hut in such cases
traffic speed shall be limited to 20 km per hour until the following day.
All works performed shall conform to the lines, grades, cross sections and
For control on the quality of materials and works carried out, the relevant
accordance with 1he Contractor shall at all times carry out work on the
consistent with the satisfactory execution of the same. For all works
accordance with the directives of the Engineer, provide and maintain, during
execution of the work, a passage for traffic either along a part of the existing
close to the highway. The Contractor shall take priot approval of the
Each coat of surface dressing shall be measured as finished work, for tire
15.3.11 Rate
The Contract unit rate for surface dressing, based on the notional rates of
spread for binder and each size of chippings, which shall be adjusted, plus
or minus, for the, difference between the notional rates of spread and the
by the rates entered in the Bill of Quantities for binder and each size of
chipping.
The contract unit rate for premixed bituminous material shall be payment in
full for carrying out the required operations including full compensation for,
(i) Making arrangements for traffic to except for initial treatment to verge,
arrangement for stock yards. all royalties, fees, rents where necessary and
(v) All labour, tools, equipment, plant including installation of hot mix plant,
power supply units and all machinery, incidental to complete the work to
these Specifications;
(vi) Carrying out the work in part widths of the road where directed; (vii)
(viii) The rate shall cover the provision of bitumen at the rate specified in the
(ix) The rates for premixed material are to include for all wastage in cutting
joints etc.
(x) The rates are to include for all necessary testing, mix design,
specific laboratory, the Contractor must arrange to carry out all necessary
incurred arc deemed to be included in the rate quoted for the material.
(xi) The cost of all plant and laying trials as specified to prove the mixing and
material.
16. SEPARATOR:-
16.1 Scope
lines levels and dimensions shall be as per the drawings. The scope of the
drawings or as directed.
16.2 Materials
The footpaths and separators shall be constructed with any of the following
types:
specifications:
(c) Natural stone slab cut and dressed from stone of good and sound quality,
thickness of the natural stone slab shall be 25 mm and minimum size shall
Drainage pipes below the footpath originating from the kerbs shall be first
Portion on back side of kerbs shall be filled and compacted with granular
15.
cement-sand mortar (1:3) laid on prepared base in such a way that there is
not rocking. The gaps between the blocks/tiles/slabs shall not be more than
kerbs.
16.3.4 Rates
17. References:-
4. Design standards for structure accordance with IRC: 5- 1998, IRC: 38,
6.Material specification by IS:1077 for bricks IS:1124 for stones ,IS:210 for
part40(BS-British standards)BS:1377.
with IS:2720(part).
9. For granular sub-base the water absorption value of the coarse aggregate
soundness test shall be carried out on the material delivery to site as per
IS:383.
10. For prime coat the porosity characteristics of the surface to be primed as
requirements of IS: 8887 & for bituminous temperature in the shade is less
than 100c.
11. For task coat shall be a bituminous emulsion complying with IS:888 &
18. Conclusion:-
and the life of flexible pavements (highway road) will also increases.
flexible pavement and we can say that highway can be useful for the