You are on page 1of 140

DEPARTMENT OF CIVIL ENGINEERING 2010-2014

1. INTRODUCTION:-

A highway pavement is a structure consisting of superimposed layers of

processed materials above the natural soil sub- grade. The payment

structure should be able to provide a surface of acceptable riding quality,

adequate skid resistance, favourable light reflecting characteristics, and low

noise pollution. The ultimate aim is to ensure that the transmitted stresses

due to wheel load are sufficiently reduced so that they will not exceed

bearing capacity of the sub-grade. Two types of pavements are generally

recognized as serving this purpose, namely flexible pavements and rigid

pavements. This chapter gives an overview of pavement types, layers, and

their functions, and pavements failures. Improper design of pavements leads

to early failure of pavements affecting the riding quality.

2. TYPE OF PAVEMENTS:-

The pavements can be classified based on the structural performance into

two, flexible pavements and rigid pavements. In flexible pavements. Wheel

loads are transferred by grain-to-grain contact of the aggregate through the

granular structure. The flexible pavement, having less flexural strength, acts

like a flexible sheet (e.g. bituminous road). On the contrary, in rigid

pavements, wheel loads are transferred to sub-grade soil by flexural strength

of the pavements and the pavements are also available. A thin layer of

flexible pavement over rigid pavement is an ideal pavement with most

desirable characteristics. However, such pavements are rarely used in new

construction because of high cost and complex analysis required.

2.1 Flexible Pavements

Flexible pavements will transmit wheel load stresses to the lower layers by

grain-to-grain transfer through the points of contact in the granular

structure (see Figure).

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Load transfer in granular structure

2.2 Deflection on flexible pavement

The wheel load acting on the pavement will be distributed to a wider area,

and the stress decreases with the depth. Taking advantage of these stress

distribution characteristic, flexible pavements normally has many layers.

Hence, the design of flexible pavement uses the concept of layered system.

Based on this, flexible pavement may be constructed in a number of layers

and the top layer has to be of best quality to sustain maximum compressive

stress, in addition to wear and tear. The lower layers will experience lesser

magnitude of stress and low quality material can be used. Flexible

pavements are constructed using bituminous materials. These can be either

in the form of surface treatments (such as bituminous surface treatments

generally found on low volume roads) or, asphalt concrete surface courses

(generally used on high volume roads such as national highways). Flexible

pavement layers reflect the deformation of the lower layers on to the surface

layer (e.g., if there is any undulation in sub-grade then it will be transferred

to the surface layer), In the case of flexible pavement, the design is based on

overall performance of flexible pavement, and the stresses produced should

be kept well below the allowable stresses of each pavement layer.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

2.3 Types of Flexible Pavements

The following types of constructiowhave been used in flexible pavement:

Conventional layered flexible pavement,

Full - depth asphalt pavement, and

Contained rock asphalt mat (CRAM).

2.3.1 Conventional flexible pavements are layered systems with high

quality expensive materials are placed in the top where stresses are high. aud low

quality cheap materials are placed in lower layers.

2.3.2 Full - depth asphalt pavements are constructed by placing

bituminous layers directly on the soil sub-grade. This is more suitable when there

is high traffic and local materials are not available.

2.3.3 Contained rock asphalt mats are constructed by placing dense/open


graded aggregate layers in between two asphalt layers. Modified dense graded

asphalt concrete is placed above the sub-grade will significantly reduce the vertical

compressive strain on soil sub-grade and protect from surface Waler.

2.4 Typical layers of a flexible pavement

Typical layers of a conventional flexible pavement includes seal coat, surface

course, tack coat, binder course, prime coat, base course, sub-base course,

compacted sub-grade, and natural sub- grade.

2.4.1 Seal Coat

Seal coat is a thin surface treatment used to water-proof the surface and to

provide skid resistance.

2.4.2 Tack Coat

Tack coat is a very light application of asphalt, usually asphalt emulsion

diluted with water. It provides proper bonding between two layers of binder

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

course and must be thin, uniformly cover the entire surface, and set very

fast.

2.4.3 Prime Coat

Prime coat is an application of low viscous cutback bitumen to an absorbent

surface like granular bases on which binder layer is placed. It provides

bonding between two layers. Unlike tack coat, prime coat penetrates into the

layer below, plugs the voids, and forms a water tight surface.

2.4.4 Surface course

Surface course is the layer directly in contact with traffic loads and generally

contains superior quality materials. They are usually constructed with

dense graded asphalt concrete (AC). The functions and requirements of this

layer are:

It provides characteristics such as friction, smoothness, drainage, etc. Also

it will prevent the entrance of excessive quantities of surface water into the

underlying base, sub-base and sub-grade,

It must be tough to resist the distortion under traffic and provide a smooth

and skid resistant riding surface,

It must be water proof to protect the entire base and sub-grade from the

weakening effect of water.

2.4.5 Binder course

This layer provides the bulk of the asphalt concrete structure. Its chief

purpose is to distribute load to the base course. The binder course generally

consists of aggregates having less asphalt and doesnt require quality as high

as the surface course, so replacing a part of the surface course by the

binder course results in more economical design.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

2.4.6 Base course

The base course is the layer of material immediately beneath the surface of

binder course and it provides additional load distribution and contributes to

the sub-surface drainage it may be composed of crushed stone, crushed

slag, and other untreated or stabilized materials.

2.4.7 Sub-Base course

The sub-base course is the layer of material beneath the base course and the

primary functions are to provide structural support, improve drainage, and reduce

the intrusion of fines from the sub-grade in the pavement structure If the base

course is open graded. Then the sub-base course with more fines can serve as filler

between sub-grade and the base dourse A sub-base course is not always needed or

used. For example, a pavement constructed over a high quality, stiff sub- grade

may not need the additional features offered by a sub-base course. In such

situations, sub base course may not be provided.

2.4.8 Sub-grade

The top soil or sub-grade is a layer of natural soil prepared to receive the

stresses from the layers above. It is essential that at no time soil sub-grade

is overstressed. It should be compacted to the desirable density, near the

optimum moisture content.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

3. INTRODUCTIONS TO THE PROJECT:


Govt. of India through NHAI has taken up the development, maintenance

and management of National Highways under NHDP Phase III programme

of 4/6 lining of 10,000 km length of highways on BOT basis, where the

intensity of traffic has increased significantly and to augment the capacity

for safe and efficient movement of traffic.

National Highway No.18 starts from Cuddapah (km 167.750) to Kurnool (km

356.502) Via Maidukur, Allagadda, Nandyal & Panyam. Total length of

highway is located in Andhra Pradesh, connecting NH: 7 @ Kurnool

Cuddapah - Kurnool (188.75Km) stretch of NH: 18 in Andhra Pradesh one of

the corridors taken up for augment the capacity under NHDP Phase III

programme. The project highway passes through Cuddapah and Kurnool

districts. A sit location map is enclosed in executive summary.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

4. PRELIMINARY INVESTUGATION:

4.1 General

The sub grade provides a foundation for supporting the pavement structure.

As a result, the required pavement thickness and performance obtained

From the pavement during its design life will depend largely upon the

strength and uniformity of the sub grade. Therefore, insofar as is

economically feasible, a through investigation of the sub grade should be

made so that design and construction.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Will ensure uniformity of support for the pavement structure and realization

of the maximum strength potential for the particular sub-grade soil type.

The importance of soil and moisture conditions under the pavement cannot

be over-emphasized with respect to frost action.

4.2 Investigation of site


Characteristic of sub grade soils and peculiar feature of the site must be

known to predict pavement performance investigations should determine the

general suitability of the sub grade soils based on classification of the soil,

moisture-density relation, degree to which the soil can be compacted,

expansion charecteristics,susceptibility to pumping, and susceptibility to


detrimental frost action. Such factors as groundwater, surface infiltration,

soil capillarity, topography, rainfall, and drainage conditions also will affect

the future support rendered by the sub grade by increasing its moisture

content and thereby reducing is strength. Past performance of existing

pavements over a minimum of 5 years on similar local sub grades should be

used to confirm the proposed design criteria.

Sub surface investigation and laboratory tests for proposed National

Highway project The objective of the exploration work was to determine the

probable sub surface Conditions such as stratification, denseness or hard

ness of the strata, position of groundwater table etc. and to evaluate

probable range of safe bearing capacity for the structure. To fulfil objective,

the work carried out is comprises of;

Drilling one borehole up to the depth of 10.0m below existing ground


level in order to know the sub surface satratification, conducting
necessary field tests and to collect disturbs and undisturbed soil
samples for laboratory testing.
Testing soil samples in the laboratory to determine its physical and
engineering properties of the soil samples, and

4.2.1 Alignment

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

The existing 2-lane carriageway alignment has number of sharp horizontal

and vertical curves which require geometric corrections and the existing

gradient of the highway in within acceptable limits, as per IRC: 73 in the

stretch of the highway where it passes through plain terrain. The existing

alignment in the rolling and mountainous terrain stretches from km

306.500 to km 322.000 requires grade correction as per IRC:SP:48-1998

Hill Road manual Widening options of this stretch will be studied in detail

keeping in the movement of existing traffic during construction,

environmental impact if hill is cut for widening purpose etc. The existing

alignment runs bisection the existing irrigation tank at km 351.800 near

Thandrapadu village for approximately 200m length on about 3.0m high


embankment,

Rocky outcrop is close to existing alignment from km 306.500 to km

322.000. This rock may be required to be cut/chipped for widening of

the existing road to 4-lane.


The alignment does not run in high embankment except on

approaches to major bridges, where the height of embankment is up

to 5m. Generally the existing road is on 0.5, to 2.5m high

embankment.
The alignment of project road passes through number of built-up

sections. The list of built-up areas and locations are shown in the

Table 1.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

4.2.2 Climate

The climate along the road is generally hot. Annual rainfall for year 2004-

2005@Cuddapah and Kurnool are as below. The average annual rainfall is

less than 1300mm. The weather pleasant during November to January.

Rainfall and temperature Recorded during 2005-2006 are shown below.

4.2.3 Carriageway width

The existing carriageway width is 7.0m expect at built up locations and

approaches to major towns. A brief detail of carriageway width is shown in

Table2.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

4.3 Pavement condition

The existing pavement has distressed at number of stretches due to


presence of irrigation water on both sides. Recently overlay/patch has been
carried out to improve the riding quality of the surface. The existing

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

pavement condition based on visual observation varies from poor to good.


The details of visual observation regarding pavement condition are given in
Table3.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

4.4 Major junctions and cross roads

Six state Highways cross/take off from NH: 18. One major junction is at
Nandyal @ km 289.000 with a road to Nandyal and another is with MDR-24
@ panyam(km 303.030).The details of junction are shown in Table4.There is
no signalized junction on this stretch of highway.

4.4.1 Cross-roads

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

There are number of side roads that take-off/meet NH: 18 from Cuddapah
to Kurnool stretch. The roads include state highways, MDRs, ODRs and
village roads. The details are shown below:

4.4.2 Land use

Type of soil along the project road includes red gravely soil, silty sand, BC

soil with gravel and black soil with gravel. Land use along the highway is

predominantly for agriculture. Majority of the land is being used for wet

crops viz. Paddy, Sugarcane etc. There are number of settlements all along

the road. The Settlements are for Residential, Commercial, Schools,

Hospitals, petrol stations etc. Major settlements are close to the existing

highway at number of locations. Existing highway requires geometric

corrections at Khajipeta, Maidukuru, Chintakunta, Gudipadu and Duvvuru

villages. Alignment is straight in Chagalamarri village and Allagadda town.

Public have encroached existing ROW in Nandyal from Km 285.000 to Km

292.000

4.4.3Traffic flow conditions

Traffic on this section of NH: 18 are of mixed type. Number of passenger

vehicles viz. buses and cars are more than the commercial vehicles & these

vehicles include 2-axle, 3-axle trucks and LCVs. Local traffic is more in the

urban/ semi-urban stretches of the project road. Relatively traffice is more

from Nandyal to Kurnool compared to Cuddapah to Nandyal stretch of NH:

18.

These are no bus-bays and no parking lay-byes for commercial vehicles. It

was observed during reconnaissance survey that a number of commercial

vehicle are being parked from km 282.750 to km 289.000 on Nandyal

bypass creating congestion for smooth flow of traffic.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Bearing capacity of the soil forgiven foundation sizes and necessary

recommendations for foundation design and construction.

4.4.4. Soil Conditions

Soil conditions should be investigated by a combination of a general survey

of sub grade conditions, preliminary subsurface investigations, and soil

borings.

4.5 General Survey of sub grade Conditions


Sources of data should include the landforms, soil conditions in ditches,

and cuts and tests of Both natural and subsurface drainage of the sub grade

must be considered.

4.5.1 Preliminary Subsurface Explorations.

(i) Soil

Soil samples from the preliminary borings should be classified and the data

used to prepare soil profiles and to select representative soils for further

testing. Measurements should include moisture contents which indicate

soft layers in the soil.

(ii) Borrow Areas

Where material is to be borrowed from adjacent areas, subsurface

explorations should these areas and carried 2 to 4 feet below the anticipated

depth of borrow. Samples from the explorations should be classified and

tested for moisture content and compactions characteristics.

5. DESIGN STANDARDS AND GUIDANCE:-


The design of highway and structures will be bases of design standards.

The design features/requirements are in accordance with the TOR and

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

bases on relevant IRC codes, MORTH & BIS specifications. Details are

mentioned in subsequent sections.

5.1 Design standards for Road

The detailed geometric design will be worked out as er standards and

following design requirements mentioned in below Table. These

requirements will be reviewed further in relation to the design traffice and

capacity of roadway in consultation with NHAI. Typical corss sections for 4-

lane divided carriageway for symmetrical widening, left / right widening and

widening proposal in built-up sections with service roads are prepared as

per IRC:73-1980 and enclosed.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

5.2 Design Standards for Structures


All structure will be windened to 3 lane requirements in each direction. The
general design standard to be followed are enclosed in Table6.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

In general, IRC standard codes to which the design shall conform to are:

1) IRC:5 (Sec-I) : General features of Design

2) IRC:6 (Sec-II)-2000 : Loads and stresses

3) IRC:SP-13 : Design of small culverts and bridges

4) IRC:18-2000 : Post tensioned concrete

5) IRC:21(Sec III)-2000 : Cement Concrete(Plain and reinforced)

6) IRC:22-1985 : Composite construction

7) IRC:78(Sec VII)-2000 : Foundations and Substructure

8) IS:14268-1995 : Low relaxation strands

9) IS:1893-1984(Reaffirmed1991):Earthquake loads

10) IS: 2911(part I) : Design and construction of board cast


in-situ piles

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

11) IRC: 83 : Bearings

5.3 Road drainage


Pavement surface drainage, shoulder and open drainage will be designed as

per IRC: SP: 42-1994 (guidelines on Road Drainage) and sub surface

drainage as per IRC: 37(Guidelines for the design of flexible pavements).

5.3.1 signage/pavement marking/pick up bus stops and


Ancillary works

Consultant site reconnaissance/inventory survey indicates need for

improvement in the project road stretch regarding following facilities for safe

and smooth traffic flow:

Provisions of kilometer stones and crash barriers at high

embankment (design basics:IRC:8-1980 & IRC :26-1967)

Provision of reflective thermoplastic pavement markings, cats eye

etc(design basic: IRC :35-1997)

Provision of retro-reflective road (design basic:IRC:67-2001)

Provision of road delineators IRC :79-1981

Solar powered junction lights using 36 volts battery (manufacturers

standard)

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

6. MATERIALS SPECIFICATIONS:
Materials specifications to be used in the construction of road and

structures will be based on the MORTH Specifications for road and bridge

works (Fourth Revision) 2001 published by IRC.

6.1 General

Materials to be used in the work shall conform to the specifications

mentioned on the drawings, the requirements laid down in this section and
specifications for relevant items of work covered under these specifications.

If any material, not covered in these specifications, is required to be used in

the work, it shall conform to relevant Indian Standards, if there are any, or

to the requirements specified by the Engineer.

6.2 Sources of materials

The Contractor shall notify the Engineer of his proposed sources of material

sprier to delivery. If it is found after trial that sources of supply previously

approved do not produce uniform and satisfactory products, or if the

product from any other source proves unacceptable at any time, the

Contractor shall furnish acceptable material from other sources at his own

expense.

6.2.1 Stones

Stones shall be of the type specified. It shall be hard, sound, free from

cracks, decay and weathering and shall be freshly quarried from an

approved quarry. Stone with round surface shall not be used. The stones,

when immersed in water for 24 hours, shall not absorb water by more than

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

5 per cent of their dry weight when tested in accordance with IS: I 124.The

length of stones shall not exceed 3 times its height nor shall they be less

than twice its height plus one joint. No stone shall be less in width than the

height and width on the base shall not be greater than three-fourth of the

thickness of the wall nor less than 150 mm.

6.2.2 Cement

Cement to be used in the works shall be any of the following types with the

prior approval of the Engineer:

a) Ordinary Portland cement, 33 Grade, conforming to IS: 269.

b) Rapid Hardening Portland cement, conforming to IS: 8041.

c) Ordinary Portland cement, 43 Grade, conforming to IS: 8112.

d) Ordinary Portland cement, 53 Grade, conforming to IS: 12269.

e) Sulphate Resistant Portland cement, conforming to IS: 12330.

Cement conforming to IS: 269 shall be used only after ensuring that the

minimum required design strength can be achieved without exceeding the

maximum permissible cement content of 540 kg/cu. m. of concrete.

Cement conforming to IS: 8112 and IS: 12269 may be used provided the

minimum cement content mentioned elsewhere from durability

considerations is not reduced. From strength considerations, these cements

shall be used with a certain caution as high early strengths of cement in the

I to 28-day range can be achieved by finer grinding and higher constituent

ratio of C3S/C2S. where C3S is Tn calcium Silicate andC2S is Di calcium

Silicate. In such cements, the further growth of strength beyond say 4weeks

may be much lower than that traditionally expected. Therefore, further

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

strength tests shall be carried out for 56 and 90 days to fine tune the mix

design from strength considerations. Cement conforming to IS: 12330 shall

be used when sodium sulphate and magnesium sulphate are present in

large enough concentration to be aggressive to concrete. The recommended

threshold values as per IS: 456 are sulphate concentration in excess of 0.2

percent in soil sub-strata or 300ppm (0.03 percent) in ground water. Tests to

confirm actual values of sulphate concentration are essential when the

structure is located near the sea coast. chemical factories and agricultural

land using chemical fertilizers and sites where there are effluent discharges

or where soluble sulphate bearing ground water level is high. Cement

conforming to IS: 12330 shall be carefully selected from strength


considerations to ensure that the minimum required design strength can be

achieved without exceeding the maximum permissible cement content of

540 kg/cu.m. of concrete .Cement conforming to IS: 8041 shall be used only

for precast concrete products after specific approval of the Engineer.

Total chloride content in cement shall in no case exceed 0.05 per cent by

mass of cement.

6.2.3 Coarse aggregates

For plain and reinforced cement concrete (PCC and RCC) or pre stressed

concrete(PSC) works, coarse aggregate shall consist of clean, hard, strong,

dense, non-porous and durable pieces of crushed stone, crushed gravel,

natural gravel or a suitable combination thereof or other approved nert

material. They shall not consist pieces of disintegrated stones, soft, flaky,

elongated particles, salt, alkali, vegetable matter or other deleterious

materials in such quantities as to reduce the strength and durability of the

concrete, or to attack the steel reinforcement. Coarse aggregate having

positive alkali-silica reaction shall not be used. All coarse aggregates shall

conform to IS: 383 and tests for conformity shall be carried out as per IS:

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

2386, Parts Ito Viii. The contractor shall submit for the approval of the

Engineer, the entire information indicated in Appendix A of IS: 383.

Maximum nominal size of coarse aggregate for various structural

components in PCC, RCC or PSC.The maximum value for flakiness index for

coarse aggregate shall not exceed 35 per cent. The coarse aggregate shall

satisfy the following requirements of grading:

6.2.4 Sand/fine aggregates

For masonry work, sand shall conform to the requirements of IS: 2116. For

plain and reinforced cement concrete (PCC and RCC) or pre stressed

concrete (PSC) works, fine aggregate shall consist of clean, hard, strong and

durable pieces of crushed stone, crushed gravel, or a suitable combination

of natural sand, crushed stone or gravel. They shall not contain dust,

lumps, soft or flaky, Materials, mica or other deleterious materials in such

quantities as to reduce the strength and durability of the concrete, or to

attack the embedded steel. Motorized sand washing machines should be

used to remove impurities from sand. Fine aggregate having positive alkali-

silica reaction shall not be used. All fine aggregates shall conform to IS: 383

and tests for conformity shall be carried out as per IS :( Parts I to VIII). The

Contractor shall submit to the Engineer the entire information indicated in

Appendix A of IS: 383. The fineness modulus of fine aggregate shall neither

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

be less then 2.0 nor greater than 3.5.SandJfine aggregate for structural

concrete shall conform to the following grading requirements:

6.25 Steel

The use of cast steel shall be limited to bearings and other similar parts.
Steel for castings shall conform to Grade 280-520N of IS: 1030. In case

where subsequent welding is unavoidable in the relevant cast steel

components, the letter N at the end of the grade designation of the steel

casting shall be replaced by letter W. 0.3 percent to 0.5 per cent copper may

be added to increase the corrosion resistance properties.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

7. EMBANKMENT TOP LAYER:-

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

7.1 General
These Specifications shall apply to the construction of embankments

including sub-grades, earthen shoulders and miscellaneous backfills with

approved material obtained from roadway and drain excavation, borrow pits

or other sources. All embankments, sub-grades, earthen shoulders and

miscellaneous backfills shall be constructed in accordance with the

requirements of these Specifications and in conformity with the lines, and

cross-sections shown on the drawings or as directed by the Engineer.

7.2 Materials and General Requirements

7.2.1 Physical requirements

The material used in embankments, sub-grades, earthen shoulders and

miscellaneous backfills shall be soil, morum, gravel, a mixture of these or

any other material approved by the Engineer. Such materials shall be free of

logs, stumps, roots, rubbish or any other ingredient likely to deteriorate or

affect the stability of the embankment/sub-grade.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

The following types of material shall be considered unsuitable for

embankment:

(a) Materials from swamps, marshes and bogs;


(b) Peat, log, stump and perishable material; any soil that classifies as OL,

OI, OH or Pt in accordance with IS: 1498;


(c) Materials susceptible to spontaneous combustion;
(d) Materials in frozen conditions
(e) Clay having liquid limit exceeding 70 and plasticity index exceeding 45;

and
(f) Material with salts resulting in leaching in the embankment.

Expansive clay exhibiting marked swell and shrinkage properties (free

swelling index exceeding 50 percent when tested as per IS:2720-Part 40)

shall not be used as a fill material. Where expansively clay with acceptable

free swelling index value is used as a fill material, sub-grade and top 500

mm portion of the embankment just below sub-grade shall be non-

expansive in nature. Any fill material with a soluble sulphate content

exceeding 1.9 grams of sulphate (expressed as SO3) per liter when tested in

accordance with BS: 1377, but using a 2:1 water-soil ratio shall not be

deposited within 500 mm or other distance described in Earthwork, Erosion

Control and Drainage the Contract, of concrete, cement bound materials or

other cementations material forming part of the Permanent works.

Materials with a total sulphate content (expressed as SO3) exceeding 0.5 per

cent by mass, when tested in accordance with BS: 1377 shall not be

deposited within 500 mm, or other distances described in the Contract, of

metallic items forming part of the Permanent Works.

The size of the coarse material in the mixture of earth shall ordinarily not

exceed 75 mm when being placed in the embankment and 50 mm when

placed in the sub-grade. However, the Engineer may at his discretion permit

the use of material coarser than this also if he is satisfied that the same will

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

not present any difficulty as regards the placement of fill material and its

compaction to the requirements of these Specifications.

The maximum particle size shall not be more than two-thirds of the

compacted layer thickness. Ordinarily, only the materials satisfying the

density requirements given in Table shall be employed for the construction of

the embankment and the sub-grade.

Notes :( 1) this is not applicable for lightweight fill material e.g. cinder, fly

ash etc.

(2) The Engineer may relax these requirements at his discretion taken into

account the available of materials for construction and other relevant

factors.

(3) The material to be used in sub-grade should also satisfy design CBR at

the dry unit weigh applicable as per Table10.

7.2.2 Borrow materials

Where the materials are to be obtained from designed borrow areas, the

location, size and shape of these areas shall be as indicated by the Engineer

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

and the same shall not be opened without his written permission. Where

specific borrow areas are not designed by the Employer/the Engineer,

arrangement for locating the source of supply of material for embankment

and sub-grade as well as compliance to environmental requirements in

respect of excavation and borrow areas as stipulated, from time to time by

the Ministry of Environment and Forests, Government of India and local

bodies, as applicable, shall be sole responsibility of the Contractor.

Borrow pits along the road shall be discouraged. If permitted by the

Engineer, these shall not be dug continuously. Ridges of not less than 8 m

width should be left at not exceeding 300 m. Small drains shall be cut

through the ridges to facilitate drainage. The depth of the pits shall be so
regulated that their bottom does not cut an imaginary line having a slope of

1 vertical to 4 horizontal projected from the edge of the final section of the

bank, the maximum depth in any case being limited to 1.5 m. Also, no pit

shall be dug within the offset width from the toe of the embankment

required as per the consideration of stability with a minimum width of 10 m.

Haulage of material to embankments or other areas of fill shall proceed only

when sufficient spreading and compaction plant is operating at the place of

deposition.

No excavated acceptable material other than surplus to requirements of the

Contract shall be removed from the site Contractor be permitted to remove

acceptable material from the site to suit his operational procedure, then he

shall make good any consequent deficit of material arising there from. Where

the excavation reveals a combination of acceptable and unacceptable

material, the Contractor shall, unless otherwise agreed by the Engineer,

carry out the excavation in such a manner that the acceptable materials are

excavated separately for use in the permanent works without contamination

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

by the unacceptable materials. The acceptable materials shall be stockpiled

separately.

The Contractor shall ensure that he does not adversely affect the stability of

excavation or fills by the respective samples from each of the identified

borrow areas and have these tested at the size laboratory following a testing

programme approved by the Engineer. It shall be ensured that the sub-grade

material when compacted to the density requirements as in Table10 shall

yield the design CBR value of the sub-grade.

The Contractor shall at least 7 working days before commencement of

compaction submit the following to the engineer for approval:

i) The values of maximum dry density and optimum content obtained

in accordance with Is 2720 (Part 7) or (Part 8) as the case may be,

appropriate for each of the fill material he intends to use.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

ii) A graph of density plotted against moisture content from which

each of the values in (i) above of maximum dry density and

optimum moisture content were determined.


iii) The dry density-moisture content-CBR relationships for light,

intermediate and heavy capacitive efforts (light corresponding to IS:

2720 (Part 7), heavy corresponding to IS: 2720 (Part 8) and

intermediate in-between the two) for each of the fill materials he

intends to use in the sub-grade.

Once the above information has been approved by the Engineer, it

shall from the basis for compaction.

7.3 Construction Operations

7.3.1 Setting out

The limits of embankment/sub-grade shall be marked by fixing better

pegs on both sides at regular intervals as guides before commencing the

earthwork. The embankment/sub-grade shall be built sufficiently wider

than the design dimension so that surplus material may be trimmed,

ensuring that the remaining material is to the desired density and in

position specified and conforms to the specified side slopes.

7.3.2 Dewatering

If the foundation of the embankment is in an area with stagnant water, and

in the opinion of the Engineer it is feasible to remove it, the same shall be

removed by bailing out or pumping, as directed by the Engineer and the area

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

of the embankment foundation shall be kept dry. Care shall be taken to

discharge the drained water so as not to cause damage to the works, crops

or any other property. Due to any negligence on the part of the Contractor,

if any such damage is caused, it shall be the sole responsibility of the

Contractor to repair/restore it to original condition or compensate the

damage at his own cost.

7.3.3 Stripping and string topsoil

In localities where most of he available embankment materials are not

conductive to plant growth, or when so directed by the Engineer, the topsoil

from all areas of cutting and from all areas to be covered by embankment
foundation shall be stripped the specified depths not exceeding 150 mm and

stored in stockpiles of heights not exceeding 2 m for covering embankment

slopes. Cut slopes and other disturbed areas where re-vegetation is desired.

Topsoil shall not be unnecessarily trafficked either before stripping or when

in a stockpile. Stockpiles shall not be unnecessarily trafficked either before

stripping or when in a stockpile. Stockpiles shall not be surcharged or

stripping or otherwise loaded and multiple handle shall be kept to a

minimum.

7.3.4 Compacting ground supporting embankment/sub-grade

Where necessary, the original ground shall be levelled to facilitate placement

of first layer of embankment, scarified, mixed with water and then

compacted by rolling so as to achieve minimum dry density as given in

Table. In case where the difference between the sub-grade level (top of the

sub-grade on which pavement rests) and ground level is less than 0.5 m and

the sub-grade level, watered and compacted in layers in accordance to not

less than 97 per cent of dry density as given in Table. Where so directed by

the Engineer, any unsuitable material occurring in the embankment

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

foundation shall be removed and replaced by approved material laid in layers

to the required degree of compaction. Embankment or sub-grade work shall

not proceed until the foundations for embankment/sub-grade have been

inspected by the Engineer for satisfactory condition and approved.

Any foundation treatment specified for embankments especially high

embankments, resting on suspect foundation as revealed by borehole logs

shall be carried out in a manner and to the depth as desired by the

engineer.

7.3.5 Spreading material in layers and bringing to appropriate

moisture content

The embankment and sub-grade material shall be spread in layers of

uniform thickness not exceeding 200 mm compacted thickness over the

entire width of embankment by mechanical means, finished by a motor

grader and compacted .The motor grader blade shall have hydraulic control

suitable for initial adjustment and maintain the same so as to achieve the

specific slope and grade. Successive layers shall not be placed until the

Table layer under construction has been thoroughly compacted to the

specified requirements as in and got approved by the Engineer. Each

compacted layer shall be finished parallel to the final cross-section of the

embankment.

Moisture content of the material shall be checked at the site of placement

prior to commencement of compaction; if found to be out of agreed limits,

the same shall be made good. Where water is required to be added in such

constructions, water shall be sprinkled from a water tanker fitted with

sprinkler capable of applying water uniformly with a controllable rate of flow

variable widths of surface but without any flooding. The water shall be

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

added uniformly and thoroughly mixed in soil by blading, discing or

harrowing until uniform moisture content is obtained throughout the depth

of the layer.

If the material delivered to the roadbed is too wet, it shall be dried, by

aeration and exposure to his sun, till the moisture content is acceptable for

compaction. Should circumstances arise, where owing to wet weather, the

moisture content cannot be reduced to the required amount by the above

procedure, compaction work shall be suspended. Moisture content of each

layer of soil shall be checked in accordance with IS: 2720 (Part 2), and

unless otherwise mentioned, shall he so adjusted, making due allowance for

evaporation losses, that at the time of compaction it is in the range of I per


cent above to 2 per cent below the optimum moisture content determined in

accordance with IS: 2720 (Para 7) or IS: 2720 (Para 8) as the case may be.

Expansive clays shall, however, be compacted at moisture content

corresponding to the specified dry density, but on the wet side of the

optimum moisture content obtained from the laboratory compaction curve.

After adding the required amount of water, the soil shall be processed by

means of graders, harrows. Rotary mixers or as otherwise approved by the

Engineer until the layer is uniformly wet.

Clods or hard lumps of earth shall be broken to have a maximum size of 75

mm when being placed in the embankment and a maximum size of 50 mm

when being placed in the sub-grade.

Embankment and other areas of fill shall, unless otherwise required in the

Contract or permitted by the Engineer, be constructed evenly over their full

width and their fullest possible extent and the Contractor shall control and

direct construction plant and other vehicular traffic uniformly over them.

Damage by construction plant and other vehicular traffic shall be made

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

good by the Contractor with material having the same characteristics and

strength as the material had before it was damaged.

Embankment and other areas of unsupported fills shall not be constructed

with steeper side slopes, or to greater widths than those shown in the

Contract, except to permit adequate compaction at the edges before

trimming back, 01. To obtain the final profile following any settlement of the

fill and the underlying material. Whenever fill is to be deposited against the

face of a natural slope, or sloping earthworks face including embankments,

cuttings, other fills and excavations steeper than 1 vertical on 4 horizontal,

such faces shall be benched immediately before placing the subsequent fill.

All permanent faces of side slopes of embankments and other as of fill


formed shall, subsequent to any trimming operations, be reworked and

sealed to the satisfaction of the Engineer and tracking a tracked vehicle,

considered suitable by the Engineer, the slope or any other method approved

by the Engineer.

7.3.6 Compaction

Only the compaction equipment approved by the Engineer shall be employed

to compact the different material types encountered during construction.

Smooth wheeled, vibratory, pneumatic tvred, sheep foot or pad foot rollers,

etc of suitable size and capacity as approved by the Engineer shall be used

for the different types and grades of materials required to be compacted

either individually or in suitable combinations. The compaction shall be

done with the help of vibratory roller of 80 to 100 KN Static weight with

plain or pad foot drum or heavy pneumatic tyred roller of adequate capacity

capable of achieving required compaction.

The Contractor shall demonstrate the efficacy of the equipment he intends

to use by carrying out compaction trials. The procedure to be adopted for

these site trials shall first be submitted to the Engineer for approval.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Earthmoving plant shall not be accepted as compaction equipment nor shall

the use of a lighter category of plant to provide any preliminary compaction

to assist the use of heavier plant he taken into account.

Each layer of the material shall be thoroughly compacted to the densities

specified in Table Subsequent layers shall be placed only after the finished

layer has been tested according to accepted by the Engineer. The Engineer

may permit measurement of field dry density by a nuclear moisture/density

gauge used in accordance with agreed procedure and the gauge is calibrated

to provide results identical to that obtained from tests in accordance with IS:

2720 (Part 28). A record of the same shall be maintained by the contractor.

When density measurements reveal any soft areas in the embankmen/lsub-

grade/earthen shoulders, further compaction shall be carried out as

directed by the Engineer. If inspite of that the specified compaction is not

achieved, the material& in the soft areas shall be removed and replaced by

approved material, compacted to the density requirements and satisfaction

of the Engineer.

7.3.7 Drainage

The surface of the embankment/sub-grade at all times during construction

shall be maintained at such a cross fall (not flatter than that required for

effective drainage of an earthen surface) as will shed water and prevent

ponding.

7.3.8 Repairing of damages caused by rain/spillage of water

The soil in the affected portion shall be removed in such areas as directed by

thc Engineer before next layer is laid and refilled in layers and compacted

using appropriate mechanical means such as small vibratory roller, plate

compactor or power rammer to achieve the required density in accordance

with. If the cut is not sufficiently wide for use of required mechanical means

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

for compaction, the same shall he widened suitably to permit their use for

proper compaction.

Tests shall be carried out as directed by the Engineer to ascertain the

density requirements of the repaired area. The work of repairing the

damages including widening of the cut, if any, shall be carried out by the

Contractor at his own cost, including the arranging of

machinery/equipment for the purpose.

7.3.9 Finishing operations

Finishing operations shall include the work of shaping and dressing the

shoulders/verge/roadded and side slopes to conform to the alignment,


levels, cross-sections and dimensions shown on the drawings or as directed

by the Engineer subject to the surface tolerance described .Both the upper

and lower ends of the side slopes shall be rounded off to improve

appearance and to merge the embankment with the adjacent terrain. The

topsoil, removed and conserved earlier shall be spread over the fill slopes as

per directions of the Engineer to facilitate the growth of vegetation. Slopes

shall be roughened and moistened slightly prior to the application of the

topsoil in order to provide satisfactory bond. The depth of the topsoil in shall

be sufficient to sustain plant growth, the usual thickness being from 75 mm

to 150 mm. Where directed, the slopes shall be surfed with sods in

accordance. If seeding and mulching of slopes is prescribed, this shall be

done to the requirement.

When earthwork operations have been substantially completed, the road

area shall be cleared of all debris, and ugly scars in the construction area

responsible for objectionable appearance eliminated.

7.4 Construction of Embankment and Sub-grade tinder

special Conditions

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

7.4.1 Earthwork for widening existing road embankment

When an existing embankment and/or sub-grade is to be widened and its

slopes are steeper than I vertical on 4 horizontal, continuous horizontal

benches.

Each at least 300 mm wide, shall be cut into the old slope for ensuring

adequate bond with the fresh embankment/sub-grade material to be added.

The material obtained from cutting of benches could be utilized in the

widening of the embankment/sub-grade. However, when the existing slope

against which the fresh material is to be placed is flatter than I vertical on 4

horizontal, the slope surface may only be ploughed or scarified instead of


resorting to benching. Where the width of the widened portions is

insufficient to permit the use of conventional rollers, compaction shall be

carried out with the help of small vibratory rollers/plate compactors/power

rammers or any other appropriate equipment approved by the Engineer. End

dumping of material from trucks for widening operations shall be avoided

except in difficult circumstances when the extra width is too narrow to

permit the movement of any other types of hauling equipment.

7.4.2 Earthwork for embankment and sub-grade to be placed

against sloping ground

Where an embankment/sub-grade is to be placed against sloping ground,

the latter shall be appropriately benched or ploughed/scarified before

placing the embankment/sub-grade material. Extra earthwork involved in

benching or due to ploughing/scarifying etc. shall he considered incidental

to the work. For wet conditions, benches with slightly inward fall and subsoil

at the lowest point shall be provided as per the drawings. Before the fill is

placed against sloping ground.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Where the Contract requires construction of transverse subsurface drain at

the cut-fill interface, work on the same shall be carried out in proper

sequence with the embankment and sub-grade work as approved by the

Engineer.

7.4.3 Earthwork over existing road surface

Where the embankment is to be placed over an existing road surface, the

work shall be carried out as indicated below

(i) If the existing road surface is of granular or bituminous type and lies

within I m of the new

Sub-grade level, the same shall be scarified to a depth of 50 mm or more if

specified, so as to provide ample bond between the old and new material

ensuring that at least 500 portions below the top of new sub-grade level is

compacted to the desired density.

(ii) If the existing road surface is of cement concrete type and lies within 1 m

of the new sub- grade level the same shall be removed completely.

(iii) If the level difference between the existing road surface and the new

formation level is more than I m, the existing surface shall be permitted to

stay in place without any modification.

7.4.4 Embankment and sub-grade around structures

To avoid interference with the construction of abutments, wing walls or

return walls of culvert/bridge structures, the Contractor shall, at points to

be determined to such structures, until such time as the construction of the

latter is sufficiently advanced to permit the completion of approaches

without the risk of damage to the structure.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Unless directed otherwise, the filling around culverts, bridges and other

structures up to a distance of twice the height of the road from the back of

the abutment shall be carried out independent of the work on the main

embankment. The fill material shall not be placed against any abutment or

wing wall, unless permission has been given by the Engineer but in any case

not until the concrete or masonry has been in position for 14 days.

The embankment and sub-grade shall be brought up simultaneously in

equal layers on each side of the structure to avoid displacement and unequal

pressure. The sequence of work in this regard shall be got approved from the

Engineer.

The material used for backfill shall not be an organic soil or highly plastic

clay having plasticity index and liquid limit more than 20 and 40

respectively when tested according to IS: 2720 (Part 5).

Filing behind abutments and wing walls for all structures shall conform to

the general guidelines given in Appendix 6 of IRC :78 (Standard

Specifications and Code of Practice for Road Bridges-Section VII) in respect

of the type of material, the extent of backfill, its laying and compaction etc.

The fill material shall be deposited in horizontal layers in loose thickness

and compacted thoroughly to the requirements of Table at compaction

required for embankment and sub-grade. Where the provision of any filter

medium is specified behind the abutment, the same shall be laid in layers

simultaneously with the laying requirements for filter medium spelt out in

(B) unless otherwise specified in the Contract.

Where it may be impracticable to use conventional rollers, the compaction

shall be carried out by appropriate mechanical means such as small

vibratory roller, plate compactor or power rammer. Care shall be taken to see

that the compaction equipment does not hit or come too close to any

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

structural member so as to cause any damage to them or excessive pressure

against the structure.

7.4.5 Construction of embankment over ground incapable of

supporting construction equipment

Where embankment is to he constructed across ground which will not

support the weight of repealed heavy loads of construction equipment, the

first layer of the fill may be constructed b placing successive loads of

material in a uniformly distributed layer of a minimum thickness required to

support the construction equipment as permitted by the Engineer.

The Contractor, if so desired by him, may also use suitable geo-synthetic

material to increase the bearing capacity of the foundation. This exception to

normal procedure will not be permitted where, in the opinion of the

Engineer, the embankments could be constructed in the approved manner

over such ground by the use of lighter or modified equipment after proper

ditching and drainage have been provided where this exception is permitted,

the selection of the material and the construction procedure to obtain an

acceptable layer shall be the responsibility of the Contractor.

The cost of providing suitable traffic conditions for construction equipment

over any area of the Contract will be the responsibility of the Contractor and

no extra payment will he made to him.

7.4.6 Embankment construction under water

Where filling or back fulling is to be placed under water, only acceptable

granular material or rock shall be used unless otherwise approved by the

Engineer. Acceptable granular material shall consist of graded, hard durable

particles with maximum particle size not exceeding 75 mm. The material

should be non-plastic having uniformity co-efficient of not less than 10. The

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

material placed in open water shall be deposited by end tipping without

compaction.

7.4.7 Earthwork for high embankment

In the case of high embankments, the Contractor shall normally use the

material from the specified borrow area. In case he desires to use different

material for his own convenience, he shall have to carry out necessary soil

investigations and redesign the high embankment at his own cost. The

Contractor shall then furnish the soil test data and design of high

embankment for approval of the Engineer, who reserves the right to accept

or reject it. If necessary, stage construction of fills and any controlled rates
of filling shall be carried out in accordance with the Contract including

installation of instruments and its monitoring.

Where required, the Contractor shall surcharge embankments or other areas

of fill with approved material for the periods specified in the Contract. If

settlement of surcharged fill results in any surcharging material, which is

unacceptable for use in the fill being surcharged, lying below formation level,

the Contractor shall remove the unacceptable material and dispose it as

PCI. Direction of the Engineer. He shall then bring the resultant level upon

formation level; the Contractor shall remove the unacceptable material and

dispose it as per direction of the Engineer. He shall then bring the resultant

level up to formation level with acceptable material.

7.5 Settlement period

Where settlement period is specified in the Contract, the embankment shall

remain in place for the required settlement period before excavating for

abutment, wing wall, retaining wall, footings, etc., or driving foundation

piles. The duration of the required settlement period at each location shall

be as provided for in the Contract or as directed by the Engineer.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

7.6 Plying of Traffic

Construction and other vehicular traffic shall not use the prepared surface

of the embankment and/or sub-grade without the prior permission of the

Engineer. Any damage arising out of such use shall, however, be made good

by the Contractor at his own expense as directed by the Engineer.

Test for embankment

Free swelling index.

Free swelling index:

Apparatus:

425 Micron IS Sieve-01 no, & l00ml capacity graduated cylinder-02 nos,

kerosene, water, glass, beakers.

Procedure:

1. Take two nos of 10 grams oven dried sample passing through 425 micron

IS Sieve.

2. Take two nos of 100ml capacity graduated cylinder, one filled with

kerosene and another filled with water up to the mark.

3. Each soil specimen shall he poured in each of the two glass graduated

cylinders of 100ml capacity.

4. After removal of entrapped air, the soil in both the cylinder shall be

allowed to settle for 24 hours.

5. Free swell index=VdVk* 100

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Vd=Volume of soil specimen from the graduated cylinder filled with water.

Vk= Volume of soil specimen from the graduated cylinder filled with

kerosene.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

8. SUB-GRADE:-

8.1 SCOPE

This work shall consists of laying and compacting an improved sub-grade

/lower sub-base of soil treated with lime on prepared sub-grade in

accordance with the requirements of these specifications and in conformity

with the lines, grades and cross sections shown on the drawings are as

directed by the Engineer. Lime treatment is generally effective for soils,

which contain a relatively high percentage of clay and silty clay.

8.2 Materials:

Except when otherwise specified, the sol used for stabilization shall be the

local clayey soil having a plasticity index greater than 8.

8.2.2 Lime:

Lime for lime-soil stabilization work shall be commercial dry lime slaked at

or pre-slaked lime delivered to the site in suitable packing. Unless otherwise

permitted by Engineer, the lime shall have purity of not less than 70% by

weight of Quicklime (CaO) when tested in accordance with IS: 1514. Lime

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

shall be properly stored to avoid prolonged exposure to the atmosphere and

consequent carbonation, which would reduce its binding properties.

8.2.3 Quantity of lime in stabilized mix

Quality of lime to be added as percentage by weight of the soil shall be as

specified in the Contract. The quality of lime of different calcium oxide

content, which shall be suitably adjusted to the approval of the engineer so

that equivalent calcium oxide is incorporated in the work. The mix design

shall be done to arrive at the appropriate quantity of lime to be added,

having due regard to the purity of the engineer so that equivalent calcium
oxide is incorporated in the work .The mix design shall be done to arrive3e

at the appropriate quality of lime to be added, having due regard to the

purity of lime, the type of soil, the moisture-density relationship, and the

design CBR/UCS value shall be at least 1.5 times the minimum field value

of CBR/UCS stipulated in the contract.

8.2.4 Water

The water to be used for lime stabilization shall be clean and free from

injurious substances. Potable water shall be preferred.

8.3 Construction Operations

8.3.1 Weather limitations

Lime-soil stabilization shall not be done when the air temperature in the

shade is less than 10 C.

8.3.2 Degree of pulverization

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

For lime stabilization, the soil before addition of stabilizer shall be pulverized

using agricultural Implements like dis harrows and ratovators to the extent

that it passes the requirements set out in Table.

8.3.3 Equipment for Construction

Stabilized soil sub-bases shall be constructed by mix-in-place method of

construction or as otherwise approved by the Engineer. Manual mixing shall

be permitted only where the width of lying is not adequate for mechanical

operations, as in small-sized jobs.

The equipment used mix-in-place construction shall be rotavator or similar

approved equipment capable of pulverizing and mixing the soil with additive

and water to specified degree to the full thickness of the layer being

processed, and of achieving the desired degree of mixing and uniformity of

the stabilized material. If so desired by the Engineer, trail runs with the

equipment shall be carried out to establish its suitability for work. The

thickness of any layer to be stabilized shall be not less than 100 mm when

compacted. The maximum thickness shall be 200 mm, provided the plant

used is accepted by the Engineer.

8.3.4 Mix-in-place method of construction

Before deploying the equipment, the soil after it is made free of undesirable

vegetation or other deleterious matters shall be spread uniformly on the

prepared sub-grade in a quantity sufficient to achieve the desired compacted

thickness of the stabilized layer. Where single-pass equipment is to be

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

employed, the soil shall be lightly rolled at the discretion of the Engineer.

The Equipment used shall either be of single-pass or multiple pass type. The

mixers shall be equipped with an appropriate device for controlling the

depth of processing and the mixing blades shall be maintained or reset

periodically so that the correct depth of mixing is obtained at all times. With

Single-pass equipment the forward speed of the machine shall be so selected

in relation to the speed that the required degree of mixing, pulverization and

depth of processing is obtained. In multiple-pass processing, the prepared

sub-grade shall be pulverized to the required depth with successive passes

of the equipment and the moisture content adjusted to be within prescribe

Limits mentioned hereinafter. The blending or stabilizing material shall then

be spread -uniformly and mixing continued with successive passes until the

required depth and uniformity of pressing have been obtained. The mixing

equipment shall be so set that it cuts slightly into the edge of the adjoining

lane processed previously so as to ensure that all the material forming a

layer has been properly processed for the full width.

8.3.5 Construction with manual means

Where manual mixing is permitted, the soil from borrow areas shall first be

freed of all vegetation and other deleterious matter and placed on the

prepared sub-grade. The soil shall then be pulverized by means of crow-

bars, pick axes or other means approved by the Engineer. Water n requisite

quantities may be sprinkled on the soil for aiding pulverization. On the

pulverized soil, the blending materials(s) in requisite quantities shall be

spread uniformly and mixed thoroughly by working with spades or other

similar implements till the whole mass are uniform After adjusting the

moisture content to be within the limits mentioned later, the mixed material

shall be levelled up to the required thickness so that it is ready to be rolled.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

8.3.6Addition of Lime

Lime may be mixed with the prepared material either in slurry form or dry

state at the option of e Contractor with the approval of the Engineer. Dry

lime shall be prevented from blowing by adding water to the lime or other

suitable means selected by the Contractor, with the approval of the

Engineer. The tops of windrowed material may be flattened or slightly

trenched to receive the lime. The distance to which lime may spread upon

the prepared material ahead of the mixing creation shall be determined by

the Engineer. No traffic other than the mixing equipment shall be allowed to

pass over the spread lime until after completion of mixing. Mixing or re-

mixing variations, regardless of equipment used, shall continue until the

material is free of any white breaks or pockets of lime and the mixture is

uniform.

Non uniformity of colour reaction, when the treated material is tested with

the standard phenolphthalein alcohol indicator, will be considered evidence

of inadequate mixing.

8.3.7 Moisture content for compaction

The moisture content at compaction checked vide IS: 2720 (Part 2) shall

neither be less than the optimum moisture content corresponding to IS:

2720 (Part 8) nor more than 2 per cent above it.

8.3.8 Rolling

Immediately after spreading, grading and leveling of the mixed material,

compaction shall be carried out with approved equipment preceded by a few

passes of lighter rollers if necessary. Rolling shall commence at edges and

progress towards centre, except at super elevated portions ire ii shall

commence at the inner edge and progress towards outer edge. During rolling

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

the re shall be frequently checked for grade and cross-fall (camber) and any

irregularities corrected by losing the material and removing/adding fresh

material. Compaction shall continue until the density achieved is at least 98

per cent of the maximum dry density for the material determined in

accordance with IS: 2720 (Part 8).

Sub-Bases, Bases (Non-Bituminous) and Shoulders Care shall be taken to

see that the compaction of lime stabilized material is completed within three

hours of its mixing or such shorter period as may be found necessary in dry

weather. During rolling it shall be ensured that roller does not bear directly

on hardened or partially hardened treated material previously laid other

than what may be necessary for achieving the specified compaction at the
joint. The final surface shall be well closed, free from movement under

compaction planes, ridges, cracks or loose material. All loose or segregated

or otherwise defective areas shall be made good to the full thickness of the

layer and re compacted.

8.3.9 Curing

The sub-base course shall be suitably cured for a minimum period of 7 days

after which subsequent pavement courses shall be laid to prevent the

surface from drying out and becoming friable. No traffic of any kind shall ply

over the completed sub-base unless permitted by the En2ineer.

8.3.10 Strength

When lime is used for improving the sub-grade, the soil-lime mix shall be

tested for its CBR value. When lime stabilized soil is used in a sub-base, it

shall be tested for unconfined compressive strength (UCS) at 7 days. In case

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

of variation from the design CBR!UCS, in situ value being lower, the

pavement design shall be reviewed based on the actual CBR/UCS value sJi1

be constructed by the Contractor at his own cost.

8.3.11 Measurements for Payment

Sabi1ized soil sub-base shall be measured as finished work in position in

cubic metres.

8.4 Sub-grade Characteristics and Strengths

97 test pits of size 1.Om x l.0m x 0.75m are dug by the side of existing

pavement edge. Pavement composition and their thicknesses are recorded


from each pit. Sub grade soil sample of approx. 5kgs collected from each test

pit for conducting following tests.

wet sieve analysis for soil classification

Moisture content of Sub grade soil

Atterberg limits to obtain plasticity index value

These results would be made use in applying corrections to BBD test values.

8.4.1 Sub grade CBR value

Maximum dry density (MDD) test is conducted at 20 test pits using sand

replacement method to work out the density of existing sub grade material.

Sub grade sample of approx. 60 kg is collected from each pit for conducting

following tests in the laboratory.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

- Wet sieve analysis

- Atterberg limits

- Maximum dry density (MDD) and Optimum moisture content (OMC)

- 4- Days soaked CBR value at three energy levels.

The test results will be utilized in assessing the quality of existing sub grade

and to suggest whether sub-grade replacement is required or not. Also, the

CBR value is used in the preliminary design of flexible pavement. The design

thickness would be used in working out the approximate cost of pavement

per sqm and to arrive at the construction cost of tjme project road.

Tests for sub-grade

California bearing ratio (CBR).

Callifornia bearing ratio(CBR):-

Procedure:-

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

This ratio expressed in percentage of force per unit area required to

penetrate of soil mass with a circular plunger of 50mm dia @1.25mm/mm.

To that required for corresponding penetration in a standard material. The

ratio is usually determined for penetration of 2.5 and 5.0mm where the ratio

at 5.0mm is used.

Volume of soil specimen : 2250cc

Wt. of compaction rammer : 4.89kg.

No. of layer :5

No. of blows on each layer : 56 blows

Preparation of test specimen:- Take a soil sample pass a 19.0mm sieve

allowance for lesser material shall be replacing by 19.0 pass and 4.75mm

retained material &mix thoroughly with water and compacted in CBR mould

layer by layer after compaction this set up shall undisturbed for 96 hours in

water.

Penetration test:- The specimen allowed to drain downwards for 15mm. The

weights the perforated plate and the top filter paper shall be removed and

the mould shall be weighted.

The mould plwe on the testing machine surcharge wt. sufficient to

procedure shall be place on the specimen.

The plunger shall be seated under a load of four kg. So that full centect is

established between the surface of the specimen and plunger. The gauge

shall then be asset to zero.

Lord shall be applied to the plunger into the soil @ 1 .25mm/mm, Reading

Of the load shall be taken at penetration of 0.5, 1.0, 1.5, 2.0, 2.5, 4.0, 5.0,

7.5, 10.0 & 12.5 mm.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

CBR Value = PT/PS*100

Penetration depth (mm) Unit Standard Load (Kg/sq.cm)

Total Standard Load (Kg)

2.5 70 1370

5.0 105 2055

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

9. GRANULAR SUB- BASE:-

9.1 Scope

This work shall consist of laying compacting well graded material on

prepared sub-grade in accordance with the requirements of these

specifications. The material shall be laid in one or more layers as sub-base

lower sub-base and upper sub base (termed as sub base sub base

hereinafter)as necessary according to lines, grades and cross sections shown

on the drawing or directed by the Engineer.

9.2 Materials

The material to be used for the work shall be natural sand, moorum, gravel,

crushed stone, or combination there of depending upon the grading

required. Materials like crushed slag crushed concrete, brick metal and

kankar may be allowed only with the specific approval of the Engineer.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

The material shall be free from organic or other deleterious constituents and

conform to one of the three grading given in table below. While the grading

in below table are in respect of close-graded granular sub base materials,

one each for maximum particle size of 75 mm, 53 mm and 26.5 mm.

The corresponding for the coarse-graded materials for each of the three

maximum particle sizes is given at table. The grading to be adopted for a

project shall be as specified in the contract.

9.3 Physical requirements

The materials shall have a10 per cent fines value of 50 km or more (for

sample in soaked condition) when tested in compliance with bs: (812 part
111). The water absorption value of the coarse aggregate shall be determine

as per IS: 2386 (part 3) ; if this value is greater than 2 per cent, the

soundness test shall be carried out on the material delivered to site as per

IS:383. For Grading II and II materials, the CBR shall be determined at the

density and moisture content likely to be developed in equilibrium

conditions which shall be taken as being the density relating to a uniform

content of per cent.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Note: The Material passing 425 micron (0.425 mm) sieve for all the three
grading when tested according to IS: 2720

(Part 5) shall have liquid limit and plasticity index not more than 25 and 6

per cent respectively.

9.3.1 Strength of Sub-Base

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

It shall be ensured prior to actual execution that the material to be used in

the sub-base satisfies the requirements of CBR and other physical

requirements when compacted and finished. When directed by the Engineer,

this shall be verified by performing CBR tests in the laboratory as required

on specimens re molded at field dry density and moisture content and any

other tests for the quality of materials, as may be necessary.

9.4 Construction Operation

9.4.1 Preparation of Sub-grade

Immediately prior to the laying of sub base, the sub-grade already finished

to as applicable shall be prepared by removing all vegetation and other

extraneous matter, lightly sprinkled with water if necessary and rolled with

two passes of 80 100 KN smooth wheeled roller.

9.4.2 Spreading and Compacting

The sub-base material of grading specified in the Contract shall be spread

on the prepared sub- grade with the help of a motor grader of adequate

capacity, its blade having hydraulic controls suitable for initial adjustment

and for maintaining the required slope and grade during the operation or

other means as approved by the Engineer.

The Material to be used for the work shall be natural sand, morum, gravel,

crushed stone, or combination thereof depending upon the grading required.

Materials like crushed slag crushed concrete, brick metal and kankar may

be allowed only with the specific approval of the Engineer. The material shall

be free from organic or other deleterious constituents and conform to one of

the three grading given in Table for grading for close-graded granular sub-

base materials. While the grading in Table are in respect of close-graded

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

granular sub-base materials, one each for maximum particle size of 75 mm,

53 mm and 26.5 mm, the corresponding grading for the coarse-graded

materials for each of the three maximum particle sizes are given at Table for

grading for coarse-graded granular sub-base materials. The grading to be

adopted for a project shall be as specified in the Contract. Mixing shall be

done messianically by the mix-in-place method. Sub-Bases, Bases (Non-

Bituminous) and Shoulders Manual mixing shall be permitted only where

the width of lying is not adequate for mechanical operations, as in small-

sized jobs. The equipment used for mix-in-place construction shall be

rotavator or similar approved equipment capable of mixing the material to

the desired degree. If so desired by the Engineer, trial runs with the
equipment shall be carried out to establish its suitability for the work.

Moisture content of the loose material shall be checked in accordance with

IS: 2720 (Part 2) and suitably adjusted by sprinkling additional water from a

truck mounted or trailer mounted water tank and suitable for applying

water uniformly and at controlled quantities to variable widths of surface or

other me4ans approved by the Engineer so that, at the time of compaction,

it is from I per cent below the optimum moisture content corresponding to

IS: 2720 (Part 8). While adding water, due allowance shall be made for

evaporation losses. After water has been added, the material shall be

processed by mechanical or other approved means like disc harrows,

rotavators until the layer is uniformly wet. Immediately thereafter, rolling

shall start. If the thickness of the compacted layer does not exceed 100 mm,

a smooth wheeled roller of 80 to 100 KN weight may he used. For a

compacted single layer up to 225 mm the compaction shall be done with the

help of a vibratory roller of minimum 80 to 100 KN static weights with plain

drum or pad foot-drum or heavy pneumatic tyred roller of minimum 200 to

300 KN weight having a minimum lyre pressure of 0.7 MN/m2 or equivalent

capacity roller capable of achieving the required compaction. Rolling shall

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

commence at the lower edge and proceed towards the upper edge

longitudinally for portions having unidirectional cross fall and super-

elevation and shall commence at the edges and progress towards the centre

for portions having cross-fall on both sides.

Each pass of the roller shall uniformly overlap not less than one-third of the

track made in the proceeding pass. During rolling, the grade and cross-fall

shall be checked and any high spots or depressions, which become

apparent, corrected by removing or adding fresh material. The speed of the

roller shall not exceed 5 km per hour. Rolling shall be continued till the

density achieved is at least 98 per cent of the maximum dry density for the

material determined as per IS: 2720 (Part 8). The surface of any layer of
material on completion of compaction shall be well closed, free from

movement under compaction equipment and from compaction planes, ridges

cracks or loose material. All loose, segregated or otherwise defective areas

shall be made good to the full thickness of layer and re-compacted.

9.4.3 Measurements for Payment

Granular sub-base shall be measured as finished work in position in cubic

meters. The protection of edges of granular sub-base extended over the full

formation as shown in the drawing shall be considered incidental to the

work of providing granular sub-base and as such no extra payment shall be

made for the same.

9.4.4 Rate

The Contract unit rate for granular sub-base shall be payment in full for

carrying out the required operation including full compensation for:

(i) Making arrangements for traffic to except for initial treatment to verges,

shoulders and construction of diversions;

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

(ii) Furnishing all materials to be incorporated in the work including all

royalties, fees, rents where necessary and all leads and lifts;

(iii) All labour, tools, equipment and incidentals to complete the work to the

Specifications; (iv) Carrying out the work in part widths of road where

directed; and

(v) Carrying out the required tests for quality control.

Tests for granular sub-base

Liquid limit and plastic limit.

Grain size analysis.

California bearing ratio (CBR)

Liquid limit and plastic limit:-

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Apparatus: liquid limit device, plastic limit device, IS 4.75mm Sieve trays.

Procedure for plastic limit:-

The plastic limit is determined by rolling out a thread of the fine portion of a

soil on a flat, nonporous the procedure is defined in ASTM standard.

If is plastic, this thread will retain its shape down to a very narrow diameter.

The sample can than be remolded and the test repeated. As the moisture

content falls due to evaporation the thread will begin to break apart at larger

diameter. The plastic limit is defined as the moisture content where the

thread breaks apart at a diameter of 3mm (about 1/8).

A Soil is considered non-plastic if a thread cannot be rolled out down to

3mm at any moisture.

Procedure for liquid limit:-

The liquid limit (LL) is the water content at which a soil changes from plastic

to liquid behavior. The original liquid limit test of Atterbergs involved mixing

pat of clay in a round-bottomed porcelain bowl of 10-12cm diameter.

A groove was cut through the pat of clay with a spatula and bowl was then

struck many times against the palm of one hand.

Casagrande subsequently standardized the apparatus and the procedures to

make the measurement more repeatable. Soil is placed into the metal cup

portion of device and a groove is made down its center with a standardized

tool of 13.5mm (0.53 in) width. The cup is repeatedly dropped 10mm onto a

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

hard rubbed base at a rate of 120 blows per minute, during which the

groove closes up gradually as a result of the impact. The number of blows

for the groove to close is recorded. The moisture content at which it takes 25

drops of the cup to cause the groove to se over a distance of 13.5mm (0.53

in) is defined as the liquid limit. The test is normally run several moisture

contents, and the moisture content which requires 25 blows to close the

groove is interpolated from the test results. The liquid limit test is defined by

ASTM standard test method D 4318. The test method also allows running

the test at one moisture content where 2O and 30 blows are required to

close the groove; then a correction factor is applied to obtain the liquid limit

from the moisture content.

Sieve analysis:-

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Apparatus:- IS Sieve 75mm, 53mm, 26.5mm, 9.5mm, 4.75mm, 2.36mm,


0.425mm, 0.075mm, Iron trays.

Procedure:-

A gradation test is performed on a sample of aggregate in a laboratory. A

typical sieve analysis involves a nested column of sieves with wire mesh

cloth (screen). See the separate mesh (scale) page for details of sieve sizing.

A representative weighed sample is poured into the top sieve which has the

largest screen openings. Each lower sieve in the column has smaller

openings than the one above. At the base is a round pan, called the receiver.

The column is typically placed in a mechanical shaker. The shaker shakes

the column, usually for some fixed amount of time. After the shaking is

complete the material on each sieve is weighed. The weight of the sample of

each sieve is then divided by the total weight to give a percentage retained

on each sieve. The size of the average particle on each sieve is then analysed

to get a cut-off point or specific size range, which is then captured on a

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

screen. The results of this test are used to describe the properties of the

aggregate and to see if it is appropriate for various civil engineering

purposes such as selecting the appropriate aggregate for concrete mixes and

asphalt mixes as well as sizing of water production well screens. The results

of this test are provided in graphical form to identify the type of gradation of

the aggregate. The complete procedure for this test is outlined in the

American Society for Testing and Materials (ASTM) C136 and the American

Association and State Highway and Transportation Officials (AASHTO) T27

A suitable sieve size for the aggregate should be selected and placed in order

of decreasing size, from top to bottom, in a mechanical sieve shaker. A pan

should be placed underneath the nest of Sieves to collect the aggregate that
passes through the smallest. The entire nest is then agitated, and the

material whose diameter is smaller than the mesh opening passes through

the sieves. After the aggregate reaches the pan, the amount of material

retained in each sieve is then weighed.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

10. WET MIX MACADAM:-

10.1 Scope

This work shall consist of laying and compacting clean, crushed, graded

aggregate and granular material, premixed with water, to a dense mass on a

prepared sub-grade/sub-base/base or existing pavement as the case may be

in accordance with the requirements in these Specifications. The Material

shall be laid in one or more layers as necessary to lines, grades and cross-

sections shown on the approved drawings or as directed by the Engineer.

The thickness of a single compacted Wet Mix Macadam layer shall not be

less than 75 mm. When vibrating or other approved types of compacting

equipment are used, the compacted depth of a single layer of the sub-base

course may be increased to200 mm upon approval of the Engineer.

10.2 Materials & Aggregates

10.2.1 Physical requirements

Coarse aggregates shall be crushed stone. If crushed gravel/shingle is used,

not less than 90 per cent by weight of the gravel/shingle pieces retained on

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

4.7mm sieve shall have at least two fractured faces. The aggregates shall

conform to the physical requirements set forth in table 14.

TabIel4. Physical requirements of aggregates for wet mix macadam for sub

base/base courses

* Aggregate may satisfy requirements of either of the two tests.

** To determine this combined proportion, the flaky stone from a

representative sample should first be separated out. Flakiness index is

weight of flaky stone metal divided by weight of stone sample. Only the

elongated particles are separated out from the remaining (non-flaky) stone

metal. Elongation index is weight of elongated particles divided by total non-

flaky particles. The value of flakiness index and elongation index so found

are added up. If the water absorption value of the coarse aggregate is greater

than 2 per cent, the soundness test shall be carried out on the material

delivered to site as per IS: 2386(part-5)

10.3 Grading requirements

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

The aggregates shall conform to the grading given in Table 15.

Materials finer than 425 micron shall have Plasticity Index (PT) not

exceeding 6.

The final gradation approved within these limits shall be well graded from

coarse to fine and shall not vary from the low limit on one sieve to the high

limit on the adjacent or vice versa.

10.4 Construction Operations

10.4.1 Provision of lateral confinement of aggregates

While constructing wet mix macadam, arrangement shall be made for the

lateral confinement of wet mix.

This shall be done by laying materials in adjoining shoulders along with that

of wet mix madam layer and following the sequence of operations.

10.4.2 Preparation of Mix

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Vet Mix Macadam shall be prepared in an approved mixing plant of suitable

capacity having provision for controlled addition of water and forced/positive

mixing arrangement like pug mill or pan type mixer of concrete batching

plant.

For small quantity of wet mix work, the Engineer may permit the mixing to

be done in concrete mixers. Optimum moisture for mixing shall he

determined in accordance with IS: 2720(Part-8) after replacing the aggregate

fraction retained on 22.4 mm sieve with material of 4.75 mm to 22.4 mm

size. While adding water, due allowance should be made for evaporation

losses. However, at the time of compaction, water in the wet mix should not

vary from the optimum value by more than agreed limits. The mixed
material should be uniformly wet and no segregation should be permitted.

10.4.3 Spreading of mix

Immediately after mixing, the aggregates shall be spread uniformly and

evenly upon the prepared sub grade-sub-base/base in required quantities.

In no case should these be dumped in heaps directly on the area where

these are to be laid nor shall their hauling over a partly completed stretch be

permitted. The mix may be spread either by a paver finisher or motor grader.

For portions where mechanical means cannot be used, manual means as

approved by the Engineer shall be used. The motor grader shall be capable

of spreading the material uniformly all over the surface. Its blade shall have

hydraulic control suitable for initial adjustments and maintaining the same

so as to achieve the specified slope and grade.

The paver finisher shall be self-propelled, having the following features:

(i) Loading hopper and suitable distribution mechanism.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

(ii) The screed shall have tamping and vibrating arrangement for initial

compaction to the layer as it is spread without rutting or otherwise marring

the surface profile.

(iii) The paver shall be equipped with necessary control mechanism so as to

ensure that the finished surface is free from surface blemishes.

Sub-Bases, Bases (Non-Bituminous) and Shoulders

The surface of the aggregate shall be carefully checked with templates and

all high or low spots remedied by removing or adding aggregate as may be

required. The layer may be tested by depth blocks during construction.

No segregation of large and fine particles should be allowed. The aggregates

as spread should be of uniform gradation with no pockets of line materials.

10.4.4 Compaction

After the mix has been laid to the required thickness, grade and cross

fall/camber the same shall be uniformly compacted, to the full depth with

suitable roller. If the thickness of single compacted layer does not exceed

100 mm, a smooth wheel roller of 80 to 100 KN weight may be used. For a

compacted single layer up to 200 mm, the compaction shall be done with

the help of vibratory roller of minimum static weight of 80 to 100 KN or

equivalent capacity roller. The speed of the roller shall not exceed 5 km/h. In

portions having unidirectional cross fall/super-elevation. Rolling shall

commence from the lower edge and progress gradually towards the upper

edge. Thereafter, roller should progress parallel to the centre line of the road,

uniformly overlapping each preceding track by at least one third width until

the entire surface has been rolled.

Alternate trips of the roller shall be terminated in stops at least 1 m away

from any preceding sop. In portions in camber, rolling should begin at the

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

edge with the roller running forward and ward until the edges have been

firmly compacted. The roller shall then progress gradually towards the

centre parallel to the centre line of the road uniformly overlapping each of

the reeding tracks by at least one-third width until the entire surface has

been rolled. Any &!cement occurring as a result of reversing of the direction

of a roller or from any other cause all be corrected at once as specified

and/or removed and made good. Along forms, kerbs. Wal1s or other places

not accessible to the roller, the mixture shall be thoroughly compacted with

mechanical tampers or a plate compactor. Skin patching of an area without

scarifying the surface to permit proper bonding of the added material shall

not be permitted. Rolling should not be done when the sub-grade is soft or
yielding or when ii causes a wave-like motion in the sub-base base course

or sub-grade.

If irregularities develop during rolling which exceed 12 mm when tested with

a 3 metre straight edge, the surface should be loosened and premixed

material added - removed as required before rolling again so as to achieve a

uniform surface conforming to the red grade and cross fall. In no case

should the use of unmixed material be permitted to make the depressions.

Rolling shall he continued till the density achieved is at least 98 per cent of e

maximum dry density for the material as determined by the method

outlined in IS: 2720(Part-8).After completion, the surface of any finished

layer shall he well-closed, free from movement under compaction

equipment or any compaction planes, ridges, cracks and loose material. All

Loss, segregated or otherwise defective areas shall be made good to the full

thickness of the re-compacted.

10.4.5 Setting and drying

After final compaction of wet mix macadam course, the road shall be allowed

to dry for 24 hours.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

10.4.6 Opening to Traffic

Preferably no vehicular traffic of any kind should be allowed on the finished

wet mix macadam surface till it has dried and the wearing course laid.

10.5 Surface Finish and Quality Control of Work

10.5.1 Rectification of Surface Irregularity

Where the surface irregularity of the wet mix macadam course exceeds the

permissible tolerance or where the course is otherwise defective due to sub-

grade soil getting mixed with the aggregates, the full thickness of the layer

shall be scarified over the affected area, reshaped with added premixed

material or removed and replaced with fresh premixed material as applicable

and recomputed. The area treated in the aforesaid manner shall not be less

than 5 m long and 2 m wide. In no case shall depressions be filled up with

unmixed and ungraded material or fines.

10.5.2 Rates

The Contract unit rate for wet mix macadam shall be payment in full for

carrying out the required operations including full compensation for all

components.

Tests for wet mix macadam

Liquid limit and plastic limit.

Grain size analysis.

Flakiness and elongation.

California bearing ratio (CBR).

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Sieve analysis:-

Apparatus:-IS a sieve 75mm, 53mm, 26.5mm, 9.5mm, 4.75mm, 2.36mm,


0.425mm, .O75mm, Iron trays.

Procedure:-

A gradation test is performed on a sample of aggregate in a laboratory. A

typical sieve analysis involves a nested column of sieves with wire mesh

cloth (screen). See- the separate mesh (scale) page for details of sieve sizing.

A representative weighed sample is poured into the top sieve which has the

largest screen opening. Each lower sieve in the column has smaller openings

than the one above. At the base is a round pan, called the receiver.

The column is typically placed in a mechanical shaker. The shaker shakes

the column, usually for some fixed amount of time. After the shaking is

complete the material on each sieve is weighed. The weight of the sample of

each sieve is then divided by the total weight to give a percentage retained

on each sieve.

The size of the average particle on each sieve is then analysed to get a cut-off

point or specific size range, which is then captured on a screen.

The results of this test are used to describe the properties of the aggregate

and to see if it is appropriate for various civil engineering purposes such as

selecting the appropriate aggregate for concrete mixes and asphalt mixes as

well as sizing of water production well screens. The results of this test are

provided in graphical form to identify the type of gradation of the aggregate.

The complete procedure for this test is outlined in the American Society for

Testing rd Materials (ASTM) C136 and the American Association and State

Highway and Transportation Officials (AASHTO) T27

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

A suitable sieve size for the aggregate should be selected and placed in order

of decreasing size, from top to bottom, in a mechanical sieve shaker. A pan

should be placed underneath the nest of sieves to collect the aggregate that

passes through the smallest. The entire nest is then agitated, ad the

material whose diameter is smaller than the mesh opening passes through

the sieves. After the aggregate reaches the pan, the amount of material

retained in each sieve is then weight.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

SHAPE TEST (ELONGATION INDEX):-

Apparatus required: Length gauge, I.S.Sieve

Procedure:

1. The sample is sieved through IS Sieve specified in the table. A minimum

of 200 aggregate pieces of each fraction is taken and weighed.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

2. Each fraction is the thus gauged individually for length in a length gauge.

The gauge length is used should be those specified in the table for the

appropriate material.

3. The pieces of aggregate from each fraction tested which could not pass

through the specified language length with its long side are elongated

particles and they are collected separately to find the total weight of

aggregate retained on the length gauge from each fraction.

4. The total amount of elongated material retained by the length gauge is

weighed to an accuracy of at least 0.1% of the weight of the test sample.

5. The weight of each fraction of aggregate passing and retained on specified

sieves sizes are found W1, W2, W3, and the total weight of sample

determined =W1+ W2+W3=Wg. Also the weight of the material from each

function retained on the specified gauge length are found= X1, x2, x3 and

the total weight retained determined x1+x2+x3=X gm.

6. The elongation index is the total weight of the material retained on the

various length gauges, expressed as a percentage of the total weight of the

sample gauged.

(X1+x2+x3+-------)

Elongation index = -----------------------

(w1+w2+w3+-----)

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

SHAPE TEST (FLAKINESS INDEX):-

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Apparatus required: The apparatus consist of a standard thickness


gauge, IS Sieve of size63, 50, 40, 31.5, 25, 20, 16, 12.5, 10 and 6.3 and a

balance to weight the samples.

Procedure

1. The sample is sieved with the sieves mentioned in the table.

2. A minimum of 200 pieces of each fraction to be tested are taken and

weighed (WI gm)

3. In order to separate flaky materials, each fraction is then gauged for

thickness on thickness gauge, or in bulk on sieve having elongated slots as

specified in the table.

4. Then the amount of flaky materials passing the gauge is weighed to an

accuracy of at least 0.1% of test sample.

5. Let the weight of the flaky materials passing the gauge be W1 gm.

Similarly the weights of the fractions passing and retained on the specified

sieves be W1, W2, W3, etc, are weighed and the total weight WI+W2+W3+ =

Wg is found. Also the weights of the materials passing each of the specified

thickness gauge are found =W 1, W2, W3.... And the total weight of the

material passing the different thickness gauges = W1+W2+W3= Wg is

found.

6. Then the flakiness index is the total weight of the flaky material passing

the various thickness gauges expressed as a percentage of the total weight of

the sample gauged.

(w1+w2+w3+----)

Flakiness index = ----------------------- X 100

(w1+w2+w3+----)

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

11. PRIME COAT OVER GRANULAR BASE:-

11. 1 Scope

This work shall consist of the application of a single coat of low viscosity

liquid bituminous material to a porous granular surface preparatory to the

superimposition of bituminous treatment or mix.

11.2 Materials

11.2.1 Prime

The choice of bituminous prime shall depend upon the porosity

characteristics of the surface to be primed as classified in IRC: 16. These

are:

(1)Surface of low porosity; such as wet macadam and water bound

macadam,

(2)Surface of medium porosity; such as cement stabilized soil base,

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

(3)Surface of high porosity; such as a gravel base.

11.2.2 Prime viscosity

The type and viscosity of the primer shall comply with requirements of IS:

8887, as sampled and tested for bituminous primer in accordance with

these standards .Guidance on viscosity and rate of spray is given in Table16.

Table16. Viscosity requirements and quantity of liquid bituminous primer

11.2.3 Choice of primer

The primer shall be bitumen emulsion, complying with IS: 8887 of a type

and grade as specified in the Contract or as directly by the Engineer. The

use of medium curing cutback as per IS: 217 shall be restricted only for

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

sites at subzero temperatures or for emergency application as directly by the

Engineer.

11.2.4 Weather and Seasonal Limitations

Bituminous primer shall not be applied to a wet surface or during a dust

storm or when the weather is foggy, rainy or windy or when the temperature

in the shade is less than 100C. Surfaces which are to receive emulsion

primer should be damp, but no free or standing water shall be present.

11.3 Construction

11.3.1 Equipment

The primer distributor shall be a self-propelled or towed bitumen pressure

sprayer for spraying the material uniformly at specified rates and

temperature. Hand spraying of small areas, inaccessible to the distributor,

or in narrow strips shall be sprayed with a pressure hand sprayer, or as

directed by the Engineer.

11.3.2 Preparation of road surface

The surface to be primed shall be prepared in accordance with and as

appropriate. Immediately prior to applying the primer the surface shall be

carefully swept of dust and loose particles, care being taken not to disturb

the interlocked aggregate. This is best achieved when the surface layer is

slightly moist (lightly sprayed with water and the surface allowed to dry) and

the surface should be kept moist until the primer is applied.

11.3.3 Application of bituminous primer

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

The viscosity and rate of application of the primer shall be as specified in

the contract, or as determined by site trials carried out as directed by the

Engineer. Where a geosynthetic is proposed for use, the requirements and

shall apply. The bituminous primer shall be sprayed uniformly in

accordance with. The method for application of the primer will depend on

type of equipment to be used, size of nozzles, pressure at the spray bar and

speed of forward movements. The contractor shall demonstrate at spraying

trial, that the equipment and method be used is capable of producing a

uniform spray, within the tolerances specified.

11.3.4 Curing of primer and opening to traffic

A primed surface shall be allowed to cure for at least 24 hours or such other

period as is found to be necessary to allow all the volatiles before any

subsequent surface treatment or mix is laid.

Any unabsorbed primer shall first be blotted with an application of sand,

using the minimum quantity possible. A primer surface shall not be opened

to traffic other than the necessary to lay the next course. A very thin layer of

clean sand may be applied to the surface to lay prevent the primer picking

up under the wheels of the paver and trucks delivery bituminous material to

the paver.

11.3.5 Measurement for payment

Prime coast shall be measured in terms of surface area of application in

square meters.

11.3.6 Rate

The contract unit rate for prime coat with adjustment as describe in shall

payment in full for carrying out the required operation including full

compensation for all components listed and as applicable to the work

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

specified in the Specification. Payments shall be on the basis of the

provision of prime coat at the application rate of 0.6 kg per square meter,

with adjustment, plus or minus, for the variation between this amount and

the actual amount by the Engineer after preliminary trails.

12. DENSE BITUMINOUS MACADAM:-

12.1 Scope

This clause specifies the construction of Dense Graded Bituminous

Macadam, (DBM), for use mainly, but not exclusively, in base/binder and

profile corrective courses. DBM is also intended for use as road base

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

material. This work shall consist of construction in a single or multiple

layers of DBM on a previously prepared base or sub base. The thickness of a

single layer shall be 50 to 100mm.

12.2 Materials

12.2.1 Bitumen

The bitumen shall be paving bitumen of Penetration Grade complying with

Indian Standard Specifications for Paving Bitumen IS: 73, and of the

penetration indicated in Table for dense bitumen macadam, or this bitumen

as modified by one of the methods specified, or as otherwise specified in the

Contract. Guidance on the selection of an appropriate grade of bitumen is

given in The Manual for Construction and Supervision of Bituminous Works.

12.2.2 Coarse aggregates

The coarse aggregates shall consist of crushed rock, crushed gravel or other

hard material retained on the 2.36 mm sieve. They shall be clean, hard, and

durable, of cubical shape, free from dust and soft or friable matter, organic

or other deleterious substances. Where the Contractors selected source of

aggregates have poor affinity for bitumen, as a condition for the approval of

that source, the bitumen shall be treated with an approved anti-strippiig

agent, as per the manufacturers recommendations, without additional

payment. Before approval of the source, the aggregates shall be tested for

stripping.

The aggregates shall satisfy the physical requirements specified in below

Table, for dense bituminous macadam. Where crushed gravel is proposed for

use as aggregate, not less than 90 % by weight of the crushed material

retained on the 4.75 mm sieve shall have at least two fractured faces.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

12.2.3 Fine aggregates

Mineral material, or a combination of the two, passing the 2.36 mm sieve

and retained on 75 micron sieve. They shall he clean, hard, durable, dry and

free from dust, and soft or friable matter. organic or other deleterious matter.

The fine aggregate shall have a sand equivalent alue of not less than 50

when tested in accordance with the requirement of IS: 2720 (Part 37). The

plasticity index of the fraction passing the 0.425 mm sieve shall not exceed

4. When tested in accordance with IS: 2720 (Part 5).

Notes: 1. IS: 2386 Part 1 5. IS: 2386 part 5

2. IS: 2386 part 2 6. IS: 2386 part 6

(The elongation test to be done only on non-flaky aggregated in the sample)

3. IS: 2386 part 4* 7. IS: 6241

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

4. IS: 2386 part 4* 8. AAASHTO T 283*

* Aggregate may satisfy requirements of either of these two tests.

** The water sensitivity test is only required if the minimum retained coating

in the stripping test is less than 95%

12.2.4 Filler

Filler shall consist of finely divided mineral matter such as rock dust,

hydrate lime or cement approved by the engineer. The filler shall be grated

within the indicated in Table 18.

The filler shall be free from organic impurities and have a Plasticity Index

not greater than 4. The Plasticity Index requirement shall not apply if filler is

cement or lime. When the coarse aggregate is gravel, 2 per cent by weight of

total aggregate, shall be Portland cement or hydrated lime and the

percentage of fine aggregate reduced accordingly. Cement or hydrated lime is

not required when the limestone aggregate is used. Where the aggregates fail

to meet the requirements of the water sensitivity test in then 2 percent by

total weight of aggregate. Of hydrated lime shall be added without additional

coat.

12.2.5 Aggregate grading and binder content

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

When tested in accordance with IS: 2386 Part 1 (wet sieving method), the

combined grading of the coarse and fire aggregates and added filler for the

particular mixture shall fall within the limits shown in Table 19, for dense

bituminous macadam grading 1 or 2 as specified in the Contract. The type

and quality of bitumen, and appropriate thickness, are also indicated for

each mixture type.

Note: The combined aggregate grading shall not vary from the low limit on

one sieve to the high limit on the adjacent sieve.

12.3 Mixer Design

12.3.1 Requirement for the mixer

Apart from conformity with the grading and quality requirement for

individual ingredients, the mixer shall meet requirement set out in Table 20.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Notes: 1. the nominal maximum particle size is one size larger than the firt

sieve to retain more than 10 percent.

2. Interpolate minimum voids in the mineral aggregate (VMA) for

design air voids value between both listed.

12.3.2 Binder content

The binder content shall be optimized to achieve their requirements of the

mixture set out in Table and the traffic volume specified in the Contract. The

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Marshall method for determining the optimum binder content shall be

adopted as described in the Asphalt Institute Manual MS-2, replacing the

aggregates retained on the 26.5 mm sieve by the aggregates passing the 26.5

mm sieve and retained on 22.4 mm sieve, where approved by the Engineer.

Where 40 mm dense bituminous macadam mixture is specified, the

modified Marshall method described in MS-2 shall be used. This method

requires modified equipment and procedures; particularly the minimum

stability values in Table shall be multiplied by 2.25 and the minimum flow

shall be 3 mm.

12.3.3 Job mix formula

The Contractor shall inform Engineer in writing, at least 20 days before the

start of the work, of the job mix formula proposed for be used in the works,

and shall give the following details:

(i) Source and location of all materials;

(ii) Proportions of all materials expressed as follows where each is applicable:

(a) Binder type, and percentage by weight of total mixture;

(b) Coarse aggregate/Fine aggregate/Mineral filler as percentage by weight of

total aggregate including mineral filler;

(iii) A single definite percentage passing each sieve for the mixed aggregate;

(iv) The individual grading of the individual aggregate fractions, and the

proportion of each in the combined grading.

(v) The results of tests enumerated in below Table as obtained by the

Contractor;

(vi) Where the mixer is a batch mixer, the individual weights of each type of

aggregate, and binder per batch, (vii) Test results of physical characteristics

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

of aggregates to be used; (viii) Mixing temperature and compacting

temperature. While establishing the job mix formula, the Contractor shall

ensure that it is based on a correct and truly representative sample of the

materials that will actually be used in the work and that the mixture and its

different ingredients satisfy the physical and strength requirements of these

Specifications. Approval of the job mix formula shall he based on

independent testing by the Engineer for which samples of all ingredients of

the mix shall he furnished by the Contractor required by the Engineer. The

approved job mix formula shall remain effective unless and until a revised

Job Mix Formula is approved.

12.3.4 Plant trials - permissible variation in job mix formula

Over the laboratory job mix formula is approved, the Contractor shall carry

out plant trials at the mixer to establish that the plant can be set up to

produce a uniform mix conforming to the Base and approved job mix

formula. The permissible variations of the individual percentages of the

various ingredients in the actual mix from the job mix formula to be used

shall be within the limits as specified in below Table.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Once the plant trials have demonstrated the capability of the plant. And true

trials are approved. The laying operation may commence. Over the period of

the first month of production for laying on the works. the Engineer shall

require additional testing of the product to establish the reliability and

consistency of the plant.

12.3.5 Laying Trials

Once the 1)1 ant trials have been successfully completed and approved, the

Contractor shall carry out laying trials, to demonstrate that the proposed

mix can be successfully laid, and compacted. The laying trial shall be

carried out on a suitable area which is not to form part of the works. unless
specifically approved in writing, by the Engineer. The area of the laying trials

shall he a minimum of 100 sq. m. of construction similar to that of the

project road, and it shall be in all respects, particularly compaction, the

same as the project construction, on which the bituminous material is to be

laid.

The Contractor shall previously inform the Engineer of the proposed method

for laying and compacting the material. The plant trials shall then establish

if the proposed laying plant, compaction plant, and methodology is capable

of producing satisfactory results. The density of the finished paving layer

shall be determined by taking cores, no sooner than 24 hours after laying,

or by other approved method.

Once the laying trials have been approved, the same plant and methodology

shall be applied to the laying of the material on the project, and no variation

of either shall be acceptable, unless approved in writing by the Engineer,

who may at his discretion required further laying trials.

12.4 Construction Operations

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

12.4.1 Preparation of base

The surface shall be thoroughly swept clean by a mechanical broom, aid the

dust removed by compressed air. In locations where mechanical broom

cannot access, other approved methods shall be used as directed by the

Engineer.

12.4.2 Rolling

The compaction process shall be carried out by the same plant, and using

the same method, as approved in the laying trials, which may be varied only

with the express approval of the Engineer in writing.

12.4.3 Opening to Traffic

The newly laid surface shall not be open to traffic for at least 24 hrs after

laying and completion of compaction, without the express approval of the

Engineer in writing.

12.4.4 Measurement for Payment

Dense Graded Bituminous Materials shall be measured as finished wok

either in cubic metres, tons or by the square metre at a specified thickness

as detailed on the Contract drawings. or documents, or as directed by the

Engineer.

12.4.5 Rate

The rate shall include the provision of bitumen, 4.25 per cent by weight of

the total mixture. The variance in actual percentage of bitumen used will be

assessed and the payment adjusted. up or down, accordingly.

Tests for Dense bituminous macadam

Aggregate impact value

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Flakiness and elongation

Marshal test

Aggregate impact value:

Apparatus required: Impact testing machine, cylinder, tamping rod, IS


Sieve 125.mm, 10mm and 2.36mm, balance.

Procedure:

The test sample consist of aggregate passing 12.5mm sieve and retained on

10mm sieve and dried in an oven for four hours at a temperature 100C to

110C and cooled. Test aggregates are filled up to about one-third full in the

cylindrical measure and tamped 25 times with rounded end of the tamping

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

rod. Further quantity of aggregate is than added up to two-third in the

cylinder and 25 stocks of the tamping rod are given. The measure is now

filled with the aggregate to over flow, tamped 25 times. The surplus

aggregate are struck off using the tamping rod as straight edge. The net

weight of the aggregate in the measure is determined to the nearest gram

and this weight of the aggregate is used for carrying out duplicate test on

the sample material. The impact machine is placed with its bottom plate flat

on the floor so that the hammer guide columns arc vertical. The cup is fixed

firmly in position on the base of the machine and the whole of the test

sample from the cylindrical measure is transferred to the cup and

compacted by tamping with 25 strokes.

The hammer is raised until its lower face is 380mm above the upper surface

of the aggregate in the cup, and allowed to fall freely on the aggregates. The

test sample is subjected to a total 15 such blows, each being delivered at an

interval of not less than one second. The crushed aggregate is then removed

from the cup and the whole of it sieved on the 2.36mm sieve until no further

significant amount passes.

The fraction passing the sieve is weighted accurate to 0.1gm. The fraction

retained on the sieve is also weighed and if the total weight of the fraction

passing and retained on the sieve is added it should not be less the original

weight is less than the original weight of the specimen by more than one

gram, if the total weight is less than the original by over one gram the result

should be discarded and a fresh test made.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Marshal Test:-

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Apparatus required:

Mould assembly, sample extractor, compaction pedestal and hammer,

breaking head, loading machine flow meter, thermometers water bath and

oven

Procedure: -

1. The coarse aggregates, fine aggregates and mineral filler material

should be proportioned and mixed in such a way that final mix after

blending has the graduation within the specified range.

2. Approximately 1200 grams of aggregates and filler are taken and

heated to a temperature of 175oC to 1950 C.

3. The compaction mould assembly and rammer are cleaned and kept

pre- heated to a temperature of 100oC to 145oC. The bitumen is

heated to temperature of l2loC to 138oC and the required quantity of

first trial percentage of bitumen is added to the heated aggregate and

thoroughly mixed using a mechanical mixer or by hand mixing with

trowel.

4. Then the mix is heated and a temperature of 150o to l6OoC is

maintained and then the mix is transferred into the pre-heated mould

and compacted by giving seventy five blows on each side.

5. The specific gravity values of different aggregates, filler and bitumen

used are determined first. The theoretical specific gravity of the mix is

determined.

6. Soon after the compacted bituminous mix specimens have cooled to

room temperature, the weight, average thickness and diameter of the

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

specimen are noted. The specimens are weighted in air and then in

water.

7. The bulk density value of the specimen if calculated from weight and

volume

8. Then the specimen to be tested is kept immersed under water in a

thermostatically controlled water bath maintained at 60o l0C for 30

to 40 minutes.

9. The specimens are taken out one, placed in the marshal lest and the

marshal stability value and flow are noted.

10. The corrected Marshall Stability value of each specimen is

determined by applying the appropriate correction factor, i9f the

average height of the specimen is not exactly 63.5mm.

11. Five graphs are plotted with values of bitumen content against

the values of density, Marshall Stability, voids in total mix, flow value,

voids filled by bitumen.

12. Let the bitumen contents corresponding to maximum density be

B 1, corresponding to maximum stability be B2 and that

corresponding to the specified voids content (at 4.0%) be B3.

Then the optimum bitumen content for mix design is given by: Bo= (BI

+B2+B3)/3.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

13. TACK COAT:-

13.1 SCOPE

This work shall consist of the application of single coat of low viscosity liquid

bituminous material to an existing bituminous road surface prepare to the

superimposition of a bituminous mix, when specified in the contrite or

instruction by the Engineer.

13.2 Material

13.2.1 Binder

The binder used for tack coat shall be a bitumen complying with IS : 8887 of

a type and grade as specified in the contrite or as directly by the engineer.

The use of emergency application as directed by the Engineer.

13.2.2 Weather and seasonal Limitations

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Bituminous material shall not be applied to a wet surface or during a dust

storm or when the weather is foggy, rainy or windy or when the temperature

in the shade is the less than 100c. Where coat is of cutback bitumen, the

surface shall be dry.

13.3 Construction

13.3.1 Equipment

The tack coat distributor shall be a self- propelled or towed bitumen

pressure sprayer, equipped for spraying the material uniform at specified

rate. Hand spraying of small areas, inaccessible to the distributor, or in

narrow strips shall be sprayed with a pressure hand sprayer, or as directed

by the engineer.

13.3.2 Preparation of base

The surface on the tack coat is to be applied shall be and from dust, dirt

and any extraneous material, and be otherwise prepared in accordance with

requirements of appropriate.

Immediately before the application of the tack coat the surface shall be

swept clean with a mechanical broom and high pressure air jet or by other

means as directed by the Engineer.

13.3.3 Application of task coat

The application of task coat shall be rate specified in the contrite , and shall

be applied uniformly. If rate application of tack coat is not specified in the

contract then it shall be at the rate specified in the below table. The normal

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

range of spraying temperature for a bituminous emulsion shall be 200c to

700c and for a cutback 500to 800c if rc-70/MC-70 is used. Where a

geosynthetic is proposed for use the provisions shall apply. The method of

application of the tack coat will depend of forward movement. The contractor

shall demonstrate at a spraying trial that the equipment and method to be

used is capable of producing a uniform spray, within the tolerance specified.

Where the material to receive an overlay is a freshly laid bituminous layer

that has not been subjected to traffic or contaminated by dust a tack coat is

not mandatory where the overlay is completed within two days.

13.3.4 Curing of task coat

The task coat shall be left to cure until the entire have approved before any

subsequent construction is started. No plant or vehicles shall be allowed on

the task coat other than those essential for the construction.

13.3.5 RATE

The contrite unit rate for granular sub-base shall be payment in full for

carrying out required operation including full compensation for.

1) Making arrangement for traffic to except for intial treatment to verges

shoulder and construction of diversions.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

2) Furnishing all materials to be incorporated in the including all

royalties, fees, rent where necessary and all leads and lifts.
3) All labour tools equipment to completed the work to the specification;
4) Carrying out the work in the part widths of road where directed and;
5) Carrying out the required test for quality.
(1)To (5) and as applicable to the work specified in these specification.

The rate shall cover the provision of task 0.2 kg square meter, with in

provision that the variance in actual quantity of bitumen used will be

assessed and the payment adjusted accordingly.

14.BITUMINOUS CONCRETE:-

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

14.1 Scope

This clause specifies the construction of Bituminous Concrete, for use in

wearing and profile corrective courses. This work shall consist of

construction in a single or multiple layers of bituminous concrete on a

previously prepared bituminous bound surface. A single layer shall be

25mm to 100 mm in thickness.

14.2 Materials

14.2.1 Bitumen

The bitumen shall be paving bitumen of Penetration Grade complying with

Indian Standard Specification for Paving Bitumen, IS: 73 and of the

penetration indicated in below Table, for bituminous concrete, or this

bitumen as modified by one of the methods specified , or as otherwise

specified in the Contract. Guidance on the selection of an appropriate grade

of bitumen is given in The Manual for Construction and Supervision of

Bituminous Works.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

14.2.2 Coarse aggregates

The coarse aggregates shall be generally as specified. Except that the

aggregates shall satisfy the physical requirements in below Table.

14.2.3 Fine aggregates

Fine aggregates consist of crushed or naturally occurring mineral material

or a combination of the two, passing the 2.36 mm sieve and retained on 75

micron sieve. They shall be clean, hard, durable, dry and free from dust, and

soft or friable matter, organic or other deleterious matter.

The fine aggregate shall have a sand equivalent value of not less than 50
when tested in accordance with the requirement of IS: 2720 (Part 37). The

plasticity index of the fraction passing the 0.425 mm sieve shall not exceed

4. When tested in accordance with IS: 2720 (Part 5)

14.2.4 Filler

Where the aggregates fail to meet the requirements of the water sensitivity

test in below Table then 2 per cent by total weight of aggregate, of hydrated

lime shall be added without additional cost

14.2.5 Aggregate grading and binder content

When tested in accordance with IS: 2386 Part 1 (wet sieving method), the

combined grading of the coarse and fine aggregates and added filler shall fall

within the limits shown in below Table for grading

1 or 2 as specified in the Contract.

14.3 Mixture Design

14.3.1 Requirements for the mixture

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Apart from conformity with the grading and quality requirements for

individual ingredients, the mixture shall meet the requirements set out in

below Table. The requirements for minimum per cent voids in minemal

aggregate (VMA) are set out in TabIe24.

14.3.2 Binder content

The binder content shall be optimized to achieve the requirements of the

mixture set Out in below Table and the traffic volume specified in the

Contract. The Marshall method for determining the optimum binder content

shall be adopted as described in The Asphalt Institute Manual MS-2.

Replacing the aggregates retained on the 26.5 mm sieve by the aggregates


passing the 26.5 mm sieve and retained on 22.4 mm sieve, where approved

by the Engineer.

14.3.3Job mix formula

The procedure for formulating the job mix formula shall be generally and the

results of tests enumerated in Table24, as obtained by the Contractors.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Notes: 1. IS: 2386 part 1 6. IS: 2386 part 5

2. IS: 2386 part 1 7.IS: 2386 part 3

(The elongation test to be done only on non-flaky aggregated in the

sample)

3. IS: 2386 part 4* 8.AASHTO T283*

4. IS: 2386 part 4* 9.IS:6241

5. BS: 812 part 114

*Aggregated may satisfy requirements of either of these two tests.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

**The water sensitivity test is only required if the minimum retained coating

in the stripping test is less than 95%.

Note: 1.The combined aggregate grading shall not very from the low limit on

one sieve to the high limit on the adjacent sieve.

2. Determined by the marshal method.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

14.3.4 Preparation of base

The surface on which the Bituminous Concrete is to be laid shall be

prepared in accordance with appropriate, or as directed by the Engineer. The

surface shall be thoroughly swept clean by mechanical broom and dust

removed by compressed air. In locations where a mechanical broom cannot

access, other approved methods shall be used as directed by the Engineer.

14.3.5 Geosynthetics

Where Geosvnthetics are specified in the Contract this shall be in

accordance with the requirements stated.

14.3.6 Stress absorbing layer

Where a stress absorbing layer is specified in the Contract, this shall be

applied in accordance with the requirements.

14.3.7 Tack coat

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Where specified in the Contract, or otherwise required by the Engineer, a

tack coat shall be applied in accordance with the provisions.

14.3.8 Mixing and transportation of the mixture

Pre-mixed bituminous materials, including bituminous macadam, dense

bituminous macadam, semi-dense bituminous concrete and bituminous

concrete, shall be prepared in a hot mix plant of adequate capacity and

capable of yielding a mix of proper and uniform quality with thoroughly

coated aggregates. Appropriate mixing temperatures can be found of these

Specifications; the difference in temperature between the binder and

aggregate should at no time exceed 14C.

In order to ensure uniform quality of the mix and better coating of

aggregates, the hot mix plant shall be calibrated from time to time.

If a continuous mixing plant is to be used for mixing the bituminous bound

macadam, the Contractor must demonstrate by laboratory analysis that the

cold feed combined grading is within the grading limits specified for that

bituminous bound material, in the case of a designed job mix, the bitumen

and filler content shall be derived using this combined grading. Further

details are available in the Manual for Construction and Supervision of

Bituminous Works.

Bituminous materials shall be transported in clean insulated vehicles, and

unless otherwise agreed by the Engineer, shall be covered while in transit or

waiting tipping. Subject to the approval of the Engineer, a thin coating of

diesel or lubricating oil may be applied to the interior of the vehicle to

prevent sticking and to facilitate discharge of the material.

14.4 Spreading

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Except in areas where a mechanical paver cannot access, bituminous

materials shall be spread, levelled and tamped by an approved self-propelled

paving machine. As soon as possible after arrival at site. The materials shall

be supplied continuously to the paver and laid without delay.

The rate of delivery of material to the paver shall be regulated to enable the

paver to operate continuously. The travel rate of the paver, and its method of

operations, shall be adjusted to ensure an even and uniform flow of

bituminous material across the screen, free from dragging, tearing, and

segregation of the material. In areas with restricted space where a

mechanical paver cannot be used, the material shall he spread, raked and

levelled with suitable hand tools by experienced staff, and compacted to the
satisfaction of the Engineer.

The minimum thickness of material laid in each paver pass shall be in

accordance with the minimum values given in the relevant parts of these

Specifications. When laying binder course or wearing course approaching an

expansion joint of a structure, machine laying shall stop 3mm short of the

joint. The remainder of the pavement up to the joint, and the corresponding

area beyond it, shall be laid by hand, and the joint or joint cavity shall be

kept clear of surfacing material.

Bituminous material, with a temperature greater than 1450C, shall not be

laid or deposited on bridge deck waterproofing systems, unless precautions

against heat damage have been approved by the Engineer. Hand placing of

pre-mixed bituminous materials shall only be permitted in the following

circumstances:

(1) For laying regulating courses of irregular shape and varying thickness.

(ii) In confined spaces where it is impracticable for a paver to operate. (iii) For

footways.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

(iv) At the approaches to expansion joints at bridges, viaducts or other

structures.

(v) For laying mastic asphalt.

(vi) For filling of potholes.

(vii) Where directed by the Engineer.

Manual spreading of pre-mixed wearing course material or the addition of

such material by hand-spreading to the paved area, for adjustment of level,

shall only be permitted in the following circumstances:

(i) At the edges of the layers of materials and at gullies and manholes.

(ii) At the approaches to expansion joints at bridges, viaducts or other

structures. (iii) As directed by the Engineer.

14.5 Rolling

Compaction of bituminous materials shall commence as soon as possible

after laying. Compaction shall be substantially completed before the

temperature falls below the minimum rolling temperatures stated in the

relevant part of these Specifications. Rolling of the longitudinal joints shall

be done immediately behind the paving operation.

After this, rolling shall commence at the edges and progress towards the

center longitudinally except that on super elevated and unidirectional

cambered portions, it shall progress from the lower to the upper edge

parallel to the center line of the pavement. Rolling shall continue until all

roller marks have been removed from the surface. All deficiencies in the

surface after laying shall he made good by the attendants behind the paver,

before initial rolling is commenced. The initial or breakdown rolling shall he

done with 8 10 tonnes dead weight smooth-wheeled.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

The intermediate rolling shall be done with 8 10 tonnes dead weight or

vibratory roller or with a pneumatic tyred roller of 12 to 15 tonnes weight

having nine wheels, with a tyre pressure of at least 5.6 kg/sqcm. The finish

rolling shall be done with 6 to 8 tonnes smooth wheeled tandem rollers.

14.5.1 Opening to Traffic

The newly laid surface shall not be open to traffic for at least 24 hours after

lying and the completion of compaction, without the express approval of the

Engineer in writing.

14.5.2 Surface Finish and Quality Control

The surface finish of the completed construction shall conform to the

requirements. All materials and workmanship shall comply with the

provisions set out in of this Specification.

14.5.3 Measurement for Payment

Dense Graded Bituminous Materials shall be measured as finished wok

either in cubic metres, tons or by the square metre at a specified thickness

as detailed on the Contract drawings, or documents, or as directed by the

Engineer.

14.5.4 Rate

The contract unit rate for Dense Graded Bituminous Macadam shall be

payment in full for carrying out the all required operations as specified, and

shall include, but not necessarily limited to all components. The rate shall

include the provision of bitumen, 4.25 per cent by weight of the total

mixture.

The variance in actual percentage of bitumen used will be assessed and the

payment adjusted, up or down. accordingly, except that the rate shall

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

include the provision of bitumen at 5.0 per cent, by weight of the total

mixture. The variance in actual percentage of bitumen used will be assessed

and the payment adjusted up or down, accordingly.

Tests for bituminous concrete

Marshal test

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

15. SURFACE DRESSING:

15.1 Scope

This work shall consist of the application of one coat or two coats of surface

dressing, each coat consisting of a layer of bituminous binder sprayed on a

previously prepared base, followed by a cover of stone chips rolled in to form

a wearing course to the requirements of these Specifications. For

information on the Design of Surface Dressing refer to the Manual for

Construction and Supervision of Bituminous Works.

15.2 Materials

15.2.1 Binder

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

The binder shall have a kinematic viscosity lying in the range 1 x 104 to 7 x

105 centistokes at the expected range of road surface temperatures at the

construction site during the period of laying. The type of binder to be used

will be stated in the Contract documents and shall comply with one of the

following:

Paving Bitumen IS: 73 Bitumen Emulsion IS: 8887

15.2.2 Aggregates

(i)Coarse aggregates

The coarse aggregates shall consist of crushed rock, crushed gravel or other
hard material retained on the 2,36 mm sieve. They shall be clean, hard, and

durable, of cubicle shape, free from dust and soft or friable matter. organic

or other deleterious matter. Where the Contractors selected source of

aggregates have poor affinity for bitumen, as a condition for the approval of

that source. The bitumen shall be treated with approved anti-stripping

agents, as per the manufacturers recommendations, without additional

payment. Before approval of the source, the aggregates shall be tested for

stripping.

Except that their water absorption shall be restricted to a maximum of I per

cent and they shall have a Polished Stone Value, as measured by the method

given in BS: 812 (Part 114), of not less than 60. The chips shall be single

sized, clean. hard, durable, of cubical shape, free from dus: and soft or

friable matter, organic or other deleterious matter and conforming to one of

the grading given in below Table.

15.2.3 Rates of spread of binder and chips

For the purpose of pricing the Bill of Quantities the rates of spread given in

Table27, shall be priced.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

15.2.4 Anti-stripping agent

Where the proposed aggregate fails to pass the stripping test then an

approved adhesion agent (Appendix 5 for details) may be added to the binder

in accordance with the manufacturer s instructions. The effectiveness of the

proposed anti-stripping agent must be demonstrated by the Contractor,

before approval by the Engineer. Dust removed in the process shall be blown

off with the help of compressed air.

15.2.5 Pre-coated chips

As an alternative to the use of an adhesion agent the chips may be pre-

coated before they are spread except when the sprayed binder film is a

bitumen emulsion. Pre-coating the chips may be carried out in any one of

the two methods:

(a) Mixing them with 0.75 to 1.0 per cent of paving bitumen by weight of

chips in a suitable mixer, the chips being heated to 1600C and the bitumen

to its application temperature. The precoated chips shall be allowed to cure

for at least one week or until they become non sticky and can be spread

easily.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

(b) Spraying the chips with a light application of creosote. Diesel oil or

kerosene at ambient temperature. This spraying can be done in a concrete

mixer or on a belt conveying the chips from stockpile to gritting Lorries.

15.3 Construction operations

15.3.1 Weather and seasonal limitations

Laying shall be suspended while freestanding water is present on the

surface to be covered, or during rain, fog and dust storms. After rain, the

bituminous surface, prime or tack coat shall be blown off with a high

pressure air jet to remove excess moisture, or the surface left to dry before

laying shall start. Laying of bituminous mixtures shall not be cal Tied out

when the air temperature at the surface on which it is to be laid is below

l00C or when the wind speed at any temperature exceeds 40 km/h at 2 m

height unless specifically approved by the Engineer.

15.3.2 Preparation of base

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

The base on which the surface dressing is to laid shall be prepared, shaped

and conditioned to the specified lines, grade and cross section in accordance

as directed by the Engineer. Prime coat.

Where needed, shall be provided directed by the Engineer. Where the

existing surface shows signs of fatting up, the excess bitumen shall be

removed by burning off, or manually, as specified. In the Contract or

directed by the Engineer. The bituminous surface to be dressed shall be

thoroughly cleaned either by using a mechanical broom and /or compressed

air, or any other approved equipment/method as specified in the Contract or

by the Engineer. The prepared surface shall be dust free, clean and dry,

(except in the case of cationic emulsion where the surface shall be damp).

15.3.3 Application of binder

The equipment and general procedures shall all be in accordance with the

Manual for Construction and Supervision of Bituminous Works. The

application temperature for the grade of binder used shall be as given in

below Table.

15.3.4 Application of stone chips

The equipment and general procedures shall all be in accordance with the

Manual for Construction and Supervision of Bituminous \Vorks. For

relatively small areas of surface dressing, carefully application of chips by

hand may be acceptable if approved by the Engineer. The rate of application

of chips shall be as determined by the procedure given in the Manual for

Construction and Supervision of Bituminous Works. Immediately after the

application of binder, clean, dry chips (in the case of emulsion binder the

chippings may be damp) shall be spread uniformly on the surface so as to

cover the surface completely with a single layer of chips.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

15.3.5 Rolling

Rolling of the chips should preferably be carried out by a pneumatic tyred

roller. Traditional steel wheeled rollers tend to crush the aggregates and if

their use cannot be avoided their weight should be limited to 8 tones. Rolling

shall commence at the edges and progress towards the centre except in

super elevated and unidirectional cambered portions where it shall proceed

from the lower edge to the higher edge. Each pass of the roller shall

uniformly overlap not less than one-third of the track made in the preceding

pass. While rolling is in progress additional chips shall be spread by hand in

necessary quantities required to make up irregularities. Rolling shall

continue until all aggregate particles are firmly embedded in the binder and

present a uniform closed surface.

15.3.6 Application of second coat of surface dressing

Where surface dressing in two coats is specified, the second coat should not

be applied until the first coat has been open to traffic for 2 or 3 weeks. The

surface on which the second coat is laid must be clean and free of dust. The

construction operations for the second coat shall be the same as described.

15.3.7 Opening to traffic

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

Traffic shall not be permitted to run on any newly surface dressed area until

the following day. In special circumstances, however, the Engineer may allow

the road to be opened to traffic immediately after rolling, hut in such cases

traffic speed shall be limited to 20 km per hour until the following day.

15.3.8 Surface Finish and Quality Control of Work

All works performed shall conform to the lines, grades, cross sections and

dimensions shown on the drawings or as directed by the Engineer, subject to

the permitted tolerances described hereinafter.

For control on the quality of materials and works carried out, the relevant

provisions shall apply.

15.3.9 Arrangements for Traffic

During the period of construction. arrangements for traffic shall be made in

accordance with 1he Contractor shall at all times carry out work on the

highway in a manner creating least interference to the flow of traffic while

consistent with the satisfactory execution of the same. For all works

involving improvements to the existing highway, the Contractor shall, in

accordance with the directives of the Engineer, provide and maintain, during

execution of the work, a passage for traffic either along a part of the existing

carriageway under improvement, or along a temporary diversion constructed

close to the highway. The Contractor shall take priot approval of the

Engineer regarding traffic arrangements during construction.

15.3.10 Measurement for Payment

Each coat of surface dressing shall be measured as finished work, for tire

area instructed to he covered, in square meters.

15.3.11 Rate

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

The Contract unit rate for surface dressing, based on the notional rates of

spread for binder and each size of chippings, which shall be adjusted, plus

or minus, for the, difference between the notional rates of spread and the

rates of spread determined as described in the Manual for Construction and

Supervision of Bituminous Works, and approved by the Engineer, multiplied

by the rates entered in the Bill of Quantities for binder and each size of

chipping.

The contract unit rate for premixed bituminous material shall be payment in

full for carrying out the required operations including full compensation for,

but not necessarily limited to:

(i) Making arrangements for traffic to except for initial treatment to verge,

shoulders and construction of diversions;

(ii) Preparation of the surface to receive the material.

(iii) Providing all materials to be incorporated in the work including

arrangement for stock yards. all royalties, fees, rents where necessary and

all leads and lifts;

(iv) Mixing, transporting, laying and compacting the mix, as specified.

(v) All labour, tools, equipment, plant including installation of hot mix plant,

power supply units and all machinery, incidental to complete the work to

these Specifications;

(vi) Carrying out the work in part widths of the road where directed; (vii)

Carrying out all tests for control of quality; and

(viii) The rate shall cover the provision of bitumen at the rate specified in the

contract, with the provision that the variation in actual percentage of

bitumen used will he assessed and the payment adjusted accordingly.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

(ix) The rates for premixed material are to include for all wastage in cutting

joints etc.

(x) The rates are to include for all necessary testing, mix design,

transporting and testing of samples, and cores. If there is not a project

specific laboratory, the Contractor must arrange to carry out all necessary

testing at an outside Laboratory. Approved by the Engineer, and all costs

incurred arc deemed to be included in the rate quoted for the material.

(xi) The cost of all plant and laying trials as specified to prove the mixing and

laying methods is deemed to be included in the Contractors rates for the

material.

16. SEPARATOR:-

16.1 Scope

The work shall consist of constructing footpaths and/or separators at

locations as specified in the drawings or as directed by the Engineer. The

lines levels and dimensions shall be as per the drawings. The scope of the

work shall include provision of all drainage arrangements as shown in the

drawings or as directed.

16.2 Materials

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

The footpaths and separators shall be constructed with any of the following

types:

(a)Cast-in-situ cement concrete of Grade M20 as per Section 1700 of the

specifications:

(b)Precast cement concrete blocks/tiles of Grade M20 as per section 1700 of

the specifications. The minimum thickness of the cement concrete block/tile

shall be 25 mm and minimum size shall be 300 mm x 300 mm.

(c) Natural stone slab cut and dressed from stone of good and sound quality,

uniform in texture, free from defects and at least equal to a sample

submitted by the contractor and approved by the Engineer. The minimum

thickness of the natural stone slab shall be 25 mm and minimum size shall

be 300mm x 300 mm.

16.3 Construction Operations

Drainage pipes below the footpath originating from the kerbs shall be first

laid in the required slope and connected to the drains/sumps/storm water

drain/drainage chutes as per provisions of the drawings, or as specified.

Portion on back side of kerbs shall be filled and compacted with granular

sub-base material of the specifications in specified thickness. The base shall

be prepared and finished to the required lines, levels and dimensions as

indicated in the drawings with the following:-

(a) Minimum 150mm thick, compacted granular sub-base material of the

Specifications, and Minimum 25mm thick cement concrete of Grade M

15.

16.3.1 Precast Cement concrete blocks/tiles/natural/stone slab

The blocks/tiles/slabs shall be set on a layer of average 12 mm thick

cement-sand mortar (1:3) laid on prepared base in such a way that there is

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

not rocking. The gaps between the blocks/tiles/slabs shall not be more than

12 mm and shall be filled with cement-sand mortar (1:3).

16.3.2 Cast-in-situ cement concrete

The minimum thickness of the cement concrete shall be 25 mm and it shall

be cast on the prepared base in panels of specified size in a staggered

manner. Construction joints shall be provided for the specifications.

16.3.3 Measurements for Payment

Footpaths and separators shall be measured in sq.metre between inside of

kerbs.

16.3.4 Rates

Contract unit rates shall be inclusive of full compensation of all labour,

materials, tools, equipment and incidental to construction of footpaths. Cost

of providing pipes and arrangements for their discharge into appropriate

drainage channels shall be incidental to the construction of footpaths.

17. References:-

1. Design of flexible pavements for a typical cross section on National

highway (NH-18) by NHAL.

2. Alignment for the existing gradient of the highway by ( Indian Road

Congress ) IRC:73& IRC: SP : 48-1998.

3. Design standards for flexible pavements in accordance with TOR and

based on relevant IRC codes, MORTH&H (Minister of road Transport &

Highway ) and BIS(Bureau of Indian standards ) specifications.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

4. Design standards for structure accordance with IRC: 5- 1998, IRC: 38,

IRC:73,IRC:38,IRC:6-2000, IRC:6-2000 and IS: 1893-1984, MORTH

specification &IRC: sp:13.

5. Indian standards for road drainage by IRC: SP:42-1994,IRC:37.

6.Material specification by IS:1077 for bricks IS:1124 for stones ,IS:210 for

cast iron, IS:8112,IS:12269&IS:12230for cement IS:383&IS:2386 for corse

aggregate parts 1to 7,IS:2116 for fine aggregate,IS:1030for steel.

7. Free swelling index exceeding 50 percent when tested as per IS:2720-

part40(BS-British standards)BS:1377.

8. Optimum moisture content compaction& rolling obtained in accordance

with IS:2720(part).

9. For granular sub-base the water absorption value of the coarse aggregate

shall be determined as per IS:2386(part3);BS:812 (part111) and the

soundness test shall be carried out on the material delivery to site as per

IS:383.

10. For prime coat the porosity characteristics of the surface to be primed as

classified in IRC:16. And viscosity of the primer shall comply with

requirements of IS: 8887 & for bituminous temperature in the shade is less

than 100c.

11. For task coat shall be a bituminous emulsion complying with IS:888 &

use of cutback bitumen as per IS:217.


12. for wet mix macadam the soundness test shall be carried out on the

material delivery to site as pr IS: 2386(part-5).


13. For dense bituminous macadam Indian standard specifications for

Paving Bitumen IS: 73 & the Asphalt Institute Manual MS-2.

S.K.D ENGINEERING COLLEGE


DEPARTMENT OF CIVIL ENGINEERING 2010-2014

14. For bituminous concrete temperature between thew binder and

aggregate should at no time exceed 14c.


15.For seal coat (surface dressing) Except that their water absorption shall

be restricted to a maximum of 1 per cent and they shall a polished stone

value, as measured method given in BS:812(part114),of not less than 60.

18. Conclusion:-

Pavement from the basic supporting structure in highway transport

each layer of pavement has a multiple of functions to perform which

has to be considered during the construction process.

Improper construction of pavement loads to early failure of pavements

affecting the riding quality also.

In the construction of flexible pavement the quality control of material

used in the construction is most important.

Mainly the material used in the construction will decided by the

national highway of authority (NHAI).

To maintain the quality control we can avoid the damage of highway

and the life of flexible pavements (highway road) will also increases.

Finally to include that we have studied the details and construction of

flexible pavement and we can say that highway can be useful for the

advancement of the community economics prosperity and general

development of the country.

S.K.D ENGINEERING COLLEGE

You might also like