IWIN BRIGHT
Total
Labour Grand
Description Qty Price Qty Material Remark
charge Total
SI No Price
Supply and installation of 2x4cx150mm2 XLPE/ SWA/PVC/Cu+ ECC cable
1 L.Sum 94600 140 43039.5 15000 58039.5
from SMDB-EL to new MCCP-18/1
Cable glanding and termination of 2x4cx 150mm2 XLPE/ SWA/PVC/Cu+
L.Sum 3850 L.Sum 480 1350 1830
2 ECC cable in the SMDB and new MCCP-18/1
Supply and installation of new 500A MCCP- 18/1 as per the new Without VFD
L.Sum 28300 8850 720 9570
3 requirement. & Starter
Supply and installation of 4cx95mm2 XLPE/ SWA/PVC/Cu+ ECC cable
4 L.Sum 15100 L.Sum L.Sum 15100
from MCCP-18/1 to new pump control panel
Cable glanding and termination of 4cx 95mm2 XLPE/ SWA/PVC/Cu+ ECC
L.Sum 3600 450 850 1300
5 cable in the MCCP- 18/1 and pump control panel
Disconnect and removal of MCCP-18/1 incomer cable (4cx185mm2
L.Sum 10700 L.Sum 1950 1950
6 XLPE/ SWA/PVC/Cu+ ECC) fed from MDB-18
Disconnect all the outgoing cables and removal of existing MCCP-18/1
L.Sum 2450 L.Sum 1600 1600
7
Disconnect and removal of Pump control panels incomer cable fed from
L.Sum 1450 L.Sum 850 850
8 MCCP-18/1
9 Supply and installation of new 600A SMDB-EL in the MDB room. L.Sum 13700 7250 720 7970
Supply and installation of 2x4cx185mm2 XLPE/ SWA/PVC/Cu+ ECC cable
L.Sum 40100 24 4824 1200 6024
10 from MDB-18 to new SMDB-EL
Supply and installation of cable tray containment for the above cable.
L.Sum 5150 2400 1800 4200
11
Cable glanding and termination of 2x4cx 185mm2 XLPE/ SWA/PVC/Cu+
L.Sum 3850 650 1400 2050
12 ECC cable in the MDB and new SMDB-EL
222850 110483.5
Supervision Charge 15000
125483.5
Exclution:
VFD
Starter
MDB-18 Modification works
Motor Control Panel