Comaprison For Electrical maintenance work at burj daman (24 Floor)

IWIN BRIGHT
Total
Labour Grand
Description Qty Price Qty Material Remark
charge Total
SI No Price
Supply and installation of 2x4cx150mm2 XLPE/ SWA/PVC/Cu+ ECC cable
1 L.Sum 94600 140 43039.5 15000 58039.5
from SMDB-EL to new MCCP-18/1
Cable glanding and termination of 2x4cx 150mm2 XLPE/ SWA/PVC/Cu+
L.Sum 3850 L.Sum 480 1350 1830
2 ECC cable in the SMDB and new MCCP-18/1
Supply and installation of new 500A MCCP- 18/1 as per the new Without VFD
L.Sum 28300 8850 720 9570
3 requirement. & Starter
Supply and installation of 4cx95mm2 XLPE/ SWA/PVC/Cu+ ECC cable
4 L.Sum 15100 L.Sum L.Sum 15100
from MCCP-18/1 to new pump control panel
Cable glanding and termination of 4cx 95mm2 XLPE/ SWA/PVC/Cu+ ECC
L.Sum 3600 450 850 1300
5 cable in the MCCP- 18/1 and pump control panel
Disconnect and removal of MCCP-18/1 incomer cable (4cx185mm2
L.Sum 10700 L.Sum 1950 1950
6 XLPE/ SWA/PVC/Cu+ ECC) fed from MDB-18
Disconnect all the outgoing cables and removal of existing MCCP-18/1
L.Sum 2450 L.Sum 1600 1600
7
Disconnect and removal of Pump control panels incomer cable fed from
L.Sum 1450 L.Sum 850 850
8 MCCP-18/1
9 Supply and installation of new 600A SMDB-EL in the MDB room. L.Sum 13700 7250 720 7970
Supply and installation of 2x4cx185mm2 XLPE/ SWA/PVC/Cu+ ECC cable
L.Sum 40100 24 4824 1200 6024
10 from MDB-18 to new SMDB-EL
Supply and installation of cable tray containment for the above cable.
L.Sum 5150 2400 1800 4200
11
Cable glanding and termination of 2x4cx 185mm2 XLPE/ SWA/PVC/Cu+
L.Sum 3850 650 1400 2050
12 ECC cable in the MDB and new SMDB-EL
222850 110483.5
Supervision Charge 15000
125483.5

Exclution:
VFD
Starter
MDB-18 Modification works
Motor Control Panel