BAHAN LANTAI
1 Keramik 30x30 cm polos Ktk 56,000.00
2 Keramik 30x30 cm motif/warna Ktk 62,000.00
3 Keramik 30x30 cm anti slip / motif kulit jeruk Ktk 67,000.00
4 Keramik 10x20 cm warna Ktk 66,000.00
5 Keramik 20x20 cm polos Ktk 60,000.00
6 Keramik 20x20 cm warna Ktk 66,000.00
7 Keramik 20x25 cm polos Ktk 60,000.00
8 Keramik 20x25 cm warna Ktk 66,000.00
9 Keramik 40x40 cm motif Ktk 67,000.00
10 Keramik 40x40 cm polos Ktk 60,000.00
11 Granit 30 x 30 cm Ktk -
12 Granit 40 x 40 cm Ktk -
13 Teralux Marmer 40 x 40 cm M2 -
14 Teralux Marmer 30 x 30 cm M2 -
15 Teralux Marmer 60 x 60 cm M2 -
16 Marmer 100 x 100 cm M2 234,000.00
17 Plint keramik 10x20 cm warna Bh 12,000.00
18 Plint keramik 10x30 cm polos Bh 1,800.00
19 Plint keramik 10x30 cm Warna Bh 2,000.00
20 Plint keramik 10x40 cm polos Bh 2,600.00
21 Plint keramik 10x40 cm Warna Bh 2,900.00
22 Plint keramik 10x20 KM/WC Bh 13,000.00
23 Plint granit 10x30 cm Bh -
24 Plint granit 10x40 cm Bh -
25 Plint teralux marmer 10x30 cm Bh -
26 Plint teralux marmer 10x40 cm Bh -
27 Plint teralux marmer 10x60 cm Bh -
28 Paving block/Conblock t = 6 cm Bh 1,450.00
30 Batu Teraso Kg -
31 Porselen (11 x 11) Cm Bh -
32 Cincin keramik Biasa Bh 625.00
33 Cincin keramik Kualitas Bh 1,100.00
1 Bahan 2016
BAHAN DINDING
1 Batu bata kecil Bh 500.00
2 Batu bata bolong besar Bh 650.00
3 Conblock HB 20 Bh -
4 Conblock HB 15 Bh -
5 Conblock HB 10 Bh -
6 Beton roster 12 x 10 x 24 Cm Bh -
7 Beton roster 20 x 20 Cm Bh 10,300.00
8 Beton roster 3 0 x 30 Cm Bh 20,500.00
9 Glassblock Bh 25,000.00
10 Batu muka berwarna M2 -
11 Batu palimanan M2 200,000.00
12 Batako Bh 5,000.00
13 Batu tempel hitam M2 200,000.00
BAHAN KAYU
1 Kayu balok klas I M3 6,000,000.00
2 Kayu balok klas II M3 2,150,000.00
3 Kayu reng klas II M3 2,550,000.00
4 Kayu balok klas III M3 1,935,000.00
5 Kayu papan klas I ( lisplank ) M3 8,000,000.00
6 Kayu papan klas I M3 6,000,000.00
7 Kayu papan tembesu M3 5,200,000.00
8 Kayu papan klas II M3 2,150,000.00
9 Kayu papan klas III M3 1,935,000.00
10 Kayu papan klas IV M3 1,700,000.00
11 Dolken kayu 8-10/400 Cm Btg 6,200.00
12 Kayu gelam 12/400 Cm Btg 20,500.00
13 Formtie/penjaga jarak bekisting/spacer Btg 6,200.00
2 Bahan 2016
15 Jaring Kawat Baja (dilas) kg -
16 Kawat bronjong kg 12,500.00
18 Kawat duri Kg 12,500.00
19 Kabel Presstressed Polos/Strands Kg 12,500.00
20 Kawat nyamuk M2 16,500.00
21 Kawat kassa M2 16,500.00
22 Kawat Burung M2 16,500.00
23 Kawat las listrik Kg 26,000.00
24 Mour dan baut 10 mm x 12 " Bh 6,750.00
25 Mour dan baut 12 mm x 12 ' Bh 7,750.00
27 Paku biasa Kg 17,000.00
28 Paku triplek Kg 21,000.00
29 Paku sekrup fixer Bh 3,200.00
30 Paku sekrup Kg 28,000.00
31 Paku beton Kg 31,000.00
32 Paku seng Kg 28,000.00
33 Paku genteng Kg 33,000.00
34 Paku GRC Kg 28,000.00
35 Pagar besi biasa M2 460,000.00
36 Pagar besi kombinasi plat lengkap M2 540,000.00
37 Pagar Besi Holo M2 485,000.00
38 Pintu pagar besi hollo M2 585,000.00
39 Teralis pintu besi ulir M2 500,000.00
40 Teralis pintu besi polos M2 450,000.00
41 Teralis jendela besi ulir M2 450,000.00
42 Teralis jendela besi polos M2 385,000.00
43 Rolling door besi M2 -
BAHAN ALMUNIUM
1 Profil Aluminium M1 77,000.00
2 Aluminium Strip M1 7,500.00
2 Rangka Pintu Alluminium M1 150,000.00
4 Sealant Tube 20,000.00
5 Pagar BRC 60x240 Cm M2 200,000.00
6 Pagar BRC 90x240 Cm M2 230,000.00
7 Pagar BRC 120x240 Cm M2 265,000.00
8 Profil kaca M1 -
9 Rangka atap baja ringan M2 130,000.00
10 Rolling door aluminium M2 385,000.00
11 Skrup Fixer Kg 28,000.00
12 Sunscreen alluminium M2 170,000.00
13 Kusen dan Pintu kamar mandi PVC Bh 850,000.00
14 Kunci pintu 2 slaag kualitas Bh 195,000.00
15 Kunci pintu 2 slaag biasa Bh 110,000.00
16 Kunci Tanam Kamar mandi Bh 65,000.00
17 Kunci Silinder Bh 55,000.00
18 Kunci selot Bh 55,000.00
19 Kunci tanam antik Bh 90,000.00
20 Kunci tanam biasa Bh 65,000.00
21 Engsel pintu Bh 13,500.00
22 Engsel jendela Bh 10,000.00
23 Tarikan pintu kualitas Bh 105,000.00
24 Tarikan pintu biasa Bh 20,000.00
25 Hak angin kualitas Bh 15,000.00
26 Hak angin biasa Bh 6,700.00
27 Tarikan jendela Bh 6,300.00
28 Grendel pintu Bh 15,300.00
29 Grendel jendela Bh 7,500.00
30 Grendel pintu Espanolete Psg -
31 Door closer Bh 160,000.00
32 Pegangan Pintu/Door Holder Bh 160,000.00
33 Door stop Bh 27,000.00
34 Door holder Bh -
35 Rel pintu dorong Bh -
36 Rolling door plastik (PVC) M2 -
37 Kunci lemari Bh 13,500.00
3 Bahan 2016
16 Bak mandi fibre glass ( 0.3 M3 ) Bh 350,000.00
17 Tangki air fibre glass 1100 ltr Bh 1,400,000.00
18 Elbow 1/2" Bh 4,000.00
19 Elbow 3/4" Bh 4,000.00
20 Elbow 1" Bh 6,000.00
21 Elbow 1 1/2" Bh 7,000.00
22 Elbow 2" Bh 10,000.00
23 Elbow 2 1/2" Bh 10,000.00
24 Elbow 3" Bh 15,000.00
25 Elbow 4" Bh 20,000.00
26 Shock 1/2" Bh 4,000.00
27 Shock 3/4" Bh 4,000.00
28 Shock/T 1" Bh 6,000.00
29 Shock 2 1/2" Bh 8,500.00
30 Shock 2" Bh 11,000.00
31 Shock 3" Bh 14,500.00
32 Shock 4" Bh 18,000.00
33 Shockdrat 3/4" Bh 5,500.00
34 Shockdrat 1/2" Bh 4,000.00
36 Selotip paralon / seal tape Bh 4,500.00
37 Pompa air Bh 450,000.00
BAHAN SANITARI
1 Closed duduk keramik (otomatis) Bh 1,800,000.00
2 Closed jongkok biasa Bh 135,000.00
3 Closed jongkok keramik standar Bh 250,000.00
4 Wastafel lengkap Unit 400,000.00
5 Kran biasa, uk. 1/2 & 3/4 Bh 15,000.00
6 Kran stainless, uk. 1/2 & 3/4 Bh 38,000.00
7 Floor drain Bh 16,000.00
8 Bak cuci piring aluminium Bh 250,000.00
9 Water drain + acsesories Bh 58,000.00
10 Urinoir Bh 1,025,000.00
11 Bak teraso Bh -
12 Badkip Porselen Bh -
BAHAN FINISHING
1 Cat besi Kg 57,000.00
2 Cat genteng Kg 36,000.00
3 Cat tembok Kg 22,500.00
4 Cat tembok (weathershield) Kg 135,000.00
5 Cat kayu Kg 56,500.00
6 Cat dasar tembok Kg 18,000.00
6 Cat dasar kayu Kg 34,000.00
7 Minyak cat Ltr 11,500.00
8 Minyak bekisting Ltr 8,500.00
9 Dempul kayu Kg 23,500.00
10 Meni Kg 36,000.00
11 Kapur Kg 7,200.00
12 Plamir tembok Kg 8,500.00
13 Ter/residu Ltr 12,000.00
14 Plitur Ltr 62,000.00
15 Vernis Ltr 55,000.00
16 Tiner Ltr 24,000.00
17 Batu apung Kg 24,000.00
18 Teak oil Ltr 12,000.00
19 Wall Paper M2 20,000.00
20 Lem aibon Kg 60,000.00
21 Lem vinyl Kg 45,000.00
22 Amplas Lbr 4,000.00
23 Lem kayu ( fox ) Kg 27,000.00
24 Soda api Kg 22,000.00
25 Sabun Kg 27,000.00
26 Kuas Bh 25,000.00
BAHAN KACA
1 Kaca bening 3 mm M2 92,000.00
2 Kaca bening 5 mm M2 108,000.00
3 Kaca bening 8 mm M2 155,000.00
4 Kaca bening 10 mm M2 220,000.00
5 Kaca rayban 3 mm M2 77,000.00
6 Kaca rayban 5 mm M2 91,000.00
7 Kaca rayban 8 mm M2 140,000.00
8 Kaca rayban 10 mm M2 238,000.00
9 Kaca biru 5 mm M2 115,000.00
10 Kaca Cermin, Tebal 5 mm M2 135,000.00
4 Bahan 2016
11 Kaca Cermin, Tebal 6 mm M2 140,000.00
12 Kaca Cermin, Tebal 8 mm M2 155,000.00
13 Kaca buram tebal 12 mm -
14 Kaca "Wireglass", Tebal 5 mm M2 112,000.00
15 Kaca Patri, Tebal 5 mm M2 113,000.00
BAHAN LAIN-LAIN
1 Jendela Nako Bh 130,000.00
2 Ijuk M3 -
3 Rapidrant Gln -
4 Puzzdith-100 XR Ltr -
5 Strorox-100 Ltr -
6 Spring knip Bh -
7 Papan nama proyek Unit 225,000.00
8 Barak kerja Unit 1,800,000.00
9 Sewa barak kerja Unit 700,000.00
10 Panel beton pracetak Lbr 140,000.00
11 Kolom beton pracetak Btg 335,000.00
12 Wall papper M2 -
5 Bahan 2016
PEMERINTAH KABUPATEN BATANG HARI
DINAS PEKERJAAN UMUM
JALAN SULTAN THAHA NO. TELP. 0743 - 21041
MUARA BULIAN
Kode Pos 36613
A. 2.2.1.3 Pembuatan 1 M2 pagar sementara dari kawat duri tinggi 1,8 meter
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3000 65,000.00 19,500.00
Tukang Kayu OH 0.2000 90,000.00 18,000.00
Kepala Tukang OH 0.0200 110,000.00 2,200.00
Mandor OH 0.0200 100,000.00 2,000.00
JUMLAH TENAGA KERJA 41,700.00
B BAHAN
Dolken Kayu 8-10 / 400 cm Batang 1.0000 6,200.00 6,200.00
Semen Portlant Kg 2.0000 1,440.00 2,880.00
Kawat Duri M1 25.0000 12,500.00 312,500.00
Pasir Beton M3 0.0050 85,000.00 425.00
Kerikil M3 0.0090 300,000.00 2,700.00
Paku Biasa Kg 0.0600 17,000.00 1,020.00
JUMLAH HARGA BAHAN 325,725.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
7 Analisa 2016
A. 2.2.1.5 Pembuatan 1 M2 kantor sementara lantai plesteran
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 2.0000 65,000.00 130,000.00
Tukang Kayu OH 2.0000 90,000.00 180,000.00
Tukang Batu OH 1.0000 90,000.00 90,000.00
Kepala Tukang OH 0.3000 110,000.00 33,000.00
Mandor OH 0.0500 100,000.00 5,000.00
JUMLAH TENAGA KERJA 438,000.00
B BAHAN
Dolken Kayu 8-10 / 400 cm Batang 1.2500 6,200.00 7,750.00
Kayu M3 0.1800 2,150,000.00 387,000.00
Paku Biasa Kg 0.0800 17,000.00 1,360.00
Besi Strip Kg 1.1000 13,000.00 14,300.00
Semen Portlant Kg 35.0000 1,440.00 50,400.00
Pasir Pasang M3 0.1500 85,000.00 12,750.00
Pasir Beton M3 0.1000 85,000.00 8,500.00
Kerikil M3 0.1500 300,000.00 45,000.00
Bata Merah Buah 30.0000 500.00 15,000.00
Seng Gelombang Lbr 1.5000 39,000.00 58,500.00
Jendela nako Buah 0.2000 130,000.00 26,000.00
Kaca Polos 5 mm M2 0.0800 108,000.00 8,640.00
Kunci Tanam Buah 0.1500 65,000.00 9,750.00
Triplek 4 mm Lbr 0.0600 72,000.00 4,320.00
JUMLAH HARGA BAHAN 649,270.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
8 Analisa 2016
A. 2.2.1.9 Pembersihan 1 M2 lapangan dan perataan
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1000 65,000.00 6,500.00
Mandor OH 0.0500 100,000.00 5,000.00
JUMLAH TENAGA KERJA 11,500.00
B BAHAN
10 Analisa 2016
A. 2.2.1.16. Pemasangan 1 M2 panel beton pracetak 5x50x213 cm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3750 65,000.00 24,375.00
Tukang Kayu OH 0.1250 90,000.00 11,250.00
Kepala Tukang OH 0.0120 110,000.00 1,320.00
Mandor OH 0.0190 100,000.00 1,900.00
JUMLAH TENAGA KERJA 38,845.00
B BAHAN
Panel beton pracetak Lbr 0.9860 140,000.00 138,040.00
Kolom beton pracetak Btg 0.5250 335,000.00 175,875.00
Semen PC Kg 45.0000 1,440.00 64,800.00
Pasir beton M3 0.0740 85,000.00 6,290.00
Kerikil M3 0.1460 300,000.00 43,800.00
JUMLAH HARGA BAHAN 428,805.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
11 Analisa 2016
A. 2.3.1.4 Menggali 1 M3 Tanah keras sedalam 1 M
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.0000 65,000.00 65,000.00
Mandor OH 0.0320 100,000.00 3,200.00
JUMLAH TENAGA KERJA 68,200.00
B BAHAN
12 Analisa 2016
A. 2.3.1.9 Pengurugan kembali 1 M3 galian tanah
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.2500 65,000.00 16,250.00
Mandor OH 0.0083 100,000.00 830.00
JUMLAH TENAGA KERJA 17,080.00
B BAHAN
0.00
JUMLAH HARGA BAHAN 0.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
13 Analisa 2016
A. 2.3.1.13 Pemasangan 1 m2 lapisan ijuk tebal 10 cm untuk bidang resapan
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1500 65,000.00 9,750.00
Mandor OH 0.0150 100,000.00 1,500.00
JUMLAH TENAGA KERJA 11,250.00
B BAHAN
Ijuk M3 6.0000 0.00 0.00
JUMLAH HARGA BAHAN 0.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
14 Analisa 2016
A. 3.2.1.9 Pemasangan 1 M3 Batu Kosong (Aanstamping)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.780 65,000.00 50,700.00
Tukang Batu OH 0.390 90,000.00 35,100.00
Kepala Tukang OH 0.039 110,000.00 4,290.00
Mandor OH 0.039 100,000.00 3,900.00
JUMLAH TENAGA KERJA 93,990.00
B BAHAN
Batu Belah/Batu Kali M3 1.200 330,000.00 396,000.00
Pasir Urug M3 0.432 75,000.00 32,400.00
JUMLAH HARGA BAHAN 428,400.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.1.1.2 Membuat 1 M3 Beton mutu f'c = 9,8 Mpa (K.125), Slump 12 2, w/c=0,78
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.6500 65,000.00 107,250.00
Tukang Batu OH 0.2750 90,000.00 24,750.00
Kepala Tukang OH 0.0280 110,000.00 3,080.00
Mandor OH 0.0830 100,000.00 8,300.00
JUMLAH TENAGA KERJA 143,380.00
B BAHAN
Semen Portlant Kg 276.0000 1,440.00 397,440.00
Pasir Beton M3 0.5910 85,000.00 50,235.00
Kerikil (Maks. 30 mm) M3 0.7496 300,000.00 224,880.00
Air Liter 215.0000 50.00 10,750.00
JUMLAH HARGA BAHAN 683,305.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.1.1.3 Membuat 1 M3 Beton mutu f'c = 12,2 Mpa (K 150), Slump 12 2, w/c=0,72
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.6500 65,000.00 107,250.00
Tukang Batu OH 0.2750 90,000.00 24,750.00
Kepala Tukang OH 0.0280 110,000.00 3,080.00
Mandor OH 0.0830 100,000.00 8,300.00
JUMLAH TENAGA KERJA 143,380.00
B BAHAN
Semen Portlant Kg 299.0000 1,440.00 430,560.00
Pasir Beton M3 0.5707 85,000.00 48,509.50
Kerikil (Maks. 30 mm) M3 0.7533 300,000.00 225,990.00
Air Liter 215.0000 50.00 10,750.00
JUMLAH HARGA BAHAN 715,809.50
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
15 Analisa 2016
F Harga Satuan Pekerjaan (D+E) 945,108.45
16 Analisa 2016
A.4.1.1.3a Membuat 1 M3 Beton mutu f'c = 12,2 Mpa (K 150), Slump 12 2, w/c=0,72
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.6500 65,000.00 107,250.00
Tukang Batu OH 0.2750 90,000.00 24,750.00
Kepala Tukang OH 0.0280 110,000.00 3,080.00
Mandor OH 0.0830 100,000.00 8,300.00
JUMLAH TENAGA KERJA 143,380.00
B BAHAN
Semen Portlant Kg 299.0000 1,440.00 430,560.00
Pasir Beton M3 0.5707 85,000.00 48,509.50
Kerikil (Maks. 30 mm) M3 0.7533 300,000.00 225,990.00
Air Liter 215.0000 50.00 10,750.00
JUMLAH HARGA BAHAN 715,809.50
C PERALATAN
Molen 0,35 M3 Hari 0.200 140,000.00 28,000.00
JUMLAH HARGA ALAT 28,000.00
A.4.1.1.4 Membuat 1 M3 lantai kerja beton mutu f'c = 7,4 Mpa (K.100), Slump (3-6) cm, w/c=0,87
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.2000 65,000.00 78,000.00
Tukang Batu OH 0.2000 90,000.00 18,000.00
Kepala Tukang OH 0.0200 110,000.00 2,200.00
Mandor OH 0.0600 100,000.00 6,000.00
JUMLAH TENAGA KERJA 104,200.00
B BAHAN
Semen Portlant Kg 230.0000 1,440.00 331,200.00
Pasir Beton M3 0.6379 85,000.00 54,221.50
Kerikil (Maks. 30 mm) M3 0.7607 300,000.00 228,210.00
Air Liter 200.0000 50.00 10,000.00
JUMLAH HARGA BAHAN 623,631.50
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.1.1.5 Membuat 1 M3 Beton mutu f'c = 14,5 Mpa (K.175), Slump (12 2) cm, w/c=0,66
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.6500 65,000.00 107,250.00
Tukang Batu OH 0.2750 90,000.00 24,750.00
Kepala Tukang OH 0.0280 110,000.00 3,080.00
Mandor OH 0.0830 100,000.00 8,300.00
JUMLAH TENAGA KERJA 143,380.00
B BAHAN
Semen Portlant Kg 326.0000 1,440.00 469,440.00
Pasir Beton M3 0.5429 85,000.00 46,146.50
Kerikil (Maks. 30 mm) M3 0.7622 300,000.00 228,660.00
Air Liter 215.0000 50.00 10,750.00
JUMLAH HARGA BAHAN 754,996.50
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.1.1.5a Membuat 1 M3 Beton mutu f'c = 14,5 Mpa (K.175), Slump (12 2) cm, w/c=0,66
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.6500 65,000.00 107,250.00
Tukang Batu OH 0.2750 90,000.00 24,750.00
Kepala Tukang OH 0.0280 110,000.00 3,080.00
Mandor OH 0.0830 100,000.00 8,300.00
JUMLAH TENAGA KERJA 143,380.00
B BAHAN
Semen Portlant Kg 326.0000 1,440.00 469,440.00
Pasir Beton M3 0.5429 85,000.00 46,146.50
Kerikil (Maks. 30 mm) M3 0.7622 300,000.00 228,660.00
Air Liter 215.0000 50.00 10,750.00
JUMLAH HARGA BAHAN 754,996.50
C PERALATAN
Molen 0,35 M3 Hari 0.200 140,000.00 28,000.00
JUMLAH HARGA ALAT 28,000.00
17 Analisa 2016
18 Analisa 2016
A.4.1.1.6 Membuat 1 M3 Beton mutu f'c = 16,9 Mpa (K 200), Slump (12 2) cm, w/c=0,61
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.6500 65,000.00 107,250.00
Tukang Batu OH 0.2750 90,000.00 24,750.00
Kepala Tukang OH 0.0280 110,000.00 3,080.00
Mandor OH 0.0830 100,000.00 8,300.00
JUMLAH TENAGA KERJA 143,380.00
B BAHAN
Semen Portlant Kg 352.0000 1,440.00 506,880.00
Pasir Beton M3 0.5221 85,000.00 44,378.50
Kerikil (Maks. 30 mm) M3 0.7637 300,000.00 229,110.00
Air Liter 215.0000 50.00 10,750.00
JUMLAH HARGA BAHAN 791,118.50
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.1.1.6a Membuat 1 M3 Beton mutu f'c = 16,9 Mpa (K 200), Slump (12 2) cm, w/c=0,61
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.6500 65,000.00 107,250.00
Tukang Batu OH 0.2750 90,000.00 24,750.00
Kepala Tukang OH 0.0280 110,000.00 3,080.00
Mandor OH 0.0830 100,000.00 8,300.00
JUMLAH TENAGA KERJA 143,380.00
B BAHAN
Semen Portlant Kg 352.0000 1,440.00 506,880.00
Pasir Beton M3 0.5221 85,000.00 44,378.50
Kerikil (Maks. 30 mm) M3 0.7637 300,000.00 229,110.00
Air Liter 215.0000 50.00 10,750.00
JUMLAH HARGA BAHAN 791,118.50
C PERALATAN
Molen 0,35 M3 Hari 0.2000 140,000.00 28,000.00
JUMLAH HARGA ALAT 28,000.00
A.4.1.1.7 Membuat 1 M3 Beton mutu f'c = 19,3 Mpa (K.225), Slump (12 2) cm, w/c=0,58
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.6500 65,000.00 107,250.00
Tukang Batu OH 0.2750 90,000.00 24,750.00
Kepala Tukang OH 0.0280 110,000.00 3,080.00
Mandor OH 0.0830 100,000.00 8,300.00
JUMLAH TENAGA KERJA 143,380.00
B BAHAN
Semen Portlant Kg 371.0000 1,440.00 534,240.00
Pasir Beton M3 0.4986 85,000.00 42,381.00
Kerikil (Maks. 30 mm) M3 0.7756 300,000.00 232,680.00
Air Liter 215.0000 50.00 10,750.00
JUMLAH HARGA BAHAN 820,051.00
C PERALATAN
Molen 0,35 M3 Hari 0.200 140,000.00 28,000.00
JUMLAH HARGA ALAT 28,000.00
A.4.1.1.8 Membuat 1 M3 Beton mutu f'c = 21,7 Mpa (K.250), Slump (12 2) cm, w/c=0,56
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.6500 65,000.00 107,250.00
Tukang Batu OH 0.2750 90,000.00 24,750.00
Kepala Tukang OH 0.0280 110,000.00 3,080.00
Mandor OH 0.0830 100,000.00 8,300.00
JUMLAH TENAGA KERJA 143,380.00
B BAHAN
Semen Portlant Kg 384.0000 1,440.00 552,960.00
Pasir Beton M3 0.4943 85,000.00 42,015.50
Kerikil (Maks. 30 mm) M3 0.7696 300,000.00 230,880.00
Air Liter 215.0000 50.00 10,750.00
JUMLAH HARGA BAHAN 836,605.50
C PERALATAN
Molen 0,35 M3 Hari 0.2000 140,000.00 28,000.00
JUMLAH HARGA ALAT 28,000.00
19 Analisa 2016
20 Analisa 2016
1 M3 membuat Beton adukan 1 Pc : 3 Ps : 5 Krl (SNI- 2002)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.6500 65,000.00 107,250.00
Tukang Batu OH 0.2500 90,000.00 22,500.00
Kepala Tukang OH 0.0250 110,000.00 2,750.00
Mandor OH 0.0800 100,000.00 8,000.00
JUMLAH TENAGA KERJA 140,500.00
B BAHAN
Semen Portlant Kg 218.0000 1,440.00 313,920.00
Pasir Beton M3 0.5200 85,000.00 44,200.00
Kerikil (Maks. 30 mm) M3 0.8700 300,000.00 261,000.00
Air Liter 215.0000 50.00 10,750.00
JUMLAH HARGA BAHAN 629,870.00
C PERALATAN
Molen 0,35 M3 Hari 0.2000 140,000.00 28,000.00
JUMLAH HARGA ALAT 28,000.00
21 Analisa 2016
A.4.1.1.19 Pemasangan 10 Kg kawat baja (Wiremesh)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0250 65,000.00 1,625.00
Tukang Besi OH 0.0250 90,000.00 2,250.00
Kepala Tukang OH 0.0250 110,000.00 2,750.00
Mandor OH 0.0010 100,000.00 100.00
JUMLAH TENAGA KERJA 6,725.00
B BAHAN
Jaring Kawat Baja (dilas) Kg 10.2000 0.00 0.00
Kawat Beton Kg 0.0500 19,000.00 950.00
JUMLAH HARGA BAHAN 950.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
22 Analisa 2016
A.4.1.1.23 Pemasangan 1 M2 Bekisting untuk balok
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.6600 65,000.00 42,900.00
Tukang Kayu OH 0.3300 90,000.00 29,700.00
Kepala Tukang OH 0.0330 110,000.00 3,630.00
Mandor OH 0.0330 100,000.00 3,300.00
JUMLAH TENAGA KERJA 79,530.00
B BAHAN
Kayu Klas III M3 0.0400 1,935,000.00 77,400.00
Paku Biasa 2"-5" Kg 0.4000 17,000.00 6,800.00
Minyak Bekisting Kg 0.2000 8,500.00 1,700.00
Balok Kayu Klas II M3 0.0180 2,150,000.00 38,700.00
Plywood Tebal 9 mm Lbr 0.3500 135,000.00 47,250.00
Kayu Dolken 8-10 cm, P=400 cm Batang 2.0000 6,200.00 12,400.00
JUMLAH HARGA BAHAN 184,250.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
23 Analisa 2016
A.4.1.1.26 Pemasangan 1 M2 Bekisting untuk Tangga
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.6600 65,000.00 42,900.00
Tukang Kayu OH 0.3300 90,000.00 29,700.00
Kepala Tukang OH 0.0330 110,000.00 3,630.00
Mandor OH 0.0330 100,000.00 3,300.00
JUMLAH TENAGA KERJA 79,530.00
B BAHAN
Kayu Klas III M3 0.0300 1,935,000.00 58,050.00
Paku Biasa 2"-5" Kg 0.4000 17,000.00 6,800.00
Minyak Bekisting Kg 0.1500 8,500.00 1,275.00
Balok Kayu Klas II M3 0.0150 2,150,000.00 32,250.00
Plywood Tebal 9 mm Lbr 0.3500 135,000.00 47,250.00
Kayu Dolken 8-10 cm, P=400 cm Batang 2.0000 6,200.00 12,400.00
JUMLAH HARGA BAHAN 158,025.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
24 Analisa 2016
A.4.1.1.31 Membuat 1 M3 balok beton bertulang (200 kg besi + bekisting)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 6.350 65,000.00 412,750.00
Tukang Batu OH 0.275 90,000.00 24,750.00
Tukang Kayu OH 1.650 90,000.00 148,500.00
Tukang Besi OH 1.400 90,000.00 126,000.00
Kepala Tukang OH 0.333 110,000.00 36,630.00
Mandor OH 0.318 100,000.00 31,800.00
JUMLAH TENAGA KERJA 780,430.00
B BAHAN
Kayu Klas III M3 0.3200 1,935,000.00 619,200.00
Paku Biasa 2"-5" Kg 3.2000 17,000.00 54,400.00
Minyak Bekisting Liter 1.6000 8,500.00 13,600.00
Besi Beton Polos Kg 210.0000 12,000.00 2,520,000.00
Kawat Beton Kg 3.0000 19,000.00 57,000.00
Semen Portlant Kg 336.0000 1,440.00 483,840.00
Pasir Beton M3 0.5400 85,000.00 45,900.00
Kerikil M3 0.8100 300,000.00 243,000.00
Kayu kelas II balok M3 0.1400 2,150,000.00 301,000.00
Plywood 9 mm M3 2.8000 135,000.00 378,000.00
Dolken kayu M3 16.0000 6,200.00 99,200.00
JUMLAH HARGA BAHAN 4,036,940.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
25 Analisa 2016
A.4.1.1.33 Membuat 1 M3 dinding beton bertulang (150 kg besi + bekisting)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 5.3000 65,000.00 344,500.00
Tukang Batu OH 0.2750 90,000.00 24,750.00
Tukang Kayu OH 1.3000 90,000.00 117,000.00
Tukang Besi OH 1.0500 90,000.00 94,500.00
Kepala Tukang OH 0.2620 110,000.00 28,820.00
Mandor OH 0.2650 100,000.00 26,500.00
JUMLAH TENAGA KERJA 636,070.00
B BAHAN
Kayu Klas III M3 0.2400 1,935,000.00 464,400.00
Paku Biasa 2"-5" Kg 3.2000 17,000.00 54,400.00
Minyak Bekisting Liter 1.6000 8,500.00 13,600.00
Besi Beton Polos Kg 157.5000 12,000.00 1,890,000.00
Kawat Beton Kg 2.2500 19,000.00 42,750.00
Semen Portlant Kg 336.0000 1,440.00 483,840.00
Pasir Beton M3 0.5400 85,000.00 45,900.00
Kerikil M3 0.8100 300,000.00 243,000.00
Kayu kelas II balok M3 0.1600 2,150,000.00 344,000.00
Plywood 9 mm M3 2.8000 135,000.00 378,000.00
Dolken kayu M3 24.0000 6,200.00 148,800.00
JUMLAH HARGA BAHAN 3,237,890.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
26 Analisa 2016
Membuat 1 M3 Pondasi Tapak Beton Bertulang ( 150 Kg besi + bekisting)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
Beton K 175 M3 1.0000 988,214.15 988,214.15
Pembesian Kg 150.0000 15,495.70 2,324,355.00
Bekisting untuk pondasi M2 5.0000 160,611.00 803,055.00
Harga Satuan Pekerjaan 4,115,624.15
27 Analisa 2016
A.4.2.1.2 Pemasangan 1 Kg Rangka kuda-kuda baja IWF
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0600 65,000.00 3,900.00
Tukang Las Konstruksi OH 0.0600 90,000.00 5,400.00
Kepala Tukang OH 0.0060 110,000.00 660.00
Mandor OH 0.0030 100,000.00 300.00
JUMLAH TENAGA KERJA 10,260.00
B BAHAN
Besi Profil Kg 1.1500 16,500.00 18,975.00
A.4.2.1.4 Pembuatan 1 M2 Pintu besi plat baja tebal 2mm rangkap, rangka baja siku
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.0500 65,000.00 68,250.00
Tukang Las Biasa OH 1.0500 90,000.00 94,500.00
Kepala Tukang OH 0.1050 110,000.00 11,550.00
Mandor OH 0.0520 100,000.00 5,200.00
JUMLAH TENAGA KERJA 179,500.00
B BAHAN
Besi Siku 30.30.3 Kg 15.0000 16,500.00 247,500.00
Besi Plat Baja Kg 32.8000 16,500.00 541,200.00
Kawat Las Kg 0.0500 26,000.00 1,300.00
28 Analisa 2016
A.4.2.1.8 Pemasangan 1 m2 pintu lipat (folding door) bahan plastik/PVC
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.4400 65,000.00 28,600.00
Tukang OH 0.4400 90,000.00 39,600.00
Kepala Tukang OH 0.0440 110,000.00 4,840.00
Mandor OH 0.0220 100,000.00 2,200.00
JUMLAH TENAGA KERJA 75,240.00
B BAHAN
Pintu lipat M2 1.0000 0.00 0.00
JUMLAH HARGA BAHAN 0.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
29 Analisa 2016
A.4.2.1.12 Pemasangan 1 M2 Pintu Alumunium Strip lebar 8 cm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0850 65,000.00 5,525.00
Tukang Khusus Alumunium OH 0.0850 90,000.00 7,650.00
Kepala Tukang OH 0.0085 110,000.00 935.00
Mandor OH 0.0042 100,000.00 420.00
JUMLAH TENAGA KERJA 14,530.00
B BAHAN
Profil Alumunium M 4.4000 77,000.00 338,800.00
Allumunium Strip M 14.6000 7,500.00 109,500.00
JUMLAH HARGA BAHAN 448,300.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
30 Analisa 2016
A.4.2.1.18 Pemasangan 1 M Talang Datar/jurai Seng BJLS 28 lebar 90 cm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.2000 65,000.00 13,000.00
Tukang OH 0.2000 90,000.00 18,000.00
Kepala Tukang OH 0.0200 110,000.00 2,200.00
Mandor OH 0.0010 100,000.00 100.00
JUMLAH TENAGA KERJA 33,300.00
B BAHAN
Seng plat M1 1.0500 43,000.00 45,150.00
Paku Kg 0.0150 21,000.00 315.00
Papan kayu klas II M3 0.0190 2,150,000.00 40,850.00
JUMLAH HARGA BAHAN 86,315.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.2.1.20 Pemasangan 1 M2 Rangka Besi Hollow 1x40.40.2mm, modul 60x120 cm, Dinding Partisi
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.2500 65,000.00 16,250.00
Tukang Besi OH 0.2500 90,000.00 22,500.00
Kepala Tukang OH 0.0250 110,000.00 2,750.00
Mandor OH 0.0130 100,000.00 1,300.00
JUMLAH TENAGA KERJA 42,800.00
B BAHAN
Rangka Metal Hollow 40.40.2mm M1 3.5000 25,833.33 90,416.67
Accessories (perkuatan, las, dll) Ls 10%x Rangka 9,041.67 9,041.67
JUMLAH HARGA BAHAN 99,458.33
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.2.1.21 Pemasangan 1 M2 Rangka Besi Hollow 1x40.40.2mm, Modul 60x60 cm, Plafond
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3500 65,000.00 22,750.00
Tukang Besi OH 0.3500 90,000.00 31,500.00
Kepala Tukang OH 0.0350 110,000.00 3,850.00
Mandor OH 0.0180 100,000.00 1,800.00
JUMLAH TENAGA KERJA 59,900.00
B BAHAN
Rangka Metal Hollow 40.40.2mm M1 4.0000 25,833.33 103,333.33
Accessories (perkuatan, las, dll) Ls 10%x Rangka 10,333.33 10,333.33
JUMLAH HARGA BAHAN 113,666.67
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
31 Analisa 2016
A.4.4.1. PEKERJAAN PASANGAN DINDING
A.4.4.1.7 Pemasangan 1 M2 Dinding bata merah (5x11x22) cm tebal 1/2 batu Campuran 1 SP : 2 PP
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3000 65,000.00 19,500.00
Tukang Batu OH 0.1000 90,000.00 9,000.00
Kepala Tukang OH 0.0100 110,000.00 1,100.00
Mandor OH 0.0150 100,000.00 1,500.00
JUMLAH TENAGA KERJA 31,100.00
B BAHAN
Bata Merah Buah 70.0000 500.00 35,000.00
Semen Portlant Kg 18.9500 1,440.00 27,288.00
Pasir Pasang M3 0.0380 85,000.00 3,230.00
JUMLAH HARGA BAHAN 65,518.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
32 Analisa 2016
A.4.4.1.8 Pemasangan 1 M2 Dinding bata merah (5x11x22) cm tebal 1/2 batu Campuran 1 SP : 3 PP
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3000 65,000.00 19,500.00
Tukang Batu OH 0.1000 90,000.00 9,000.00
Kepala Tukang OH 0.0100 110,000.00 1,100.00
Mandor OH 0.0150 100,000.00 1,500.00
JUMLAH TENAGA KERJA 31,100.00
B BAHAN
Bata Merah Buah 70.0000 500.00 35,000.00
Semen Portlant Kg 14.3700 1,440.00 20,692.80
Pasir Pasang M3 0.0400 85,000.00 3,400.00
JUMLAH HARGA BAHAN 59,092.80
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.4.1.9 Pemasangan 1 M2 Dinding bata merah (5x11x22) cm tebal 1/2 batu Campuran 1 SP : 4 PP
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3000 65,000.00 19,500.00
Tukang Batu OH 0.1000 90,000.00 9,000.00
Kepala Tukang OH 0.0100 110,000.00 1,100.00
Mandor OH 0.0150 100,000.00 1,500.00
JUMLAH TENAGA KERJA 31,100.00
B BAHAN
Bata Merah Buah 70.0000 500.00 35,000.00
Semen Portlant Kg 11.5000 1,440.00 16,560.00
Pasir Pasang M3 0.0430 85,000.00 3,655.00
JUMLAH HARGA BAHAN 55,215.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
D Jumlah (A+B+C)
E Overhead & Profit 10% x D 0.00
F Harga Satuan Pekerjaan (D+E) 0.00
D Jumlah (A+B+C)
E Overhead & Profit 10% x D 0.00
F Harga Satuan Pekerjaan (D+E) 0.00
33 Analisa 2016
A.4.4.1.18 Pemasangan 1 M2 Dinding conblock HB15 campuran 1 SP : 3 PP
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3200 65,000.00 20,800.00
Tukang Batu OH 0.1200 90,000.00 10,800.00
Kepala Tukang OH 0.0120 110,000.00 1,320.00
Mandor OH 0.0160 100,000.00 1,600.00
JUMLAH TENAGA KERJA 34,520.00
B BAHAN
HB-15 Buah 12.5000 0.00 0.00
Semen Portlant Kg 22.7400 1,440.00 32,745.60
Pasir Pasang M3 0.5500 85,000.00 46,750.00
Besi angker diameter 8 Kg 0.2800 0.00 0.00
JUMLAH HARGA BAHAN 79,495.60
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
D Jumlah (A+B+C)
E Overhead & Profit 10% x D 0.00
F Harga Satuan Pekerjaan (D+E) 0.00
D Jumlah (A+B+C)
E Overhead & Profit 10% x D 0.00
F Harga Satuan Pekerjaan (D+E) 0.00
D Jumlah (A+B+C)
E Overhead & Profit 10% x D 0.00
F Harga Satuan Pekerjaan (D+E) 0.00
D Jumlah (A+B+C)
E Overhead & Profit 10% x D 0.00
F Harga Satuan Pekerjaan (D+E) 0.00
34 Analisa 2016
35 Analisa 2016
A.4.4.1.23 Pemasangan 1 M2 Dinding terawang (rooster) 12x11x24 cm Campuran 1 SP : 4 PP
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3000 65,000.00 19,500.00
Tukang Batu OH 0.1000 90,000.00 9,000.00
Kepala Tukang OH 0.0100 110,000.00 1,100.00
Mandor OH 0.0150 100,000.00 1,500.00
JUMLAH TENAGA KERJA 31,100.00
B BAHAN
Bata Berongga Bh 30.0000 0.00 0.00
Semen Portlant Kg 11.0000 1,440.00 15,840.00
Pasir Pasang M3 0.0350 85,000.00 2,975.00
JUMLAH HARGA BAHAN 18,815.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
36 Analisa 2016
A.4.4.2.23 Pemasangan 1 M2 Plesteran ciprat 1 SP : 2 PP
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3000 65,000.00 19,500.00
Tukang Batu OH 0.1000 90,000.00 9,000.00
Kepala Tukang OH 0.0100 110,000.00 1,100.00
Mandor OH 0.0150 100,000.00 1,500.00
JUMLAH TENAGA KERJA 31,100.00
B BAHAN
Semen Portlant Kg 4.320 1,440.00 6,220.80
Pasir Pasang M3 0.006 85,000.00 510.00
JUMLAH HARGA BAHAN 6,730.80
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
37 Analisa 2016
A.4.4.2.27 Pemasangan 1 M2 Acian
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.2000 65,000.00 13,000.00
Tukang Batu OH 0.1000 90,000.00 9,000.00
Kepala Tukang OH 0.0100 110,000.00 1,100.00
Mandor OH 0.0100 100,000.00 1,000.00
JUMLAH TENAGA KERJA 24,100.00
B BAHAN
Semen Portlant Kg 3.2500 1,440.00 4,680.00
JUMLAH HARGA BAHAN 4,680.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
40 Analisa 2016
41 Analisa 2016
A.4.4.3.28 Pemasangan 1 M' Plint ubin teralux marmer ukuran 10x60 cm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0900 65,000.00 5,850.00
Tukang Batu OH 0.0900 90,000.00 8,100.00
Kepala Tukang OH 0.0090 110,000.00 990.00
Mandor OH 0.0050 100,000.00 500.00
JUMLAH TENAGA KERJA 15,440.00
B BAHAN
Plint Ubin Granit Bh 1.7000 #REF! #REF!
Semen Portlant Kg 1.1400 1,440.00 1,641.60
Pasir Pasang M3 0.0030 85,000.00 255.00
Semen Warna Kg 0.1000 2,625.00 262.50
JUMLAH HARGA BAHAN #REF!
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
42 Analisa 2016
43 Analisa 2016
A.4.4.3.35a Pemasangan 1 M2 Lantai keramik ukuran 30x30 cm (polos)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.7000 65,000.00 45,500.00
Tukang Batu OH 0.3500 90,000.00 31,500.00
Kepala Tukang OH 0.0350 110,000.00 3,850.00
Mandor OH 0.0350 100,000.00 3,500.00
JUMLAH TENAGA KERJA 84,350.00
B BAHAN
Ubin Keramik Bh 11.8700 5,727.27 60,429.09
Semen Portlant Kg 10.0000 1,440.00 14,400.00
Pasir Pasang M3 0.0450 85,000.00 3,825.00
Semen Warna Kg 1.5000 2,625.00 3,937.50
JUMLAH HARGA BAHAN 82,591.59
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
44 Analisa 2016
45 Analisa 2016
A.4.4.3.36c Pemasangan 1 M2 Lantai keramik ukuran 40x40 cm (polos)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.7000 65,000.00 45,500.00
Tukang Batu OH 0.3500 90,000.00 31,500.00
Kepala Tukang OH 0.0350 110,000.00 3,850.00
Mandor OH 0.0350 100,000.00 3,500.00
JUMLAH TENAGA KERJA 84,350.00
B BAHAN
Ubin Keramik Bh 6.6300 11,000.00 72,930.00
Semen Portlant Kg 9.8000 1,440.00 14,112.00
Pasir Pasang M3 0.0450 85,000.00 3,825.00
Semen Warna Kg 1.3000 2,625.00 3,412.50
JUMLAH HARGA BAHAN 94,279.50
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
46 Analisa 2016
47 Analisa 2016
A.4.4.3.39.2 Pemasangan 1 M' Plint keramik ukuran 10x40 cm (warna)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0900 65,000.00 5,850.00
Tukang Batu OH 0.0900 90,000.00 8,100.00
Kepala Tukang OH 0.0090 110,000.00 990.00
Mandor OH 0.0050 100,000.00 500.00
JUMLAH TENAGA KERJA 15,440.00
B BAHAN
Plint Ubin Granit Bh 2.6500 2,900.00 7,685.00
Semen Portlant Kg 1.1400 1,440.00 1,641.60
Pasir Pasang M3 0.0030 85,000.00 255.00
Semen Warna Kg 0.0250 2,625.00 65.63
JUMLAH HARGA BAHAN 9,647.23
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
48 Analisa 2016
A.4.4.3.45 Pemasangan 1 M2 underlayer (pelapis bawah karpet)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1200 65,000.00 7,800.00
Tukang Batu OH 0.1200 90,000.00 10,800.00
Kepala Tukang OH 0.0120 110,000.00 1,320.00
Mandor OH 0.0060 100,000.00 600.00
JUMLAH TENAGA KERJA 20,520.00
B BAHAN
Underlayer m2 1.0500 #REF! #REF!
Lem Kg 0.3500 45,000.00 15,750.00
JUMLAH HARGA BAHAN #REF!
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
49 Analisa 2016
A.4.4.3.54b Pemasangan 1 M2 Dinding keramik ukuran 30x30 cm (warna)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.9000 65,000.00 58,500.00
Tukang Batu OH 0.4500 90,000.00 40,500.00
Kepala Tukang OH 0.0450 110,000.00 4,950.00
Mandor OH 0.0450 100,000.00 4,500.00
JUMLAH TENAGA KERJA 108,450.00
B BAHAN
Ubin Keramik Bh 11.8700 6,272.72 66,903.64
Semen Portlant Kg 9.3000 1,440.00 13,392.00
Pasir Pasang M3 0.0180 85,000.00 1,530.00
Semen Warna Kg 1.9400 2,625.00 5,092.50
JUMLAH HARGA BAHAN 86,918.14
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
50 Analisa 2016
51 Analisa 2016
A.4.4.3.61 Pemasangan 1 M2 Floor hardener
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1200 65,000.00 7,800.00
Tukang Batu OH 0.1200 90,000.00 10,800.00
Kepala Tukang OH 0.0120 110,000.00 1,320.00
Mandor OH 0.0060 100,000.00 600.00
JUMLAH TENAGA KERJA 20,520.00
B BAHAN
Floor Hardener Kg 5.0000 0.00
JUMLAH HARGA BAHAN 0.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
D Jumlah (A+B+C)
E Overhead & Profit 10% x D 0.00
F Harga Satuan Pekerjaan (D+E) 0.00
52 Analisa 2016
A.4.5.1.6 Pemasangan 1 M2 langit-langit lambrisering kayu, tebal 9 mm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.8000 65,000.00 52,000.00
Tukang Kayu OH 0.8000 90,000.00 72,000.00
Kepala Tukang OH 0.0800 110,000.00 8,800.00
Mandor OH 0.0400 100,000.00 4,000.00
JUMLAH TENAGA KERJA 136,800.00
B BAHAN
Kayu papan M3 0.0150 2,150,000.00 32,250.00
Paku Tripleks Kg 0.0100 21,000.00 210.00
JUMLAH HARGA BAHAN 32,460.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
53 Analisa 2016
A.4.5.2.32 Pemasangan 1 M2 Genteng Metal
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.2000 65,000.00 13,000.00
Tukang Kayu OH 0.1000 90,000.00 9,000.00
Kepala Tukang OH 0.0100 110,000.00 1,100.00
Mandor OH 0.0010 100,000.00 100.00
JUMLAH TENAGA KERJA 23,200.00
B BAHAN
Genteng Metal M2 1.0200 65,000.00 66,300.00
Paku genteng Kg 0.2000 33,000.00 6,600.00
JUMLAH HARGA BAHAN 72,900.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
54 Analisa 2016
A.4.5.2.37 Pemasangan 1 M' Nok Sirap
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1250 65,000.00 8,125.00
Tukang Kayu OH 0.2500 90,000.00 22,500.00
Kepala Tukang OH 0.0250 110,000.00 2,750.00
Mandor OH 0.0060 100,000.00 600.00
JUMLAH TENAGA KERJA 33,975.00
B BAHAN
Seng plat 3 x 6" Lbr 0.4000 43,000.00 17,200.00
Paku 1/2-1" Kg 0.0500 21,000.00 1,050.00
Paku biasa Kg 0.0500 17,000.00 850.00
JUMLAH HARGA BAHAN 19,100.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
55 Analisa 2016
A.4.5.2.41 Pemasangan 1 M' Nok Aluminium
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1000 65,000.00 6,500.00
Tukang Kayu OH 1.0000 90,000.00 90,000.00
Kepala Tukang OH 0.1000 110,000.00 11,000.00
Mandor OH 0.0500 100,000.00 5,000.00
JUMLAH TENAGA KERJA 112,500.00
B BAHAN
Nok standar 40x18 Bh 1.2000 #REF! #REF!
Paku hak panjang 15 cm Kg 0.0400 #REF! #REF!
JUMLAH HARGA BAHAN #REF!
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.6.1.1 Pembuatan dan pemasangan 1 M3 kusen pintu dan kusen jendela kayu klas I
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 7.0000 65,000.00 455,000.00
Tukang Kayu OH 21.0000 90,000.00 1,890,000.00
Kepala Tukang OH 2.1000 110,000.00 231,000.00
Mandor OH 0.3500 100,000.00 35,000.00
JUMLAH TENAGA KERJA 2,611,000.00
B BAHAN
Balok Kayu M3 1.1000 6,000,000.00 6,600,000.00
Paku 10 cm Kg 1.2500 17,000.00 21,250.00
Lem Kayu Kg 1.0000 27,000.00 27,000.00
JUMLAH HARGA BAHAN 6,648,250.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.6.1.2 Pembuatan dan pemasangan 1 M3 kusen pintu dan kusen jendela kayu klas II
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 6.0000 65,000.00 390,000.00
Tukang Kayu OH 18.0000 90,000.00 1,620,000.00
Kepala Tukang OH 1.8000 110,000.00 198,000.00
Mandor OH 0.3000 100,000.00 30,000.00
JUMLAH TENAGA KERJA 2,238,000.00
B BAHAN
Balok Kayu M3 1.2000 2,150,000.00 2,580,000.00
Paku 10 cm Kg 1.2500 17,000.00 21,250.00
Lem Kayu Kg 1.0000 27,000.00 27,000.00
JUMLAH HARGA BAHAN 2,628,250.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
56 Analisa 2016
A.4.6.1.3 Pembuatan dan pemasangan 1 M2 pintu pintu klamp standar, kayu klas II
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3500 65,000.00 22,750.00
Tukang Kayu OH 1.0500 90,000.00 94,500.00
Kepala Tukang OH 0.1050 110,000.00 11,550.00
Mandor OH 0.0180 100,000.00 1,800.00
JUMLAH TENAGA KERJA 130,600.00
B BAHAN
Papan Kayu kelas II M3 0.0400 2,150,000.00 86,000.00
Paku Kg 0.0500 17,000.00 850.00
JUMLAH HARGA BAHAN 86,850.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.6.1.4 Pembuatan dan pemasangan 1 M2 pintu pintu klamp sederhana, kayu klas III
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3500 65,000.00 22,750.00
Tukang Kayu OH 1.0500 90,000.00 94,500.00
Kepala Tukang OH 0.1050 110,000.00 11,550.00
Mandor OH 0.0180 100,000.00 1,800.00
JUMLAH TENAGA KERJA 130,600.00
B BAHAN
Papan Kayu kelas III M3 0.0400 2,150,000.00 86,000.00
Paku Kg 0.0500 17,000.00 850.00
JUMLAH HARGA BAHAN 86,850.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.6.1.6 Pembuatan dan pemasangan 1 M2 pintu dan jendela kaca, kayu klas II
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.8000 65,000.00 52,000.00
Tukang Kayu OH 2.4000 90,000.00 216,000.00
Kepala Tukang OH 0.2400 110,000.00 26,400.00
Mandor OH 0.0400 100,000.00 4,000.00
JUMLAH TENAGA KERJA 298,400.00
B BAHAN
Papan Kayu kelas II M3 0.0240 2,150,000.00 51,600.00
Lem Kayu Kg 0.3000 27,000.00 8,100.00
JUMLAH HARGA BAHAN 59,700.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
57 Analisa 2016
A.4.6.1.7 Pembuatan dan pemasangan 1 M2 pintu dan jendela Jalusi, kayu klas I
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.0000 65,000.00 65,000.00
Tukang Kayu OH 3.0000 90,000.00 270,000.00
Kepala Tukang OH 0.3000 110,000.00 33,000.00
Mandor OH 0.0500 100,000.00 5,000.00
JUMLAH TENAGA KERJA 373,000.00
B BAHAN
Papan Kayu kelas I M3 0.0640 6,000,000.00 384,000.00
Lem Kayu Kg 0.5000 27,000.00 13,500.00
JUMLAH HARGA BAHAN 397,500.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.6.1.7a Pembuatan dan pemasangan 1 M2 pintu dan jendela Jalusi, kayu klas II
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.0000 65,000.00 65,000.00
Tukang Kayu OH 3.0000 90,000.00 270,000.00
Kepala Tukang OH 0.3000 110,000.00 33,000.00
Mandor OH 0.0500 100,000.00 5,000.00
JUMLAH TENAGA KERJA 373,000.00
B BAHAN
Papan Kayu kelas II M3 0.0640 2,150,000.00 137,600.00
Lem Kayu Kg 0.5000 27,000.00 13,500.00
JUMLAH HARGA BAHAN 151,100.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.6.1.8 Pembuatan 1 M2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90 cm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.7000 65,000.00 45,500.00
Tukang Kayu OH 2.1000 90,000.00 189,000.00
Kepala Tukang OH 0.2100 110,000.00 23,100.00
Mandor OH 0.0350 100,000.00 3,500.00
JUMLAH TENAGA KERJA 261,100.00
B BAHAN
Papan Kayu kelas II M3 0.0250 2,150,000.00 53,750.00
Paku halus Kg 0.0300 21,000.00 630.00
Lem Kayu Kg 0.5000 27,000.00 13,500.00
Plywood tebal 4 mm Lbr 1.0000 72,000.00 72,000.00
JUMLAH HARGA BAHAN 139,880.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
58 Analisa 2016
A.4.6.1.10 Pemasangan 1 M2 Jalusi kusen, kayu klas I
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.6700 65,000.00 43,550.00
Tukang Kayu OH 2.0000 90,000.00 180,000.00
Kepala Tukang OH 0.2000 110,000.00 22,000.00
Mandor OH 0.3350 100,000.00 33,500.00
JUMLAH TENAGA KERJA 279,050.00
B BAHAN
Papan Kayu kelas I M3 0.0600 6,000,000.00 360,000.00
Lem Kayu Kg 0.1500 27,000.00 4,050.00
JUMLAH HARGA BAHAN 364,050.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.6.1.12 Pemasangan 1 M2 teakwood rangkap lapis formika, rangka expose kayu kelas II
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.8500 65,000.00 55,250.00
Tukang Kayu OH 2.5500 90,000.00 229,500.00
Kepala Tukang OH 0.2550 110,000.00 28,050.00
Mandor OH 0.0430 100,000.00 4,300.00
JUMLAH TENAGA KERJA 317,100.00
B BAHAN
Papan Kayu kelas II M3 0.0250 2,150,000.00 53,750.00
Paku halus Kg 0.0300 21,000.00 630.00
Lem Kayu Kg 0.8000 27,000.00 21,600.00
Teakwood tebal 4 mm Lbr 1.0000 110,000.00 110,000.00
Formika Lbr 0.5000 142,000.00 71,000.00
JUMLAH HARGA BAHAN 256,980.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
59 Analisa 2016
A.4.6.1.13 Pemasangan 1 M3 Konstruksi kuda-kuda konvensional, kayu klas II bentang 6 m
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 4.0000 65,000.00 260,000.00
Tukang Kayu OH 12.0000 90,000.00 1,080,000.00
Kepala Tukang OH 1.2000 110,000.00 132,000.00
Mandor OH 0.2000 100,000.00 20,000.00
JUMLAH TENAGA KERJA 1,492,000.00
B BAHAN
Balok Kayu M3 1.1000 2,150,000.00 2,365,000.00
Besi Strip tebal 5mm Kg 15.0000 13,000.00 195,000.00
Paku 12 cm Kg 5.6000 17,000.00 95,200.00
JUMLAH HARGA BAHAN 2,655,200.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
60 Analisa 2016
A.4.6.1.18 Pemasangan 1 M2 rangka atap sirap, kayu klas II
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1200 65,000.00 7,800.00
Tukang Kayu OH 0.1200 90,000.00 10,800.00
Kepala Tukang OH 0.0120 110,000.00 1,320.00
Mandor OH 0.0060 100,000.00 600.00
JUMLAH TENAGA KERJA 20,520.00
B BAHAN
Kayu kelas II M3 0.0140 2,150,000.00 30,100.00
Paku biasa Kg 0.0570 17,000.00 969.00
JUMLAH HARGA BAHAN 31,069.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
61 Analisa 2016
A.4.6.1.21a Pemasangan 1 M' Lisplank ukuran (2x20) cm, kayu klas I
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1000 65,000.00 6,500.00
Tukang Kayu OH 0.2000 90,000.00 18,000.00
Kepala Tukang OH 0.0200 110,000.00 2,200.00
Mandor OH 0.0050 100,000.00 500.00
JUMLAH TENAGA KERJA 27,200.00
B BAHAN
Papan kayu M3 0.0063 8,000,000.00 50,400.00
Paku biasa Kg 0.0500 17,000.00 850.00
JUMLAH HARGA BAHAN 51,250.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
62 Analisa 2016
A.4.6.1.23 Pemasangan 1 M2 Dinding pemisah (60 x 120) cm kayu klas II
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1500 65,000.00 9,750.00
Tukang Kayu OH 0.4500 90,000.00 40,500.00
Kepala Tukang OH 0.0450 110,000.00 4,950.00
Mandor OH 0.0080 100,000.00 800.00
JUMLAH TENAGA KERJA 56,000.00
B BAHAN
Balok Kayu M3 0.0280 2,150,000.00 60,200.00
Paku 5-10 cm Kg 0.1500 17,000.00 2,550.00
JUMLAH HARGA BAHAN 62,750.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
63 Analisa 2016
A.4.6.1.27 Pemasangan 1 M2 Dinding lambrisering dari plywood ukuran (120 x 240) cm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0250 65,000.00 1,625.00
Tukang Kayu OH 0.0750 90,000.00 6,750.00
Kepala Tukang OH 0.0080 110,000.00 880.00
Mandor OH 0.0010 100,000.00 100.00
JUMLAH TENAGA KERJA 9,355.00
B BAHAN
Plywood 4 mm Lbr 0.4000 72,000.00 28,800.00
Paku triplek Kg 0.0500 21,000.00 1,050.00
JUMLAH HARGA BAHAN 29,850.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
1 M3 Pemasangan balok-balok, balok loteng dan konstruksi kuda-kuda sederhana, kayu kelas II (Analisa B
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 8.0000 65,000.00 520,000.00
Tukang Kayu OH 24.0000 90,000.00 2,160,000.00
Kepala Tukang OH 2.4000 110,000.00 264,000.00
Mandor OH 0.4000 100,000.00 40,000.00
JUMLAH TENAGA KERJA 2,984,000.00
B BAHAN
Balok kayu kelas II M3 1.1000 2,150,000.00 2,365,000.00
Paku Kg 5.6000 17,000.00 95,200.00
JUMLAH HARGA BAHAN 2,460,200.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
64 Analisa 2016
1 M3 Pasang Sandaran (loneng), kayu kelas II (Analisa BOW)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 8.0000 65,000.00 520,000.00
Tukang Kayu OH 24.0000 90,000.00 2,160,000.00
Kepala Tukang OH 2.4000 110,000.00 264,000.00
Mandor OH 0.4000 100,000.00 40,000.00
JUMLAH TENAGA KERJA 2,984,000.00
B BAHAN
Balok kayu kelas II M3 1.1000 2,150,000.00 2,365,000.00
Paku Kg 5.6000 17,000.00 95,200.00
JUMLAH HARGA BAHAN 2,460,200.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
1 M2 Pasang dinding/loteng papan disugu kedua belah pihak dengan sambungan lidah (Analisa BOW)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.2800 65,000.00 18,200.00
Tukang Kayu OH 0.8000 90,000.00 72,000.00
Kepala Tukang OH 0.0800 110,000.00 8,800.00
Mandor OH 0.0140 100,000.00 1,400.00
JUMLAH TENAGA KERJA 100,400.00
B BAHAN
Kayu kelas II, papan T=2cm M3 0.0220 2,150,000.00 47,300.00
Paku Kg 0.2000 17,000.00 3,400.00
JUMLAH HARGA BAHAN 50,700.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
65 Analisa 2016
1 M2 Memasang lantai papan kayu kelas II (Analisa BOW)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.2000 65,000.00 13,000.00
Tukang Kayu OH 0.5000 90,000.00 45,000.00
Kepala Tukang OH 0.0500 110,000.00 5,500.00
Mandor OH 0.0100 100,000.00 1,000.00
JUMLAH TENAGA KERJA 64,500.00
B BAHAN
Kayu kelas II, papan T=3cm M3 0.0350 2,150,000.00 75,250.00
Paku Kg 0.2000 17,000.00 3,400.00
JUMLAH HARGA BAHAN 78,650.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
66 Analisa 2016
A.4.6.2.4 pemasangan 1 buah kunci Silinder
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0050 65,000.00 325.00
Tukang Kayu OH 0.5000 90,000.00 45,000.00
Kepala Tukang OH 0.0500 110,000.00 5,500.00
Mandor OH 0.0030 100,000.00 300.00
JUMLAH TENAGA KERJA 51,125.00
B BAHAN
Kunci Silinder Bh 1.0000 65,000.00 65,000.00
JUMLAH HARGA BAHAN 65,000.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
67 Analisa 2016
A.4.6.2.10 pemasangan 1 buah door closer
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0500 65,000.00 3,250.00
Tukang Kayu OH 0.5000 90,000.00 45,000.00
Kepala Tukang OH 0.0500 110,000.00 5,500.00
Mandor OH 0.0030 100,000.00 300.00
JUMLAH TENAGA KERJA 54,050.00
B BAHAN
Door closer Bh 1.0000 160,000.00 160,000.00
JUMLAH HARGA BAHAN 160,000.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
68 Analisa 2016
A.4.6.2.16 Pemasangan 1 M2 kaca 3 mm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0150 65,000.00 975.00
Tukang Kayu OH 0.1500 90,000.00 13,500.00
Kepala Tukang OH 0.0150 110,000.00 1,650.00
Mandor OH 0.0008 100,000.00 80.00
JUMLAH TENAGA KERJA 16,205.00
B BAHAN
Kaca 3 mm M2 1.1000 92,000.00 101,200.00
Sealant Kg 0.0500 20,000.00 1,000.00
JUMLAH HARGA BAHAN 102,200.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
69 Analisa 2016
A.4.6.2.20 Pemasangan 1 M2 Kaca Cermin tebal 5 mm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0150 65,000.00 975.00
Tukang Kayu OH 0.1500 90,000.00 13,500.00
Kepala Tukang OH 0.0150 110,000.00 1,650.00
Mandor OH 0.0008 100,000.00 80.00
JUMLAH TENAGA KERJA 16,205.00
B BAHAN
Kaca cermin 5 mm M2 1.1000 135,000.00 148,500.00
JUMLAH HARGA BAHAN 148,500.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
70 Analisa 2016
A.4.7.1.4 Pengecatan 1 M2 bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0700 65,000.00 4,550.00
Tukang Cat OH 0.0090 90,000.00 810.00
Kepala Tukang OH 0.0060 110,000.00 660.00
Mandor OH 0.0030 100,000.00 300.00
JUMLAH TENAGA KERJA 6,320.00
B BAHAN
Cat Menie Kg 0.2000 36,000.00 7,200.00
Plamuur Kg 0.1500 23,500.00 3,525.00
Cat Dasar Kg 0.1700 34,000.00 5,780.00
Cat Penutup Kg 0.2600 56,500.00 14,690.00
Kuas Bh 0.0100 25,000.00 250.00
Pengencer Kg 0.0300 11,500.00 345.00
Amplas Lbr 0.2000 4,000.00 800.00
JUMLAH HARGA BAHAN 32,590.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.7.1.5 Pengecatan 1 M2 bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat penutup)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0700 65,000.00 4,550.00
Tukang Cat OH 0.1050 90,000.00 9,450.00
Kepala Tukang OH 0.0040 110,000.00 440.00
Mandor OH 0.0030 100,000.00 300.00
JUMLAH TENAGA KERJA 14,740.00
B BAHAN
Cat Menie Kg 0.2000 36,000.00 7,200.00
Plamuur Kg 0.1500 23,500.00 3,525.00
Cat Dasar Kg 0.1700 34,000.00 5,780.00
Cat Penutup Kg 0.3500 56,500.00 19,775.00
Kuas Bh 0.0100 25,000.00 250.00
Pengencer Kg 0.0300 11,500.00 345.00
Amplas Lbr 0.2000 4,000.00 800.00
JUMLAH HARGA BAHAN 37,675.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
71 Analisa 2016
A.4.7.1.8 Pelaburan 1 M2 bidang kayu dengan cat residu atau ter
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1000 65,000.00 6,500.00
Mandor OH 0.0060 100,000.00 600.00
JUMLAH TENAGA KERJA 7,100.00
B BAHAN
Residu atau ter Ltr 0.3500 12,000.00 4,200.00
JUMLAH HARGA BAHAN 4,200.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.7.1.10 Pengecatan 1 M2 Tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0200 65,000.00 1,300.00
Tukang Cat OH 0.0630 90,000.00 5,670.00
Kepala Tukang OH 0.0063 110,000.00 693.00
Mandor OH 0.0030 100,000.00 300.00
JUMLAH TENAGA KERJA 7,963.00
B BAHAN
Plamuur Kg 0.1000 8,500.00 850.00
Cat Dasar Kg 0.1000 18,000.00 1,800.00
Cat Penutup Kg 0.2600 22,500.00 5,850.00
JUMLAH HARGA BAHAN 8,500.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
A.4.7.1.11 Pengecatan 1 M2 Tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0280 65,000.00 1,820.00
Tukang Cat OH 0.0420 90,000.00 3,780.00
Kepala Tukang OH 0.0042 110,000.00 462.00
Mandor OH 0.0030 100,000.00 300.00
JUMLAH TENAGA KERJA 6,362.00
B BAHAN
72 Analisa 2016
A.4.7.1.15 Pemasangan 1 M2 wallpaper
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0200 65,000.00 1,300.00
Tukang Cat OH 0.2000 90,000.00 18,000.00
Kepala Tukang OH 0.0200 110,000.00 2,200.00
Mandor OH 0.0025 100,000.00 250.00
JUMLAH TENAGA KERJA 21,750.00
B BAHAN
Wall papper M2 0.1200 #REF! #REF!
Lem Kg 0.2000 27,000.00 5,400.00
JUMLAH HARGA BAHAN #REF!
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
73 Analisa 2016
A.5.1.1.5 Pemasangan 1 buah wastafel
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 1.2000 65,000.00 78,000.00
Tukang Batu OH 1.4500 90,000.00 130,500.00
Kepala Tukang OH 0.1500 110,000.00 16,500.00
Mandor OH 0.0600 100,000.00 6,000.00
JUMLAH TENAGA KERJA 231,000.00
B BAHAN
Wastafel Unit 1.2000 400,000.00 480,000.00
Semen Portlant Kg 6.0000 1,440.00 1,440.00
Pasir Pasang M3 0.0100 85,000.00 85,000.00
Perlengkapan Ls 12%xwastafel 48,000.00 48,000.00
JUMLAH HARGA BAHAN 614,440.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
74 Analisa 2016
A.5.1.1.14 Pemasangan 1 buah floor drain
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0100 65,000.00 650.00
Tukang Batu OH 0.1000 90,000.00 9,000.00
Kepala Tukang OH 0.0100 110,000.00 1,100.00
Mandor OH 0.0050 100,000.00 500.00
JUMLAH TENAGA KERJA 11,250.00
B BAHAN
Floor Drain Unit 1.0000 16,000.00 16,000.00
JUMLAH HARGA BAHAN 16,000.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
75 Analisa 2016
A.5.1.1.26 Pemasangan 1 M' Pipa PVC tipe AW diameter 3/4"
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0360 65,000.00 2,340.00
Tukang Batu OH 0.0600 90,000.00 5,400.00
Kepala Tukang OH 0.0060 110,000.00 660.00
Mandor OH 0.0020 100,000.00 200.00
JUMLAH TENAGA KERJA 8,600.00
B BAHAN
Pipa PVC 3/4" M 1.2000 7,000.00 8,400.00
Perlengkapan Ls 35%xPVC 1/2" 2,940.00 2,940.00
JUMLAH HARGA BAHAN 11,340.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
76 Analisa 2016
A.5.1.1.32 Pemasangan 1 M' Pipa PVC tipe AW diameter 4"
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0810 65,000.00 5,265.00
Tukang Batu OH 0.1350 90,000.00 12,150.00
Kepala Tukang OH 0.0135 110,000.00 1,485.00
Mandor OH 0.0040 100,000.00 400.00
JUMLAH TENAGA KERJA 19,300.00
B BAHAN
Pipa PVC 4" M 1.2000 67,500.00 81,000.00
Perlengkapan Ls 35%xPVC 4" 28,350.00 28,350.00
JUMLAH HARGA BAHAN 109,350.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
77 Analisa 2016
A.5.1.1.36a Pemasangan 1 M' Pipa beton diameter 40 cm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.3800 65,000.00 24,700.00
Tukang Batu OH 0.1900 90,000.00 17,100.00
Kepala Tukang OH 0.0190 110,000.00 2,090.00
Mandor OH 0.0190 100,000.00 1,900.00
JUMLAH TENAGA KERJA 45,790.00
B BAHAN
Pipa beton/gorong-gorong Bh 1.1000 166,000.00 182,600.00
Bata merah M3 0.5500 0.00
Semen portland Kg 10.3000 1,440.00 14,832.00
Pasir pasang M3 0.0610 85,000.00 5,185.00
Pasir urug M3 0.0690 75,000.00 5,175.00
JUMLAH HARGA BAHAN 207,792.00
C PERALATAN
0.00
JUMLAH HARGA ALAT 0.00
78 Analisa 2016
A.8.4.1 HARGA SATUAN PEKERJAAN PEMASANGAN PIPA
79 Analisa 2016
A.8.4.1.5 Pemasangan 1 M' Pipa PVC 200 mm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.1890 65,000.00 12,285.00
Tukang Pipa OH 0.0950 90,000.00 8,550.00
Mandor OH 0.0190 100,000.00 1,900.00
JUMLAH TENAGA KERJA 22,735.00
B BAHAN
Pipa PVC 200 mm M' 1.0000 333,333.33 333,333.33
JUMLAH HARGA BAHAN 333,333.33
C PERALATAN
Sewa tripot/trakel & handle crane 2 T Hari 0.0240 20,000.00 480.00
JUMLAH HARGA ALAT 480.00
80 Analisa 2016
A.8.4.1.37 Pemasangan 1 M' Pipa GIP 200 mm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.7960 65,000.00 51,740.00
Tukang Pipa OH 0.3980 90,000.00 35,820.00
Mandor OH 0.0800 100,000.00 8,000.00
JUMLAH TENAGA KERJA 95,560.00
B BAHAN
Pipa GIP 200 mm M' 1.0000 112,500.00 112,500.00
JUMLAH HARGA BAHAN 112,500.00
C PERALATAN
Sewa tripot/trakel & handle crane 2 T 0.00
JUMLAH HARGA ALAT 0.00
81 Analisa 2016
A.8.4.5.4 Pengetesan 1 M' Pipa 150 mm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0080 65,000.00 520.00
Mandor OH 0.0008 100,000.00 80.00
JUMLAH TENAGA KERJA 600.00
B BAHAN
Air Test (air bersih) M3 0.0180 50,000.00 900.00
Bahan bakar Ltr 0.0600 10,500.00 630.00
Oli Ltr 0.0020 33,500.00 67.00
JUMLAH HARGA BAHAN 900.00
C PERALATAN
0.00
JUMLAH HARGA ALAT
Pekerjaan Pemboran Pilot Hole dari 2" s/d 4" panjang 0-50 M
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Geolistrik OH 3.0000 110,000.00 330,000.00
Bor Master OH 3.0000 90,000.00 270,000.00
Driller OH 3.0000 65,000.00 195,000.00
Mekanik OH 3.0000 65,000.00 195,000.00
Welder OH 3.0000 65,000.00 195,000.00
Crow OH 6.0000 65,000.00 390,000.00
JUMLAH TENAGA KERJA 1,575,000.00
B BAHAN
Oli Ltr 3.0000 33,500.00 100,500.00
Solar Ltr 630.0000 10,500.00 6,615,000.00
Pertamax Ltr 30.0000 10,500.00 315,000.00
Crease Kg 1.5000 22,500.00 33,750.00
Lumpur Kg 15.0000 540.00 8,100.00
JUMLAH HARGA BAHAN 100,500.00
C PERALATAN
Depresiasi mesin bor Hari 3.0000 108,000.00
Depresiasi pompa air Hari 3.0000 76,000.00 228,000.00
JUMLAH HARGA ALAT
Pekerjaan Pemboran Pilot Hole dari 2" s/d 4" panjang 50-80 M
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Geolistrik OH 4.0000 110,000.00 440,000.00
Bor Master OH 4.0000 90,000.00 360,000.00
Driller OH 4.0000 65,000.00 260,000.00
Mekanik OH 4.0000 65,000.00 260,000.00
Welder OH 4.0000 65,000.00 260,000.00
Crow OH 8.0000 65,000.00 520,000.00
JUMLAH TENAGA KERJA 2,100,000.00
B BAHAN
Solar Ltr 480.0000 10,500.00 5,040,000.00
Pertamax Ltr 60.0000 10,500.00 630,000.00
Lumpur Kg 20.0000 540.00 10,800.00
JUMLAH HARGA BAHAN 5,680,800.00
C PERALATAN
Depresiasi mesin bor Hari 4.000 108,000.00 432,000.00
Depresiasi pompa air Hari 4.000 76,000.00 304,000.00
JUMLAH HARGA ALAT 736,000.00
82 Analisa 2016
83 Analisa 2016
Pekerjaan Pembesaran Lubang Bor 4" s/d 6" panjang 0-50 M
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Geolistrik OH 2.0000 110,000.00 220,000.00
Bor Master OH 2.0000 90,000.00 180,000.00
Driller OH 2.0000 65,000.00 130,000.00
Mekanik OH 2.0000 65,000.00 130,000.00
Welder OH 2.0000 65,000.00 130,000.00
Crow OH 4.0000 65,000.00 260,000.00
JUMLAH TENAGA KERJA 1,050,000.00
B BAHAN
Oli Ltr 3.0000 33,500.00 100,500.00
Solar Ltr 240.0000 10,500.00 2,520,000.00
Pertamax Ltr 30.0000 10,500.00 315,000.00
Crease Kg 1.5000 22,500.00 33,750.00
Lumpur Kg 15.0000 540.00 8,100.00
JUMLAH HARGA BAHAN 2,977,350.00
C PERALATAN
Depresiasi mesin bor Hari 2.0000 108,000.00 216,000.00
Depresiasi pompa air Hari 2.0000 76,000.00 152,000.00
JUMLAH HARGA ALAT 368,000.00
84 Analisa 2016
Pekerjaan Samplink Weld Head dan Groting Semen/Unit Sumur
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Bor Master OH 1.0000 90,000.00 90,000.00
Mekanik OH 1.0000 65,000.00 65,000.00
Welder OH 1.0000 65,000.00 65,000.00
Crow OH 3.0000 65,000.00 195,000.00
JUMLAH TENAGA KERJA 415,000.00
B BAHAN
Solar Ltr 60.0000 10,500.00 630,000.00
Pasir M3 2.0000 85,000.00 170,000.00
Weld head Unit 1.0000 63,000.00 63,000.00
Samplink Unit 1.0000 59,000.00 59,000.00
Semen Kg 250.0000 1,440.00 360,000.00
JUMLAH HARGA BAHAN 1,282,000.00
C PERALATAN
85 Analisa 2016
1 M2 Pekerjaan Aspal Goreng Tebal 4 cm
No. Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja OH 0.0217 65,000.00 1,410.50
Mandor OH 0.0022 100,000.00 220.00
JUMLAH TENAGA KERJA 1,630.50
B BAHAN
Aspal Kg 5.5000 12,000.00 66,000.00
Kerikil M3 0.0300 300,000.00 9,000.00
Pasir beton M3 0.0475 85,000.00 4,037.50
Minyak tanah Ltr 0.4900 10,300.00 5,047.00
Kayu bakar M3 0.0800 175,000.00 14,000.00
JUMLAH HARGA BAHAN 98,084.50
C PERALATAN
Truk Jam 0.0100 175,000.00 1,750.00
Mesin Gilas (4-6 ton ) Jam 0.0144 190,000.00 2,736.00
Alat bantu Ls 1.0000 3,500.00 3,500.00
JUMLAH HARGA ALAT 7,986.00
86 Analisa 2016
Pasir 1,400
Kerikil 1,350
tap metal