Old Construction Method New Construction Method

Timber Framing Steel Framing

With wood framing, dimensional Steel components are precisely


lumber is cut to fit at the job site sized during production at an off-
Timber framing construction is a site factory, meaning less work is
method of building with heavy required on the construction site.
timbers rather than dimensional There is greater flexibility with
lumber such as 2x4s. the design process as opposed to
Traditional timber framing is the platform frames, as steel allows
method of creating structures for greater spacing in between
using heavy squared-off and vertical studs, larger open spans,
carefully fitted and joined and other design elements that
timbers with joints secured by require more structural strength
large wooden pegs. than dimensional lumber can
The method comes from making provide.
things out of logs and tree trunks The beams and columns
without modern high tech saws produced are very strong, but
to cut lumber from the starting also very thick; this type of steel
material stock. is most often used to construct
Using axes, adzes, and draw commercial buildings, but these
knives, hand-powered auger drill beams are also used sparingly in
bits (brace and bit), and high-end residential projects that
laborious woodworking, artisans have large spans requiring the
or farmers could gradually added strength of steel I-
assemble a building capable of beams.
bearing heavy weight without Steel-framed homes are built in a
excessive use of interior space similar way to platform-framed
given over to vertical support wood homes individual steel
posts. beams are assembled on-site,
piece by piece, to form the
skeleton structure of the building.
Old Construction Method New Construction Method
Masonry Wall System Curtain Wall System

These are walls made of brick or A curtain wall is defined as thin,


cement blocks held together with usually aluminum-framed wall,
cement mortar and are often containing in-fills of glass, metal
plastered with cement plaster on panels, or thin stone.
both surfaces. The framing is attached to the
Masonry walls are heavy, and building structure and does not
require lots of skilled labour, carry the floor or roof loads of the
which means that they are falling building.
out of favor in most countries in A curtain wall system is an outer
which labour is expensive. Their covering of a building in which
weight is also a problem in high- the outer walls are non-
rise buildings. structural, but merely keep the
Masonry walls cannot be weather out and the occupants
constructed to an unlimited in.
height - broadly speaking, most A curtain wall is designed to
are considered stable only to a resist air and water infiltration,
height of 10-15 ft (3 - 4m). sway induced by wind and
One problem with masonry walls seismic forces acting on the
is that they rely mainly on their building, and its own dead load
weight to keep them in place; weight forces
each block or brick is only loosely Curtain walls differ from store-
connected to the next via a thin front systems in that they are
layer of mortar. designed to span multiple floors,
They do not perform well in and take into consideration
earthquakes, when entire design requirements such as:
buildings are shaken horizontally. thermal expansion and
Many collapses during contraction; building sway and
earthquakes occur in buildings movement; water diversion; and
that have load-bearing masonry thermal efficiency for cost-
walls. effective heating, cooling, and
lighting in the building.

Old Construction Method New Construction Method


Cast-in-situ Construction Precast Construction

In Cast-In-Situ Construction In Precast Construction elements


elements are manufactured on are manufactured in a controlled
site and hence it is difficult to casting environment and have it
control mix, placement and is easier to control mix,
curing. placement and curing.
Quality control and maintenance Quality can be controlled and
is difficult. maintained easily.
More labours are required and Less labours are required and
more skilled labours are required. less skilled labours are required.
Construction is slow as gaining of Precast construction is quick as it
strength requires time. can be installed immediately and
Increase in strength at situ by there is no waiting for it to gain
accelerated curing is a difficult strength.
task. Increase in strength can be
Elements are cast in open achieved by accelerated curing.
environment. Elements can be cast in
On site strength test is required. controlled condition.
On site strength test is not
required.