Professional Documents
Culture Documents
Shamsul Idris
March, 2008
Course Title: Geo-Information Science and Earth Observation
for Environmental Modelling and Management
by
Shamsul Idris
Thesis submitted to the International Institute for Geo-information Science and Earth
Observation in partial fulfilment of the requirements for the degree of Master of
Science in Geo-information Science and Earth Observation for Environmental
Modelling and Management
Bus Rapid Transit has emerged as an economically beneficial mass rapid transit with
significant potential in developing cities. Many other cities in Asia announced plans
for introducing BRT corridors following popular beliefs that it can reduce
congestion, benefit of ridership, improve air quality and demonstrates relatively low
capital cost per mile of investment. Despite the current BRT development, the
performance and potential impacts of BRT system have hardly been researched. The
main motivation of this research is to examine the potential impact of a BRT
corridor on air quality and as well as to car traffic.
This research examined the impact from physical design of BRT on a highway
corridor. BRTs exclusive lane greatly reduces the available road space for
remaining mixed lane. This impact on car traffic can be modelled where limited road
space reduces mobility. When travelling time increases, certain percentage of
vehicle traffic will disappear when road space is no longer available (Goodwin et al
1998). The potential reduction of traffic can reach as high as 40%. While reduction
of Carbon Monoxide can reach an average of 31%. This research concluded that
BRT system can help improve modal split, alleviate congestion and bring added
value to the environment.
i
Acknowledgements
Firstly I would like to thanks the European Union Erasmus Mundus scholarship
programme. Under this programme I have experienced the wonderful academic lives
In University of Southampton, Lund University, University of Warsaw and ITC, and
different cultures in these four countries.
I am grateful to my first supervisor; Dr. Ir. Luc Boerboom and second supervisor;
Dr. Sherif Amer. Both of them guided me through my thesis and spend valuable
time sharing their scientific thinking.
I would like to thank all GEM classmates which we spend almost eighteen months
together leaving me with joyful memories.
ii
Table of contents
Abstract
Acknowledgement
Table of content
List of figures
List of tables
1. Introduction........................................................................................................ 1
1.1. Urbanization and Mobility....................................................................... 1
1.2. Statement of the Problems....................................................................... 4
1.3. Objectives and Sub-objectives................................................................. 7
1.4. Research Questions ................................................................................. 7
1.5. Research Method ..................................................................................... 8
1.5.1. GIS Analysis....................................................................................... 9
1.5.2. Car Traffic Modeling .......................................................................... 9
1.5.3. Emission Mapping ............................................................................ 11
1.6. Thesis Structure ..................................................................................... 12
2. Literature Review ............................................................................................ 13
2.1. Introduction ........................................................................................... 13
2.2. Traditional Four-Step Transportation Models ....................................... 13
2.3. Geographical Information System......................................................... 15
2.4. Bus Rapid Transit .................................................................................. 16
2.5. Transport Related Emission................................................................... 19
3. Study Area Description.................................................................................... 21
3.1. Introduction ........................................................................................... 21
3.2. Location and description of Klang Valley............................................. 21
3.3. Population and Urbanization ................................................................. 22
3.4. Public Transportation System in Klang Valley ..................................... 24
4. Materials and Methods..................................................................................... 26
4.1. Materials................................................................................................ 26
4.1.1. Data Collection ................................................................................. 26
4.1.2. Secondary Sources............................................................................ 26
4.2. Methodology ......................................................................................... 28
4.3. Transportation Modeling ....................................................................... 28
4.4. Emission Mapping................................................................................. 35
5. Analysis and Results ........................................................................................ 37
5.1. Introduction ........................................................................................... 37
5.2. GIS Analysis.......................................................................................... 37
5.2.1. Identifying Suitable BRT Corridor ................................................... 39
iii
5.2.2. Accessibility Analysis ...................................................................... 45
5.3. Car Traffic Modeling............................................................................. 47
5.3.1. Validation of Car Traffic Volume..................................................... 47
5.3.2. Projection from Car Traffic Modeling .............................................. 49
5.3.3. Projection of Car Traffic on BRT corridor ....................................... 51
5.4. Possible Impact of Bus Rapid Transit ................................................... 52
5.4.1. Introduction ...................................................................................... 52
5.4.2. Possible Impact to Car Traffic .......................................................... 52
5.4.3. Possible Impact to Vehicle Emission................................................ 55
5.4.4. Air Pollution Map Generated from Car Traffic in 2010 ................... 55
5.4.5. Benefit and Cost Analysis of BRT System....................................... 58
6. Conclusion ....................................................................................................... 61
6.1. Limitation of Study................................................................................ 61
6.1.1. Sensitivity Analysis .......................................................................... 61
6.1.2. Data Preparation for Traffic Modeling ............................................. 61
6.2. Conclusion............................................................................................. 61
iv
List of figures
v
Figure 5-17 Result from Reduction of Carbon Monoxide Emission with BRT
System ...................................................................................................................... 57
Figure 5-18 Benefit Cost Ratio of Corridor Segment ............................................... 60
vi
List of tables
Table 1-1 Change in Modal Composition in Klang Valley between 1985 and 1997 . 5
Table 2-1 Capital Cost for Different Mass Rapid Transit Systems .......................... 18
Table 3-1 Population and Forecast for year 2005 to 2010 ('000).............................. 23
Table 4-1 Carbon Monoxide Load Factor for Petrol Car.......................................... 35
Table 5-1 Result of Car Trips from OD Matrix for year 2010 ................................. 41
Table 5-2 Summary of Accessibility Analysis ......................................................... 47
Table 5-3 Statistical Relationship between Observed and Modeled Car Traffic
Volume for year 2005............................................................................................... 48
Table 5-4 Car Traffic Volume from Selected Count Station .................................... 53
Table 5-5 Potential CO Emission Saving on BRT Corridor..................................... 55
Table 5-6 Benefit Analysis of Corridor Length........................................................ 58
Table 5-7 Cost Analysis of Corridor Length ............................................................ 59
vii
1. Introduction
Bus Rapid Transit has emerged as an economically beneficial mass rapid transit with
significant potential in developing cities. Indonesia is running its own busway called
TransJakarta BRT. Bangkok is expected to open five BRT routes by September
2008 and Delhi government has granted approval for six new BRT corridors for
operation by December 2009. Many other cities in Asia announced plans for
introducing BRT corridors following popular beliefs that it can reduce congestion,
benefit of ridership, improve air quality and demonstrates relatively low capital cost
per mile of investment (Federal Transit Administration 2004; Institute for
Transportation & Development Policy 2007). Despite the current BRT development,
the performance and potential impacts of BRT system have hardly been researched.
The main motivation of this research is to examine the potential impact of a BRT
corridor on air quality and as well as to car traffic.
General Introduction
The twentieth century has witnessed the rapid urbanisation of the worlds
population. The United Nations estimates that by 2025, more than half of the
developing world population will be living in cities. In the most developed region of
the world, urbanisation is well advanced where almost three quarters of the
population lived in urban settlements in 2005 (United Nations 2005). Remarkably in
most developing countries, car ownership rates grow faster than population or
income. In developing countries in Asia, this is becoming major problem and is
expected to become more serious as these cities are among the largest and most
populated area in the region. Higher income has led to increased vehicle ownership
and rising consumption of transport goods, and fast construction of new
infrastructure which in turn encouraged generation of additional vehicular traffic.
In developing countries, the increasing use of the car seems to attach to the
psychological views of the car as symbol of freedom, status and power and
these belief is stressing the traffic condition in the city (Vasconcellos 1997). It is a
common viewpoint that people values personal car as fulfilling one of the
deficiency needs. According to Maslow (Maslow 1943), deficiency needs refer to
the desires that the individual does not feel anything if they are met, but feels
anxious if they are not met. One of such deficiency needs is esteem needs, which
1
is met by fulfilling self esteem, confidence, respect from others and achievement in
life. Human psychological views towards having and driving car have prolonged to
aggravate the environmental problem in developing countries especially in Asia
region. Congestion will result in more emission and further degrade the environment
with even more hazardous gases release to the atmosphere.
2
vehicle ownership is primarily dependent on income. World Bank claimed though,
while vehicle ownership is primarily dependent on income, the growth of urban road
space with income is likely to be slower than that of traffic volume with income.
Secondly, population growth rates can as well provide indication on level of
motorization. Rapidly growing cities have above average car ownership rates in
relation to income levels and below average proportions of land space devoted for
traffic movement. Together, these may aggravate congestion in these cities.
Therefore income level and population growth rates can provide explanation of
transport differences between Asian countries.
In fast growing cities, traffic congestion reduces average speed and increases vehicle
emission. The World Bank estimates that by increasing the average speed in city
traffic from 10 kilometers per hour (km/h) to 20 km/h could cut Carbon Monoxide
(CO) emissions by nearly 40 percent (The World Bank 2007). Nevertheless, the
suggestion will result in further congestion by greater car use in the long run.
Instead, the congestion problems need to be solved in way of adaptation of new
technologies or systems that can reduce unit emission rates without generating extra
traffic to negate the benefit. Through proper public transportation planning, the new
system can encourage greater public usage and reduce congestion of private vehicle.
One of the strategies in promoting public mode is to improve efficiency in public
transportation. Efficiency can be defined in many ways but the strategy must be
concerned not only with keeping costs down but also to maximise the number of
beneficiaries. Keeping the cost down will encourage the poor to use public
transportation with confidence and comfort. When adequate public transportation is
not available, usually the rich will continue to use private car while the relatively
poor will shift first to motorcycles, then to taxis, and ultimately to inexpensive cars
as their incomes increase. Taking example from India, the Peoples Car dubbed
Tata Nano will favour mostly the lower income group. In shorter term, the negative
side of affordable mobility will make the congestion on the road even worst.
Therefore, it is important to carefully examine the impact of new transportation
system because failure will hamper transportation strategies and may well bring
severe consequences to traffic congestion, undesirable urban structure, adverse
human and environmental impacts and wasteful use of resources (Beimborn,
Kennedy et al. 1996).
3
1.2. Statement of the Problems
This section identifies urban transportation issues in Klang Valley due to its rapid
development and high population growth. Attributable to the geographical location,
topology, urban planning and development, these issues are obviously peculiar and
specific only to this region, but can be found common to many cities in developing
Asian countries. The three major problems in urban transportation are traffic
congestion, over reliance on private vehicle and declining public modal split. These
problems will be explained in the next section to allow better understanding in the
development of this research.
Problem on transportation network in Klang Valley intensifies when the highway
and road are overburden with private vehicles especially cars and motorcycles. In a
most recent urban transportation study in Klang Valley reported that the traffic
volume at selected screenline locations is in the range of 26,216 to 361,783 number
of vehicles (Perunding Bersatu 2005). This study estimated that in year 2000, the
average number of cars per household is 1.7 cars and nearly 64% of working
populations travel by car. The trend of people relying on cars is currently taking toll
on road networks in Klang Valley. Figure 1-2 shows yearly rise of number of new
private vehicles registered from 1996 until 2006. It is interesting to note that the total
number of private vehicles in 2006 represents nearly 46.8 percent of the total
number of vehicle registered in Malaysia (Ministry of Transport 2007). To this
point, private vehicle ownership has increased more rapidly and this growth has
exceeded the capacity of the current road space. The numbers of private vehicles are
expected to increase with loose regulation on automobile ownership and with no
traffic restraining measure from the transport authority.
Figure 1-2 Private Vehicle Registered in Malaysia
600,000
500,000
Number of Unit
400,000
Motorcycle
300,000
Car
200,000
100,000
0
1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006
Year
4
In the past 20 years, modal composition between private and public trip has been
shifted. The patronage of public transport has declined from 34 per cent in 1985 to
20 per cent in 1997 (in table 1-1). Looking at the declining modal split, policy
makers have resorted to rail based public transportation. Their main goal is to lessen
transportation problems and improve the public to private modal split ratio to 30:70
by year 2020.
Table 1-1 Change in Modal Composition in Klang Valley between 1985 and 1997
Mode 1985 1997
Private Mode: Total Total
Motorcycle 0.190 0.237
Car 0.467 0.657 0.566 0.803
Public Mode:
Stage bus /Mini Bus 0.243 0.079
Factory bus /School Bus 0.100 0.102
Rail 0.000 0.343 0.016 0.197
Modal Split 66 : 34 80 : 20
Source: Perunding Bersatu (2005) and JICA (1999)
The planning and development of transportation in Klang Valley is aiming to
encourage public modal shift from overly dependent on private vehicle. The public
transport authority has taken step to improve the public bus services. In 2004, public
bus service is put under sole operation of Rangkaian Pengangkutan Integrasi Deras
Sendirian Berhad (RapidKL) from previous transport operators. Bus services were
improved with new vehicles, schedules and routes to provide an integrated, efficient
and reliable public transport service for the most part of Klang Valley. According to
transport operator, despite the new services, public acceptance is slow as majority of
the public still prefer to use private vehicle for commuting.
Public transport authorities give more preference to rail as the backbone for public
transport services in the Klang Valley. Public bus services were improved only as
support to the urban rail system. There is no plan or initiative to turn public bus
services into modern and efficient mode of travel. There is new development of
rapid transit in Western Europe, United States, South America and some parts of
Asia. It is called the Bus Rapid Transit or BRT which has emerged as an advanced
and innovative mass rapid transit solution for urban transportation.
5
The BRT is increasingly being accepted as an inventive way of transporting mass
commuters with newer bus technology, separate right-of-way, clean and comfortable
stations, efficient fare collection system and others distinct features (Institute for
Transportation & Development Policy 2007). The system is claimed to deliver fast,
comfortable and cost-effective solutions for urban mobility and it is an ideal solution
for developing cities to ease its congestion problem. It is likely to impact car users in
terms of their motivation to change travel mode and renew people perception
towards public transportation.
Solving urban transportation problems is a complex task and involves a large
number of steps. The use of transportation modeling in this research facilitate
analysis on the potential impact of such system on the environment which in this
case, the air quality. Models are important because transportation plans and
investments are based on projections about future travel pattern. Models are used to
estimate the number of trips that will be made for a given land use and transportation
system at some future year. The general research design (figure 1-3) starts with the
possible impact of BRT routing and accessibility analysis in Geographical
Information System (GIS). After that, car traffic modeling will estimate number of
trips that will be made in study area and the results from car traffic will be quantified
(numbers of car and vehicle emission). Then, the impact of BRT system will be
assessed in term of car traffic emission and benefit to air quality with emission
maps. In every urban transportation study, it is important to justify the cost of new
infrastructure and relate the benefit it can bring to air quality. As a final point, this
research will examine the benefit to cost ratio of BRT corridor to air quality using
earlier analyses.
6
1.3. Objectives and Sub-objectives
The main objective is to model the potential impact of bus rapid transit on air
quality. The impact of the bus system is examined on the impact to car traffic, CO
emission and the benefit of each kilometer to the air quality.
More specific objectives are:
1. To establish mutual impact of BRT routing on planning and accessibility.
2. To examine the possible impact of BRT to traffic on the corridor.
3. To examine the possible impact of BRT to vehicle emission.
4. To relate the benefit and cost of BRT system to environment.
7
1.5. Research Method
The overall methodology of this research is illustrated in Figure 1-4 below. The
research problems are identified through investigation of urban transportation
development in the study area. Then the research problems are evaluated and the key
theories are conceptualized by literature review. Through research problems, the
main objectives together with specific sub-objectives are formulated. Research
objectives guided the development of research questions in this research. The
methodology is developed from both disciplines of GIS and transportation and the
results are merged into emission analysis for study area. The general research design
from figure 1-3 is incorporated into the overall methodology. It is straightforward
and can be replicated for different scenario. The methodologies for GIS Analysis
method (A), Car Traffic Modeling (B) and Emission Mapping (C) will be explained
further in the next section.
Figure 1-4 Overall Research Methodology
8
1.5.1. GIS Analysis
GIS analysis make use spatial data that has been developed by local planning
agency. Primarily three elements from geodatabase are used in the GIS analysis. The
elements are land use, administrative and transportation as shown in figure 1-5. The
output expected from this analysis is results of service area, accessibility and buffer
analysis on the selected BRT corridor. The full analysis will be explained in Chapter
5 of this research.
Figure 1-5 GIS Analysis Methodology
9
Figure 1-6 Transport Modeling Methodology
10
1.5.3. Emission Mapping
Figure 1-7 represents emission mapping methodology progressing from GIS analysis
and car traffic modeling in the two previous sections. The result of Total Car Trips
[D] derived from figure 1-6 will be used as input data to create map of line sources.
CO emission factor is applied from specific vehicle emission database (the
description of the database is explained later in section 4.2.2). Then CO emission is
calculated based on car trips on each link to generate CO emission map.
Subsequently, analysis is made between car emission with and without BRT system
on the corridor.
Figure 1-7 Emission Mapping Methodology
11
1.6. Thesis Structure
Chapter 1 Introduction
Briefly presents the background for the research, identifies research problems,
defines the objectives and questions and shows the general overview how the
research aims to achieve the objectives.
Chapter 6 Conclusion
The last chapter presents the limitations of study and conclusion of this research.
12
2. Literature Review
2.1. Introduction
In this research, proper understanding of urban transportation and GIS are required
to answer research questions. This chapter will give descriptions on important
element on the subject to aid development of this research. Modeling the BRT
system help to establish and examine the potential impact it has on the air quality.
The impact of the bus system is examined on the car traffic, CO emission and the
benefit to the environment.
13
Travel demand model attempts to estimate travel pattern from multitude of
individuals making choices about whether to travel (trip generation), where to travel,
(trip distribution), which mode to use (modal split) and which route to use (trip
assignment). The modeling process begins with generating an estimate of the
amount of trips expected in the urban system usually at the zonal level or traffic
analysis zones (TAZ). Trip generation attempts to predict the number of trip
produced and attracted to each TAZ.
The second sub-model is referred as trip distribution. It determines flows and
allocates the trips generated in origin zones to destinations in the study area and the
travel cost between them. The third sub-model is modal split. Here trips are
apportioned to various modes of transport based on travel cost and preferences.
The four-step modeling process finishes with a trip assignment module that takes
estimated trips that have been generated, distributed, and sorted by mode, and loads
them onto various segments of the transport network. Transport simulation usually
proceeds sequentially amongst these four stages in the order in which they are
described above. The output from each step served as an input to the next step of the
process. However in reality, travel decisions are rarely taken in this sequence but
rather depends on the form of utility function assumed to governed travel choices
(Mark 2007).
Traditional urban transport modeling requires an extensive range of data, most of it
is related to traffic zones, transportation network, trip factors and socio economic
interaction. Data availability is an important factor when considering the trade-off
between fulfilling the data requirement and the benefit it may offer (Henscher,
Button et al. 2004). Data available for this research is considered valuable to achieve
the main objective and answer the research questions. Among the major types of
variables for data used in this research are discussed by Rodrigue et al. (2006) and
have been divided into five categories:
Zoning design- Spatial land use map is useful to represent distinctive land use
pattern such as residential, industrial, agriculture and etc. In principle land use
information will facilitate generation of a smaller zone called TAZ. These zones
usually have homogeneous activities and should conform to census, collective areas
(postal code) or physical boundary where possible.
Transportation network- It is a representation of the structure and geometry of
transportation network mainly composed of links, nodes, turns and junctions.
Transport network are fundamental element in providing accessibility and
movements along with origin-destination matrices.
14
Trip generation factors- These factors estimate the number of trips, people, freight,
that each level of economic activity generates. Usually trip maker consider element
of income, mode preference and consumption level for making their journey. Most
of the information is gathered using survey or inferred from observation.
Employment and workplaces- They account for significant inducement effect over
transportation modeling since employment is consider as exogenous factor for trip
generation and attraction. Travelling is a direct outcome of the number of jobs from
workplaces in zones.
Population and housing- They act as generator of trip as people and household
account for the origin of trips making. There are diverse ranges of income, standard
of living, housing condition, individual preference that will have effect on trip
generation process.
The model is employed in this research because it is commonly known method and
widely accepted in urban transport planning. Furthermore, the modeling software
used the basic principles from the traditional four step model.
Accessibility
Accessibility is a key element to transport geography since it describes the mobility
of either people or goods. Rodrigue et al. (2006) defined accessibility as the
measure of capacity of a location to be reached by or to reach different locations.
Since accessibility is dominantly the outcome of transportation activities, it usually
presents the most significant influence of transportation on location. In ArcGIS
Network Analyst, accessibility can be measured in term of travel time, distance or
any other impedance on the network (ESRI 2006). The structure of transportation
network and capacity are the key elements in determination of accessibility.
Planning the location of future BRT station is crucial to ensure suitability of
locations and optimum operational capacity can be achieved. Accessibility measure
can be used to determine percentage of population which are within specific travel
range and coverage for a potential BRT station. Accessibility analysis can be
15
achieved using Service Area function. Service Area computed by Network Analyst
can identify the accessible streets within certain distance using network features.
Service area can also locate what is alongside the accessible streets for example
nearest bus stop, hospital or supermarket.
Figure 2-2 Examples of Buffered Line, Points and Multiple Rings Buffer
16
Figure 2-3 The Characteristics of Different Tyre-Based Public Transportation
17
Figure 2-4 Bus Rapid Transit in Bogota, Colombia
Table 2-1 Capital Cost for Different Mass Rapid Transit Systems
City Type of System Length Cost per km
(km) (US$ million/km)
Kuala Lumpur (PUTRA) Light Rail Transit 29.0 50.0
Bangkok (BTS) Light Rail Transit 23.7 72.5
Los Angeles Light Rail Transit 23.0 37.8
Kuala Lumpur Monorail Monorail 8.6 38.1
Bangkok MRTA Metro rail 20.0 142.9
Shanghai Metro Metro rail 87.2 62.0
Caracas (Line 4) Metro rail 12.0 90.3
Tunisia Tram 30.0 13.3
San Diego Rail Trolley 75.0 17.2
Porto Alegre Bus rapid transit 27.0 1.0
18
Curitiba Bus rapid transit 57.0 2.5
Bogota (Phase 1) Bus rapid transit 40.0 5.3
19
impairment, reduced work capability and poor learning ability are among the health
effects associated with high exposure to CO.
Figure 2-5 shows that passenger cars are the major contributor of CO in Klang
Valley. While vans and lorries contributed 35.37%, motorcycles 15.34%, buses
2.04% and taxis 1.90% (Department of Environment Malaysia 2007 (a)).
40.00% 35.37%
Percentage
30.00%
20.00% 15.34%
10.00%
2.04% 1.90%
0.00%
Cars Van & Lorries M/cycles Buses Taxis
Type
20
3. Study Area Description
3.1. Introduction
Malaysia is a federation of thirteen states and three federal territories in Southeast
Asia with a total landmass of 329,749 square km. The capital city is Kuala Lumpur
while Putrajaya is the seat of the federal government. The country is separated into
two regions the Malay Peninsula and Borneo by the South China Sea. Countries near
to Malaysias borders are Thailand, Indonesia, Singapore and Brunei. Located near
the equator, the weather is characterized by tropical climate.
Since its independence, Malaysia's economic record has been exceptional. Real
gross domestic product (GDP) grew by an average of 6.5% per year from 1957 to
2005 (Economic Planning Unit 2006). The economy experienced sustained rapid
growth averaging almost 8% annually. Malaysia today is a middle-income country
with a multi-sector economy based on services and manufacturing. At present,
Malaysia is one of the largest exporters of semiconductor devices, electrical goods,
and information and communication technology products.
21
Figure 3-2 Administrative Boundaries in Klang Valley
The population in this area was more than 4.5 millions in 2000, with 1.3 million
concentrated in Kuala Lumpur, followed by Petaling (1.1 million), Hulu Langat
(0.86 million), Klang (0.64 million) and Gombak (0.54 million) (Department of
Statistic Malaysia 2007). Area in central part of Klang Valley is growing rapidly.
Basically, this is the main commercial and administrative centres. About 20 percent
of the nations population live within Klang Valley in year 2000 and the number are
expected to grow with rapid expansion of residential and industrial especially in
district of Petaling and Klang.
22
Table 3-1 show the population statistic in from 1980 to 2000. The forecasted
population number was adapted from the related urban transportation study. From
the total population in the Klang Valley of about 5.5 million forecasted in 2010,
Kuala Lumpur would account for 27%, Petaling 26%, Hulu Langat 18%, Klang 16%
and Gombak 13%.
Table 3-1 Population and Forecast for year 2005 to 2010 ('000)
AAGR
District 1980* 1991* 2000* 2005 2007 2010
(%)
Kuala
978.3 1,262.1 1,305.8 1,396 1,435 1,493 1.5
Lumpur
Gombak 176.1 373.5 537.5 651 677 716 2.2
Hulu
189.0 438.5 864.5 908 939 987 1.9
Langat
Petaling 385.5 670.6 1,184.1 1,333 1,390 1,476 2.4
Klang 298.3 430.6 643.4 780 829 902 3.7
Total 2,027.2 3,175.3 4,535.4 5,068 5,270 5,573 2.2
Source: * Department of Statistic and Annual Average Growth Rate (AAGR) is for
2000-2020 (Perunding Bersatu, 2005)
Districts of Petaling and Kuala Lumpur are the most populated region in Klang
Valley and both districts are projected to reach 3 millions inhabitants by 2010. The
population and employment largely concentrated in district of Petaling where more
people prefer to live and work (Perunding Bersatu 2005).
23
Urban population sprawl can be seen from Figure 3-3 where urban sprawl initially
originated from Kuala Lumpur, Petaling, Subang Jaya, Klang and Selayang, These
areas have expanded into new conurbation as far as 10 km from 1988 until 1999.
The most rapid urban expansion can be seen in district of Petaling, Kuala Lumpur
and Klang.
24
Despite these modern systems, public transport usage in Kuala Lumpur continued to
drop. A study by JICA (1999) found that only 16% of all trips in Kuala Lumpur
were taken using public transport, one of the lowest among cities in the Asian
region. This may due to various reasons, including the increase in car ownership and
preference for road development, lack of connectivity between the various rail-based
services, and poor bus service.
Surveys from previous urban transportation studies are considered significant for
this research. The result (in figure 3-4) shows that there is a huge gap between their
current commuting time and expected commuting time when using public transport
mode. The graph shows both car and motorcycle users stated preference for using
public transport mode in accordance with the degree of time saving expected from
public modes. Only a 50 percent time saving will effectively persuade them to
become a regular public transport user.
Figure 3-4 Stated Preference to using public modes in accordance with time
saving
25
4. Materials and Methods
4.1. Materials
26
4.1.2.2. Klang Valley Integrated Public Transport System and Land Use
Development Plan (2005)
Another urban transportation study was undertaken by Perunding Bersatu. This
study involved a number of expertise involving land use planners, transport
planners, socio economist, GIS experts and academicians from ITC. The main
objectives of this study are to propose new public transport corridors with
considerations to land use and traffic demand management, to propose transit zones
and public transport facilities and to propose an integrated public transport system
for the next 20 years (target year 2020). The main proposal from this study is a rail
based integrated public transport masterplan for Klang Valley. The stakeholder
prefers the development of rail based network as inter and intra city travel in Klang
Valley. Hence this study is developed on a regional transport system based on the
rail network.
Important information referred from this study is the stated preference and spatial
data. The stated preference survey was conducted on selected sample of household
that use private transport to travel. The survey results were on type of improvement
that would likely induce them to shift to public mode. Meanwhile, the spatial data is
prepared by one of planning agency in Ministry of Federal Territory. It is stored in
personal Geodatabase format. The geodatabase was built using ARC/Info and
ARCview consisting data on population, socio economic information, land use and
transportation network. The geodatabase was fully utilised throughout this research
for analysis and results part.
27
4.2. Methodology
This research is designed to model the potential impact of BRT on air quality.
Modeling the impact on environment will require analysis in both GIS and
transportation to get reliable result on air pollution estimate. Methodologies have
been developed for each analysis to relate output from these two processes into
emission mapping. As a case study, to model BRT system, situation at Klang Valley,
Malaysia has been considered. Earlier urban transportation studies in Klang Valley
have provided greater understanding of transportation problems and description of
transportation characteristic in this region. Furthermore, the availability of spatial
data had influenced methodologies used in this study. The main objective is to
model car traffic flow for Klang Valley and model the impact on air pollution with
introduction of BRT system. The result of number of private car on each link was
used to generate emission map (in ArcGIS) based on Carbon Monoxide emission
load factor per gram per vehicle per kilometer travel. This part will be explained
further in emission mapping methodology. The application of GIS analyses in this
research is to establish the mutual impact of BRT corridor on planning and
accessibility of the mass transit system. The application of GIS will be explained in
Chapter 5: Result and Analysis.
28
modeling process except for Mode Split since for this study the major effect of
BRT on a corridor will be on car traffic loads on major links of the transportation
network. This research attempts to answer research questions related to the effect
only from private car. All processes and formulas were adapted from OmniTRANS
Reference Manual.
Figure 4-1 Traditional Four-Step Model
29
Useful features in this software is the capability of importing and exporting data
with other planning packages such as Tranplan, TRIPS, Integration, Metanet and
ArcView. The spatial data in shapefiles were imported into the OmniTRANS.
Though, it was required to specify a mapping of the objects and their attributes into
the OmniTRANS database structure by creating a script. A script is a small text file
with specific commands for the software to perform. Predefined scripts are available
and can be edited to suit different modeling requirements. For this purpose, ArcView
script was created and executed to import the links, centroids and TAZs. The
networks were projected using Cartesian Projection system with automatic scaling.
There are only two projection systems supported i.e. Cartesian and Universal
Transverse Mercator (UTM). The author attempted to change the projection system
and spheroid to UTM with Everest (Malaysia 1969) though failed because the
project has no longitude/latitude values. OmniTRANS does not allow the use of
different projection system. After importing, the author noticed that OmniTRANS
automatically creates centroid connectors which link all zone centroids to road
network. That is each centroid connector is connected to link that is located outside
the zones. All the centroid connectors were deleted and new centroids connectors
were created to link centroid to the nearest link in individual zone. Another
important thing to mention is that the road networks are set to left hand rule of the
road as the oncoming traffic in Malaysia is seen coming on the right side. This is set
in network preference setting in OmniTRANS.
The networks structure imported were checked for connectivity. It was done by
using the Path Engine function which basically builds on the screen the shortest
path between any two nodes/zone centroids. This function is useful for testing
networks structure and link connectivity. It also allows user to display paths through
a certain centroid or node, or display several paths starting from the same centroid. If
the same node or centroid is clicked twice, a shortest path tree will be drawn from
this node or centroid to all (other) centroids.
Trip Generation
Prior to performing analysis, we first need to know data of population, information
on socio-economic, trips behaviour, employment activities and some of the variables
and attributes of the transport network in the Klang Valley. Relevant data will be
forecasted for 2005, 2007 and 2010 using future growth rate. Socio economic data
inside GIS shapefile such as resident, work population, household and student were
exported into spreadsheet. Annual Average Growth Rate (AAGR) for 2000-2020
(from Table 3-1) was applied to population according to individual rate. This is to
reflect different growth rate for particular district. Household size of Klang Valley is
30
about 4.5 persons per household. While number of student is calculated based on
estimation that 18.3% is school going population between 5-14 years old. AAGR,
household size and student percentage was adapted from study by Perunding Bersatu
(2005). Working population is forecasted based on 1.9% of AAGR from total
employment sector forecasted in Ninth Malaysian Plan (EPU, 2006). The output is
zonal data for 241 TAZs consisting data of resident, work population, household and
student for 2005, 2007 and 2010 for Klang Valley.
Then, zonal data were used to estimate trip generation. It is the total number of trips
generated or attracted to each zone of the study area. Trip generation was calculated
in worksheet using parameter of different purpose of trip to arrive at total number of
production and generation to and from each zone. The parameters used for different
trip purpose were adapted from JICA (1999) study (refer Appendix 1-A). The
parameters are different for each purpose of trip production and attraction. The Trip
Generation Model is calculated outside OmniTRANS using spreadsheet and later
copied into Combination Trip Ends matrix. The matrix stored all trips with
production and attraction computed for each zones for trip distribution modeling.
Trip Distribution
The next step is to allocate these trips to particular destination so a trip matrix can be
produced. This process is called trip distribution. Before any trip distribution can be
undertaken, the software needs to calculate impedances between all zones and
determine the shortest path between all centroids. Skims matrices are usually
calculated based on distance and travel time. For this purpose, another script was
prepared and executed to calculate impedances based on distance and travel time and
store the results in separate matrices.
Using the trip productions, trip attractions and the impedances between zones, trips
were distributed between each origin and destination zone. The gravity model is
used to perform trip distribution. It is one of the most important spatial interaction
methods.
The doubly constraint gravity model will be applied to perform the trip distribution:
Tij = ai bj Pi Aj Fij ...............................................................................................(1)
where
Tij = number of trips from zones i to zone j,
ai , b j = scaling factors,
Pi = production of zone i,
31
Aj = attraction of zone j,
Fij = accessibility of j from i.
The accessibility Fij are in turn computed using a distribution function:
Fij =1.5exp(-0.05cij)(2)
in which the accessibilities depend on the impedances cij (e.g. distance or travel
time) between zones i and j; the larger the impedance, the lower the accessibility.
This function is called Exponential Distribution function. Finally the doubly
constraint gravity model requires that both predicted outflows from origin and
destinations to match observed totals, which in this case trip totals are balanced
towards productions. Trip distribution is executed by executing script using the
productions, attractions, a skim matrix and Exponential Distribution function. The
resulting origin-destination matrix is stored in matrix cube of 241 x 241 zones.
Trip Assignment
The last stage in classical model requires the assignment of the trips by each mode to
their corresponding networks. Traffic assignment basically performs the route choice
on the network for all trips between each origin and destination pair. Trips are
loaded onto the network using Volume Averaging methods. In Volume Averaging
assignment, volumes are assigned to a network in an iterative process. Volume is
calculated as a linear combination of the volume found in the previous iteration and
the volume added by means of an all-or-nothing assignment performed in the current
iteration. This process terminates when the maximum number of 10 iterations has
been reached. The author set the maximum iterations at 10 in order to save time for
computation on trip assignment.
The capacity-restrained assignment methods can be extended in OmniTRANS by
taking into account link delays. Based on a capacity restrained traffic assignment,
the link flows are influenced by existing travel times and respective link capacity.
OmniTRANS performed this assignment using an iterative process by which trips
are loaded onto the network. At the same time, the link travel times are adjusted
according to the assignment volume and capacity. The relationship between volume
of traffic and resulting travel time is explained with a Travel Time Function. The
objective of applying capacity effect is to achieve a network wide balance or
equilibrium between link flows and travel time together taking into consideration the
network capacity.
Travel Time Function (figure 4-2) defines the relationship between the volume of
traffic on a link and the resulting travel time. As general rule, travel time increases
32
as traffic builds up. Link capacity is seen as contributing factor. If a link is almost
full to capacity, travel time will increase more rapidly than in a situation where there
is sufficient link capacity left. The BPR function is developed by the American
Bureau of Public Roads and incorporated into OmniTRANS. It defines the
relationship with the following equation:
T = T0 ( 1 + (V/Q))..(3)
where:
T = travel time
V = volume
Q = capacity
T0 = free-flow travel time
and = function parameters
In short, T0 represents a base travel time which is then factored to give a new travel
time for a given link. If =0.5, delays will occur only if the link is close to
approaching full capacity (main highways). If =2.0 significant delays will occur
well before full capacity is reached (residential roads). The parameter is usually
equal to 4.0. In this modeling, each link type was set to different function
parameters (Highway; = 2.0, Primary Distributor; = 1.0, District Distributor and
Minor Road; = 1.5 and Local Distributor; = 2.0).
33
assignment showed routes that all trips were assigned and the numbers of cars on
each link. With trip assignment and the use of previous step, we can obtain realistic
estimates on effects of BRT system to the selected corridor. Technically, the BRT
will have a separate runway on a three lanes road. This will drastically reduce the
available lane for mixed traffic and as well the road capacity. The Travel Time
Function will be applied to examine the possible effect of BRT to car users in
respect of capacity restraint and travelling time. This methodology will examine the
effect to private transport users on the selected corridor and adjoining road network
in a 24 hours traffic demand modeling.
34
4.4. Emission Mapping
One of the sub-objectives of this research is to examine the extent of Carbon
Monoxide (CO) emission from car traffic. CO is the result of incomplete fuel
combustion and source of vehicle pollutant. Carbon Monoxide is largely emitted by
passenger cars which accounted for 45.35% from the total emission from mobile
sources in Malaysia (Department of Environment Malaysia 2007 (b)). At present,
there is lack of emission testing facilities for mobile sources in Malaysia.
Experimental set up (consisting of a chassis dynamometer unit) for determination of
emission factors is expensive and only available at PROTON factory. PROTON is
the national car manufacturer in Malaysia. Engineers have tested emissions factors
of Carbon Monoxide, Hydrocarbon and Nitrogen Oxides using PROTONs car
under standard driving cycles (University Malaya Consultancy Unit 2003).
Nevertheless, the emission load factor recorded does not represent emission from
various car manufacturer and different road conditions. The author discovered a
comprehensive emission load database prepared by the Netherlands Organisation for
Applied Scientific Research with 12,000 emission testing on various road
conditions, vehicle types and age (Statistics Netherland 2007). The database should
provide accurate CO emission load factor for this research.
The methodology in emission mapping requires estimation from line sources.
Emissions from line sources are the results of vehicles travelling on road. The
process of producing emission map in this research was accomplished by generating
rasterized maps of line sources and CO emission load factor. Then the CO emission
load factors from the database are used to estimate emission from car traffic on
different road. Car emission from model year 2000 was selected as load factor for
calculating emission because Malaysia is currently adapting Euro 2 technology since
year 2000 (University Malaya Consultancy Unit 2003; Asian Development Bank
2006). The CO emission load factor for petrol car is illustrated in table 4-1 with car
model year and emission for three road conditions.
Table 4-1 Carbon Monoxide Load Factor for Petrol Car
built-up rural motor
Model year
areas roads ways
2000 2.986618 1.021474 1.366294
Measurement in gram/vehicle kilometre
Source: from Netherlands Organisation for Applied Scientific Research
35
In general, methodology to quantify vehicle emissions progresses from vehicle
activity to mobile sources emission. New methodology for estimating emission
advances with improvement of dispersion model (Gaussion based) and interpolation
(ordinary and universal Kriging) probabilistic map of pollution concentration
(Potoglou and Kanaroglou 2005). However this research is limited to emission
mapping developed from traffic model and rasterized map. Both method of pollution
mapping are not considered in this research because of limited data and time factor.
36
5. Analysis and Results
5.1. Introduction
This chapter presents the research outputs, the impact of BRT on air quality in Klang
Valley, Malaysia. In this research, the base year selected is 2007. The BRT system is
modelled for year 2010 because in general, a BRT project can be planned within a
period of 12 to 18 months (Institute for Transportation & Development Policy
2007). Here the results are presented with major steps in the analysis processes. The
next section shows how GIS and car traffic modeling was utilised to achieve the
objective and sub-objectives of this research. As mentioned earlier, the application
of GIS analysis is to establish the mutual impact of BRT on planning and
accessibility of the mass transit. The elements in analysis will include planning of
BRT corridor and evaluation of accessibility for BRT systems.
The second section of analysis involves car traffic modeling for Klang Valley.
Prediction of car traffic was made using OmniTRANS in year 2005, 2007, 2010.
The prediction for year 2005 is used to validate between actual with modelled car
traffic volume on selected traffic station. Since BRT is modelled for 2010, the author
created two scenarios; (1) without BRT system and (2) with BRT system. The aim is
to examine the possible impact of BRT corridor to car traffic. Third part of analysis
involves examination of potential impact of vehicle emission between scenarios 1
and 2. Both scenarios will be evaluated with generation of Carbon Monoxide
emission maps to assimilate the impact of car traffic with vehicle emission on the
road networks. Finally this chapter concludes with the analysis of Benefit and Cost
to justify the cost of BRT system with the benefit to air quality.
37
only as good as the data put into the GIS in the first place. In geodatabase, topology
is the arrangement that defines how point, line, and polygon features share
coincident geometry (de By, Georgiadou et al. 2004). Topology validation involves
defining and enforcing data integrity rules for example; there should be no gaps
between polygons, line must be larger than cluster tolerance or other different rules
of topology validation. Topology deals with spatial properties that do not change
under certain transformation (ESRI 2006). For this reason, topology for road
network was validated so that they do not overlap in the network. GIS software used
throughout this study is ArcGIS 9.2 developed by ESRI, Redland, California.
The author found out that the planning agency validated the topology of major road
network by attaching rules whereby feature class must not be larger than cluster
tolerance of 0.001535 meters and do not overlap (BKWPPLK 2004). The author
found no explanation on specific cluster tolerance in related publication. According
to ArcGIS documentation, users can use cluster tolerance that is ten times the x,y
resolution and expect very good results (ESRI 2006). However, users are advised to
keep the movement small by means of keeping the x,y tolerance small. If an x,y
tolerance is too small (such as 2 times x,y resolution or less), it may not properly
integrate the line work of coincident boundaries. The author verified that the
Geodatabase has x,y tolerance of 0.000256 meter and x,y resolution of 0.000128
meter. The default value is based on the x,y tolerance of the feature dataset and
cannot be changed to smaller value. Meanwhile, details of projections and
coordinate systems of each feature classes were verified that they have the same
projection and coordinate system (refer Appendix 1-B) throughout the GIS analysis.
In this research, spatial data was acquired from established, authoritative and reputed
sources. Therefore in the author opinion, it is sufficient to accept and use the
Geodatabase for this research.
Data Preparation
Shapefiles related to transportation network were processed before being attached to
network dataset. Attributes field such as link type, speed and time (second) were
added into shapefile. Type of road was established based on field road hierarchy.
Each link was group into five classes and given specific link code. (Highway = 2,
Primary Distributor = 11, District Distributor = 21, Local Distributor = 1 and Minor
Road = 23). This coding will be used later in car traffic modeling. Speed was set at
maximum speed limit fixed by Ministry of Work, Malaysia. In general, speed limits
for each road type are: Highway = 110 km/hour, Primary Distributor = 90 km/hour,
District Distributor = 80 km/hour, Local Distributor = 60 km/hour and Minor Road
= 50 km/hour. Travel time was calculated by dividing length in km with speed limit
38
and multiplied with 3600 to get measurement in second. Later, a network dataset
was built for the whole road network in ArcCatalog.
39
The result of suitable BRT corridor was overlaid with population density. The result
showed that corridors are located near main conurbation area which can serve larger
number of beneficiaries. It is also apparent that population densities are larger near
these major arterial road. Area with high population concentration was identified to
be located in district of Petaling and Klang and both are predicted to have significant
increase in population size in year 2020 (Perunding Bersatu, 2005). Urban planners
reported that district of Petaling has the second highest employment concentration in
Klang Valley and the highest percentage of total commercial floor space and
distribution of industrial areas. Both district of Petaling and Klang are connected by
one major arterial road which serve medium to long distance trip between the capital
city. Based on these considerations, the author selected Federal Highway as suitable
corridor for BRT system in the study area. The next section extends discussion for
the selected BRT corridor.
40
Figure 5-2 Annual Total Traffic Volume from Selected Station from 1996-2005
1200000
1000000
TRAFFIC VOLUME
800000 BR101
BR807
600000
BR806
400000 BR805
200000
0
1996 1997 1998 1999 2000 2001 2002 2003 2004 2005
YEAR
Table 5-1 Result of Car Trips from OD Matrix for year 2010
The trips between each OD pair from districts of Klang, Petaling and Kuala Lumpur
can be visualized on maps as illustrated in figure 5-3. It can be generalized that trips
between the three districts converged on the selected BRT corridor which
emphasizes the importance of the highway to car users. The highway runs parallel
along major cities such as Petaling Jaya, Subang Jaya and Shah Alam and these
areas are expected to experience stable population and economic growth in the
future (Perunding Bersatu 2005).
41
Figure 5-3 Origin and Destination Car Trips for district of Klang, Petaling and
Kuala Lumpur in 2010
Klang District
Petaling District
(include major city of
Shah Alam, Subang
Jaya and Petaling Jaya)
42
The classification of land use within five kilometer buffer from the corridor was
performed to identify major land use classes and to locate residential, commercial
and industrial areas along the BRT corridor. Figure 5-4 shows the land use
classification based on land use map from 1999. The author selected five kilometer
distance as buffer distance because the author made an assumption that individual
living or working within that distance will be benefited from a BRT system in the
study area.
The distribution of land use in figure 5-5 shows percentage of different land use
classes. Transportation planning is directly linked to land use pattern. Residential
areas accounted for 41% from total land use classification and considered to be an
important element to determine population forecast and household activities for the
future. The latest land use map was not available from the planning agency.
7%
7%
RESIDENTIAL
9%
41% AGRICULTURE
INDUSTRY
OTHERS
INSTITUTIONAL
10%
RECREATIONAL
COMMERCIAL
13%
13%
43
Planning of BRT Stations on Federal Highway
Development of BRT Stations on Federal Highway needs to ensure that the systems
being developed are made as successful as possible. The aim of planning public
transportation system is to maximise the number of beneficiaries. In previous thesis
on urban planning, Kabir (2004) sited several locations suitable for transit zone in
Klang Valley. This research employed spatial multicriteria evaluation for transit
zone location in Klang Valley. The result of his research is illustrated in figure 5-6.
From his research, the rectangle box on the map represents Scenario 2 which
represents sites that are already urbanized and would attract good number of
ridership. The author believed that BRT station should correspond to suitable
location for transit zones developed by Kabir. Therefore, the author selected five
sites as potential station for BRT system based on earlier suitability analysis. The
sites selected for BRT station are Klang, Shah Alam, Subang Jaya, Petaling Jaya and
Kuala Lumpur.
Figure 5-6 Collection of Suitable Sites for Transit Zone in Klang Valley
44
5.2.2. Accessibility Analysis
The next process is to examine the impact of accessibility to resident living near to a
BRT system. Accessibility refers to how easy it is for individual to go to a site. The
accessibility is measure by finding accessible street within certain distance to a BRT
station. The authors assumption is that people will be able to access the station
within five kilometer either using public or private transportation. In ArcGIS
Network Analyst, accessibility can be measured in terms of travel time or distance
on the network. Evaluating accessibility help answer question such as spatial
coverage of people living within certain distance from a BRT station. It is also to
determine how suitable a site is for mode integration and for maximising ridership.
A simple way is to do a buffer around a point to determine spatial coverage of
accessibility. However this does not reflect the actual accessibility to the site.
Network Analyst allows us to find service areas around any location on a network. A
network service area is a region that includes all accessible streets that are within
specific impedance. In figure 5-7, Service Area calculation has identified accessible
street that can be reached within five kilometer from BRT station. Multiple rings
buffer shows that impedance increases in 1000 meter with each band from the
potential BRT station.
Figure 5-7 Accessibility of Service Area within five kilometer from BRT Station
45
Result from previous analysis will be used to select bus stop that are within five
kilometer from Service Area. The author assumed that on average, local bus service
will be serving accessible street within five kilometer of a BRT station. These bus
stops were selected using SQL query. Proximity to bus stop was used to measure
population coverage within walking distance to and from bus stop in areas covered
by bus services. In figure 5-8, walking distance is calculated by applying buffer from
each selected bus stop.
In a reasonably well served urban area, passenger should be able to catch a bus
within 500 meter of their home or work place. Distance in excess of 500 meter may
be acceptable in low density areas but the maximum walking distance should not
exceed one kilometer. The walking distances were according to distance
recommended by The World Bank (1987). Currently, local bus services are provided
by RapidKL (public transport operator) to travel around local neighbourhood and get
to the nearest rail station or bus hubs. It is assumed that individuals will be able to
take local buses from any of the selected bus stops to get to the BRT station.
Table 5-2 shows summary of accessibility measured from individual bus stop.
According to this analysis, the accessibility to bus stops changes with impedance
where 74.1% of the populations were able to catch a bus within 500 meters from
their residence and 25.9% are located in distance of 1000 meter. The buffer distance
analysis uses Euclidean distance and assumes that all populations have equal
walking distance and ignoring physical objects and footpaths to reach the bus stop.
46
Hence, it was accepted that majority of population will be able to get local bus
within accessible street in five kilometer to the BRT station.
47
In regression, the R2 coefficient of determination is a statistical measure that will
give some information about the goodness of fit of a model. It measures relationship
between two variables. Based on table 5-3, the correlation coefficients between
modelled and actual volumes are good and considered to be significant for
predicting future car traffic volume. Conclusively, the modelled car traffic volumes
on 15 stations are assumed to be representative values of the selected links.
However, variables in figure 5-10 are not normally distributed. An obvious
relationship between the two variables can be observed but it is not linear. The
deviation could be attributed to differences in actual traffic count which was
conducted in 16 hours period and car traffic in 24 hours modeling. It is possible to
perform 16 hours car traffic modeling but it would take longer time for
OmniTRANS to calculate result for each hour. Therefore, the author was satisfied
with the correlation coefficient between observed and modelled car traffic and
incorporated results from car traffic modeling (24 hours) into further analysis.
Table 5-3 Statistical Relationship between Observed and Modeled Car Traffic
Volume for year 2005
Statistical relationship Observed Modelled
Maximum 305,287 235,653
Minimum 19,209 42,525
Standard Deviation 82,099 61,876
R2 0.8233
R correlation coefficient 0.9073
Figure 5-10 Observed and Modeled Traffic Volume on Selected Traffic Station
250000
Modeled Traffic Volume
200000
150000
100000
50000
0
0 100000 200000 300000 400000
Observed Traffic Volume
48
5.3.2. Projection from Car Traffic Modeling
Car trips were generated into OD Matrix which stores the number of trip between
each OD pair. Car Traffic modeling in Klang Valley predicted that 3,923,916 car
trips will be generated in 2005, 4,079,176 in 2007 and 4,312,059 in 2010. The
numbers of trips has increased by 3.8% (2007) and 5.4% (2010). Figure 5-11 is
produced by taking the number of car from selected traffic station in different years.
Generally all traffic stations foreseen growth in car traffic volume near to the BRT
corridor. There are a few stations with little reduction of car traffic and considered to
be small. It can be concluded that car traffic volume increased with population and
increased mobility which linked to social and economic activities in study area. In
this research, the effect of inflation and price is not considered.
350,000
300,000
Car Traffic Volume
250,000
2005
200,000
2007
150,000
2010
100,000
50,000
-
B 1
02
BR 5
6
BR 9
1
B 3
04
BR 5
6
07
W 3
W 5
6
10
10
10
10
10
0
11
80
80
80
80
81
R1
R1
R8
R8
BR
BR
BR
BR
BR
BR
R
B
Traffic Station
49
Figure 5-12 Result of Car Traffic in 2010 for Klang Valley
50
5.3.3. Projection of Car Traffic on BRT corridor
Figure 5-13 represents the car traffic on BRT corridor. The analysis shows the
development of car traffic on the highway from 2005 until 2010. The growth of car
trips will continues if no policy or traffic demand management is introduced. It is
concluded that traffic volume on BRT corridor continues to rise steadily until 2010.
51
5.4. Possible Impact of Bus Rapid Transit
5.4.1. Introduction
This section examined the possible impact of BRT to car traffic and emission. The
author will examine the impact of BRT to car traffic volume on the corridor and
later look at the amount of Carbon Monoxide emission from car traffic.
52
restricted. This phenomenon is also known as traffic evaporation which occurs due
to car user balancing travel time against the available options. In shorter term, car
users will choose different route to avoid the limited road space which is easily
congested on the BRT corridor.
350,000
300,000
Car Traffic Volume
250,000
200,000 No BRT
150,000 With BRT
100,000
50,000
-
BR 1
B 2
BR 5
B 6
BR 9
B 1
BR 2
B 3
B 4
BR 5
B 6
BR 7
W 3
W 5
6
10
10
0
10
0
10
0
11
0
80
0
80
0
81
R1
R1
R1
R8
R8
R8
R8
R
B
In table 5-4, the most significant reduction of car traffic is recorded at three traffic
station. The reduction in number of car ranges from 23% to 40%. The large
reduction compared to other 12 stations may be attributed to their location near to
main traffic convergence and close distance to Central Business District.
Conclusively, these traffic stations are located on the main arterial road which leads
directly into the city.
Figure 5-15 shows the impact of BRT system to car traffic on the corridor. The top
image shows the severity of car traffic on the highway without a BRT system. While
bottom image shows that BRT can reduce traffic volume up to 40% on BRT
53
corridor. This is directly contributed to exclusive lane segregated for BRT system.
Image on the top identify bottleneck on the highway. This bottleneck usually located
at the junction where the traffic from access road convergences with main highway.
54
5.4.3. Possible Impact to Vehicle Emission
Another sub-objective of this research is to estimate the extent of emissions of
Carbon Monoxide (CO) pollutants from car traffic on the BRT corridor. This is done
by applying emission factors (gram of CO emitted per vehicle per kilometer travel)
on every link. In this analysis, map of CO emission is produced to examine the
impact of BRT system to vehicle emission on the corridor. The possible impact to
vehicle emission is calculated for BRT corridor as shown in table 5-5. An average
reduction of 30.5% can be expected on CO emission from car traffic.
55
Figure 5-16 Emission Map of Carbon Monoxide on Road Network
56
Figure 5-17 Result from Reduction of Carbon Monoxide Emission with BRT
System
Figure 5-17 shows emission map showing net change between scenario 1 and 2. It
can be concluded that major reduction can be observed on the BRT corridor where
net reduction (darker red) of CO emission is higher. However there is also net
increase of CO emission on other links as car user using alternative route to avoid
BRT corridor. This can be seen on link with light yellow colour on the map. This
can be attributed to car users who choose different route to avoid the BRT corridor.
57
5.4.5. Benefit and Cost Analysis of BRT System
In many instances, it is possible to monetarize the factor. This will allow a cost
benefit analysis to be conducted across many different factors. Factor such as CO
emission savings can be calculated from change in car traffic emission between the
two scenarios and apportioned to cost of BRT system per segment. In general, the
benefit will tend to decrease as distance from the city centre increases. At certain
point, the benefit will diminish and become insufficient to justify the benefit over
investment of BRT system in the study area. Since the demand for BRT is not
known, this research will quantify benefit from CO emission saved from the
reduction of the pollutant. Final analysis will justify the benefit per segment of BRT
based on CO emission savings over capital cost of the system.
58
5.4.5.2. Cost for BRT System
Capital Cost for BRT system is calculated using BRT Infrastructure Cost
Calculator from ITDP which based on cost data from existing BRT systems and
input from BRT expert. The cost calculator gives initial estimation of infrastructure
costs. Actual costing will depend on local conditions and situations. However, the
author believes that it is useful for cost analysis in this research. Using the cost
calculator, the capital cost for 31.43 kilometer BRT corridor will cost about
42,424,863 (USD$61,619,800) with 5 stations. Major costs include busway
reconfiguration, stations construction, electronic ticketing system, Intelligent
Transportation System and other related cost. However it does not include cost for
BRT vehicle. Cost per kilometer of BRT system is calculated at 1,353,541
(USD$1,965,945). The exchange rate of USD$1.00 = 0.69 (as at 11 February
2008). Table 5-7 shows the cost analysis based on corridor length.
59
The basis in performing benefit cost analysis of corridor segment is by comparing
the emission saved from car traffic on the mixed lane. Once the BRT corridor no
longer brings extra benefit in comparison to the capital cost, then the point has been
reached where exclusive BRT lane no longer produces added value to air quality. In
figure 5-18, the corridor is producing net emission saving from segment A to E.
After segment E, the benefit to cost ratio falls below a value of 0.1, meaning that the
costs of extending the BRT line outweigh the emission savings benefit. It can be
concluded that after segment H, the BRT can no longer brings benefit to air quality.
0.20
0.18
0.16
Benefit/Cost Ratio
0.14
0.12
0.10
0.08
0.06
0.04
0.02
0.00
A B C D E F G H
Corridor Segm ent
60
6. Conclusion
6.2. Conclusion
The analyses from previous chapter are presented with important findings:
BRT system with an exclusive lane has resulted in reduction of car traffic on mixed
lane. The reduction of car traffic is 23% to 40% which is considered significant to
discourage the public from using private car for commuting. BRT is an alternative
restraining measure which may discourage car usage and at the same time offers
mobility with better travelling speed. It gives alternative to car users instead of
punitive option. The impact from reduction is greater at locations or junctions where
traffic from access road convergences with main highway
However, further observation revealed that car users are avoiding the selected BRT
corridor because the effect of fewer lanes reduces the road capacity. The effect of
overflow can be seen to the adjacent road network or highway where car users are
predicted to take an alternative route away from road with limited capacity.
61
The corridor selection was based on arterial road which connects the major
conurbation in Klang Valley. The wealthier areas are obviously the location of
higher vehicle ownership. From the standpoint of shifting car users to public
transport, there is greater emission and congestion reduction potential in targeting
car owning households. The selection of corridor is made on arterial road which has
major access to high income residential areas.
BRT system has resulted in reduction on average 31% of CO emission from car
traffic on the on the mixed traffic lane. Benefit cost analysis performed clarified that
each segment of BRT corridor has different added value of benefit. In general the
added value lessens with distance to city centre. The added value can increase if at
certain of point of time, the emission from vehicle increases. The justification of
adding extra of BRT corridor can be re-examined if there is a significant change in
emission saved on the extra corridor length.
Conclusively, a successful public transport service should compete in term of total
travel time, comfort, cost and convenience. This will ensure the viability of policy
measures to shift people into public mode. A high quality public transport system is
the stimulus to encourage car owners to try an alternative. Transport demand
management measures are an effective tool to help further discourage private vehicle
use. Such other measures include congestion charging, parking fees, vehicle
ownership fees and day use restrictions.
BRT may have positive impact to air quality and at the same time reduce traffic on
the corridor, reduce passenger travelling time, reduce CO emission from private car,
induce private car to shift to public transport and change the modal split. Finally, it
should be fully integrated with land use policies in order to ensure the growth of
transit oriented development around BRT stations. The location of shops, services
and residences within walking distance of stations can ensure that as the city grows,
the BRT system will serve the mobility needs of new residents.
62
References
Aronoff, S. (1989). Geographic information systems : a management perspective.
Ottawa, WDL Publications.
Asian Development Bank. (2006, 10 October 2007). "Country Synthesis Report on
Urban Air Quality Management - Malaysia." from
http://www.adb.org/Documents/Reports/Urban-Air-Quality-
Management/malaysia.pdf.
Beimborn, E., R. Kennedy, et al. (1996). Inside the blackbox : making transportation
models work for livable communities. Milwaukee, WI, Citizens for a Better
Environment.
BKWPPLK (2004). Application of Geographical Information System in Klang
Valley. Federal Territory Development and Klang Valley Planning Division,
Ministry of Federal Territory.
Bureau of Transport Economics. (1998). "Urban Transport Models: A Review,
Working Paper." from http://www.btre.gov.au/publications/27/Files/wp39.pdf.
de By, R. A., P. Y. Georgiadou, et al. (2004). Principles of geographic information
systems : an introductory textbook. Enschede, ITC.
Department of Environment Malaysia (2007 (a)). DOE Annual Report 2005.
Putrajaya, Department of Environment: 150.
Department of Environment Malaysia (2007 (b)). Malaysia Environmental Quality
Report 2006. Putrajaya, Department of Environment: 73.
Department of Statistic Malaysia. (2007). "Population and Housing Census 2000."
Retrieved 23 December 2007, from
http://www.statistics.gov.my/english/census/pressdemo.htm?file=pressdemo.
Economic Planning Unit. (2006). "Ninth Malaysia Plan 2006-2010." Retrieved 29
August 2007, from http://www.epu.jpm.my/rm9/html/english.htm.
ESRI (2006). ArcGIS: Using ArcGIS Desktop. Redland, California, ESRI.
Federal Transit Administration. (2004). "Characteristics of Bus Rapid Transit for
Decision-Making."
Henscher, D. A. e., K. J. Button, et al. (2004). Handbook of transport geography and
spatial systems. Amsterdam etc., Elsevier.
Institute for Transportation & Development Policy. (2007). "Bus Rapid Transit
Planning Guide." Retrieved 1 September 2007, from http://itdp.org/brt_guide.html.
Jamal, H. H., Pillay, M.S., Zailina, H., Shamsul, B.S., Sinha, K., Zaman, Huri Z.,
Khew, S.L., Mazrura, S., Ambu, S., Rahimah, A. and Ruzita, M.S. (2004). A Study
of Health Impact & Risk Assessment of Urban Air Pollution in Klang Valley,
Malaysia. Kuala Lumpur, UKM Pakarunding Sdn Bhd.
63
Japan International Cooperation Agency (1999). A Study on Integrated Urban
Transportation Strategies for Environmental Improvement in Kuala Lumpur. Kuala
Lumpur, Federal Territory Development and Klang Valley Planning Division.
Kabir, A. (2004). Development of a decision support model for transit zone location
choice : a spatial multicriteria evaluation for Klang Valley, Malaysia. Enschede,
ITC: 98.
Levinson, H. S. (2003). Bus rapid transit : synthesis of case studies.
Mark, Z. (2007). Introductory Notes in Transport Planning and Travel Demand
Modeling. Enschede, ITC.
Maslow, A. (1943). A Theory of Human Motivation. Psychological Review. 50:
370-396.
Ministry of Transport. (2007). "Malaysia Transport Statistic (Land Transport)."
Retrieved 31 August 2007, from http://www.mot.gov.my/BM/stat/darat.htm.
Ministry of Work Malaysia. (2007). "Road Traffic Volume Malaysia 2006."
Morichi, S. (2005). "Long Term Strategy for Transport System in Asian
Megacities." Journal of the Eastern Asia Society for Transportation Studies 6: 1-22.
Perunding Bersatu (2005). Klang Valley integrated public transport system and land
use development plan, Klang Valley Malaysia : final report. Kuala Lumpur,
Perunding Bersatu for Malaysian Ministry of Federal Territories.
Potoglou, D. and P. S. Kanaroglou (2005). "Carbon Monoxide Emissions from
Passenger Vehicles: Predictive Mapping with an Application to Hamilton, Canada."
Transportation Research Part D 10: 97-109.
Rodrigue, J. P., C. Comtois, et al. (2006). Geography of transport systems. London
etc., Routledge.
Statistics Netherland. (2007, 25 May 2007). "Methods for calculating the emissions
of transport in the Netherlands." Retrieved 2 October 2007, from
http://www.cbs.nl/en-GB/menu/methoden/dataverzameling/2006-11-methoden-
rapport-verkeer-eng1.htm.
The World Bank. (2007). "Cities on the Move: A World Bank Urban Transport
Strategy Review." Retrieved 20 December 2007, from
http://www.worldbank.org/transport/urbtrans/cities_on_the_move.pdf.
United Nations. (2005). "World Urbanization Prospects: The 2005 Revision
Population Database." Retrieved 23 December 2007, from
http://www.un.org/esa/population/publications/WUP2005/2005WUPHighlights_Fin
al_Report.pdf.
University Malaya Consultancy Unit (2003). Project on the Formulation of Emission
Factors for Industrial Pollutants in Malaysia. Kuala Lumpur, University Malaya.
Vasconcellos, E. A. (1997). "The demand for cars in developing countries."
Transportation Research Part A: Policy and Practice 31(3): 245-258.
64
APPENDICES
Appendix 1-A
Parameters for Calculating Trip Generation
Production Attraction
Purpose Parameter Unit Parameter Unit
Home to 0.46725 Trip/person 0.85025 Trip/Job
Work
Work to 0.97825 x Trip Attraction 0.97825 x Trip Production
Home
Home to 0.9358 x job (30.62) 0.9358 x job (30.62)
Business
Business 1.7337 x job (5.69) + 0.7533 x 1.7337 x job (5.69) + 0.7533 x
to Home job (22.1) job (22.1)
Home to 1.00833 Trip/student 1.00833 Trip/student
School
School to 0.97733 x Trip Attraction 0.97733 x Trip Attraction
Home
Home to 0.36025 Trip/person 0.1079 x pop (11.8) + 0.2127 x
Other job (11.46) - 21.2
Other to 0.3495 Trip/person 0.1079 x pop (11.8) + 0.2127 x
Home job (11.46) - 21.2
Appendix 1-B
Summary of Projection and Coordinate System
Projected Coordinate System: KV_PCS
Projection: Hotine_Oblique_Mercator_Azimuth_Natural_Origin
False_Easting: 804671.28000000
False_Northing: 0.00000000
Scale_Factor: 0.99984000
Azimuth: 323.02579050
Longitude_Of_Center: 102.25000000
Latitude_Of_Center: 4.00000000
Linear Unit: Meter
Geographic Coordinate System: KV_GCS
Datum: D_Kertau
Prime Meridian: Greenwich
Angular Unit: Degree
65