Professional Documents
Culture Documents
F12
2. Work Location : 220 kV GIS Substation Engineer, Supervisor, Electricians and Helpers.
Yes No Yes No
Signature : Date :
7. Approvals
The completed Work Method Statement must be submitted at least seven full working days prior to the
commencement of activities.
Where the Work Method Statement indicates the use of Hazardous Substances, a Material Hazard Data
Sheet must be attached.
After the Area Owners approval the Work Method Statement shall be forwarded to EHS department for
approval
The approved Work Method Statement must be attached to the permit(s) to work and all persons involved
in the job instructed in its requirements.
Severity
Probability Low x1 Medium x 2 High x3
Significant Risk = High Risk (6-9) or Medium Risk (3-4) in terms of probability and severity
Tolerable Risk = Risk reduced to an acceptable level = Low Risk (1-2)
Residual Risk = Risk remaining after implementing recommended control actions (usually very minor).
8. Safety Analysis
Identified Hazard(s) Persons Exposed To Precautions and Plan of actions To Be Taken Severity x Probability =
Individual Activities To Associated With Activity Hazard To Remove / Control Hazards Risk
Complete Work. List In
Sequence of Activity Residual Risk
(Use Risk Estimator
Chart)
1.PREPARATION FOR WORK. Slips, trips and fall at the Maintain housekeeping around in the working
same level. area.
Hot weather. All workers involve in the activity must be
Manual handling aware of heat stress, supervisor to ensure
hazards. drinking cold water is available.
Electrical shock Emal / SNC rep., Engr., Supervisor to give tool box talk regarding proper
2x2=4
Supv. Elec,helpers. manual handling.
Authorized personnel only allowed to perform
the tusk
Job will be performed under supervision.
Use appropriate signages and warning tape to
barricade
Emal / SNC rep., Engr., Wear P.P.E.'s at all times (hard hat, clear
safety glass inside the building, safety shoes, 2x2=4
Not using P.P.E.'s Supv. Elec,helpers.
hand gloves, dust mask, fire retardant long
sleeve shirt / pants).
2. WORKING AT HEIGHT
While working at height all should ensure
Emal / SNC rep., Engr.,
Fall from height wearing safety harness and 100% tie off. 2x2=4
Supv. Elec,helpers
Non conductive (fibre or wooden) ladder are
to be used if required.
This sheet must be properly completed detailing all of the steps required to complete the job along with the sequence of events and each of the hazards
arising. Failure to properly complete the form will result in non-approval.
(Additional sheets to be used as required)
Product Name
Duration of Exposure
Frequency of Exposure
Controls to be implemented