Quantity Estimate

Sunkoshi Hydropower
Total Civil Works

T. Qty' Unit
S.N. Item

1 Site Clearance 2,582.83 sft


2 Earthwork Exavation 3,879.72 cft
3 Backfilling of Earthwork 1,939.86 cft
4 Brick Soling 2,981.07 sft
5 P.C.C
PCC(1:3:6) Works 235.73 cft
6 Tie Beam RCC 235.73 cft
6 Flooring Works
Screeding and punning 2,038.14 sft
7 Brick Works
Toe Wall 1,125.23 cft
8 Enco Panel Wall 3,965.70 sft
9 CGI Sheet 3196.55 sft
10 Metal Post 727.88kgs.
11 Truss kgs.
12 Aluminum works 519.75 sft
13 Rebar 944.30 kgs.
Quantity Estimate

Excavation and Backfilling Works


S.N. Particulars Nos. Length Breadth Height Quantity Units
1 Earthwork
1.1 Site clearance & Lay-out /
Setting out of the Building. 1 Area taken from Site plan 2,582.83 sq.ft

Total 2,582.83 sq.ft


1.2 Earthwork Excavation
Grid A-A 1 14.830 3.000 3.000 133.47
Grid B-B 1 26.000 3.000 3.000 234.00
Grid C-C 1 38.670 3.000 3.000 348.03
Grid C'-C' 1 38.670 3.000 3.000 348.03
Grid D-D 1 33.250 3.000 3.000 299.25
Grid E-E 1 33.250 3.000 3.000 299.25
Grid 1-1 1 17.250 3.000 3.000 155.25
Grid 1'-1' 1 76.250 3.000 3.000 686.25
Grid 2-2 1 19.330 3.000 3.000 173.97
Grid 3-3 1 53.080 3.000 3.000 477.72
Grid 4-4 1 68.500 3.000 3.000 616.50
Inclined 1 12.000 3.000 3.000 108.00
Total 3,879.72 Cu.ft
1.3 Earthwork in Filling
@50% of Excavation 1939.86
Total 1,939.86 Cu.ft
Remarks
Quantity Estimate

Sub Structure Works


S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
A Sub Structure Works

1 PCC Above soling 1 419.08 2.25 0.25 235.73


Total 235.73 Cu.ft

2 Tie Beam RCC


Grid A-A 1 14.830 0.750 0.750 8.34
Grid B-B 1 26.000 0.750 0.750 14.63
Grid C-C 1 38.670 0.750 0.750 21.75
Grid C'-C' 1 38.670 0.750 0.750 21.75
Grid D-D 1 33.250 0.750 0.750 18.70
Quantity Estimate

Sub Structure Works


S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
Grid E-E 1 33.250 0.750 0.750 18.70
Grid 1-1 1 17.250 0.750 0.750 9.70
Grid 1'-1' 1 76.250 0.750 0.750 42.89
Grid 2-2 1 19.330 0.750 0.750 10.87
Grid 3-3 1 53.080 0.750 0.750 29.86
Grid 4-4 1 68.500 0.750 0.750 38.53
Total 235.73 Cu.ft
REBAR DETAIL MEASUREMENT SHEET
Cutti Total
Leng Quanti
SN Di No ng Wt/ Quanti
Description th ty
. a . Lengt M ty
(M) (Kg)
h (ft.) (Kg)
1 Rebar in Tie Beam
Grid A-A 12 6 15.99 4.875 0.889 26.000
Stirrups 8 32 2.83 0.863 0.395 10.901
Grid B-B 12 6 27.16 8.280 0.889 44.163
Stirrups 8 54 2.83 0.863 0.395 18.516
Grid C-C 12 6 42.330 ### 0.889 68.829
Stirrups 8 85 2.83 0.863 0.395 28.857
Grid D-D 12 6 34.41 ### 0.889 55.951
Stirrups 8 69 2.83 0.863 0.395 23.458
Grid E-E 12 6 34.41 ### 0.889 55.951
Stirrups 8 69 2.83 0.863 0.395 23.458
Grid 1-1 12 6 17.250 5.259 0.889 28.049
Stirrups 8 35 2.83 0.863 0.395 11.760
Grid 1'-1' 12 6 76.25 ### 0.889 ###
Stirrups 8 153 2.83 0.863 0.395 51.981
Grid 2-2 12 6 20.49 6.247 0.889 33.317
Stirrups 8 41 2.83 0.863 0.395 13.968
Grid 3-3 12 6 55.58 ### 0.889 90.374
Stirrups 8 111 2.83 0.863 0.395 37.890
Grid 4-4 12 6 72.16 ### 0.889 ###
Stirrups 8 144 2.83 0.863 0.395 49.193
Inclined 12 6 13.16 4.012 0.889 21.398
Stirrups 8 26 2.83 0.863 0.395 8.971
Total Quantity in Kg. : ###
Grid A-A 1 14.830
Grid B-B 1 26.000
Grid C-C 1 38.670
Grid C'-C' 1 38.670
Grid D-D 1 33.250
Grid E-E 1 33.250
Grid 1-1 1 17.250
Grid 1'-1' 1 76.250
Grid 2-2 1 19.330
Grid 3-3 1 53.080
Grid 4-4 1 68.500
Inclined 1 12.000

28.8
2.4
Quantity Estimate

Brick Works
S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
A Sub Structure Works
1 Flat Brick Soling Works
Below Toe wall 1 419.08 2.25 942.93
Flat Brick Soling Works 1 Area= 2038.14 2038.14
Total 2981.07 sft
2 Toe wall
9" 1 419.08 0.75 2.08 653.76
14" 1 419.08 1.17 0.25 122.58
18" 1 419.08 1.50 0.25 157.16
22" 1 419.08 1.83 0.25 191.73
Total 1125.23 Cu.ft
Quantity Estimate

METAL POST
S.N. Particulars Nos. Length Total Meter Kg/m Quanity Units Remarks
A Main post
Metal post(4" diameter,5mm thickness) 5 14.00 70.00 21.34 11.70 249.70
13 9.5 123.50 37.65 12.70 478.19
Total 727.88 kg
Quantity Estimate

Metal Work
S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
A CGI Sheet
roof 1.25 Area= 2557.24 3,196.55 sq.ft
Total 3196.55 sq.ft
Quantity Estimate

Flooring Works
S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
A. BASEMENT FLOOR
Screeding and Punning 1 Area= 2038.14 2,038.14 sq.ft
Total 2,038.14 sq.ft
Quantity Estimate

Enco Panel Works


S.N. Particulars Nos. Length Breadth Height Quantity Units
1 Cement Board wall
Grid A-A 1 14.00 9.50 133.00
deduction
Window -1 4.00 4.50 -18.00

Grid B-B 1 24.42 9.50 231.99


deduction
Window -1 4.00 4.50 -18.00

Grid C-C 1 33.66 9.50 319.77


deduction
Window -1 2.50 4.50 -11.25

Grid C'-C' 1 45.160 9.50 429.02


deduction
Door -1 2.50 7.00 -17.50

Grid D-D 1 33.25 9.50 315.88


deduction
Door -1 3.00 7.00 -21.00

Grid E-E 1 33.25 9.50 315.88

Grid 1-1 1 16.830 9.50 159.89


deduction
Window -1 2.50 4.50 -11.25
Window -1 4.00 4.50 -18.00

Grid 1'-1' 1 76.250 9.50 724.38


deduction
Window -2 2.50 4.50 -22.50
Window -2 4.00 4.50 -36.00
Door -1 3.00 7.00 -21.00
Door -2 2.50 7.00 -35.00

Grid 2-2 1 15.250 9.50 144.88

Grid 3-3 1 53.080 9.50 504.26


deduction
Window -1 4.00 4.50 -18.00
Door -3 3.00 7.00 -63.00

Grid 4-4 1 68.500 9.50 650.75


deduction
Window -4 4.00 4.50 -72.00

Reception Room 1 74.25 4.50 334.13


Quantity Estimate

Enco Panel Works


S.N. Particulars Nos. Length Breadth Height Quantity Units
Inclined 1 12.000 9.50 114.00
deduction
Door -1 4.00 7.40 -29.60

3965.70 sft
Remarks
Remarks
Quantity Estimate
Sunkoshi Hydropower
Aluminum Works
S.N. Particulars Nos. Length Breadth Height Quantity Units Remarks
1 Aluminum works
Door 4'X7'-6" 1 4.00 7.50 30.00
Door 3'X7' 7 3.00 7.00 147.00
Door 2'-6"'X7' 3 2.50 7.00 52.50
Window 4'X4'-6"' 13 4.00 4.50 234.00
Window 2'-6"'X4'-6"' 5 2.50 4.50 56.25
519.75 sft
Quantity Estimate
0
Truss
S.N. Particulars Nos. Length Total Meter Kg/m Quanity
A Main Post
1 Rafter (80 mm)Down 9 15.50 139.50 42.52 9.25 393.29
2 Rafter (80 mm)Up 9 20.00 180.00 54.86 9.25 507.47
3 Post and bracing (50 mm) 9 24.50 220.50 67.21 5.55 372.99
Total 1273.74

B Purlin 8 93.75 750.00 228.59 5.55 1,268.67


Total 1268.67
Units Remarks

kg T=5mm
kg T=5mm
kg T=5mm
kg

kg T=5mm
kg
SUMMARY OF ESTIMATING
Project:-
Location :-
Consultant :-
Rate Amount
S.N. Description of Works Unit Qty. Rmks
(NPR) (NPR)
1 SITE CLEARANCE
Clearing the site of all vegetation roots and all unusual
materials including excavation of top soil to a depth of 15 cm
including existing layer of bitumen road, removing bushes, trees
a and levelling the site for staking the useful items in specified Sq ft
space and disposing other items as per instruction of the site
engineer all complete including layoutogf building road and
ancillary services

2 EXCAVATION AND BACKFILLING WORKS


Earthwork in excavation in trenches, foundation etc in all kinds
of soil including timbering and pumping out water from
a foundation (if necessary), dressing side, ramming of bottom as Cu ft
per specification, drawing & instruction of site engineer
Backfilling the sides of foundation, toe walls , trenches etc and
filling under floor or within plinth, open trenches with approval
quality of selected earth available within permishes or to be
brought from outside and laid in layers not exceeding 150mm in
b thickness including watering , ramming levelling and compacting Cu ft
to 95% proctor density with use of mechanical rammer etc
complete as directed and instructed by engineer/ Owner.

Providing, laying first class chimney made dry flat brick soling
c with sand blending inperfect line & level including proper Sq ft
compaction all complete
3 Concrete & Allied Works
Providing and laying plain cement concreteM10 (1:3:6) in
foundation and floors using specified graded coarse aggrigate of
approval quality at various locations etc. machine mixing,
a consolidating with rammers/ vibrators, curing, finishing to Cu ft
approval level, lines as per drawing , specification and
instruction of site engineer

Providing and laying plain cement concrete M20 (1:11/2:3) in


foundation and floors using specified graded coarse aggrigate of
approval quality at various locations etc. machine mixing,
b consolidating with rammers/ vibrators, curing, finishing to Cu ft
approval level, lines as per drawing , specification and
instruction of site engineer

Supplying and fixing Steel reinforcement bar including bending,


Binding of TMT reinforcement bar with 16 guage black wire and
c placing in position as per drawing , specification & instruction all KG
complete
4 MASONARY AND ALLIED WORKS
Providing and laying local chimney made brick masonry work in
cement sand mortar (1:5) in substructure finished in perfecr line
a & level including wetting the bricks, packing the joints & curing Cu ft
the works complete in all thickness of walls as per drawing

5 Steel Roofing & Allied Works


a Supply , fabrication and instalation of Metal post columns KG
SUMMARY OF ESTIMATING
Project:-
Location :-
Consultant :-
Rate Amount
S.N. Description of Works Unit Qty. Rmks
(NPR) (NPR)
Supply , fabrication and instalation of tubular truss,
Purlins,beams including necessary batten plates, cleats etc with
b minimum yield strength conforming to fy 250 N/mm2 with 4.6 KG
grade of nut bolt 7 washers including one coat of red oxide primer and
two coats of approved enamel paints

Supply & installation of CGI roofing sheets including ridge works


c Sq ft

6 FLOOR FINISHES
Providing, laying, compacting, curing average 50m m thick
screed with 1:4 cxement sand mortar in perfect lines ,level
a including punning works as per design, specification and Sq ft
instruction of the site engineer
7 ALUMINIUM DOOR WINDOWS AND ALLIED WORKS
Supplying and fitting Aluminium swing door and sliding Windows
a Sq ft
of section all complete.
Total Construction Works
VAT 13%
Total Cost