Professional Documents
Culture Documents
neer
ingmanual
s
Engineering manuals for GEO5 programs
Introduction ................................................................................ 2
Engineering manuals are new teaching material for GEO5 software. They were developed as a
reaction to hotline and frequently asked questions of users. The objective of each chapter is to
explain how to solve the concrete engineering problems using GEO5 software.
Assignment here the problem is described with all input data needed for solving the problem in
selected the program
Conclusion has the conclusion of the problem and the final verification of the construction. It tells
if the structure is satisfactory or not and if there are any modifications needed.
In each chapter there are also notes, which explain the problem in general as well as links to other
materials.
The basic educational materials of GEO5 software suite (from FINE s r.o.) are:
The first chapter explains how to set standards and chose an analysis method, which is the same for
all GEO5 programs. In further chapters one standard is selected, by which the construction is verified.
This chapter explains the correct use of Settings administrator that serves to choose
standards, partial factors and verification methodology. It is the basic step needed for all GEO5
programs.
Introduction
GEO5 software is used in 90 countries worldwide. Engineering tasks are the same
everywhere to prove that the construction is safe and well designed.
The basic characteristic of structures (eg. geometry of wall, terrain, localization of anchors
etc.) are the same all over the world; the way of proving that the construction is safe and the theory
of analysis used are different. Large quantities of new theories and mainly partial factors of analysis
lead to input of large amounts of data and complicated programs. The Settings administrator was
created in GEO5 for version 15 to simplify this process.
In the Settings administrator are defined all input parameters, including standards, methods
and coefficients for the current country. The idea is that each user will understand the Settings
defined in the program (or will define a new Setting of analysis), which the user then uses in their
work. To the Settings administrator and Settings editor the user then goes only occasionally.
Assignment:
Perform an analysis of a gravity wall per the picture below for overturning and slip according to
these standards and procedures:
1) CSN 73 0037
2) EN 1997 DA1
3) EN 1997 DA2
4) EN 1997 DA3
5) Safety factor on SF=1.6
Solution
Firstly, input the data about the construction and geological conditions in the frames:
Geometry, Assign and Soils. Skip the other frames because they are not important for this
example.
MG Gravelly silt,
19,0 30,0 0 15,0
firm consistency
In the frame Assign, the first soil will be assigned automatically to the layer or layers.
This can be changed when necessary.
When the basic input of construction is done, we can choose standards, and then finally run
the analysis of the gravity wall.
In the frame Settings click the button Select and choose number 8 Czech Republic
old standards CSN (73 1001, 73 1002, 73 0037).
Note: The look of this window depends on standards that are currently active in the Settings
administrator more information in the help of the program (press F1). If the setting you want to use
isn`t on the list in the dialog window Settings list, you can activate it in the Settings administrator.
Now, open up the frame Verification and after analyzing the example record the utilization
of construction (in the frame Verification) - 53,1% resp. 66,5%.
Then return to the frame Settings and choose number 3 Standard EN 1997 DA1.
Repeat this procedure for settings number 4 Standard EN 1997 DA2 and number 5
Standard EN 1997 DA3.
The analyzed utilization of constructions are (77,8% and 69,7%) for EN 1997, DA2 or (53,5%
and 74,7%) for EN 1997, DA3.
Verification
Overturning Slip
Note: This simple method can be used to compare retaining structures or stability analyses. When
analyzing foundations, the load (basic input data) must be computed according to relevant standards.
That is the reason why it doesnt make sense, to compare foundation design by various standards
with the same values of load (nominal values).
In this chapter, the design of cantilever wall and its overall analysis is described.
Assignment
Design a cantilever wall with a height of 4,0 m and analyze it by EN 1997-1 (EC 7-1, Design
approach 1). The terrain behind the structure is horizontal. The ground water table is 2,0 meters
deep. Behind the wall acts a strip surcharge with a length of 5,0 meters and with a magnitude of 10
kN/m2. The foundation soil consists of MS Sandy silt, stiff consistency, S r 0,8 , allowable bearing
capacity is 175kPa. The soil behind the wall will consist of S-F Sand with trace of fines, medium
dense soil. The cantilever wall will be made of reinforced concrete of class C 20/25.
For solving this problem, we will use the GEO5 program, Cantilever wall. In this text, we will
explain solving this example step by step.
In the frame Settings click on Select and then choose analysis setting Nr. 3 Standard
EN 1997 DA1.
In the frame Geometry choose the wall shape and enter its dimensions.
Then, define the parameters of soil by clicking Add in the frame Soils. Wall stem
is normally analyzed for pressure at rest. For pressure at rest analysis, select Cohesionless.
3
normally entered in the interval 1 2
3
ef
Angle of Cohesion
Profile Unit weight Angle of friction
Soil internal of soil
structure soil
m kN m friction
3
(Soil classification)
ef cef kPa
Frame Terrain
The ground water table is at a depth of 2,0 meters. In the frame Water select the type of
water close to the structure and its parameters.
In the next frame define Surcharge. Here, select permanent and strip surcharge
on the terrain acting as a dead load.
In the frame FF resistance select the terrain shape in front of the wall and then define
other parameters of resistance on the front face.
Note: In this case, we do not consider the resistance on the front face, so the results will be
conservative. The FF resistance depends on the quality of soil and allowable displacement of the
structure. We can consider pressure at rest for the original soil, or well compacted soil. It is possible to
consider the passive pressure if displacement of structure is allowed. (for more information, see HELP
F1)
Then, in the frame Stage settings choose the type of design situation. In this case, it will be
permanent. Also choose the pressure acting on the wall. In our case, we will choose active pressure,
as the wall can move.
Now, open up the frame Verification, where you analyze the results of overturning and slip
of the cantilever wall.
Note: The button In detail in the right section of the screen opens a dialog window with detailed
information about the analysis results.
Analysis results:
Now we have several possibilities how to improve the design. For example, we can:
Note: A base jump is usually analyzed as an inclined footing bottom. If the influence of the base jump
is considered as front face resistance, then the program analyses it with a straight footing bottom,
but FF resistance of the construction is analyzed to the depth of the down part of the base jump
(More info in HELP F1)
Then analyze the newly designed construction for overturning and slip.
Now, the overturning and slip of the wall are both satisfactory.
Note: In this case, we analyze the bearing capacity of the foundation soil on an input value, which we
can get from geological survey, resp. from some standards. These values are normally highly
conservative, so it is generally better to analyze the bearing capacity of the foundation soil in the
program Spread footing that takes into account other influences like inclination of load, depth of
foundation etc.
Frame Dimensioning
Then, open up the frame Stability and analyze the overall stability of the wall. In our case,
we will use the method Bishop, which result in conservative results. Perform the analysis
with optimization of circular slip surface and then leave the program by clicking OK.
Results or pictures will be shown in the report of analysis in the program Cantilever wall.
In this chapter an analysis of an existing gravity wall for permanent and accidental design situations is
performed. Construction stages are also explained.
Assignment
Using EN 1997-1 (EC 7-1, DA2) standard, analyze an existing gravity wall for stability, overturning, and
slip .
Road traffic acts on the wall with magnitude of 10 kPa. Check the possibility to install the barrier on
the top of the wall. An accidental load from a car crash is considered as 50 kN/m and it acts
horizontally at 1,0 m. Dimensions and shape of the concrete wall can be seen in the picture below.
Inclination of the terrain behind the construction is 10 , the foundation soil consists of silty
Determination of bearing capacity and dimensioning of the wall is not part of this task. In this
analysis, consider effective parameters of soil.
Solution:
For analyzing this task, use the GEO5 program Gravity wall. In this text, we will describe
the steps of analyzing this example in two construction stages.
1st construction stage analyzing the existing wall for road traffic.
In the frame Settings click on Select and choose Nr. 4 Standard EN 1997 DA2.
Then, in the frame Geometry, select the shape of the gravity wall and define its
parameters.
Frame Geometry
24 kN m 3 . Wall is made from concrete C 12/15 and steel B500. Then define parameters of soil
and assign them to the profile.
Angle of Cohesion
Soil Unit weight Angle of friction
internal friction of soil
structure soil
(Soil classification) kN m 3 ef cef kPa
MS Sandy silt,
18,0 26,5 12,0 18,0
firm consistency
Note: The magnitude of active pressure depends also on friction between the structure and soil in the
3
angle 1 2
3
ef . In this case we consider the influence of friction between the structure
and soil with value of 2 ef ( d =18 ), when analyzing earth pressure. (More info in HELP F1).
3
Frame Terrain
In the next frame, define Surcharge. Input the surcharge from road traffic as Strip, with
its location on terrain, and as a type of action select Variable.
Note: In this case, we do not consider resistance on the front face, so the results will be conservative.
The FF resistance depends on the quality of soil and allowable displacement of the structure. We
consider pressure at rest for the original soil or well compacted soil. It is possible to consider passive
pressure only if displacement of structure is allowed. (More info in HELP F1).
In the frame Stage settings select the type of design situation. In the first construction
stage, consider the permanent design situation.
Note: The button In detail in the right section of the screen opens a dialog window with detailed
information about the results of the analysis.
Then, open up the frame Stability and analyze the overall stability of the wall. In our case,
we will use the method Bishop, which results in conservative results. Perform an analysis
with optimization of circular slip surface and then validate everything by clicking OK.
Results or pictures will be shown in the report of analysis in the program Gravity wall.
Now, add construction stage 2 using tool bar in the upper left corner of the screen.
In this stage, define the load from the impact of the vehicle to the barrier, using the frame
Input forces. The load ais accidental and considers the impact of a vehicle with a weight of 5 tons.
Then open the frame Stage settings change the design situation on accidental.
The data in the other frames that we entered in stage 1 has not changed, so we dont have to
open these frames again. Select the frame Verification to perform the verification on overturning
and slip again.
Conclusion
The existing gravity wall in case of bearing capacity satisfies only for the first construction
stage, where road traffic acts. For the second construction stage, which is represented as impact to
the barrier on the top of the wall by a vehicle of 5 tons, the wall is not satisfactory.
As a solution to increase bearing capacity for overturning and slip it is possible to introduce
soil anchors. alternatively it is possible to place a barrier on the edge of the road, so the wall is not
loaded by a force from the crashing car.
In this chapter is the design of non-anchored retaining wall for permanent and accidental loads
(flooding)
Assignment
Design non-anchored retaining wall from pile sheeting using the EN 1997-1 (EC 7-1, DA3)
standard in non-homogenous geologic layers. The depth of excavation is 2,5 m. The ground water
table is at a depth of 1,0 m. Analyze the construction also for flooding; when the water is 1,0 m
above the top of the wall (mobile anti-flood barriers should be installed.)
Solution:
For solving this problem, we will use the GEO5 program, Sheeting design. In this text, we will
explain each step to solve this example:
In the frame Settings click on Select and then choose Nr. 5 Standard EN 1997 DA3.
Then, input the geological profile, parameters of soil and assign them to the profile.
Angle of Cohesion
Soil Profile Unit weight Angle of friction
internal of soil
structure soil
m kN m 3
friction
(Soil classification)
cef kPa
ef
SC Clayey sand,
1,5 2,5 18,5 27,0 8,0 14,0
medium dense soil
In the frame Geometry, select the shape of bottom of the excavation and input its depth.
Frame Geometry
Note: coefficient of reduction of earth pressure below the ditch is considered while analyzing braced
sheeting (retaining wall with soldier beams) only; for a standard sheeting pile wall it equals 1,0 For
more information, see HELP (F1).
In this case, we do not use the frames Anchors, Props, Supports, Pressure
determination, Surcharge and Applied forces. The frame Earthquake also has no influence
Then, in the frame Stage settings, select the design situation as permanent.
Now, open up the frame Analysis and click on the button Analyze. This will perform
the analysis of the retaining wall.
Note: For cohesive soils is recommended by many standards to use minimal dimensioning pressure
acting on the retaining wall. The standard value for the ceofficient of minimal dimensioning
pressure is Ka = 0,2. It means that minimum pressure on the structure is 0,2 of geostatic stress
never less.
Within the design of pile sheeting retaining wall, we are interested in the depth of
construction in the soil and internal forces on the structure. For the 1st construction stage, the results
of analysis are:
In the next stage, we are going to show you how to analyse the minimum depth in soil
and internal forces in the soil for the accidental design situation floods.
Now, select stage 2 on the toolbar Stage of construction on the upper left corner of your
screen. (If needed, add a new one)
Then, in the frame Stage settings, select the design situation Accidental.
All other values are the same as in the 1st construction stage, so we dont have to change data
in other frames, so we go on to the frame Analysis and click again on the button Analyze.
The minimum length of pile sheeting is set as the maximum of necessary length from
construction stage 1 and construction stage 2 .
We design the pile sheeting based on the maximum bending moment using the table of pile
sheeting with allowable bearing capacities shown below.
Based on the chart, we will select the pile sheeting VL 503 (500 340 9,7 mm), the steel
grade S 270 GP, of which the maximum bending moment is M max 224,0 kN m .
Analysis result:
In the design of non-anchored restraint retaining wall, we are verifying values of minimum
depth of the structure in the soil, and the internal forces in the structure:
The designed pile sheeting retaining wall VL 503 from S 270 steel with length of 6,6 meters satisfies.
In this chapter, we will show you how to design a retaining wall with one row of anchors.
Assignment:
Design a retaining wall with one anchor row made from pile sheeting using EN 1997-1 (EC 7-
1, DA3) standard. The depth of ditch is 5,0 m. The anchor row is 1,5 m below the surface. The soils,
geological profile, ground water table and shape of terrain are the same as in the last task. Remove
construction stage two so as to not consider flooding.
Solution:
For solving this problem, we will use a GEO5 program, Sheeting design. In this text, we will
explain each step of this example:
Leave the frames Settings, Profile, Soils, Terrain, Water and Stage settings from
the previous problem without changes. Also, delete construction stage 2 if you are reusing the file
from problem 4.
Open up the frame Anchors and click on the button Add. For this case, add one anchor
row in the depth of 1,5 m below the top of the wall with anchor spacing at 2,5 m. Also define the
length of the anchors (which has no effect in the Sheeting design program, it is only for visualization)
and slope of the anchors (15 degrees).
Frame Anchors
In the frame Analysis select support at heel. For now, select Wall fixed at heel. Now
perform the analysis.
Now, perform an analysis for wall hinged at heel (construction stage 2). Then, compare the
results and, depending on comparison, design the embedment depth.
Now, add a new verification in the upper left corner of the frame.
Toolbar Verification
Select the option Wall hinged at heel and perform the analysis.
Frame Analysis
The overall length of the structure should be in the interval of Hfixed Hhinged. For wall fixed
at heel is the length of the structure is longer, but the anchor force is smaller. For wall hinged at heel,
it is the opposite, so larger anchor force and shorter length of the construction. It is the users task to
design the dimensions of the structure.
Conclusion
In our design, we will use pile sheeting VL 503 from steel S 270 with an overall length of 9,0
m, anchors with size of force 240 kN with anchor spacing of 2,5 m. In the next chapter, we will check
this structure in the program Sheeting check.
Note: The design cannot be taken as the final and it needs to be checked in the Sheeting check
program, because on the real structure there is redistribution of earth pressure due to anchoring.
In this chapter, we will show you how to verify a designed retaining wall with verification of inner
stability of the anchors and overall stability of the structure.
Assignment
Solution:
For solving this problem, we will use the GEO5 program, Sheeting check. In this text, we will
explain each step to solve this task:
To make our work easier, we can copy the data from the last task, when we designed the
wall in the Sheeting design program by clicking in this program on Edit on the upper toolbar and
selecting Copy data. In Sheeting check program click on Edit and then Paste data. Now we
have most of the important data from the last task copied in to this program, so we dont have to
input much of the needed data.
Note: the selection Analysis of depending pressures do not reduce allows the analysis of limit
pressures (active and passive) without the reduction of input parameters by partial factors. This is
better for estimation of real behavior of construction.On the other hand, it does not follow EN 1997-1
Standard. (More info in HELP F1)
Then, open up the frame Modulus k h , and choose the selection analyze Schmitt. This
method for the determination of modulus of subsoil reaction depends on the oedometric modulus
and stiffness of the structure. (More info in HELP F1)
Frame Modulus k h
Note: the modulus of subsoil reaction is an important input when analyzing a structure by the method
of dependent pressures (elasto-plastic nonlinear model). The modulus k h affects the deformation,
which is needed to reach active or passive pressures. (More info in HELP F1)
In the frame Soils enter the following values for each soil type. Poissons ratio and the oedemetric
modulus were not entered in the previous program, so they must be entered here.
In the frame Geometry define the parameters of the sheet pile type of wall, section
length, coefficient of pressure reduction below ditch bottom, geometry and material of the
construction. From the sheet pile database, select the VL 503 (500 340 9,7 mm).
Now, in the frame Excavation define the first ditch depth 2,50 m for the first construction
stage.
Now, go to frame Analysis. In the left part of the frame, you can see the modulus of subsoil
reaction, in the right section earth pressures and displacement. (For more information, see HELP
F1)
Frame Analysis
Add another construction stage as indicated below. Here we define the anchoring of the
wall and overall excavation. We cannot change the frames Settings, Profile, Modulus Kh,
Soils and Geometry, because these data are the same for all construction stages. We will only
change data in the frames Excavation and Anchors.
In the frame Excavation, change the depth of the ditch to the final depth 5,0 m.
Frame Excavation
Then, go to the frame Anchors and click on the button Add. For this structure, we will
add a row of anchors to a depth 1,5 m below the top of the wall (below the surface). Also define
other important parameters: overall length of the Anchor input as 10 m, slope angle as 15 and
anchor spacing as 2,5 m. Enter a prestress force equal to 240 kN and the diameter of the anchor.
Frame Anchors
We dont change any other input data. Now, perform the analysis to view the maximums of
internal forces and maximum displacement of the anchored structure.
Frame Analysis
Sheet pile VL 503 (500 340 9,7 mm), quality of steel S 270 GP satisfies.
Now, open the frame Inter. stability. You can see, that the internal stability of anchors is not
satisfactory. This means, that the anchor could tear from the soil.
The reason for this is that the anchor is too short, so in the frame Anchors, change its
length to 12 meters. This newly designed anchor then satisfies the internal stability requirements.
Analysis done:
In this chapter, we are showing how to design and verify a multi-anchored wall.
Assignment
Verify a multi-anchored wall made from steel soldier piles I 400 with a length of 21,0
m. Depth of the ditch is 15,0 m. The terrain is horizontal. The surcharge acts at the surface
and is permanent with size of 25,0 kN m 2 . The GWT behind the construction is 10,0 m
below the surface.
For solving this task, use the GEO5 program Sheeting Check. The analysis will be
performed in the classical way without reduction of input data so the real behavior of the
structure will be grasped. Internal stability of the anchor system and overall stability will be
checked with a safety factor of 1,5. This solution assumes you have entered the soil types
and profiles, and permanent load as listed above.
Note. The coefficient of reduction of earth pressures below the excavation reduces the
pressures in the soil. For classical retaining walls this is equal 1,0. For braced sheeting it is
less than or equal to one. It depends on size and spacing of braces (More info in help - F1).
Now, we will describe the building of the wall stage by stage. It is necessary to model
the task in stages, to reflect how it will be constructed in reality. In each stage it is necessary
to look at values of internal forces and deformation. If the sheeting is not stable in some
stage of construction or if the analyzed deformation is too large, then we need to change
structure for example to make the wall embedment longer, make the ditch shallower,
increase the anchor forces etc.
In construction stage 1, the ditch is made to depth ofa 3,0 m. In the stage 2, anchor is
placed at a depth of 2,5 m. The GWT behind the structure is at a depth of 10,0 m beneath
the surface.
In the 3rd construction stage, the ditch is excavated to a depth of 6,5 m. In the 4th
stage, anchor is placed at a depth of 5,5 m. The GWT is not changed so far.
In the 11th, and last, construction stage, the ditch is excavated to a depth of 15,0 m. We will
not add new anchors. The GWT in front of the wall is at a depth of 15,5 m. Behind the wall it
is at a depth of 10,0 m.
Note: Due to deformation of the structure the forces in anchors are changing. These changes
depend on the stiffness of the anchors and the deformation of the anchors head. The force
All the stages are sarisfactorily analyzed that means that the structure is stable and
functional in all stages of the construction. The deformation must also be checked that it is
not too large, as well as that the anchor force does not exceed the bearing capacity of the
anchor (The user must check this as this is not checked by the program Sheeting check).
Note: If the program does not find a solution in some of the construction stages, then the
data must be revised e.g. to make the structure longer, make the forces in anchors larger,
change the number or position of anchors, etc.
Open the frame Envelopes in the 1st construction stage, where you see the
maximum and minimum values of variables.
Frame Envelopes
The bending moment is calculated per one meter (foot) of structure, so we have to calculate
the moment acting on the soldier beam. The spacing of soldier beams in our example is 2,0
m, so the resulting moment is 220,80 * 2,0 = 441,6 KNm.
Go to the frame Internal stability in the last construction stage and look at maximum
allowable force in each anchor and the specified safety factor. The minimum safety factor is
1.5.
Note : The verification is done this way. At first we iterate the force in the anchor, resulting in
an equilibrium of all forces acting on the earth wedge. This earth wedge is bordered by
construction, terrain, the middle of the roots of anchors and the theoretical heel of structure.
If an anchor is not satisfactory the best way to resolve the issue is to make it longer or
decrease the prestressed force.
Conclusion
The structure was successfully designed with a maximum deformation of 28,8 mm.
This is satisfactory for this type of construction. Additionally, the limits of forces in anchors
were not exceeded.
Verification of bearing capacity of cross-section - SATISFACTORY
Internal stability SATISFACTORY
Anchor nr. 4 (analyzed safety factor): SFmin 5,34 > SFa 1,50
In this chapter, we are going to show you how to verify the slope stabilityfor critical
circular and polygonal slip surfaces (using its optimization), and the differences between
methods of analysis of slope stability.
Assignment
Perform a slope stability analysis for a designed slope with a gravity wall. This is a
permanent design situation. The required safety factor is SF = 1,50. There is no water in the
slope.
Solution
For solving this problem, we will use the GEO5 program, Slope stability. In this text,
we will explain each step to solve this problem:
In the frame Settings click on Select and choose option nr. 1 Standard safety
factors.
Then model the interface layers, resp. terrain using these coordinates:
Then, input the geological profile, define the parameters of soil, and assign them to the
profile.
or different parameters of soil in one direction - are not considered in the assigned soils.
Model the gravity wall as a Rigid Body with a unit weight of 23,0 kN m 3 . The slip
surface does not pass through this object because it is an area with large strength. (More
info in HELP F1)
In the next step, define a surcharge, which we consider as permanent and strip with
its location on the terrain surface.
Note: A surcharge is entered on 1 m of width of the slope. The only exception is concentrated
surcharge, where the program calculates the effect of the load to the analyzed profile. For
more information, see HELP (F1).
Then, in the frame Stage settings, select the design situation. In this case, we
consider it as Permanent design situation.
Now open up the frame Analysis, where the user enters the initial slip surface using
coordinates of the center ( x, y ) and its radius or using the mouse directly on the desktop
by clicking on the interface to enter three points through which the slip surface passes.
Note: In cohesive soils rotational slip surfaces occur most often. These are modeled using
circular slip surfaces. This surface is used to find critical areas of an analyzed slope. For non-
cohesive soils, an analysis using an polygonal slip surface should be also performed for slope
stability verification (see HELP F1).
Now, select Bishop as the analysis method, and then set type of analysis as
Optimization. Then perform the actual verification by clicking on Analyze.
Note: optimization consists in finding the circular slip surface with the smallest stability the
critical slip surface. The optimization of circular slip surfaces in the program Slope stability
evaluates the entire slope, and is very reliable. For different initial slip surfaces, we get the
same result for a critical slip surface
The level of stability defined for critical slip surface when using the Bishop evaluation
method is satisfactory :
Analysis 2:
Now select another analysis on the toolbar in upper right corner of your Analysis
frame in GEO5.
Toolbar Analysis
Note: Using this procedure, the slip surface made for all methods corresponds to critical slip
surface from the previous analysis scenario using the Bishop method. For better results the
user should choose the method and then perform an optimization of slip surfaces.
Note: the selection of method of analysis depends on experience of the user. The most
popular methods are the method of slices, from which the most used is the Bishop method.
The Bishop method does yield conservative results.
For reinforced or anchored slopes other rigorous methods (Janbu, Spencer and Morgenstern-
Price) are preferable. These more rigourous methods meet all conditions of balance, and they
better describe real slope behaviour.
It is not needed (or correct) to analyze a slope with all methods of analysis. For example, the
Swedish method Fellenius Petterson yields very conservative results, so the safety factors
could be unrealistically low in the result. Because this method is famous and in some
countries required for slope stability analysis, it is a part of GEO5 software.
In the last step of analysis, input the polygonal slip surface. As a method of analysis,
select Spencer, as analysis type select optimization, enter a polygonal slip surface and
perform the analysis.
Note: Optimization of a polygonal slip surface is gradual and depends on the location of the
initial slip surface. This means that it is good to make several analyses with different initial
slip surfaces and with different numbers of sections. Optimization of polygonal slip surfaces
can be also affected by local minimums of factor of safety. This means the real critical
surface does need to be found. Sometimes it is more efficient for the user to enter the
starting polygonal slip surface in a similar shape and place as an opitimised circular slip
surface.
Note: We often get complaints from users that the slip surface after the optimization
disappeared. For non-cohesive soils, where cef 0 kPa the critical slip surface is the same
as the most inclined line of slope surface. In this case, the user should change parameters of
the soil or enter restrictions in which the slip surface cant pass.
Conclusion
SATISFACTORY
Spencer (polygonal - optimization): SF 1,58 SFs 1,50
SATISFACTORY
This designed slope with a gravity wall satisfies stability requirements.
In this chapter, we are going to describe the stability analysis of an existing slope, then how
to model a sheeting wall being built, and how to check its internal and external stability.
Assignment:
Perform an analysis of an existing slope and then verify the design of an underground
wall for construction of parking areas. When performing the analysis, consider the
permanent design situation in all construction stages. Verify the stability using safety factors.
The safety factor needed is SFs 1,50 . All stability analyses are peformed using the Bishop
Scheme of assignment
The wall is made from concrete class C 30/37, the thickness of the wall is h 0,5 m .
Solution:
For solving this task, use the GEO5 program Slope Stability. In this text, we will describe the
solution of this task step by step.
In the frame Settings, click on Select and then choose analysis settings nr. 1
Standard safety factors.
Then, model the interface of layers, resp. terrain using these coordinates.
Interface coordinates
Note: If data is entered incorrectly, it can be undone using the button UNDO (shortcut Ctrl-
Z). In the same manner,we can use the opposite function REDO (Shortcut Ctrl-Y).
Then define the soil parameters and assign them to the profile.
Now open up the frame Analysis and run the verification of stability of the original
slope. As a verification method select Bishop and then perform the optimization of circular
slip surface. How to input slip surface and optimization principle is described in more detail
in the previous chapter and in HELP (F1).
Frame Embankment
Analysis 2 internal stability of retaining wall
Now return to the 1st construction stage and add a new soil with name Material of
the retaining wall. Define the value of the ficticious cohesion as cef 650 kPa , the angle of
internal friction as a small value (for example ef 1 ) since the program doesnt allow to
Analysis 3 slope stability behind the earth cut and retaining wall (internal stability)
The analysis results of internal stability show that the slope with the earth cut and
the retaining wall is stable:
Before running the analysis of the external slope stability, add restrictions on the
optimization procedure using lines that the slip surface cant intersect when it executes the
optimization procedure (More info in HELP F1). In our example the restriction lines are the
same as the borders of the pile sheeting.
Note: for analysis of external slope stability it is appropriate to input the retaining wall as a
solid body. When the wall is modeled as a solid body, the slip surface doesnt intersect it
during the optimization evaluation.
From the results of external stability we can see, that the slope with the earth cut
and retaining wall is stable:
Conclusion
The objective of this chapter was to verify the slope stability and design of earth cut
with retaining wall for the construction of a car park with ananalysis of internal and external
stability. The results of analyses are:
This slope with earth cut and retaining wall from concrete (with width of 0,5 m) in terms of
long-term stability satisfies evaluation criteria.
For the same bending moment it is also necessary to design and check reinforcements for
example in program FIN EC Concrete 2D.
In this chapter, we are going to show you how to design spread footing easily and effectively.
Assignment:
Using EN 1997-1 (EC 7-1, DA1) standards, design the dimensions of a concentric spread
footing. Forces from columns act on the top of foundation. Input forces are: N , H x , H y , M x , M y .
The terrain behind the structure is horizontal; foundation soil consists of S-F Sand with trace of
fines, medium dense soil. At 6,0 m is Slightly weathered slate. The GWT is also at a depth of 6,0 m.
The depth of foundation is 2,5 m below the original terrain.
Solution
For solving this problem, we will use the GEO5 program Spread footing. Firstly, we input all
the data in each frame, except Geometry. In the Geometry frame, we will then design the spread
footing.
In the frame Settings, click on Select and then choose nr. 3 Standard EN 1997
DA1.
Also select an analysis method in this case Analysis for drained conditions. We will not
analyze settlement.
Frame Settings
Note: Usually, spread footings are analyzed for drained conditions= using the effective parameters of
soil ( ef , cef ). Analysis for undrained conditions is performed for cohesive soils and short-term
performance using total parameters of soil ( u , cu ). According to EN 1997 total friction considered is
always u 0 .
In the next step enter the geological profile, soil parameters and assign them to the profile.
In the next step, open up the frame Foundation. As a type of foundation, choose Centric spread
footing and fill in the dimensions such as depth from the original grade, depth of footing bottom,
thickness of foundation and inclination of finished grade. Also, input the weight of overburden, which
is the backfill of spread footing after construction.
Frame Foundation
Note: The depth of the footing bottom depends on many different factors such as natural and climatic
factors, hydrogeology of the construction site and geological conditions. In the Czech Republic the
depth of footing bottom is recommended to be at least 0,8 meters beneath the surface due to
freezing. For clays it is recommended that the depth be greater, such as 1,6 meters. When analyzing
the bearing capacity of a foundation, the depth of the foundation is considered as the minimal
vertical distance between the footing bottom and the finished grade.
Frame Load
Note: For design of dimensions of spread footing, generally the design load is the deciding load. ,
However, in this case we are using the analysis settings EN 1997-1 - DA1, and you must enter the
value of service load too, because the analysis requires two design combinations.
Note: Surcharge around the foundation influences the analysis for settlement and rotation of the
foundation, but not bearing capacity. In the case of vertical bearing capacity it always acts favorably
and no theoretical knowledge leads us to analyze this influence.
In the frame Water enter the ground water depth as 6,0 meters.
Then open up the frame Stage settings and select permanent as the design situation.
Now, open the frame Geometry and apply the function Dimensions design; with which
the program determines the minimum required dimensions of the foundation. These dimensions can
be edited later.
In the dialog window it is possible to input the bearing capacity of foundation soil Rd or select
Analyze. We will chose Analyse for now. The program automatically analyzes the foundation
weight and weight of soil below foundation and determines the minimum dimensions of the
foundation.
Note: Design of centric and eccentric spread footing is always performed such that that the
dimensions of foundation are as small as they can be and still maintain an adequate vertical bearing
capacity. The option Input designs the dimensions of a spread footing based on the entered
bearing capacity of the foundation soil.
Conclusion:
The bearing capacity of designed foundation (2,0x2,0 m) is satisfactory.
In this chapter, we describe how analysis of settlement and rotation of a spread footing is
performed.
Assignment:
Analyze the settlement of centric spread footing designed in last chapter (10. Design
of dimensions of spread footing). The geometry of the structure, load, geological profile and
soils are the same as in the last chapter. Perform the settlement analysis using the
oedometric modulus, and consider the structural strength of soil. Analyze the foundation in
terms of limit states of serviceability. For a structurally indeterminate concrete structure, of
which the spread footing is a part, the limiting settlement is: sm,lim 60,0 mm.
For solving this task, we will use the GEO5 program Spread footing. We will use the
data from the last chapter, where almost all required data is already entered.
Basic Input:
The design of spread footing in the last task was performed using the standard EN
1997, DA1. Eurocodes do not order any theory for the analysis of settlement, so any
common settlement theory can be used. Check the setting in the frame Settings by clicking
on Edit. In the tab Settlement select the method Analysis using oedometric modulus
and set Restriction of influence zone to based on structural strength.
Note: The structural strength represents the resistance of a soil against deformation from a
load. It is only used in Czech and Slovak Republic. In other countries, the restriction of the
influence zone is described by percentage of Initial in-situ stress. Recommended values of
structural strength are from CSN 73 1001 standards (Foundation soil below the foundation)
In the next step, define the parameters of soils for settlement analysis. We need to
edit each soil and add values for Poissons ratio, coefficient of structural strength and
oedometric modulus, resp. deformation modulus.
Analysis:
Now, run the analysis in the frame Settlement. Settlement is always analyzed for
service load.
- Initial in-situ stress in the footing bottom is considered from the finished grade
Note: the value of in-situ stress in the footing bottom has influence on the amount of
settlement and the depth of influence zone a larger initial in-situ stress means less
settlement. The option of in-situ stress acting on the footing bottom depends on the time the
footing bottom is open. If the footing bottom is open for a longer period of time, the soil
compaction will be less and it is not possible to consider the original stress conditions of the
soil.
Note: the coefficient 1 reflects the influence of the depth of the foundation and gives more
realistic results of the settlement
Results of analysis
The final settlement of the structure is 16,9 mm. Within an analysis of limit states of
serviceability we compare the values of the analyzed settlement with limit values, which are
permissible for the structure.
Note: The stiffness of structure (soil-foundation) has a major influence on the settlement.
This stiffness is described by the coefficient k if k is greater then 1, the foundation is
considered to be stiff and settlement is calculated under a characteristic point (located in
0,37l or 0,37b from the center of the foundation, where l and b are dimensions of
foundation). If coefficient k is lower then 1, the settlement is calculated under the center of
foundation.
The Spread footing program also provides results for the rotation of the foundation, which is
analyzed from the difference of settlement of centers of each edge.
Conclusion
Frame "Settings"
Then we enter the layer interface. The objective is to select two layers between
which the consolidation takes place.
Frame "Interface"
The soil parameters are entered in the next step. For soils being consolidated, it is
required to specify either the coefficient of permeability " k " or the coefficient of
consolidation " c v ". Approximate values can be found in HELP (F1).
Then we assign the soils to the profile. The frame surcharge in the 1st construction
stage is not taken into consideration, since in this example it will be represented by the
actual embankment body (in stages 2 to 5). In the next step, we shall enter the ground water
table (hereinafter the "GWT") using the interface points, in our case at ground level.
In the frame Stage settings, you can only modify layout and refinement of holes, so
leave the standard settings.
The first "Calculation" stage represents the initial geostatic stress at the initial
construction time. However, it is necessary to specify the basic boundary conditions for the
consolidation calculation in further stages. The top and bottom interface of the
consolidating soil is entered, as well as the direction of water flow from this layer i.e. the
drainage path.
Note: The embankment acts as a surcharge to the original ground surface. It is assumed
that a well-executed (optimally compacted) embankment theoretically does not settle. In a
In the "Analysis" frame enter the time duration of the 2nd stage corresponding
to the actual embankment construction time. The actual calculation of the settlement
cannot be performed yet because, when determining consolidation, it is first necessary to
know the whole history of the earthwork structure loading, i.e. all construction stages.
Since the embankment is built gradually, we are considering the linear load growth
in the 2nd construction stage. In subsequent stages, the duration of the stage is entered (1
year i.e. 365 days 3rd stage, 10 years i.e. 3,650 days 4th stage and the overall settlement
5th stage) and the whole loading is introduced at the beginning of the stage.
The calculations are performed after enter the last construction stage, which is on
the "Overall settlement", is turned on (you can check it at any stage apart from the first
one).
Conclusion:
The embankment settlement (under its centre) within one year from its construction
is 84.5 mm (= 113.7 29.2) and after ten years 282.5 mm (= 311.7 29.2).