CP pre commissioning testing Sche

Feb-17
Activity
14 15 16 17 18 19 20 21
Pre commissioning tests Zone for cooling tower/Sump no
S6,S7,S8,S9,S10,S11,S12,S13,S14
1) Continuity between system H1.H2.H3.H4.H5.H6.H7
positive output and anode feeders H8.H9.H10.H11.H12.H13.H14
2) Continuity check between system H15.H16.H17.H18.H19.H20.H21 Friday
negatives H22.H23.H24.H25.H26.H27.H28
3) Continuity of system negative H29.H30.H31.H32.H33.A1.A2
between separate anode zones. A3,A4,A5,A6,A7,A8,A9,A10
4) Discontinuity check between
A11,A12,A13,A14,A15
positive and negative circuits.
5) Reference electrode base potential Sump 370-W-1040
and polarity checks Sump 310-V-5050
6) Natural potential of CP system first Sump 320-V-5056
time Sump 330-V-5053
Sump 340-SU-9001
Sump 350-V-5052
B1,B2,B3,B4,B5,
B6,B7,B8,B9,B10,B11,B12
S1,S2,S3,S4,S5
S6,S7,S8,S9,S10,S11,S12,S13,S14
H1.H2.H3.H4.H5.H6.H7
H8.H9.H10.H11.H12.H13.H14
H15.H16.H17.H18.H19.H20.H21
H22.H23.H24.H25.H26.H27.H28
Natural potentional after 7 days H29.H30.H31.H32.H33.A1.A2
A3,A4,A5,A6,A7,A8,A9,A10
A11,A12,A13,A14,A15
Sump 370-W-1040
Sump 310-V-5050
Sump 320-V-5056
Sump 330-V-5053
Sump 340-SU-9001
Sump 350-V-5052

Note: If potential difference recorded on 75% of the cells after 7 days differ by more than 50mV from
if the deviation is not more than 50mv then we can power up the TR for all the zones
missioning testing Schedule for ibn sina POM project
Mar-17
22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11

Friday

Friday

7 days differ by more than 50mV from those at reading taken at first time the system be left to cure for another 7 days because curing has not stabilized
er up the TR for all the zones
12 13