You are on page 1of 4

203: ABS-CBN vs CA Clearly, there was no acceptance of VIVA's offer, for it was met

FACTS: by a counter-offer which substantially varied the terms of the


In 1990, ABS-CBN and VIVA executed a Film Exhibition offer. Even if it be conceded arguendo that Del Rosario had
Agreement whereby the latter gave the former an exclusive accepted the counter-offer, the acceptance did not bind VIVA,
right to exhibit 24 VIVA Films for TV telecast. Later, VIVA, as there was no proof whatsoever that Del Rosario had the
through respondent Vincent del Rosario, offered ABS-CBN a specific authority to do so.
list of 3 film packages (36 titles) from which the latter may
exercise its right of first refusal under their agreement. ABS- 204: PALATTAO vs CA
CBN ticked off 10 titles therefrom. Facts:

Thereafter, in February 1992, Del Rosario offered ABS-CBN When respondent's lease contract expired, he filed an action
airing rights over a package of 104 movies for P60 million. In for specific performance to enforce his alleged right to
April, 1992, Del Rosario, and Eugenio Lopez of ABS-CBN, met purchase the property. Pending negotiations for an amicable
at a restaurant to discuss the package proposal. According to settlement, the trial court issued a status quo order. Unable to
Lopez, however, what they agreed upon was ABS-CBN's reach an amicable settlement, petitioner-lessor subsequently
exclusive film rights to 14 films for P36 million. Del Rosario filed an ejectment case against the respondent on the ground
denied the same. He insisted that the discussion was on of expiration of the period of the lease contract. Respondent
VIVA's offer of 104 films for P60 million, to which ABS-CBN refused to vacate the leased premises claiming that there was
later made a counter proposal but rejected by VIVA's Board of a perfected contract of sale of the leased property. He also
Directors. Hence, VIVA later granted RBS the exclusive right to contended that the filing of the ejectment case violated their
air the 104 VIVA films, including the 14 films supposedly agreement to maintain the status quo. The MTC rendered a
granted to ABS-CBN. decision in favor of petitioner and ordered respondent to
vacate the property. The RTC and CA, however, reversed the
ISSUE: decision.
WON there was a perfected contract between VIVA and ABS-
CBN with regards to offer made by VIVA on Feb. 1992. On appeal, the Supreme Court held that the status quo applied
only during the period of negotiations for an amicable
RULING: settlement, not for the duration of the pendency of the specific
NO. Absence of the requisites to make a valid contract. performance case; that an injunction suit and/or specific
performance case cannot preclude the filing of, or abate, an
A contract is a meeting of minds between two persons whereby ejectment case; that there are no "strong reason of equity" to
one binds himself to give something or to render some service sustain the suspension or dismissal of the ejectment case; that
to another 37 for a consideration. There is no contract unless no contract of sale was perfected because the parties failed to
the following requisites concur: (1) consent of the contracting agree on the extent of the lot subject of the proposed sale; and
parties; (2) object certain which is the subject of the contract; that even assuming, that they did agree, there was
and (3) cause of the obligation, which is established. 38 A subsequently a mutual withdrawal from the contract because
contract undergoes three stages: respondent failed to pay the downpayment and did not insist
(a) preparation, conception, or generation, which is the on the sale of the subject lot.
period of negotiation and bargaining, ending at the
moment of agreement of the parties; Ruling:
(b) perfection or birth of the contract, which is the moment
when the parties come to agree on the terms of the Contracts that are consensual in nature, like a contract of sale,
contract; and are perfected upon mere meeting of the minds. Once there is
(c) consummation or death, which is the fulfillment or concurrence between the offer and the acceptance upon the
performance of the terms agreed upon in the contract. 39 subject matter, consideration, and terms of payment, a contract
Contracts that are consensual in nature are perfected upon is produced. The offer must be certain. To convert the offer into
mere meeting of the minds. Once there is concurrence a contract, the acceptance must be absolute and must not
between the offer and the acceptance upon the subject matter, qualify the terms of the offer; it must be plain, unequivocal,
consideration, and terms of payment a contract is produced. unconditional, and without variance of any sort from the
The offer must be certain. To convert the offer into a contract, proposal. A qualified acceptance, or one that involves a new
the acceptance must be absolute and must not qualify the proposal, constitutes a counter-offer and is a rejection of the
terms of the offer; it must be plain, unequivocal, unconditional, original offer. Consequently, when something is desired which
and without variance of any sort from the proposal. A qualified is not exactly what is proposed in the offer, such acceptance is
acceptance, or one that involves a new proposal, constitutes a not sufficient to generate consent because any modification or
counter-offer and is a rejection of the original offer. variation from the terms of the offer annuls the offer. In the
Consequently, when something is desired which is not exactly case at bar, while it is true that private respondent informed
what is proposed in the offer, such acceptance is not sufficient petitioner that he is accepting the latter's offer to sell the leased
to generate consent because any modification or variation from property, it appears that they did not reach an agreement as to
the terms of the offer annuls the offer. the extent of the lot subject of the proposed sale. Clearly,
therefore, private respondent's acceptance of petitioner's offer
When Mr. Del Rosario of VIVA met with Mr. Lopez of ABS-CBN was not absolute, and will consequently not generate consent
at the Tamarind Grill on 2 April 1992 to discuss the package of that would perfect a contract.
films, said package of 104 VIVA films was VIVA's offer to ABS-
CBN to enter into a new Film Exhibition Agreement. But ABS- 205: National Commercial Bank of Saudi Arabia vs CA
CBN, sent, through Ms. Concio, a counter-proposal in the form Facts:
of a draft contract proposing exhibition of 53 films for a
consideration of P35 million. This counter-proposal could be As the case has been pending for more than nineteen years,
nothing less than the counter-offer of Mr. Lopez during his this Court ordered the trial court (Regional Trial Court of Makati
conference with Del Rosario at Tamarind Grill Restaurant. City) and the Court of Appeals to elevate all the records of the
case for final resolution. Upon this Court's directive, petitioner merely alleged that they were forced to restructure their loan
National Commercial Bank of Saudi Arabia and the for fear of having their mortgaged properties foreclosed.
Metropolitan Bank and Trust Co., Inc. (successor of movant However, it is axiomatic that this would not amount to vitiated
respondent Philippine Banking Corporation) filed their consent. The last paragraph of Article 1335 of the New Civil
memoranda. On December 7, 2004, the parties, through their Code specifically states that a threat to enforce ones claim
respective counsels, filed a joint motion before this Court for through competent authority, if the claim is just or legal, does
approval of an undated compromise agreement which was not vitiate consent. Foreclosure of mortgaged properties in
executed for the purpose of ending the longstanding litigation. case of default in payment of a debtor is a legal remedy
afforded by law to a creditor. Hence, a threat to foreclose the
Issue: mortgage would not, per se, vitiate consent.
The new promissory note is a contract of adhesion. It is so-
WON Compromise Agreement is valid called because its terms are prepared by only one party while
the other party merely affixes his signature signifying his
Ruling: adhesion thereto. They are not invalid per se; they are not
entirely prohibited. The one who adheres to the contract is in
Under Article 1306 of the Civil Code, contracting parties may reality free to reject it entirely; if he adheres, he gives his
establish such stipulations, clauses, terms and conditions as consent.
they may deem convenient, provided they are not contrary to
law, morals, good customs, public order, or public policy. Thus, 207: Archbishop Fernando R. Capalla, etc. vs COMELEC
a compromise agreement whereby the parties make reciprocal Winning bidder is not precluded from modifying or
concessions to resolve their differences to thereby put an end amending certain provisions of the contract bidded upon.
to litigation is binding on the contracting parties and is However, such changes must not constitute substantial or
expressly acknowledged as a juridical agreement between material amendments that would alter the basic parameters of
them. To be valid, the compromise agreement must be based the contract and would constitute a denial to the other bidders
on real claims and actually agreed upon in good faith. Both of the opportunity to bid on the same terms.
conditions are present in the case at bar. In clear, categorical
language, each of the parties have manifested their desire, by Facts:
forging the Compromise Agreement, to abbreviate the legal Pursuant to its authority to use an Automated Election System
battle and settle the case amicably to both their satisfaction. As (AES), the Commission on Elections (COMELEC) posted and
the Agreement is not contrary to law, public order, public policy, published an invitation to apply for eligibility and to bid for the
morals or good customs, the same is hereby approved 2010 Poll Automation Project. COMELEC awarded the contract
for the project to respondent Smartmatic-TIM. Thereafter,
206: Development Bank of the Philippines vs Perez COMELEC and Smartmatic-TIM entered into a Contract for the
Provision of an Automated Election System for the May 10,
DBP sent a letter to Bonita Perez, informing the latter 2010 Synchronized National and Local Elections (AES
of the approval of an industrial loan amounting to P214,000.00. Contract, for brevity). The contract between the COMELEC
The respondents were made to sign four promissory notes and Smartmatic-TIM was one of lease of the AES with option
covering the total amount of the loan, P235,000.00. Three to purchase (OTP) the goods listed in the contract. In said
promissory notes for P24,000.00, P48,000.00, and contract, the Comelec was given until December 31, 2010
P142,000.00, respectively, were executed, totaling within which to exercise the option. In a letter, Smartmatic-TIM,
P214,000.00. These promissory notes were all due on August through its Chairman Cesar Flores (Flores), proposed a
31, 1988. A fourth promissory note due on September 19, 1988 temporary extension of the option period to buy the PCOS
was, likewise, executed to cover the additional loan of machines until March 31, 2011. The COMELEC did not
P21,000.00. The promissory notes were to be paid in equal exercise the option within the extended period. Several
quarterly amortizations and were secured by a mortgage extensions were given for the COMELEC to exercise the OTP
contract covering real and personal properties. On September until its final extension on March 31, 2012. On March 29, 2012,
6, 1978, the petitioner sent a letter to the respondents the COMELEC issued a resolution resolving to accept
informing them of the terms for the payment of the Smartmatic-TIMs offer to extend the period to exercise the
P214,000.00 industrial loan. On November 8, 1978, the OTP until March 31, 2012. Archbishop Capalla, et al. thus
petitioner sent another letter to the respondents informing them assailed the validity and constitutionality of the COMELEC
about the terms and conditions of their additional P21,000.00 Resolutions for the purchase of the subject PCOS machines as
industrial loan. Due to the respondents' failure to comply with well as the Extension Agreement and the Deed of Sale
their amortization payments, the petitioner decided to foreclose covering said goods mainly on the ground that the option
the mortgages that secured the obligation. However, in a Letter period provided for in the AES contract between the
dated October 7, 1981, Mrs. Perez requested for a COMELEC and Smartmatic-TIM had already lapsed and, thus,
restructuring of their account due to difficulties they were could no longer be extended, such extension being prohibited
encountering in collecting receivables. The restructuring of by the contract.
their accounts was approved. The loan was restructured, and ISSUE:
the respondents signed another promissory note in the amount Whether or not the unilateral extension of the option period
of P231,000.00 at 18% interest per annum, payable quarterly, which Smartmatic-TIM granted to COMELEC and which the
over a period of ten years. latter accepted constitutes circumvention of the law on public
Issue: bidding. No
WON the new promissory note is voidable for not having been HELD:
voluntarily signed by the respondents and for being a contract It is a basic rule in the interpretation of contracts that an
of adhesion instrument must be construed so as to give effect to all the
Held: provisions of the contract. In essence, the contract must be
No. There was no evidence showing that the respondents read and taken as a whole. While the contract indeed
signed the new promissory note through mistake, violence, specifically required the COMELEC to notify Smartmatic-TIM of
intimidation, undue influence, or fraud. The respondents its OTP the subject goods until December 31, 2010, a reading
of the other provisions of the AES contract would show that the Laguna Bus Company and Batangas Transportation Company
parties are given the right to amend the contract which may refused to pay and even demanded that their rentals be
include the period within which to exercise the option. There is, reduced since they can hardly pay the rentals on the leased
likewise, no prohibition on the extension of the period, provided premises.
that the contract is still effective. Issues: WON the lessees (LBC and BTC) may be given a
Considering, however, that the AES contract is not an ordinary reduction of rent
contract as it involves procurement by a government agency,
the rights and obligations of the parties are governed not only Ruling:
by the Civil Code but also by RA 9184. In this jurisdiction, No.
public bidding is the established procedure in the grant of We are not at all convinced that the lease contract brought no
government contracts. The award of public contracts, through material advantage to the lessor for the period of suspension. It
public bidding, is a matter of public policy. The parties are, must be recalled that the lease contract not only stipulated for
therefore, not at full liberty to amend or modify the provisions of the transfer of the lessor's right to operate the lines covered by
the contract bidded upon. A winning bidder is not precluded the contract, but also for a forbearance on the part of the lessor
from modifying or amending certain provisions of the contract to operate transportation business along the same lines and
bidded upon. However, such changes must not constitute to hold a certificate for that purpose. Thus, even if the lessee
substantial or material amendments that would alter the basic would not actually make use of the lessor's certificates over the
parameters of the contract and would constitute a denial to the leased lines, the contractual commitment of the lessor not to
other bidders of the opportunity to bid on the same terms. The operate on the lines would sufficiently insure added profit to the
determination of whether or not a modification or amendment lessees on account of the lease contract. In other words, the
of a contract bidded out constitutes a substantial amendment commitment alone of the lessor under the contract would
rests on whether the contract, when taken as a whole, would enable the lessees to reap full benefits therefrom since the
contain substantially different terms and conditions that would commuting public would, after all, be forced at their
have the effect of altering the technical and/or financial inconvenience and prejudice to patronize petitioner's
proposals previously submitted by the other bidders. The remaining buses.
modifications in the contract executed between the
government and the winning bidder must be such as to render 209: National Marketing Corp vs. Alias Development Corp
the executed contract to be an entirely different contract from
the one bidded upon. Smartmatic-TIM was not granted Facts:
additional right that was not previously available to the other On July 21, 1948, defendant Atlas offered to sell to
bidders. Admittedly, the AES contract was awarded to the plaintiff 8,000 metric tons of galvanized sheets at the price
Smartmatic-TIM after compliance with all the requirements of a of U.S. $247 per ton of 1,000 kilos, to be shipped beginning
competitive public bidding. Although the AES contract was August, 1948.
amended after the award of the contract to Smartmatic-TIM, On July 24, 1948, the plaintiff made an order and
the amendment only pertains to the period within which the agreed to purchase the galvanized sheets offered by
COMELEC could exercise the option because of its failure to defendant Atlas with the condition that the seller should furnish
exercise the same prior to the deadline originally agreed upon a performance bond in favor of the plaintiff in the amount of
by the parties. Hence, the amendment of the AES contract is P100,000.00;
not substantial. More importantly, the amendment of the AES On August 5, 1948, the plaintiff and defendant Atlas
contract is more advantageous to the Comelec and the public (sales broker for West India Commercial Corp. of New York
City, N.Y., U.S.A.) executed a contract of purchase and sale
208: LTB vs. Manabat wherein the said defendant obligated itself to sell 8,000 metric
tons of galvanized steel sheets, at the price of U.S. $247 per
Facts: On January 20, 1956, a contract was executed whereby ton of 1,000 kilos;
the Bian Transportation Company leased to the Laguna- Under the aforementioned contract, defendant Atlas
Tayabas Bus Company at a monthly rental of P2,500.00 its obligated itself to furnish in favor of Pratra (who?) a
certificates of public convenience over the lines known as performance bond in the sum of P100,000.00 to guarantee the
Manila-Bian, Manila-Canlubang and Sta. Rosa-Manila, and to faithful compliance of all the terms and conditions of the said
the Batangas Transportation Company its certificate of public contract, with defendant Alto as surety;
convenience over the line known as Manila-Batangas Wharf, In compliance with its undertakings in the contract,
together with one 'International' truck, for a period of five years, the plaintiff on August 26, 1948, opened a letter of credit with
renewable for another similar period, to commence from the the Philippine National Bank for the amount of U.S.
approval of the lease contract by the Public Service $1,976,000.00 in favor of the West India Commercial Corp. of
Commission. On the same date the Public Service New York, United States.
Commission provisionally approved the lease contract on Defendant and West India Corp failed to deliver the
condition that the lessees should operate on the leased lines in 8,000 galvanized sheets.
accordance with the prescribed time schedule and that such
approval was subject to modification or cancellation and to Issues: WON the non-delivery of defendant is justifiable
whatever decision that in due time might be rendered in the
case. Ruling:
Sometime after the execution of the lease contract, the plaintiff
Bian Transportation Company was declared insolvent. Yes. There is a New York Supreme Court decision to
Plaintiff Bian Transportation Company, represented by the effect that a "material variance between the letter of credit
Francisco C. Manabat, then filed this action against defendants and the sales agreement would excuse non-performance by
Laguna Tayabas Bus Company and Batangas Transportation the seller.
Company for the recovery of the sum of P42,500 representing No liability was incurred under the contract of purchase and
the accrued rentals for the lease of the certificates of public sale because of such failure to make the delivery. Such being
convenience of the former to the latter, corresponding to the the case, the question of whether or not defendant Atlas, which
period from January, 1958, to May, 1959.
acted as a sales broker, could be held liable for the alleged
breach need not be passed upon.

You might also like