You are on page 1of 4

LIFTING PLAN METHOD & RISK ASSESSMENT

Project BG new Administration Building Project Date 15\1\2013


Site/location BG building Client BG Egypt
Document Ref. LP 002 / / Rev Issued by Mivan Limited
Appointed Person carrying
Eng / Mohamed Ali Date of Assessment: 10\1\2013
out the Assessment:
Contact: HSE officer Phone: 01021998033 Fax:
Site contact: Site engineer Phone: 010012471115 Fax:
Description of lift:
NB 50% reduction in load capability if man basket is used.
Details of Loads Load Position 1 Load Position 2 Load Position 3
Weight: 10000 kg
Dimensions: 7mX25cmX225cm
Height of lift (worst case only): 27m
Max. radius (worst case only): 30m
Date of lift: 10 Jun 2013
Time of lift: 10 AM

Details of Cranes 1st 2nd 3rd


Make & model: Liebherr
Capacity: 250tons
Boom length: 60m
Outrigger spread: 9.8 meter
Outrigger load: N.A
Max. ground bearing capacity: N.A
Counterweight: 100ton
Weight of crane: 170ton

Alternative Crane Details


Make & model:
Capacity:
Jib length:
Outrigger spread:
Outrigger load:
Max. ground bearing capacity:
Counterweight:
Weight of crane:

Ground Conditions (Visual assessment)


Access/Egress for crane & good
transport:
Lifting position: good
Lifting Accessories
Slings (wire rope): good Slings (webbing): N/A
Slings (chains): good Shackles: good
Other Accessories: good

Identification of Hazards

Proximity Hazard Present? Proximity Hazard (cont.) Present?


Overhead power lines X Other hazards identified X
Other overhead obstacles X
Underground services X
Excavations X Load Hazard Present?
Unstable/ Soft ground X Slinging difficulties X
Hazardous chemicals/materials X Top heavy X
Confined working area X Sharp edges X
Restricted access - width X Other hazards identified X
Restricted access - height X
Other vehicles X

Assessment of Risk

Hazard Harm Recommended Control

1. Crush injuries. 1. PPE and equipment for job in hand.


1. Falling loads. 2. Minor cuts and abrasions
to fatalities
2. Runaway loads 2. Correct tools and equipment Ensure that the
lifting equipment being used has the capacity to
3. Snapping of ropes, chains or carry the load being
webbing straps Lifted. If no reliable information is available as to
the weight of the load, always err on
the side of safety when estimating the weight of the
load
3. Lifting equipment must be handled with respect.

4. Check for signs of mechanical damage to slings,


straps, chains, hooks etc before use.

5. Ensure the load can be held in check as required


to prevent unnecessary swinging or runaway of the
load

6. Always consider the position of other people and


warn them before lifting the load.

7. Ensure work area suitably cleared and warning


signs posted as required.

Collapses the crane or falling Persons injuries Clear weather is required and permissible wind
load during work in a bad speed.
Weather

Operational Requirements:

Site Provisions:

1- Stopped work in this area


2- Specified two flag men in this area
Notes

1. We will use 4 legged chains for lift the load from the ground to the roof
3- Weather conditions, ground conditions, nearby water sources etc.
Clear weather is required and permissible wind speed.
4-Details of communication system between crane operator, slinger/ signaller, crane co-ordinator etc.
Radio communication
5- Test and thorough examination.
The lifting accessories certificate is attached.
6- Control of loads.
By using two robs tied in two opposite side

Method Statement

Responsibilities
Infrastructure project will undertake the responsibilities for the management of this lifting operation as
defined in the OSHA Standard for the lifting and movement of goods involving crane operation.

Personnel
Infrastructure project will provide the following personnel complete with relevant personal protective
equipment. The duties of these people will be as defined in OSHA Standard:-

Title Name Title Name


Appointed Slinger(s)
Person
Crane Signaller(s)
Supervisor
Crane Driver(s) Mohamed Ali Mohamed Crane Erectors

Note: The appointed person may decide that one person can carry out more than one duty. This
does not however, include the crane driver who must concentrate on operating the crane.
Weather Conditions
The Appointed Person or, in his absence, the Crane Supervisor, will ensure that the lifting operation only
takes place if the weather conditions are within the limits recommended by the crane manufacturer. 3
day weather forecast.

Ground Conditions

Have assurances been obtained that the ground can withstand the load? Yes/No
Sequence of Operations

1 The work place is .prepared for the mobile crane.

Uploading the shriller unit from the ground by using lifting bar and lift it to the roof by crane
2

Appointed Persons Acceptance of Responsibilities

I confirm that the lifts have been planned and will be carried out in Signed:
accordance with OSHA Standard and that I accept responsibility for
the preparation of this Risk Assessment and Method Statement.
Date:

Crane Supervisors Acceptance of Duties

I confirm that I have been fully briefed on the contents of this Risk Signed:
Assessment and Method Statement and that I accept the duty of
ensuring that the lift(s) will be carried out in accordance with the
method and procedures set out in this document. Date: