Rev. : A
Page : 1/5
OPERATION AND MAINTENANCE GUIDE
OPERATION GUIDE
3.2.2. START-UP
1. Initial conditions
In the following example (typical), the unit is provided with an automatic synchro-
device.
The machine is in the cooldown mode and the hydraulic ratchet is in automatic
operation every 3 minutes. All is ready for a future start-up. The start-up sequence will
be made in automatic mode.
All devices are in good condition, the water, oil, fuel levels are within the limits, the
battery is charged, the oil temperature above 10C. There is no alarm on the CRT.
All electric motors are ready to start on automatic order (isolators closed), the control
circuits supplied, the turbine shaft at rest.
Rev. : A
Page : 2/5
OPERATION AND MAINTENANCE GUIDE
OPERATION GUIDE
2.Start-up (typical sequence with diesel starting mean and gas fuel)
TURBINE IN
STANDBY
AUTO SELECTED
START ORDER
LUBE OIL PUMP RATCHETTING : 88 20 CS ENERGIZED
STARS : 88QA HR
FLAME DETECTION :
28FD
Rev. : A
Page : 3/5
OPERATION AND MAINTENANCE GUIDE
OPERATION GUIDE
(A)
GENERATOR BREAKER
CLOSES 52G
POWER GENERATION
Rev. : A
Page : 4/5
OPERATION AND MAINTENANCE GUIDE
OPERATION GUIDE
3. Shutdown (typical sequence with diesel starting mean and gas fuel)
BASE LOAD TURBINE
GAS FUEL
STOP ORDER
TNR DECREASES
LOAD DECREASES
REVERSE POWER
DETECTED
14 HS SPEED LEVEL
DECREASING
14 HA SPEED LEVEL
IF REDUCING GEAR (14HM) SPEED LEVEL GAS FUEL VENT GAS FUEL STOP
COMPT. TEMP. LOW DECREASING SOLENOID VALVE
DEENERGISED (20VG) DEENERGISES
REDUCING GEAR FAN. (20FG)
MOTOR. STOPS (88VG) IF WHEELSPACE (14 HR) SPEED LEVEL
TURBINE COOLING AIR TEMP. LOM DETECTED DETECTED
FAN MOTOR STOPS L69 TWW
88BT (A)
Rev. : A
Page : 5/5
OPERATION AND MAINTENANCE GUIDE
OPERATION GUIDE
(A)
COOLDOWN
TIMER (62 CD)
STOP ORDER
TURBINE IN
STAND-BY