The Public Authority For Applied

Education & Training

Construction, Completion, Operation &


Maintenance of the Nursing Institute at
PAEET Shuwaikh Campus

Contract No. PA/AFA/112-2008/2009

Project Method Statement

Dar Al Hadiah Consultant Engineer

Real Estate Construction & Fabrication Co.


Contents

1. Introduction
1.1 Project Parties
1.2 Project Information
1.3 Project Components
1.4 Site Location
1.5 Site Staff Organization Chart
1.5a Organization Chart
1.5 b Job Description
2. Project Obstacles
3. Construction Strategy
1. Zoning Plans
2. Project Milestones & Constrains
3. Project Priorities
4. Construction Methodology
1. Methodology flow Chart
2. Procurement
3. Excavation, Shoring & Dewatering
4. Foundation
5. Basement walls & columns
6. Slab formwork circulation
7. Roofing system
8. Faade Finishes
9. Finishing Works & Electromechanical works
10. External Works
11. Authorities Approval, Testing & Commissioning
5. Site Logistics
6. Activity Coding & ID System
7. Productivity Rates

Real Estate Construction & Fabrication Co.


1-Introduction

1
Real Estate Construction & Fabrication Co.
1.1- Project Parties

Public Authority for Applied Education &


Owner
Training

Construction
Turner Projacs
Manager

Consultant Dar Al Hadiah Consultant Engineers

Contractor Real Estate Construction & Fabrication Co.

2
Real Estate Construction & Fabrication Co.
1.2- Project Information

Project Nursing Institute

Project Location PAAET Campus, Shuwaikh

730 Calendar days including all holidays from


Project Duration
date of enterprise

Project Value KD 6,930,000.000

3
Real Estate Construction & Fabrication Co.
1.3-Project Component
The project comprises the construction, completion & maintenance of the Nursing
Institute for The Public Authority For Applied Education & Training. The Project is
located at the south west side of PAAET Campus, Shuwaikh.
The project includes one building and external landscape, the Building consists of
Basement, Ground Floor, 1st Floor, 2nd Floor & Roof.
The area of each project component is as follows:
Basement area : Total area 8136.64 m2
Ground Floor Area : 8009.54 m2
First Floor Area : 7040 m2
Second Floor Area : 7040 m2
Roof Floor Area : 204 m2
The Basement will include the following:
Car park with a capacity of 104 cars.
A shelter area for peace time & war time. Upon completion it will be ready
to accommodate 100 person
Electric & Mechanical rooms for the pumps, generators, transformers,
water tanks and all major electromechanical equipments
The Ground Floor will include the Following:
Registration & students waiting area
Class rooms with capacity for 600 students
2 nos of Auditorium rooms for 240 students
Examination halls
Students book store
Studio
Dinning halls & central kitchen unit
2nos prayer rooms

4
Real Estate Construction & Fabrication Co.
The First & Second Floor will include the Following :
Staff rooms
Conference room
Technical Director Office
Class rooms for 860 students
Computer Class rooms
Nursing labs
Physics labs
Language labs
Biology labs
pharmacology labs
Chemistry labs.
General study halls with library
Instruction technology support unit
Research rooms
Video conference
Media presentation labs.
A Roof floor that will include 4 mechanical rooms.
External area that will include Infrastructure and landscape works such as
pavement tiles as well as parking lot area for 150 car and 12 busses

5
Real Estate Construction & Fabrication Co.
The Major Activities
The construction of the Nursing Institute Building, will generally comprises of the
following :
1. Site Clearance
2. Excavation, Shoring / Dewatering & Termite Control
3. Complete Structure works
4. Waterproofing works
5. Masonry works
6. Finishing works including interior & exterior finishes for floors, walls, ceiling
and wall partitions
7. Steel, wood & aluminum doors & windows frames, leaves and hardware.
8. Metal works
9. All MEP works
10. LPG Works
11. Electrical Equipment (Smart sys)
12. Kitchen Equipment
13. Furnishing
14. Signage (External & Internal)
15. Shelter works
16. Elevators
17. Faade (Concrete panels cladding, curtain wall)
18. External Works (Infrastructure services, Landscapes)

6
Real Estate Construction & Fabrication Co.
1.4- Site Location

Location of the Project


The Project (Nursing Institute) owned by the Public Authority of
Applied Education & Training (PAAET). The site is located at south
western corner of PAAET Shuwaikh campus. The campus resides
between Jamal abdul Nasser street from north, Al Jahra road from
south, Al Jahez street from the west and Al-Ghazali street from the
east. a plan is attached to indicate the location of the project.

7
Real Estate Construction & Fabrication Co.
N

STC Building

MEW Substation

Figure 1.1

Real Estate Construction & Fabrication Co.


1.5- Site Staff Organization Chart

9
Real Estate Construction & Fabrication Co.
Project Manager
Secretary

Messenger
Document Controller

Safety Quality Control Senior Planning Quantity Arch.Coord


Officer Engineer Project Engineer Engineer Surveyor Engineer

Civil Subcontractors MEP Structure


Lab
Subcontractor
Tech. Engineer
Engineer
MEP
Coordinator
General Land
Draftsmen Draftsmen
Forman Surveyor
Elec PL & FF HVAC
Engineer Engineer Engineer
Civil
Forman
Elec PL & FF HVAC
Foreman Foreman Foreman

Waterproofing Dewatering Shoring Carpentry Alum. Works Precast Concrete. Shelter Equip. Elevator Ready mix
subcontractor subcontractor subcontractor subcont. Subcontractor Subcontractor Subcontractor Subcontractor conc
Supplier

Waterproofing Dewatering Shoring works Carpentry Alum. Works Precast Concrete Shelter Equip. Elev
Foreman Foreman Foreman Foreman Foreman Foreman Foreman Foreman

Lab Furniture Decoration works Metal works Kitchen Equip


subcontractor subcontractor subcontractor subcontractor
Key Legend

Required Contractually Decoration Decoration Metal Works Waterproofing


works Foreman works Foreman Foreman Foreman
Not Required Contractually
10
Responsibility Line

Coordination Line
1.5b- Job Description

Project Manager :
Overall project policy and monitoring relations with consultant and clients team.
Conducting daily / weekly meetings with all staff / subcontractors to point out the
difficulties in work activities, requirement of resources, order/ direct material and
equipment at site with maximum efficiency, find solutions and taking immediate
actions
Review correspondence for proper action
Financial follow up and control the cost of project duration execution, follow up
monthly payment certificates, variation orders in co-ordination with Q.S/Planner
He will be directing the Senior Project Engineer, Architectural engineer, Planning
Engineer, Quality Control engineer, Quantity Surveyor and the Safety Officer
Senior Project Engineer:
Overall area activities directing, monitoring and controlling the productivity of all staff.
He will determine possible critical areas and activities have to be improved for the
successful completion of project in time
Find solutions and taking immediate action required to push the work in proper
coordination with project manager
He will be assisted by the site engineer, foreman, safety officer and
services/finishing works engineers
He will be directing the Subcontractors, Site Engineer, General foreman and Land
Surveyor and reporting to the Project Manager
Architectural Coordination Engineer:
Overall technical coordination, preparation of architectural drawing, composite
drawings.
He will be responsible for the coordination between subcontractors for the
preparation of shop drawings.
Find technical solutions with consultants and subcontractors and taking immediate
action required
He will be reporting directly to the Project Manager, and will be directing the
structural engineer and the architectural draftsmen.

11
Real Estate Construction & Fabrication Co.
Planning Engineer :
Preparation, submission, approval of the project schedule, updates, revisions,
adjustments and monitor the construction progress, identify/initiate potential variance
and delays, follow up resource assignment. He will be reporting directly to the Project
manager and will coordinate with Senior Project Engineer to follow up and monitor
construction activities and the Q.S for the preparation of CLS, as well the
subcontractors.
Preparation, submission, approval of cost loaded schedule in coordination with Q.S
Prepare the monthly / fortnightly work programmes including values of work done vs
planned values
Prepare monthly progress reports
Follow up the updates of material / drawing submittal logs & procurement of material
Preparation & submittal of Pre-meeting submittals
Quantity surveyor:
Preparation of Cost load values for all activities as per Project construction schedule
in coordination with planning engineer
Check quantities, preparation of payment application under the supervision of the
project manager and in co-ordination with the Planning engineer / Senior project
engineer
Preparation of Subcontractors payments, analyzing variations, claims and all other
contractual issues in coordination with planning engineer

Safety Officer : Establish and follow up safety procedures all in accordance with the safety
manual prepared by him. He will be reporting to Project Manager, and will be coordinating
with the Senior Project Engineer to ensure safety control at site.
Quality Control Engineer :
All the aspects of materials / quality control of site works, and site laboratory
functioning.
Review preparation of all submittals of subcontractors, suppliers materials, samples
to provide continuous flow of procurements as per the requirement of Project
Programme. As well as E1 & E2 logs
Responsible for all technical aspects regarding shop drawings preparation and
coordination between different subcontractors.
Preparation of Method statements and follow up procurement of materials and
equipment.
Supervise Quaility control procedures and will follow up all types of submittals such
as Subcontractors, suppliers shop drawings, materials, etc.

12
Real Estate Construction & Fabrication Co.
Structural Engineer :
Structural shop drawings preparation.
Coordination between the different subcontractors
Prepare, submit and get approval of structural As-Built drawings.
To coordinate with the Project Manager / MEP Coordinator for the progress priority
of shop drawings submittal and to solve site structural problems on daily basis
He will be assisted by the draftsmen.
Civil Engineer :
Work under the directives of the Project Engineer and will be responsible to carry out
the works as site directly, and to arrange laborers, materials, equipment, machine
etc.
To supervise the work of subcontractors and arrange their responsibility
To report for any material or other requirements well in time and report to the Project
Engineer in case of expected shortage.
To supervise the foremen and advise him to carry out the work according to
drawings, specification.
To get the work inspection of A/E and follow up with checklists in co-ordination with
QC Engineer
To follow up the works progress under the responsibility of Project Manager and
Project Engineer and ensure that CCS is followed.
Land Surveyor : Assisting Site Engineers, Foremen with all levels, coordination
information. He will be reporting to the Civil Engineer.
General Foreman : Proper execution of Daily work / weekly work program as provided by
the Civil Engineer and proper distribution of resources. He will reporting to the Civil Engineer
and will be managing the labors at site.
Electrical Engineer :
Follow up the execution of electrical works at site
Follow up all electrical materials submittal and approvals as well as procurement and
delivery of these materials to the site.
Find solutions take immediate actions
Testing and commissioning of all electrical works prior handing over the project
Mechanical Engineer:
Follow up the execution of mechanical works at site
Follow up all mechanical materials submittal and approvals as well as procurement
and delivery of these materials to the site.
Find solutions take immediate actions
Testing and commissiong of all mechanical works prior handing over the project

13
Real Estate Construction & Fabrication Co.
2- Project Obstacles

1- Time milestones & constraints.


The contractor is obliged to plan and execute the works within the
contractual milestones and constraints. Accordingly, the
contractor will provide the adequate resources to execute the
construction activities to fulfil the contract milestone.

2- Site Accessibility limitation


The contractor shall have only one side for site access, due to the
site location. Accordingly, only one side will be utilized, and
the contractor shall plan for the execution of the works
accordingly

3- Tightness of location
Major project obstacle is the tightness of the location, where there is
no enough space for the A/E & contractors offices, store, labour
rest shed steel yard, etc

14
Real Estate Construction & Fabrication Co.
3- Construction Strategy
3.1 Project Zoning :
For more control & closer follow up of the project, buildings are divided into different zones, this is based on
different functions, structural nature such as expansion joints, or volume of work
The following presents the project elements and the number of zones for each:
The Nursing college : Divided to 3 zones
The External Works : Divided to 3 Zones
These Zones will include the structural, finishes and electromechanical works.
To further meet the requirement and needs of the project, those zones were developed into smaller sub zones as
follows :
For the structural purpose and requirements each zone will be divided to 2 sub zones:
Sub zone A1, Sub zone A2 for Zone A
Sub zone B1, Sub zone B2 for Zone B
Sub zone C1, Sub zone C2 for Zone C
For the Finishing & electromechanical purpose each zone will be divided to the following :
Class rooms/Corridors Sub zone
Shelter area sub zone (at basement only)
Transformer room sub zone (at basement only)
Mechanical room sub zone (at basement only)
Ramps Sub zone (at basement only)
Wet area sub zone
Stair case sub zone
Open court area 1
Open court area 2
Open court area 3
For External works Zones will be divided as follows:
Zone 1
Zone 2
Zone 3
Detailed sketched are attached to illustrate the Zoning system of the project

15
Real Estate Construction & Fabrication Co.
N

16

Figure 3.1
17
N

Sub Zone C1 Sub Zone B1


Sub Zone A1

Sub Zone C2 Sub Zone B2 Sub Zone A2

18
Basement
Figure 3.2
N

Sub Zone C1
Sub Zone B1
Sub Zone A1

Sub Zone C2 Sub Zone B2 Sub Zone A2

19
Ground Floor
Figure 3.3
N

Sub Zone C1 Sub Zone B1


Sub Zone A1

Sub Zone C2 Sub Zone B2 Sub Zone A2

20

1st Floor Floor


Figure 3.4
N

Sub Zone C1 Sub Zone B1

Sub Zone A1

Sub Zone C2 Sub Zone B2 Sub Zone A2

21

2nd Floor Floor


Figure 3.5
N

Sub Zone C1 Sub Zone B1


Sub Zone A1

Sub Zone C2 Sub Zone B2 Sub Zone A2

22
Roof
Figure 3.6
23
N

24

Figure 3.7
N

25
Figure 3.8
Figure 3.9
26
N

27
Figure 3.10
N

28
Figure 3.11
29
N
Elevations Zoning System North Elevation

East Elevation
West Elevation

Sub Zone Sub Zone Sub Zone


O3 O2 O1

30
Figure 3.12 South Elevation
Elevations Zoning System

Zone A Zone B Zone C

North Elevation

East Elevation
(Zone A)
31
Figure 3.13
Elevations Zoning System

Zone C Zone B Zone A

South Elevation

West Elevation (Zone C)

32
Figure 3.14
3.2- Project Milestones & Constraints

33
Real Estate Construction & Fabrication Co.
Activity Activity Duration
Months
ID Description Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 2
Nursing Institute
Subtotal 731

Start milestone
10 Start Milestone of the Project 0
Mobilization
20 Contractor's Mobilization 45
Engineering
30 Shopdrawings,Materials Submittals & Approvals 365
Procurement & Delivery
40 Materials Procurement & Delivery 440
Sub-Structure
50 Excavation & Backfilling 75
60 Foundations & Sub-Structure 120
Super-Structure
70 Super Structure Works 330
E/M Works
80 Electrical & Mechanical Works 595
Finishing Works
90 Masonary & Finishing Works 390
Elevation Works
100 Elevations Works 180
Roofing Works
110 Roofing System 90
Furniture
130 Fixed Furniture & Equipment 75
External Works
120 External Works 150
Testing & Commissioning
140 Power On 1
150 Testing & Commissioning 60
Substantial Completion
160 Project Substantial Completion 0

Run Date 11JAN09 13:35 NURI Sheet 1 of 1


DAR AL34
HADIAH Date Revision Checked Approved

Nursing Institute
Construction Master Schedule
Primavera Systems, Inc.
3.3 The Project Priority

The Project priorities will be for the main building. After excavation the
concrete skeleton works, will take place. As explained previously, the
main building will be consisting of 3 zone (A, B & C), and accordingly,
the sequence of work will start from Zone A to B to C as will be
explained in detail in the construction methodology. The next priority
will be for the faade work. The last stage will be for the external
works.

35
Real Estate Construction & Fabrication Co.
4-Construction Methodology

36
Real Estate Construction & Fabrication Co.
4.1- Methodology Flow Chart

37
Layout

Excavation

S Dewatering, Excavation (2nd Stage), anti-termite

U
Blinding : Casting + Curing
B
S
Waterproofing + Screed
T
R Raft Foundation
U

Raft Foundation
Formwork + Reinf 1st Layer
C
T Drainage + Pipelines + other MEP Services
U
R Reinforcement 2nd Layer + Casting concrete

Basement Floor
Col.& Walls : Formwork + Shelter Equip + MEP + Reinf + Casting + curing

Slab : Formwork + Fix Reinforcement + MEP + Concrete + Curing

S
U G.F, 1st 2nd, Roof Col: Formwork + Fix Shutter + MEP
P Service + Concrete + Curing
E
R
S G.F, 1st, 2nd, Roof & Upper Roof Slab : Formwork + Fix
T Reinforcement + MEP + Concrete + Curing
U Attic Slab
C
T Activity Sequence up to Upper Roof
U
R
Curtain Precast Int. & Ext Block works +
e Concrete
wall works Finishing & MEP
Cladding

External Works & Landscape

38
4.2- Procurement

39
Procurement
Long lead items are the materials that are specified to be delivered from
abroad (such as diesel generator, AHUs, Ceramic tiles, marble tiles, etc)
or materials that needs a period for fabrication (such as doors, windows,
etc) therefore, it requires a long duration to arrive to the site and might
affect the installation works if not properly planned and tracked.
The material will be procured by the contractor and his subcontractor but
all procurement will be through the main contractor only, since its his
responsibility as per contract conditions to review and make necessary
coordination for his subcontractors procurement after the material
samples and catalogues are approved by the engineers.
Critical materials such as concrete, reinforcement and waterproofing,
water stop, termite control as well as the shelter equipment are affecting
the early activities of the project. The related submittals and approvals of
these types of materials will be finalized as early as possible.
Other long lead materials will be existing in our project, all these long lead
materials will be elaborated in the CCS and the material / procurement log,
to monitor and control its delivery on time and to ensure no delays will
occur.

40
List of Early Critical Material

No CSI Division Description


1 Div 02 Termite Control
2 Div 02 Dewatering system
3 Div 02 Shoring system
4 Div 03 Steel Reinforcement
5 Div 03 Form Work
6 Div 03 Concrete Ready Mix
7 Div 03 Water Stop
8 Div 07 Waterproofing Material
9 Div 13 Shelter Equipment
10 Div 15 Drainage Pipes

List of Long Lead Items

No CSI Division Description Lead Time Source


1 Div 03 Precast Concrete Panels 6 month Local
2 Div 04 Glass Masonry Block 6 month Overseas
3 Div 05 Pipe Tube Railing 6 month Local
4 Div 05 Arch Metal 6 month Local
5 Div 07 Building Insulation 3 month Local
6 Div 08 Steel Doors 6 month Local
7 Div 08 Flush Wooden doors 6 month Local
8 Div 08 Aluminium doors 6-10 month Overseas
9 Div 08 Curtain walls + Alum Windows 6-10 month Overseas
10 Div 08 Doors Hardware 6-10 month Overseas
11 Div 08 Glazing 6-10 month Overseas
12 Div 09 Ceramic Tiles 6-10 month Overseas
13 Div 09 Acoustical Suspended Ceiling 6-10 month Overseas
14 Div 09 Metal Ceiling 6-10 month Overseas
15 Div 09 Stone Flooring 3-4 month Local
16 Div 09 Stone Flooring Adhesive Grouts 6-10 month Overseas
17 Div 09 Reselient Flooring & accessories 6-10 month Overseas
18 Div 09 Vinyl coverings 6-10 month Overseas
19 Div 09 Wooden Flooring 6-10 month Overseas
20 Div 09 Rubber Flooring 6-10 month Overseas
21 Div 09 Carpet Flooring 6-10 month Overseas
22 Div 11 Unit Kitchen 6-10 month Overseas
23 Div 12 Fixed Furniture 6-10 month Overseas
24 Div 13 Shelter Equipment 3-4 month Overseas
25 Div 14 Elevators 8-10 month Overseas
26 Div 15 HVAC Pumps 8-10 month Overseas
27 Div 15 AHUS 8-10 month Overseas
28 Div 15 Plumbing Equipmemt 8 month Overseas
29 Div 15 Ducts 2month Local
30 Div 16 Diesel Generator 12 month Overseas
31 Div 16 Switch Baords 10-12 month Overseas
32 Div 16 Distribution Boards 4 month Overseas
33 Div 16 Trunking 4 month Overseas
34 Div 16 Light fittings 10-12 month Overseas

41
4.3- Excavation, Shoring &
Dewatering

42
Survey mark up and Layout
Necessary bench mark and grid layout are established by the
contractors land surveyor (Recafco), and cross checked by
consultants land surveyor (Hadiya) for acceptance before
starting the works.

Marking Foundation
The Marking and layout of foundations will be done by site
engineer / foreman and cross checked by land surveyor. The
level and the co-ordinates will be carried out from the approved
Grid Line and Bench mark

Excavation
After establishing bench marks and grid lines, excavation works
will take place, 2nos of loaders will start excavating 1m depth at
Zone A. After that, the same will take place at Zone B then
Zone C with the same sequence shown in the attached plan.
After excavation of 1m in each zone, shoring H-Beams will be
installed, and excavation works will proceed till 0.5m above
water table while installing shoring timbers every 2m of
excavation. After reaching 0.5m above water table level the
dewatering system will be installed and operated. After
installation & operation of dewatering system, excavation and
shoring works will proceed till the level of anchors. Shoring
anchors will be installed and tested, and excavation & shoring
works will proceed till the bottom of foundation level.
Note: Only 3 sides will include shoring works, there will be no
shoring works for the side at Axis Z. For curved parts, the
shoring works will be segmented.
The temporary access ramp will be made as indicated in the
attached plan, and will be removed while casting the last part of
raft foundation.
The expected completion of the excavation works will be on the
5th month from the date of enterprise

43
N
Ramp

Start

Zone C Zone B Zone A


Start

Figure 4.1

The sequence of work for the stages of excavation, shoring and dewatering will be as
shown in the above plan
44
Excavation Plan
Shoring Plan

45
Figure 4.2
4.4- Foundation

46
Termite Control
For the raft foundation area, the leveled surface will be treated with anti-
termite treatment before casting blinding concrete.
Subcontractor as well as the material used, will be submitted to the
consultant for approval prior to execution of works

Foundation
After termite control, a 10cm thick blinding will be casted & after curing the
water proofing will proceed as per specified layers and drawings and then
will be protected with 5cm screed layer.
After completion of water proofing works and screed protection, raft
foundation work shall be carried out by fixing rebars and shuttering for the
sides of the raft. After completion of rebars fixation for bottom and top layers,
shuttering the sides and installing the utilities pipes, casting preparation will
take place and the raft foundation will be poured using the adequate number
of tansmixers and concrete pumps. The execution of raft foundation will be
as per the zoning strategy, 2 crews will be available for executing the
foundation works and will be working in parallel. he sequence of works and
movement of crews will be illustrated in the attached plans.
Ramp Footings will be carried out later on after completion of waterproofing
for basement walls and backfilling till the bottom of ramps foundation level.
After casting the ramp foundations the walls will be casted and then water
proofing will be carried out. After waterproofing is completed, backfilling
under ramp S.O.G will start till the bottom of slab level and then the concrete
works for the S.O.G will take place.
After casting of raft foundation the Tower cranes will be installed as will be
explained in the site logistic plan.

47
N

Zone C1 Zone B1 Zone A1

Crew no 1

C2 Zone B2 Zone A2

Crew no 2

48
Raft Foundation
Figure 4.3
4.5- Walls & Columns

49
Basement Walls
After the raft foundation is hardened enough, installation of rebars for walls shall
start and the Doka formwork will be lifted and fixed in position using a crane. The
available formwork for the walls will be enough to cast 45 mr (3 sets each 15m
with 4.50m height) The walls will be casted in 17 cycles as shown in the
attached plan with an expected date of 5 days for each cycle. The wall shutter
will be dismantled after the specified duration of casting each wall, and will be
used again for the next cycle. Shelter Equipments will be embedded in the
concrete as it will be fixed prior casting of concrete. Shelter equipments (valves
and blast doors) will installed using cranes
Form work System
The formwork system that will be used will be Doka large-area formwork Top 50
The major components of the system will be:
1. Doka Timber H-Beam
2. Doka steel waling
3. Plywood
4. Supporting Props
5. Tie Rods

Doka formwork Top 50

50
Columns
10 nos of column sets will be used for casting the columns.
Each cycle will take 2 days (1 day for steel reinforcement fixation + 1 day for
shuttering & casting)
For example, sub zone C2 contains a number of 53 columns, 10 columns will be
casted in1 cycles so the total number of cycles will be 6 cycles, each cycle requires
2 days so the total duration of casting the columns for sub zone C2 will be 12 days.

Columns Formworks
Doka Formwork Top 50 will be used for casting the columns
The components of the System will be:
Doka timber H-Beam
Steel Waling
Plywood
Tie rods
Props for Supporting sides of formwork

Column Formwork Detail

51
14 N
1
6 5 4

Walls Formwork Circulation


6

Total of Formwork Available = 45 mr

8 8 9

2
8

7
9
10 14
15

11

13
13
13

12 52
5 4 3
15
Figure 4.4
N
1

Total of Formwork Available = 45 mr

Casted Walls 53

Under Construction
Figure 4.5
N
4

Total of Formwork Available = 45 mr

Casted Walls 54
4 3
Under Construction
Figure 4.6
N

6 5

Total of Formwork Available = 45 mr

Casted Walls 55 5
Under Construction
Figure 4.7
N

Total of Formwork Available = 45 mr

8 8 9

7
9
10
17

11

13
13
13

Casted Walls 12 56
17
Under Construction
Figure 4.8
14 N

Total of Formwork Available = 45 mr

14
15

Casted Walls 57
15
Under Construction
Figure 4.9
4.6- Slabs Formwork Circulation

58
Slab formwork circulation
After completion of walls and columns, formwork for slabs shall start. 3
formwork sets (Doka) will be available to execute and cast the slabs with
total area of 4,360m2. each formwork set will be as the following :
Formwork set 1 = 979m2 and will be used for sub zones A1 & B1
Formwork set 2 = 2160m2 and will be used for sub zones A2 & C2
Formwork set 3 = 1225m2 and will be used for sub zones B2 & C1
Each formwork of the above will be used in 8 cycles, each of different
durations as for formwork set 1 will have 27 days duration for each cycle,
Formwork set 2 will have 33 days for each cycle and Formwork set 3 will
have 32 days for each cycle
The expected finish date of the superstructure works will be at the 17 month
from the date of enterprise
Plans illustrating each formwork set utilization are attached

Scaffolding System
The Scaffolding system that will be used for the concrete slabs will be the
Dokaflex floor formworks system . The system will be containing of 3
components
Floor Prop Eco 20
Doka Timber H-Beam (H20)
Plywood

59
N
Total of Formwork Available = 4360m2

Sub Zone Sub Zone Sub Zone


C1 B1 A1

Formwork Set 3 = Formwork Set Formwork Set 1 =


1225 m2 1 = 979 m2 979 m2

Area = 1255m2
Area = 979m2
Area = 822m2

Sub Zone Sub Zone Sub Zone


C2 B2 A2

Formwork Set 2 = Formwork Set 2 =


2160 m2 2160 m2
Formwork Set 3 =
1225 m2

Area = 2160m2 Area = 1255m2 Area = 1730m2

There will be 3 sets of Formwork available for


casting all concrete slabs, as illustrated in plan
60
Figure 4.10

Ground Floor Plan


Formwork Set 1 Circulation Formwork Set 2 Circulation Formwork Set 3 Circulation
Area of formwork set is 979m2 Area of formwork set is 2160m2 Area of formwork set is 1225 m2

The formwork will be moving between The formwork will be moving between The formwork will be moving between
Sub zone A1 & B1 horizontally & Sub zone A2 & C2 horizontally & Sub zone B2 & C1 horizontally &
vertically as shown below vertically as shown below vertically as shown below

SF SF SF

FF FF FF

GF GF GF

BF BF BF

Sub Zone B1 Sub Zone A1 Sub Zone C2 Sub Zone A1 Sub Zone C1 Sub Zone B2

Area of Sub zone slab A1 = 979m2 Area of Sub zone slab A2 = 1730m2 Area of Sub zone slab B2 = 1255m2
Area of Sub zone slab B1 = 822m2 Area of Sub zone slab C2 = 2160m2 Area of Sub zone slab C1 = 1235m2

61
The Cycle of each movement will The Cycle of each movement will The Cycle of each movement will
take 27 days take 33 days take 32 days
Formwork Circulation Bar Chart

Formwork Set 1 (979m2)

Days
Activity
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Formwork Shuttering
fixing Steel Reinforcement
Installation of services pipes
Concrete Casting
Curing & Dismantling formwork

Formwork Set 2 (2160m2)

Days
Activity
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Formwork Shuttering
fixing Steel Reinforcement
Installation of services pipes
Concrete Casting
Curing & Dismantling formwork

Formwork Set 3 (1225 m2)

Days
Activity
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
Formwork Shuttering
fixing Steel Reinforcement
Installation of services pipes
Concrete Casting
Curing & Dismantling formwork

62
Cycles of Concrete Slabs

Cycle 1
Floor Zone A1 Zone A2 Zone B1 Zone B2 Zone C1 Zone C2

Roof Slab

Second Floor Slab

First Floor Slab

Ground Floor Slab FW Set 1 FW Set 2

Cycle 2
Floor Zone A1 Zone A2 Zone B1 Zone B2 Zone C1 Zone C2

Roof Slab

Second Floor Slab

First Floor Slab

Ground Floor Slab FW Set 1 FW Set 3

Cycle 3
Floor Zone A1 Zone A2 Zone B1 Zone B2 Zone C1 Zone C2

Roof Slab

Second Floor Slab

First Floor Slab FW Set 1

Ground Floor Slab FW Set 3 FW Set 2

Cycle 4
Floor Zone A1 Zone A2 Zone B1 Zone B2 Zone C1 Zone C2

Roof Slab

Second Floor Slab

First Floor Slab FW Set 2 FW Set 1 FW Set 3

Ground Floor Slab

Cycle 5
Floor Zone A1 Zone A2 Zone B1 Zone B2 Zone C1 Zone C2

Roof Slab

Second Floor Slab FW Set 1

First Floor Slab FW Set 3 FW Set 2

Ground Floor Slab

63
Cycle 5
Floor Zone A1 Zone A2 Zone B1 Zone B2 Zone C1 Zone C2

Roof Slab

Second Floor Slab FW Set 2 FW Set 1 FW Set 3

First Floor Slab

Ground Floor Slab

Cycle 6
Floor Zone A1 Zone A2 Zone B1 Zone B2 Zone C1 Zone C2

Roof Slab FW Set 1

Second Floor Slab FW Set 3 FW Set 2

First Floor Slab

Ground Floor Slab

Cycle 7
Floor Zone A1 Zone A2 Zone B1 Zone B2 Zone C1 Zone C2

Roof Slab FW Set 2 FW Set 1 FW Set 3

Second Floor Slab

First Floor Slab

Ground Floor Slab

Cycle 8
Floor Zone A1 Zone A2 Zone B1 Zone B2 Zone C1 Zone C2

Roof Slab FW Set 3 FW Set 2

Second Floor Slab

First Floor Slab

Ground Floor Slab

64
4.7- Roofing System

65
Roofing system
Once all heavy works are completed on roof, and drainage and other inserts are fixed in
place, the area will be cleaned and roofing works starts. All roofing layers shall be as per
drawings / specifications / manufacturer recommendations. After each layer is completed, it
will be inspected / approved by the engineer before applying the next layer. After roof work
works are completed, flash up and rain water outlets and other roof fixtures shall be
erected. A section detail is attached below to illustrate the roofing system layers.

66
4.8- Faade Works

67
Faade works
The faade works will include installation of concrete panel cladding as well as curtain
wall works. Sigma paint shall be applied in the elevations of open court areas.
After completion of concrete works in each zone, block works shall be carried out, for
both external and internal once the external block works are completed insulation
works will take place and after completion of insulation works on external block works
concrete precast panel cladding works shall start. Opening in block works will be
provided to receive precast support ribs without causing damages to the adjacent
works.
Curtain wall works shall proceed immediately after the completion of concrete works.
After completion of concrete works, Curtain wall brackets will be fixed and aligned, after
completion of brackets, aluminium frames will be installed and then the glass will be
erected after installation of aluminium frames.
The windows will be fixed after the completion of external cladding as it will rest on the
precast panels.
The sequence of works and crews movement shall be as per the zoning strategy. The
crews movement will be from Zone A to Zone B to Zone C. 2 crews will be provided for
the installation of Concrete precast cladding. Tower cranes and mobile cranes will be
used for the installation of the precast panels
Plaster and sigma works are also included in the internal faade works in the open
court area, completion of these activities will be depending on dismantling the tower
cranes and clearing the area to enable the erection of scaffolding. The tower crane will
be dismantled after the completion of roofing system works as well as uploading the
required materials to its locations in the floors. However, 3 sides can be carried out
prior the dismantling of tower cranes to expedite the works.

68
Elevation 1
Sequence of Work

Zone B
Zone C Zone A

Crews Movement
Elevation 2
Elevation 4

Sub Zone Sub Zone Sub Zone


O3 O2 O1

Crews Movement
69
Figure 4.11

Elevation 3
4.9- Finishing & Electromechanical Works

70
Finishing & Electromechanical works
Finishing works will include the following:
Masonry block works & gypsum board partitions
Wall finishes such as plaster, painting & ceramic tiles for wet area
Ceiling works such as gypsum board and tiles, metal ceiling
Flooring works such as terrazzo tiles, marble tiles, resilient flooring, carpet tiles, carpet
roles for prayer rooms, rubber tiles, raised flooring, ceramic flooring for wet areas as well
as epoxy paints for the car park area at the basement.
Electromechanical works shall include the following :
Water supply & drainage piping
HVAC ducting & piping
Electrical conduiting and wiring
Equipments such as generators, pumps, AHUs and exhaust fans
Sanitary fixtures & toilet accessories
Electrical accessories

71
Finishing Strategy
The finishing works shall start with the masonry works. The masonry works will be externally &
internally., internal & external masonry can be carried out once the site is ready and the slabs
scaffolding are removed. Simultaneously fire fighting pipes, chilled water pipes, HVAC ducting,
drainage and water supply H/L pipes shall start.
Wall finishes will consist of sand cement plaster & paint while in wet areas ceramic tiles. The
plaster works will be carried out after completion of first fix electromechanical works such as
electrical conduits, and plumbing pipes at wet areas. Paint works & ceramic works shall follow up
once plaster work is completed, as for painting works will be on stages (Paint preparation, 2nd
Painting coat, and Final painting coat which will be carried out at the final stage of the project)
Ceilings will be consisting of gypsum boards and tiles, metal false ceiling as well as plaster and
paint for wet area and stair cases. False ceiling works shall take place after the completion of all
MEP works above false ceiling and the completion of the paint putty & first coat.
Floor finishes will consist of various materials such as terrazzo tiles, vinyl tiles, marble tiles,
carpet tiles, etc. all materials will be applied on the prepared beds after wall plastering and
fixation of the door frames and all other interior finishes on the walls and ceiling will be done
afterwards. In case of carpet tiles & roles, flooring works will be done after completion of other
finishing works.
Electromechanical works will be divided to three items:
First fix items such as piping, ducting, cable trays, etc works at high level, will be carried
out after removal of slab formwork, while conduits will be carried out after the completion
of block works.
Second Fix items such as equipments, pumps, elect panels shall be carried out after
completion of second painting coats and flooring.
Third Fix items such as elect accessories, sanitary fixtures, toilet accessories, etc shall be
carried out after installation of doors leaves and hardware as well as 2nd painting coats.

72
Finishing & Electromechanical works strategy
As per the Zoning strategy of the finishing works, the execution of works will be carried out as follows:
Dry Areas
The finishing works will include the following:
Plaster & Paint for wall.
Gypsum Board & Tiles for false ceiling.
Marble tiles, Vinyl tiles, Terrazzo Tiles, Ceramic Tiles and Carpet tiles for Flooring.
The sequence of works are planned to be carried out as follows:
1. Block works & First fix electromechanical works such as elec conduits, ducting & piping
2. Installation of door frames
3. Plaster works
4. Paint preparation & Putty
5. Window frames
6. Screed for flooring (vinyl and carpet tiles)
7. First fix gypsum board partition + door frames + First fix Electromechanical
8. Insulation & closing gypsum board partition + Paint preparation & Putty
9. Installation of HVAC ducts, FF pipes, elec conduits above ceiling
10. False ceiling suspension system
11. Installation of false ceiling services tiles
12. KFD visual inspection prior closing false ceiling
13. Painting of ceiling
14. Flooring tiles (Marble, Terrazzo, Ceramic)
15. Fixing door leaves & window glazing
16. Doors & windows hardware
17. Painting Coats
18. Final fix electromechanical
19. Final painting coat
20. Installation of carpet & vinyl tiles

The above mentioned activities will be added in more details in the CCS

73
Corridors
The finishing works will include the following:
Plaster & Paint for walls
Gypsum Board & Tiles for false ceiling
Marble tiles & Vinyl Tiles for First & second floors
The sequence of works are planned to be carried out as follows:
1. Block works & First fix electromechanical works such as elec conduits, ducting &
piping
2. Installation of door frames
3. Plaster works
4. Paint preparation & Putty
5. Screed for flooring (Vinyl or carpet)
6. False ceiling suspension system
7. Installation of false ceiling services tiles
8. KFD visual inspection prior closing false ceiling
9. Painting of ceiling
10. Installation of Marble tiles
11. Fixing door leaves & window glazing
12. Doors & windows hardware
13. Final fix electromechanical
14. Final painting coat
15. Installation of vinyl tiles

The above mentioned activities will be added in more details in the CCS

74
Wet areas
The finishing works will include the following:
Ceramic walls
Plaster & Paint for ceiling
Ceramic Flooring
Sanitary fixtures & Toilet accessories
The sequence of works are planned to be carried out as follows:
1. Block works & First fix electromechanical works such as elec conduits, water supply & drainage
pipes at low level
2. Waterproofing works
3. Installation of door frames
4. Plaster works
5. Steel frame for marble counters
6. Ceramic tiles for walls
7. Ceramic for floors
8. Doors Leaves
9. Doors & windows hardware
10. Installation of marble counter
11. Installation of Sanitary fixtures and toilet accessories
12. Painting of ceiling
13. Final fix electromechanical
Air Handling Units Installation:
The Air Handling Units will be kept in the stores once arrived to the site
The maximum dimensions of the AHUs will be 1.60mX1.00m X0.55m and will have a weight
of 100kg
The air handling units will be lifted by 4 labors through the staircases to reach the required
floors and will be installed above the attic slab after the completion of attic slab water
proofing works and prior completion of block work above attic slab so that enough space will
be available to install the AHU.

The above mentioned activities will be added in more details in the CCS

75
Staircase area
The finishing works will include the following:
Plaster & Paint for walls
Plaster & Paint for ceiling
Marble tiles Flooring
Handrails
The sequence of works are planned to be carried out as follows:
1. Block works & First fix electromechanical works such as elec conduits
2. Installation of door frames
3. Plaster works
4. Paint preparation & putty
5. 2nd coat painting
6. Marble tiles and skirting
7. Doors Leaves
8. Doors & windows hardware
9. Fixing handrails
10. Final fix electromechanical
11. Final Painting coats

Sequence of Work & Crews movement


One crew for each trade will start in execution as soon as the finishing works are ready, the
movement of each crew will be zone wise. Once the finishing works at Zone C is ready to start,
another crew will be added to have a total of two crews working together. The first crew (Crew 1) will
be moving horizontally and vertically between Zones A & B, while the second crew (Crew 2) will be
moving vertically in Zone C. A diagram is attached to illustrate the crews movement for execution of
Finishing works.

76
Internal
Internal Block MEP First Block Works Internal
Works Fixation Block Works
Attic Slab

Installation Plaster Installation of


MEP First Door frames
of Door frames Works Fixation

Paint Prep. & Plaster Works


Screed for Waterproofing
Flooring Putty works
Paint
MEP above preparation &
First Fix Gypsum false ceiling Installation
Putty
Board partition
of Door frames

First Fix MEP For 2nd Painting


G.B Partitions Plaster Works Stage
Installation of
False ceiling
Insulation & gypsum suspension sys Steel frame for
board partition Marble tiles &
marble counter
closing Skirting
Installation of
False ceiling Ceramic tiles for Doors Leaves
Paint Preparation & service tiles
Putty for G.B
Walls
Partitions

Painting of G.B Ceramic Tiles for Doors &


Ceiling Doors Leaves windows
Floors
Hardware

Door Leaves, window Flooring Installation of


Doors Hardware Fixing Handrail
glazing & Hardware Marble Counter
tiles

Installation of Sanitary MEP Final


Final Fix Fixtures & Toilet access fixation
Painting Coats electromechanical
77 Final Painting
Painting of Final Fix coat
Carpet & Vinyl Final Painting Coats
ceiling electromechanical
Finishing & electromechanical works sequence & crews
movement

Crew 2 Crew 1 Crew 1


SF
4 8 7

Crew 2 Crew 1 Crew 1


FF
3 6 5

Crew 2
GF Crew 1 Crew 1
2
4 3

Crew 1 Crew 1
BF Crew 2
1 2 1

Zone C Zone B Zone A


Figure 4.12

Two crews will be provided to execute the works, the number below the crew indicates the
movement sequence of the crew

78
4.10- External Works

79
External works
After completion of concrete skeleton and most of the faade works ( Elevations
1,2 & 3) the external works shall be carried out. The execution of external works will
be in two stages as follows :

Infrastructure Services
The infrastructure service should start with the lower network (storm work network
+ sanitary network) we will locate all pipe lines & manhole as per approved shop
drawings & coordination drawings. We will excavate for pipelines and manhole
location.
After fixing installing & fixing all manholes and pipelines in the approved levels and
locations, we will backfill the pipe lines in layers as specified.
The network of fresh water, brackish, fire protection and LPG will be done as per
approved drawings and method statement
All the external services such as laying of cables, installation of street lights,
communication network etc. will be carried out as per the approved shop drawings
and contract specification.
For all infrastructure piping works, the concrete encasement will be done as per
approved shop drawings & specifications
Hard Landscape
General method for all the hard landscape elements is the same, it will be carried
out after completion of infrastructure services. It will begin with site measurements
and placement of the precasted concrete curb stones along their specified path.
This will form the area for developing the asphalt roads as per contract
specifications.
Development of the pavements, paths and paved areas will be done on
compacted soil, by placing the polythene sheet if needed, concrete slabs and
mortar or sand beds for the specified finishes (precast concrete tiles, precast
concrete interlocking pavers)

80
As per the construction strategy and methodology, the external works will be divided to 4
Zones as follows :
Zone 1
Zone 2
Zone 3
The sequence of work for the external works will be related to the site logistics as well as the
concrete and cladding works. The execution of works will be planned to take place in four
stages as explained in the following:
Stage 1
Once the concrete works are completed, the steel reinforcement workshop will be no longer
required and will be removed from the site. In addition the cladding works for the east elevation
will be completed. Accordingly, the site will be ready for the external works at Zone 1 to be
carried out. Such works will include all infrastructure works as well as the landscaping works.
The material store will be one of the main obstacle in execution of the external works, therefore
its is planned to be relocated in the basement at Zone C (A plan for the new stores location is
attached).
In addition, the temporary vehicle road will be rerouted as illustrated on the attached plans.
The works that will take place in this stage are the following:
Infrastructure works
Kerbstone works
Sub grade for asphalt
Stage 2
After completion of stage 1. Cladding works at the south and west elevations is expected to be
completed. Accordingly, external works at Zone 2 will be carried out. Rerouting of the
temporary vehicle road will be taken into consideration. The works that will take place in this
stage are as follows:
Infrastructure Works
Kerbstone works
Sub grade for asphalt
Stage 3
After completion of stage 2. Cladding works at the north elevation is expected to be completed.
Accordingly, external works at Zone 3 will be carried out. Rerouting of the temporary vehicle
road will be taken into consideration. The works that will take place in this stage are as follows:

Infrastructure Works
Kerbstone Works
Sub grade for Asphalt

81
After completion of all above mentioned stages, final asphalt layers and interlock tiling
works shall be carried out. The sequence of these works shall be as per construction
strategy.

The existing external services near the shelter escape will be studied and relocated and
will be assured to stay fully operating and maintained.

82
N

83

Figure 4.13
N

84

Figure 4.14
N

85

Figure 4.15
Level formation

Excavation for Lower network (Storm & Drainage pipes)

Installation of Pipes & Manholes

Encasement &
Backfilling

Excavation of higher network pipes

Installation of pipes & manholes

Encasement & Backfilling

Completion of
Infrastructure works

Landscape Works

Fixing Curbstone

Laying Asphalt Layers

Interlock Tiles paving


86
4.11- Authority Approvals, Testing &
Commissioning

87
Authority Approvals, testing & commissioning
Authority approvals , testing and commissioning are all linked to the completion of
respective works and are included in the schedule under a separate section
A diagram is attached to clarify the procedure followed in order to complete the
project
Testing & Commissioning
Plumbing system
A. During the manufacture (at Contractor's premises only), installation and
after completion of works; the system, sections of the system or its
components shall be tested by the Contractor / specialist Subcontractor in
the presence of the Engineers representative, as directed below or
elsewhere. The Contractor shall procure all testing instruments and
accessories and bear all costs in connection with the same:
1. Basic materials for conformity with the specified standards.
2. Supports and anchors for ability to withstand required loads.
3. Wall mounted sanitary fixtures with a dead weight of 100 kgs.
4. Pumping equipment for the specified flow, head, controls, safety
interlocks and alarms; noise criteria, etc.
5. Heat transfer equipment for full load capability, controls, safety
interlocks, and alarms and operation of safety valves.
6. Filtration equipment for flow, head loss, filtration fineness, controls
alarms, regeneration etc.
7. Control system for operating ranges, tolerances, cutout, alarms
8. Water supply systems for required flow and pressure at
simulated peak flow conditions (open sectional control valves
estimated no. of outlets in open condition, in series).
9. Drainage systems for simulated peak flow conditions and performance
of trap seals (by simultaneous discharge of all water closets
stack or groups).
10. Piping in general for line, level and slopes.
11. Sanitary fixtures for operation of fittings and proper fixation.

88
B. Balance and regulate the following items, systems.
1. Globe valves on pump discharge for design flow.
2. Balancing valves in circulating systems for equal or proportionate flow.
3. Thermostats for cut in cut out temperatures or range.
4. Angle valves on fixture supply for regulated flow.

TESTING OF PRESSURIZED PIPING

A. The pipes shall be jointed, plugged and shall have been in position for
at least 24 hours, before the tests are carried out.
B. The piping shall be tested for line, gradient and water tightness. The
Contractor shall furnish all labour, and necessary testing instruments
such as gauges, pumps etc. as directed by the Engineers
representative. A minimum of two (2) nos identical pressure gauges
shall be installed at extremities of the piping circuit to be tested.
C. Fill the piping with clean fresh water, leaving all high points open to
allow for purging of air. Allow a soaking period of at least 24 hours for
cement lined or concrete pipes.
D. Pressurize the system using manual pumps in increments of 25 percent
of the test pressure. Allow a standing period of 10 minutes after each
pressure increment. Pressure testing using motor driven pump is not
permitted.
E. Do not over pressurize the system under any circumstance. If the test
pressure is close to the maximum permissible pressure of any of the
system components, install calibrated pressure relief valves in the
tested circuit.
F. Prior to testing keep all valves and control devices in open position.
After completion of pressure test, close each valve one at a time
starting from the pressure release end, so as to ensure tightness of the
valve.
G. The piping shall be hydrostatically tested at a pressure of 690 Kpa (100
psig) or 1.5 times the system working pressure, whichever is greater,
but limited to 1379 Kpa (200 psig) for copper and steel piping and 1034
Kpa (150 psig) for UPVC piping. The pressure shall be maintained for
at least 4 hours. In metallic piping, allow for pressure fluctuations due
to ambient temperature variations. Record the circuit temperature
along with the pressure readings.
H. Check for leaks by swabbing with a dry tissue. Drop in pressure to the
order of 10 Kpa (1.5 psig) per hour shall be considered as acceptable.
I. Do not subject sanitary fixture chrome fittings to the test pressure.
J. Piping shall be tested in segments during the progress of the work.
Maintain an official log book for recording the tests carried out on
sections of piping, including test pressure, date of test
89
TESTING OF DRAIN, WASTE AND VENT PIPING

A. The pipes shall be joined, plugged and shall have been in position for at
least 24 hours before the tests are carried out.
B. The piping shall be tested for line, gradient and water tightness. Furnish
all labour and necessary testing instruments as directed by the
Engineers representative.
C. Install compression type rubber plugs with bleeding caps to plug branch
risers in horizontal piping. Install inflatable pneumatic rubber plugs for
vertical risers and other inaccessible areas.
D. Fill the piping with clean fresh water, leaving all the high points open to
allow purging of air.
E. All soil, waste, vent and storm piping shall be tested by filling entire
system with water to a minimum head of 3 Ms (10 feet) minimum at
any part of the system. The system shall hold the water level to within
100 mm (4 inch) drop in 8 hours. Vertical piping shall be tested in
sections of two or three floors at a time.
F. Check for leaks by swabbing with a dry tissue.
G. Test completed piping by simultaneous flushing of all water closets.
Test drainage branches by simultaneous discharge of filled bath tubs,
washbasins etc.

DISINFECTION AND FLUSHING OF FRESH WATER PIPING SYSTEM

A. Prior to starting work, verify that system is complete, flushed and clean.
B. Ensure pH of water to be treated is between 7.4 and 7.6 by adding
alkali (caustic soda or soda ash) or acid (hydrochloric acid).
C. Add disinfectant, free chlorine in liquid, powder or tablet form to obtain
50 to 80 mg/L residual.
D. Fill the system piping with chlorinated water and bleed water from
outlets to ensure distribution and test for disinfectant residual at
minimum 15 percent of outlets.
E. Maintain disinfectant in system for 24 hours.
F. During the disinfections period install temporary warning signs in both
Arabic and English at conspicuous places throughout the Project
against using the chlorinated water.
G. If final disinfectant residual tests less than 25 mg/L, at any outlet, repeat
treatment.
H. Flush disinfectant from system until residual equal to that of incoming
water or 1.0 mg/L.
I. Take samples no sooner than 24 hours after flushing, from remote outlet
of each riser and from water entry, and analyse in accordance with
AWWA C601. Submit result of analysis to Engineers representative for
approval.

90
INSPECTION, TESTS AND ADJUSTMENTS OF FIRE PUMPS

A. Prior to Start Up.


1. The pump motor assembly alignment shall be checked and adjusted, if
necessary. Steel cleats shall be welded on pump and motor bases to lock them in
aligned position.
2. Foundation and coupling bolts shall be tightened and locked.
3. Pump shaft shall be checked for free rotation.
4. Electrical continuity and insulation of motor and the control panel shall be
checked by meggering.
5. The calibration of the relief valve opening and its installation shall be checked
and corrected if necessary.
6. The system isolating valve/s shall be shut-off and the test line opened.
7. The tripping element of the circuit breaker shall be
checked for correct selection
and proper installation. The star-delta change over timing shall
be adjusted to
the period recommended by the motor manufacturer.
8. System power supply voltage shall be checked and all other
checks outlined in
the controller operation manual performed, before energizing the
controller.
9. The suction lines and the pump casing shall be checked for
proper filling with
water.

B. The following shall be executed to start the system up:


1. The direction of rotation of the pump shall be checked and
corrected, if
necessary, by momentary operation of the emergency start
lever.
2. The valve on the test line shall be partially closed to avoid the
operation of the
pump at high discharge rates.
3. The pump shall be started on manual mode.
4. The motor full load current shall be checked by manipulating
the flow.
5. The pressure relief valve shall be checked for proper
operation by gradually
closing the test valve.
6. The pump and motor bearings shall be checked for signs of
overheating.
7. The suction line shall be checked for signs for entry of air and
proper suction
intake flow.
C. The pump performance shall be verified as follows:
1. The pump head shall be checked at 10091 % and 150 % of
nominal flow and
D. The following shall be executed to put the system into
Service:
1. Isolate the fire pump controllers.
2. Close the test line and open the system isolating valve.
Ensure that the system
outlets are closed.
3. Fill the system with the jockey pump. Maintain pressure for 24
hours and ensure
that there are no leaks.
4. Energize fire pump controllers and ensure that the system is
in automatic mode.

HVAC Systems
During the manufacture (in Contractors premises only) and installation and
after completion of works; the system, sections of the system or its
components shall be tested by the Contractor/Specialist Subcontractor in
the presence of the Engineers Representative as directed below or
elsewhere. The Contractor shall procure all testing instruments and
accessories and bear all costs in connection with the same:
1. Basic materials for conformity with the specified standards.
2. Supports and anchors for ability to withstand required loads.
3. Pumping equipment for the specified flow, head, controls, safety
interlocks and alarms; noise criteria, etc.
4. Heat transfer equipment for full load capability, controls, safety
interlocks, and alarms and operation of safety valves.
5. Control system for operating ranges, tolerances, cutout, alarms etc.

Electrical works Testing & Commissioning

Wiring Devices

A. Test all switches, socket outlets etc., for correct polarity and continuity of
conductors in
the presence of and to the entire satisfaction of the Engineer.
B. Carry out live phase to earth loop impedance tests at all switches and socket
outlets
with an approved earth loop impedance tester to the entire satisfaction of the
Engineer.
Ensure that all device plates have satisfactory earth continuity to the protective
conductor system.
C. Test all 13 Amp. socket outlets for instantaneous tripping of associated
distribution
board current operated earth leakage circuit breaker using testing equipment,
approved by the Engineer.

92
Diesel Generator
Testing shall be carried out at full load after completion of installation by the
Engine manufacturer's qualified representation by the Engine manufacturer's
qualified representative in the presence of the Engineer.
2. If the above cannot be done then testing shall be done at the
manufacturer/supplier's premises at full load in the presence of the Engineer. All
arrangements and costs incurred by such a test shall be responsibility of the
Contractor.

Switch Boards
Test shall be performed at the manufacturers plant in accordance with BS-5486.
The manufacturer shall submit the test reports to the purchaser for approval.
Inspection shall be carried out at the manufacturers plant and test witnessed by the
Engineer before delivery of equipment to site.

UPS
1. Routine tests shall be carried out at the manufacturers works on each completed unit
and witnessed by the Purchaser and Owner or his appointed representatives. These
tests shall include:
a. Insulation resistance test
b. Dielectric strength test
c. Operational and sequence test
d. Performance test
e. Transient response test
The transient response should record the results with oscillograms. These
tests shall include:
- Simulation of an inverter failure which would cause the full load to
transfer from the inverter to standby power.
- Manual return of the full load from standby power to the inverter.
- Simulation of failure of the AC power input of the battery charger.
- Simulation of battery charger failure.
- Measurement of the inverter output voltage when the input voltage is
varied between 10 percent and the frequency, between 2 Hz.
f. Short circuit tests
- Short the inverter output circuit to record the current limiting effect of
the inverter.
- Short the output of one of the branch circuits to ensure clearing of the
fault.
g. Temperature rise test
h. Noise level test
i. Measurement of dimensions
j. Visual check of workmanship and finish
2. The manufacture shall submit these test reports for Owners approval.
3. Approval by the purchaser/Owner shall not relieve the manufacturer of his
commitments under the terms of the purchase order and this specifications.

93
Telecommunication System
Testing shall conform to TIA/EIA TSB-67 Transmission Performance Specifications
for
Field Testing of Unshielded Twisted Cabling Systems and ANSI/TIA/EIA-568-A-1,
Propagation Delay and Delay Skew Specification for 100-ohm 4-pair cable. Testing
shall be accomplished using level III field testers.
Test each pair of each cable for opens, shorts, grounds, and pair reversal. Correct
grounded and reversed pairs. Examine open and shorted pairs to determine if
problem
is caused by improper termination. If termination is proper, tag bad pairs at both ends
and note on termination sheets.
1) Perform testing of copper cables with tester meeting TIA/EIA TSB-67 and
ANSI/TIA/EIA-568-A-1 requirements.
2) If horizontal cable contains bad conductors or shield, remove and replace cable.

Fire Alarm & Detection System


A. After the installation is complete, the contractor shall conduct operating
commissioning tests. The system installation, testing and commissioning
shall be as per Kuwait Fire Brigade approval and requirements.
B. The Fire Alarm System shall be completely programmed in accordance
with Kuwait Fire Brigade requirement and a specialist from the
manufacturer shall attend and demonstrate the complete system.

Public Address System


A. The completed public address system shall be fully tested and adjusted the
transformer
taps for appropriate sound level by the contractor in the presence of the owners
representative.
B. Measure and record sound pressure levels at designated locations.
C. Upon completion of a successful test, the Contractor shall so certify in writing to
the
Owner and provide detailed, demonstration and training.
D. Submit all shop drawings indicating installation details, cable routing and system
configuration and technical catalogue for each component.

94
KFB MOE KM MEW MOC Civil Defense

Submit fire alarm, fire Submit of Submit HVAC MEW Site Submit MOC
protection, smoke Substation as built & load inspection & intake dwgs for
ventilation system shop shop dwg calculation to Approval approval
drawing & materials to MOE
KFB
Checking of site
Approval of Approval of Payment of Fee Inspection of
issuance of
Approval of fire alarm, Substation shop HVAC as built & by the owner Intake By MOC
clearing
fire protection, smoke dwgs load calculation
certificate by KM
ventilation system by MOE
shop drawing & Approval by
materials by KFB MOC
Substation Submit elec as
Civil works built & all loads
inspection to MOE Physical
Inspection of installation,
Installation prior ceiling inspection
closing Approval of Approve elec as approval by
Civil works built & all loads MOC
inspection by MOE
Final Installation & Payment of
Arch. Visual fees by owner
Fix Transformer, Inspection of site
inspection by KFB
HT Panel &
connection by Connection,
MOE Approval
MOE activation of
Approval by KFB telephone lines
Payment of fee by MOC
to MOE by owner
Issuance of letter of
Letter to KM for
Power connection
Power connection Third Party
to MOE by KM
inspection
KFB Final operation
Electrical Connection to site
Civil Defense
Final certification of inspection
acceptance

Testing & commissioning


95
Project Complete
5-Site Logistics

96
Real Estate Construction & Fabrication Co.
5 - Site Logistics Plan
The Site Logistic Plan includes the temporary fences, sign boards, Consultant site
offices, Contractors site offices, subcontractors site offices, consultant and
contractors car park shed, workshops for cutting & bending steel, stores for
keeping materials, labors toilets & rest sheds. Temporary access routes are taken
in consideration to allow equipments & machines movement around the
construction site facilities. For further illustrations, refer to the attached plan

Two Tower cranes (TC-1 and TC-2) will be erected as shown in the attached
plans. The first Tower Crane TC-1 will be located at the open court area between
axis (H & S) and axis (21 & 28). The second Tower crane TC-2 will be located at
the open court area between axis (H & S) and axis (6 & 12). Both Tower cranes
will have radius of 55 m and lifting capacity of 52.6 KN and will be installed after
casting the raft foundation. A plan is attached to indicate the proposed
foundation of the tower crane which will be submitted for approval to the
consultant.
Impact of Tower Crane (TC-1)
Due to the tower crane location in the open court area between axis (21
& 28). Some construction activities will be on hold till dismantling the
tower crane, such as the following:
Part of the concrete slab in the ground floor (tower crane location)
Cast in situ terrazzo tiles
Flooring works at the basement.
External Plaster works
Impact of Tower Crane (TC-2)
Due to the tower crane location in the open court area between axis (6 &
12). Some construction activities will be on hold till dismantling the tower
crane, such as the following:
Part of the concrete slab in the ground floor (tower crane location)
Cast in situ terrazzo tiles
Flooring works at the basement.
External Plaster works
Tower Crane Dismantling
2 mobile cranes will be used for dismantling the tower crane, the tower
crane boom and the counter jib will first be dismantled.
After dismantling the boom and counter jib, the operator cabin will be
dismantled.
After dismantling the operator cabin, the tower crane section will be
dismantled one by one till all sections are dismantled

97
Real Estate Construction & Fabrication Co.
Mobilization
The construction phase shall commence upon receiving the handing over of the site from the
municipality. Accordingly, mobilization works shall start. The mobilization will be in accordance
with the proposed time schedule and contract milestones and within this period all requirements
mentioned in the specifications and other contract documents will be followed and coordinated
with the municipality and other authorities for all related approvals and permits.
The mobilization works shall include the following:
Consultant & Contractor/ Subcontractors site offices
A/E site offices will be erected by a professional subcontractor, while main contractor
staff office will be constructed by our carpentry workshop, and will be sited as approved
by the engineer, In addition to all the site temporary services such as fire fighting, water
supply, drainage, electric HVAC, telephone network, etc. The offices will be furnished
and equipped as required. Suitable paved temporary site access roads as per standard.
Detailed shop drawing for the above will be submitted for consultants review and
approval prior execution.
Consultant & Contractor car park sheds
Consultant and main contractor car park shed will be erected by a professional
subcontractor to allow adequate number of cars, and will be sited as approved by the
engineer. Detailed Shop drawing will be submitted for review and approval prior the
execution.
Temporary fence
A complete fence will be executed as specified in tender documents, with the relevant
approved shop drawings. All Client, CM and consultant requirements shall be taken into
consideration
Sign Boards
Shop drawings will be submitted in due time for the same for approval prior fixation, as
well as all calculations required. Necessary electrical supply to sign board lighting shall
be provided.
Stores
Covered storage area for different type of materials will be provided, and will be sited as
approved by the engineer.
Work shops
The site will be provided with work shops for steel reinforcement preparation, cutting
and bending, as well as formwork and shutter assembling

98
Real Estate Construction & Fabrication Co.
Labors rest sheds & toilets
Labors rest sheds, drinking fountains, guard house, etc shall be provided, and will be
located as approved by the engineer.
Temporary Lighting & Power
Adequate lighting and power shall be provided for all construction tools and
equipment without overloading the temporary facilities, and shall be made available
for construction operations of all trades .
Construction debris removal
The debris will be removed as required to maintain the site tidy and accessible all the
time, and the same will be transported to the offsite dumping area.
Temporary Controls
Temporary controls shall be taken in consideration as specified during the
construction period, such as noise control, dust control, water control , fire fighting
control, etc.
First Aid Facilities
First aid Facilities shall be provided as per the safety program

99
Real Estate Construction & Fabrication Co.
Site Logistic Plan

100
Figure 5.1
Real Estate Construction & Fabrication Co.
Tower Cranes Locations

Tower Crane (TC2)

Tower Crane (TC1)

Figure 5.2
101

Real Estate Construction & Fabrication Co.


102

Real Estate Construction & Fabrication Co.


Figure 5.3
6- Activity Coding & ID System

103
Real Estate Construction & Fabrication Co.
Nursing Institute - PAAET

RECAFCO

Activity Coding System

No Description Number of characters Notes


1 Phase 1
2 Building 1
3 Floor 2
4 Zone 1
5 Sub Zone 2
6 Subcontractor 2
7 Division 3
8 Sub Division 5

No Type Description Notes


1 G General
2 E Engineering Phase
3 C Construction Phase
4 S Project Closure

No Location Description Notes


1 G General
2 C Subcontractors/Sppliers
3 S Shop Drawings
4 M Materials
5 B Main Building
6 X External Works
7 T Testing & Commissioning
8 A Authorities Approvals
9 O Close Out
10 P Provisional Items

No Floor Description Notes


1 GN General
2 SA Submittal & Approvals
3 MU Mock Ups
4 PR Procurement
5 FD Foundation
6 BF Basement
7 GF Ground Floor
8 FF First Floor
9 SF Second Floor
10 RF Roof
11 UR Upper Roof
12 EV Elevators
13 ST Staircases
14 EL Elevations
15 EX External Works

No Zone Description Notes


1 G General
2 A Zone A
3 B Zone B
4 C Zone C
5 S Shelter Area only in basement
6 N North Elevation
7 O South Elevation
8 W West Elevation
9 E East Ealevation
10 1 Zone 1 for external works
11 2 Zone 2 for external works
12 3 Zone 3 for external works

104
No Sub Zone Description Notes
1 GN General
2 A1 Zone A1 For Concrete works only
3 A2 Zone A2 For Concrete works only
4 B1 Zone B1 For Concrete works only
5 B2 Zone B2 For Concrete works only
6 C1 Zone C1 For Concrete works only
7 C2 Zone C2 For Concrete works only
8 DR Dry Areas
9 WT Wet Areas
10 CO Corridors
11 S1 Stair Case 1
12 S2 Stair Case 2
13 S3 Stair Case 3
14 S4 Stair Case 4
15 S5 Stair Case 5
16 S6 Stair Case 6
17 S7 Stair Case 7
18 S8 Stair Case 8
19 S9 Stair Case 9
20 MA Mechanical Area
21 TR Transformer Room
22 O1 Open Court Area 1
23 O2 Open Court Area 2
24 O3 Open Court Area 3
25 IS Infrastructure works
26 LS Landscape works

No Subcontractor Description Notes


1 RC Recafco Main Contractor
2 DS Drake & Skull Electormechanical Subcontractor
3 JN Jassim Al-Nisf Waterproofing Subcontractor
5 KF Kuwait Foundation Shoring works subcontractor
6 AL Alico Kuwait Aluminium Works subcont.
7 BD Boodai Trading Co Shelter Equip. subcontractor
8 KZ KZ Pest Control Anti Termite Subcontractor
9 ET ETA Engineering & Elevator Co Elevator works subcontractor

No Division Description Notes


1 GN0 General
2 020 Division 02 - Earth Works
3 030 Division 03 - Concrete Works
4 040 Division 04 - Masonry Works
5 050 Division 05 - Metal Works
6 070 Division 07 - Thermal & Moisture Protection
7 080 Division 08 - Doors & Windows
8 090 Division 09 - Finishes
9 100 Division 10 - Specialities
10 110 Division 11 - Equipment
11 120 Division 12 - Furinture
12 130 Division 13 - Special Construction
13 140 Division 14 - Conveying System
14 15P Division 15 - Mechanical Works (Plumbing)
15 15F Division 15 - Mechanical Works (Fire Fighting)
16 15H Division 15 - Mechanical Works (HVAC)
17 15L Division 15 - Mechanical Works (LPG)
18 160 Division 16 - Electrical works

No CSI Subdivision Description Notes


1 01110 SUMMARY OF WORKS
2 01250 CONTRACT MODIFICATION PROCEDURE
3 01290 PAYMENT PROCEDURES
4 01311 PROJECT COORDINATION
5 01312 MECHANICAL AND ELECTRICAL COORDINATION
6 01313 PROJECT MEETINGS
7 01321 NETWORK ANALYSIS SCHEDULES
8 01322 CONSTRUCTION PHOTOGRAPHS
9 01330 SUBMITTAL PROCEDURES
10 01333 DOCUMENT PRODUCT DATA AND SAMPLES
11 01400 QUALITY REQUIREMENTS
12 01420 REFERENCE STANDARDS AND DEFINATIONS
13 01455 MOCK UP REQUIREMENTS

105
No CSI Subdivision Description Notes
14 01458 TESTING LABORATORY SERVICES
CONSTRUCTION FACILITIES AND TEMPORARY
15 01505
CONTROL
16 01521 FIELD OFFICE AND SHEDS
17 01555 TRAFFIC CONTROL
18 01561 SAFETY MEASURES AND STANDARD
19 01562 TEMPORARY BARRIERS AND ENCLOSURES
20 01580 PROJECT IDENTIFICATION AND SIGNS
21 01600 PRODUCT REQUIREMENT
22 01632 ALTERNATIVES AND SUBSTITUTES
23 01722 FIELD ENGINEERING
24 01732 CUTTING AND PATCHING
25 01741 FINAL CLEANING
26 01742 PROGRESS CLEANING
27 01750 STARTING AND ADJUSTING
28 01770 CLOSEOUT PROCEDURES
29 01783 OPERATION AND MAINTENANCE
30 01785 DUTIES DURING MAINTENANCE PERIOD
31 01787 PROJECT WARRANTIES
32 01789 PROJECT RECORD DOCUMENTS
33 02210 SUBSURFACE INVESTIGATION
34 02330 SITE CLEARING
35 02240 DEWATERING
36 02260 EXCAVATION SUPPORT & PROTECTION
37 02300 EARTH WORK
38 02362 TERMITE CONTROL
39 02510 ASPHALT WORK
40 02580 ROADWAY AND PARKING MARKINGS
41 02772 PRECAST CONCRETE CURBS
42 02783 INTERLOCK PRECAST CONCRETE PAVERS
43 02890 TRAFIC SIGN AND SIGNALS
44 03100 CONCRETE FORMWORK
45 03200 STEEL REINFORCEMENT
46 03300 CAST IN-PLACE CONCRETE
47 03480 PLANT PRECAST ARCH. CONCRETE
48 03550 CONCRETE TOPPING & FLOOR FINISH
49 03520 LIGHTWEIGHT CONCRETE FILL
50 03535 SAN CEMENT SCREED
51 04050 CONC. UNIT MASONRY
52 04815 GLASS UNIT MASONARY
53 05500 METAL FABRICATIONS
54 05521 METAL RAILINGS
55 05580 ARCHITECTURAL METAL
56 07110 MEMBRANE WATERPROOFING
57 07120 FLUID APPLIED W/P
58 07160 BITOMINIOUS WATERPROOFING
59 07210 BUILDING INSULATION
60 07320 PRECAST CONC. ROOF TILES
61 07551 MODIFIED BITUMINIOUS PROOFING
62 07620 SHEET METAL FLASHING & TRIM
63 07920 JOINT SEALANT
64 07840 FIRESTOPPING
65 08110 STEEL DOORS AND FRAMES
66 08120 ALUMINIUM WORKS (DOORS)
67 08210 FLUSH WOOD DOOR
68 08310 ACCESS DOORS & PANELS
69 08520 ALUMINIUM DOORS & WINDOWS
70 08710 DOOR HARDWARE
71 08800 GLAZING
72 08900 GLAZED CURTAIN WALL

106
No CSI Subdivision Description Notes
73 09220 PORTLAND CEMENT PLASTER
74 09250 GYPSUM BOARD
75 09260 GYPSUM BOARD ASSEMBLIES
76 09310 CERAMIC TILE
77 09420 PRECAST TERRAZZO
78 09440 CAST IN SITU TERRAZZO
79 09505 GYP.BOARD SUSP.CEILING
80 09510 SUSPENDED CEILING
81 09546 METAL CEILINGS
82 09638 STONE FLOORING
83 09651 RESILIENT BASE AND ACCESSORIES
84 09653 SHEET VINYL FLOOR COVERING
85 09671 EPOXY FLOORING
86 09680 CARPET TILES
87 09910 PAINTING
88 10265 IMPACT RESISTANT WALL PROTECTION
89 10270 ACCESS FLOORING
90 10400 IDENTIFICATION SIGNS
91 10810 TOILET ACCESSORIES
92 11460 UNIT KITCHENS
93 12566 LABORATORY FURNITURE
94 13036 PUBLIC SHELTER
95 14210 ELECTRIC TRACTION ELEVATORS
96 15050 PLUMBING SYSTEM
97 15060 HANGERS AND SUPPORTS
98 15070 MECHANICAL SOUND & VIBRATION CONTROL
99 15075 MECHANICAL IDENTIFICATION
100 15080 MECHANICAL INSULATION
101 15100 PLUMBING PIPING
102 15121 EXPANSION COMPENSATION
103 15122 METERS AND GUAGES
104 15123 PIPING SPECIALITIES
105 15140 PLUMBING SPECIALITIES
106 15181 HYDRONIC PIPING AND VALVES
107 15183 REFRIGERANT PIPING
108 15185 HVAC PUMPS
109 15190 FUEL PIPING
110 15300 FIRE PROTECTION SYSTEM
111 15310 FIRE PROTECTION PIPING
112 15320 FIRE PUMPS & ACCESSORIES
113 15325 SPRINKLERS SYSTEM
114 15330 FIRE PROTECTION SPECIALITIES
115 15355 FOAM EXISTING SYSTEM
116 15375 STAND PIPE AND HOSE SYSTEM
117 15400 PLUMBING EQUIPMENT
118 15410 PLUMBING FIXTURES
119 15450 WATER STORAGE TANKS AND ACCESSORIES
120 15500 HVAC SYSTEM
121 15725 AIR HANDLING UNITS
122 15731 PACKAGED AIR HANDLING UNITS
123 15734 COMPUTER ROOM AIR CONDITIONING UNIT
124 15738 SPLIT SYSTEM AIR CONDITIONING UNIT
125 15761 AIR COILS
126 15763 FAN COIL UNITS
127 15785 AIR TO AIR ENERGY RECOVERY UNITS
128 15810 DUCTS (DUCT WORK)
129 15820 DUCT ACCESSORIES
130 15837 CENTRIFUGAL FANS AND AXIAL FANS
131 15838 POWER ROOF VENTILATORS
132 15841 BYPASS VARIABLE AIR VOLUME TERMINALS
133 15855 DIFFUSERS, REGISTER AND GRILLS

107
No CSI Subdivision Description Notes
134 15900 BUILDING AUTOMATION SYSTEM
135 15860 AIR CLEANING DEVICES
136 15950 TESTING ADJUSTING & BALANCES OF HVAC
137 15900 BUILDING AUTOMATION SYSTEM
138 15400 PLUMBING SYSTEMS
139 15500 HVAC SYSTEMS
140 16050 BASIC ELECTRICAL MATERIALS & METHODS
141 16060 GROUNDING & BONDING
142 16075 ELECTRICAL IDENTIFICATION
143 16123 BUILDING WIRES & CABLES
144 16130 RACEWAY & BOXES
145 16133 CABLE TRAYS
146 16134 UNDERFLOOR RACEWAY ASSEMBLIES
147 16140 WIRING DEVICES
148 16210 ELECTRICAL WORKS FOR SUBSTATION
149 16235 DIESEL GENERATOR
150 16441 SWITCHING BOARDS
151 16442 PANEL BOARDS
152 16443 MOTOR CONTROL CENTERS
153 16500 LIGHTING FIXTURES
154 16611 UNINTERRUPTIBLE POWER SUPPLY SYSTEM
155 16640 AUTOMATIC TRANSFER SWUTCH
156 16670 LIGHTING PROTECTION SYSTEM
157 16710 TELECOMMUNICATION SYSTEM
158 16721 INTEGERATED FIRE ALARM
159 16725 SECURITY AND CCTV SYSTEM
160 16771 AUDIO VISUAL SYSTEM
161 16800 CLOCK SYSTEM
162 16821 PUBLIC ADDRESS SYSTEM
163 16850 TV AND SATELITE SYSTEM
164 16860 INTERACTIVE ELECTRONIC SMART BOARD

108
Activity ID System

20 characters will be used for the Activity ID

1 . 3 . 5 6 . 8 . 10 11 . 13 14 15 16 17 . 19 20

Phase Location Floor Zone Sub Zone Subdivision Number

Example

C.B.GF.A.WT.09310.01 = Ceramic Flooring for wet areas at Ground floor Zone A

109
7- Productivity Rates

110
Real Estate Construction & Fabrication Co.
Productivity Rates

No. of working days : 6 days/ week (Saturday to Thursday, Friday is day off)
Working shifts : one shift / day
Working hours : 8 hours / day
Over time and Fridays shall be used if necessary to keep on schedule or to compensate for any unexpected events.

Productivity
No Division Item Describtion Crew (Manpower/Equipment)
Rate per day
1 Div 02 Excavation Works 350 m 1nos Loader
2 Div 02 Shoring 50 m 4 shoring labours
3 Div 02 Backfilling 80 m 2 Roller + 2 compactor + 4 labors
4 Div 02 Preparation of blinding 200 m 3 Labours + 1 Compactor
5 Div 02 Anti Termite Control 600 m 1 labour
6 Div 02 Kerbstones 75m 3 Masons
7 Div 02 Inerlock Tiles 30m 4 Masons
1 Asphalt paver + Roller + Pnuematic wheel
8 Div 02 Asphalt 2000m
+ compacter & compressor
9 Div 03 Concrete Slab 30m 4 carpenters + 2 labour + 4 Steel Fixers
10 Div 03 Concrete Columns 5 nos 2 carpenters + 2 steel Fixers + 2 Labours
11 Div 03 Precast Concrete Cladding 60m 6 mason + 1 crane
12 Div 03 Concrete Topping / Screed 40m 5 concreter + 1 finisher
13 Div 03 Leight weight concrete 60m 6 concreter + 1 finisher
14 Div 04 Block Works 15m 1 Block work mason + 1 Labour
15 Div 04 Glass Block Works 5m 1 Mason + 1 Helper
16 Div 05 Handrails 10m 1 Handrail mason + 1 helper
17 Div 07 Waterproofing membrane 60m 1 WP mason
18 Div 07 Protection Board 60m 1 WP mason
19 Div 07 Building Insulation 100m 1 Mason + 1 Helper
20 Div 07 Concrete Pavers for Roof 30m 1 Tile Layer + 1 Helper
21 Div 07 Metal panels cladding 30m 1 Cladding Mason + 1 Helper
22 Div 07 Aluminium Flashing 60m 1 Mason + 1 Helper
23 Div 07 Fire Stop 40mr 1 Mason + 1 Helper
24 Div 08 Door Frames 5 Nos 1 Doors carpenters + 1 helper
25 Div 08 Door Leaves 5 Nos 1 Doors carpenters + 1 helper
26 Div 08 Door Hardware 5 Nos 1 Doors carpenters + 1 helper
27 Div 08 Frameless Glass panels 30m 2 Metal Masons + 1 helper
28 Div 09 Cement plaster 1st stage 60m 1 Plaster mason + 1 Helper
29 Div 09 Cement plaster 2nd stage 30m 1 Plaster mason + 1 Helper
30 Div 09 Ceramic walls for wet areas 12m 1 ceramic mason + 1 helper
31 Div 09 Ceramic Skirting 30mr 1 ceramic mason + 1 helper
32 Div 09 G.B partition Studs+1st Layer +Insulation 20m 2 mason + 1 Helper
33 Div 09 G.B parititions Closing 50m 2 mason + 1 Helper
34 Div 09 Gypsum false ceiling 20m 1 Mason + 1 Helper
35 Div 09 Metal false ceiling 30m 1 Mason + 1 Helper
36 Div 09 Paint preparation 40m 1 Painter
37 Div 09 Painting Coats 40m 1 Painter
38 Div 09 Vinyl Tiles 25m 1 Tile Layer + 1 Helper
111
Productivity
No Division Item Describtion Crew (Manpower/Equipment)
Rate per day
39 Div 09 Rubber Tiles 25m 1 Tile Layer + 1 Helper
40 Div 09 Marble Tiles 12m 1 Tile Layer + 1 Helper
41 Div 09 Marble Skirting 30mr 1 Tile Layer + 1 Helper
42 Div 09 Marble Threshold 20mr 1 Tile Layer + 1 Helper
43 Div 09 Marble Counter 15mr 1 Tile Layer + 1 Helper
44 Div 09 Granite Flooring 12m 1 Tile Layer + 1 Helper
45 Div 09 Terrazzo Tiles 15m 1 Tile Layer + 1 Helper
46 Div 09 Insitu Terrazo tiles 5m 1 Tile Layer + 1 Helper
47 Div 09 Carpet Tiles 40m 1 Tile Layer + 1 Helper
48 Div 09 Wood Flooring 10m 1 Mason + 1 Helper
49 Div 10 Wall & Corner guards 7 nos 1 Mason + 1 Helper
50 Div 10 Toilet Accessories 5 nos 1 Mason + 1 Helper
51 Div 10 Access Flooring 20m 1 Mason + 1 Helper
52 Div 10 Internal Signage 12 Nos 1 Signage Mason
53 Div 12 Lab Furnitures 10 seats 1 Finishing Carp. + 1 helper
54 Div 13 Shelter Doors 1 nos 3 Mason + 1 Helper
55 Div 15 Laying Water supply pipes 30m 1 plumber + 1 helper
56 Div 15 Laying Drainage pipes 24m 1 plumber + 1 helper
57 Div 15 Laying Fire Fighting Pipes 24m 1 FF Pipe Fitter + helper
58 Div 15 Laying HVAC Ducts 70 kg 1 Duct Fitter + 1 helper
59 Div 15 Duct Insulation 20 m 1 Duct Fitter + 1 helper
60 Div 15 HVAC Piping 20m 1 Pipe Fitter + 1 helper
61 Div 16 Installing Cable Trays 15m 1 Electrician + Helper
62 Div 16 Electrian Conduiting 24m 1 Electrician + Helper
63 Div 16 Wiring Works 400m 3 Electricians + 3 helpers
64 Div 16 Laying Cables 20m 3 Electricians + 3 helpers

112