Ornate International Ltd.
Response: a) Dimensions have been provided and height of partition wall has been mentioned
in architectural drawings. Please check the architectural drawing.
b) Dining and prayer rooms are going to be shifted outside the building confirmed
by the factory owner.
2. Revise as-built structural drawings. Revise beam layout as per actual condition. Mention
thickness of the retaining wall.
Response: a) Beam layout has been revised. Please check the as built structural drawing.
b) Thickness of the retaining wall has been mentioned. Please check the drawing.
3. Revise the live load plan as some mismatch found between the provided load plan and the
live loads assigned in FE model. Mention proper live loads for all the floor areas as per the
floor usage.
Response: Live load plan has been revised and corrected. Please check the live load plan.
4. Revise the FE analysis models. Some mismatch was found between the as-built drawings
and the models regarding beam layout plan. revise as per the actual condition. Assign all
loads properly in the models as some mismatch was found between the load plan and the
models. Assign correct dead loads in the stair zones. Revise the material properties for beams
which require strengthening.
Response: a) Beam layout plan has been revised as per actual condition and all loads have
been assigned properly in the models.
5. Revise the retrofitting drawings as per the corrected calculations and FE analysis models.
Mention the thickness of retrofitted MAT section. Correct drawings as some mismatch were
found between the retrofitting beam layout plan and the retrofitting model. Mention the
embedment depths of the reinforcements with chemicals to be used. Mention correct concrete
strength for retrofitting works in the drawings.
b) recommendations for all the issues mentioned in the initial inspection report.
1. Column Stresses
-DEA has been done and retrofitting has been recommended for overstressed
column.
4. Structural drawings not consistent with each other and with the as built
structure
-Corrected as built drawing has been prepared.
7. Provide working sequence and time schedule for retrofitting works and QC agreement
signed by both parties (Factory management and Consultant).