Professional Documents
Culture Documents
Welcome to
Mumbais
new gateway
to the world!
A shining example of
world-class engineering! If airports reflect the character and
personality of a city, then the new
Mumbai International Airport sports
all the verve and vibrancy of Indias
throbbing commercial capital. And,
Larsen & Toubro, is proud to have
created a gateway for the world that
is truly a landmark of the future. Built
to exacting specifications and by
overcoming innumerable challenges,
this very complex brownfield project is
yet another sterling example of L&Ts
engineering prowess and reaffirms its
leadership position in providing total
infrastructure solutions for a new India.
We started our MIAL journey almost out the work. Simultaneously, we The magnitude of the project was
6 years ago and as EPC contractor had to co-ordinate with airline almost too huge to consider. Every
for the entire project, our challenges industries across the world through day about 15,000 workmen, 1,000
were mindboggling! It was one NOTAM that gave no room for engineers, 200+ sub-contractors and
of the most complex brownfield failure or slippages. A concourse was some 4000 of their staff turned up for
projects that had to be executed built to join the two terminals while work. 250 engineers and architects
The new Terminal 2 of Mumbai project requires extensive country, every time we pass without disrupting the operations a 3.3 km, 6-lane elevated corridor formed the on-site design team
International Airport is truly globally planning; time bound schedules through it, we will cherish and of a fully-functional airport! We had connected the airport with the while expats were mobilized from
benchmarked for its architecture, and constant monitoring to ensure take pride to have been associated to double the passenger capacity of Western Express Highway to address the world over for various functions.
design, quality and cost. I have timely execution of elaborate with this dream project. Indias busiest airport by building a Mumbais traffic problem. The 83.8 Project planning, which was globally
not seen many, in fact, any other engineering. T2 of the Mumbai massive infrastructure right in the metre tall ATC tower and the terminal benchmarked, involved handling of
airport even outside India that is as International Airport represents It is good to have associated with heart of Mumbai with no extra land building, which incorporates the more than 200 specialized national
good as this one! Unique in terms one of L&Ts best performances GVK who also share our ideology to expand, no time to shut down, dancing peacock in every element and international agencies.
and reflects the flawless teamwork in partnering only with the best to highly sensitive from a commercial, is an engineering marvel. The latest
of the synergy of aesthetics and
and smooth coordination that political and security point of view; technologies such as rubbilization At the end of the day, we had to live
functioning, this is easily one of the bring about perfection. I am glad
and finally, world-class quality to be for apron construction, high rise up to the expectations of a lot of
most beautiful airports in the world. have become synonymous with that L&T was a part of creating
delivered in a limited time frame. jaw crushers for dismantling, hot stakeholders the client, the airport
us. Now, that the airport is fully Mumbais first public building that tapping for diverting live fuel authorities, the Government, the
The overall framework and operational and has become also doubles up as an art project. It The new terminal building, lines, carbon reinforced fiber local statutory bodies but none as
concept for this kind of gigantic an important landmark of the constructed over the footprint of
is a national symbol! technology for strengthening an big as the passengers themselves.
the existing international terminal existing bridge under the operating And we did that in style, which
building, on a built-up area 4 runway, erection of 28000 tons of is typical for every L&T executed
times larger was made possible structural steel roof using launching project.
by demolishing several existing girder over 40m tall highway
structures. On the Airside, we had trusses, were all a part of the Hats-off to the entire MIAL project
to reconstruct two existing runways mechanization strategy adopted to team for having created such a
with defined time windows to carry quicken this project. marvelous edifice!
As the ever-throbbing commercial capital of India, Mumbai has a number of facets to be 80,000 light fixtures, 750 kilometers of conduiting and another 250 kilometers of HT/LT
proud of and we are honoured that we have been able to add to that long and illustrious cables, 940 chandeliers, 3,000 CCTV cameras, some 26,000 data points, a Diya
list with a gateway that is truly world-class and representative of the exuberant Wall with 1,000 LED lamps the numbers are totally awesome but that was our
spirit of Mumbai. Our journey commenced with a vision to create one of the challenge in the Electrical and IT space. It was our responsibility to breathe life
and infuse light into this huge structure. The magnitude of the task was huge
most sophisticated, state-of-the-art and picturesque airports in the world
that called for micro-planning. Each and every aspect, however insignificant,
and I am absolutely delighted that we have been able to translate this lofty had to be checked and approved because back-tracking would have cost us
vision into breathtaking reality. The challenges that we encountered at time, which we did not have and erosion of our margins which we could not
MIAL were unique that required an equally unique and robust team that allow. We were dealing with a plethora of suppliers from around the world and
could drive the project with passion. And they did so quite splendidly! had to be ever-vigilant that deliveries and installations were happening like
The MIAL project has showcased to the world, L&Ts construction prowess clockwork. Several new technologies and methodologies were adopted to
and seamless project management capabilities. Perhaps, what is even fast-track the project like using multiple conduits instead of cable trays
more satisfying for us is that through this project, we believe, we have been and flexible cables for wires. Our team was young and dynamic driven by
able to take stakeholder satisfaction to an all-time high. After all, we are the urge to create systems that shall suffer no downtime! At the
not only in the business of creating landmarks of the future, we are also end of the project, we are proud for having contributed in the
transforming lives for the better. creation of a masterpiece.
The project was very complex with multifarious challenges that had to be resolved, phase-wise, Making a thousand peacocks dance was the vision with which the finishes team took up the
as we proceeded and kudos to the entire MIAL project team for having succeeded despite MIAL project. Every single square inch of the terminal, be it interior or exterior, had to
seemingly overwhelming odds. Some of the operative words that describe the MIAL project have the touch of perfection to not just create a landmark project, but an edifice that
are Planning, Co-ordination, Quality, Execution and Timeliness. Managing the huge would be regarded as one of the worlds most stunning airport terminals. The numbers
work force was like leading an army with so many people, who were experts in their were mind blowing, 80,000 sq.m of GFRG canopy, 1.83 lakh sq.m of granite, 1.10
various domains, drawn from various parts of the country and the globe. Since lakh sq.m of metal ceiling and 30,000 sq.m of carpet. With such mega volumes
we were working to stringent deadlines, it was imperative to get the right involved in every procurement item, standardisation was indeed a challenge.
resources at just the right time. Overall, it was one of our toughest Detailed method statements followed by mock-ups and strict adherence
assignments but we were able to deliver a world-class facility on time, thanks to the charted sequence of execution made implementation seamless
to the qualities that sets L&T apart, its design excellence, construction and smooth. The swank finishes have truly created the intended wow
capabilities, the freedom to take calculated risks all brought together effect with even the Prime Minister of India terming the terminal as
by unmatched teamwork which contributed to the creation of this The Pride of the Nation.
beautiful edifice.
When we embarked upon the project, the entire footprint of the proposed For L&T, MIAL was the fourth international airport project in an Indian metro, and although the
terminal measuring 125,000 sq.m was occupied by various facilities. The considerable experience gained from these previous projects did hold the team in good stead, we
teams primary task therefore was to plan and create the required footprint, were yet faced with a whole lot of challenges hitherto not faced that required new and innovative
inch by meticulous inch by demolishing to commence construction. solutions. Considered perhaps the worlds most complex brownfield airport project, the planning
This called for consistent out of the box thinking from the team in for MAIL combined several unprecedented dimensions and the team faced them head-on. Our
terms of construction sequences, erection methodology and innovative goal was to create a global landmark. Sharp planning and committed implementation, coupled
equipment to be deployed. Getting it right the first time was the operative with rigorous follow-ups, saw the project progress at unbelievable speeds. Once commissioned,
phrase for the planning team simply because there was neither the time the task of testing, commissioning and successfully integrating over 75 MEP, airport and IT
for rework nor room for deviation. Activities were planned and scheduled systems and carrying out 200 project operation trials was arduous but completed, thanks to
in tandem such that when combined with faultless execution, it would seamless cross-functional interfacing. The sophisticated electro-mechanical and IT enabled
bring out nothing but the expected results. An indomitable BHS, HBSS, VHT and PBB airport systems called for impeccable standards of execution and
spirit, steely determination and unfailing commitment became commissioning. The remarkable six-lane elevated corridor constructed right over a busy
the work culture at the MIAL project site which transformed an operational at-grade road has become a marvelous dedicated access to the terminal. The
ambitious dream into reality. The successful completion of the success of the MIAL project was indeed a perfect performance through flawless teamwork
MIAL project has greatly boosted the self-confidence and pride of everyone involved in it. and smooth coordination.
The name of the mighty Maratha king sits well on the Mumbai International
Airport for its resplendent splendor. The project is unique as it is perhaps one of
the very few airport expansion projects that have been successfully completed
despite the challenges of being a brownfield project, in the midst of a fully
functional airport with only limited space available to operate smoothly as well
as to expand in tandem to futuristic needs.
40 million by 2015 tonnes of cargo per year to close to 40 Airports Company South Africa (ACSA)
million passengers and about a million Global and Airports Authority of India
A master plan was developed with a tonnes of air cargo shipment by 2015. (AAI). MIAL was awarded the mandate
vision and framework for the long-term for operating and modernizing the
but at the same time realistic in the Mumbai International Airport Chhatrapati Shivaji International
Airport (CSIA), Mumbai in April 2006.
short term, to build a swanky world- Pvt. Ltd. GVK leads the consortium with 50.5%
class airport factoring in the limitations
Mumbai International Airport Pvt. Ltd. stake while BSDM holds 13.5%, ACSA
and challenges. The aim was to increase
(MIAL) is a Public Private Partnership Global 10% and AAI the remaining 26%.
the present capacity of handling 25.6 MIALs vision is to transform CSIA to
million passengers and 0.5 million joint venture between GVK, Bid Services
one of the worlds best airports. Exterior view of Terminal 2
Division (Mauritius) Limited (BSDM),
The baggage handling system of the Mumbai International Airport has been
designed and executed, embracing many new features and services, to make
the processing of hold baggages easier, less stressful and reassuring for
passengers.
Picture this. If nearly 3 billion precision. Surprisingly, the truth is The baggage handling system of
passengers enplane every year that all this is accomplished by an the Mumbai International Airport
at CSIA, one can well imagine efficient Baggage Handling System has been designed and executed,
the amount of hand and check-in (BHS) with a lean team operating and embracing many new features and
baggage that has to be handled. The managing it. This becomes critical services, to make the processing of
thought itself can be intimidating especially since baggage mishandling hold baggages easier, less stressful and
and it would be natural to imagine can be an expensive affair for it cost reassuring for passengers. Initially
many thousands of hands and minds the airline industry a whopping $2.06 planned to cater to passenger traffic
working to ensure accuracy and billion in 2012 alone! of 9600 bags/hour up to 2015, the BHS Baggage make-up area
Distribution Systems (MDS), database management systems, baggage processed messages to the airport host. The HLC
management information systems, baggage information equipment and the LLC devices are linked via the networking
systems and baggage information display systems. edge switches located at the BHS field.
BHS receives flight information, baggage source messages The entire BHS system monitoring, control and visualization
with real time updates and communicates the sort destination is centralised via SCADA (Supervisory Control And Data
Aerial view of tilt tray sorter
be diverted to the bomb cooling pit of 4, transporting through Levels 3 and The baggage is supplied one by one from
the airport through an automated lift 2 to the make-up carousels in Level 1. the conveyor lines to the first belt on the
system and subsequently to threat bag The check-in facility has 6 islands for induction where the TTS control system
carrying vehicles. economy passengers with 28 counters inducts the baggage onto an empty tray
on each island totalling to 168 counters. on the sorter, scans its barcode tag,
Design features The 2 CIP VIP exclusive check-in transports it to the sorter and tilts it into
facilities have 10 counters on each a predefined carousel through the chute.
The foundation of this well-designed island. The bags are transported to the
baggage system is an optimised 18 make-up carousels after the security Control system
mechanical layout, complete with and custom screening as per the flight
the conveying lines, maintenance allocation. Majority of these conveyors The lifeline of the BHS is the control
accesses, screening machines and are designed as suspended structures system that handles all the conveyors
processes complying to the prescribed from the deck above, allowing the and sortation devices which are divided
security standards viz. International space below on the ground for drive-in, into Low Level Controls (LLC) and High
air transport association, International loading and drive-out functions. Level Controls (HLC).
civil aviation organisation, Bureau of
Indian civil aviation security, European Tilt Tray Sortation LLC includes all elements involved in
security standards, Transport security, the PLC (Program Logical Controllers)
Administration, etc. The Spine of the baggage handling based control of the equipment such as
system is the Tilt Tray Sortation (TTS) panels, sensors, actuators, etc. All bags
The design of the layout had system which distributes the bags to the are virtually tracked and sorted to the
been validated through computer respective make-up carousels through designations as per the screening results
simulations and emulations to verify the tilting mechanism. The airport by the PLCs.
the design and determine the maximum features 2 sorters with 278 trays on
baggage processing time apart from each sorter operating at a speed of 1.9 HLC includes all elements of the
system throughputs as defined in the m/s giving it a capacity to process 5400 control system above the PLCs,
specification. bags/hr. The baggage from the check- including networking of equipment,
in/transfer conveyor lines is supplied servers, workstations, etc. It controls
The departure system is laid out to two LS-4000E Tilt Tray Sorter via the IT system of BHS which includes
declining from check-in hall at Level inductions. sort allocation controls, Message Vertical sorting unit
Escalator
With a capacity to handle 9000 persons
/ hour, the heavy duty escalators have
a rated speed of 0.5 m/s and rise-
range from 3 to 11.6 m. Among the 55
escalators installed is Indias tallest
airport escalator which rises to 11.6
meters going all the way from the 6th to
10th level of the multi-level car parking
(MLCP). Eight escalators are exclusively
for the transportation of passengers View of elevators and escalators
Escalator set amidst grand interiors between MLCP and the terminal
building. objective of minimal downtime even Interiors
during the design stage. The complete
The interior of elevators had to
All major airports have to envisage heavy passenger flow and hence it is Travelators VHT system has been interfaced with the
Building Management System (BMS) for
be upscale to be in-sync with the
imperative that the building design factors the need for a hassle free and Travelators a.k.a moving walkways have monitoring and well-established brands ambience of the terminal. To meet
the demanding quality parameters of
been thoughtfully provided around the such as Schindler, TKE and Kone offered
relaxed experience at the terminal. terminal to improve passenger mobility. international warranties and excellent finishes, a specialized and dedicated
MIAL features 41 of such equipment service support. vendor was engaged to work
with a handling capacity of 16,200 exclusively on enhancing the interior
persons / hour and a rated speed of 0.65 No stumbling with these look and feel of the elevators.
The vertical and horizontal alone. The number, location, speed consumption. The auto start sensors m/s. If installed one behind another, the
transportation (VHT) system of and capacity of the VHT systems to be ensure that escalators and travelators travelators would measure a whopping challenges Installation
travelators, escalators and elevators deployed was arrived at after a detailed start only on detecting approaching 1.3 km in length. MIAL also features
Logistics VHT being supply items with long lead
aim to ease congestion and ensure a traffic study conducted by an expert passengers to maximise energy the first Pit-less Travelator installed in
efficiency and equipment lifetime. times had to be strictly monitored even
seamless flow of passengers (departing team. Asia which eliminates the need for a Escalators and travelators were
during production and dispatch of
and arriving), goods, baggage, staff and travelator pit and simply rests on the delivered in heavy segments (weighing
The VHT blends well with the aesthetic units from Spain, Germany and China.
visitors. Design and engineering finished floor. in tons) after the main faade work was
standards and aspirations of the terminal In addition to stringent factory testing
completed so it took some planning
183 internal transportation equipment MIALs VHT systems are capable of non- architecture. Consistency in the standard prior to dispatch, experts from these
have been installed at MIAL of which of material used for the escalators and Operations and maintenance and effort to bring these segments
stop operations, in either direction, into the terminal area through the countries were invited to carry out the
177 are located at the terminal area and are designed for low energy travelators was ensured while factors testing and commissioning.
The VHT team embarked with an available openings.
SCADA panels
array of decorative and combination have been designed for trouble free, safe Public area light fixtures - 44,000 nos
light fixtures. functioning with sufficient emergency Non-public area light
backup. Occupancy sensors located fixtures - 13,000 nos
Crowning lights in office spaces automatically adjusts
Chandelier - 943 nos
lighting lumens based on the presence or
Several decorative ceiling-mounted absence of occupants in the room. LED fixtures - 17,000 nos
chandeliers enhance the look, feel and
aesthetics of the circulation area that
have been custom designed like flower
petals to resemble the CSIA logo. The
diffusers are made of Borosilicate float
glass in amber colour.
Efficiently lit-up
The non-public area lighting system is
designed to enhance task performance,
improve appearance and ensure cost and
environmental efficiency. Areas such
as the MEP rooms, substations, baggage
Lighting that integrates skylight and electrical light handling systems, office spaces and closets Decorative ceiling lights at retail area
It was no different in the case of MIAL. systems included procurement, radio), airport operations (Airport
The IT infrastructure was designed to design, planning and progress Operational Database AODB) and
meet such demanding operational needs monitoring, QA / QC and project information message broker also fell
by providing complete user friendly implementation of a dedicated within its ambit. The IT system is a
access at all passenger interface points large scale entity that interconnects
network backbone and flight
apart from ensuring safe operation of the Terminal with the other ancillary
information display system. Security
the Terminal. buildings.
systems (access control and CCTV),
utility systems (public address &
L&T set sky-high benchmarks in Network the backbone
providing a robust IT environment voice alarm, building management,
and the scope of work of the enabled distributed antenna and trunk mobile The network infrastructure connects Interior view of Airport Operations Control Center
Services Centre (ASC), the Engineering Systems integration and Docking Guidance System). It
Systems Management Centre (ESMC), also integrates the mechanical &
and the Telecommunications System
information broker electrical systems such as HVAC, fire
Management Centre (TSMC). Three The systems integration package detection & protection, fuel hydrant
large video walls ensures clear integrates the various IT systems system, electrical power and lighting
monitoring for the operations team. (IT network, BMS, FIDS and PAVA, systems and the airports operational
The AOCC also features a dedicated ACS and CCTV) with the airport database.
visitors gallery for accommodating systems (Baggage Handling System,
high profile visitors and stake holders. Passenger Boarding Bridges, Visual Various systems have been integrated
with the AODB using the Information
Message Broker (IMB) which is
based on Web Sphere Process Server
and Web Sphere MQ. IMB does the
transformation, validation and Cozy interiors that give a soothing experience
information and data dissemination
from one system to others as required. If passengers are greeted by a comfortable ambience of 23C1C and
IMB receives flight data, resource and RH in comfort zone at the Mumbai T2 Terminal it is thanks to the well-
planning information from AODB
to share with other systems, post designed HVAC package.
validation. IMB receives real time
updates like on-block, off-block, Thanks to a well-designed HVAC several zones based on various factors, 100% treated fresh air units supplying
package, passengers are greeted by a requirements and functions and then treated fresh air to tenant spaces such
chute updates, first bag, last bag,
comfortable ambience of 23C1C and accorded weightage based on their as retail, duty free shops, restaurants,
baggage statistics, check-in counter
RH in comfort zone at the Mumbai T2 functions such as IT, critical services, eateries and CIP/VIP lounges within
updates from BHS, FIDS and VDGS that zone.
Terminal and a suitable atmosphere passenger and retail zones.
and sends this information to AODB. for the trouble free operation of critical
equipment and gadgets. The occupancy The terminal building had 13 zones Life safety systems such as smoke
Extensive testing was done in the and fresh air loads are based on with each one having a mechanical extract systems and lift / stairwell
Integrated Test Facility (ITF) as National Building Code (NBC) - 2005 room that housed the Air Handling processor pressurization systems
well as in the actual production recommendations. Units (AHUs) and the heat recovery are based on the respective NFPA
environment, for flawless units for that particular zone. The heat codes. The smoke extract systems for
recovery unit consisted of enthalpy public areas include smoke extract
integration. Design Criteria fans designed for high temperatures
wheel and supply / extracts fans with
FIDs screen of baggage handling system The terminal area was divided into filters. Some mechanical rooms had (300C) and fire rated ducts.
Detailed Engineering and installation. Pipes of about 25 km and that each pipe joint was 100% leak proof
over 300 rmt ducting from AHUs were as rectification of joint failures would be
Installation distributed in the building spread over a extremely difficult once commissioned.
535 drawings were painstakingly very large area. Extensive radiography tests were
prepared and meticulously checked in conducted prior to hydraulic testing to
3D Naviss Works for clash detection Chilled Water System ensure zero leakage.
prior to releasing it for site execution.
For clash resolution, 3D Revit software The utility room located 1.5 km from Air Distribution System
was used as it required coordination T2, pumps 5800 cu.m/hr of water to
with multiple utility services. The the terminal through a 1.1 m diameter, All AHUs are typically two-tier
terminal area was divided into buildings pre-insulated underground pipe located constructions with supply air fans
and levels to enable better control on below the existing roads. It was essential and filters in the lower tier and return
Exterior view of utility complex
air fans in the higher levels. The AHUs water became very dirty on the first on the HVAC system. The controlled
are located in the basement area for fill following installation. About 35 fresh air is then supplied through the
easy maintenance apart from keeping lakh liters of water was used to flush CO 2 sensors.
servicing personnel away from visitor and remove sediments before the final
zones to ensure passenger safety. commissioning. The condensate recovery system
Medium pressure ducting carries was commissioned by pumping low
dehumidified air from AHUs to Energy Savings temperature condensate generated from
conditioned spaces while filters AHUs back to the cooling towers to reduce
with activated carbon and alumina An airport never sleeps. To operate it the cooling tower inlet temperature and
impregnated with KMnO4 (Potassium 24 x 7, the annual power consumption thereby the power consumption apart
of the HVAC system alone could from providing savings in the make-up
Permanganate) are used to combat the
run into several millions which is water consumption of cooling tower.
effect of exhaust fumes from aircraft
unaffordable. The answer lay in Cooling tower fan motors are operated
that could be present in the fresh air. On
energy conservation at all times through Variable Frequency Drives
the upstream side, pre-filters and back
through chillers of very low power (VFDs) for energy savings at part loads.
filters have been provided.
consumption and high efficiency
pumps. The thickness of insulation
Water Flushing and was also carefully selected to
Building Automation System
Commissioning maintain low temperature drop from (BAS)
utility to building distribution. For
To achieve the desired chiller Yet another unique feature of Terminal
all to breathe easy considering the
performance and maintain low power T2 is BAS with 936 (473 DDCs + 463
high occupancy rates, the building
consumption of chillers, it was essential required 14 Lakh cu.m/hr of fresh air VAV converters) controllers and over
to meet the required water parameters which was met by treating exhaust 3300 sensors installed for the HVAC
before circulation through chillers and air through heat recovery units to equipment alone. This system has
Chiller plant AHU coils. Being a large system, the lower the intake of fresh air load been integrated with the Building
Management System for remote Quality yy Chillers and AHUs are AHRI certified
controlling and monitoring of all HVAC and use environment friendly
equipment including Variable Air Several national and international refrigerant (R134A)
Volume boxes for energy conservation standards have been strictly adhered
and comfortable air-conditioning. to, implemented and inspected at yy Motors used in pumps are energy
In addition, the Chiller Management every stage during manufacture, efficient (EFF-1) complying to IS
System (CMS) has also been integrated delivery and installation. 12615
with BMS for remote monitoring.
yy Fire dampers meet UL 555 standards
yy All fans are AMCA certified
Gas suppression system
yy Smoke extraction ducts are 2 hours
fire rated as per BS 476
yy A separate fire paint booth was Risk mitigation at all levels and types are of paramount importance in public
established to ensure uniform
coating quality
buildings such as airports. Large capital is invested for the safe and secure
yy T
he ducting work was carried out
operations of a terminal building and fire detection and protection system
as per SMACNA standards using is significant among them.
appropriate tools and tackles
yy T
he supports were fabricated in a
dedicated workshop and fixed using MIAL features the worlds most area, the FAS equips the fire commander Fire Protection Systems
advanced Fire Alarm System (FAS). with the convenience of extinguishing
laser beam technique to maintain a
Systems such as VESDA (Very Early a fire from a remote and dedicated fire yy Internal hydrant system : 400 nos
straight line and uniformity
Smoke Detection Apparatus) have command centre. The Fire Protection
been deployed using 60,000 detectors System at T2 employs over 50,000 yy External hydrant system : 100
yy Piping is done as per IS -1239 & IS
and devices connected in loops using sprinklers connected with 270 km pipe hydrants connected with 4 km long
589
650 km of cable to offer one of the most and 500 hydrants. Rooms containing ring fire main
yy Standard welding procedures were efficient fire management systems. computing systems have been installed yy S
prinklers : 50000 nos covering
followed as per IS 10234 with gas suppression system that uses
Covering four lakh sq.m of building every nook and corner of the
eco-friendly NOVEC -1230 gas. terminal
Air handling units
Meeting the water demands of an airport terminal is crucial that can allow no
Central alarm control facility
lapses. The PHE package at MIAL had its own share of complications primarily
yy G
as suppression system: for all terminal building was divided into to automatically operate as per the
due the major quantities involved in the scope and due to the large number
communication rooms 350 fire zones as per the fire strategy cause and effect matrix. of vendors being involved for the supply of numerous construction material.
and all important electromechanical
yy P
re - action sprinkler system: Never dampened to meet
and IT services such as HVAC, access
control room equipment protected
with pre action sprinkler system, doors, public announcement system, challenges Even the orders for the PHE package to avoid wall chasing and for easy
baggage handling system and vertical came through in a staggered manner maintenance. Rainwater is efficiently yy 1
0 MLD SBR type Sewerage
with double interlock using air and
& horizontal transport system were The biggest challenge was to create throwing planning and implementation harvested across the entire terminal as Treatment Plant
detection
a system with global benchmarking out of gear several times over during the a green measure and adequate storm yy 4 MLD Sewage Treatment Plant
integrated to meet the requirements
yy W
ater curtain system: installed at while having to interface with course of the project. water piping drains off the runoff
of this fire strategy and evacuation yy 12 Sewage pumping stations
MLCP to isolate the affected area various other services of the terminal. water while manholes at all accessible
plans. A comprehensive cause and The Brihanmumbai Muncipal locations ensure easy maintenance. yy 120 km of piping
Testing & Commissioning of Fire Corporation supplies domestic water to
yy F
irst aid fire extinguishers: 3500 effect matrix was also developed to Several pumping systems of the existing yy 15 Hydro-pneumatic systems
Protection System on finish works the terminal while water for flushing
nos installed for first level of identify the operational mode of the terminal have been refurbished and yy 157 Public / staff washrooms
such as false ceilings, wall claddings is catered to by treated grey water. The
protection electromechanical and IT systems put to use at the new terminal as a cost
and carpeting was difficult that internal drainage system is single stack yy 22 De-watering pumps
falling in the respective fire zones in saving initiative.
yy F
ire water pumping called for close monitoring. Several with hubless CI piping and individual
case of fire alarm activation.
system : 6 pumps connected to 470 advanced pneumatic and leakage venting arrangements. Planning and Sewage Treatment Plant
cu.m underground fire water tank The fire alarm panel provides signal to tests were carried out for gas based implementing the drainage gravity systems. The water input to this system
fire suppression systems during the flow piping was truly a challenge due to For the very first time in India, a 10 MLD undergoes a series of treatments
various systems such as air handling
Integration units, fire dampers, fans, fire shutters testing and commissioning stage to clashes of various other services. Sewage Treatment Plant employing including screen, CASS basin, pressure
ensure safety. UK based CASS (Cumulative Activated sand filter, UF, RO and finally the treated
Integration of the Fire Alarm System of BHS, travelators, escalators, Another striking feature is that all the Sludge System) technology was installed water is discharged for utilization to
is a critical part of the testing and elevators, access controlled doors wash rooms have been provided with which has substantially reduced sludge cooling towers, flushing purposes,
commissioning activity. The complete and public announcement system pipe chases featuring exposed piping volume as compared to conventional gardening and landscaping.
flooring and ceiling panels with awesome chandeliers. of the airport experience to a traveler
just before he/she boards an airplane.
To accord a fitting and royal farewell
panels have been electro-galvanized to a visitor who has already been
Glass Fiber Reinforced decorated using dichroic glass to give
pampered by the splendid interiors
a vibrant look to terminal roof. The following fabrication and are
Gypsum intriguing HRR structure resembles a polyester powder coated using custom right from the entrance, the interiors
honeycomb and covering a vast area colors. Other areas have been finished of the fixed link bridges are exquisitely
Perhaps the first attraction for
of 48,100 sq.m. with a warm wood grain to create a
passengers will be the Head done with soft carpeted floors, artificial
cozy atmosphere. For enhancing the
House Roof (HHR) that has been stone clad walls, acoustic metal ceiling
architecturally finished using Gypsum Acoustic metal false ceiling acoustic property of the ceiling and
to control sound up to 35 dB, sound and automatic glass doors partitions
Fiber Reinforced Glass (GFRG). A The ceiling above most public areas absorbent fleece has been used. About featuring brush finished steel
light weight material, weighing only has been covered with attractive 90880 sq.m of such metal false ceiling handrails.
8 kg/sq.m, GFRG can be easily molded acoustic metal panels. 0.6 mm has been commissioned at the MIAL
into various shapes and have been thick, these cold rolled carbon-steel project. Interior view of fixed link bridges
disputes, mismatches and site clashes. project. The functioning involved key issue resolution meetings with
A floor manager was akin to a project cordial meetings and joint decisions clients. Other responsibilities included
manager for the floor and some of the that kept the client happy at all efficient management of the floor area,
critical tasks handled by him included: times. A systematic problem solving creating better working conditions,
methodology was followed that maintaining workmen discipline and
yy Manage and document front involved weekly log implementation, creating a common resource pool
clearances interface with design and weekly comprising access devices and the like.
yy I nterface point among various
stakeholders
Design
View of the expansive check-in area
Procurement
HSE/QA-QC
The floor team worked upon issue resolutions, interface management and Package teams
Clients
subcontract interactions becoming almost the face of L&T for the client as well Subcontractors
as the internal customer, across disciplines. yy Sequencing, monitoring and de-
bottle necking of works in line with
schedule
yy Ensuring HSE, protection and
The construction of the Mumbai systems, 11 MEP systems and over 20 Floor Team which soon became the housekeeping on the floor
International Airport was very much interior packages, all working with face of L&T for the client as well as the
yy Issue resolution, particularly
like solving a huge engineering jigsaw each other requiring a staggering internal customer, across disciplines.
multidisciplinary problems
puzzle. It involved several teams amount of multi-stage clearances. A This organization mirrored a typical
matrix structure, with the floor manager yy Floor logistics
working feverishly in tandem at the multi-functional core team popularly
same location demanding insightful known as the Floor Team took on becoming the focal point for the various
Floor management expeditiously
management for targets to be achieved the onus of ensuring that everything disciplines.
resolved over 2000 clashes and
as per schedule or even earlier. Project went like clockwork. Issue resolutions, Coordination between multiple agencies coordinated the contractual closure
management had the unenviable task interface management and subcontract was thus effectively streamlined and of additional items which were
of coordinating between 5 structural interactions were all handled by the processes were set-up to manage critical for the completion of the
Baggage reclaim area
contingency, equipment recovery air traffic tower, Terminal 1C where the Individual System Tests
behavior and backed-up data (re) master computer room 1 is located, it Equipment Tests
configuration tests, including any data was necessary to have a master interface
network related components.
diagram, a master system interface list
Integration testing which confirms and sequence of commissioning for
functionality across systems were different systems.
yy Sequencing, phasing and monitoring
conducted in two stages: firstly at the the T&C activities of all systems
integration test facility and then at The terminal was divided into twelve
the site. The tests were conducted in a different blocks identifying the coverage yy Coordination for project operation
controlled test facility. The systems were area of different systems and a sequence trials
connected through a mock-up of the was developed to have a seamless T&C yy Develop sequence of T&C activities
network communications to mitigate with proper monitoring between facilities and readiness for
risks at an early stage with a strong focus project operation trials to commence
on software / firmware functionality of Major responsibilities of T&C yy Master system interface matrix as
different systems. team per different PTS and ICD
yy Commission sequence for different
Scope of T&C yy Develop guidelines and templates
systems
for testing, commissioning, training,
yy 35 systems under the scope of L&T yy Integrate testing sequence for
project operation trials, operation
yy 21 systems by MIAL and maintenance manuals different interfaces
yy 68 interface via dedicated cabling yy Review and validation of test yy Develop integrated T&C schedule
procedures as per the technical
yy 110 interface via shared IT network Testing, commissioning and
specifications, interface control
integration of multiple airport
yy 08 interface via IT shared network documents
systems needed special skills and the
through IB yy Identification and incorporation ability to communicate effectively
yy 835 string testing of special requirements of to define and redefine every single
OMDA, specific standards like requirement so as to advance the
yy 5 group testing
NFPA, ASHRAE, NEC, and client stage of static installation with
yy 55 scenario testing requirements respect to prescribed requirements.
Testing was a crucial stage that preceded the safe and orderly handing over
of the MIAL project. The process of testing the specified and quantifiable
characteristics of an equipment/system guarantees its operability and for the
airport, it was in terms of performance, reliability, safety and traceability apart
from ensuring compliance to the design intent and specifications.
For the final act of a safe and orderly The Master Testing Plan (MTP) for Equipment testing was conducted
handing over of the MIAL project, the project was in accordance to the during manufacturing and factory
testing was the crucial last stage. conditions of the Main Contract (MCoC) acceptance tests whereas project site
Commissioning of the airport involves which L&T had entered into with MIAL. and pre-commissioning tests were done
networking with innumerable entities The main work breakdown for Testing on-site.
such as the client, consultants, and Commissioning (T&C) was made
Individual system tests included
architects and vendors to understand as per the requirements of the MCoC commissioning and performance tests.
every single technical requirement of and was divided into four major stages Commissioning were tests focused on
the project in detail. following a bottom-top approach. additional levels of complexity and Immigration counters
Overcoming multiple
challenges
Though Team L&T achieved resounding
success in the task of airfield works, it
was not without encountering multiple
challenges such as:
yy The existing airport site is land
locked by the surrounding city,
complicating logistics planning
yy Construction in an operational
environment, on top of the existing
pavements that are being used daily
for aircraft operations and parking
had its own complexities
yy The Mithi River diversion was
a complex job. Since the actual
quantity of hard rock encountered
Mithi River bridge
Illuminated view of apron
was 600% more than the predicted and environmental friendly, the of working on a functional runway,
estimate, 25 rock breakers were project team adopted rubblization the project was handed over one day
deployed all along the location for and concrete recycling technologies in ahead of schedule.
completing the job on time the T2 apron development works. The
yy An invisible blast fence was procured
yy Time restrictions for operations were existing concrete was either rubblized
and installed for the first time in
major challenges in-situ or crushed on-site and recycled
India
for reuse as base-course material
yy Frequent disruptions to work due to
by using specialist machineries yy Strengthening of existing Mithi
VIP visits
imported from Europe. The base River bridge under operating main
yy The Mumbai climate which can material underneath the existing runway carriage way was executed
potentially shutdown all works apron pavement was also recycled. before schedule to accommodate
during the monsoon period lasted Apart from material being reused, A 380 (Code F) aircraft
almost 4 months these initiatives also saved a great deal
yy E3 Taxiway was constructed in a
yy Non-availability of existing of transportation requirement and
restricted time during 14/32 runway
underground service layouts thereby reduced the use of fossil fuel.
closure from 10th October 2011 to
Despite the inherent challenges, the 12th January 2012 and was handed
Many reasons for L&T to take over 8 days ahead of schedule
project team successfully completed
approximately 24 lakh cu.m of earth
a bow!
yy N5 taxiway was constructed during
work, 8 lakh cu.m of concreting and 4 yy L&T took up the critical work of main
the restricted time period of main
lakh t of asphalt - a truly amazing feat runway up-gradation involving
runway shutdown for six hours from
considering that it was accomplished restricted timelines from 09 a.m. to
20th January 2012 to 20th May 2012.
without any disruptions to a fully 05 pm with complete confidence
It was completed 10 days ahead of
functional airport. and experience gained from past
schedule
projects. The project was handed
Going green over for air traffic from 05 p.m. to yy Installation of zero radar footprint,
09 a.m the following day. Despite invisible blast fence made of fibre
To make the project more economical this short time period and criticality glass for the very first time in India
Veiw of remote stand for parking
PAPI system
Being one of Asias busiest runways,
Mumbais airport is equipped with
an advanced Precision Approach
Path Indicator System, also known as
Instrumental landing that ensures
View of PAPI lights
displaced threshold design to clear
obstacles around the airport.
redundant fiber network takes care of back-up and ring main supply system
Power and control network / the Airfield Ground Light (AGL) and will power the system within 15 seconds
AGL substations Control & Monitoring System (CMS). of a mains power failure.
Two 11/0.433 kV substations are All the runway circuits are fed through Apron high mast lighting
provided to cater to the AGL system, the a 250 KVA UPS to ensure reliable
operations. In addition, the AGL system
power supply to which is fed by a 11 kV
redundant network system. A dedicated substations are provided with 100% DG As per ICAO requirements, 38 high
The Runway and Taxiway Lighting System have been designed to handle Code
F Aircraft Airbus (A 380-800) which is presently the biggest flying aircraft and
in aviation history too.
The Airfield Ground Lighting (AGL) runways - RWY 14/32 & RWY 09/27 Individual Lamp Control and
provided at Mumbai international - the AGL technology has been Monitoring System (ILCMS)
airport is one of the most technologically designed to cater to cross runway
sophisticated systems with design operations even during low visibility All the AGL light fixtures are provided
capabilities complying to CAT II conditions. Several more advanced with addressable switching devices for
Category as per the ICAO (International and sophisticated features have been better controlling and monitoring and
Civil Aviation Organization) Annexure integrated. to reduce maintenance downtime. The
14 & DGCA CAR (Director General system provides lamp on/off status, lamp
of Civil Aviation Compliance and SFL system failure status to both the maintenance
Requirement). teams and Air Traffic Controllers. The
For the first time in India, the AGL system ILCMS also interfaces with AGL CMS
Some glowing features was designed with Sequential Flash for the Air Traffic Controllers to use the
Lighting System to provide additional routing facility to guide aircrafts from the
Since the airport features two cross guidance for approaching aircrafts. runways to the apron stands. VDGS & high mast lights at apron area
Mumbai is perhaps the only metro in India to boast off an The centre spine was constructed using conventional
airport located right in the heart of the city. Though well cast-in-situ methods with massive staging works whereas
connected to the arterial Western Express Highway, reaching the cantilever portion was precast and connected to the
it can be quite harrowing. To address this vexing traffic issue, a main spine using state-of-the-art stitch concreting and
dedicated elevated corridor leading to an expansive forecourt post tensioned cables. This four lane access way connects
was proposed as a part of the MIAL project. MMRDAs Sahar elevated portion to the airports forecourt
with a deck width of 19.2 m that expands to a whopping 73
The MIAL elevated corridor features some of the best-in-class m (9 lanes along with wide footpaths in front of departure)
technology making it a landmark in its own right. There are as it approaches the terminal departure bay. A couple of two
81 spans of cast in-situ spine connected to a precast cantilever lane ramps enable ascent and descent from the departure
with void former of 2200 mm diameter, a first-of-its-kind level leading to Powai and Sakinaka parts of Mumbai. Three
structure in the country. Another unique aspect is that it connecting ramps at an elevated level of 16 m connect the
contains various types of superstructures comprising of in- MMRDA portion and level 10 of the multi-level car park.
situ PSC & RCC voided slabs, PSC & RCC box apart from I Tree-lined, the deck of the superstructure features attractive
girder spans. While the superstructure is varied in dimension, palm trees and shrubs in the median apart from aesthetic
the cantilever section was precast and erected using specially lighting that adds to the grandeur.
designed launching girders.
Features
Built in a site area of 1200 sq.m, the
tower consists of 3 floors at its base
called the technical block for security
and Airport Authority of India (AAI)
staff for ATC operation. There are 4 floors
at the top called the Stalk and CAB that
accommodates the ATC operational
area, navigation equipment, etc. The rest
Aesthetic elements such as plants and fountains enliven the ambience Illuminated view of ATC sky tower
of the tower between the technical block (50 TR) for cab Level. The staircase and
and stalk is only a RCC shaft housing firemen lift has been provided with one
lifts and staircases. duty and one stand-by pressurization
fan for each area.
Scope of works
Construction methodology
Civil works
The ATC sky tower is unique in its
design, construction, erection and
Plot area: 2800 sq.m (approx.) functional performance. It stands tall
PCC = 125 cu.m from FGL on 11 pile caps of which the
central cap supports the central core
RCC = 4546 cu.m
wall which extends up to +77.80 m (level
Shuttering = 19550 sq.m 0 to level 22) and an inclined skirt wall
Reinforcement = 705 t which connects to the central core at
+62.05 m (level 0 to level 18). Passenger
Structural steel = 260 t and firemen elevators are provided
inside the core with a staircase through
PHE- UG sump works the core from level 0 to level 22.
Domestic tank (2 nos) = 30,150 litres The 1st lift core wall (3 m) was executed
using conventional formwork while
Fire storage tank = 4,24,000 litres further lifts were executed using Retail area at the terminal
Flush (grey water) = 30,552 litres climbing formwork. The technical block
floors followed after the core and skirt
Electrical wall completion up to level-4. The skirt For a project of the size and complexity of MIAL, it was imperative to set
wall ascends right up to 3 lifts below
the core wall and the staircase inside ATC sky tower
project specific quality objectives with regard to monitoring, auditing and
Transformer (2 nos) = 1000 KVA each the core ascends 3 lifts below the core reviewing so as to exceed the expectations of the client, in specific, and visitors
Diesel generator (2 nos) = 1000 KVA each wall using conventional formwork.
Concreting was done using pipe line. Accuracy in profile was achieved by to the airport, in general.
VHT shuttering that involved pre-check and
The skirt wall is connected to the post concrete check surveys. The skirt
Audit inspections and test plans were prepared were taken even for small components
central core at + 62.05 m (level-18). and core walls were constructed using
Passenger Lift ( 1 no) = 800 kg capacity and implemented during project such as screws and nuts before use at the
After the connection of core and skirt, the jump formwork system. Formwork
Annual audit plans that covered every execution. A material approval system site.
Firemen Lift (1 no ) = 1600 kg capacity the preparatory slab was taken up fixing for concrete and installation
department within the project, vendors was introduced and over 350 materials
for erection. During the same time of faade glass panels was monitored Third party tests were conducted for
and sub-contractors were drawn up and were approved in the contractors
HVAC the core continued leaving the beam through an anemometer for wind
status reviewed on a bi-monthly basis works package. An exclusive system every lot of structural and reinforcement
embedment at the respective cab level velocity. The structure has an external steel irrespective of quantity. These
with effectiveness measured once every for material approval of sub-contractor
Air cooled direct expansion type slabs. After erection of the preparatory coat of anti-fungal, dust resistant, and tests also took into consideration the
6 months. works package was also implemented
packaged air conditioning units for slab, the structural steel beams along anti-carbonation paint which involved structural design intent in terms of
by taking approval from designers and
technical block and cab level with with rolla-deck sheets and rebar was a critical procedure of heavy staging durability and seismic conditions. About
estimated cooling load of 190.6 KW (58 fixed in position for level-18 to 20 and around the structure and sequential Monitoring of materials architects from both the L&T and the
MIAL teams. So tight was the material 28000 tons of structural steel and 30000
TR) for technical block and 175.5 KW concreted. painting from top to bottom. tons of reinforcement steel were tested.
Activity based method statements, approval system that due approvals
wall panels, drains, ducts and chambers Quick-set concrete bored piles were completely verified
to reduce construction time and achieve and inspected by deploying a full-time
the desired quality. To overcome time constraints during geo-technical engineer along with a QC
runway overlay works, quick set concrete engineer.
Light weight concrete was used for encasing ducts and pipes so
as to allow usage of the runway within 6 The investigation of raft subsoil of
Light weight concrete having density hours from the commencement of work. Terminal 2 was carried out to determine
equal to that of water was used to the general sub surface conditions and
overcome extended thickness to achieve Milling of asphaltic pavement grout underneath the basement surface
the desired slope and at the same time using ground penetration radar survey
reduce the load on the RC structure in Milled asphalt material was used as a
which is an electromagnetic geophysical
the multi-level car park. substitute to granular sub-base in minor
method for mapping of cavity in rock
pavements and shoulders, thus reducing
anchor and the grout vicinity.
Gypsum plaster cost and consumption of material.
so as to create awareness on quality. Deployment of pour sequence tough task that becomes increasingly
Work methodology was also displayed tougher when the stones are sourced
to achieve consistency in quality. Pour sequence concept for all concrete from various locations across the globe.
pours were introduced covering the To avoid shade variations and to ensure
Vendor Satisfaction Report (VSR) necessary resource, rate of pour and avoidance of unsuitable shades in the
standby arrangement stone works, it was decided to proceed
VSR was implemented to understand
with dry lay of stone before the final wet
the vendors perception of project Shade variation in natural stones
lay. Architects from L&T & MIAL were
organization and thereby facilitate them
Complying with the approved shades, involved in identifying the right shades Work in progress at the bull nose and elevated road network
to build long-term relationships and
when it comes to natural stones, is a of stones to avoid the use of unsuitable
maintain enhanced quality levels.
stones with different shades. This
exercise was done in addition to source
inspection. The strategy of contracts management was focused on creating a better
MIAL team, take a bow! Protection of works understanding of the contract obligations and its implementation at every
level of staff involved in the project.
Protecting the final finished product
yy MIAL, ATC Tower: ACCE(I) - Billimoria Award-2012, Excellence in inside a terminal building where several
construction of high rise building/structure other activities were proceeding in
yy MIAL, ATC Tower: Commendation award from Golden Peacock Jury for tandem was important. For instance, The contracts management team strategies with foresight considering The lofty aspirations of the client (GVK)
occupational health & safety in 2011 protecting the granite flooring and glazing comprised a clutch of expert talent future risks. to create a world-class airport saw the
from breakage or scratches was very with world-class specialization to project team relying on the capabilities
yy Rajiv Gandhi National Quality Award-2011, Commendation certificate with
difficult. Replacing the damages involved However, the MIAL project had certain of several third party organizations that
a Silver Plaque under the category of large scale service industries from guide and support a young and
cost, time and other complications since unique characteristics rendering had no prior presence in India. This
Bureau of Indian Standards. dynamic mainstream staff team.
most of such materials were imported. contracts management, in general, considerably increased the need for a
yy MIAL, ATC Tower won the Outstanding Concrete Structure Award-2013 Backed by the benefit of steep learning
Special protective measures were and risk management, in particular, robust and efficient risk management
from Indian Concrete Institute curves from three other mega airport incredibly challenging. The fact that this
adopted such as covering the stone works strategy.
yy MIAL twice won L&Ts internal Annual Quality Trophy 2010-11 and 2012-13 construction project contracts at brownfield project was located in the
with commercial plywood and wrapping
in major job sites under Airport business unit. breakable materials like glass with Hyderabad, Bangalore and Delhi, the middle of one of Indias most densely The strategy of the contracts management
cardboard sheets. team formulated experience-based populated areas was a major challenge. team was focused on creating a better
An administration teams
work kicks-off way before
even the mobilization
process begins for a
project.
In the case of MIAL, the challenge for
the admin team was to provide suitable
and comfortable accommodation for
all the staff members who were trans-
located from various parts of the country
and, perhaps, the world. This involved
a staggering 450 families and about 350
bachelors.
yy 1
200 vendor (sub-contractor) codes
created
Business continuity and back- Managing the back-up process
up service yy 8
1412 documents handled in
True data protection requires EDMS
yy Daily back-up and reporting
continuous management. As new data
yy Daily monitoring and maintenance yy 3
8,000 purchase orders processed
is created and changes made, back-up
of back-up status
processes and storage devices have to through SCM module
yy Regular testing of restore
availability be monitored, tested, and updated. The
yy Data recovery MIAL IT team successfully addressed
View of TC closet
During the construction phases and the life-cycle of a building, large amounts
of information are handled that enables task control, data integration,
material and resource control and communication exchange between the
company and its suppliers. In the MIAL project too information technology
played a vital role.
Organizations depend heavily technology in order to achieve time, Fully managed IT support
on Information Technology for cost, and quality goals. services
creating, processing and protecting
data. Construction projects are no Project Management yy Round-the-clock monitoring of
exception and require extensive servers, firewalls and critical devices
Armed with project management
exchange of data and information software, contractors were able to manage yy Remote support for computer/ EIP
between the project participants complicated business processes with issues when identified by monitoring
on a regular basis. It is therefore of planning, organizing and managing the service or help desk
paramount importance that project various resource pools available ensuring
yy On-site services
management remains adaptive to efficient project execution, high quality
newer developments in information results and overall business profitability. yy Voice enabled tech support State-of-the-art design facility
The speed of
construction depends
on how advanced is
the equipment that
has been deployed at
the site.
Planning resources such as man &
machinery were unique for MIAL due
to the sheer volumes and the high
fluctuations in requirements due to
staggered receipt and packaging of
jobs. It was therefore the responsibility
of a specially formed central resource
planning team to mobilize, deploy and
demobilize all critical resources such
Workmen arriving to start the days work at the check-in hall
as batching plants, steel service centre,
formwork, plant & machinery apart
from workmen and staff with the twin and labelled in detail to ensure easy right machine was made available based Material
objectives of optimum utilisation of identification at site. on the construction methodology and
resources at levels and avoidance of programme schedule which propelled Handling enormous quantity of bulk
any compromise in the progress of the Plant and machinery the progress of work as scheduled. materials such as aggregates could
project. In several packages, the project was result in erroneous quantification of the
Plant and Machinery (P&M) was the completed ahead of schedule due to the physical stock. Hence, third party survey
Formwork engine that powered the project. The innovative deployment of P&M. teams were hired to ensure the accurate
quantification of available physical stock.
Handling 7600 tons of formwork
material and reconciling such huge stock Major Plant & Machinery deployed by L&T
periodically is humanly impossible, Workmen
if attempted manually. A dedicated Equipment Quantity (nos)
software was developed for this which Terming the workforce that trudged
Batching Plant (60 - 120 cu.m, combined capacity - everyday into the project as an army
also avoided duplication during manual 04
315 cu.m/hr) would have been an understatement. The
counting. Item-specific 2-D bar-coded
stickers were developed and used on Hot Mix Plant (200 TPH) 01 manpower exceeded 15000 during peak
the formwork material for faultless Steel Service Centre - 2000 t / month 01 periods of construction. Mobilising and
inventory management. retaining workmen of such huge numbers
Tower Crane 11 across disciplines of construction was
Weigh Bridge - 330 t capacity 05 certainly a challenge that was overcome
Steel service centre by tying-up with social organizations to
Soil Compactor - 10 t 02
Since huge volumes of rebar had to source rural unskilled labour. An on-site
Wheel Loader 05 training centre established with the help
be cut and customised for concreting,
a sophisticated steel service centre Boom Placer 03 of L&Ts Construction Skills Training
with 3000 t per month capacity was Institute, trained such raw workforce
Sensor Pavers 02
established right at the early stages greatly enhancing their skill levels
Concreting Pumps (30 & 60 cu.m/hr) 06 within short periods. Suitable workmen
of the project that helped automate
rebar works. Wastage was substantially Transit Mixers 04 tenements were planned at the vicinity
reduced by using bar bending schedules of the project along with management
Power Generator (6556 KVA) 54
(BBSs) with RC CAD software and other of daily commute using the dedicated
Welding Machine 25 services of 130 buses from Mumbais
special software to optimize the cutting
schedule. The cut rebar were organised EOT Crane 03 BEST undertaking.
Massive formwork used for painting the ATC sky tower
High-reach jaw crushers in action along with blowers Strengthening the bridge over
the River Mithi under the
main runway
Cable net wall structure a clean and seamless look including all
the capabilities of a conventional wall An aircraft takes off from Mumbai
MAIL uses a highly transparent system. MIAL is also benchmarked for airports runway every three minutes.
structural glass system called using the longest unidirectional cable To withstand the impact of so many
the cable net wall structure that net wall structure in the world, the frequent take-offs and to support
eliminates the use of conventional only cable wall of its type that uses gigantic aircrafts (such as the Airbus
support structures, utilized are pre- sharp corners. Three types of systems A 380) that weigh close to 600 tons,
tensioned cables arrayed in vertical have been used, such as, building the bridge over River Mithi had to be
or horizontal patterns. This glass wall to roof, building to building and strengthened. CFRP (Carbon Fibre
structure gives the transparent facade roof to roof. Reinforced Polymer) was used to
MIAL had several firsts and numerous path breaking innovations to be proud
of in the areas of construction, demolition and recycling of construction
waste.
Demolition by hydraulic yy The total quantity crushed was was isolated from the remaining
32,000 cu.m of which reinforced portion using diamond wire
concrete crushing machine concrete alone was 16,000 cu.m cutting of concrete members such
as slabs and beams.
Destruction for construction was an
y y About 13,000 cu.m of RCC ramp
oft used term in the MIAL project as at a height of 23 m and about yy Reinforcement retrieved from the
several existing structures had to be 35,000 sq.m floor area of the 20 scrap alone amounted to 2500 tons
demolished to make way for the newer m high terminal building was of steel
ones. For this a 26 m high reach boom demolished.
hydraulic concrete crusher and a dust yy Resulted in 35 % savings in cost
boss water spraying machine were yy Only a portion of the slab and when compared to conventional
used in combination. ramp that was meant to be retained demolition methods
Structural steel erection using highway truss
Contributors for the articles Orders Valued `6718 Crs in the bag!
L&T Construction has won new orders order from the Gujarat Water water system and heat rejection
Project planning & control : Rajesh Kanade, Supply and Sewerage Board for the system at Gujarat apart from other
cumulatively worth ` 6718 crores
Rushikesh N Jogdand, Manoj G construction of an underground orders. The Power Transmission and
across various business segments
Baggage handling system : Rajesh Kanade, Ramanujam, in the period October to December drainage system in nine towns of Distribution business has bagged
Sumesh M 2013. Among some of the major Gujarat. turnkey orders in several parts of the
orders bagged is the construction of country and an international order
Passenger boarding bridges : Rajesh Kanade, Ramanujam, The Heavy Civil Infrastructure
a green-field international airport in has been won for the construction of
Manoj Jadhav Business won orders from the
Kannur, a super speciality facility for a 132 kV transmission line.
Vertical & horizontal transportation : Rajesh Kanade, WE Sampath, the Safdarjung Hospital, New Delhi Department of Atomic energy for
Kumar Pranav and the construction of a sinter plant design, engineering and supply of
in eastern India. The Waste Water thermonuclear reactor components
Electrical works : D.C. Mallick for cooling water system, chilled
Business secured a major turnkey
Lighting works : G. Bhowmick
IT systems : Sagar Sunil Agrawal
Maharashtra CM flags off Indias Making its presence felt at the Modern
first monorail Airports Africa 2013 Expo, Nairobi
The Chief Minister of Maharashtra, Africas premier summit on airport
Mr. Prithviraj Chavan, and Deputy Chief infrastructure, Modern Airports Africa
Minister, Mr. Ajit Pawar, inaugurated the 2013, was held in Nairobi, Kenya
Mumbai Monorail on 1st February 2014. The on 19th and 20th November 2013 in
formal flag-off took place at Wadala Station, which L&T Construction displayed
and a plaque to commemorate the occasion its comprehensive capabilities in
was unveiled at Chembur Station. providing EPC services for the airport
infrastructure sector.
Mr. K. Venkataramanan, CEO & MD, L&T,
attended the inaugural ceremony, along Mr. T.Krishna, Segment Head
with several senior political leaders of Airports, made a presentation on L&Ts
the city and representatives from the comprehensive and multi-dimensional
state government. Commenting on capabilities in airport construction
L&Ts role in building the countrys first- at the conference. He stressed on the
of-its-kind mass rapid transit system, advantages of having EPC mode, an
Mr. Venkataramanan expressed happiness emerging trend in the region, for
that L&T played a key role in a landmark construction in Africa.
project that the Chief Minister had said
would give Mumbai a new identity. An impressive pavilion projected
the companys capabilities in airport
The elevated guideways on which the construction by displaying signature
monorail runs was among the many system, power supply & distribution, the many high-profile infrastructure airport projects and ATC Towers
challenging civil construction projects as well as the automated fare collection projects executed by L&T on a total executed in India & the Middle East. were among the other exhibitors. The demand of tourism in Africa has
undertaken by L&T. The Companys system and interface management. The turnkey basis in consortium with Scomi Airport Authorities from Kenya, Kenyan double digit growth at the existing created opportunities at regional and
role also extended to the DC traction Mumbai Monorail is the latest among Engineering Bhd. of Malaysia. Airways, Uganda, Zambia and Ghana Airports coupled with growing international hubs.
Gold rating awarded by Indian Green Presence at the Rail and Urban
Building Council to several projects Transit expo
Solar business releases manuals and 15th anniversary of L&T Build India
documents for effective process flow Scholarship
Mr. S.N. Subrahmanyan and Dr. Srinivasan Sunderrajan, Director,NIT Trichy exchanging the documents
To commemorate the milestone of Managing Director, Dr. A. Ramakrishna, Infrastructure vertical and co-
the completion of 15 years of the L&T way back in 1997, this programme that ordinator of the programme, shared
Build India Scholarship, an unique began with just 40 engineers has now the journey of BIS from 1998 and
industry-academia collaboration blossomed into one of the best industry how based on the feedback from all
towards transforming engineers into initiatives and has produced more than stakeholders at the 10th anniversary
construction technology managers, a 500 of the finest engineers and leaders. in 2009, the programme was greatly
one-day conclave was inaugurated on Since L&Ts projects are spread across enhanced to benefit all.
21st February 2014, at L&T Constructions the country, we are taking efforts to
Head Quarters campus in Chennai. expand this by getting other institutes of Significantly, on the sidelines of the BIS
The Solar Business recently released The manuals were released by Mr. document on Standard Erection Conclave, Mr. S.N. Subrahmanyan and
Entitled the BIS Conclave, the event eminence on board, he added.
Operation & Maintenance training S. Rajavel, EVP and Head, Water & Drawings of Solar PV plants was Dr. Srinivasan Sunderrajan, Director,
saw the participation of the Dean
manual, Testing & Commissioning Renewable Energy IC and were handed released by Mr. R. Srinivasan, Proud of this achievement, he stressed NIT Trichy, signed and exchanged a
and professors from IIT, Madras, IIT
manual, Standard Erection Drawings over to the respective department heads. VP and Head, Renewable Energy, the importance of adding a few crucial MoU to adopt and implement the BIS
Delhi, NIT, Suratkal, NIT, Trichy; senior
document for Solar PV Plants and Man- The Operation & Maintenance (O&M) Security Solution & Smart Grid BU areas to the curriculum like quantity programme in NITs Trichy campus
leadership from L&T and more than 300
day master for CSP. manual will greatly help the site team and will help in standardization of survey, estimation, facility management, too.
BIS staff working with L&T including the
in structuring and constantly reviewing erection procedures, increasing the legal and commercial so that students
These manuals and documents were current batch of BIS students.
their day to day operations. Not only productivity and quality of work and could acquire both theoretical and Professors from IIT, Madras and
made by the Solar team for effective will it help in the easy induction of new sub-contractor management. Delhi shared their experiences
For the last 15 years, L&T has been practical knowledge of managing mega
process flow and are expected to: engineers to the team but also in their and Professor Koshy Varghese of
backing this unique initiative which has projects. L&T Build India Scholarship
better understanding of the Solar PV Man-day Master (CSP Plants) was IIT, Madras, said that BIS was the
become an avenue to transform bright has already given a fine crop of engineers
yy Achieve operational excellence plants for tension free and high quality released by Mr. Shaji John, Head, longest running programme in IIT
young engineers into great leaders to L&T, for the industry and for the
yy Standardize the procedures and maintenance practices. Solar Business and will act as a ready having achieved several milestones
through a structured programme and country and has become a one-point-
processes reckoner for costing, site operations like the first such programme to be
training at college and project sites, stop for people who dare to dream and
The Testing & Commissioning (T&C) and scheduling, thus improving the awarded the ISO certification. They
yy Improve the efficiency of site said Mr. S.N. Subrahmanyan, Member aspire to become leaders, he concluded.
manual details the practices to be reliability of planning and reducing also referred to various technical
operations of the Board and Senior Executive
followed in a very user friendly the time. Earlier in his welcome address, advancements made at different
yy Inculcate a sense of knowledge Vice President (Infrastructure and
and structured manner to improve Mr. A.L. Sekhar, Executive Vice L&T project sites contributed by BIS
sharing Construction), L&T. With the vision
process quality and efficiency. The President & Head, Heavy Civil scholars.
and initial efforts of our former Joint
MoU signed with NIT-K Surathkal - L&T bags The Economic Times Good
to enhance industry-institute partnership Corporate Citizen Award
The Finance Minister, Mr. P. Chidambaram,
A Memorandum of Understanding presented to L&T, The Economic Times
was signed by L&T Construction with (ET) Good Corporate Citizen Award
the National Institute of Technology- at a glittering function in Mumbai on
Karnataka, Surathkal on 4th November December 07, 2013.
2013 to enhance Industry-Institute
partnership between the two The award was received by
organizations. The MoU was signed by Mr. A.M. Naik, Group Executive
Mr. S N Subrahmanyan, Sr. Executive Chairman. The Corporate Citizen Award
Vice President (Infrastructure & is part of the prestigious annual bouquet
Construction) and Prof. Swapan of Awards for Corporate Excellence
Bhattacharya, Director, NIT-K at an presented by ET - Indias largest selling
event held in the Manapakkam campus, business newspaper.
Chennai.
Accepting the award, Mr. A.M. Naik
As per the MoU, NIT-K will partner L&T said, As a concept, CSR is ingrained
in implementing the L&T Build India in our DNA and has been part of our
Scholarship (BIS) Programme, under value system long before it became
which L&T sponsors a two-year full time largely realised to do so. There is no
M.Tech Programme in Construction short cut. The only way growth is
Technology & Management (CTM). sustainable is when growth is inclusive.
The L&T BIS Programme is a flagship The awards jury cited L&Ts steadfast
programme of the companys Industry- commitment to CSR over the years. It the marginalised sections of the society going interventions in education, skill
Academia initiative, which has been said that over 700,000 people among have been beneficiaries of L&Ts on- building, and mother and child care.
running for the last fifteen years
in partnership with IIT-Madras and
IIT-Delhi. Several additional areas
of collaboration, like Research to
Commercialisation were also discussed. KVR conferred with a Life Time Achievement
award at the 4th EPC World Awards 2013
Speaking on the occasion, Prof.
Bhattacharya said that L&T was held in
high esteem throughout the country
for its professionalism and innovative
management approach, as well as
for its role in building the countrys
institutions. He lauded the L&T BIS
initiative as an extremely innovative
Mr. K V Rangaswami, Advisor to
one in the area of Industry-Academia
the Group Executive Chairman was
interaction.
conferred with a Life Time Achievement
SNS stated that with the ever Award in recognition of his outstanding
growing need for skilled technical contribution to the construction industry,
personnel, the time had come to at the 4th EPC World Awards 2013 held on
expand the programme in 14th December at Hotel Ashok, New Delhi.
partnership with other premier
The EPC World award recognizes and
academic institutions and said that NIT-K
honors companies/individuals broadly
Surathkal, with its impeccable academic
covering the entire Infrastructure &
credentials would greatly enrich this
Construction industry on the basis
long-term partnership through
The signing ceremony was also Department of Civil Engineering and of their qualitative and quantitative
increasing technical collaboration
attended by the Business Heads and Prof. M.B. Saidutta, DeanAlumni performance during the year 2013.
in the field of Construction
Technology, Management, Engineering HR Heads of L&T Construction and by Affairs & Institutional Relations,
and Research. Prof. Katta Venkataramana, Head NIT-K.
100 ECC CONCORD, October13 - March14 ECC CONCORD, October13 - March14 101
Awards Awards
This EPC World award recognizes and This coveted innovation prize was
honors companies/individuals broadly received by Mr. R Srinivasan, VP & Head-
covering the entire Infrastructure & of PT&Ds exceptional contribution in committee, Jury and Knowledge Partner Renewable Energy BU, Mr. Shaji John,
Construction industry on the basis the Power Transmission & Distribution - Ernst & Young unanimously decided to Head- Solar Business and Ms. Harshitha
of their qualitative and quantitative sector, with fine examples of works honor L&T Constructions PT&D IC for S Kumar, Head- Microgrid and Rooftop
performance during 2013. In the light & projects delivered, the Organizing its outstanding contribution. PV Systems.
Company of the Year award for Bulk spectrum of L&Ts capabilities through
executed solar projects. Over 170
exhibitors in the areas of Photovoltaic
102 ECC CONCORD, October13 - March14 ECC CONCORD, October13 - March14 103
Awards Awards
Pragati Towers project awarded for Best Construction Contractor Award for
Engineering Excellence L&T Oman LLC
The Best Construction Contractor Award
Pragati Towers, a multi-storeyed was bagged by L&T Oman LLC at the
total precast residential building Dossier Construction Awards 2013 for
constructed by L&T was conferred the innovative and successful steps in the
Third Best Engineering Marvel Award construction industry (commercial,
2013 for its innovative features. institutional, residential, civil and roads
The project has also won the Public sector) in Oman. The selection was
Choice Award 2013 from Engineering based on clear and consistent leadership,
Watch Magazine for Engineering commitment to core Constructing
Excellence. Excellence principles across projects
and activities that have left a lasting
This honour was received by impression on the industry. This award
Mr. Madhav P Deshpande (Segment was validated by the prestigious auditing
Head Affordable & Mass Housing house KPMG.
RB&F BU) and Mr. K Senou (Head-
Precast Initiatives RB&F BU) from Shri. Dossier Construction is Omans first
Sushil Kumar, Member of Parliament and only Business to Business (B2B)
and Prof P.B Sharma, Vice Chancellor magazine for the last seven years.
of Delhi Technological University on Published by United Media Services
(UMS), Dossier-Construction is a This award was presented by HE. Communications, Sultanate of Oman
24th October 2013. Pragati Towers is a
strategic partner for all major industry Dr. Ahmed Mohammed Salem Al- along with HH. Sayyid Tarik Bin Shabib
G+23 storied residential slum rehab by L&T Constructions B&F IC using towers covering 6.3 lakh sq.ft built-up
trade shows in Muscat. Futaisi, Minister of Transport & Al Said to the L&T team.
towers, Phase -I designed and built Precast Technology. It consists of three area and 1012 flats.
104 ECC CONCORD, October13 - March14 ECC CONCORD, October13 - March14 105
Awards Awards
Holck-Larsen Centre
CSTI Pilkhuwa bags Best Vocational & Visitors Impressions
Skills Institution award
CSTI Pilkhuwa has been adjudged
the Best Vocational & Skills
Institution at the National Education
Summit & ASSOCHAM Education
Excellence Awards 2014. CSTI bagged
this award under the category of
Vocational and Skills Training - Best
Use of Technology for Vocational
Education & Skills Training. The
event was jointly organised by the
Planning Commission, Ministry of
HRD and NSDC on 19 th February at
Hotel Shangrila, New Delhi. Padma
Vibhushan Dr. Karan Singh, Member
of Parliament, presented the trophy
to Mr. S. Natrajan, Head CSTD and My wife and I greatly enjoyed the This museum is fantastic, thank you all
Col. N.B.Saxena, Regional Training historical view of L&T for the warm welcome.
Manager. Nobel Laureate Prof. Kurt Wuthrich, Mrs. Mr. Bjarne Moltke Hansen, MD & CEO,
Marinne Wuthrich & Professors from Country Head M/s F L Smidth, India
IIT Chennai
106 ECC CONCORD, October13 - March14 ECC CONCORD, October13 - March14 107
AR posthumously awarded
Padma Bhushan
The late Dr. A Ramakrishna (AR), former President
and Deputy Managing Director, was posthumously
honoured with the Padma Bhushan in the category of
Science & Engineering on Republic Day 2014. It was
a fitting recognition for this Master Builder and for his
wonderful contribution to the rise of L&T Construction
in an association that spanned over four decades.
Speaking about the signal distinction, Group
Executive Chairman, Mr. A M Naik, said: This honour
is richly deserved recognition of Dr. Ramakrishnas
accomplishments in the field of infrastructure and
construction.
L&Ts CEO and Managing Director, Mr. K. Venkataramanan
described Dr. Ramakrishna as a doyen of the construction
industry and added that the Padma Bhushan was national
recognition of his expertise.
AR, who passed away on August 20th, 2013, has left
an indelible mark on L&T Construction through his
innovative thinking, inspirational leadership and
humane disposition apart from being the moving force
behind building some of the countrys most spectacular
landmarks.
A technocrat par excellence who worked his way
up through technological excellence and innovative
strategies, is how Mr. K V Rangaswami, Advisor to the
Group Executive Chairman described AR and added
that he was quintessentially an organization builder.
Mr. S. N. Subrahmanyan, Member of the Board &
Senior Executive Vice President (Infrastructure & The Institute of Engineers, Andhra
Construction), who had the privilege of ARs tutelage Pradesh Chapter, Hyderabad has
during his formative years was more eloquent in his instituted Annual Endowment
praise. I am very happy to know that our beloved AR
has been conferred with the Padma Bhushan Award,
Lectures to commemorate
the most prestigious civilian award in our country. It is Dr. A. Ramakrishnas contribution
really a proud moment for all of us at L&T. It is indeed a to the infrastructural development
most fitting tribute to one of the most outstanding civil of the county at large and to
engineer and technocrat. He has been a great mentor
and boss. Under his leadership, erstwhile ECC witnessed Andhra Pradesh in particular.
new unprecedented peaks and diversified into many
new lines of business. He was seen as a humane leader
in L&T with pleasing demeanour, optimism and vision.
We, at L&T, salute the memory and the considerable
accomplishments of this great champion of our
Company.
Edited by Mr. V.S. Ramana for L&T Construction from L&T Construction Headquarters, Manapakkam, Chennai - 600 089. The views expressed in this
magazine are not necessarily those of the Management. The contents of this magazine may not be reproduced without the written permission of the Editor.
Not for sale. Only for free circulation among employees of L&T Construction and their customers.