Gantt Chart_x000D_

Task Name Start


Start date 9/21/2014
Demo Prep 10/1/2014
Demolition 10/6/2014
Excavation 10/25/2014
Concrete 11/1/2014
Pre backfill 11/13/2014
Framing 10/25/2014
Roof 11/19/2014
Plumbing 10/29/2014
Windows 11/22/2014
HVAC 11/29/2014
Electrical 12/10/2014
A/V 12/10/2014
House wrap 12/27/2014
Insulation 12/3/2014
Drywall 1/3/2015
Exterior stone 1/3/2015
Exterior case work 1/4/2015
Laundry/furnace room flooring 2/16/2015
Hardwoods 1/19/2015
Tile 2/3/2015
Cabinets 1/18/2015
Plumbing -hang sinks 2/16/2015
Interior doors 2/25/2015
Millwork 2/15/2015
Interior painting 2/28/2015
Stone Counters 3/21/2015
Schedule Buffer 2/28/2015
Decks 2/28/2015
Interior doors- hang & hardware 5/3/2015
Appliances 5/2/2015
Plumbing 5/2/2015
Electrical 5/3/2015
Bathroom Glass 5/9/2015
Garage Door dress up 5/13/2015
FINAL Inspections 5/2/2015
Wrap up 5/9/2015
Gantt Chart_x000D_

House Cleaning 5/29/2015


Complete 6/1/2015
Gantt Chart_x000D_

End Duration (days) Next tab for Gantt Chart


9/30/2014 9
10/6/2014 5
10/24/2014 18
Or Click Here to Create Your Con
10/29/2014 4
11/13/2014 12
11/15/2014 2
12/5/2014 41
12/10/2014 21
12/9/2014 41
12/15/2014 23
12/20/2014 21
12/22/2014 12
12/15/2014 5
12/30/2014 3
12/21/2014 18
1/23/2015 20
1/17/2015 14
1/13/2015 9
3/11/2015 23
3/10/2015 50
2/14/2015 11
3/6/2015 47
2/23/2015 7
3/9/2015 12
2/17/2015 2
4/14/2015 45
3/31/2015 10
3/10/2015 10
3/18/2015 18
5/13/2015 10
5/3/2015 1
5/5/2015 3
5/11/2015 8
5/13/2015 4
5/18/2015 5
5/2/2015 0
6/5/2015 27
Gantt Chart_x000D_

6/10/2015 12
6/1/2015 0
Gantt Chart_x000D_

k Here to Create Your Construction Timeline in Smartsheet


Gantt Chart_x000D_
Gantt Chart_x000D_
Gantt Chart_x000D_
Gantt Chart_x000D_
Gantt Chart_x000D_

You might also like