You are on page 1of 633

Name of Work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at

Maddilapalem, Visakhapatnam in the place of existing A & B staff quarters.

GENERAL ABSTRACT

Sr. No. Particulars Amount Remarks

01 No. of Floors Cellar+Ground+4 floors


02 Plot Area in Sq.Yds 1,034.00
03 Plot Area in Sq.Mts 865.00
04 Plinth Area in Sq.ft. 15,805.00
05 Cost of Civil Work 34,800,000.00
06 Cost of Internal Amenities
a) Internal Water supply & Sanitary) 934,466.98
b) Internal Electrification 1,601,529.56
Sub Total : 2,535,996.54 2,535,996.54
07 Cost of External Amenities
a) Septic Tank 388,219.65
b) Circular Sump 175,000.00
c) Compound Wall 514,383.84
d) Old building dismantling 560,000.00
Sub Total : 1,637,603.49 1,637,603.49
08 Provision for Front elevation LS 1,044,000.00
09 Total (5 to 8) 40,017,600.03
10 Add: Price Escalation at 5% 1,020,000.00
11 Total (9+10) 41,037,600.03
12 Add: VAT at 5% 2,051,880.00
13 Add: Service Tax at 5.60% 2,298,106.00
14 Add: Labour Cess at 1% 410,376.00
15 Add: Q.C. at 0.25% 102,594.00
16 Add: NAC at 0.1% 41,038.00
17 Provision for Seignorage charges 74,300.00
18 Total (11 to 17) 46,015,894.03
19 Provision for External Electrification 600,000.00
20 Provision for Lift 1No. 2,000,000.00
21 Provision for Building Licese fee LS 1,500,000.00
22 Provision for 100 KVA Generator LS 1,200,000.00
23 Provision for Land scaping and Avenue Plantation LS 500,000.00
24 Provision for Bore Well, Motors, Municipal Water LS 800,000.00
25 Provision for Soil Investigation charges 500,000.00
26 Provision for Paper publication charges 300,000.00
27 Provision for Fire Fighting system LS 600,000.00
28 Add : LS for other unforceen items 848,199.00
29 Total (18 to 28) 54,864,093.03

Total Scheme Cost : Rs.550.00 Lakhs

Gen.ABS
ABSTRACT FOR CIVIL
Name of Work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at Maddi
Visakhapatnam in the place of existing A & B staff quarters.
Sl.
Quantity Description Rate Unit
No.
Earth work excavation for foundations and depositing on
bank for all lifts and with aninitial lead of 10m including all
operational, incidental, labour charges such as shoring
1 2593.722 96.95 1 Cum.
sheeting, planking, strutting, etc. complete for finished item
of work excluding dewatering charges etc. as per SS- 20 B
(APSS 308).

Laying PCC work of mix (1 : 4 : 8) proop. Using 40 mm


gauge hard granite machine crushed metal including cost
2 35.732 and conveyance of all materials, machine mixing, labour 4474.10 1 Cum.
charges, tamping, curing, taxes etc., complete for
foundations.

Supply and placing of the Design Mix Concrete of grade


M30 corresponding to IS 456 using WEIGH BATCHER
using minimum cement content of 380 Kg. per Cum with
12mm and 20mm size graded machine crushed hard
granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement,
fine aggregate ( sand) coarse aggregate, water etc., to site
and including, sales & other taxes on all materials including
all operational, incidental and labour charges such as weigh
3 batching, machine mixing, laying concrete, Vibrating, curing
etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No.402 including
centering shuttering using adjastable Jack Screws, Props
and Acro span beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross members
etc., Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its fabrication
charges for finished item of work. FOUNDATIONS, PLINTH,
PEDESTALS (Below Plinth).

A 124.449 For Footings 9893.65 1 Cum.


B 14.024 For Pedestals 10382.20 1 Cum.
C 38.951 For Plinth Beams 12158.26 1 Cum.

ABS-Civil
Sl.
Quantity Description Rate Unit
No.

Supply and placing of the Design Mix Concrete of grade


M30 corresponding to IS 456 using WEIGH BATCHER
using minimum cement content of 380 Kg. per Cum with
12mm and 20mm size graded machine crushed hard
granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement,
fine aggregate (sand) coarse aggregate, water etc., to site
and including, sales & other taxes on all materials including
all operational, incidental and labour charges such as weigh
4 batching, machine mixing, laying concrete, vibrating, curing
etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No.402) including
centering shuttering using adjastable Jack Screws, Props
and Acro span beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross members
etc., Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its fabrication
charges for finished item of work. COLUMNS, LINTELS,
WATER TANKS, RCC, WALLS IN BUILDINGS.

A For PCC M30 Concrete for steps


a 14.394 For cellar floor steps 12156.40 1 cum.
b 9.012 FOR GROUND FLOOR 12156.40 1 cum.
c 0.632 FOR FIRST FLOOR 12348.86 1 cum.
d 0.632 FOR SECOND FLOOR 13565.40 1 cum.
e 0.632 FOR THIRD FLOOR 13845.26 1 cum.
f 0.632 FOR FOURTH FLOOR 14125.10 1 cum.
B For Columns
a 24.042 For cellar floor 12390.15 1 cum.
b 13.563 GROUND FLOOR 12390.15 1 cum.
c 13.563 FOR FIRST FLOOR 12660.55 1 cum.
d 13.563 FOR SECOND FLOOR 13955.05 1 cum.
e 13.563 FOR THIRD FLOOR 14312.80 1 cum.
f 13.563 FOR FOURTH FLOOR 14670.60 1 cum.
C For Lintels
a 0.042 For cellar floor 12156.40 1 cum.
b 0.127 GROUND FLOOR 12156.40 1 cum.
c 0.401 FOR FIRST FLOOR 12156.40 1 cum.
d 1.615 FOR SECOND FLOOR 13180.45 1 cum.
e 1.741 FOR THIRD FLOOR 13267.85 1 cum.
f 1.741 FOR FOURTH FLOOR 13355.26 1 cum.
g 0.084 FOR FIFTH FLOOR 13442.60 1 cum.

D R.C.C. Side walls


56.389 R.C.C. Side walls 14806.51 1 cum.

ABS-Civil
Sl.
Quantity Description Rate Unit
No.

Filling with useful available excavated earth (excluding rock)


in trenches, sides of foundations and basement with initial
lead in layers not exceeding 15 cm thick,consolidating each
5 184.674 deposited layer by watering and ramming including cost and 278.75 1 Cum.
conveyance of water to work site and all operational,
incidental, labour charges, hire charges of T & P etc.,
complete for finisheditem of work. (APSS NO. 309 & 310).

Laying PCC work of mix (1 : 5 : 10) prop. Using 40 mm


gauge hard granite machine crushed metal including cost
6 129.442 and conveyance of all materials, machine mixing, labour 4257.95 1 Cum.
charges, tamping, cruing charges, taxes etc., complete for
foundations.

Supply and placing of the Design Mix Concrete of grade


M30 corresponding to IS 456 using WEIGH BATCHER
using minimum cement content of 380 Kg. per Cum with
12mm and 20mm size graded machine crushed hard
granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement,
fine aggregate (sand) coarse aggregate, water etc., to site
and including, sales & other taxes on all materials including
all operational, incidental and labour charges such as weigh
7
batching, machine mixing, laying concrete, curing
etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No.402) including
centering shuttering using adjastable Jack Screws, Props
and Acro span beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross members
etc., Complete, laying concrete, curing etc. complete but
excluding cost of steel and its fabrication charges for
finished item of work. CHAJJAS.

15.070 FOR SECOND FLOOR 1420.90 1 Sqm.


16.744 FOR THIRD FLOOR 1455.45 1 Sqm.
16.744 FOR FOURTH FLOOR 1488.45 1 Sqm.
1.122 FOR FIFTH FLOOR 1523.05 1 cum.

ABS-Civil
Sl.
Quantity Description Rate Unit
No.

Supply and placing of the Design Mix Concrete of M 30


corresponding to IS 456 using WEIGH BATCHER using
minimum cement content of 380 Kg. per Cum with 12mm
and 20mm size graded machine crushed hard granite metal
(coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including,
sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching,
8
machine mixing, laying concrete, vibrate, curing
etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No.402)including
centering shuttering using adjastable Jack Screws, Props
and Acro span beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross members
etc., Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its fabrication
charges for finished item of work. RCC SLABS, BEAMS.

A FOR SLABS
a 107.400 For cellar floor 10293.55 1 cum.
b 57.377 GROUND FLOOR 10293.55 1 cum.
c 45.809 FOR FIRST FLOOR 10463.24 1 cum.
d 54.187 FOR SECOND FLOOR 10838.00 1 cum.
e 58.065 FOR THIRD FLOOR 11035.75 1 cum.
f 58.065 FOR FOURTH FLOOR 11219.75 1 cum.
g 11.232 FOR FIFTH FLOOR 11410.10 1 cum.

B FOR BEAMS
a 29.996 For cellar floor 11399.15 1 cum.
b 15.260 GROUND FLOOR 11399.15 1 cum.
c 15.019 FOR FIRST FLOOR 11626.60 1 cum.
d 15.770 FOR SECOND FLOOR 12057.55 1 cum.
e 15.770 FOR THIRD FLOOR 12302.50 1 cum.
f 15.770 FOR FOURTH FLOOR 12545.90 1 cum.
g 1.605 FOR FIFTH FLOOR 12790.85 1 cum.

Providing impervious coat to exposed RCC roof slab surface


with CM(1:3), 20mm thick with 1kg of water proof compound
per bag of cement laid over roof when it is green including
cost of all materials,, including conveyance charges of
9
materials and including all operational, incidental and labour
charges for mixing mortar, laying, rendering smooth and
thread lining, curing, rounding off junctions of wall and slab
etc,, complete for finished item of work.

A 370.438 FOR CELLAR 447.70 1 Sqm.


B 37.064 FOR FIFTH FLOOR 493.10 1 Sqm.

ABS-Civil
Sl.
Quantity Description Rate Unit
No.

Providing High Yield Strength Deformed Steel bars (Fe 415


Grade as per IS : 1786 and as amended upto date) of
different diameters including labour charges for cutting
bending to required size shapes, placing in position with
cover blocks of approved materials and size and tying firmly
with M.S. Binding wire of 20 SWG forming grills for
reinforcement work as per approved designs and drawings
including cost and conveyance of deformed steel bars,
10
including all wastage such as overlaps, welded joints, chairs
spacer bars including cost and conveyance of binding wire
cover blocks and all incidental, opeartional labour charges
including sales and other taxes on all materials etc.,
complete for finished item of work in all floors (APSS
No.126) (Payment will be made on the basis of weight of
fabrication deformed bars only) (No re-rolled steel shall be
allowed) complete for (8 mm to 40 mm).

A 49.970 For cellar floor 63465.35 1 MT


B 11.218 GROUND FLOOR 63465.35 1 MT
C 9.816 FOR FIRST FLOOR 64753.75 1 MT
D 11.091 FOR SECOND FLOOR 64882.60 1 MT
E 11.574 FOR THIRD FLOOR 65011.45 1 MT
F 11.574 FOR FOURTH FLOOR 65140.25 1 MT
G 1.600 FOR FIFTH FLOOR And 6th Floor 65269.10 1 MT

Masonry work in CM (1:6) prop with Flyash Cement solid


blocks of size 290 x 225 x 140 mm for manufacturing of
flyash solid blocks using flyash of 80 kgs, cement of 15
kgs.Gypsum of 5 kgs. and stone dust including cost and
11
conveyance of all materials, labour charges, , scaffolding
and curing etc., complete with a compressive strength not
lessthan 50 kg/sqcm for walls for Superstructure Walls. For
Super Structure.

a 38.181 For cellar floor 6112.50 1 cum.


b 52.951 FOR GROUND FLOOR 6112.50 1 cum.
c 57.795 FOR FIRST FLOOR 6457.00 1 cum.
d 69.195 FOR SECOND FLOOR 6656.30 1 cum.
e 68.225 FOR THIRD FLOOR 6856.20 1 cum.
f 68.225 FOR FOURTH FLOOR 7055.45 1 cum.
g 32.906 FOR FIFTH FLOOR 7255.35 1 cum.

Masonry work in CM (1:4) prop with Flyash Cement solid


blocks of size 230 x 100 x 140 mm for manufacturing of
flyash solid blocks using flyash of 80 kgs, cement of 15
kgs.Gypsum of 5 kgs. and stone dust including cost and
12
conveyance of all materials, labour charges,, scaffolding and
curing etc., complete with a compressive strength not
lessthan 50 kg/sqcm for walls for Superstructure Walls. For
Partion walls.

a 8.012 FOR GROUND FLOOR 6583.10 1 cum.


b 6.998 FOR FIRST FLOOR 7039.00 1 cum.

ABS-Civil
Sl.
Quantity Description Rate Unit
No.
c 6.998 FOR SECOND FLOOR 7349.55 1 cum.
d 6.998 FOR THIRD FLOOR 7661.10 1 cum.
e 6.998 FOR FOURTH FLOOR 7971.45 1 cum.

Plastering with CM (1:4), 12 mm thick in singlecoat with.


Screened sand with sponge finishing including cost and
13
coneyance of all meterials hacking surface, scaffolding,
leads, lifts and labour charges etc., complete for CEILING.

a 1685.481 For cellar floor 173.60 1Sqm


b 472.851 FOR GROUND FLOOR 179.40 1Sqm
c 395.736 FOR FIRST FLOOR 191.55 1Sqm
d 425.962 FOR SECOND FLOOR 197.95 1Sqm
e 451.815 FOR THIRD FLOOR 204.40 1Sqm
f 451.815 FOR FOURTH FLOOR 210.80 1Sqm
g 44.309 FOR FIFTH FLOOR 217.20 1Sqm

Providing plastering in CM(1:3), 20mm thick laid over


Granolithic flooring bed when it is green including cost of all
materials, seigniorage charges, including conveyance
charges of materials and including all operational, incidental
14 654.000 435.90 1Sqm
and labour charges for mixing mortar, laying, rendering
smooth and thread lining, curing, rounding off junctions of
wall and floor etc,, complete for finished item of work FOR
ORNAMENTAL PLASTERING.

Plastering with CM 2 coats, 12 mm thick, base coat in CM


(1:5), 8mm thick and top coat in CM (1:3), 4mm thick with
sponze finishing to suit application of Altek finish including
15 cost and conveyance of all materials and water to work site
and all operational incidental labour charges such as mixing
mortar, lift charges, curing etc.complete for finished item of
work as per SS No. 901, 904 for Exterior Walls.

a 481.364 For cellar floor 390.95 1Sqm


b 119.400 FOR GROUND FLOOR 390.95 1Sqm
c 95.175 FOR FIRST FLOOR 414.42 1Sqm
d 205.606 FOR SECOND FLOOR 416.76 1Sqm
e 214.535 FOR THIRD FLOOR 419.11 1Sqm
f 214.535 FOR FOURTH FLOOR 421.45 1Sqm
g 226.720 FOR FIFTH FLOOR 423.80 1Sqm

Plastering with CM in 2 coats of 12 mm thick, base coat in


CM (1:5) of 8mm thick, top coat in CM (1:3) of 4mm thick
with sponze finishing to suit application of Altek finish
including cost and conveyance of all material and water to
16
work site and all operational incidental labour charges such
as mixing mortar, lift charges, curing etc.complete for
finished item of work as per SS No. 901, 904 for Interior
Walls.
a 61.570 For Cellar floor 399.10 1Sqm
b 695.245 FOR GROUND FLOOR 402.05 1Sqm

ABS-Civil
Sl.
Quantity Description Rate Unit
No.
c 634.565 FOR FIRST FLOOR 428.45 1Sqm
d 1017.947 FOR SECOND FLOOR 433.75 1Sqm
e 661.295 FOR THIRD FLOOR 439.05 1Sqm
f 661.295 FOR FOURTH FLOOR 444.35 1Sqm
g 126.270 FOR FIFTH FLOOR 449.65 1Sqm

Plastering with CM (1:3), 20 mm thickin single coat with


Screened sand with sponge finishing including cost and
17 coneyance of all meterials hancking surface, scaffolding,
leads lifts and labour charges etc., complete PLASTERING
FOR FLOORING.
842.651 Cellar Floor 447.70 1Sqm

Granolithic concrete flooring 20 mm thick with (1:1:2) using


6mm to 12 mm size hard granite metal laid over CC bed
already laid or RCC Roof slab in alternate panels of size not
18 exceeding 1.5Mt x 1.5Mt. and finishing the top surface to
required slopes including cost of all materials like cement,
metal, sand and water etc., complete for finished item of
work.
842.651 Cellar Floor 363.25 1Sqm

Flooring with vitrified tiles of size not less than 598 mm x


598 mm, 8 to 10 mm thick glossy finish premium colour
normal colour 1st quality set over base coat of cement
mortar (1:8), 12mm thick over CC bed already laid or RCC
roof slab, including neat cement slurry of honey like
19
consistency spread @ 3.3.kgs per sqm & jointed neatly with
white cement paste to full depth mixed with pigment of
matching shade, Pointing with CM (1:3) including cost of all
materials like cement, sand water and tiles etc., complete,
for finished item of work.

a 222.064 GROUND FLOOR 1698.75 1Sqm


b 209.791 FOR FIRST FLOOR 1735.35 1Sqm
c 247.679 FOR SECOND FLOOR 1739.00 1Sqm
d 272.101 FOR THIRD FLOOR 1742.65 1Sqm
e 272.101 FOR FOURTH FLOOR 1746.30 1Sqm

Providing skirting to internal walls to 15 cm height/risers of


steps with vitrified tiles length equal to flooring stones, set
over base coat of CM (1:5) 12 mm thick with cement slurry
of honey like consistency spread at the rate of 3.30 kgs per
20
sqm and jointed with white cement paste mixed with pigment
of matching shade to full depth, including cost of all
materials like tiles, cement, sand and water etc., complete
for finished item of work.

a 22.206 FOR GROUND FLOOR 1707.50 1Sqm


b 20.979 FOR FIRST FLOOR 1744.06 1Sqm
c 24.768 FOR SECOND FLOOR 1747.70 1Sqm
d 27.210 FOR THIRD FLOOR 1751.40 1Sqm
e 27.210 FOR FOURTH FLOOR 1755.05 1Sqm

ABS-Civil
Sl.
Quantity Description Rate Unit
No.

Flooring with ceramic tiles of 7.3mm thick of 1st quality of all


shades set over base coat of cement mortar (1:8), 12 mm
thick over CC bed already laid or RCC roof slab, including
neat cement slurry of honey like consistency spread @
21
3.3.kgs per sqm & jointed neatly with white cement paste to
full depth mixed with pigment of matching shade, including
cost of all materials like cement, sand water and tiles etc.,
complete, for finished item of work.

a 38.412 GROUND FLOOR 996.30 1Sqm


b 38.412 FOR FIRST FLOOR 1032.90 1Sqm
c 38.412 FOR SECOND FLOOR 1036.55 1Sqm
d 38.412 FOR THIRD FLOOR 1040.20 1Sqm
e 38.412 FOR FOURTH FLOOR 1043.85 1Sqm

Dadoing walls with 1st quality of glazed plain coloured tiles


of 5 to 7 mm thick of any size cement base in C.M.(1:3)
Prop. and neat cement slurry of honey like consistency at
the rate of 3.30 Kgs. cement per Sq.mt. mixed with pigment
22
of matching shade of tiles including charges, curing etc.,
complete as directed by the department for finished of work
inclusive of all taxes for
BATH ROOMS.

a 23.681 For cellar floor 694.94 1Sqm


b 148.413 GROUND FLOOR 694.94 1Sqm
c 186.565 FOR FIRST FLOOR 704.14 1Sqm
d 123.424 FOR SECOND FLOOR 705.09 1Sqm
e 123.424 FOR THIRD FLOOR 705.99 1Sqm
f 123.424 FOR FOURTH FLOOR 706.90 1Sqm

Supply and fixing of High strength cement concrete designer


tiles of 30mm thicknes of M40 Grade which top 12mm thick
shall be for color pigmentation with imported colour and
white cement to get required reflective glazing inclisive of all
taxes. and over a bse coat of C.M.(1:8) Prop. 20 mm thick
23 including neat cement slurry of honey like consistency
spread at the rate of 3.30 Kg. per Sq,/ and filling the joints
with white cement at 2.00 Kg. per Sq.m. mixed with pigment
of matching shade including cost and conveyance of all
materials, labour charges, laying of tiles etc., complete as
directed by the Department for Stair case and Portco.

a 114.670 For Cellar floor 1060.15 1Sqm


b 68.019 FOR GROUND FLOOR 1060.15 1Sqm
c 12.152 FOR FIRST FLOOR 1096.75 1Sqm
d 12.152 FOR SECOND FLOOR 1100.40 1Sqm
e 12.152 FOR THIRD FLOOR 1104.06 1Sqm
f 12.152 FOR FOURTH FLOOR 1107.71 1Sqm

ABS-Civil
Sl.
Quantity Description Rate Unit
No.

Providing and fixing door frame fabricated from section


made of galvanized steel powder coated (base steel as per
IS 513,galvanized as per IS 217 with zinc of 120
grams/square meter). The factory made section should be
with a powder coating of pure polyester powder of 50-60
microns thick with total coated thickness of 1.25 mm. Size of
door frame section should be of 105 x 60 mm with a rebate
of 38mm to accommodate 30 mm thick door shutter with
groove to insert gasket in the frame section, frame section
24 6.000 to be filled with polyurethane foam. the frame section should 4458.30 1 No.
be cut to length and joined by way be way of welding. Each
frame should be provided with : 2mm thick MS powder
coated butt hinges of 100 mm long -3 Nos. for single shutter,
6Nos. double shutter. CRCA Electroplates stiffeners of 6
Nos. -3 in each vertical for double shrtter and 40mm x 200
mm x 1.2 mm hold fasts screwed to stiffeners - 6Nos. with
split end tail. Nylon Aldrop Receiver -1No. for single shutter
frame. Tie Rod 1 No. DOOR FRAME FOR WITH OUT SILL
OF SIZE 0.91X2.13 M.

extruded sections in over all dimentions of 40 x 48mm


having wall thickness of 1.55 mm. wiht usual porcess
veriation of +/- 0.3mm complete and Sintex door shutter
made from specially Hot Press Moulded SMC (Sheet
moulding coumpound sheets, Polyurethene core and PVC
Frame Section SMS sheets shall be made from SMC
comforming to IS 13410 sheet shall have an average
thickness of 1.4 mm +0.35 mm on both sides. Core of the
door shutter shall be filled with high density polyurethane
foam , injected wiht the help of hydraulic injection method
shutter frame to be made of PVC extruded section
confirming to IS:10151 :1982 of size 26 mm x 46 mm with a
wall thickness of 1.4 mm +0.3mm on both sides
25 48.000 8394.25 Each
corresponding to sintex code DWUF 305. The hardware
locations shall be reinforced with special polymeric
reinforcement wooden blocks of suitable size. The corners
of the shutter frame shall be reinforced with Polymeric 'L'
shaped angle of size 105 mm x 230 mm corresponding to
Sintex code PR-02 the lock rail shall be made from PVC
extruded sections having overall dimensions of 26 mm x 46
mm 1.5 mm +0.3mm on both sides, with usual process
variation corresponding to Sintex code 305 combining two
numbers. Wooden pieces are inserted on the periphery.
Suitable MS Tube reinforcement shall be provided on
vertical sides of shutter frame the rate inclusive of all taxes
and finished item work Color: White & Grey. SINTEX

Supply and fixing of Flush door single leaf flushdoor shutter


of solid bond wood black board type 30mmthick conforming
to IS2202 commercial ply on both faces including cost of
fixtures of M.S.Powder coated 1 No. 250 mm long aldrop, 1
26 6.000 No. of 200 mm long aldrop, 1 No. of 200 mm tower blot, 1 4057.35 1 No.
No. 125 mm long handle including cost and conveyance of
all materials and labour charges etc., complete as per
drawing and as directed by the department for DOOR OF
SIZE: 0.91 X 2.13 Mts.

ABS-Civil
Sl.
Quantity Description Rate Unit
No.

Providing and fixing ofdouble Openable / Casement


Windows with fly mesh made of pre-painted steel (Base
steel as per IS 513 of 0.80 mm. thick galvanized as per IS-
277 with Zinc of 120 GSM), finish painted with a polyester
paint of 60-65 microns thick and section for outer frame fo
100 x 45 mm., centre mullion of 100x60 mm, section for
shutter of 52 x 25 mm x 0.6 mm thick, section for fly-shutter
of 52 x 25 m x 0.6 mm thick and fitted with stainless steel 32
gauge fly mesh of 304 grade with 144 holes per Sq.inch and
mullions to have double rebate for glazed shutter and fly-
shutter with a provision for guard bars/grills and the sections
cut to length metre joined with corner bracket, centre mullion
27 58.000 15188.25 Each
fixed with mullion cap, 1 No.of High grade nylon latch
handle, window stopper, 2 Nos. of with MS powder coated/
SS ball bearing butt Hinges provided per shutter and
windows fitted with 4 mm thick plain float glass with rubber
gaskets including fixing the frames in concrete/ masonry
wall by means of self expanding screws, including 10 mm
square guard bars with 6" (152.4mm) pitch etc., complete
for finished item of work. Windows of size 5'-0"x4'-0"
(1524x1219.20mm) outerframe section of size 80x45mm,
shutterframe section size of 52x25mm, vertical mullion
section of size 100x60mm beeding section size of 9x12mm
to be provided for glass holding.

Providing and fixing of top hung Ventilators made of pre-


painted steel (Base steel as per IS 513of 0.80mm thick
galvanized as per IS 277 with Zinc of 120 GSM), finish
painted with a polyester paint of 60-65 microns thick and
section for outer frame of 80 x 45mm, centre mullion of 80 x
60mm, section for shutter of 52 x 25mm x 0.6mm thick,
outer frame and mullions to have rebate for glazed shutter
with a provision for guard bars/ grills and the sections cut to
length metre joined with corner bracket, centre mullion fixed
with mullion cap, 1No. of High grade nylon latch handle,
28 window stopper, 2 Nos. of with MS powder coated / SS ball
bearing but hinges provided per shutter and windows fitted
with 4 mm thick plain float glass with rubber gaskets
including fixing the frames in concrete / masonry wall by
means of self expanding screws, including 10mm square
guard bars with 6" (152.4mm) pitch etc., complete for
finished item of work. Single fixed louvers ventilator size of
2'-0" x 2'-0" (609.6 x 609.6 mm) outer frame box section size
of 80 x 45mm.Ventilator window 2'-6" x 1'-6" . Outer frame
section size 72 x 0mm shutter frame section size of 47 x
20mm 0.91 x 0.46 mm. Ventilator window.

30.000 W1 - windows of size 0.91 x 0.45 1993.20 Each

ABS-Civil
Sl.
Quantity Description Rate Unit
No.

Supply and fixing of rolling shutter made of 80 x 1.25 mm.


machine rolled CRCA laths, interiocked together through
their entire length and jointed together at the ends by end
locks, mounted on specially designed pipe shaft of 50 mm.
dia nominal bore MS. B class pipe wiht brackets, plates,
29 210.542 guide channels, stoppers, bottom locking plates and 3250.55 1 Sq.mtr.
arrangements for inside & outside locking with push-pull
operations inlcuding cost of hood cover and springs
complete, painted wiht one coat of approved steel primer,
locks, ball bearings, all accessories etc., complete for
finished item of work as per special spn : 1108.

PAINTING to new WOOD work / Iron work in two coats with


synthetic enamel paint of approved colour, over one coat of
30 917.462 primary coat including cost and conveyance of all materials, 163.95 1 Sq.mtr.
incidental charges such as sand paper, cleaning the surface,
cost of brushes and putty etc., complete. (Three coats).

Providing and applying synthetic plaster putty or plaster of


parris putty or lime punning of average 1 to 2mm thickness
over plastered surface to prepare the surface even and
smooth after throughly brushing the surface to remove all
dirt and remains of loose powdered materials, applying
emery paper ,sand the surface ,clean & wipe off loose
31
dust ,applying knifing paste filler putty knife/muslin pad ,air
dry for 2-3 hrs sand with 180 and 320no,emery paper for the
surface preparation including cost and conveyance of all
matrials to work site and all operational ,incidental,labour
chages etc complete for finished item of work for internal
walls.

a 1747.051 For Cellar floor 219.50 1 Sq.mtr.


b 1168.096 FOR GROUND FLOOR 219.50 1 Sq.mtr.
c 1030.301 FOR FIRST FLOOR 219.50 1 Sq.mtr.
d 1443.909 FOR SECOND FLOOR 219.50 1 Sq.mtr.
e 1113.110 FOR THIRD FLOOR 219.50 1 Sq.mtr.
f 1113.110 FOR FOURTH FLOOR 219.50 1 Sq.mtr.
g 170.579 FOR FIFTH FLOOR 219.50 1 Sq.mtr.

Painting to new walls with 2 coats of water proof cement


paint interior grade-I of approved brand and shade over a
base coat of approved cement primer grade I making 3
coats in all to give an even shade after throughly brushing
32
the surface to remove all dirt and remains of loose
ppowdered materials to work site and all operational,
incidental, labour charges etc., complete for finished item of
work as per SS 912 for internal walls.

a 1747.051 For Cellar floor 193.40 1 Sq.mtr.


b 1168.096 FOR GROUND FLOOR 193.40 1 Sq.mtr.
c 1030.301 FOR FIRST FLOOR 193.40 1 Sq.mtr.
d 1443.909 FOR SECOND FLOOR 193.40 1 Sq.mtr.

ABS-Civil
Sl.
Quantity Description Rate Unit
No.
e 1113.110 FOR THIRD FLOOR 193.40 1 Sq.mtr.
f 1113.110 FOR FOURTH FLOOR 193.40 1 Sq.mtr.
g 170.579 FOR FIFTH FLOOR 193.40 1 Sq.mtr.

Painting to new walls with 2 coats of water based cement


primer of exteriorgrade -II paint of approved brand and
shade over a base coat of approved cement primer grade-2
making 3 coats in all to give an even shade after throughly
33
brushing the surface to remove all dirt and remains of loose
ppowdered materials to work site and all operational,
incidental, labour charges etc., complete for finished item of
work as per SS 912 for exterior walls.

a 481.364 For Cellar floor 193.70 1 Sq.mtr.


b 119.400 FOR GROUND FLOOR 193.70 1 Sq.mtr.
c 95.175 FOR FIRST FLOOR 193.70 1 Sq.mtr.
d 205.606 FOR SECOND FLOOR 193.70 1 Sq.mtr.
e 214.535 FOR THIRD FLOOR 193.70 1 Sq.mtr.
f 214.535 FOR FOURTH FLOOR 193.70 1 Sq.mtr.
g 226.720 FOR FIFTH FLOOR 193.70 1 Sq.mtr.

Supply and fixing 110 mm dia 4.00 Kg./Sq.Cm. pressure


P.V.C.Pipe of Prince / Sudhakar make from roof up to
34 68.000 basement level including plain bend clips and shoe as per 273.05 1RMT
ISI. Standard fixed to wall with pipe clips including labour
charges etc., complete for RAIN WATER PIPE.

Total:
Add for Unforcein items
Total:

ABS-Civil
ABSTRACT FOR CIVIL
mmercial Complex (Cellar+Ground+4Floors) at Maddilapalem,
n the place of existing A & B staff quarters.

Amount

251,461.35

159,868.54

1,231,254.85
145,599.97
473,576.39

ABS-Civil
Amount

-
174,979.22
109,553.48
7,804.48
8,573.33
8,750.20
8,927.06
-
297,883.99
168,047.60
171,715.04
189,272.34
194,124.51
198,977.35
-
510.57
1,543.86
4,874.72
21,286.43
23,099.33
23,251.51
1,129.18
-
-
834,924.29

ABS-Civil
Amount

51,477.88

551,157.56

-
21,412.96
24,370.05
24,922.61
1,708.86
-

ABS-Civil
Amount

-
1,105,527.27
590,613.02
479,310.56
587,278.71
640,790.82
651,474.78
128,158.24
-
-
341,928.90
173,951.03
174,619.91
190,147.56
194,010.43
197,848.84
20,529.31
-

165,845.09
18,276.26

ABS-Civil
Amount

3,171,363.54
711,954.30
635,622.81
719,612.92
752,442.52
753,933.25
104,430.56

233,381.36
323,662.99
373,182.32
460,582.68
467,764.25
481,358.08
238,744.55
-

-
52,743.80
49,258.92

ABS-Civil
Amount
51,432.15
53,612.38
55,784.21
-

292,599.50
84,829.47
75,803.23
84,319.18
92,350.99
95,242.60
9,623.91
-

285,078.60

188,189.26
46,679.43
39,442.42
85,688.36
89,913.76
90,415.78
96,083.94
-

24,572.59
279,523.25

ABS-Civil
Amount
271,879.37
441,534.51
290,341.57
293,846.43
56,777.31
-

377,254.85
-

306,092.98
-

377,231.22
364,060.81
430,713.78
474,176.81
475,169.98
-

37,916.75
36,588.63
43,287.03
47,655.59
47,754.91

ABS-Civil
Amount
-

38,269.88
39,675.75
39,815.96
39,956.16
40,096.37
-

16,456.87
103,138.13
131,367.88
87,025.03
87,136.11
87,248.43
-

121,567.40
72,110.34
13,327.71
13,372.06
13,416.54
13,460.89
-

ABS-Civil
Amount

26,749.80

402,924.00

24,344.10

ABS-Civil
Amount

880,918.50

59,796.00

ABS-Civil
Amount

684,377.30

150,417.89

383,477.69
256,397.07
226,151.07
316,938.03
244,327.65
244,327.65
37,442.09
-

337,879.66
225,909.77
199,260.21
279,252.00

ABS-Civil
Amount
215,275.47
215,275.47
32,989.98
-

93,240.21
23,127.78
18,435.40
39,825.88
41,555.43
41,555.43
43,915.66
-

18,567.40

33,791,952.73
1,008,047.27
34,800,000.00

ABS-Civil
DETAILED ESTIMATE
Name of work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at Madd
Visakhapatnam in the place of existing A & B staff quarters.

Sl.
Description Nos. Length Breadth Depth
No.

Earth work excavation for foundations and


depositing on bank for all lifts and with aninitial lead
of 10m including all operational, incidental, labour
1 charges such as shoring incidental, sheeting,
planking, strutting, etc. complete for finished item of
work excluding dewatering charges etc. as per SS-
20 B (APSS 308).

For Cellar Foundations 1 x 1 40.83 20.12 2.60


Deduct for south east corner -1 x 1 3.30 9.92 2.60
For flooring concrete 1 x 1 39.02 18.31 0.15
Deduct for south side portion -1 x 1 5.23 2.83 0.15
Deduct for south east corner -1 x 1 3.30 9.69 0.15
Sub Total :
For footings x
FG-1 1 x 17 1.00 1.00 1.125
FG-2 1 x 16 1.25 1.25 1.225
FG-3 1 x 7 1.70 1.70 1.475
FG-4 1 x 6 2.35 2.35 1.650
FG-5 1 x 4 2.45 2.45 1.700
FG-6 1 x 6 2.70 2.70 1.800
FG-7 1 x 6 2.85 2.85 1.850
CF-1 1 x 2 2.70 2.70 1.450
CF-2 1 x 2 3.90 2.15 1.950
Sub Total :
Grand Total :

Laying PCC work of mix (1 : 4 : 8) proop. Using 40


mm gauge hard granite machine crushed metal
2 including cost and conveyance of all materials,
machine mixing, labour charges, tamping, curing,
taxes etc., complete for foundations.

FG-1 1 x 17 1.00 1.00 0.150


FG-2 1 x 16 1..25 1.25 0.150
FG-3 1 x 7 1.70 1.70 0.150
FG-4 1 x 6 2.35 2.35 0.150
FG-5 1 x 4 2.45 2.45 0.150
FG-6 1 x 6 2.70 2.70 0.150
FG-7 1 x 6 2.85 2.85 0.150
CF-1 1 x 2 2.70 2.70 0.150
CF-2 1 x 2 3.90 2.15 0.150
TOTAL Total :

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Supply and placing of the Design Mix Concrete of


grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380
Kg. per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate ( sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
3 mixing, laying concrete, Vibrating, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402 including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work.
FOUNDATIONS, PLINTH, PEDESTALS (Below
Plinth).

A. Footings
FG-1 1 x 17 0.80 0.80 0.225
FG-2 1 x 16 1.05 1.05 0.325
FG-3 1 x 7 1.50 1.50 0.425
FG-4 1 x 6 2.15 2.15 0.600
FG-5 1 x 4 2.25 2.25 0.650
FG-6 1 x 6 2.50 2.50 0.750
FG-7 1 x 6 2.65 2.65 0.800
CF-1 1 x 2 2.50 1.80 0.550
CF-2 1 x 2 3.70 1.95 0.900
TOTAL Total :
B. Pedastal
For Coloums 1 x 33 0.45 0.45 0.450
For Coloums 1 x 29 0.75 0.75 0.600
CF-1 1 x 4 0.45 0.45 0.450
CF-2 1 x 4 0.60 0.60 0.600
TOTAL Total :
C Plinth Beam
For C55-C70, C45-C54, C33-C42. 1 x 3 39.48 0.23 0.300
For C43 1 x 1 4.78 0.23 0.300
For C44 1 x 1 3.73 0.23 0.300
For C27 1 x 1 3.00 0.23 0.300
For C28 1 x 1 3.73 0.23 0.300
For C16-C19 1 x 1 31.43 0.23 0.300

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

For C15-C20 1 x 1 36.83 0.23 0.300


For C1-C7 1 x 1 14.58 0.23 0.300
For C8-C14 1 x 1 16.83 0.23 0.300
For C29-C32 1 x 1 5.23 0.23 0.300
For C2-C57, C4-C59, C6-C61, C7-C62, C8-C64,
1x 9 18.77 0.23 0.300
C9-C65, C11-C67, C13-C69 and C14-C70.
For C5 and C10 1 x 2 2.83 0.23 0.300
For C30 and C31 1 x 2 3.07 0.23 0.300
For C33 and C65 1 x 1 9.08 0.23 0.300
For C1-C33 1 x 1 12.00 0.23 0.300
For CF1 Strap beam 1 x 2 2.50 0.45 0.550
For CF2 Strap beam 1 x 2 3.70 1.10 0.900
TOTAL Total :

Supply and placing of the Design Mix Concrete of


grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380
Kg. per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
4 mixing, laying concrete, vibrating, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402) including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work.
COLUMNS, LINTELS, WATER TANKS, RCC,
WALLS IN BUILDINGS.

A For PCC M30 Concrete for steps

For cellar floor steps 1 x 20 x 1 1.24 0.34 0.15


For cellar floor steps 2 x 20 x 1 1.24 0.34 0.15
North side ramp to GF 1 x 2 11.27 3.47 0.15
1 x 2x 1 1.47 3.47 0.15
Total Total :
Ground floor steps
steps 1x 20 x 1 1.24 0.34 0.15

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Ramp from road to ground floor 1x 2 8.05 3.47 0.15


Total Total :
1st Floor
steps concrete 1x 20 x 1 1.24 0.34 0.15
2nd Floor
steps concrete 1x 20 x 1 1.24 0.34 0.15
3rd floor
steps concrete 1x 20 x 1 1.24 0.34 0.15
4th floor
steps concrete 1x 20 x 1 1.24 0.34 0.15
B FOR COLUMNS
For Cellar floor
Columns 22 and 25 1x 2 0.38 0.60 2.745
Columns 35,36, 39, 40,21, 26,17, 47, 51, 52, 48,
1x 22 0.30 0.60 2.745
18,41,34, 46, 49, 50, 19, 37, 38, 53 and 16.
Columns-10,11,4,5,6,9 and 27 1x 7 0.30 0.45 2.745
Columns-3,7,8,12, 2, 13, 14, 29 and 32. 1x 9 0.30 0.30 2.745
Coloumns 15,28,43,44,62,64,33,45, 56, 60, 58, 63,
66, 68, 1, 20, 23, 24, 30,31, 42, 54, 55, 57, 59, 61, 1x 30 0.23 0.375 2.745
65, 67, 69 and 70.
Total Total :
Ground floor
C-22 and C-25 1x 2 0.38 0.60 2.745
Columns 35,36, 39, 40,21, 26,17, 47, 51, 52, 48,
1x 22 0.30 0.60 2.745
18,41,34, 46, 49, 50, 19, 37, 38, 53 and 16.
C-29 and C-32 1x 2 0.30 0.30 2.745
C-23,24 and C-30,31 1x 4 0.23 0.375 2.745
Total Total :

1st Floor Total :


2nd Floor -- -- -- Total :
3rd floor -- -- -- Total :
4th floor -- -- -- Total :
C LINTELS
Cellar floor
Lift Room 1x 1 1.22 0.23 0.15
Ground Floor Total :
Lift Room 1x 1 1.22 0.23 0.15
For toilets doors 2x 4 1.06 0.10 0.10
Total Total :
First Floor
Lift Rooms 1x 1 1.22 0.23 0.15
For toilets doors 2x 5 1.06 0.10 0.10
For toilets ventilators 2x 3 1.22 0.23 0.15
Total Total :
2nd Floor

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Lift Rooms 1 x 1 1.22 0.23 0.15


For toilets doors 2 x 5 1.06 0.10 0.10
Windows 1 x 18 1.82 0.23 0.15
Ventilators 1 x 6 1.22 0.23 0.15
Stair case room doors 1 x 2 1.22 0.23 0.15
Total Total :
3rd Floor
Lift Rooms 1 x 1 1.22 0.23 0.15
For toilets doors 2 x 5 1.06 0.10 0.10
Windows 1 x 20 1.82 0.23 0.15
Ventilators 1 x 6 1.22 0.23 0.15
Stair case room doors 1 x 2 1.22 0.23 0.15
Total Total :
4th Floor -- -- -- Total :
5th Floor
Lift room door and head room door 1x 2 1.22 0.23 0.15
D R.C.C. Side walls
West side walls 1 x 1 17.06 0.23 1.83
North side walls 1 x 1 39.20 0.23 1.83
East side walls 1 x 1 17.40 0.23 1.83
South side walls 1 x 1 41.91 0.23 1.83
Water tank side walls allround 1 x 1 18.40 0.23 1.83
Total Total :

Filling with useful available excavated earth


(excluding rock) in trenches, sides of foundations
and basement with initial lead in layers not
exceeding 15 cm thick,consolidating each deposited
5 layer by watering and ramming including cost and
conveyance of water to work site and all operational,
incidental, labour charges, hire charges of T & P
etc., complete for finisheditem of work. (APSS NO.
309 & 310).

Earth work qty.


Deduct :
PCC (1:4:8)
Footings
Pedastal
Plinth beam
Total :

Laying PCC work of mix (1 : 5 : 10) prop. Using 40


mm gauge hard granite machine crushed metal
6 including cost and conveyance of all materials,
machine mixing, labour charges, tamping, cruing
charges, taxes etc., complete for foundations.

For Cellar flooring bed concrete 1x 1 39.02 18.31 0.15


Deduct for South side portion -1 x 1 5.23 2.83 0.15

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Deduct for South east corner -1 x 0.5 9.69 3.30 0.15


For alround the building GF path way
West side 1x 1 11.00 1.29 0.15
North side 1x 1 45.87 1.52 0.15
(5.6+1.52
East side 1x 1 9.60 0.15
)/2
1x 1 7.80 1.52 0.15
South side 1x 1 38.25 1.29 0.15
Total Total :

Supply and placing of the Design Mix Concrete of


grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380
Kg. per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
7 labour charges such as weigh batching, machine
mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for
finished item of work (APSS No.402) including
centering shuttering using adjastable Jack Screws,
Props and Acro span beams including all pipe
bracings, clamps couplings pre fabricated steel H-
frames, cross members etc., Complete, laying
concrete, curing etc. complete but excluding cost of
steel and its fabrication charges for finished item of
work. CHAJJAS.

2nd Floor
Windows 1x 18 1.82 0.46 --
3rd Floor
Windows 1x 20 1.82 0.46 --
4th Floor
Windows 1x 20 1.82 0.46 --
5th Floor
Head room door and lift room door 1x 2 1.22 0.46

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Supply and placing of the Design Mix Concrete of M


30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380
Kg. per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
8 mixing, laying concrete, vibrate, curing etc.,complete
but excluding cost of steel and its fabrication
charges for finished item of work (APSS
No.402)including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work. RCC
SLABS, BEAMS.

A FOR SLABS
Cellar floor
For slab 1x 1 39.48 18.77 0.15
Waist slab for stair case 1x 1 9.63 1.47 0.175
Deduction
Stair case rooms area -1 x 1 4.77 3.30 0.15
South side portion -1 x 1 4.77 2.06 0.15
South east corner -1 x 0.5 3.30 9.69 0.15
TOTAL Total :
Ground floor
For slab 1 x 1 31.43 10.97 0.15
Waist slab for stair case 1 x 1 9.63 1.47 0.175
Ramp to ground floor slab 1 x 2 8.05 3.93 0.15
Slab projection alround 1 x 1 79.06 0.30 0.15
Deduction : Stair case rooms area -1 x 1 4.77 3.30 0.15
Ramp portion -1 x 2 3.47 7.21 0.15
TOTAL Total :
First floor
For slab 1x 1 31.43 10.97 0.15
Waist slab for stair case 1x 1 9.63 1.47 0.175
Slab projection alround 1x 1 73.83 0.30 0.15
Deduction
Stair case rooms area -1 x 1 4.77 3.30 0.15
Span C-36 - C39 and C-48 - C51 -1 x 1 12.17 5.12 0.15
TOTAL Total :

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

2nd floor
For slab 1x 1 31.43 10.97 0.15
Waist slab for stair case 1x 1 9.63 1.47 0.175
Slab projection alround 1x 1 81.23 0.30 0.15
Deduction
Span C-37 - C38 and C-49 - C50 -1 x 1 4.77 5.12 0.15
TOTAL Total :
3rd floor
For slab 1x 1 31.43 10.97 0.15
Waist slab for stair case 1x 1 9.63 1.47 0.175
Slab projection alround 1x 1 86.00 0.30 0.15
TOTAL Total :

4th floor Total :


5th floor
Stair case head room Slab 1 x 1 5.23 3.76 0.15
Stair case waist Slab 1 x 1 9.63 1.47 0.18
Water tank top and bottom 1 x 2 4.60 4.60 0.10
Lift room bottom and top slab 1 x 2 2.29 2.29 0.15
TOTAL Total :
B FOR ROOF BEAMS
Cellar floor Beam
For span C55 - C70, C45 - C54 1 x 2 39.48 0.23 0.305
C43 and C33 1 x 2 4.32 0.23 0.305
C44, C42 and C28 1 x 3 3.27 0.23 0.305
C27 1 x 1 2.77 0.23 0.305
C15 - C20 1 x 1 36.83 0.23 0.305
C1 - C7 1 x 1 14.58 0.23 0.305
C8 -C14 1 x 1 16.83 0.23 0.305
C55-C33 1 x 1 9.08 0.23 0.305
C33 -C1 1 x 1 12.00 0.23 0.305
C2-C57, C13-C69, C14 -C70 1 x 3 19.64 0.23 0.305
C47 - C59, C52 - C67 1 x 2 3.27 0.23 0.305
C22 - C61 and C25 - C65 1 x 2 16.03 0.23 0.305
C37 - C62 and C38-C64 1 x 2 8.62 0.23 0.305
At C3,C4, C5,C6,C7,C8,C9,C10,C11,C12 and
1x 12 2.37 0.23 0.305
between C6 and C7
Staircase mid landing 1 x 2 3.17 0.23 0.305
Ramp beam C22 - C48 1 x 2 11.27 0.30 0.30
C17 - C49 1 x 2 12.74 0.30 0.30
C48 - C49, C36-C37 1 x 4 3.40 0.30 0.30
C22-C17 1 x 2 3.70 0.30 0.30
TOTAL Total :
Grond floor Roof Beam
For span C46 - 48, C34-36, C51-53 and C39-41 1x 4 9.63 0.23 0.305
C49-50, RB 5 B 1x 2 5.23 0.23 0.305

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

C37-38 1 x 1 4.77 0.23 0.305


S2-S2 1 x 1 17.10 0.23 0.305
RB2 1 x 2 3.47 0.23 0.305
RB3 Lift 1 x 1 1.83 0.23 0.30
C16-19 1 x 1 31.43 0.23 0.305
C16-46, C47,C48,C17-49, C18-50, C51, C36-52
1x 8 10.74 0.23 0.305
C19-53
RB9A and RB5A 1x 2 5.36 0.23 0.305
Lift beam RB14 1x 2 2.06 0.23 0.30
Staircase mid landing beam 1x 2 3.17 0.23 0.280
TOTAL Total :
1st floor Roof Beam -- -- -- --
For span C16 - 19, C34-41 1 x 2 31.43 0.23 0.305
RB2 1 x 2 3.47 0.23 0.305
RB3 Lift 1 x 1 1.83 0.23 0.305
S2 -S2 1 x 1 17.10 0.23 0.305
C46-48, C51-53 1 x 2 9.63 0.23 0.305
C16-46, C47,C48,RB9, C51, RB9, C52, C19-53 2x 4 10.74 0.23 0.305
C17-37, C18-38 1x 2 5.16 0.23 0.305
Lift beam RB12 1x 2 2.06 0.23 0.300
Staircase mid landing beam 1x 2 3.17 0.23 0.280
TOTAL Total :
2nd floor Roof Beam
First floor roof beam quantity -- -- -- --
For span C37- 49, C38-50 1x 2 5.35 0.23 0.305
TOTAL Total :

3rd floor Roof Beam Total :


4th floor Roof Beam Total :
5th floor Roof Beam
Staircase head room long beam 1x 2 5.23 0.23 0.305
Staircase head room short beam 1x 2 3.30 0.23 0.305
Staircase midlanding beam 1x 2 3.17 0.23 0.280
TOTAL Total :

Providing impervious coat to exposed RCC roof slab


surface with CM(1:3), 20mm thick with 1kg of water
proof compound per bag of cement laid over roof
when it is green including cost of all materials,,
including conveyance charges of materials and
9 including all operational, incidental and labour
charges for mixing mortar, laying, rendering smooth
and thread lining, curing, rounding off junctions of
wall and slab etc,, complete for finished item of
work.

For Cellar Floor 1x 1 39.48 18.77 --


Deduction for Southeast corner -1 x 0.5 3.30 9.69
Southside -1 x 1 4.77 2.06

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Slab area -1 x 1 31.43 10.97


Total Total :
For 5 th Floor
Over terrace 1x 1 31.43 10.97 --
Over projection 1x 1 74.58 0.30 --
water tank side walls allround Top & Bottom 1x 1 4.60 6.60 --
Deductions
Stair case Room (-) -1 x 1 4.72 3.32
Total Total :

Providing High Yield Strength Deformed Steel bars


(Fe 415 Grade as per IS : 1786 and as amended
upto date) of different diameters including labour
charges for cutting bending to required size shapes,
placing in position with cover blocks of approved
materials and size and tying firmly with M.S. Binding
wire of 20 SWG forming grills for reinforcement work
as per approved designs and drawings including
cost and conveyance of deformed steel bars,
10 including all wastage such as overlaps, welded
joints, chairs spacer bars including cost and
conveyance of binding wire cover blocks and all
incidental, opeartional labour charges including
sales and other taxes on all materials etc., complete
for finished item of work in all floors (APSS No.126)
(Payment will be made on the basis of weight of
fabrication deformed bars only) (No re-rolled steel
shall be allowed) complete for (8 mm to 40 mm).

For Cellar
For Footing Qty as above 124.449 0.150 MT/Cum
Pedestals Qty as above 14.024 0.080 MT/Cum
Plinth Beams Qty as above 38.951 0.120 MT/Cum
Colunms Qty as above 24.042 0.150 MT/Cum
Lintals Qty as above 0.042 0.080 MT/Cum
R.C.C. Side walls Qty as above 56.389 0.080 MT/Cum
For Roof Slab Qty as above 107.400 0.120 MT/Cum
Roof Beams Qty as above 29.996 0.150 MT/Cum
TOTAL Total :
Ground floor
For Columns Qty as above 13.563 0.150 MT/Cum
Fro Lintals Qty as above 0.127 0.080 MT/Cum
For Roof Slab Qty as above 57.377 0.120 MT/Cum
For Roof Beams Qty as above 15.260 0.150 MT/Cum
TOTAL Total :
For 1 st Floor
For Columns Qty as above 13.563 0.150 MT/Cum
Fro Lintals Qty as above 0.401 0.080 MT/Cum

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

For Roof Slab Qty as above 45.809 0.120 MT/Cum


For Roof Beams Qty as above 15.019 0.150 MT/Cum
Total Total :
2nd Floor
For Columns Qty as above 13.563 0.150 MT/Cum
Fro Lintals Qty as above 1.615 0.080 MT/Cum
Chajjas Qty as above 0.754 0.080 MT/Cum
For Roof Slab Qty as above 54.187 0.120 MT/Cum
For Roof Beams Qty as above 15.770 0.150 MT/Cum
Total Total :
3rd Floor
For Columns Qty as above 13.563 0.150 MT/Cum
Fro Lintals Qty as above 1.741 0.080 MT/Cum
Chajjas Qty as above 0.837 0.080 MT/Cum
For Roof Slab Qty as above 58.065 0.120 MT/Cum
For Roof Beams Qty as above 15.770 0.150 MT/Cum
Total Total :
4th Floor
For Columns Qty as above 13.563 0.150 MT/Cum
Fro Lintals Qty as above 1.741 0.080 MT/Cum
Chajjas Qty as above 0.837 0.080 MT/Cum
For Roof Slab Qty as above 58.065 0.120 MT/Cum
For Roof Beams Qty as above 15.770 0.150 MT/Cum
Total Total :
5th Floor
Fro Lintals Qty as above 0.084 0.080 MT/Cum
Chajjas Qty as above 0.056 0.080 MT/Cum
For Roof Slab Qty as above 11.232 0.120 MT/Cum
For Roof Beams Qty as above 1.605 0.150 MT/Cum
Total Total :

Masonry work in CM (1:6) prop with Flyash Cement


solid blocks of size 290 x 225 x 140 mm for
manufacturing of flyash solid blocks using flyash of
80 kgs, cement of 15 kgs.Gypsum of 5 kgs. and
11 stone dust including cost and conveyance of all
materials, labour charges, , scaffolding and curing
etc., complete with a compressive strength not
lessthan 50 kg/sqcm for walls for Superstructure
Walls. For Super Structure.

Cellar Floor
Stair Case side walls 1 x 2 5.000 0.23 2.745
Lift Room 1 x 1 7.320 0.23 2.745
Alround the Building above ground 1 x 1 115.370 0.23 0.76
L shape wall 1 x 2 9.160 0.23 1.68
Total Total :
Ground floor

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Vertical walls 1 x 2 7.270 0.23 2.745


Lift Room 1 x 1 7.320 0.23 2.745
Long wall south side horizantal 1 x 1 31.430 0.23 2.745
Long wall north side horizantal 1 x 2 9.630 0.23 2.745
Short wall vertical 1 x 4 10.540 0.23 2.745
Short wall horizontal 1 x 2 3.450 0.23 2.745
Deduction for rolling shutter (13'-0") -1 x 2 3.960 0.23 2.745
Deduction for rolling shutter (14'-0") -1 x 7 4.260 0.23 2.745
Total Total :

For 1st Floor


Lift Room 1 x 1 7.32 0.23 2.745
Long walls horizantal 1 x 1 31.43 0.23 2.745
Long walls horizantal 1 x 2 8.30 0.23 2.745
Long walls horizantal 1 x 2 5.82 0.23 3.05
Short walls vertical 1 x 2 4.97 0.23 2.745
Short walls vertical 1 x 4 10.54 0.23 2.745
Entrance side wall 1 x 2 5.06 0.23 2.745
Deductions
For rolling shutters -1 x 7 4.26 0.23 2.745
For rolling shutters -1 x 1 3.96 0.23 2.745
For rolling shutters -1 x 1 2.74 0.23 2.745
For rolling shutters -1 x 1 2.44 0.23 2.745
Total Total :
2nd Floor
Lift Room 1 x 1 7.32 0.23 2.745
Long walls horizantal 1 x 1 31.43 0.23 2.745
Long walls horizantal 1 x 2 5.82 0.23 3.05
Long walls horizantal 1 x 2 13.50 0.23 2.745
Short walls vertical 1 x 1 4.72 0.23 2.745
Short walls vertical 1 x 4 10.54 0.23 2.745
Deductions
For windows -1 x 18 1.52 0.23 1.37
For ventilators -1 x 6 0.91 0.23 0.45
For staircase room doors -1 x 2 0.91 0.23 2.13
Total Total :
3rd Floor
Lift Room 1 x 1 7.32 0.23 2.745
Long walls horizantal 1 x 2 31.43 0.23 2.745
Long walls horizantal 1 x 1 4.72 0.23 2.745
Long walls horizantal 1 x 2 5.82 0.23 3.05
Short walls vertical 1 x 2 10.54 0.23 2.745
Short walls vertical 1 x 1 5.37 0.23 2.745
Staircase side wall 1 x 2 5.63 0.23 2.745
Deductions
For windows -1 x 20 1.52 0.23 1.37
For ventilators -1 x 6 0.91 0.23 0.45

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

For staircase room doors -1 x 2 0.91 0.23 2.13


Total Total :

4th Floor -- -- -- Total :


5th Floor
Head room alround 1 x 1 16.14 0.23 2.745
Parapet wall alround 1 x 1 85.46 0.23 0.760
Lift room alround 1 x 1 7.32 0.23 2.745
Staircase side walls 1 x 1 5.00 0.23 2.745
Total Total :

Masonry work in CM (1:4) prop with Flyash Cement


solid blocks of size 230 x 100 x 140 mm for
manufacturing of flyash solid blocks using flyash of
80 kgs, cement of 15 kgs.Gypsum of 5 kgs. and
12 stone dust including cost and conveyance of all
materials, labour charges,, scaffolding and curing
etc., complete with a compressive strength not
lessthan 50 kg/sqcm for walls for Superstructure
Walls. For Partion walls.

For Ground Floor Toilets


Horizantal walls 1 x 2 3.05 0.10 3.05
Horizantal walls 1 x 2 1.33 0.10 3.05
Horizantal walls 1 x 2 1.95 0.10 3.05
Vertical walls 1 x 2 4.55 0.10 3.05
Vertical walls 1 x 2 1.35 0.10 3.05
Vertical walls 1 x 2 2.50 0.10 3.05
Vertical walls 1 x 2 0.75 0.10 2.13
Deductions
For doors -2 x 4 0.76 0.10 2.13
Total Total :
1st Floor
Horizantal walls 1 x 2 3.05 0.10 3.05
Horizantal walls 1 x 2 1.33 0.10 3.05
Horizantal walls 1 x 2 1.95 0.10 3.05
Vertical walls 1 x 2 3.42 0.10 3.05
Vertical walls 1 x 2 1.35 0.10 3.05
Vertical walls 1 x 2 2.50 0.10 3.05
Vertical walls 1 x 2 0.75 0.10 2.13
Deductions
For doors -2 x 5 0.76 0.10 2.13
Total Total :

2nd Floor -- -- -- Total :

3rd Floor -- -- -- Total :

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

4th Floor -- -- -- Total :

Plastering with CM (1:4), 12 mm thick in singlecoat


with. Screened sand with sponge finishing including
13 cost and coneyance of all meterials hacking surface,
scaffolding, leads, lifts and labour charges etc.,
complete for CEILING.

For Cellar Floor


Inside slab 1 x 1 39.48 18.77
Staircase waist slab 1 x 1 9.63 1.47
For coloums 1 x 24 1.80 2.745
For beams 1 x 1 260.45 0.84
Wall both sides 1 x 2 115.57 2.75
Deductions : South east corner -1 x 0.5 3.30 9.69
South side portion -1 x 1 4.77 2.06
Staircase room -1 x 1 4.77 3.30
Total Total :
For Ground Floor
Slab 1 x 1 31.43 10.97
Staircase waist slab 1 x 1 9.63 1.47
Ramp 1 x 2 8.05 3.93
Slab projection 1 x 1 79.06 0.30
Beams 1 x 1 51.53 0.84
Columns 1 x 10 1.80 2.745
Deductions : Stair case room -1 x 1 4.77 3.30
Ramp -1 x 2 7.21 3.47
Total Total :
1st Floor
Slab 1 x 1 31.43 10.97
Waist slab bottom 1 x 1 9.63 1.47
Slab projection 1 x 1 73.83 0.30
Beams 1 x 1 51.53 0.84
Columns 1 x 10 1.80 2.75
Deductions : Stair case room -1 x 1 4.77 3.30
Ramp -1 x 1 12.17 5.12
Total Total :

2nd Floor
Slab 1 x 1 31.43 10.97
Waist slab bottom 1 x 1 9.63 1.47
Slab projection 1 x 1 81.23 0.30
Beams 1 x 1 51.53 0.84
Columns 1 x 8 1.80 2.75
Deductions : Stair case room -1 x 1 4.77 3.30
Slab -1 x 1 4.77 5.12
Total Total :

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

3rd Floor
Slab 1 x 1 31.43 10.97
Waist slab bottom 1 x 1 9.63 1.47
Slab projection 1 x 1 86.00 0.30
Beams 1 x 1 51.53 0.84
Columns 1 x 8 1.80 2.75
Deductions : Stair case room -1 x 1 4.77 3.30
Total Total :

4th Floor -- -- -- Total :

5th Foor
Stair case Head Room 1x 1 5.23 3.76 --
Waist slab bottom 1x 1 9.63 1.47
Lift room top and bottom slab 1x 2 2.29 2.29
Total Total :

Providing plastering in CM(1:3), 20mm thick laid


over Granolithic flooring bed when it is green
including cost of all materials, seigniorage charges,
including conveyance charges of materials and
14 including all operational, incidental and labour
charges for mixing mortar, laying, rendering smooth
and thread lining, curing, rounding off junctions of
wall and floor etc,, complete for finished item of work
FOR ORNAMENTAL PLASTERING.

North side 1x 1 32.03 15.00


West side 1x 1 11.57 15.00
Total Total :

Plastering with CM 2 coats, 12 mm thick, base coat


in CM (1:5), 8mm thick and top coat in CM (1:3),
4mm thick with sponze finishing to suit application of
Altek finish including cost and conveyance of all
15 materials and water to work site and all operational
incidental labour charges such as mixing mortar, lift
charges, curing etc.complete for finished item of
work as per SS No. 901, 904 for Exterior Walls.

For Cellar Floor


Stair case outside long wall 1 x 2 5.17 -- 2.745
Stair case outside short wall 1 x 1 4.77 -- 2.745
Lift room alround 1 x 1 8.24 -- 2.745
Alround the Ground leval both sides and top 1 x 1 115.37 -- 2.745
L Shape wall both sides 1 x 2x 2 9.16 -- 2.745
Total Total :
Ground floor
Alround the building 1x 1 84.8 -- 3.05

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Deductions
Rolling shetter -1 x 2 3.96 -- 2.745
Rolling shetter -1 x 7 4.26 -- 2.745
Front ramp -1 x 1 12.09 -- 2.745
Ventilators -1 x 6 0.91 -- 0.45
Total Total :
1 st Floor
Alround the building 1x 1 84.8 -- 3.05
Deductions
Rolling shetter -1 x 7 4.26 -- 2.745
Rolling shetter -1 x 1 3.96 -- 2.745
Rolling shetter -1 x 1 2.74 -- 2.745
Rolling shetter -1 x 1 2.44 -- 2.745
Ventilators -1 x 6 0.91 -- 2.745
Front opening -1 x 1 15.13 -- 2.745
Total Total :
2nd Floor
Alround the building 1x 1 84.8 -- 3.05
Deductions
For windows -1 x 18 1.52 -- 1.37
Ventilators -1 x 6 0.91 -- 0.45
Front opening -1 x 1 4.77 -- 2.745
Total Total :
3rd Floor
Alround the building 1x 1 84.8 -- 3.05
Deductions
For windows -1 x 20 1.52 -- 1.37
Ventilators -1 x 6 0.91 -- 0.45
Total Total :
4th Floor Total :
5th Floor
Head room alround 1x 1 16.14 -- 3.05
Parapet wall alround 1x 1 85.46 -- 1.75
Lift room alround 1x 1 9.16 -- 3.05
Total Total :

Plastering with CM in 2 coats of 12 mm thick, base


coat in CM (1:5) of 8mm thick, top coat in CM (1:3)
of 4mm thick with sponze finishing to suit
application of Altek finish including cost and
16 conveyance of all material and water to work site
and all operational incidental labour charges such as
mixing mortar, lift charges, curing etc.complete for
finished item of work as per SS No. 901, 904 for
Interior Walls.

Cellar Floor
Stair case in side Long walls 1x 2 5.17 - 2.745
Stair case in side Short walls 1x 1 4.77 - 2.745

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Lift Room inside 1x 4 1.83 - 2.745


Total Total :
Ground Floor
Stair case in side Long walls 1 x 2 5.17 -- 3.05
Stair case in side Short walls 1 x 1 4.72 -- 3.05
Lift room in side 1 x 4 1.83 -- 3.05
Lift room out side 1 x 1 9.12 -- 3.05
Inside left side hall and right side hall 1 x 2 47.17 -- 3.05
Ramp 2 sides 1 x 2 11.13 -- 3.05
Ramp side walls 2 x 2 5.77 -- 3.05
For Toilets --
Horizontal walls 2 x 2 3.05 -- 3.05
Horizontal walls 2 x 2 1.95 -- 3.05
Horizontal walls 2 x 2 1.33 -- 3.05
Vertical walls 2 x 2 4.55 -- 3.05
Vertical walls 2 x 2 2.50 -- 3.05
Vertical walls 2 x 2 1.35 3.05
Vertical walls 2 x 2 0.75 2.13
Deductions
For quarters doors. -2 x 4 0.76 -- 2.13
Total Total :
1 st Floor
Stair case in side Long walls 1 x 2 11.00 -- 3.05
Stair case in side Short walls 1 x 1 4.72 -- 3.05
Ramp side wall 2 x 2 5.29 -- 3.05
Inside hall left side and right side 1 x 2 36.77 -- 3.05
Carridor 2 sides 1 x 2 12.47 -- 3.05
Lift room inside 1 x 4 1.83 -- 3.05
Lift room out side 1 x 1 9.12 -- 3.05
Quarters inside alround 1 x 2 16.94 -- 3.05
Horizontal walls 2 x 2 3.05 -- 3.05
Horizontal walls 2 x 2 1.95 -- 3.05
Horizontal walls 2 x 2 1.33 -- 3.05
Vertical 1 x 2 3.27 -- 3.05
Vertical 2 x 2 2.50 -- 3.05
Vertical 2 x 2 1.35 -- 3.05
Vertical 2 x 2 0.75 -- 3.05
Deductions
For staircase -2 x 2 1.98 -- 3.05
For toilet doors -2 x 4 0.76 -- 2.13
Total Total :
2nd Floor
Stair case in side Long walls 1 x 2 11.00 -- 3.05
Stair case in side Short walls 1 x 2 4.72 -- 3.05
Ramp side wall long wall 1 x 4 5.37 -- 3.05
Lift room inside 1 x 1 1.83 -- 3.05
Lift room out side 1 x 2 9.12 -- 3.05

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Inside hall left side and right side 2x 2 47.17 -- 3.05


Toilets
Horizontal walls 2 x 2 3.05 -- 3.05
Horizontal walls 2 x 2 1.95 -- 3.05
Horizontal walls 2 x 2 1.33 -- 3.05
Horizontal walls 2 x 2 5.20 -- 3.05
Vertical 2 x 2 3.27 -- 3.05
Vertical 2 x 2 2.50 -- 3.05
Vertical 2 x 2 1.35 -- 3.05
Vertical 2 x 2 0.75 -- 3.05
Deductions
For staircase room door -1 x 2 0.91 -- 2.13
For toilet doors -2 x 4 0.76 -- 2.13
Total Total :
3rd Floor
Stair case in side Long walls 1x 2 5.40 -- 3.05
Stair case in side Short walls 1x 3 4.72 -- 3.05
Inside hall left side and right side 1x 2 52.12 -- 3.05
Toilets
Horizontal walls 2 x 2 3.05 -- 3.05
Horizontal walls 2 x 2 1.95 -- 3.05
Horizontal walls 2 x 2 1.33 -- 3.05
Horizontal walls 2 x 2 5.20 -- 3.05
Vertical 2 x 2 3.27 -- 3.05
Vertical 2 x 2 2.50 -- 3.05
Vertical 2 x 2 1.35 -- 3.05
Vertical 2 x 2 0.75 -- 2.13
Lift room inside 1 x 4 1.83 -- 3.05
Lift room outside 1 x 1 9.12 -- 3.05
Deductions
Toilet doors -2 x 4 0.76 -- 2.13
Staircase room door -1 x 2 0.91 -- 2.13
Total Total :

4th Floor -- -- -- Total :

5th Floor
Stair case in side Long walls 1 x 2 5.40 -- 3.05
Stair case in side Short walls 1 x 3 4.72 -- 3.05
Lift room inside 1 x 4 1.83 -- 3.05
Lift room outside 1 x 1 9.12 -- 3.05
Total Total :

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Plastering with CM (1:3), 20 mm thickin single coat


with Screened sand with sponge finishing including
17 cost and coneyance of all meterials hancking
surface, scaffolding, leads lifts and labour charges
etc., complete PLASTERING FOR FLOORING.

Cellar Floor
(46.32+
floorarea 1x 1 38.70)/2
20.11
deductions -1 x 1 4.72 2.59
Total Total :

Granolithic concrete flooring 20 mm thick with


(1:1:2) using 6mm to 12 mm size hard granite metal
laid over CC bed already laid or RCC Roof slab in
alternate panels of size not exceeding 1.5Mt x
18 1.5Mt. and finishing the top surface to required
slopes including cost of all materials like cement,
metal, sand and water etc., complete for finished
item of work.
Cellar Floor
(46.32+
floorarea 1x 1 38.70)/2
20.11
deductions -1 x 1 4.72 2.59
Total Total :

Flooring with vitrified tiles of size not less than 598


mm x 598 mm, 8 to 10 mm thick glossy finish
premium colour normal colour 1st quality set over
base coat of cement mortar (1:8), 12mm thick over
CC bed already laid or RCC roof slab, including neat
19 cement slurry of honey like consistency spread @
3.3.kgs per sqm & jointed neatly with white cement
paste to full depth mixed with pigment of matching
shade, Pointing with CM (1:3) including cost of all
materials like cement, sand water and tiles etc.,
complete, for finished item of work.

Ground Floor
Floor area 1 x 1 30.97 10.51
Deduction for ramp portion -1 x 2 3.47 7.21
toilet rooms -1 x 2 5.82 3.30
stari case room -1 x 1 4.54 3.30
Total Total :
First floor
Floor area 1 x 1 30.97 10.51
Deduction for span C36-C39-C48-C51 -1 x 1 12.17 5.12
Toilet rooms -1 x 2 5.82 3.30
Staircaseroom -1 x 1 4.54 3.30
Total Total :

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Second floor
Floor area 1 x 1 30.97 10.51
Deduction for staircase room -1 x 1 4.54 3.30
Deduct for toilet portion -1 x 2 5.82 3.30
For span C37-C38-C49-50 -1 x 1 4.77 5.12
Total Total :
Third floor
Floor area 1x 1 30.97 10.51
Deduction for staircase room -1 x 1 4.54 3.30
Deduct for toilet portion -1 x 2 5.82 3.30
Total Total :

Forth floor Total :

Providing skirting to internal walls to 15 cm


height/risers of steps with vitrified tiles length equal
to flooring stones, set over base coat of CM (1:5) 12
mm thick with cement slurry of honey like
20 consistency spread at the rate of 3.30 kgs per sqm
and jointed with white cement paste mixed with
pigment of matching shade to full depth, including
cost of all materials like tiles, cement, sand and
water etc., complete for finished item of work.

Ground floor (Skirting Qty. = 10% of flooring Qty.) 222.064 10%


1st floor 209.791 10%
2nd floor 247.679 10%
3rd floor 272.101 10%
4th floor 272.101 10%

Flooring with ceramic tiles of 7.3mm thick of 1st


quality of all shades set over base coat of cement
mortar (1:8), 12 mm thick over CC bed already laid
or RCC roof slab, including neat cement slurry of
21 honey like consistency spread @ 3.3.kgs per sqm &
jointed neatly with white cement paste to full depth
mixed with pigment of matching shade, including
cost of all materials like cement, sand water and tiles
etc., complete, for finished item of work.

Toilets
Groundfloor 1 x 2 5.82 3.30
1st floor 1 x 2 5.82 3.30
2 nd Floor 1 x 2 5.82 3.30
3 rd Floor 1 x 2 5.82 3.30
4 th Floor 1 x 2 5.82 3.30

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Dadoing walls with 1st quality of glazed plain


coloured tiles of 5 to 7 mm thick of any size cement
base in C.M.(1:3) Prop. and neat cement slurry of
honey like consistency at the rate of 3.30 Kgs.
22 cement per Sq.mt. mixed with pigment of matching
shade of tiles including charges, curing etc.,
complete as directed by the department for finished
of work inclusive of all taxes for
BATH ROOMS.

Cellar floor
Stair case side long walls 1x 2 5.43 - 1.52
Stair case side short walls 1x 1 4.72 - 1.52
Total Total :
Ground floor
Stair case side long walls 1 x 2 5.43 -- 1.52
Stair case side short walls 1 x 1 4.72 1.52
Toilet horizontal walls 1 x 2 17.17 1.52
Toilet vertical walls 1 x 2 15.64 -- 1.52
Lift room 1 x 2 8.22 -- 1.52
Total Total :
1stfloor
Toilets quantity
Toilet horizontal walls 1 x 2 17.17 1.52
Toilet vertical walls 1 x 2 15.64 -- 1.52
Stair case side long walls 1 x 2 5.43 - 1.52
Stair case side short walls 1 x 1 4.72 - 1.52
Lift room 1 x 2 8.22 -- 1.52
for corridor 1 x 1 25.10 -- 1.52
Total Total :
2nd Floor
Toilet horizontal walls 1 x 2 17.17 1.52
Toilet vertical walls 1 x 2 15.64 -- 1.52
Stair case side long walls 1 x 2 5.43 - 1.52
Stair case side short walls 1 x 1 4.72 - 1.52
Total -- -- -- Total :

3rdfloor -- -- -- Total :

4th floor -- -- -- Total :

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Supply and fixing of High strength cement concrete


designer tiles of 30mm thicknes of M40 Grade which
top 12mm thick shall be for color pigmentation with
imparted colour and white cement to get required
reflective glazing inclisive of all taxes. and over a
bse coat of C.M.(1:8) Prop. 20 mm thick including
23 neat cement slurry of honey like consistency spread
at the rate of 3.30 Kg. per Sq,/ and filling the joints
with white cement at 2.00 Kg. per Sq.m. mixed with
pigment of matching shade including cost and
conveyance of all materials, labour charges, laying
of tiles etc., complete as directed by the Department
for For stair case and Portco.

For Cellar floor


Steps rise and tread 1x 20 1.24 0.49
Steps rise and tread 2x 20 1.24 0.49
North side ramp 1x 2 11.27 3.47
Total Total :
Ground floor
Steps rise and tread 1x 20 1.24 0.49
Ramp 1x 2 8.05 3.47
Total Total :
First floor
Steps rise and tread 1x 20 1.24 0.49

Total Total :

Second floor Total :

Third floor Total :

Fourth floor Total :

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Providing and fixing door frame fabricated from


section made of galvanized steel powder coated
(base steel as per IS 513,galvanized as per IS 217
with zinc of 120 grams/square meter). The factory
made section should be with a powder coating of
pure polyester powder of 50-60 microns thick with
total coated thickness of 1.25 mm. Size of door
frame section should be of 105 x 60 mm with a
rebate of 38mm to accommodate 30 mm thick door
shutter with groove to insert gasket in the frame
section, frame section to be filled with polyurethane
24 foam. the frame section should be cut to length and
joined by way be way of welding. Each frame should
be provided with : 2mm thick MS powder coated butt
Supplying and fixing of PVC Door frames made from
hinges of 100 mm long -3 Nos. for single shutter,
extruded sections in over all dimentions of 40 x
6Nos. double shutter. CRCA Electroplates stiffeners
48mm having wall thickness of 1.55 mm. wiht usual
of 6 Nos. -3 in each vertical for double shrtter and
porcess veriation of +/- 0.3mm complete and Sintex
40mm x 200 mm x 1.2 mm hold fasts screwed to
door shutter made from specially Hot Press Moulded
stiffeners - 6Nos. with split end tail. Nylon Aldrop
SMC (Sheet moulding coumpound sheets,
Receiver -1No. for single shutter frame. Tie Rod 1
Polyurethene core and PVC Frame Section SMS
No. DOOR FRAME FOR WITH OUT SILL OF SIZE
sheets shall be made from SMC comforming to IS
0.91X2.13 M.
13410 sheet shall have an average thickness of 1.4
mm +0.35 mm on both sides. Core of the door
shutter shall be filled with high density polyurethane
foam , injected wiht the help of hydraulic injection
method shutter frame to be made of PVC extruded
D1 - Doors
section of size 0.91x2.13
confirming to IS:10151 :1982 of size 26 mm 1x 6 -- -- --
x 46 mm with a wall thickness of 1.4 mm +0.3mm on
25 both sides corresponding to sintex code DWUF 305.
The hardware locations shall be reinforced with
special polymeric reinforcement wooden blocks of
suitable size. The corners of the shutter frame shall
Sintex doors size
be reinforced withof 0.76 x 2.13
Polymeric 'L' shaped angle of size 1x 48 -- -- --
105 mm x 230 mm corresponding to Sintex code
PR-02 and
Supply the fixing
lock ofrailFlush
shall
doorbesingle
madeleaffrom PVC
flushdoor
extrudedofsections
shutter solid having
bond overall dimensions
wood black board oftype
26
mm x 46 mm
30mmthick 1.5 mm to
conforming +0.3mm
IS2202on both sides,
commercial plywith
on
usualfaces
both process variation
including cost ofcorresponding to Sintex
fixtures of M.S.Powder
code 305
coated combining
1 No. 250 mmtwo longnumbers.
aldrop, 1Wooden
No. of 200 pieces
mm
26 long
are inserted
aldrop, 1onNo.the periphery.
of 200 mm tower Suitable
blot, 1MS No.Tube
125
reinforcement
mm long handle shall be provided
including on vertical
cost and conveyancesides of
shutter
all frameand
materials thelabour
rate inclusive of allcomplete
charges etc., taxes and as
finished item work Color: White & Grey.
per drawing and as directed by the department for SINTEX
ENDURA
DOOR OFDOOR
SIZE: SHUTTER
0.91 X 2.13(26MM
Mts. THICK).

Door shutters 1x 6 -- -- --

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Providing and fixing ofdouble Openable / Casement


Windows with fly mesh made of pre-painted steel (Base
steel as per IS 513 of 0.80 mm. thick galvanized as per
IS-277 with Zinc of 120 GSM), finish painted with a
polyester paint of 60-65 microns thick and section for
outer frame fo 100 x 45 mm., centre mullion of 100x60
mm, section for shutter of 52 x 25 mm x 0.6 mm thick,
section for fly-shutter of 52 x 25 m x 0.6 mm thick and
fitted with stainless steel 32 gauge fly mesh of 304 grade
with 144 holes per Sq.inch and mullions to have double
rebate for glazed shutter and fly-shutter with a provision
for guard bars/grills and the sections cut to length metre
27 joined with corner bracket, centre mullion fixed with
mullion cap, 1 No.of High grade nylon latch handle,
window stopper, 2 Nos. of with MS powder coated/ SS
ball bearing butt Hinges provided per shutter and
windows fitted with 4 mm thick plain float glass with
rubber gaskets including fixing the frames in concrete/
masonry wall by means of self expanding screws,
including 10 mm square guard bars with 6" (152.4mm)
pitch etc., complete for finished item of work. Windows of
size 5'-0"x4'-0" (1524x1219.20mm) outerframe section of
size 80x45mm, shutterframe section size of 52x25mm,
vertical mullion section of size 100x60mm beeding
section size of 9x12mm to be provided for glass holding.

W - window of size 1.52 x 1.37 1x 58 -- -- --

Providing and fixing of top hung Ventilators made of pre-


painted steel (Base steel as per IS 513of 0.80mm thick
galvanized as per IS 277 with Zinc of 120 GSM), finish
painted with a polyester paint of 60-65 microns thick and
section for outer frame of 80 x 45mm, centre mullion of
80 x 60mm, section for shutter of 52 x 25mm x 0.6mm
thick, outer frame and mullions to have rebate for glazed
shutter with a provision for guard bars/ grills and the
sections cut to length metre joined with corner bracket,
centre mullion fixed with mullion cap, 1No. of High grade
nylon latch handle, window stopper, 2 Nos. of with MS
28 powder coated / SS ball bearing but hinges provided per
shutter and windows fitted with 4 mm thick plain float
glass with rubber gaskets including fixing the frames in
concrete / masonry wall by means of self expanding
screws, including 10mm square guard bars with 6"
(152.4mm) pitch etc., complete for finished item of work.
Single fixed louvers ventilator size of 2'-0" x 2'-0" (609.6 x
609.6 mm) outer frame box section size of 80 x
45mm.Ventilator window 2'-6" x 1'-6" . Outer frame
section size 72 x 0mm shutter frame section size of 47 x
20mm 0.91 x 0.46 mm. Ventilator window.

V - Ventilators of size 0.91 x 0.45 1x 30 -- -- --

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Supply and fixing of rolling shutter made of 80 x 1.25


mm. machine rolled CRCA laths, interiocked
together through their entire length and jointed
together at the ends by end locks, mounted on
specially designed pipe shaft of 50 mm. dia nominal
bore MS. B class pipe wiht brackets, plates, guide
29 channels, stoppers, bottom locking plates and
arrangements for inside & outside locking with push-
pull operations inlcuding cost of hood cover and
springs complete, painted wiht one coat of approved
steel primer, locks, ball bearings, all accessories
etc., complete for finished item of work as per
special spn : 1108.

For rollingshutter 1 x 14 4.26 2.745


For rollingshutter 1 x 1 2.74 -- 2.745
For rollingshutter 1 x 1 2.44 -- 2.745
For rollingshutter 1 x 3 3.96 -- 2.745
Total Total :

PAINTING to new WOOD work / Iron work in two


coats with synthetic enamel paint of approved
colour, over one coat of primary coat including cost
30 and conveyance of all materials, incidental charges
such as sand paper, cleaning the surface, cost of
brushes and putty etc., complete. (Three coats).

for rollingshutter 14 x 2 4.26 2.745


for rollingshutter 1 x 2 2.74 -- 2.745
for rollingshutter 1 x 2 2.44 -- 2.745
for rollingshutter 3 x 2 3.96 -- 2.745
Doors D2 48 x 2 0.76 2.745
Doors D1 6 x 2 0.91 2.745
Window of size 5'-0" x 4'-6" 58 x 2 1.52 1.37
Ventilators of size 3'-0" x 1'-6" 30 x 2 0.91 0.45
Total Total :

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Providing and applying synthetic plaster putty or


plaster of parris putty or lime punning of average 1
to 2mm thickness over plastered surface to prepare
the surface even and smooth after throughly
brushing the surface to remove all dirt and remains
of loose powdered materials, applying emery
31 paper ,sand the surface ,clean & wipe off loose
dust ,applying knifing paste filler putty knife/muslin
pad ,air dry for 2-3 hrs sand with 180 and
320no,emery paper for the surface preparation
including cost and conveyance of all matrials to work
site and all operational ,incidental,labour chages etc
complete for finished item of work for internal walls.

Cellar floor
Cellar Ceiling Qty. --
Cellar Plastering Qty
Total Total :
Groundfloor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
1st Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
2nd Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
3rd Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
4th Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
5th Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Painting to new walls with 2 coats of water proof


cement paint interior grade-I of approved brand and
shade over a base coat of approved cement primer
grade I making 3 coats in all to give an even shade
32 after throughly brushing the surface to remove all
dirt and remains of loose ppowdered materials to
work site and all operational, incidental, labour
charges etc., complete for finished item of work as
per SS 912 for internal walls.

Cellar floor
Cellar Ceiling Qty. -- -- --
Cellar Plastering Qty
Total Total :
Groundfloor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
1st Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
2nd Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
3rd Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
4th Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :
5th Floor
Ceiling Qty -- -- --
Plastering Qty
Total Total :

Det-Civil
Sl.
Description Nos. Length Breadth Depth
No.

Painting to new walls with 2 coats of water based


cement primer of exteriorgrade -II paint of approved
brand and shade over a base coat of approved
cement primer grade-2 making 3 coats in all to give
33 an even shade after throughly brushing the surface
to remove all dirt and remains of loose ppowdered
materials to work site and all operational, incidental,
labour charges etc., complete for finished item of
work as per SS 912 for exterior walls.

Cellar floor
External Plastering Qty. -- -- --

Ground floor
External Plastering Qty. -- -- --

1st Floor
External Plastering Qty. -- -- --

2nd Floor
External Plastering Qty. -- -- --

3rd Floor
External Plastering Qty. -- -- --

4th Floor
External Plastering Qty. -- -- --

5th Floor
External Plastering Qty. -- -- --

Supply and fixing 110 mm dia 4.00 Kg./Sq.Cm.


pressure P.V.C.Pipe of Prince / Sudhakar make from
roof up to basement level including plain bend clips
34 and shoe as per ISI. Standard fixed to wall with pipe
clips including labour charges etc., complete for
RAIN WATER PIPE.
For down take pipe 1x 4 17.00 --

Det-Civil
ETAILED ESTIMATE
mmercial Complex (Cellar+Ground+4Floors) at Maddilapalem,
n the place of existing A & B staff quarters.

QUANTITY Unit

2135.899
-42.557
107.168
-2.220
-2.398
2195.892

19.125
30.625
29.839
54.673
40.817
78.732
90.160
21.141
32.718
397.830
2593.722 Cum.

2.550
3.000
3.035
4.970
3.602
6.561
7.310
2.187
2.517
35.732 Cum.

Det-Civil
QUANTITY Unit

2.448
5.733
6.694
16.641
13.163
28.125
33.708
4.950
12.987
124.449 Cum.

3.007
9.788
0.365
0.864
14.024 Cum.

8.172
0.330
0.257
0.207
0.257
2.169

Det-Civil
QUANTITY Unit

2.541
1.006
1.161
0.361

11.656

0.391
0.424
0.627
0.828
1.238
7.326
38.951 Cum.

0.632
1.265
11.732
0.765
14.394 Cum.

0.632

Det-Civil
QUANTITY Unit

8.380
9.012 Cum.

0.632 Cum.

0.632 Cum.

0.632 Cum.

0.632 Cum.

1.252
10.870
2.594
2.223

7.103

24.042 Cum.

1.252
10.870
0.494
0.947
13.563 Cum.

13.563 cum.
13.563 cum.
13.563 cum.
13.563 cum.

0.042
0.042 Cum.
0.042
0.085
0.127 Cum.

0.042
0.106
0.253
0.401 Cum.

Det-Civil
QUANTITY Unit

0.042
0.106
1.130
0.253
0.084
1.615 Cum.

0.042
0.106
1.256
0.253
0.084
1.741 Cum.
1.741 cum.

0.084 Cum.

7.181
16.499
7.324
17.640
7.745
56.389 Cum.

397.830

-35.732
-124.449
-14.02
-38.951
184.674 Cum.

107.168
-2.220

Det-Civil
QUANTITY Unit

-2.398
0.000
2.129
10.458
5.126
1.778
7.401
129.442 Cum.

15.070 Sqm

16.744 Sqm

16.744 Sqm

1.122 Sqm

Det-Civil
QUANTITY Unit

111.156
2.477

-2.361
-1.474
-2.398
107.400 Cum.

51.718
2.477
9.491
3.558
-2.361
-7.506
57.377 Cum.

51.718
2.477
3.322

-2.361
-9.347
45.809 Cum.

Det-Civil
QUANTITY Unit

51.718
2.477
3.655
0.000
-3.663
54.187 Cum.

51.718
2.477
3.870
58.065 Cum.

58.065 Cum.

2.950
2.477
4.232
1.573
11.232 Cum.

5.539
0.606
0.688
0.194
2.584
1.023
1.181
0.637
0.842
4.133
0.459
2.249
1.209
1.995
0.445
2.029
2.293
1.224
0.666
29.996 Cum.

2.702
0.734

Det-Civil
QUANTITY Unit

0.335
1.200
0.487
0.126
2.205
6.027
0.752
0.284
0.408
15.260 Cum.

4.410
0.487
0.128
1.200
1.351
6.027
0.724
0.284
0.408
15.019 Cum.

15.019
0.751
15.770 Cum.

15.770 Cum.
15.770 Cum.

0.734
0.463
0.408
1.605 Cum.

741.040
-15.989
-9.826

Det-Civil
QUANTITY Unit

-344.787
370.438 Sqm

344.787
22.374
30.360

-15.670
37.064 Sqm

18.667
1.122
4.674
3.606
0.003
4.511
12.888
4.499
49.970 MT

2.034
0.010
6.885
2.289
11.218 MT

2.034
0.032

Det-Civil
QUANTITY Unit

5.497
2.253
9.816 MT

2.034
0.129
0.060
6.502
2.366
11.091 MT

2.034
0.139
0.067
6.968
2.366
11.574 MT

2.034
0.139
0.067
6.968
2.366
11.574 MT

0.007
0.004
1.348
0.241
1.600 MT

6.314
4.621
20.167
7.079
38.181 Cum

Det-Civil
QUANTITY Unit

9.180
4.621
19.843
12.160
26.618
4.356
-5.000
-18.827
52.951 Cum

4.621
19.843
10.480
8.165
6.276
26.618
6.389

-18.827
-2.500
-1.730
-1.540
57.795 Cum

4.621
19.843
8.165
17.046
2.980
26.618

-8.621
-0.565
-0.892
69.195 Cum

4.621
39.687
2.980
8.165
13.309
3.390
7.109

-9.579
-0.565

Det-Civil
QUANTITY Unit

-0.892
68.225 Cum

68.225 Cum

10.190
14.938
4.621
3.157
32.906 Cum

1.861
0.811
1.190
2.776
0.824
1.525
0.320
0.000
-1.295
8.012 Cum

1.861
0.811
1.190
2.086
0.824
1.525
0.320

-1.619
6.998 Cum

6.998 Cum

6.998 Cum

Det-Civil
QUANTITY Unit

6.998 Cum

741.040
14.156
118.584
218.778
634.479
-15.989
-9.826
-15.741
1685.481 Sqm

344.787
14.156
63.273
23.718
43.285
49.410
-15.741
-50.037
472.851 Sqm

344.787
14.156
22.149
43.285
49.410
-15.741
-62.310
395.736 Sqm

344.787
14.156
24.369
43.285
39.528
-15.741
-24.422
425.962 Sqm

Det-Civil
QUANTITY Unit

344.787
14.156
25.800
43.285
39.528
-15.741
451.815 Sqm

451.815 Sqm

19.665
14.156
10.488
44.309 Sqm

480.450
173.550
654.000 Sqm

28.383
13.094
22.619
316.691
100.577
481.364 Sqm

258.640

Det-Civil
QUANTITY Unit

-21.740
-81.856
-33.187
-2.457
119.400 Sqm

258.640

-81.856
-10.870
-7.521
-6.698
-14.988
-41.532
95.175 Sqm

258.640

-37.483
-2.457
-13.094
205.606 Sqm

258.640

-41.648
-2.457
214.535 Sqm
214.535 Sqm

49.227
149.555
27.938
226.720 Sqm

28.383
13.094

Det-Civil
QUANTITY Unit

20.093
61.570 Sqm

31.537
14.396
22.326
27.816
287.737
67.893
70.394

37.210
23.790
16.226
55.510
30.500
16.470
6.390

-12.950
695.245 Sqm

67.100
14.396
64.538
224.297
76.067
22.326
27.816
103.334
37.210
23.790
16.226
19.947
30.500
16.470
9.150

-24.156
-12.950
634.565 Sqm

67.100
28.792
65.514
5.582
55.632

Det-Civil
QUANTITY Unit

575.474

37.210
23.790
16.226
63.440
39.894
30.500
16.470
9.150

-3.877
-12.950
1017.947 Sqm

32.940
43.188
317.932

37.210
23.790
16.226
63.440
39.894
30.500
16.470
6.390
22.326
27.816

-12.950
-3.877
661.295 Sqm

661.295 Sqm

32.940
43.188
22.326
27.816
126.270 Sqm

Det-Civil
QUANTITY Unit

854.876

-12.225
842.651 Sqm

854.876

-12.225
842.651 Sqm

325.495
-50.037
-38.412
-14.982
222.064 Sqm

325.495
-62.310
-38.412
-14.982
209.791 Sqm

Det-Civil
QUANTITY Unit

325.495
-14.982
-38.412
-24.422
247.679 Sqm

325.495
-14.982
-38.412
272.101 Sqm

272.101 Sqm

22.206 Sqm.
20.979 Sqm.
24.768 Sqm.
27.210 Sqm.
27.210 Sqm.

38.412 Sqm.
38.412 Sqm.
38.412 Sqm.
38.412 Sqm.
38.412 Sqm.

Det-Civil
QUANTITY Unit

16.507
7.174
23.681 Sqm

16.507
7.174
52.197
47.546
24.989
148.413 Sqm

52.197
47.546
16.507
7.174
24.989
38.152
186.565 Sqm

52.197
47.546
16.507
7.174
123.424 Sqm

123.424 Sqm

123.424 Sqm

Det-Civil
QUANTITY Unit

12.152
24.304
78.214
114.670 Sqm

12.152
55.867
68.019 Sqm

12.152

12.152 Sqm

12.152 Sqm

12.152 Sqm

12.152 Sqm

Det-Civil
QUANTITY Unit

6.000 Nos.

48.000 Nos.

6.000 Nos.

Det-Civil
QUANTITY Unit

58.000 Nos.

30.000 Nos.

Det-Civil
QUANTITY Unit

163.712
7.521
6.698
32.611
210.542 Sqm

327.424
15.043
13.396
65.221
200.275
29.975
241.558
24.570
917.462 Sqm

Det-Civil
QUANTITY Unit

1685.481
61.570
1747.051 Sqm

472.851
695.245
1168.096 Sqm

395.736
634.565
1030.301 Sqm

425.962
1017.947
1443.909 Sqm

451.815
661.295
1113.110 Sqm

451.815
661.295
1113.110 Sqm

44.309
126.270
170.579 Sqm

Det-Civil
QUANTITY Unit

1685.481
61.570
1747.051 Sqm

472.851
695.245
1168.096 Sqm

395.736
634.565
1030.301 Sqm

425.962
1017.947
1443.909 Sqm

451.815
661.295
1113.110 Sqm

451.815
661.295
1113.110 Sqm

44.309
126.270
170.579 Sqm

Det-Civil
QUANTITY Unit

481.364 Sqm

119.400 Sqm

95.175 Sqm

205.606 Sqm

214.535 Sqm

214.535 Sqm

226.720 Sqm

68.000 Rmt

Det-Civil
CIVIL DATAS
As per Common SSR 2015-16
Name of Work :- Construction of Commercial Complex (Cellar+Gr
Maddilapalem, Visakhapatnam in the place of existing A & B S

Earth work excavation for foundations and depositing on bank for all lifts and with an init
operational, incidental, labour charges such as shoring incidental, sheeting, planking, struttin
1
item of work .in ordinary soils by manual means upto 3.00mt depth excluding dewatering c
(APSS 308)

A.P.Standard Data No.9 Unit -1 CUM


A) Labour
Man Mazdoor Day 3.64

Add 75% Extra for foundation Rs.


Total Rs.
Add 13.615% Contractor's Profit & Over head charges Rs.
Total Rs.
Rate per 1 CUM Rs.
Sundries
Total Rs.

B) Labour for other works Unit -1 CUM


Man Mazdoor Day 3.64
Add 13.615% Contractor's Profit & Over head charges Rs.
Total Rs.
Rate of 1 Cum Rs.
Add Sundreis
Total Rs.

Data-Civil
Earth work excavation for foundations and depositing on bank for all lifts and with an init
operational, incidental, labour charges such as shoring incidental, sheeting, planking, struttin
1A
item of work .in ordinary soils by Mechanical means upto 3.00mt depth excluding dewaterin
B (APSS 308)

A.P.Standard Data No.10 (P.16) Unit -1 CUM


A) Labour
Man Mazdoor including 40% labour towards Day 8.32
Minicipal limits area allowance
B) Machinery
Hydraulic excavator (P.256, S.No.4) Hrs 6.00
Total Rs.
Add 13.615% Contractor's Profit & Over head charges Rs.
Total Rs.
Rate per 1 CUM Rs.
Sundries
Total Rs.

Data-Civil
Laying PCC work of mix (1 : 4 : 8) prop. Using 40 mm gauge hard granite machine crush
2
conveyance of all materials, machine mixing, labour charges, tamping, curing, taxes etc., com

A.P.Standard Data No.22, Page No.20 (BLD-CSTN)-3.5


A. MATERIALS:
Cement MT 0.162
Coarse aggregate 40 mm (HBG Metal) -
Cum. 0.90
( as per chart)
Fine aggregate (Sand) Cum 0.45
Water (including for curing) Urban KL. 1.2
(P.No.223, Item No.189.a)
B. MACHINERY
Concrete Mixer 10/7 cft (0.2/0.8 Cum. Capacity)
Hour 1
300/200 Diesel (Pg.No.230,Item.16)
Add. 40% on Crew charges of 206.70 Hour 1
(P.No.289, Item No.18)
C. LABOUR:
Mason 1st class (including area allowance) Day 0.1
Man Mazdoor (including area allowance) Day 1.39
Total Rs.
Add 13.615% Contractor's Profit & Over head charges Rs.
Sundries Rs.
Total Rs.

Data-Civil
Supply and placing of the Design Mix Concrete of grade M30 corresponding to IS 456 usi
minimum cement content of 380 Kg. per Cum with 12mm and 20mm size graded machine
(coarse aggregate) from approved quarry including cost and conveyance of all materials
( sand) coarse aggregate, water etc., to site and including, sales & other taxes on all mater
3 incidental and labour charges such as weigh batching, machine mixing, laying concrete, Vi
but excluding cost of steel and its fabrication charges for finished item of work (APSS
shuttering using adjastable Jack Screws, Props and Acro span beams including all pipe bra
fabricated steel H-frames, cross members etc., Complete, laying concrete, vibrating, curing
cost of steel and its fabrication charges for finished item of work. FOUNDATIONS, PLINTH, P

A.P.Standard Data No.31 A, P.No.24 and 25.


A. MATERIALS:
a 20mm HBG graded metal Cum 0.53
b 12 mm HBG graded metal Cum 0.27
Sand Cum 0.40
Cement MT 0.38
Water (including for curing) Urban KL. 1.20
(P.No.223, Item No.189.a)
B. LABOUR:
Mason 1st class (including area allowance) Day 0.133
Mason 2nd class (including area allowance) Day 0.267
Man Mazdoor (including area allowance) Day 4.600
C. MACHINERY
Weigh Batcher 0.50 Cum/Hour Hire charges (Machine mixing)
of Item No.9 of P.No.229 Cum. 1.333
Add M.L 40% on CREW Charges 320.00 Hour 1.333
vide P.No. 229 item No 9
Needle vibrator hire charges 40mm. As per Hour 1.333
vide P.No. 230 item No 40
Add M.L 40% on CREW Charges 148.80 Hour 1.333
Sundries
Total

Data-Civil
A) FOR FOOTINGS
Cost of M30 Grade Concreate Cum 1
Centring charges Cum 1
(Item No.1A P.No.66)
Add M.L 40% on labour charges 473.00 Cum 1
Total (Item No.IA, P.No.66). Rs.
Add 13.615% Contractor's Profit & Over head charges Rs.
Sundries Rs.
Total

Data-Civil
B) PEDESTALS
Cost of M30 Grade Concreate Cum 1
Centring charges Cum 1
(Item No.1C P.No.66)
Add M.L 40% on labour charges 753.00 Cum 1
Total Rs.
Add 13.615% Contractor's Profit & Over head charges Rs.
Sundries Rs.
Total

Data-Civil
C) PLINTH BEAMS
Cost of M30 Grade Concreate Cum 1
Centring charges Cum 1
(Item No.1D P.No.66)
Add M.L 40% on labour charges 1141.00 Cum 1
Total Rs.
Add 13.615% Contractor's Profit & Over head charges Rs.
Sundries Rs.
Total

Data-Civil
Supply and placing of the Design Mix Concrete of grade M30 corresponding to IS 456 usi
minimum cement content of 380 Kg. per Cum with 12mm and 20mm size graded machine
(coarse aggregate) from approved quarry including cost and conveyance of all materials
(sand) coarse aggregate, water etc., to site and including, sales & other taxes on all mater
incidental and labour charges such as weigh batching, machine mixing, laying concrete, vi
4
but excluding cost of steel and its fabrication charges for finished item of work (APSS
shuttering using adjastable Jack Screws, Props and Acro span beams including all pipe bra
fabricated steel H-frames, cross members etc., Complete, laying concrete, vibrating, curing
cost of steel and its fabrication charges for finished item of work. COLUMNS, LINTELS, WAT
BUILDINGS.

A.P.Standard Data No.31 B (Page No.25)


I .VRCC M30
A. MATERIALS:
a 20mm HBG graded metal Cum 0.53
b 12 mm HBG graded metal Cum 0.27
Sand Cum 0.40
Cement MT 0.38
Water (including for curing) KL 1.20
(P.No.223, Item No.189.a)
B. LABOUR:
Mason 1st class (including area allowance) Day 0.167
Mason 2nd class (including area allowance) Day 0.167
Man Mazdoor (including area allowance) Day 5.600
C. MACHINERY
Weigh Batcher 0.50 Cum/Hour Hire charges (Machine mixing)
of Item No.9 of P.No.229 Cum. 1.333
Add M.L 40% on CREW Charges 320.00 Hour 1.333
vide P.No. 229 item No 9
Needle vibrator hire charges 40mm. As per Hour 1.333
vide P.No. 230 item No 40
Add M.L 40% on CREW Charges 148.80 Hour 1.333
Sundries
Total

Data-Civil
A II. PCC M30 for Steps

VRCC M30 - Rs. 8184.35


Deduct Vibration charges 313.14
Rate for PCC M30 = 7871.21
Cost of M30 Grade Concreate Rs.
Centring charges Rs. 2344.00 (P.No.66, SI.No.1E)
Centring Material charges Rs 1133.00
Centring Labour charges Rs. 1211.00
Winch charges (P.231, Sl.No.66) (1.333 x 577.00 = 769.14
Crew charges 1.333x248.00=330.58 x M.L@40%= 132.23
Lift Charges = Rs. Charges
901.37
Centering Charges vide Item
No.1e, P.No.66 & 68 of SSR vide
Sl. Initial
Floor M.L P.No.131 Total
No. Rate Material Labour
@ 40% of
1 Cellar 7871.21 1133.00 1211.00 484.40 A.P.Stand
-- 10699.61
2 G.F 7871.21 1133.00 1211.00 484.40 -- 10699.61
3 1St 7871.21 1133.00 1332.00 532.80 -- 10869.01
4 2nd 7871.21 1133.00 1453.00 581.20 901.37 11939.78
5 3rd 7871.21 1133.00 1574.00 629.60 978.28 12186.09
6 4th 7871.21 1133.00 1695.00 678.00 1055.19 12432.40
7 5th 7871.21 1133.00 1817.00 726.80 1132.10 12680.11

Data-Civil
B) For COLOUMNS centering with steel scaffolding pipes, jack props, steel centering plat

VRCC M30 - @ Rs. 8184.35 Rs.


Centring charges Rs. 2041.00 (P.No.66, SI.No.1G)
Centring Material charges Rs 341.00
Centring Labour charges Rs. 1700.00
Winch charges (P.231, Sl.No.66) (1.333 x 577.00 = 769.14
Crew charges 1.333x248.00=330.58 x M.L@40%= 132.23
Lift Charges = Rs. Charges
901.37
Centering Charges vide Item
No.1e, P.No.66 & 68 of SSR vide
Sl. Initial
Floor M.L P.No.131 Total
No. Rate Material Labour
@ 40% of
1 Cellar 8184.35 341.00 1700.00 680.00 A.P.Stand
-- 10905.35
2 G.F 8184.35 341.00 1700.00 680.00 -- 10905.35
3 1St 8184.35 341.00 1870.00 748.00 -- 11143.35
4 2nd 8184.35 341.00 2040.00 816.00 901.37 12282.72
5 3rd 8184.35 341.00 2210.00 884.00 978.28 12597.63
6 4th 8184.35 341.00 2380.00 952.00 1055.19 12912.54
7 5th 8184.35 341.00 2550.00 1020.00 1132.10 13227.45

Data-Civil
C) FOR LINTELS centering with steel scaffolding pipes, jack props, steel centering plates

VRCC M30 - Rs. 8184.35


Deduct Vibration charges 313.14
Rate for PCC M30 = 7871.21
Cost of M30 Grade Concreate Rs.
Centring charges Rs. 2344.00 (P.No.66, SI.No.1E)
Centring Material charges Rs 1133.00
Centring Labour charges Rs. 1211.00
Winch charges (P.231, Sl.No.66) (1.333 x 577.00 = 769.14
Crew charges 1.333x248.00=330.58 x M.L@40%= 132.23
Lift Charges = Rs. Charges
901.37
Centering Charges vide Item
No.1e, P.No.66 & 68 of SSR vide
Sl. Initial
Floor M.L P.No.131 Total
No. Rate Material Labour
@ 40% of
1 Cellar 7871.21 1133.00 1211.00 484.40 A.P.Stand
-- 10699.61
2 G.F 7871.21 1133.00 1211.00 484.40 -- 10699.61
3 1St 7871.21 1133.00 1211.00 484.40 -- 10699.61
4 2nd 7871.21 1133.00 1211.00 484.40 901.37 11600.98
5 3rd 7871.21 1133.00 1211.00 484.40 978.28 11677.89
6 4th 7871.21 1133.00 1211.00 484.40 1055.19 11754.80
7 5th 7871.21 1133.00 1211.00 484.40 1132.10 11831.71

Data-Civil
D R.C.C.Side walls

1.00 Cum cost of VRCC M30 grade rate as per data Rs.
1.00 Cum centering charges as per Sl. No.315, P.No.267 of PH SOR.
at Rs.1115/0.23 Rs.
Total Rs.
Add 13.615% Contractor's Profit & Over head charges Rs.
SUNDRIES
TOTAL

Data-Civil
Filling with useful available excavated earth (excluding rock) in trenches, sides of foundati
lead in layers not exceeding 15 cm thick,consolidating each deposited layer by watering and
5
conveyance of water to work site and all operational, incidental, labour charges, hire charge
finisheditem of work. (APSS NO. 309 & 310) OUT PU

A.P.Standard Data No.BLD-CSTN-2-9 (Page No.180


A.Labour
Man Mazdoor (including area allowance) Day 3.120
B.Material
Water (including for curing) Urban KL. 0.72
(P.No.223, Item No.189.a)
Total
Add 13.615% Contractor's Profit & Over head charges Rs.
Total (for 6.00 Cum)
Rate per 1 Cum
sundries

Data-Civil
Laying PCC work of mix (1 : 5 : 10) prop. Using 40 mm gauge hard granite machine crus
6 conveyance of all materials, machine mixing, labour charges, tamping, cruing charge
foundations.
A.P.Standard Data No.24 P.No.21 (BLD-CSTN-3.7).
A. MATERIALS:
Cement MT 0.1296
Coarse aggregate 40 mm (HBG Metal) -
Cum. 0.90
( as per chart)
Fine aggregate (Sand) Cum 0.45
Water (including for curing) Urban KL. 1.2
(P.No.223, Item No.189.a)
B. MACHINERY
Concrete Mixer 10/7 cft (0.2/0.8 Cum. Capacity)
Hour 1
300/200 Diesel (Pg.No.230,Item.16)
Add. 40% on Crew charges of 206.70 Hour 1
(P.No.289, Item No.18)
C. LABOUR:
Mason 1st class (including area allowance) Day 0.10
Man Mazdoor (including area allowance) Day 1.39
Total Rs.
Add 13.615% Contractor's Profit & Over head charges Rs.
Sundries Rs.
Total

Data-Civil
Supply and placing of the Design Mix Concrete of grade M30 corresponding to IS 456 usin
Cum (6.00cum / Hr) using minimum cement content of 380 Kg. per Cum with 12mm and
crushed hard granite metal (coarse aggregate) from approved quarry including cost and con
cement, fine aggregate (sand) coarse aggregate, water etc., to site and including, sales &
7 including all operational, incidental and labour charges such as weigh batching, machine m
etc.,complete but excluding cost of steel and its fabrication charges for finished item of wo
centering shuttering using adjastable Jack Screws, Props and Acro span beams includin
couplings pre fabricated steel H-frames, cross members etc., Complete, laying concre
excluding cost of steel and its fabrication charges for finished item of work. CHAJJAS.

VRCC M30 - Rs. 8184.35


Deduct Vibration charges 313.14
Rate for PCC M30 = 7871.21
0.05 Cum Cost of M30 Grade Concreate @ Rs. Rs.
Winch charges (P.231, Sl.No.66) (1.333 x 577.00 = 769.14 38.46
Crew charges 1.333x248.00=330.58 x M.L@40%= 132.23 6.61
Plastring LiftCentering
Charges =
Charges vide Item
Rs. Charges
901.37 45.07
in C.M No.1F, P.No.66 & 68 of SSR vide
Sl.
Floor InitialRate (1:4) vide M.L P.No.131 Total
No. Material Labour
data No.13 @ 40% of
1 Cellar 393.56 for 2 Sqm.
275.76 224.00 186.00 74.40 A.P.Stand
-- 1153.72
2 G.F 393.56 275.76 224.00 186.00 74.40 -- 1153.72
3 1St 393.56 275.76 224.00 205.00 82.00 -- 1180.32
4 2nd 393.56 275.76 224.00 223.00 89.20 45.07 1250.59
5 3rd 393.56 275.76 224.00 242.00 96.80 48.92 1281.04
6 4th 393.56 275.76 224.00 260.00 104.00 52.76 1310.08
7 5th 393.56 275.76 224.00 279.00 111.60 56.61 1340.53

Data-Civil
Supply and placing of the Design Mix Concrete of M 30 corresponding to IS 456 using WEIG
cement content of 380 Kg. per Cum with 12mm and 20mm size graded machine crushed
aggregate) from approved quarry including cost and conveyance of all materials like ce
coarse aggregate, water etc., to site and including, sales & other taxes on all materials includ
8 and labour charges such as weigh batching, machine mixing, laying concrete, vibrate, curing
cost of steel and its fabrication charges for finished item of work (APSS No.402)includin
adjastable Jack Screws, Props and Acro span beams including all pipe bracings, clamps c
H-frames, cross members etc., Complete, laying concrete, vibrating, curing etc. complete bu
its fabrication charges for finished item of work. RCC SLABS, BEAMS.

A.P.Standard Data No.31 C P.No.25 (BLD-CSTN-3.16)


I .VRCC M30
A. MATERIALS:
a 20mm HBG graded metal Cum 0.53
b 12 mm HBG graded metal Cum 0.27
Sand Cum 0.40
Cement MT 0.38
Water (including for curing) KL 1.20
(P.No.223, Item No.189.a)
B. LABOUR:
Mason 1st class (including area allowance) Day 0.067
Mason 2nd class (including area allowance) Day 0.133
Man Mazdoor (including area allowance) Day 3.077
C. MACHINERY
Weigh Batcher 0.50 Cum/Hour Hire charges (Machine mixing)
of Item No.9 of P.No.229 Cum. 0.308
Add M.L 40% on CREW Charges @ 320.00 Hour 0.308
vide P.No. 229 item No 9
Needle vibrator hire charges 40mm. As per Hour 0.308
vide P.No. 230 item No 40
Add M.L 40% on CREW Charges 148.80 Hour 0.308
Sundries
Total

Data-Civil
A) For Roof Slab centering with steel scaffolding pipes, jack props, steel centering plates

Cost of M30 Grade Concreate Rs.


Centring charges Rs.389.00/1 Sq.mtr/0.15 P.No.66, I.No.1I
Centring Material charges Rs.227.00/Sqm./0.15 = Rs.1513.33/Cum
Centring Labour charges Rs.162.00/Sqm./0.15 = Rs.1080.00/Cum
Winch charges (0.267 x 577.00 = 154.05
Crew charges 0.267 x 248.00 = 66.21 x M.L @ 40% = 26.48
180.53
Charges
Centering Charges vide Item
No.1.i, P.No.66 & 68 of SSR vide
Sl. Initial
Floor M.L P.No.131 Total
No. Rate Material Labour
@ 40% of
1 Cellar 6034.70 1513.33 1080.00 432.00 A.P.Stand
-- 9060.03
2 G.F 6034.70 1513.33 1080.00 432.00 -- 9060.03
3 1St 6034.70 1513.33 1186.66 474.66 -- 9209.35
4 2nd 6034.70 1513.33 1293.33 517.33 180.53 9539.22
5 3rd 6034.70 1513.33 1406.66 562.66 195.94 9713.29
6 4th 6034.70 1513.33 1511.33 604.53 211.34 9875.23
7 5th 6034.70 1513.33 1620.00 648.00 226.75 10042.78

Data-Civil
B) For Roof Beam centering with steel scaffolding pipes, jack props, steel centering plate

Cost of M30 Grade Concreate


Centring charges Rs. 3428.00/1 Cum (Page.6, Sl.No.1H)
Centring Material charges Rs.2002.00/Cum
Centring Labour charges Rs.1426.00/Cum

Centering Charges vide Item Charges


No.1.h, P.No.66 & 68 of SSR vide
Sl. Initial
Floor M.L P.No.131 Total
No. Rate Material Labour
@ 40% of
1 Cellar 6034.70 2002.00 1426.00 570.40 A.P.Stand
-- 10033.10
2 G.F 6034.70 2002.00 1426.00 570.40 -- 10033.10
3 1St 6034.70 2002.00 1569.00 627.60 -- 10233.30
4 2nd 6034.70 2002.00 1711.00 684.40 180.53 10612.63
5 3rd 6034.70 2002.00 1854.00 741.60 195.94 10828.24
6 4th 6034.70 2002.00 1996.00 798.40 211.34 11042.44
7 5th 6034.70 2002.00 2139.00 855.60 226.75 11258.05

Data-Civil
Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm th
compound per bag of cement laid over roof when it is green including cost of all materials,, in
9
of materials and including all operational, incidental and labour charges for mixing mortar, l
thread lining, curing, rounding off junctions of wall and slab etc,, complete for finished item of

A.P.Standard Data No.148 P.No.71 (BLD-CSTN-10-25).


A) MATERIALS:
Cement Mortal 1:3 prop. 0.210 x Rs.4672.47 0.21
Water proof compound 2.00 Kg. x Rs.52.00 2.00
(P.No.25, Item No.241) (SOR-2014-15)
B) LABOUR
Mason 1st class 0.660 x Rs.385.00/Day 0.66
Mason 2nd class 1.540 x Rs.345.00/Day 1.54
Mazdoor (unskiled) 3.70 x Rs.295.00/Day 3.70
Add M.L 40% on labour charges 2038.70 40%
Total Rs.
Rate per 1 Sqm. Rs.
Lift Charges vide P.No.131 of
A.P.Standard data
10 %
Sl. Initial labour
Floor charges M.L Total
No. Rate
Rs.2038.7 Labour @ 40%
0 / 10
Sqms.
1 Cellar 394.04 - - 394.04
2 G.F 394.04 - - 394.04
3 1St 394.04 20.39 8.16 422.59
4 2nd 394.04 22.43 8.97 425.44
5 3rd 394.04 24.46 9.78 428.28
6 4th 394.04 26.50 10.60 431.14
7 5th 394.04 28.54 11.42 434.00
8 6th 394.04 30.58 12.23 436.85

Data-Civil
Providing High Yield Strength Deformed Steel bars (Fe 415 Grade as per IS : 1786 an
different diameters including labour charges for cutting bending to required size shapes, p
blocks of approved materials and size and tying firmly with M.S. Binding wire of 20 SWG fo
work as per approved designs and drawings including cost and conveyance of deformed ste
10
such as overlaps, welded joints, chairs spacer bars including cost and conveyance of bind
incidental, opeartional labour charges including sales and other taxes on all materials etc., c
work in all floors (APSS No.126) (Payment will be made on the basis of weight of fabrication
rolled steel shall be allowed) complete for (8 mm to 40 mm).

A.P.Standard Data No.36 P.No.28 (BLD-CSTN-4-2).


A) Material
HYSD bars including 5 per cent for overlaps
and wastage 1.05 MT x Rs.48,000/-/MT MT
Binding wire 6.00 Kg. x Rs. 70.00/Kg. Kg
Item No.3, P.No.201 of Irrigation
B) Labour for cutting, bending, shifting to site, tying and placing in position
Blacksmith / Bar bender 10 Nos. x Rs.450.00/Day (P.No.253) Nos
Mazdoor (Unskilled) 10.00 x Rs.295.00/Day (P.No.256). Nos
Add M.L 40% on labour charges 8100.00 X 40% Nos
Total

Lift Add
Charges 13.615%
vide towards
Sl. Initial M.L. @
Floor P.No.131 Total contractor
No. Rate 40%
of 's profit &
A.P.Stand O.H.
ard data Charges

1 Cellar 55860.0 - - 55860.00 7605.34


2 G.F 55860.0 - - 55860.00 7605.34
3 1St 55860.0 810.00 324.00 56994.00 7759.73
4 2nd 55860.0 891.00 356.40 57107.40 7775.17
5 3rd 55860.0 972.00 388.80 57220.80 7790.61
6 4th 55860.0 1053.00 421.20 57334.20 7806.05
7 5th 55860.0 1134.00 453.60 57447.60 7821.49

Data-Civil
Masonry work in CM (1:6) prop with Flyash Cement solid blocks of size 290 x 225 x 140 mm
solid blocks using flyash of 80 kgs, cement of 15 kgs.Gypsum of 5 kgs. and stone dust inclu
11
all materials, labour charges, scaffolding and curing etc., complete with a compressive stren
for walls for Superstructure Walls. For Super Structure.

A.P.Standard Data No.55 P.No.35 (BLD-CSTN-5-17).


A. MATERIALS:
No of blocks required for one cum of Masonry (As per chart) Nos. 110
110 Nos. x Rs. 24.00 / 1 No.
Cost of Cement Mortar (1:6) 0.10 Cum x Rs.3232.47Cum Cum 0.10
B. LABOUR
Mason 1st class Day 0.42
Mason 2nd class Day 0.92
Man Mazdoor Day 0.70
Woman Mazdoor Day 2.10
Add M.L 40% on labour charges 1,417.40 X 40%
Total Rs.
Scaffolding charges vide P.No.66 of SSR - Rs.71.76/1Sqm.
Scaffolding charges material Rs.9.93/1Sqm./0.225 = Rs. 44.13/Cum
Scaffolding labour charges Rs.61.83/1Sqm./0.225 = Rs.274.80/Cum
Scaffolding Charges vide Item Charges
No.1.a, P.No.66 of SSR vide
Sl. Initial
Floor M.L P.No.131 Total
No. Rate Material Labour
@ 40% of
1 Cellar 4951.14 44.13 274.80 109.92 A.P.Stand
-- 5379.99
2 G.F 4951.14 44.13 274.80 109.92 -- 5379.99
3 1St 4951.14 44.13 390.13 156.05 141.74 5683.19
4 2nd 4951.14 44.13 505.33 202.13 155.91 5858.65
5 3rd 4951.14 44.13 620.88 248.35 170.09 6034.59
6 4th 4951.14 44.13 736.00 294.40 184.26 6209.93
7 5th 4951.14 44.13 851.55 340.62 198.44 6385.88

Data-Civil
Masonry work in CM (1:4) prop with Flyash Cement solid blocks of size 230 x 100 x 140 mm
solid blocks using flyash of 80 kgs, cement of 15 kgs.Gypsum of 5 kgs. and stone dust inclu
12
all materials, labour charges,, scaffolding and curing etc., complete with a compressive stren
for walls for Superstructure Walls. For Partion walls.

A.P.Standard Data No.55A P.No.35 (BLD-CSTN-5-17).


No of blocks required for one cum of Masonry (As per chart) Nos. 245
Cost of Cement Mortar (1:4) Cum 0.10
B. LABOUR
Mason 1st class Day 0.42
Mason 2nd class Day 0.92
Man Mazdoor Day 0.70
Woman Mazdoor Day 2.10
Add M.L 40% on labour charges 1,417.40 X 40%
Total Rs.
Scaffolding charges vide P.No.66 of SSR - Rs.71.76/1Sqm.
Scaffolding charges material Rs.9.93/1Sqm./0.1 = Rs. 99.30/Cum
Scaffolding labour charges Rs.61.83/1Sqm./0.1 = Rs.618.30/Cum
Scaffolding Charges vide Item vide
Sl. Initial No.1.a, P.No.66 of SSR
Floor P.No.131 Total
No. Rate Material Labour of
1 Cellar 5076.61 99.30 618.30 -- 5794.21
2 G.F 5076.61 99.30 618.30 -- 5794.21
3 1St 5076.61 99.30 877.80 141.74 6195.45
4 2nd 5076.61 99.30 1137.00 155.91 6468.82
5 3rd 5076.61 99.30 1397.00 170.09 6743.00
6 4th 5076.61 99.30 1656.00 184.26 7016.17
7 5th 5076.61 99.30 1916.00 198.44 7290.35
8 6th 5076.61 99.30 2175.00 212.61 7563.52

Data-Civil
Plastering with CM (1:4), 12 mm thick in singlecoat with. Screened sand with sponge
13
coneyance of all meterials hacking surface, scaffolding, leads, lifts and labour charges etc., c

A.P.Standard Data No.77 P.No.42 (BLD-CSTN-8-2).

A) MATERIALS:
Cement Mortar (1:4) as per mortar chart 0.15 3972.53
B) LABOUR:
Mason 1st class Day 0.60
Man Mazdoor (including area allowance) Day 0.96
Add: M.L. 40% ( 559.20 ) Day

Rate per Sqm 137.88


Scaffolding Charges vide Item vide
Sl. Initial No.1A, P.No.67 of SSR
Floor P.No.131 Total
No. Rate Material Labour of
1 Cellar 137.88 2.37 12.55 152.80
2 Ground 137.88 2.37 17.64 157.89
3 First 137.88 2.37 22.73 5.59 168.57
4 Second 137.88 2.37 27.82 6.15 174.22
5 Third 137.88 2.37 32.91 6.71 179.87
6 Fourth 137.88 2.37 38.00 7.27 185.52
7 Fifth 137.88 2.37 43.08 7.83 191.16

Data-Civil
Providing plastering in CM(1:3), 20mm thick laid over Granolithic flooring bed when it
materials, seigniorage charges, including conveyance charges of materials and including a
14
labour charges for mixing mortar, laying, rendering smooth and thread lining, curing, round
floor etc,, complete for finished item of work FOR ORNAMENTAL PLASTERING.

A.P.Standard Data No.148 P.No.71 (BLD-CSTN-10-25). Unit = 1 sqm


MATERIALS:
Cement Mortal 1:3 prop. Cum 0.21
LABOUR
Mason 1st class Day 0.66
Mason 2nd class Day 1.54
Mazdoor (unskiled) Day 3.70
Add M.L 40% on labour charges 2038.70 X 40%
Total Rate per 10 Sqm. Rs.
Add 13.615% contractor's Profit & Over Head charges Rs.
Total Rs.
Total Rate per 1 Sqm. Rs.
sundries Rs.
Total Rate per 1 Sqm.

Data-Civil
Plastering with CM 2 coats, 12 mm thick, base coat in CM (1:5), 8mm thick and top coa
sponze finishing to suit application of Altek finish including cost and conveyance of all mat
15
and all operational incidental labour charges such as mixing mortar, lift charges, curing etc.
work as per SS No. 901, 904 for Exterior Walls.

A.P.Standard data No.85 P.No.44 (BLD-CSTN-8-10).

A) MATERIALS:
Base Coat in CM(1:5), 8 mm thick
Cement MT 0.0317
Fine aggregate (Sand) Cum 0.11
Top Coat in CM(1:3), 4 mm thick
Cement MT 0.0192
Fine aggregate (Sand) Cum 0.04
B) LABOUR:
Mason 1st class Day 0.63
Mason 2nd class Day 1.47
Mazdoor (unskiled) Day 3.9
Add M.L 40% on labour charges 2063.85 X 40% Rs.
Total Rate per 10 Sqm. Rs.
Rate per 1 Sqm. Rs.

Scaffolding Charges vide Item Charges


No.1A, P.No.108 of SSR vide
Sl. Initial
Floor M.L P.No.131 Total
No. Rate Material Labour
@ 40% of
1 Cellar 344.10 A.P.Stand
-- 344.10
2 Ground 344.10 -- 344.10
3 First 344.10 20.64 364.74
4 Second 344.10 22.70 366.80
5 Third 344.10 24.77 368.87
6 Fourth 344.10 26.83 370.93
7 Fifth 344.10 28.89 372.99

Data-Civil
Plastering with CM in 2 coats of 12 mm thick, base coat in CM (1:5) of 8mm thick, top c
with sponze finishing to suit application of Altek finish including cost and conveyance of all
16
site and all operational incidental labour charges such as mixing mortar, lift charges, curing e
of work as per SS No. 901, 904 for Interior Walls.

A.P.Standard data No.85


A) MATERIALS:
Base Coat in CM(1:5), 8 mm thick
Cement MT 0.0317
Fine aggregate (Sand) Cum 0.11
Top Coat in CM(1:3), 4 mm thick
Cement MT 0.0192
Fine aggregate (Sand) Cum 0.04
B) LABOUR:
Mason 1st class Day 0.63
Mason 2nd class Day 1.47
Mazdoor (unskiled) Day 3.90
Add M.L 40% on labour charges 2063.85 X 40% Rs.
Total Rate per 10 Sqm. Rs.
Rate per 1 Sqm. Rs.

Scaffolding Charges vide Item vide


Sl. Initial No.1A, P.No.108 of SSR
Floor P.No.131 Total
No. Rate Material Labour of
1 Cellar 344.10 0.99 6.18 -- 351.27
2 Ground 344.10 0.99 8.78 -- 353.87
3 First 344.10 0.99 11.37 20.64 377.10
4 Second 344.10 0.99 13.97 22.70 381.76
5 Third 344.10 0.99 16.56 24.77 386.42
6 Fourth 344.10 0.99 19.16 26.83 391.08
7 Fifth 344.10 0.99 21.75 28.89 395.73

Data-Civil
Plastering with CM (1:3), 20 mm thickin single coat with Screened sand with sponge
17 coneyance of all meterials hancking surface, scaffolding, leads lifts and labour charges etc., c
FLOORING.

A.P.Standard Data No.148 P.No.28 (BLD-CSTN-10-25). Unit = 1 sqm

MATERIALS:
Cement Mortal 1:3 prop. Cum 0.21
Water proof compound 2.00 Kg. x Rs.52.00 (SOR-2014-15) Kg 2
LABOUR
Mason 1st class Day 0.66
Mason 2nd class Day 1.54
Mazdoor (unskiled) Day 3.70
Add M.L 40% on labour charges 2038.70 X 40%
Total Rate per 10 Sqm. Rs.
Add 13.615% contractor's Profit & Over Head charges Rs.
Total Rs.
Total Rate per 1 Sqm. Rs.
sundries Rs.
Total Rate per 1 Sqm.

Data-Civil
Granolithic concrete flooring 20 mm thick with (1:1:2) using 6mm to 12 mm size hard gra
18 already laid or RCC Roof slab in alternate panels of size not exceeding 1.5Mt x 1.5Mt. and
required slopes including cost of all materials like cement, metal, sand and water etc., comple

A.P.Standard Data No.111 P.No.55 (BLD-CSTN-9-13). Unit 1Sqm.


A. MATERIALS:
6mm to 12 mm HBG graded metal
1036.98 + 1399.48 /2 1218.23 Cum 0.17
Sand Cum 0.085
Cement MT 0.12
B. LABOUR:
Mason 1st class Day 1.25
Mason 2nd class Day 0.06
Mazdoor (unskiled) Day 3.00
Add M.L 40% on labour charges 1507.50 X 40%

Add 13.615% contractor's Profit & Over Head charges Rs.


Total Rs.
Rate per 1 Sqm.
Water @ 1% on 359.65 Rs.
Sundries Rs.
Total

Data-Civil
Flooring with vitrified tiles of size not less than 598 mm x 598 mm, 8 to 10 mm thick g
normal colour 1st quality set over base coat of cement mortar (1:8), 12mm thick over CC b
19 slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & join
paste to full depth mixed with pigment of matching shade, Pointing with CM (1:3) includ
cement, sand water and tiles etc., complete, for finished item of work.

A.P.Standard Data No.103 P.No.51 (BLD-CSTN-9-5). Unit = 1 Sqm


A. MATERIALS:
Vitrified tiles of 1st quality of size ( 8 to 10 mm thick)
(P.No.17, S.No.52) 10.50 x Rs. 1048.00/Sqm Sqm 10.5
Cement for CM (1:8) proportion for base coat MT 0.0216
Cement for slurry 0.033
Sand for CM (1:8) 0.12
White cement for jointing & pointing (Sl.No.1154 Page No.64). Kg 2
LABOUR
Mason 1st class Day 0.96
Mason 2nd class Day 2.24
Mazdoor (unskiled) Day 3.30
Add M.L 40% on labour charges 2299.20 X 40%
Total Rs.
add: for water @ 1% on 14803.68
Total Rate per 10 Sqm. Rs.
Rate per 1 Sqm. Rs.

Lift Charges vide


P.No.131 of Add
A.P.Standard data 13.615%
10 % towards
Sl. Initial
Floor labour TOTAL contractor Total
No. Rate
charges M.L 's profit &
Rs.2299.2 @ 40% O.H.
0 for Charges
10Sqm.
1 Cellar -- -- --
2 G.F. 1495.17 -- -- 1495.17 203.57 1698.74
3 1 st 1495.17 22.99 9.20 1527.36 207.95 1735.31
4 2 nd 1495.17 25.29 10.12 1530.58 208.39 1738.97
5 3 rd 1495.17 27.59 11.04 1533.80 208.83 1742.62
6 4 th 1495.17 29.89 11.96 1537.02 209.26 1746.28
7 5 th 1495.17 32.19 12.88 1540.23 209.70 1749.94

Data-Civil
Providing skirting to internal walls to 15 cm height/risers of steps with vitrified tiles length
over base coat of CM (1:5) 12 mm thick with cement slurry of honey like consistency sprea
20
sqm and jointed with white cement paste mixed with pigment of matching shade to full
materials like tiles, cement, sand and water etc., complete for finished item of work.

A.P.Standard Data No.118 P.No.58 (BLD-CSTN-9-20). Unit = 1 Sqm


A. MATERIALS:
Vitrified tiles of 1st quality of size ( 8 to 10 mm thick)
(P.No.17, S.No.52) Sqm 10.5
Cement for CM (1:8) proportion for base coat MT 0.03456
Cement for slurry 0.033
Sand for CM (1:8) 0.12
White cement for jointing & pointing (Sl.No.1154 Page No.64). Kg 2.00
LABOUR
Mason 1st class Day 0.96
Mason 2nd class Day 2.24
Mazdoor (unskiled) Day 3.30
Add M.L 40% on labour charges 2299.20 X 40%
Total Rs.
add: for water @ 1% on 14879.79
Total Rate per 10 Sqm. Rs.
Rate per 1 Sqm. Rs.

Lift Charges vide


P.No.131 of Add
A.P.Standard data 13.615%
10 % towards
Sl. Initial
Floor labour TOTAL contractor Total
No. Rate
charges M.L 's profit &
Rs.2299.2 @ 40% O.H.
0 for Charges
10Sqm.
1 Cellar -- -- --
2 G.F. 1502.86 -- -- 1502.86 204.61 1707.47
3 1 st 1502.86 22.99 9.20 1535.05 209.00 1744.05
4 2 nd 1502.86 25.29 10.12 1538.27 209.44 1747.70
5 3 rd 1502.86 27.59 11.04 1541.49 209.87 1751.36
6 4 th 1502.86 29.89 11.96 1544.71 210.31 1755.02
7 5 th 1502.86 32.19 12.88 1547.92 210.75 1758.67

Data-Civil
Flooring with ceramic tiles of 7.3mm thick of 1st quality of all shades set over base coa
mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of hone
21
3.3.kgs per sqm & jointed neatly with white cement paste to full depth mixed with pigment
cost of all materials like cement, sand water and tiles etc., complete, for finished item of work

A.P.Standard Data No.104 P.No.51 & 52.


A. MATERIALS:
Ceramic tiles of 1st quality of size ( 7.30mm thick)
(P.No.16, S.No.38) (SOR-2014-15) Sqm 10.5
Cement for CM (1:8) proportion for base coat MT 0.0216
Cement for slurry 0.033
Sand for CM (1:8) 0.12
White cement for jointing & pointing (Sl.No.1154 Page No.64). Kg 2.00
LABOUR
Mason 1st class Day 0.96
Mason 2nd class Day 2.24
Mazdoor (unskiled) Day 3.30
Add M.L 40% on labour charges 2299.20 X 40%
Total Rs.
add: for water @ 1% on 8682.18
Total Rate per 10 Sqm. Rs.
Rate per 1 Sqm. Rs.

Lift Charges vide


P.No.131 of Add
A.P.Standard data 13.615%
10 % towards
Sl. Initial
Floor labour TOTAL contractor Total
No. Rate
charges M.L 's profit &
Rs.2299.2 @ 40% O.H.
0 for Charges
10Sqm.
1 Cellar -- -- --
2 G.F. 876.90 -- -- 876.90 119.39 996.29
3 1 st 876.90 22.99 9.20 909.09 123.77 1032.86
4 2 nd 876.90 25.29 10.12 912.31 124.21 1036.52
5 3 rd 876.90 27.59 11.04 915.53 124.65 1040.18
6 4 th 876.90 29.89 11.96 918.75 125.09 1043.83
7 5 th 876.90 32.19 12.88 921.96 125.53 1047.49

Data-Civil
Dadoing walls with 1st quality of glazed plain coloured tiles of 5 to 7 mm thick of any size ce
and neat cement slurry of honey like consistency at the rate of 3.30 Kgs. cement per S
22 matching shade of tiles including charges, curing etc., complete as directed by the dep
inclusive of all taxes for
BATH ROOMS.
A.P.Standard Data No.116, Page No.57.
A. MATERIALS:
Ceramic Glazed tiles of 1st quality of size (5 to 7mm thick)
(P.No.17, S.No.44) (SOR-2014-15) Sqm 10.5
Cement for CM (1:8) proportion for base coat MT 0.0576
Cement for slurry 0.033
Sand for CM (1:8) 0.12
White cement for jointing & pointing (Sl.No.1154 Page No.64). Kg 6.00
LABOUR
Mason 1st class Day 0.77
Mazdoor (unskiled) Day 0.80
Add M.L 40% on labour charges 579.40 X 40%
Total Rs.
add: for water @ 1% on 6055.89
Total Rate per 10 Sqm. Rs.
Rate per 1 Sqm. Rs.

Lift Charges vide


P.No.131 of Add
A.P.Standard data 13.615%
towards
Sl. Initial 10 %
Floor TOTAL contractor Total
No. Rate labour
M.L 's profit &
charges O.H.
@ 40%
Rs.579.40 Charges
for 10Sqm.

1 Cellar 611.64 -- -- 611.64 83.27 694.91


2 G.F. 611.64 -- -- 611.64 83.27 694.91
3 1 st 611.64 5.79 2.32 619.75 84.38 704.13
4 2 nd 611.64 6.37 2.55 620.56 84.49 705.05
5 3 rd 611.64 6.95 2.78 621.37 84.60 705.97
6 4 th 611.64 7.53 3.01 622.19 84.71 706.90
7 5 th 611.64 8.11 3.24 623.00 84.82 707.82

Data-Civil
Supply and fixing of High strength cement concrete designer tiles of 30mm thicknes of M40
shall be for color pigmentation with imported colour and white cement to get required refle
taxes. and over a bse coat of C.M.(1:8) Prop. 20 mm thick including neat cement slurry of h
23
at the rate of 3.30 Kg. per Sq,/ and filling the joints with white cement at 2.00 Kg. per S
matching shade including cost and conveyance of all materials, labour charges, laying of til
by the Department for Stair case and Portco.

A.P.Standard Data No.104. P.No.51 (BLD-CSTN-9-6). Unit = 1 sqm


A. MATERIALS:
High strength Cement Concrete tiles
(P.No.19, S.No.98) (SOR-2014-15) Sqm 10.5
Cement for CM (1:8) proportion for base coat MT 0.0216
Cement for slurry 0.033
Sand for CM (1:8) 0.12
White cement for jointing & pointing (Sl.No.1154 Page No.64). Kg 2.00
LABOUR
Mason 1st class Day 0.96
Mason 2nd class Day 2.24
Mazdoor (unskiled) Day 3.30
Add M.L 40% on labour charges 2299.20 X 40%
Total Rs.
add: for water @ 1% on 9238.68
Total Rate per 10 Sqm. Rs.
Rate per 1 Sqm. Rs.

Lift Charges vide


P.No.131 of Add
A.P.Standard data 13.615%
towards
Sl. Initial 10 %
Floor TOTAL contractor Total
No. Rate labour 's profit &
charges M.L
O.H.
Rs.2299.2 @ 40%
Charges
0 for
10Sqm.
1 Cellar 933.11 -- -- 933.11 127.04 1060.15
2 G.F. 933.11 -- -- 933.11 127.04 1060.15
3 1 st 933.11 22.99 9.20 965.30 131.43 1096.72
4 2 nd 933.11 25.29 10.12 968.52 131.86 1100.38
5 3 rd 933.11 27.59 11.04 971.74 132.30 1104.04
6 4 th 933.11 29.89 11.96 974.96 132.74 1107.70
7 5 th 933.11 32.19 12.88 978.17 133.18 1111.35

Data-Civil
Providing and fixing door frame fabricated from section made of galvanized steel powder c
513,galvanized as per IS 217 with zinc of 120 grams/square meter). The factory made sect
coating of pure polyester powder of 50-60 microns thick with total coated thickness of 1
section should be of 105 x 60 mm with a rebate of 38mm to accommodate 30 mm thick door
24 gasket in the frame section, frame section to be filled with polyurethane foam. the frame se
and joined by way be way of welding. Each frame should be provided with : 2mm thick MS
100 mm long -3 Nos. for single shutter, 6Nos. double shutter. CRCA Electroplates stiffeners
for double shrtter and 40mm x 200 mm x 1.2 mm hold fasts screwed to stiffeners - 6Nos. wi
Receiver -1No. for single shutter frame. Tie Rod 1 No. DOOR FRAME FOR WITH OUT SILL

Unit- Each
Door size 0.91 x 2.13 m with out sill

Cost of door frame ., Page No.39, Rmt 5.17


item No.814 per frame horizental lengths 1 x 0.91 = 0.91
Verticial lenghts 2 x 2.13 = 4.26
Total lenghts 5.17 RM
Total Rs.
Add 13.615% contractor's Profit & Over Head charges Rs.
Sundries Rs.
Total Rs.

Data-Civil
Supplying and fixing of PVC Door frames made from extruded sections in over all dimention
thickness of 1.55 mm. wiht usual porcess veriation of +/- 0.3mm complete and Sintex door
Hot Press Moulded SMC (Sheet moulding coumpound sheets, Polyurethene core and PVC
shall be made from SMC comforming to IS 13410 sheet shall have an average thickness o
sides. Core of the door shutter shall be filled with high density polyurethane foam , injecte
injection method shutter frame to be made of PVC extruded section confirming to IS:10151 :1
25 with a wall thickness of 1.4 mm +0.3mm on both sides corresponding to sintex code DWUF
shall be reinforced with special polymeric reinforcement wooden blocks of suitable size. The
shall be reinforced with Polymeric 'L' shaped angle of size 105 mm x 230 mm correspondi
lock rail shall be made from PVC extruded sections having overall dimensions of 26 mm x
both sides, with usual process variation corresponding to Sintex code 305 combining two n
inserted on the periphery. Suitable MS Tube reinforcement shall be provided on vertical sid
inclusive of all taxes and finished item work Color: White & Grey. SINTEX ENDURA DOOR S

Unit - Each
Cost of door frame vide P.No.51, Item No.717
@ Rs.244/Rmt.
For each door frame 0.76 + 1.98 +1.98 Rmt
4.72Rmt. (SOR-2014-15)
Door Shutter Size 0.76 x 2.13 = 1.6188 Sqm
cost of Shutter with frame (SOR-2014-15) Sqm
(As per item No.723 page No.52)
Cost of fixtures
1 No. 264 mm. long Aluminim Aldrop (IS2681 20mm long) Nos
(item No.262 page No. 12)
1 No. Cost of tower bolt (P.No.11 Item No.231) Nos
10 mm. bolt (IS204) 200 mm long.
2 Nos. 125 mm. long Alluminum Door handle (IS208) Nos
( As per P.No.12, Item No.255 )
3 Nos. But hinges (As per P.No.12, Item No.246) Nos
(IS 205)100 mm long.
Total
Add 13.615% contractor's Profit & Over Head charges
Sundries
Total

Data-Civil
Supply and fixing of Flush door single leaf flushdoor shutter of solid bond wood black board
to IS2202 commercial ply on both faces including cost of fixtures of M.S.Powder coated 1 No
26 of 200 mm long aldrop, 1 No. of 200 mm tower blot, 1 No. 125 mm long handle including
materials and labour charges etc., complete as per drawing and as directed by the departme
X 2.13 Mts.

Size Shutter 0.85 x 2.10 = 1.785 Sqm


cost of flush door shutter @ Rs.1034.00/1Sqm
(As per item No.805, Page No.34) Sqm

Cost of fixtures
1No.250mm long 10mm dia MS powder coated Aldrop Nos
(item No.266 page NO.12)
1 No 200 mm long 12 mm dia MS powder coat Aldrop Nos
(item No.265 page No.12)
1 No 200 mm long 10 mm dia tower bolt powder coated Nos
( item No.238, page No.12)
1 No. 125 mm long MS. Power coated handle Nos
(item No.257 page NO.12)
Labour charges
1.785 Sqm labour charges Sqm
SSR item No.1058 page 59
Add: M.L. 40% on labour charges
Total
Add 13.615% contractor's Profit & Over Head charges
Sundries
Total

Data-Civil
Providing and fixing ofdouble Openable / Casement Windows with fly proof mesh made of
as per IS 513 of 0.80 mm. thick galvanized as per IS-277 with Zinc of 120 GSM), finish pain
60-65 microns thick and section for outer frame fo 100 x 45 mm., centre mullion of 100x60 m
25 mm x 0.6 mm thick, section for fly-shutter of 52 x 25 m x 0.6 mm thick and fitted with stain
of 304 grade with 144 holes per Sq.inch and mullions to have double rebate for glazed s
provision for guard bars/grills and the sections cut to length metre joined with corner brack
27
mullion cap, 1 No.of High grade nylon latch handle, window stopper, 2 Nos. of with MS pow
butt Hinges provided per shutter and windows fitted with 4 mm thick plain float glass with ru
the frames in concrete/ masonry wall by means of self expanding screws, including 10 mm
(152.4mm) pitch etc., complete for finished item of work. Windows of size 5'-0"x4'-0" (15
section of size 80x45mm, shutterframe section size of 52x25mm, vertical mullion section
section size of 9x12mm to be provided for glass holding.

Size of window 1.52mx1.37m


Arear of the window 1.52X1.37 m =2.08 Sq.mtr.
2.08 Sq.mtr. cost of double shutter window Sqm
vide P.No.55 item No.974
Add 13.615% contractor's Profit & Over Head charges
Total
add sundries

Data-Civil
Providing and fixing of top hung Ventilators made of pre-painted steel (Base steel as
galvanized as per IS 277 with Zinc of 120 GSM), finish painted with a polyester paint of 60-
for outer frame of 80 x 45mm, centre mullion of 80 x 60mm, section for shutter of 52 x 25mm
and mullions to have rebate for glazed shutter with a provision for guard bars/ grills and the
joined with corner bracket, centre mullion fixed with mullion cap, 1No. of High grade nylon lat
28
Nos. of with MS powder coated / SS ball bearing but hinges provided per shutter and window
float glass with rubber gaskets including fixing the frames in concrete / masonry wall by mea
including 10mm square guard bars with 6" (152.4mm) pitch etc., complete for finished item
ventilator size of 2'-0" x 2'-0" (609.6 x 609.6 mm) outer frame box section size of 80 x 45mm
6" . Outer frame section size 72 x 0mm shutter frame section size of 47 x 20mm 0.91 x 0.46

For Fixed glaged Ventilator window size .091 x 0.46 mtr.


Area of Ventilator window 0.91 x 0.46 = 0.42 x 4177.00/1Sq.mtr. Sqm
vide P.No.55 item No.979
Add 13.615% contractor's Profit & Over Head charges
Sundries
Total

Data-Civil
Supply and fixing of rolling shutter made of 80 x 1.25 mm. machine rolled CRCA laths, inter
entire length and jointed together at the ends by end locks, mounted on specially design
nominal bore MS. B class pipe wiht brackets, plates, guide channels, stoppers, bottom lock
29
for inside & outside locking with push-pull operations inlcuding cost of hood cover and spring
coat of approved steel primer, locks, ball bearings, all accessories etc., complete for finished
spn : 1108.

Cost of rolling shutter Rs.2861.00/- per 1 Sq.Mt. Sqm


(vide Page no.11 Item No.218)
Add 13.615% contractor's Profit & Over Head charges
Sundries
Total

Data-Civil
PAINTING to new WOOD work / Iron work in two coats with synthetic enamel paint of appr
30 primary coat including cost and conveyance of all materials, incidental charges such as sand
cost of brushes and putty etc., complete. (Three coats).

A.P.Standard data No.173 &195


Primary coat
MATERIALS
Wood Primer Item No.482, P.No.20 Lit
LABOUR
Painters Nos
Add. M.L 40% on labour
Add. Sundries for Brushes, Soap, Putty @ 1.00% on 367.50
Paint
MATERIALS
Two coats synthatic enamil vide P.No.32, Item No.399 Lit
1.2 Lts. X Rs.253.00/Ltr.
LABOUR
Painters 1.20 Nos. @ Rs:345/Each(p.no.21,slno.507) Lit
Add M.L 40% on labour
Total
Add 13.615% contractor's Profit & Over Head charges
Total
Rate per 1 Sqm
sundries

Data-Civil
Providing and applying of wall putty of white cement or polymer or cement based of avera
plastered surface to prepare the surface even and smooth after throughly brushing the su
remains of loose powdered materials, applying emery paper ,sand the surface ,clean & w
31
knifing paste filler putty knife/muslin pad ,air dry for 2-3 hrs sand with 180 and 320no,e
preparation including cost and conveyance of all matrials to work site and all operational
complete for finished item of work for internal walls.

A.P.Standard Data No.18.


A. MATERIALS:

Putty (Pno 21 item no 517)


for 875.00 / 20 Kgs (Rs.43.75/ Kg.) Kg 23.00
B. LABOUR
Painter 1 St class Nos 0.273
Painter 2 nd class Nos 0.637
Mazdoor Nos 0.91
Add M.L 40% on labour charges 661.12 X 40%
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Total
Rate per 1 Sqm
Sundries

Data-Civil
Painting to new walls with 2 coats of water proof cement paint interior grade-I of approved b
coat of approved cement primer grade I making 3 coats in all to give an even shade after th
32
to remove all dirt and remains of loose ppowdered materials to work site and all operationa
etc., complete for finished item of work as per SS 912 for internal walls.

A.P.Standared data no.172 p.no.81

Cost of cement primer 1 Kg. (Item No.478, P.No.20) Kg 1.00


1st Class painter day 0.21
2nd Class painter day 0.49
Add M.L 40% on labour 284.55 X 40%
Cost of Altek / PMCC or equivalent top coat high UV Resistant
Kg 3.50
exterior paint vide
Item No.520, P.No.29 (Rate 1300/25 = 52.00/-) Kg
1st Class painter day 0.15
2nd Class painter day 0.35
Mazdoor (unskilled) day 1.50
Add M.L 40% on labour 683.25 X 40%
Total
Add 13.615% contractor's Profit & Over Head charges
Total
Rate per 1 Sqm
Sundries

Data-Civil
Painting to new walls with 2 coats of water based cement primer of exteriorgrade -II paint o
over a base coat of approved cement primer grade-2 making 3 coats in all to give an even sh
33
the surface to remove all dirt and remains of loose ppowdered materials to work site and all o
charges etc., complete for finished item of work as per SS 912 for exterior walls.

A.P.Standared data no.172 p.no.81

Cost of cement primer Grade -II, 1 Kg. (Item No.479, P.No.20) kg 1


1st Class painter day 0.21
2nd Class painter day 0.49
Add M.L 40% on labour 284.55 X 40%
Cost of Altek / PMCC/ Deco orient base or equivalentexterior
kg 3.50
texture
Item No.519, P.No.21 (Rate 1000/25 = 40.00/-) Kg
1st Class painter day 0.15
2nd Class painte day 0.35
Mazdoor (unskilled day 1.50
Add M.L 40% on labour 683.25 X 40%
Total
Add 13.615% contractor's Profit & Over Head charges
Total
Rate per 1 Sqm

Data-Civil
Supply and fixing 110 mm dia 4.00 Kg./Sq.Cm. pressure P.V.C.Pipe of Prince / Sudhakar ma
34 level including plain bend clips and shoe as per ISI. Standard fixed to wall with pipe clips in
complete for RAIN WATER PIPE.

17 mtr Cost of PVC 110 MM dia. Pipe


(Item No.347, P.No.81) (484/3 = 161.33) Rmt 1.00
1No. Clips vide p.no.83,item no.440 (18.00/2) No. 1.00
1 Rmt. Labour charges P.No.83, Sl.No.486 Rmt 1
Total
Add 13.615% contractor's Profit & Over Head charges
Total

Data-Civil
CIVIL DATAS
er Common SSR 2015-16
of Commercial Complex (Cellar+Ground+4Floors) at
am in the place of existing A & B Staff quarters.

depositing on bank for all lifts and with an initial lead of 10m including all
as shoring incidental, sheeting, planking, strutting, etc. complete for finished
means upto 3.00mt depth excluding dewatering charges etc. as per SS- 20 B

(taking output : 10 Cum)

320.00 1164.80

873.60
2038.40
277.53
2315.93
231.59
0.01
231.60

(taking output : 10 Cum)


320.00 1164.80
158.59
1323.39
132.34
0.01
132.35

Data-Civil
depositing on bank for all lifts and with an initial lead of 10m including all
as shoring incidental, sheeting, planking, strutting, etc. complete for finished
al means upto 3.00mt depth excluding dewatering charges etc. as per SS- 20

(taking output : 240 Cum)

448.00 3727.36

2791.00 16746.00
20473.36
2787.45
23260.81
96.92
0.03
96.95

Data-Civil
Using 40 mm gauge hard granite machine crushed metal including cost and
, labour charges, tamping, curing, taxes etc., complete for foundations.

Unit = 1 cum

5873.00 951.43

1146.98 1032.28

1617.43 727.84
103.00 123.60

338.60 338.60

82.68 82.68

588.00 58.80
448.00 622.72
3937.95
536.15
0.00
4474.10

Data-Civil
crete of grade M30 corresponding to IS 456 using WEIGH BATCHER using
um with 12mm and 20mm size graded machine crushed hard granite metal
including cost and conveyance of all materials like cement, fine aggregate
e and including, sales & other taxes on all materials including all operational,
gh batching, machine mixing, laying concrete, Vibrating, curing etc.,complete
ation charges for finished item of work (APSS No.402 including centering
rops and Acro span beams including all pipe bracings, clamps couplings pre
etc., Complete, laying concrete, vibrating, curing etc. complete but excluding
nished item of work. FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth).

Unit = 1 cum

1666.98 883.50
1399.48 377.86
1617.43 646.97
5873.00 2231.74
103.00 123.60

588.00 78.20
525.00 140.18
448.00 2060.80

556.80 742.21
128.00 170.62

175.40 233.81

59.52 79.34
0.01
Rs. 7768.85

Data-Civil
7768.85 7768.85
750.00 750.00

189.20 189.20
8708.05
1185.60

Rs. 9893.65

Data-Civil
7768.85 7768.85
1068.00 1068.00

301.20 301.20
9138.05
1244.15

Rs. 10382.20

Data-Civil
7768.85 7768.85
2476.00 2476.00

456.40 456.40
10701.25
1456.98
0.03
Rs. 12158.26

Data-Civil
crete of grade M30 corresponding to IS 456 using WEIGH BATCHER using
um with 12mm and 20mm size graded machine crushed hard granite metal
including cost and conveyance of all materials like cement, fine aggregate
and including, sales & other taxes on all materials including all operational,
gh batching, machine mixing, laying concrete, vibrating, curing etc.,complete
ation charges for finished item of work (APSS No.402) including centering
rops and Acro span beams including all pipe bracings, clamps couplings pre
etc., Complete, laying concrete, vibrating, curing etc. complete but excluding
inished item of work. COLUMNS, LINTELS, WATER TANKS, RCC, WALLS IN

Unit 1 Cum

1666.98 883.50
1399.48 377.86
1617.43 646.97
5873.00 2231.74
103.00 123.60

588.00 98.20
525.00 87.68
448.00 2508.80

556.80 742.21
128.00 170.62

175.40 233.81

59.52 79.34
0.02
Rs. 8184.35

Data-Civil
7871.21

13.615%
towards
contractor' Sundires Amount
s profit &
O.H.
1456.75 0.04 12156.40
1456.75 0.04 12156.40
1479.82 0.03 12348.86
1625.60 0.02 13565.40
1659.14 0.03 13845.26
1692.67 0.03 14125.10
1726.40 0.04 14406.55

Data-Civil
ffolding pipes, jack props, steel centering plates etc.,.

8184.35

13.615%
towards
contractor' Sundires Amount
s profit &
O.H.
1484.76 0.04 12390.15
1484.76 0.04 12390.15
1517.17 0.03 12660.55
1672.29 0.04 13955.05
1715.17 0.00 14312.80
1758.04 0.02 14670.60
1800.92 0.03 15028.40

Data-Civil
lding pipes, jack props, steel centering plates etc.,.

7871.21

13.615%
towards
contractor' Sundires Amount
s profit &
O.H.
1456.75 0.04 12156.40
1456.75 0.04 12156.40
1456.75 0.04 12156.40
1579.47 0.00 13180.45
1589.94 0.02 13267.85
1600.42 0.04 13355.26
1610.89 0.00 13442.60

Data-Civil
8184.35

4847.83
13032.18
1774.33

Rs. 14806.51

Data-Civil
rth (excluding rock) in trenches, sides of foundations and basement with initial
nsolidating each deposited layer by watering and ramming including cost and
erational, incidental, labour charges, hire charges of T & P etc., complete for
) OUT PUT : 6 CUM.

Unit = 1 cum

448.00 1397.76

103.00 74.16

1471.92
200.40
Rs. 1672.32
Rs. 278.72
0.03
Rs. 278.75

Data-Civil
. Using 40 mm gauge hard granite machine crushed metal including cost and
xing, labour charges, tamping, cruing charges, taxes etc., complete for
Unit - 1 Cum

5873.00 761.14
1146.98 1032.28
1617.43 727.84
103.00 123.60

338.60 338.60
82.68 82.68

588.00 58.80
448.00 622.72
3747.67
510.24
0.04
Rs. 4257.95

Data-Civil
crete of grade M30 corresponding to IS 456 using WEIGH BATCHER of 0.50
nt content of 380 Kg. per Cum with 12mm and 20mm size graded machine
ate) from approved quarry including cost and conveyance of all materials like
egate, water etc., to site and including, sales & other taxes on all materials
our charges such as weigh batching, machine mixing, laying concrete, curing
nd its fabrication charges for finished item of work (APSS No.402) including
Screws, Props and Acro span beams including all pipe bracings, clamps
cross members etc., Complete, laying concrete, curing etc. complete but
arges for finished item of work. CHAJJAS.

Unit -1 Sqm.

393.56

13.615%
towards
contractor' Sundires Amount
s profit &
O.H.
157.08 0.00 1310.80
157.08 0.00 1310.80
160.70 0.03 1341.05
170.27 0.04 1420.90
174.41 0.00 1455.45
178.37 0.00 1488.45
182.51 0.01 1523.05

Data-Civil
ete of M 30 corresponding to IS 456 using WEIGH BATCHER using minimum
12mm and 20mm size graded machine crushed hard granite metal (coarse
g cost and conveyance of all materials like cement, fine aggregate (sand)
luding, sales & other taxes on all materials including all operational, incidental
, machine mixing, laying concrete, vibrate, curing etc.,complete but excluding
or finished item of work (APSS No.402)including centering shuttering using
pan beams including all pipe bracings, clamps couplings pre fabricated steel
aying concrete, vibrating, curing etc. complete but excluding cost of steel and
ork. RCC SLABS, BEAMS.

Unit 1 Cum

1666.98 883.50
1399.48 377.86
1617.43 646.97
5873.00 2231.74
103.00 123.60

588.00 39.40
525.00 69.83
448.00 1378.50

556.80 171.49
128.00 39.42

175.40 54.02

59.52 18.33
0.04
Rs. 6034.70

Data-Civil
olding pipes, jack props, steel centering plates etc.,.

6034.70

13.615%
towards
contractor' Sundires Amount
s profit &
O.H.
1233.52 0.00 10293.55
1233.52 0.00 10293.55
1253.85 0.04 10463.24
1298.76 0.02 10838.00
1322.46 0.00 11035.75
1344.51 0.01 11219.75
1367.32 0.00 11410.10

Data-Civil
olding pipes, jack props, steel centering plates etc.,.

Rs. 6034.70

13.615%
towards
contractor' Sundires Amount
s profit &
O.H.
1366.01 0.04 11399.15
1366.01 0.04 11399.15
1393.26 0.04 11626.60
1444.91 0.01 12057.55
1474.26 0.00 12302.50
1503.43 0.03 12545.90
1532.78 0.02 12790.85

Data-Civil
RCC roof slab surface with CM(1:3), 20mm thick with 1kg of water proof
when it is green including cost of all materials,, including conveyance charges
ncidental and labour charges for mixing mortar, laying, rendering smooth and
of wall and slab etc,, complete for finished item of work.

Unit = 1 Sqm

4677.29 982.23
52.00 104.00

420.00 277.20
375.00 577.50
320.00 1184.00
815.48
3940.41
394.04
Add
13.615%
towards
Sund -
contractor' Amount
ries
s profit &
O.H.
Charges
53.65 0.01 447.70
53.65 0.01 447.70
57.54 0.03 480.15
57.92 0.03 483.40
58.31 0.01 486.60
58.70 0.01 489.85
59.09 0.02 493.10
59.48 0.02 496.35

Data-Civil
Steel bars (Fe 415 Grade as per IS : 1786 and as amended upto date) of
s for cutting bending to required size shapes, placing in position with cover
tying firmly with M.S. Binding wire of 20 SWG forming grills for reinforcement
s including cost and conveyance of deformed steel bars, including all wastage
cer bars including cost and conveyance of binding wire cover blocks and all
ding sales and other taxes on all materials etc., complete for finished item of
will be made on the basis of weight of fabrication deformed bars only) (No re-
8 mm to 40 mm).

Unit -1MT

1.050 42000.00 44100.00


6.000 70.00 420.00

10.00 490.00 4900.00


10.00 320.00 3200.00
Rs. 3240.00
Rs. 55860.00

Sundries Amount

0.01 63465.35
0.01 63465.35
0.02 64753.75
0.03 64882.60
0.04 65011.45
0.00 65140.25
0.01 65269.10

Data-Civil
Cement solid blocks of size 290 x 225 x 140 mm for manufacturing of flyash
of 15 kgs.Gypsum of 5 kgs. and stone dust including cost and conveyance of
d curing etc., complete with a compressive strength not lessthan 50 kg/sqcm
r Structure.

Unit = 1 cum

24.00 2,640.00
-
3267.77 326.78
-
420.00 176.40
375.00 345.00
320.00 224.00
320.00 672.00
566.96
4,951.14

13.615%
towards
contractor' Sundires Amount
s profit &
O.H.
732.49 0.02 6112.50
732.49 0.02 6112.50
773.77 0.04 6457.00
797.65 0.00 6656.30
821.61 0.00 6856.20
845.48 0.04 7055.45
869.44 0.04 7255.35

Data-Civil
Cement solid blocks of size 230 x 100 x 140 mm for manufacturing of flyash
of 15 kgs.Gypsum of 5 kgs. and stone dust including cost and conveyance of
nd curing etc., complete with a compressive strength not lessthan 50 kg/sqcm
on walls.

Unit = 1 cum
11.00 2,695.00
3972.53 397.25
-
420.00 176.40
375.00 345.00
320.00 224.00
320.00 672.00
566.96
5,076.61

towards
contractor' Sundires Amount
s profit &
788.88 0.01 6583.10
788.88 0.01 6583.10
843.51 0.04 7039.00
880.73 0.00 7349.55
918.06 0.04 7661.10
955.25 0.03 7971.45
992.58 0.02 8282.95
1029.77 0.01 8593.30

Data-Civil
singlecoat with. Screened sand with sponge finishing including cost and
scaffolding, leads, lifts and labour charges etc., complete for CEILING.

Rs. 595.88

420.00 252.00
320.00 307.20
223.68
Rs. 1378.76

towards
contractor' Sundires Amount
s profit &
20.80 0.00 173.60
21.50 0.01 179.40
22.95 0.03 191.55
23.72 0.01 197.95
24.49 0.04 204.40
25.26 0.02 210.80
26.03 0.01 217.20

Data-Civil
thick laid over Granolithic flooring bed when it is green including cost of all
onveyance charges of materials and including all operational, incidental and
endering smooth and thread lining, curing, rounding off junctions of wall and
FOR ORNAMENTAL PLASTERING.

Unit = 1 sqm

4677.29 982.23

420.00 277.20
375.00 577.50
320.00 1184.00
815.48
3836.41
522.33
4358.74
435.87
0.03
Rs. 435.90

Data-Civil
base coat in CM (1:5), 8mm thick and top coat in CM (1:3), 4mm thick with
finish including cost and conveyance of all materials and water to work site
s such as mixing mortar, lift charges, curing etc.complete for finished item of
Walls.

Unit -1Sqm.

5873.00 186.17
1684.43 185.29

5873.00 112.76
1684.43 67.38

420.00 264.60
375.00 551.25
320.00 1248.00
825.54
3440.99
344.10
13.615%
towards
contractor' Sundires Amount
s profit &
O.H.
46.85 0.00 390.95
46.85 0.00 390.95
49.66 0.02 414.42
49.94 0.02 416.76
50.22 0.02 419.11
50.50 0.02 421.45
50.78 0.02 423.80

Data-Civil
hick, base coat in CM (1:5) of 8mm thick, top coat in CM (1:3) of 4mm thick
Altek finish including cost and conveyance of all material and water to work
arges such as mixing mortar, lift charges, curing etc.complete for finished item
Walls.

Unit = 1 Sqm

5873.00 186.17
1684.43 185.29

5873.00 112.76
1684.43 67.38

420.00 264.60
375.00 551.25
320.00 1248.00
825.54
3440.99
344.10

towards
contractor' Sundires Amount
s profit &
47.83 0.00 399.10
48.18 0.00 402.05
51.34 0.01 428.45
51.98 0.01 433.75
52.61 0.02 439.05
53.25 0.02 444.35
53.88 0.04 449.65

Data-Civil
single coat with Screened sand with sponge finishing including cost and
, scaffolding, leads lifts and labour charges etc., complete PLASTERING FOR

Unit = 1 sqm

4677.29 982.23
52.00 104.00

420.00 277.20
375.00 577.50
320.00 1184.00
815.48
3940.41
536.49
4476.90
447.69
0.01
Rs. 447.70

Data-Civil
with (1:1:2) using 6mm to 12 mm size hard granite metal laid over CC bed
panels of size not exceeding 1.5Mt x 1.5Mt. and finishing the top surface to
s like cement, metal, sand and water etc., complete for finished item of work.

1218.23 207.10
1684.43 143.18
5873.00 704.76

420.00 525.00
375.00 22.50
320.00 960.00
603.00
3165.54
430.99
3596.52
359.65
3.60

Rs. 363.25

Data-Civil
ss than 598 mm x 598 mm, 8 to 10 mm thick glossy finish premium colour
at of cement mortar (1:8), 12mm thick over CC bed already laid or RCC roof
like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement
matching shade, Pointing with CM (1:3) including cost of all materials like
for finished item of work.

Unit = 1 Sqm

1048.00 11004.00
5873.00 126.86
5873.00 193.81
1684.43 202.13
29.00 58.00

420.00 403.20
375.00 840.00
320.00 1056.00
919.68
14803.68
148.04
14951.71
1495.17

Sund -
Amount
ries

--
0.01 1698.75
0.04 1735.35
0.03 1739.00
0.03 1742.65
0.02 1746.30
0.01 1749.95

Data-Civil
m height/risers of steps with vitrified tiles length equal to flooring stones, set
th cement slurry of honey like consistency spread at the rate of 3.30 kgs per
mixed with pigment of matching shade to full depth, including cost of all
etc., complete for finished item of work.

Unit = 1 Sqm

1048.00 11004.00
5873.00 202.97
5873.00 193.81
1684.43 202.13
29.00 58.00
0.00
420.00 403.20
375.00 840.00
320.00 1056.00
919.68
14879.79
148.80
15028.59
1502.86

Sund -
Amount
ries

--
0.03 1707.50
0.01 1744.06
0.00 1747.70
0.04 1751.40
0.03 1755.05
0.03 1758.70

Data-Civil
ck of 1st quality of all shades set over base coat of cement mortar (1:8), 12
C roof slab, including neat cement slurry of honey like consistency spread @
cement paste to full depth mixed with pigment of matching shade, including
and tiles etc., complete, for finished item of work.

Unit = 1 sqm

465.00 4882.50
5873.00 126.86
5873.00 193.81
1684.43 202.13
29.00 58.00

420.00 403.20
375.00 840.00
320.00 1056.00
919.68
8682.18
86.82
8769.00
876.90

Sund -
Amount
ries

--
0.01 996.30
0.04 1032.90
0.03 1036.55
0.02 1040.20
0.02 1043.85
0.01 1047.50

Data-Civil
in coloured tiles of 5 to 7 mm thick of any size cement base in C.M.(1:3) Prop.
sistency at the rate of 3.30 Kgs. cement per Sq.mt. mixed with pigment of
, curing etc., complete as directed by the department for finished of work

Unit = 1 sqm

413.00 4336.50
5873.00 338.28
5873.00 193.81
1684.43 202.13
29.00 174.00
0.00
420.00 323.40
320.00 256.00
231.76
6055.89
60.56
6116.44
611.64

Sund -
Amount
ries

0.03 694.94
0.03 694.94
0.01 704.14
0.04 705.09
0.02 705.99
0.00 706.90
0.03 707.85

Data-Civil
oncrete designer tiles of 30mm thicknes of M40 Grade which top 12mm thick
ed colour and white cement to get required reflective glazing inclisive of all
p. 20 mm thick including neat cement slurry of honey like consistency spread
the joints with white cement at 2.00 Kg. per Sq.m. mixed with pigment of
ance of all materials, labour charges, laying of tiles etc., complete as directed
o.

Unit = 1 sqm

518.00 5439.00
5873.00 126.86
5873.00 193.81
1684.43 202.13
29.00 58.00

420.00 403.20
375.00 840.00
320.00 1056.00
919.68
9238.68
92.39
9331.06
933.11

Sund -
Amount
ries

0.00 1060.15
0.00 1060.15
0.03 1096.75
0.02 1100.40
0.02 1104.06
0.01 1107.71
0.00 1111.35

Data-Civil
from section made of galvanized steel powder coated (base steel as per IS
120 grams/square meter). The factory made section should be with a powder
microns thick with total coated thickness of 1.25 mm. Size of door frame
bate of 38mm to accommodate 30 mm thick door shutter with groove to insert
o be filled with polyurethane foam. the frame section should be cut to length
frame should be provided with : 2mm thick MS powder coated butt hinges of
os. double shutter. CRCA Electroplates stiffeners of 6 Nos. -3 in each vertical
2 mm hold fasts screwed to stiffeners - 6Nos. with split end tail. Nylon Aldrop
Rod 1 No. DOOR FRAME FOR WITH OUT SILL OF SIZE 0.91X2.13 M.

759.00 3924.03

3924.03
534.26
0.01
4458.30

Data-Civil
made from extruded sections in over all dimentions of 40 x 48mm having wall
eriation of +/- 0.3mm complete and Sintex door shutter made from specially
coumpound sheets, Polyurethene core and PVC Frame Section SMS sheets
13410 sheet shall have an average thickness of 1.4 mm +0.35 mm on both
ed with high density polyurethane foam , injected wiht the help of hydraulic
of PVC extruded section confirming to IS:10151 :1982 of size 26 mm x 46 mm
both sides corresponding to sintex code DWUF 305. The hardware locations
einforcement wooden blocks of suitable size. The corners of the shutter frame
ed angle of size 105 mm x 230 mm corresponding to Sintex code PR-02 the
sections having overall dimensions of 26 mm x 46 mm 1.5 mm +0.3mm on
responding to Sintex code 305 combining two numbers. Wooden pieces are
e reinforcement shall be provided on vertical sides of shutter frame the rate
Color: White & Grey. SINTEX ENDURA DOOR SHUTTER (26MM THICK).

Unit - Each

4.72 244.00 1151.68

1.6188 3162.00 5118.65

1.00 329 329.00

1.00 141 141.00

2.00 126 252.00

3.00 132 396.00

Rs. 7388.33
Rs. 1005.92

Rs. 8394.25

Data-Civil
lushdoor shutter of solid bond wood black board type 30mmthick conforming
uding cost of fixtures of M.S.Powder coated 1 No. 250 mm long aldrop, 1 No.
tower blot, 1 No. 125 mm long handle including cost and conveyance of all
e as per drawing and as directed by the department for DOOR OF SIZE: 0.91

Unit :: Each

1.785 1314.00 2345.49

1.00 151.00 151.00

1.00 115.00 115.00

1.00 56.00 56.00

1.00 34.00 34.00

1.785 348 621.18

Rs. 248.47
Rs. 3571.14
Rs. 486.21

Rs. 4057.35

Data-Civil
asement Windows with fly proof mesh made of pre-painted steel (Base steel
as per IS-277 with Zinc of 120 GSM), finish painted with a polyester paint of
ame fo 100 x 45 mm., centre mullion of 100x60 mm, section for shutter of 52 x
r of 52 x 25 m x 0.6 mm thick and fitted with stainless steel 32 gauge fly mesh
and mullions to have double rebate for glazed shutter and fly-shutter with a
ons cut to length metre joined with corner bracket, centre mullion fixed with
h handle, window stopper, 2 Nos. of with MS powder coated/ SS ball bearing
ws fitted with 4 mm thick plain float glass with rubber gaskets including fixing
eans of self expanding screws, including 10 mm square guard bars with 6"
d item of work. Windows of size 5'-0"x4'-0" (1524x1219.20mm) outerframe
ction size of 52x25mm, vertical mullion section of size 100x60mm beeding
ass holding.

Unit : Each

2.08 6427.00 13368.16

Rs. 1820.075
15188.23
0.02
Rs. 15188.25

Data-Civil
ors made of pre-painted steel (Base steel as per IS 513of 0.80mm thick
GSM), finish painted with a polyester paint of 60-65 microns thick and section
n of 80 x 60mm, section for shutter of 52 x 25mm x 0.6mm thick, outer frame
ter with a provision for guard bars/ grills and the sections cut to length metre
ed with mullion cap, 1No. of High grade nylon latch handle, window stopper, 2
aring but hinges provided per shutter and windows fitted with 4 mm thick plain
ng the frames in concrete / masonry wall by means of self expanding screws,
(152.4mm) pitch etc., complete for finished item of work. Single fixed louvers
mm) outer frame box section size of 80 x 45mm.Ventilator window 2'-6" x 1'-
ter frame section size of 47 x 20mm 0.91 x 0.46 mm. Ventilator window.

Unit : Each

0.42 4177.00 1754.34

Rs. 238.85
0.01
Rs. 1993.20

Data-Civil
80 x 1.25 mm. machine rolled CRCA laths, interiocked together through their
nds by end locks, mounted on specially designed pipe shaft of 50 mm. dia
ts, plates, guide channels, stoppers, bottom locking plates and arrangements
perations inlcuding cost of hood cover and springs complete, painted wiht one
earings, all accessories etc., complete for finished item of work as per special

Unit - 1 Sqm.
1.00 2861.00 2861.00

Rs. 389.53
0.02
Rs. 3250.55

Data-Civil
k in two coats with synthetic enamel paint of approved colour, over one coat of
of all materials, incidental charges such as sand paper, cleaning the surface,
hree coats).

Unit : 1 Sqm.

0.70 158 110.60

0.70 375 262.50


Rs. 105.00
Rs. 3.67

1.20 276 331.20

1.20 375.00 450.00


180.00
Rs. 1442.97
Rs. 196.46
Rs. 1639.43
Rs. 163.94
0.01
Rs. 163.95

Data-Civil
e cement or polymer or cement based of average 1 to 2mm thickness over
ven and smooth after throughly brushing the surface to remove all dirt and
lying emery paper ,sand the surface ,clean & wipe off loose dust ,applying
air dry for 2-3 hrs sand with 180 and 320no,emery paper for the surface
of all matrials to work site and all operational ,incidental,labour chages etc
al walls.

Unit = 1 Sqm

43.75 1006.25

480.00 131.04
375.00 238.88
320.00 291.20
264.45
Rs. 1931.81
Rs. 263.02
Rs. 2194.83
Rs. 219.48
Rs. 0.02
Rs. 219.50

Data-Civil
proof cement paint interior grade-I of approved brand and shade over a base
king 3 coats in all to give an even shade after throughly brushing the surface
owdered materials to work site and all operational, incidental, labour charges
er SS 912 for internal walls.

Unit : 1 Sqm.
165.00 165.00
480.00 100.80
375.00 183.75
113.82
52.00 182.00

480.00 72.00
375.00 131.25
320.00 480.00
273.30
Rs. 1701.92
Rs. 231.72
Rs. 1933.64
Rs. 193.36
Rs. 0.04
Rs. 193.40

Data-Civil
based cement primer of exteriorgrade -II paint of approved brand and shade
r grade-2 making 3 coats in all to give an even shade after throughly brushing
f loose ppowdered materials to work site and all operational, incidental, labour
ork as per SS 912 for exterior walls.

Unit : 1 Sqm.
210.00 210.00
480.00 100.80
375.00 183.75
113.82
40.00 140.00

480.00 72.00
375.00 131.25
320.00 480.00
273.30
Rs. 1704.92
Rs. 232.12
Rs. 1937.04
Rs. 193.70

Rs. 193.70

Data-Civil
Cm. pressure P.V.C.Pipe of Prince / Sudhakar make from roof up to basement
s per ISI. Standard fixed to wall with pipe clips including labour charges etc.,

Unit - 1Rmt

161.33 161.33
9.00 9.00
70.00 70.00
Rs. 240.33
Rs. 32.72
Rs. 273.05

Data-Civil
ABSTRACT FOR INTERNAL WATER SUPPLY AND SANITARY
Name of Work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at Maddi
Visakhapatnam in the place of existing A & B staff quarters.
Sl.
Quantity Description of item Rate Unit
No.

Supply and laying of ASHIRVAD/ Ajay/ Astral flowguard or


equivalent CPVC pipes conforming to (IS 15778:2007) with
malleable specials to meet the requirement of ASTMD-2846
and are produced in CTS (copper tube sizes 1/2" ton 2")
such as Tees, Elbows, Check nuts, unions, bushes, etc.,
Solvent Cement including fixing in walls ceiling floors
1
including for necessary exacavation in all sorts of soils,
chasing in the walls etc., refilling consolidation with the
excavated earth & Making bores in cement mortar and
complete. When making a transition use metal threads
fittings, including all taxes for finished item of work as
directed by the Engineer in charge. Sump to over head tank.

A 286.000 54 mm dia OD pipe 596.50 RMT


B 520.000 28.60mm dia OD pipe 240.90 RMT
Supplying and Fixing of 12.70mm NP Bib tap indian make
heavy duty, Seiko or equivalent fancy type deluxe with
2 20.000 necessary fittings etc., complete including cost and 293.15 EACH
conveyance of all materials, all taxes and all labour charges
for finished item.
Supplying and Fixing of 12.70mm NP long body Bib tap
indian, Seiko/Nice or equivalent fancy type deluxe with
3 20.000 necessary fittings etc., complete including cost and 723.75 EACH
conveyance of all materials, all taxes and all labour charges
for finished item.
Supplying and fixing of 50 mm dia G.M.Peet Valve as per
I.S.778 1st Class of approved make Zoloto including cost
4 6.000 4216.25 EACH
and conceyance of all materials, labour charges etc.,
complete.
Supplying and fixing of 25 mm dia G.M.Peet valve as per
I.S.778 1st Class of approved make Zoloto including cost
5 20.000 1400.90 EACH
and conceyance of all materials, labour charges etc.,
complete.
Supplying and Fixing of 12.70mm NP Angle stop cock
indian make 400gms, Seiko or equivalent fancy type deluxe
6 20.000 with necessary fittings etc., complete including cost and 538.55 EACH
conveyance of all materials, all taxes and all labour charges
for finished item of work in all floors.

Supply and fixing of 38.1 mm C.P. waste coupling Half or


7 20.000 269.30 EACH
Full Thead 1st Quality Indian make Parryware of equivalent.

SANITARY FITTINGS

ABS-Int.WS
Sl.
Quantity Description of item Rate Unit
No.

Supply, Installation and commissioning approved make floor


mounted EWC (suit), White coloured CASCADE model 'P'
of 'S' trap with dual flush porcelain cistern fixed on EWC with
all internal parts of dual flush cistern, ultra solid seat cover
of approved make with rubber buffer and cap 15 mm angle
8 20.000 11008.20 EACH
stop cock 450 mm long PVC inter connection pipe wall
flanges all of approved make etc. completeincluding cost, all
taxes and all labour charges etc., complete including cutting
and making good the walls and floors wherever required as
directed by Engineer-in-charge.

Supply & Fixing White glazed flat back half stall Urinals 1
St guailty conforming to I S 2556-1995 with standard C P
Spreader of over all size 95 x 95 x 57 mm conforming to I S
9 20.000 3477.75 EACH
2556-part 6, sec.6-1974 fixed with screws complete Indian
make ( H S W / Parry /Neycer ) 410 x 265 x305 mm and
12.70 mmdia N P push cock.

Supplying & Fixing Indian make Flat Back Wash Hand Basin
(HSW/Parryware/Neycer) 1st quality with single C.P.Pillar
cock, conforming to IS:2556-Part-4-1972 with waste fittings
like 38.10mm waste coupling, rubber plug, chain, 32 mm
nominal size C.P fitting with parallel pipe thread conforming
to IS/:2963-1979 and fitted with 12.70mm dia. Chromium
Plated Pillar tap of 1st quality Indian make 400 grams
10 20.000 Seiko / Esso or equivalent etc., complete with standard CI 1761.05 EACH
brackets including wooden block, 31.75 mm PVC flexible
waste pipe of 914.4mm long, 15mm inlet PVC connection
with unions complete, including cutting and making good the
walls where ever required for the following sizes etc.,
complete for different floors, including cost, all taxes and
conveyance of all materials and all labour charges etc.,
complete for finished item of work.

Supplying and fixing of 3" dia P.V.C Nanhay Trap prince /


Sudhakar or any ISI Brand with jally including cost and
11 30.000 115.90 EACH
conveyance of all material and labour charges etc.,
complete.
Supplying and fixing 110 mm (4") dia., PVC Vent pipe of
Prince /Sudhakar make and jointing and making holes and
12 382.160 redoing the same in good condition including cost and 273.05 1 RMT
conveyance of material, Labour charges Fixing etc.,
complete.
Supplying and fixing 160 mm (6") dia., PVC pipe of
Prince /Sudhakar make of 4 Kg/ Sq.Cm. and jointing and
13 20.000 making holes and redoing the same in good condition 536.10 1 RMT
including cost and conveyance of material, Labour charges
Fixing etc., complete.

ABS-Int.WS
Sl.
Quantity Description of item Rate Unit
No.
Supplying and fixing 75 mm (3") dia., PVC Pipe of Prince
/Sudhakar make of 4 Kg/Sq.Cm. and jointing and making
14 240.000 holes and redoing the same in good condition including cost 207.95 1 RMT
and conveyance of material, Labour charges Fixing etc.,
complete.
Supplying and fixing 150 mm x 100 mm SWG GULLY TRAP
of ISI make conforming to ISI 651 & 4127 with C.I Grating
15 4.000 288.60 EACH
including Cost and Conveyance of all materials etc.,
complete.
Constructing brick masonry inspection chamber of size
457.2 mm x 457.2 mm (1'6"x1'6") in CM 1:6 prop. upto
914.4 mm (3'0") and fitted with light weight 457.2 mm x
16 4.000 3109.69 EACH
457.2 mm (1'6"x1'6") C.I frame and cover of 20 Kg.
including cost all taxes and conveyance of all materials etc.,
complete for finished item of work.
Supplying and fixing 110mm dia., PVC Vent Cowl of
Prince/Sudhakar make suitable for Vent pipe with air tight
17 8.000 21.60 EACH
joint including cost and of all material, Labour charges Fixing
etc., complete.

Constructing 904.0 mm (30) dia brick masonry inspection


chamber as per IS - 4111: Part-1:1986 with cement mortar
(1:6) prop using 2nd Class Clay Bricks of 225 mm thick from
approved source having a minimum crushing strength of 5
N/sq.mm including plastering with cement mortar 1:3 prop;
thick both inside and outside fitted with 20 dia RCC
manhole covers and frames including excavating pits up to a
depth of 904 mm (3'-0") in all sorts of soils (exculding rock)
18 2.000 and laying cement conrete (1:4:8) 150 mm thick using 40 8881.30 EACH
mm HBG Metal and P.C.C. 1:2:4 benching and channel 100
mm thick as per Standard specification and including cost
and conveyance of all materials like cement, sand, bricks,
water etc., to site, cost of seigniorage charges on all
materials and all incidental and operational, labour charges
like mixing cement mortar, constructing masonry, lift
charges, curing etc., complete for finished item of work as
per Standard specification.

Supplying and fixing of 110.00 mm dia P.V.C. Door Bends


Prince/Sudhakar are equivalent make suitable for bath room
19 22.000 conneciton including cost and conveyance of all materials 94.30 EACH
jointing labour chareges for fixing etc. complete as directed
by the Department.
Supplying and fixing of 110 mm dia P.V.C. Door Single Tee
Prince/ Sudhakar are equivalent make suitable for bath
20 20.000 room conneciton including cost and conveyance of all 147.70 EACH
materials jointing labour chareges for fixing etc. complete as
directed by the Department.

ABS-Int.WS
Sl.
Quantity Description of item Rate Unit
No.
Supplying and fixing of 76.20 mm dia P.V.C. Door Bends
Prince/Sudhakar are equivalent make suitable for bath room
21 4.000 conneciton including cost and conveyance of all materials 76.15 EACH
jointing labour chareges for fixing etc. complete as directed
by the Department.
Supplying and fixing of 75 mm dia P.V.C. Door Tee
Prince/Sudhakar are equivalent make suitable for bath room
22 32.000 conneciton including cost and conveyance of all materials 82.95 EACH
jointing labour chareges for fixing etc. complete as directed
by the Department.
Constructing Brick masonry chamber over the gully trap or
peet valve and fitted with 304.8 x 228.6 m size CI frame and
23 4.000 538.55 EACH
hinged cover including plastering and finishing etc.,
complete.

Supply and fixing 25.4 mm dia and 609.6 mm long CP


anodized Towel Rod with brackets and aluminium screws
24 20.000 186.35 EACH
including cost and conveyance of all materials and labour
charges etc., complete as ditected by the Department.

Supplying and fixing 50.8 Cm dia C.I. Man hole frame &
25 2.000 cover for chamber (Medium weight) as per IS:1726-40Kgs. 3048.30 EACH
For Water Tanks.
TOTAL
Add L.S for unforceen items
Say. TOTAL:

ABS-Int.WS
R INTERNAL WATER SUPPLY AND SANITARY
mmercial Complex (Cellar+Ground+4Floors) at Maddilapalem,
n the place of existing A & B staff quarters.

Amount

170,599.00
125,268.00

5,863.00

14,475.00

25,297.50

28,018.00

10,771.00

5,386.00

ABS-Int.WS
Amount

220,164.00

69,555.00

35,221.00

3,477.00

104,348.79

10,722.00

ABS-Int.WS
Amount

49,908.00

1,154.40

12,438.78

172.80

17,762.60

2,074.60

2,954.00

ABS-Int.WS
Amount

304.60

2,654.40

2,154.20

3,727.00

6,096.60

930,567.27
3,899.71
934,466.98

ABS-Int.WS
DETAILED ESTIMATE For W/S And S/F

Name of work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at Maddilap


Sl. Visakhapatnam in the place of existing A & B staff quarters.
No. Description of Item Nos. L B D

1 Supply and laying of ASHIRVAD/ Ajay/ Astral


flowguard or equivalent CPVC pipes conforming to
(IS 15778:2007) with malleable specials to meet the
requirement of ASTMD-2846 and are produced in
CTS (copper tube sizes 1/2" ton 2") such as Tees,
Elbows, Check nuts, unions, bushes, etc., Solvent
Cement including fixing in walls ceiling floors
including for necessary exacavation in all sorts of
soils, chasing in the walls etc., refilling consolidation
with the excavated earth & Making bores in cement
mortar and complete. When making a transition use
metal threads fittings, including all taxes for finished
item of work as directed by the Engineer in charge.
Sump to over head tank.

A 54 mm dia OD pipe
Tank to Roof Slab 1 x 1 72.00 -- --
From ground sump to over head tank inlet 1 x 1 75.00 -- --
From Top Floor to 1st Floor 1 x 8 15.00 -- --
From 1st Floor to Cellar 1 x 1 19.00 -- --
Total :
B 28.60 mm dia OD pipe
From Top Floor to 1st Floor 1 x 4 x 16 5.00 -- --
From 5th Floor, G.F. and Cellar Floor 1x 2x 4 5.00 -- --
For Tap connection 1 x 40 x 4.00 -- --
Total :
2 Supplying and Fixing of 12.70mm NP Bib tap indian
make heavy duty, Seiko or equivalent fancy type
deluxe with necessary fittings etc., complete
including cost and conveyance of all materials, all
taxes and all labour charges for finished item.

For Taps all Floors 4x 5 -- -- --


3 Supplying and Fixing of 12.70mm NP long body Bib
tap indian, Seiko/Nice or equivalent fancy type
deluxe with necessary fittings etc., complete
including cost and conveyance of all materials, all
taxes and all labour charges for finished item.

For Taps all Floors 4x 5 -- -- --


4 Supplying and fixing of 50 mm dia G.M.Peet Valve
as per I.S.778 1st Class of approved make Zoloto
including cost and conceyance of all materials,
labour charges etc., complete.

1
Det-Int.WS
Sl.
No. Description of Item Nos. L B D

G M Feet Value 50 mm dia 1x 6 -- -- --


5 Supplying and fixing of 25 mm dia G.M.Peet valve
as per I.S.778 1st Class of approved make Zoloto
including cost and conceyance of all materials,
labour charges etc., complete.
G M Feet Value 25 mm dia 4x 5 -- -- --
6 Supplying and Fixing of 12.70mm NP Angle stop
cock indian make 400gms, Seiko or equivalent
fancy type deluxe with necessary fittings etc.,
complete including cost and conveyance of all
materials, all taxes and all labour charges for
finished item of work in all floors.

Angle valves 4x 5 -- -- --
7 Supply and fixing of 38.1 mm C.P. waste coupling
Half or Full Thead 1st Quality Indian make
Parryware of equivalent.
For coupling with pipe 4x 5 -- -- --

FOR SANITARY
8 Supply, Installation and commissioning approved
make floor mounted EWC (suit), White coloured
CASCADE model 'P' of 'S' trap with dual flush
porcelain cistern fixed on EWC with all internal parts
of dual flush cistern, ultra solid seat cover of
approved make with rubber buffer and cap 15 mm
angle stop cock 450 mm long PVC inter connection
pipe wall flanges all of approved make etc.
completeincluding cost, all taxes and all labour
charges etc., complete including cutting and making
good the walls and floors wherever required as
directed by Engineer-in-charge.

CASCADE 4x 5 -- -- --
9
Supply & Fixing White glazed flat back half stall
Urinals 1 St guailty conforming to I S 2556-1995 with
standard C P Spreader of over all size 95 x 95 x 57
mm conforming to I S 2556-part 6, sec.6-1974 fixed
with screws complete Indian make ( H S W /
Parry /Neycer ) 410 x 265 x305 mm and 12.70
mmdia N P push cock.
White glazed flat back stall Urinals 4x 5 -- -- --

1
Det-Int.WS
Sl.
No. Description of Item Nos. L B D

10 Supplying & Fixing Indian make Flat Back Wash


Hand Basin (HSW/Parryware/Neycer) 1st quality
with single C.P.Pillar cock, conforming to IS:2556-
Part-4-1972 with waste fittings like 38.10mm waste
coupling, rubber plug, chain, 32 mm nominal size
C.P fitting with parallel pipe thread conforming to
IS/:2963-1979 and fitted with 12.70mm dia.
Chromium Plated Pillar tap of 1st quality Indian
make 400 grams Seiko / Esso or equivalent etc.,
complete with standard CI brackets including
wooden block, 31.75 mm PVC flexible waste pipe of
914.4mm long, 15mm inlet PVC connection with
unions complete, including cutting and making good
the walls where ever required for the following sizes
etc., complete for different floors, including cost, all
taxes and conveyance of all materials and all labour
charges etc., complete for finished item of work.

Hand wash basin 4x 5 -- -- --


11 Supplying and fixing of 3" dia P.V.C Nanhay Trap
prince / Sudhakar or any ISI Brand with jally
including cost and conveyance of all material and
labour charges etc., complete.
Nanhay Trap 5x 6 -- -- --

12
Supplying and fixing 110 mm (4") dia., PVC Vent
pipe of Prince /Sudhakar make and jointing and
making holes and redoing the same in good
condition including cost and conveyance of material,
Labour charges Fixing etc., complete.
W.C. Connections G.F. to 4th Floor 5 x 4 2.44 -- --
Connections Cellar 1 x 4 2.44 -- --
Vertical vent pipe 1 x 4 22.00 -- --
IC to IC connection 2 x 4 12.20 -- --
Chamber to chamber connection 1 x 2 54.00 -- --
septic tank to out side
drain connection 1x 1 30.00 -- --
Total: Total :
13 Supplying and fixing 160 mm (6") dia., PVC pipe of
Prince /Sudhakar make of 4 Kg/ Sq.Cm. and jointing
and making holes and redoing the same in good
condition including cost and conveyance of material,
Labour charges Fixing etc., complete.

IC to Septic tank 1x 2 10.00 -- --

1
Det-Int.WS
Sl.
No. Description of Item Nos. L B D

14 Supplying and fixing 75 mm (3") dia., PVC Pipe of


Prince /Sudhakar make of 4 Kg/Sq.Cm. and jointing
and making holes and redoing the same in good
condition including cost and conveyance of material,
Labour charges Fixing etc., complete.

Out let 4th floor to Ground 1x 2x 4 20.00 -- --


Bath Connection 1x 2x 4 10.00 -- --
Total Total :
15 Supplying and fixing 150 mm x 100 mm SWG
GULLY TRAP of ISI make conforming to ISI 651 &
4127 with C.I Grating including Cost and
Conveyance of all materials etc., complete.
For Toilet & Kitchen & Wash Basin 2x 2 -- --
16 Constructing brick masonry inspection chamber of
size 457.2 mm x 457.2 mm (1'6"x1'6") in CM 1:6
prop. upto 914.4 mm (3'0") and fitted with light
weight 457.2 mm x 457.2 mm (1'6"x1'6") C.I frame
and cover of 20 Kg. including cost all taxes and
conveyance of all materials etc., complete for
finished item of work.

Inspection Chamber 1x 4 -- --
17 Supplying and fixing 110mm dia., PVC Vent Cowl of
Prince/Sudhakar make suitable for Vent pipe with air
tight joint including cost and of all material, Labour
charges Fixing etc., complete.
2x 4 -- --
18 Constructing 904.0 mm (30) dia brick masonry
inspection chamber as per IS - 4111: Part-1:1986 with
cement mortar (1:6) prop using 2nd Class Clay Bricks of
225 mm thick from approved source having a minimum
crushing strength of 5 N/sq.mm including plastering with
cement mortar 1:3 prop; thick both inside and outside
fitted with 20 dia RCC manhole covers and frames
including excavating pits up to a depth of 904 mm (3'-0")
in all sorts of soils (exculding rock) and laying cement
conrete (1:4:8) 150 mm thick using 40 mm HBG Metal
and P.C.C. 1:2:4 benching and channel 100 mm thick as
per Standard specification and including cost and
conveyance of all materials like cement, sand, bricks,
water etc., to site, cost of seigniorage charges on all
materials and all incidental and operational, labour
charges like mixing cement mortar, constructing masonry,
lift charges, curing etc., complete for finished item of work
as per Standard specification.

3'-0" dia inspecitonchambers 1x 2 -- --

1
Det-Int.WS
Sl.
No. Description of Item Nos. L B D

19 Supplying and fixing of 110.00 mm dia P.V.C. Door


Bends Prince/Sudhakar are equivalent make
suitable for bath room conneciton including cost and
conveyance of all materials jointing labour chareges
for fixing etc. complete as directed by the
Department.

Door bends 4x 5 -- --
. Connections Cellar 5th Floor 1x 2 -- --
Total :
20 Supplying and fixing of 110 mm dia P.V.C. Door
Single Tee Prince/ Sudhakar are equivalent make
suitable for bath room conneciton including cost and
conveyance of all materials jointing labour chareges
for fixing etc. complete as directed by the
Department.

Door Tee 4x 5 -- --
21 Supplying and fixing of 76.20 mm dia P.V.C. Door
Bends Prince/Sudhakar are equivalent make
suitable for bath room conneciton including cost and
conveyance of all materials jointing labour chareges
for fixing etc. complete as directed by the
Department.

Top floor 1x 4 -- --
22 Supplying and fixing of 75 mm dia P.V.C. Door Tee
Prince/Sudhakar are equivalent make suitable for
bath room conneciton including cost and
conveyance of all materials jointing labour chareges
for fixing etc. complete as directed by the
Department.

1st, 2nd, 3rd and 4th floors 2x 4x 4 -- --


23 Constructing Brick masonry chamber over the gully
trap or peet valve and fitted with 304.8 x 228.6 m
size CI frame and hinged cover including plastering
and finishing etc., complete.
Gully trap chambers 2x 2 -- --
24
Supply and fixing 25.4 mm dia and 609.6 mm long
CP anodized Towel Rod with brackets and
aluminium screws including cost and conveyance of
all materials and labour charges etc., complete as
ditected by the Department.
Towel rods 4x 5 -- --
25 Supplying and fixing 50.8 Cm dia C.I. Man hole
frame & cover for chamber (Medium weight ) as per
IS:1726-40Kgs. For Water Tnaks.
For man hole cover for water tanks 1x 2 -- --

1
Det-Int.WS
LED ESTIMATE For W/S And S/F

mmercial Complex (Cellar+Ground+4Floors) at Maddilapalem,


n the place of existing A & B staff quarters.
Quantity

72.000
75.000
120.000
19.000
286.000 Rmt

320.000
40.000
160.000
520.000 Rmt

20.000 Nos.

20.000 Nos.

1
Det-Int.WS
Quantity

6.000 Nos.

20.000 Nos.

20.000 Nos.

20.000 Nos.

20.000 Nos.

20.000 Nos.

1
Det-Int.WS
Quantity

20.000 Nos.

30.000 Nos.

48.800
9.760
88.000
97.600
108.000

30.000
382.160 Rmt

20.000 Rmt

1
Det-Int.WS
Quantity

160.000
80.000
240.000 Rmt

4.000 Nos

4.000 Nos

8.000 Nos

2.000 Nos

1
Det-Int.WS
Quantity

20.000
2.000
22.000 Nos

20.000 Nos

4.000 Nos

32.000 Nos

4.000 Nos

20.000 Nos

2.000 Nos

1
Det-Int.WS
L EAD C HAR T

(As per Common S.S.R. 2016-2017)


PATRUNIVALASA , SRIKAKULAM
Deduct
Initial Net
Description Source of Conveyance 13.615%
Sl.No. Lead in K.M. Unit charges as Conveyance
of material supply charges. Contractor
per S.S.R Charges
Profit

6 MM Hard
1 granite metal Rapaka 29 1 Cum 735.00 386.40 46.30 340.10

10 mm hard
2 granite metal Rapaka 29 1 Cum 935.00 386.40 46.30 340.10

12.5 mm
hard granite
3 metal Rapaka 29 1 Cum 1097.50 386.40 46.30 340.10

20 mm hard
4 granite metal Rapaka 29 1 Cum 1365.00 386.40 46.30 340.10

40 mm hard
5 granite metal Rapaka 29 1 Cum 845.00 386.40 46.30 340.10
Sand for
Concrete
( Un Bonthala
6 sreened) Koduru 14 1 Cum 95.00 197.40 23.66 173.74
Sand for Bonthala
7 mortar Koduru 14 1 Cum 165.00 197.40 23.66 173.74

Sand for Bonthala


8 filling Koduru 14 1 Cum 95.00 197.40 23.66 173.74

9 Gravel chilakapalem 19 1 Cum 103.00 260.40 31.20 229.20


Rought
stone (RR
10 Masonary) Rapaka 29 1 Cum 180.00 386.40 46.30 340.10

11 Filling Earth Local 1 1 Cum 0.00 31.50 3.77 27.73

Steel (HYSD
12 Bars) Local 1 MT. 34500.00 --
13 Cement Local 1 MT. 6600.00 --
14 Bitumen Vizag HPCL 119 1 MT. 28435.93 837.40 100.35 737.05

Flyash Lime
Solid Bricks
size: 29 x Each 24.00 0.00
22.5 x 14
Cm.
50 Kgs./1
15 Sq.Cm. Local
Flyash Lime
Solid Bricks Each 20.00 0.00
size: 29 x 15
x 14 Cm.
50 Kgs./1
16 Sq.Cm. Local

Flyash Lime
Solid Bricks
Size 29 x 10 Each 11.00 0.00
x 14 Cm.
50 Kgs./1
17 Sq.Cm. Local
9.5 to 11.20
mm HBG
18 metal Rapaka 29 1 cum 656.00 386.40 46.30 340.10
5 to 7 mm
HBG metal
19 IRC Rapaka 29 1 Cum. 504.00 386.40 46.30 340.10

65 mm HBG
20 metal IRC Rapaka 29 1 Cum. 379.00 386.40 46.30 340.10
19 to 22mm
HBG metal
21 IRC Rapaka 29 1 Cum. 984.00 386.40 46.30 340.10
2.36 to 5 mm
HBG metal
22 IRC Rapaka 29 1 Cum. 308.00 386.40 46.30 340.10
40 to 45 mm
HBG metal
23 IRC Rapaka 29 1 Cum. 588.00 386.40 46.30 340.10
Name of Work :- PATRUNIVALASA,SRIKAKULAM.
Cement Mortor Chart
QtY Unit Rate Amount
Cement ( 1 ; 1 ) Prop
Cement 1440.00 Kgs 1 Cum 6.60 9504.00
Sand 1.05 1 Cum 338.74 355.68
Labour 0.20 Each 350.00 70.00
20% M L On Labour 14.00
9943.68
Cement ( 1 ; 3 ) Prop
Cement 480.00 1 Cum 6.60 3168.00
Sand 1.05 1 Cum 338.74 355.68
Labour 0.20 Each 350.00 70.00
20% M L On Labour 14.00
3607.68
Cement ( 1 ; 4 ) Prop
Cement 360.00 1 Cum 6.60 2376.00
Sand 1.05 1 Cum 338.74 355.68
Labour 0.20 Each 350.00 70.00
20% M L On Labour 14.00
2815.68
Cement ( 1 ; 5 ) Prop
Cement 288.00 1 Cum 6.60 1900.80
Sand 1.05 1 Cum 338.74 355.68
Labour 0.20 Each 350.00 70.00
20% M L On Labour 14.00
2340.48

Cement ( 1 ; 6 ) Prop
Cement 240.00 1 Cum 6.60 1584.00
Sand 1.05 1 Cum 338.74 355.68
Labour 0.20 Each 350.00 70.00
20% M L On Labour 14.00
2023.68
Cement ( 1 ; 8 ) Prop
Cement 180.00 1 Cum 6.60 1188.00
Sand 1.05 1 Cum 338.74 355.68
Labour 0.20 Each 350.00 70.00
20% M L On Labour 14.00
1627.68
Seignorage GRAND
Reference
charges TOTAL

Item No.50,
0.00 P.No.27 1075.10

Item No.51,
0.00 P.No.27 1275.10

Item No.52,
0.00 P.No.27 1437.60

Item No.53,
0.00 P.No.27 1705.10

Item No.55,
0.00 P.No.28 1185.10

Item No.27,A
0.00 P.No.308 268.74
Item No.27,A
0.00 P.No.309 338.74

Item No.27,B
0.00 P.No.309 268.74
Item No.8,
0.00 P.No.25 332.20

Item No.22
0.00 A, P.No.15 520.10

27.73

34500.00
6600.00
29172.98

Item No.10,
P.No.13 24.00
Item No.12,
P.No.13 20.00

Item No.13,
P.No.13 11.00

Item No.41,
P.No.27 996.10

Item No.4,
P.No.18 844.10

Item No.54,
P.No.18 719.10

Item No.49,
P.No.18 1324.10

Item No.45,
P.No.18 648.10

Item No.51,
P.No.18 928.10
STATEMENT SHOWING THE LABOUR RATES INCLUDING
ALLOWANCES 20%
Rate/D 20%
Sl No Description ay allowence Total Amt

1 MM 350 70 420

2 1st Cl Mason 445 89 534

3 2nd Cl Mason 400 80 480

4 Painter Class 1 510 102 612

5 Painter Cla 2 400 80 480

6 Bar bender 555 111 666

7 Blacksmith 445 89 534

8 Carpenter Cl 1 475 95 570

9 Carpenter Cl 2 400 80 480

10 Elctrition 515 103 618

Helper & Semi


Skilled 400 80 480
HE LABOUR RATES INCLUDING
WANCES 20%

Remarks

Page No 8,Sl No 3

Page No 6,Sl No 11

Page No 8,Sl No 35

Page No 7,Sl No 35

Page No 8,Sl No 37

Page No 6,Sl No 11

Page No 6,Sl No 2

Page No 6,Sl No 4

Page No 7,Sl No 4

Page No 6,Sl No 5
CIVIL DATA
As per Common SSR
Name of Work :- PATRUNIVALAS

Earth work excavation for foundations and depositing on bank for all lif
1 labour charges such as shoring incidental, sheeting, planking, strutting
means upto 3.00mt depth excluding dewatering charges etc. as per SS

A.P.Standard Data No.12


A) Labour
Man Mazdoor

Add 75% Extra for foundation

Add 13.615% Contractor's Profit & Over head charges

Rate per 1 CUM


Sundries

1A B) Labour for other works


Man Mazdoor
Add 13.615% Contractor's Profit & Over head charges

Rate of 1 Cum
Add Sundreis

2 Sand for filling including cost seignorage and conveyance of all ma


watering and ramming etc complete as per SS
Filling Sand rate as per chart
Labour charges
Man Mazdoor 0.31 x Rs.350.00/-
Add M.L. 40% on labour charges
TOTAL
Add over heads & contracotrs profit at 13.615%
Add Sundries
Total

Filling in Basements with carted earth from approved source to site fo


3 cost and conveyance of all material and labour charges etc., complete.
A.P.Standard Data No.17&9.
A) Labour
Cost of 1Cum Ear 42 including 20% labour towards
Minicipal limits area allowance
1 KM lead charges.
Man Mazdor. (437.50/6)

Add 13.615% Contractor's Profit & Over head charges

Sundries
Laying PCC work of mix (1 : 4 : 8) prop. Using 40 mm gauge hard g
4
materials, machine mixing, labour charges, tamping, curing, taxes etc.,

A.P.Standard Data No.22, Page No.20 (BLD-CSTN)-3.5


A. MATERIALS:
Cement
Coarse aggregate 40 mm (HBG Metal) - (
as per chart)
Fine aggregate (Sand)
Water (including for curing) Urban
(P.No.223, Item No.189.a)
B. MACHINERY
Concrete Mixer 10/7 cft (0.2/0.8 Cum. Capacity) 300/200 Diesel
(Pg.No.42,Item.16).
Add. 20% on Crew charges of
(P.No.42, Item No.16)
C. LABOUR:
Mason 1st class (including area allowance)
Man Mazdoor (including area allowance)
Total
Add 13.615% Contractor's Profit & Over head charges
Sundries
Total
Supply and placing of the Design Mix Concrete of grade M30 corresp
content of 380 Kg. per Cum with 12mm and 20mm size graded mac
quarry including cost and conveyance of all materials like cement, fine
sales & other taxes on all materials including all operational, incidental
5
concrete, Vibrating, curing etc.,complete but excluding cost of steel a
including centering shuttering using adjastable Jack Screws, Props and
fabricated steel H-frames, cross members etc., Complete, laying conc
fabrication charges for finished item of work. FOUNDATIONS, PLINTH

A.P.Standard Data No.31 D, P.No.24 and 25.


A. MATERIALS:
a 20mm HBG graded metal
b 12.5 mm HBG graded metal
Sand
Cement
Water (including for curing) Urban
(P.No.223, Item No.189.a)
Admixture @ 40mm for 50 kg of weight of cement.
(7.60*40=304ml.item.No.419P.No.34.
B. LABOUR:
Mason 1st class (including area allowance)
Mason 2nd class (including area allowance)
Man Mazdoor (including area allowance)
C. MACHINERY
Batching Plant at 6.00cum per 1 Hour.
of Item No.9 of P.No.42
Add M.L 20% on CREW Charges
vide P.No. 229 item No 9
Trancsit Mixer 4.00cum capicity for lead up to 1 Km.
(item No.1 P.No.42).
Add M.L 20% on CREW Charges .
Concrete pump Item.No.1236P.No.130..
Needle vibrator hire charges 40mm. As per
vide P.No. 43 item No 40
Add M.L 20% on CREW Charges
Sundries
Total
6 FOR FOOTINGS
Cost of M30 Grade Concreate
Centring charges
(Item No.1A P.No.131)
Add M.L 20% on labour charges
Total (Item No.IA, P.No.131).
Add 13.615% Contractor's Profit & Over head charges
Sundries
Total
7 PEDESTALS
Cost of M30 Grade Concreate
Centring charges
(Item No.1C P.No.131)
Add M.L 20% on labour charges
Total
Add 13.615% Contractor's Profit & Over head charges
Sundries
Total
8 PLINTH BEAMS
Cost of M30 Grade Concreate
Centring charges
(Item No.1D P.No.131
Add M.L 20% on labour charges
Total
Add 13.615% Contractor's Profit & Over head charges
Sundries
Total
Supply and placing of the Design Mix Concrete of grade M30 corresp
content of 380 Kg. per Cum with 12mm and 20mm size graded mac
quarry including cost and conveyance of all materials like cement, fine
sales & other taxes on all materials including all operational, incidental
9
concrete, vibrating, curing etc.,complete but excluding cost of steel a
including centering shuttering using adjastable Jack Screws, Props and
fabricated steel H-frames, cross members etc., Complete, laying conc
fabrication charges for finished item of work. COLUMNS, LINTELS, WA

APStandard data No.31E.


A. MATERIALS:
a 20mm HBG graded metal
b 12.5 mm HBG graded metal
Sand
Cement
Water (including for curing) Urban
(P.No.223, Item No.189.a)
Admixture @ 40ml for 50 kg of weight of cement.
(7.60*40=304ml.item.No.419 P.No.34.
B. LABOUR:
Mason 1st class (including area allowance)
Mason 2nd class (including area allowance)
Man Mazdoor (including area allowance)
C. MACHINERY
Batching Plant at 6.00cum per 1 Hour.
of Item No.9 of P.No42
Add M.L 20% on CREW Charges
vide P.No. 229 item No 9
Trancsit Mixer 4.00cum capicity for lead up to 1 Km.
(item No.1 P.No.42).
Add M.L 20% on CREW Charges .
Concrete pump Item.No.1736 P.No.130
Needle vibrator hire charges 40mm. As per
vide P.No. 43item No 40
Add M.L 20% on CREW Charges
Sundries
Total
VRCC M30 - Rs.
Deduct Vibration charges
Rate for PCC M30 =
Cost of M30 Grade Concreate
Centring charges Rs.
Centring Material charges Rs
Centring Labour charges Rs.
Winch charges (P.231, Sl.No.66) (1.333 x 530.30 =706.88
Crew charges 1.333x263.60=351.37 x M.L@20%=
Lift Charges =

Centering Charges vide I


No.1e, P.No.66 & 68 of S
Sl. Initial
Floor
No. Rate
Material

1 GF. 6158.78 1133.00


2 FF 6158.78 1133.00
3 2nd Floor 6158.78 1133.00
4 3rd Floor 6158.78 1133.00
5 4th Floor 6158.78 1133.00
6 5th Floor 6158.78 1133.00
7 6th Floor 6158.78 1133.00
8 7th Floor 6158.78 1133.00
9 8th Floor 6158.78 1133.00
10 For COLUMNS centering with steel scaffolding pipes, jack props,
VRCC M30 - @ Rs.
Centring charges Rs.
Centring Material charges Rs
Centring Labour charges Rs.

Centering Charges vide I


Sl. Initial No.1e, P.No.66 & 68 of S
Floor
No. Rate
Material
1 G.F 6489.20 341.00
2 FF 6489.20 341.00
3 2nd Floor 6489.20 341.00
4 3rd Floor 6489.20 341.00
5 4th Floor 6489.20 341.00
6 5th Floor 6489.20 341.00
7 6th Floor 6489.20 341.00
8 7th Floor 6489.20 341.00
9 8th Floor 6489.20 341.00
11 FOR LINTELS centering with steel scaffolding pipes, jack props, s
VRCC M30 - Rs.
Deduct Vibration charges
Rate for PCC M30 =
Cost of M30 Grade Concreate
Centring charges Rs.
Centring Material charges Rs
Centring Labour charges Rs.
Centering Charges vide I
Sl. Initial No.1e, P.No.66 & 68 of S
Floor Material
No. Rate
1 G.F 6158.78 1133.00
2 FF 6158.78 1133.00
3 2nd Floor 6158.78 1133.00
4 3rd Floor 6158.78 1133.00
5 4th Floor 6158.78 1133.00
6 5th Floor 6158.78 1133.00
7 6th Floor 6158.78 1133.00
8 7th Floor 6158.78 1133.00
9 8th Floor 6158.78 1133.00

Laying PCC work of mix (1 : 5 : 10) prop. Using 40 mm gauge hard


12
materials, machine mixing, labour charges, tamping, cruing charges, ta
A.P.Standard Data No.24 P.No.21 (BLD-CSTN-3.7).
A. MATERIALS:
Cement
Coarse aggregate 40 mm (HBG Metal) - ( as per chart)
Fine aggregate (Sand)
Water (including for curing) Urban
(P.No.223, Item No.189.a)
B. MACHINERY
Concrete Mixer 10/7 cft (0.2/0.8 Cum. Capacity) 300/200 Diesel
(Pg.No.42,Item.16).
Add. 20% on Crew charges of
(P.No.42, Item No.16)
C. LABOUR:
Mason 1st class (including area allowance)

Man Mazdoor (including area allowance)


Total
Add 13.615% Contractor's Profit & Over head charges
Sundries
Total

Supply and placing of the Design Mix Concrete of grade M30 correspo
using minimum cement content of 380 Kg. per Cum with 12mm and
aggregate) from approved quarry including cost and conveyance of all
etc., to site and including, sales & other taxes on all materials inclu
13
batching, machine mixing, laying concrete, curing etc.,complete but e
work (APSS No.402) including centering shuttering using adjastable Ja
clamps couplings pre fabricated steel H-frames, cross members etc., C
steel and its fabrication charges for finished item of work. CHAJJAS, L

VRCC M30 - Rs.


Deduct Vibration charges
Rate for PCC M30 =
Winch charges (P.231, Sl.No.66) (1.333 x 530.30 =706.88

Crew charges 1.333x263.60=351.37 x M.L@20%=

Lift Charges =
0.05 Cum Cost of M30 GradePlastring
Concreate @ Rs.6204.03
in Centering Charges vide Item
C.M (1:4) P.No.66 & 68 of SSR
Sl.
Floor InitialRate vide data Material
No.
No.13 for 2
1 G.F 307.94 Sqm.
251.70 224.00
2 FF 307.94 251.70 224.00
3 2nd Floor 307.94 251.70 224.00
4 3rd Floor 307.94 251.70 224.00
5 4th Floor 322.96 251.70 224.00
6 5th Floor 322.96 251.70 224.00
7 6th Floor 322.96 251.70 224.00
8 7th Floor 322.96 251.70 224.00
9 8th Floor 322.96 251.70 224.00
Supply and placing of the Design Mix Concrete of M 30 corresponding
of 380 Kg. per Cum with 12mm and 20mm size graded machine cr
including cost and conveyance of all materials like cement, fine aggreg
& other taxes on all materials including all operational, incidental an
14
concrete, vibrate, curing etc.,complete but excluding cost of stee
No.402)including centering shuttering using adjastable Jack Screws,
couplings pre fabricated steel H-frames, cross members etc., Complet
of steel and its fabrication charges for finished item of work. RCC BEAM

A.P.Standard Data No.31 C P.No.25 (BLD-CSTN-3.16)


I .VRCC M30
A. MATERIALS:
a 20mm HBG graded metal
b 12.50 mm HBG graded metal
Sand
Cement
Water (including for curing) Urban
(P.No.223, Item No.189.a)
Admixture @ 40ml for 50 kg of weight of cement.
(7.60*40=304ml.item.No.419 P.No.34.
B. LABOUR:
Mason 1st class (including area allowance)
Mason 2nd class (including area allowance)
Man Mazdoor (including area allowance)
C. MACHINERY
Batching Plant at 6.00cum per 1 Hour.
of Item No.9 of P.No42
Add M.L 20% on CREW Charges
vide P.No. 229 item No 9
Trancsit Mixer 4.00cum capicity for lead up to 1 Km.
(item No.1 P.No.42).
Add M.L20% on CREW Charges .
Concrete pump Item.No.1736 P.No.130
Needle vibrator hire charges 40mm. As per
vide P.No. 43item No 40
Add M.L 20% on CREW Charges
Sundries
Total

Cost of M30 Grade Concreate


Centring charges Rs. 3428.00/1 Cum (Page.131, Sl.No.1H)
Centring Material charges Rs.2002.00/Cum
Centring Labour charges Rs.1426.00/Cum

For roof Beam.


Centering Charges vide I
No.1.h, P.No.131 of SS
Sl. Initial
Floor
No. Rate
Material

1 GF 4993.01 2002.00
2 FF 4993.01 2002.00
3 2nd Floor 4993.01 2002.00
4 3rd Floor 4993.01 2002.00
5 4th Floor 4993.01 2002.00
6 5th Floor 4993.01 2002.00
7 6th Floor 4993.01 2002.00
8 7th Floor 4993.01 2002.00
9 8th Floor 4993.01 2002.00
15 For roof Slab.
Centering Charges vide Item
Sl. Initial P.No.131of SSR
Floor
No. Rate
Material
1 GF 4993.01 227.00
2 FF 4993.01 227.00
3 2nd Floor 4993.01 227.00
4 3rd Floor 4993.01 227.00
5 4th Floor 4993.01 227.00
6 5th Floor 4993.01 227.00
7 6th Floor 4993.01 227.00
8 7th Floor 4993.01 227.00
9 8th Floor 4993.01 227.00

Providing impervious coat to exposed RCC roof slab surface with


cement laid over roof when it is green including cost of all materia
16
operational, incidental and labour charges for mixing mortar, laying, r
wall and slab etc,, complete for finished item of work.

A.P.Standard Data No.60 P.No.Xii (BLD-CSTN-6-8).


A) MATERIALS:
Cement Mortal 1:3 prop. 0.210 x Rs.3596.03
Water proof compound 2.00 Kg. x Rs.52.00
(P.No.25, Item No.241) (SOR-2014-15)
B) LABOUR
Mason 1st class 0.660 x Rs445..00/Day
Mason 2nd class 1.540 x Rs.400.00/Day
Mazdoor (unskiled) 3.70 x Rs.350.00/Day
Add M.L 20% on labour charges
Total
Rate per 1 Sqm.
Lift Charges vide P.No.13
A.P.Standard data

Initial 10 %
Sl. No. Floor
Rate labour
charges
Rs.1600.
25 / 10
Sqms.
1 GF 278.19
2 FF 278.19 16.00
3 2nd Floor 278.19 17.60
4 3rd Floor 278.19 19.20
5 4th Floor 278.19 20.80
6 5th Floor 278.19 22.40
7 6th Floor 278.19 24.00
8 7th Floor 278.19 25.60
9 8th Floor 278.19 27.20
Providing High Yield Strength Deformed Steel bars (Fe 415 Grade
including labour charges for cutting bending to required size shapes,
and tying firmly with M.S. Binding wire of 20 SWG forming grills for r
17 cost and conveyance of deformed steel bars, including all wastage su
conveyance of binding wire cover blocks and all incidental, opeartiona
complete for finished item of work in all floors (APSS No.126) (Payme
only) (No re-rolled steel shall be allowed) complete for (8 mm to 40 mm

A.P.Standard Data No.36 P.No.28 (BLD-CSTN-4-2).


A) Material
HYSD bars including 5 per cent for overlaps
and wastage 1.05 MT x Rs.34500/-/MT 34500
Binding wire 6.00 Kg. x Rs. 60.00/Kg.
Item No.3, P.No.11 of Irrigation
B) Labour for cutting, bending, shifting to site, tying and placing in p
Bar bender 10 Nos. x Rs.555.00/Day (P.No.06)
Mazdoor (Unskilled) 10.00 x Rs.350.00/Day (P.No.08).
Add M.L 20% on labour charges
Total

Lift
Charges
vide
P.No.131
Initial
Sl. No. Floor of
Rate
A.P.Stand
ard data
9050*10
%

1 GF 47445.00 -
2 FF 47445.00 905.00
3 2nd Floor 47445.00 995.50
4 3rd Floor 47445.00 1086.00
5 4th Floor 47445.00 1176.50
6 5th Floor 47445.00 1267.00
7 6th Floor 47445.00 1357.50
8 7th Floor 47445.00 1448.00
9 8th Floor 47445.00 1538.50
Masonry work in CM (1:6) prop with Flyash Cement solid blocks of siz
flyash of 80 kgs, cement of 15 kgs.Gypsum of 5 kgs. and stone du
18
scaffolding and curing etc., complete with a compressive strength not
Structure.
A.P.Standard Data No.55 P.No.35 (BLD-CSTN-5-17).
A. MATERIALS:
No of blocks required for one cum of Masonry (As per chart)
110 Nos. x Rs. 20.00 / 1 No.
Cost of Cement Mortar (1:6) 0.10 Cum x Rs.2012.03 Cum
B. LABOUR
Mason 1st class
Mason 2nd class
Man Mazdoor
Woman Mazdoor
Add M.L 20% on labour charges
Total
Scaffolding charges vide P.No.133 of SSR - Rs.71.76/1Sqm.
Scaffolding charges material Rs.9.93/1Sqm./0.150 = Rs. 66.20/Cum
Scaffolding labour charges Rs.61.83/1Sqm./0.150 = Rs412.20/Cum

Scaffolding Charges vide


Initial No.1.a, P.No.66 of SSR
Sl. No. Floor
Rate Material
Foundatio
1 4,244.25 0
n.
2 GF 4244.25 66.20
3 FF 4244.25 66.20
4 2nd Floor 4244.25 66.20
5 3rd Floor 4244.25 66.20
6 4th Floor 4244.25 66.20
7 5th Floor 4244.25 66.20
8 6th Floor 4244.25 66.20
9 7th Floor 4244.25 66.20
10 8th Floor 4244.25 66.20
Masonry work in CM (1:4) prop with Flyash Cement solid blocks of siz
flyash of 80 kgs, cement of 15 kgs.Gypsum of 5 kgs. and stone du
19
scaffolding and curing etc., complete with a compressive strength not
walls.

A.P.Standard Data No.55A P.No.35 (BLD-CSTN-5-17).


No of blocks required for one cum of Masonry (As per chart)
Cost of Cement Mortar (1:4) as per chart.
B. LABOUR
Mason 1st class
Mason 2nd class
Man Mazdoor
Woman Mazdoor
Add M.L 20% on labour charges
Total
Scaffolding charges vide P.No.133 of SSR - Rs.71.76/1Sqm.
Scaffolding charges material Rs.9.93/1Sqm./0.1 = Rs. 99.30/Cum
Scaffolding labour charges Rs.61.83/1Sqm./0.1 = Rs.618.30/Cum
Scaffolding Charges vide
No.1.a, P.No.66 of SSR
Initial
Sl. No. Floor
Rate
Material

1 GF 4818.45 99.30
2 FF 4818.45 99.30
3 2nd Floor 4818.45 99.30
4 3rd Floor 4818.45 99.30
5 4th Floor 4818.45 99.30
6 5th Floor 4818.45 99.30
7 6th Floor 4818.45 99.30
8 7th Floor 4818.45 99.30
9 8th Floor 4818.45 99.30
Plastering with CM (1:4), 12 mm thick in singlecoat with. Screened san
20
hacking surface, scaffolding, leads, lifts and labour charges etc., compl

A.P.Standard Data No.Xi P.No.54 (BLD-CSTN-6-2).

A) MATERIALS:
Cement Mortar (1:4) as per mortar chart
B) LABOUR:
Mason 1st class
Mason 2nd class
Man Mazdoor
Add: M.L. 20% 1600.25

Rate per Sqm


Scaffolding Charges vide
Initial No.1A, P.No.67 of SS
Sl. No. Floor
Rate Material
1 GF 234.27 2.37
2 FF 234.27 2.37

Providing plastering in CM(1:3), 20mm thick laid over Grano


seigniorage charges, including conveyance charges of materials and
mortar, laying, rendering smooth and thread lining, curing, rounding o
FOR ORNAMENTAL PLASTERING.

A.P.Standard Data No.148 P.No.71 (BLD-CSTN-10-25).


MATERIALS:
Cement Mortal 1:3 prop.
LABOUR
Mason 1st class
Mason 2nd class
Mazdoor (unskiled)
Add M.L 20% on labour charges
Total Rate per 10 Sqm.
Add 13.615% contractor's Profit & Over Head charges
Total
Total Rate per 1 Sqm.
sundries
Total Rate per 1 Sqm.
3 2nd 234.27 2.37
4 3rd 234.27 2.37
5 4th Floor 234.27 2.37
6 5th Floor 234.27 2.37
7 6th Floor 234.27 2.37
8 7th Floor 234.27 2.37
9 8th Floor 234.27 2.37
Plastering with CM (1:3), 12 mm thick in singlecoat with. Screened san
20
hacking surface, scaffolding, leads, lifts and labour charges etc., compl

A.P.Standard Data No.53 P.No.Xi (BLD-CSTN-6-1).

A) MATERIALS:
Cement Mortar (1:3) as per mortar chart
B) LABOUR:
Mason 1st class
Mason 2nd class
Man Mazdoor
Add: M.L. 20% 1600.25

Rate per Sqm


Scaffolding Charges vide
Initial No.1A, P.No.67 of SS
Sl. No. Floor Material
Rate
1 GF 246.15 2.37
2 FF 246.15 2.37
3 2nd 246.15 2.37
4 3rd 246.15 2.37
5 4th Floor 246.15 2.37
6 5th Floor 246.15 2.37
7 6th Floor 246.15 2.37
8 7th Floor 246.15 2.37
9 8th Floor 246.15 2.37
Plastering with CM (1:5), 12 mm thick in singlecoat with. Screened san
21
hacking surface, scaffolding, leads, lifts and labour charges etc., compl

A.P.Standard Data No.77 P.No.42 (BLD-CSTN-8-2).

A) MATERIALS:
Cement Mortar (1:5) as per mortar chart
B) LABOUR:
Mason 1st class
Mason 2nd class
Man Mazdoor
Add: M.L. 20% 1600.25 )

Rate per Sqm


Scaffolding Charges vide
Initial No.1A, P.No.67 of SS
Sl. No. Floor Material
Rate
1 GF 259.14 0.99
2 FF 259.14 0.99
3 2nd 259.14 0.99
4 3rd 259.14 0.99
5 4th Floor 259.14 0.99
6 5th Floor 259.14 0.99
7 6th Floor 259.14 0.99
8 7th Floor 259.14 0.99
9 8th Floor 259.14 0.99
Plastering with CM (1:5), 12 mm thick in singlecoat with. Screened san
22
hacking surface, scaffolding, leads, lifts and labour charges etc., compl

A.P.Standard Data No.77 P.No.42 (BLD-CSTN-8-2).

A) MATERIALS:
Cement Mortar (1:5) as per mortar chart
B) LABOUR:
Mason 1st class
Mason 2nd class
Man Mazdoor
Add: M.L. 20% ( 1600.25 )

Rate per Sqm


Scaffolding Charges vide
Initial No.1A, P.No.67 of SS
Sl. No. Floor Material
Rate
1 GF 227.14 0.00
2 FF 227.14 0.00
3 2nd 227.14 0.00
4 3rd 227.14 0.00
5 4th Floor 227.14 0.00
6 5th Floor 227.14 0.00
7 6th Floor 227.14 0.00
8 7th Floor 227.14 0.00
9 8th Floor 227.14 0.00
Flooring with vitrified tiles of size not less than 598 mm x 598 mm, 8
quality set over base coat of cement mortar (1:8), 12mm thick over CC
23
honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with
shade, Pointing with CM (1:3) including cost of all materials like cemen

A.P.Standard Data No.103 P.No.51 (BLD-CSTN-9-5).


A. MATERIALS:
Vitrified tiles of 1st quality of size ( 8 to 10 mm thick)
(P.No.9, S.No.100) 10.50 x Rs. 1048.00/Sqm
Cement for CM (1:8) proportion for base coat
Cement for slurry
Sand .
White cement for jointing & pointing (Sl.No.1154 Page No.64).
LABOUR
Mason 1st class
Mason 2nd class
Mazdoor (unskiled)
Add M.L 20% on labour charges
Total
add: for water @ 1% on
Total Rate per 10 Sqm.
Rate per 1 Sqm.

vide
Initial
Sl. No. Floor P.No.131
Rate
of
1 G.F 1333.50 0.00
2 FF 1333.50 22.99
3 2nd Floor 1333.50 25.28
4 3rd Floor 1333.50 27.57
5 4th Floor 1333.50 29.86
6 5th Floor 1333.50 32.15
7 6th Floor 1333.50 34.44
8 7th Floor 1333.50 36.73
9 8th Floor 1333.50 39.02

Providing skirting to internal walls to 15 cm height/risers of steps with


CM (1:5) 12 mm thick with cement slurry of honey like consistency sp
24
paste mixed with pigment of matching shade to full depth, including cos
finished item of work.
A.P.Standard Data No.118 P.No.58 (BLD-CSTN-9-20).
A. MATERIALS:
Vitrified tiles of 1st quality of size ( 8 to 10 mm thick)
(P.No.09, S.No.100)
Cement for CM (1:8) proportion for base coat
Cement for slurry
Cost ofSand
White cement for jointing & pointing (Sl.No.1154 Page No.64).
LABOUR
Mason 1st class
Mason 2nd class
Mazdoor (unskiled)
Add M.L 20% on labour charges
Total
add: for water @ 1% on
Total Rate per 10 Sqm.
Rate per 1 Sqm.
Lift Charges vide
P.No.131 of
A.P.Standard data

Initial
Sl. No. Floor
Rate
10 %
Initial labour
Sl. No. Floor charges
Rate
Rs.2478.
20 for
10Sqm.
1 G.F 1352.23 --
2 FF 1352.23 24.78
3 2nd Floor 1352.23 27.25
4 3rd Floor 1352.23 29.72
5 4th Floor 1352.23 32.19
6 5th Floor 1352.23 34.66
7 6th Floor 1352.23 37.13
8 7th Floor 1352.23 39.60
9 8th Floor 1352.23 42.07
Flooring with NON-SKID ceramic tiles of 7.3mm thick of 1st quality
over CC bed already laid or RCC roof slab, including neat cement sl
25
neatly with white cement paste to full depth mixed with pigment of ma
and tiles etc., complete, for finished item of work.
A.P.Standard Data No.104 P.No.51 & 52.
A. MATERIALS:
Ceramic tiles of 1st quality of size ( 7.30mm thick)
(P.No.16, S.No.38) (SOR-2014-15)
Cement for CM (1:8) proportion for base coat
Cement for slurry
Cost of Sand
White cement for jointing & pointing (Sl.No.1154 Page No.64).
LABOUR

Mason 1st class

Mason 2nd class


Mazdoor (unskiled)
Add M.L 20% on labour charges
Total
add: for water @ 1% on
Total Rate per 10 Sqm.
Rate per 1 Sqm.
Lift Charges vide
P.No.131 of
A.P.Standard data
10 %
Initial labour
Sl. No. Floor charges
Rate
Rs.2478.
20for
10Sqm.
1 G.F 839.85 --
2 FF 839.85 24.78
3 2nd Floor 839.85 27.25
4 3rd Floor 839.85 29.72
5 4th Floor 839.85 32.19
6 5th Floor 839.85 34.66
7 6th Floor 839.85 37.13
8 7th Floor 839.85 39.60
9 8th Floor 839.85 42.07

Dadooing walls with 1st quality of glazed plain coloured tiles of 5 t


cement slurry of honey like consistency at the rate of 3.30 Kgs. cemen
26
charges, curing etc., complete as directed by the department for finishe
BATH ROOMS.
A.P.Standard Data No.116, Page No.57.
A. MATERIALS:
Ceramic Glazed tiles of 1st quality of size (5 to 7mm thick)
(P.No.10, S.No.115)
Cement for CM (1:8) proportion for base coat
Cement for slurry
Sand for CM (1:8)
White cement for jointing & pointing (Sl.No.1154 Page No.64).
LABOUR
Mason 1st class
Mazdoor (unskiled)
Add M.L 20% on labour charges
Total
add: for water @ 1% on
Total Rate per 10 Sqm.
Rate per 1 Sqm.
Lift Charges vide
P.No.131 of
A.P.Standard
10 % data
labour
Initial charges
Sl. No. Floor
Rate Rs.622.6
5 for
10Sqm.
1 G.F 890.34 --
2 FF 890.34 6.22
3 2nd Floor 890.34 6.84
4 3rd Floor 890.34 7.46
5 4th Floor 890.34 8.08
6 5th Floor 890.34 8.70
7 6th Floor 890.34 9.32
8 7th Floor 890.34 9.94
9 8th Floor 890.34 10.56
Providing and fixing door frame fabricated from section made of galva
per IS 217 with zinc of 120 grams/square meter). The factory made sec
60 microns thick with total coated thickness of 1.25 mm. Size of door
accommodate 30 mm thick door shutter with groove to insert gasket in
27
the frame section should be cut to length and joined by way be way
powder coated butt hinges of 100 mm long -3 Nos. for single shutter,
each vertical for double shrtter and 40mm x 200 mm x 1.2 mm hold
Receiver -1No. for single shutter frame. Tie Rod 1 No. DOOR FRAME

Door size 0.91 x 1.98 m with out sill

Cost of door frame ., Page No.73,


item No.861 per frame horizental lengths 1 x 0.91 = 0.91
Verticial lenghts 2 x 1.92 = 3.84
Total lenghts 4.75 RM
Total
Add 13.615% contractor's Profit & Over Head charges
Sundries
Total

Providing and fixing door frame fabricated from section made of galva
per IS 217 with zinc of 120 grams/square meter). The factory made sec
60 microns thick with total coated thickness of 1.25 mm. Size of door
accommodate 30 mm thick door shutter with groove to insert gasket in
28
the frame section should be cut to length and joined by way be way
powder coated butt hinges of 100 mm long -3 Nos. for single shutter,
each vertical for double shrtter and 40mm x 200 mm x 1.2 mm hold
Receiver -1No. for single shutter frame. Tie Rod 1 No. DOOR FRAME
Door size 0.91 x 1.98 m with sill

Cost of door frame ., Page No.73,


item No.861 per frame horizental lengths 2 x 0.91 = 1.82
Verticial lenghts 2 x 1.92 = 3.84
Total lenghts 5.66 RM
Total
Add 13.615% contractor's Profit & Over Head charges
Sundries
Total

Providing and fixing door frame fabricated from section made of galva
per IS 217 with zinc of 120 grams/square meter). The factory made sec
60 microns thick with total coated thickness of 1.25 mm. Size of door
accommodate 30 mm thick door shutter with groove to insert gasket in
29
the frame section should be cut to length and joined by way be way
powder coated butt hinges of 100 mm long -3 Nos. for single shutter,
each vertical for double shrtter and 40mm x 200 mm x 1.2 mm hold
Receiver -1No. for single shutter frame. Tie Rod 1 No. DOOR FRAME

Door size 0.76 x 1.98 m with out sill

Cost of door frame ., Page No.73,


item No.861 per frame horizental lengths 2 x 0.76 = 1.52
Verticial lenghts 2 x 1.95 = 3.90
Total lenghts 5.42
Total
Add 13.615% contractor's Profit & Over Head charges
Sundries

Total
30 Supply and fixing of Flush door single leaf shutter of 30 mm thick with
thick on both faces including cost of fixtures of M.S.Powder coated ma
of 200 mm tower blot, 1 No. 125 mm long handle including cost and c
drawing and as directed by the department for DOOR OF SIZE: 0.91 X

a) Size Shutter 0.85 x 1.95 = 1.65 Sqm 1.65


cost of flush door shutter @ Rs.1314.00/1Sqm
(As per item No81page.65

b) Cost of fixtures
1No.250mm long 10mm dia MS powder coated Aldrop
(item No. 275page NO.23)
1 No 200 mm long 12 mm dia MS powder coat Aldrop
(item No.274 page No.22)
1 No 200 mm long 10 mm dia tower bolt powder coated
( item No.247, page No.21)
1 No. 125 mm long MS. Power coated handle
c) (item No.266 page NO.22)
Labour charges
1.65 Sqm labour charges
SSR item No.1107 page 120
Add: M.L. 20% on labour charges
Total
Add 13.615% contractor's Profit & Over Head charges
Sundries
Total
Supply and fixing of Flush door single leaf flushdoor shutter of so
commercial ply on both faces including cost of fixtures of M.S.Powder
31
No. of 200 mm tower blot, 1 No. 125 mm long handle including cost a
per drawing and as directed by the department for DOOR OF SIZE: 0.7

Size Shutter 0.70 x 1.95 = 1.36 Sqm 1.365


cost of flush door shutter @ Rs.1314.00/1Sqm
(As per item No.819, Page No.65)

Cost of fixtures
1No.250mm long 10mm dia MS powder coated Aldrop
(item No.276 page NO.23)
1 No 200 mm long 12 mm dia MS powder coat Aldrop
(item No.274 page No.22)
1 No 200 mm long 10 mm dia tower bolt powder coated
( item No.247, page No.21)
1 No. 125 mm long MS. Power coated handle
(item No.257 page NO.12)
Labour charges
1.365 Sqm labour charges
SoR item No.1107page 120
Add: M.L. 20% on labour charges
Total
Add 13.615% contractor's Profit & Over Head charges
Sundries
Total

Supply and fixing of Flush door single leaf flushdoor shutter of solid
conforming to IS2202 commercial ply on both faces including cost of
32
200 mm long aldrop, 1 No. of 200 mm tower blot, 1 No. 125 mm lon
charges etc., complete as per drawing and as directed by the departme
Size Shutter 0.85 x 1.95 = 1.36 Sqm 1.657
cost of flush door shutter @ Rs.2188.00/1Sqm
(As per item No.817, Page No.65)

Cost of fixtures
1No.250mm long 10mm dia MS powder coated Aldrop
(item No.276 page NO.23)
1 No 200 mm long 12 mm dia MS powder coat Aldrop
(item No.274 page No.22)
1 No 200 mm long 10 mm dia tower bolt powder coated
( item No.247, page No.21)
1 No. 125 mm long MS. Power coated handle
(item No.257 page NO.12)
Labour charges
1.365 Sqm labour charges
SSR item No.1107page 120
Add: M.L. 20% on labour charges
Total
Add 13.615% contractor's Profit & Over Head charges
Sundries
Total
Supplying and fixing of PVC Door frames made from extruded section
mm. wiht usual porcess veriation of +/- 0.3mm complete and Sintex
moulding coumpound sheets, Polyurethene core and PVC Frame Se
sheet shall have an average thickness of 1.4 mm +0.35 mm on bo
polyurethane foam , injected wiht the help of hydraulic injection meth
IS:10151 :1982 of size 26 mm x 46 mm with a wall thickness of 1.4 m
33
The hardware locations shall be reinforced with special polymeric rein
frame shall be reinforced with Polymeric 'L' shaped angle of size 105 m
be made from PVC extruded sections having overall dimensions of 2
variation corresponding to Sintex code 305 combining two numbers
reinforcement shall be provided on vertical sides of shutter frame the r
SINTEX ENDURA DOOR SHUTTER (26MM THICK).

Cost of door frame vide P.No.51, Item No.717


@ Rs.244/Rmt.
For each door frame 0.76 + 1.83+1.83=4.42.
4.42Rmt. (SOR-2014-15)
Door Shutter Size 0.76 x 1.83 = 1.39 Sqm
cost of Shutter with frame (SOR-2014-15)
(As per item No.723 page No.52)
Cost of fixtures
1 No. 200 mm. long Aluminim Aldrop (IS2681 200mm long)
(item No.271 page No. 22)
1 No. Cost of ALLU tower bolt (P.No.21 Item No.240)
10 mm. bolt (IS204) 200 mm long.
2 Nos. 125 mm. long Alluminum Door handle (IS208)
( As per P.No22, Item No.264 )
3 Nos. But hinges (As per P.No 22., Item No.255)
(IS 205)100 mm long.
Total
Add 13.615% contractor's Profit & Over Head charges
Sundries
Total

34 Providing and fixing of Openable / Casement Windows with fly mesh m


galvanized as per IS 277 with Zinc of 120 GSM), finish painted with a p
100 x 45 mm, centre mullion of 100 x 60 mm, section for shutter of 52
mm thick and fitted with stainless steel 32 gauge fly mesh of 304 grade
glazed shutter and fly-shutter with a provision for guard bars/grills and t
mullion fixed with mullion cap, 1 No. of High grade nylon latch handle, w
butt Hinges provided per shutter and windows fitted with 4 mm thick pla
concrete/masonry wall by means of self expanding screws, Including 10
finished item of work.

Size of window -1.22mx1.22m


Area of the window -1.22x1.22 m =1.488
Cost of double shutter at Rs.7069.00.00/1Sq.mtr.
vide P.No.106 item No.1006
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Add sundries
Total
35 Size of window -0.91mx1.22m
Area of the window -0.91x1.22 m =1.11
Cost of double shutter at Rs.7069.00/1Sq.mtr.
vide P.No.54 item No.972
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Add sundries
Total

36 Size of window -1.22 X0.61m


Area of the window -1.22X0.61 =0.744 Sq.m
Cost of double shutter at Rs.6748.00.00/1Sq.mtr.
vide P.No.54 item No.971
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Add sundries
Total

37 Size of window -0.91 X0.61m


Area of the window -0.91X0.61 =0.555 Sq.m
Cost of double shutter at Rs.6748.00.00/1Sq.mtr.
vide P.No.54 item No.971
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Add sundries
Total
Providing and fixing of top hung Ventilators made of pre-painted steel (
with Zinc of 120 GSM), finish painted with a polyester paint of 60-65 mi
of 80 x 60 mm, section for shutter of 52 x 25 mm x 0.6 mm thick, outer
for guard bars/grills and the sections cut to length metre joined with cor
38
grade nylon latch handle, window stopper, 2 nos. of with MS Powder co
fitted with 4 mm thick plain float glass with rubber gaskets including fixin
screws, Including 10 mm Square guard bars with 6 (152.4mm) pitch et
shutter size of 2 0 x 2 0 (760mmX310mm) outer frame section size o

A Size of Ventilator -0.76x0.61m.


Area of the window -0.76x0.61 =0.4636 Sq.m
Cost of double shutter at Rs.6105.00/1Sq.mtr.
vide P.No.55 item No.976
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Add sundries
Total

Providing and applying of wall putty of white cement or polymer or cem


prepare the surface even and smooth after throughly brushing the s
39 applying emery paper ,sand the surface ,clean & wipe off loose dust ,
sand with 180 and 320no,emery paper for the surface preparation i
operational ,incidental,labour chages etc complete for finished item of w

A.P.Standard Data No.18.


A. MATERIALS:

Putty (Pno 40 item no 525)


for 875.00 / 20 Kgs (Rs.43.75/ Kg.)
B. LABOUR
Painter 1 St class P.No.07 Sl.No35.
Painter 2 nd class
Mazdoor
Add M.L 20% on labour charges
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Total
Rate per 1 Sqm
Sundries

Painting to new walls with 2 coats of water proof cement paint interior
cement primer grade I making 3 coats in all to give an even shade a
40
loose ppowdered materials to work site and all operational, incidental, l
for internal walls.
A.P.Standared data no.172 p.no.81

Cost of cement primer 1 Kg. (Item No.487, P.No.38)


1st Class painter
2nd Class painter
Add M.L 20% on labour
Cost of Altek / PMCC or equivalent top coat high UV Resistant exterior
vide
Item No.529, P.No.40 (Rate 1300/25 = 52.00/-)
1st Class painter
2nd Class painter
Mazdoor (unskilled)
Add M.L 20% on labour
Total
Add 13.615% contractor's Profit & Over Head charges
Total
Rate per 1 Sqm
Sundries
Painting to new walls with 2 coats of water based cement primer of ext
approved cement primer grade-2 making 3 coats in all to give an eve
41
remains of loose ppowdered materials to work site and all operational,
per SS 912 for exterior walls.

A.P.Standared data no.172 p.no.81

Cost of cement primer Grade -II, 1 Kg. (Item No.488, P.No.38)


1st Class painter
2nd Class painter
Add M.L 20% on labour
Cost of Altek / PMCC/ Deco orient base or equivalentexterior texture
Item No.528, P.No.40 (Rate 1000/25 = 40.00/-)
1st Class painter
2nd Class painte
Mazdoor (unskilled
Add M.L 20% on labour
Total
Add 13.615% contractor's Profit & Over Head charges
Total
Rate per 1 Sqm
Sundries

Supply and fixing 110 mm dia 4.00 Kg./Sq.Cm. pressure P.V.C.Pipe o


42
plain bend clips and shoe as per ISI. Standard fixed to wall with pipe cli

17 mtr Cost of PVC 110 MM dia. Pipe


(Item No.347, P.No.156) (484/3 = 161.33)
1No. Clips vide p.no.158,item no.440
1 Rmt. Labour charges P.No.160, Sl.No.486
Total
Add 13.615% contractor's Profit & Over Head charges
Total
43 Supply and fixing of 16 to 18 mm thick polished Black Grainte stone
conveyance of all materials for Kitchen Plotform with machine finishi
connection etc., complete

A.P.Standard Data No.105


1.05 Sqmt. Cost of high Polished Black Grainte stone Ra 2352.00/Sqm
(as per SSR Item No.32, P.No.2)
0.021 Cum cost of C.M (1:8) Prop. at Rs. 1619.53/1 Cum

3.3 Kgs. cost of cement at Rs.6.6/Kg.


0.60 Kgs. cost of white cement at Rs.29.00/Kg.
(as per SSR Item No.1154, P.No.64)
Labour
Mason 1st class Day

Mason 2nd class Day


Mazdor Day
20 % M L on Labour ( 4535.00 )
For 10 Sqm
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Add sundries
TOTAL.

44 Supplying and fixing of sink with polished Black Granite Stone of thick
and waste water pipe including cost and conveyance of all materials , l

Base -0.61 x 0.61 = 0.37


Side -2.14 x 0.31 = 0.66
Total 1.03
Cost of 1.03 Sq.mter Granite stone sink at Rs.2352.00
(as per SSR Item No.32, P.No.3)
Rate for half rounding Rs. 289.00/1RM=2.44 RM x 289.00/1RM
Add cutting charges vide item No.1096 p.No.119 at Rs.15.00/1RM
Add fixing charges -L.S.

Total
Add.13.615% towards Contractor Profit & O.H.Charges
Add sundries
Total

45
Providing & placing on terrace (at all floors levels) polyethylene water s
cover and suitable locking arrangement & making necessary holes for
supports for tanks.

For 500 litres capasity of tank 500 lit x 8.00/ 1 Liter.


Rate as per SSR item 1165 page no.125 per 1 litre

Add.13.615% towards Contractor Profit & O.H.Charges


Add sundries
Total

PAINTING to new WOOD work / Iron work in two coats with synth
46 including cost and conveyance of all materials, incidental charges such
complete. (Three coats).

A.P.Standard data No.173 &195


Primary coat
MATERIALS
Wood Primer Item No.491, P.No.38
LABOUR
Painters II CLASS P.No.199 Sl.No.37.
Add. M.L 20% on labour
Add. Sundries for Brushes, Soap, Putty @ 1.00% on Rs.460.60
Paint
MATERIALS
Two coats synthatic enamil vide P.No.39, Item No.516
1.2 Lts. X Rs.253.00/Ltr.
LABOUR
Painters Iind cl. @ Rs:400/Each.
Add M.L 20% on labour
Total
Add 13.615% contractor's Profit & Over Head charges
Total
Rate per 1 Sqm
sundries

Granolithic concrete flooring 20 mm thick with (1:1:2) using 6mm to 1


Roof slab in alternate panels of size not exceeding 1.5Mt x 1.5Mt. a
materials like cement, metal, sand and water etc., complete for finishe
47
A.P.Standard Data No.111 P.No.55 (BLD-CSTN-9-13).
A. MATERIALS:
6mm to 12 mm HBG graded metal
1075.10 + 1437.60
Sand
Cement
B. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskiled)
Add M.L 20% on labour charges

Add 13.615% contractor's Profit & Over Head charges


Total
Rate per 1 Sqm.
Water @ 1% on 339.79
Sundries
Total

Ground
1 343.18
Floor
48 R.R.Masonary in C.M.(1:8) Prop. using hard stone other than granite in
etc., complete for FOUNDATION AND BASEMENT.

A.P.Standard Data No.68 (Page No.39 & 40)

A) MATERIALS :
Cement
Rough Stone as per chart
Bond stone
Sand

B)
LABOUR
Mason 1st class
Man Mazdoor
Add M.L20% on labour
Total
Add 13.615% contractor's Profit & Over Head charges
Sundries.
Total
CIVIL DATAS
As per Common SSR 2016-17
Work :- PATRUNIVALASA (v) SRIKAKULAM .

epositing on bank for all lifts and with an initial lead of 10m including all operational, inc
heeting, planking, strutting, etc. complete for finished item of work .in ordinary soils by m
ng charges etc. as per SS- 20 B (APSS 308)

Unit -1 CUM (taking output : 10 Cum)

Day 5.2 350.00

Rs.
Total Rs.
fit & Over head charges Rs.
Total Rs.
Rs.

Total Rs.

Unit -1 CUM (taking output : 10 Cum)


Day 5.2 350.00
fit & Over head charges Rs.
Total Rs.
Rs.

Total Rs.

and conveyance of all materials and labour charges filling spreading sectioning,
ng etc complete as per SS Under Footings and Flooring
Unit 1 Cum.
Rs. 279.83

Rs. 108.5
Rs. 43.40
Rs. 431.73
Rs. 58.78
Rs. 0.04
Rs. 490.55

approved source to site for leveling the road portions as per standered specification inc
ur charges etc., complete.
Unit -1 CUM

bour towards Day 3.64 42.00


rea allowance

Day 0.31 72.92

Total Rs.
fit & Over head charges Rs.
Total Rs.

Total Rs.
sing 40 mm gauge hard granite machine crushed metal including cost and conveyanc
amping, curing, taxes etc., complete for foundations.

D-CSTN)-3.5 Unit = 1 cum

MT 0.162 6600.00
(
Cum. 0.90 1185.10
Cum 0.45 268.74
KL. 1.2 103.00

ty) 300/200 Diesel Hour 1 352.50

219.70 Hour 1 43.94

Day 0.1 534.00


Day 1.39 420.00
Rs.
fit & Over head charges Rs.
Rs.
Rs.
rete of grade M30 corresponding to IS 456 using WEIGH BATCHER using minimum
20mm size graded machine crushed hard granite metal (coarse aggregate) from ap
materials like cement, fine aggregate ( sand) coarse aggregate, water etc., to site and inc
all operational, incidental and labour charges such as weigh batching, machine mixing
excluding cost of steel and its fabrication charges for finished item of work (APSS
e Jack Screws, Props and Acro span beams including all pipe bracings, clamps coupli
c., Complete, laying concrete, vibrating, curing etc. complete but excluding cost of steel
FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth).

Unit = 1 cum

Cum 0.56 1705.10


Cum 0.24 1437.60
Cum 0.40 268.74
MT 0.38 6600.00
KL. 1.20 103.00

1Lt. 0.304 150.00

Day 0.056 534.00


Day 0.056 480.00
Day 0.917 420.00

Cum. 0.222 539.30


340.60 Hour 0.222 68.12

Hour 0.222 1915.00


283.90 Hour 0.222 56.78
Hour 0.222 342.00
Hour 1.333 184.60

158.20 Hour 1.333 31.64

Rs.
Cum 1 5463.29
Cum 1 750.00

473.00 Cum 1 94.60


Rs.
fit & Over head charges Rs.
Rs.
Rs.

Cum 1 5463.29
Cum 1 1068.00

753.00 Cum 1 150.60


Rs.
fit & Over head charges Rs.
Rs.
Rs.

Cum 1 5463.29
Cum 1 2476.00

1141.00 Cum 1 228.20


Rs.
fit & Over head charges Rs.
Rs.
Rs.
rete of grade M30 corresponding to IS 456 using WEIGH BATCHER using minimum
d 20mm size graded machine crushed hard granite metal (coarse aggregate) from ap
materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site and inc
all operational, incidental and labour charges such as weigh batching, machine mixing
excluding cost of steel and its fabrication charges for finished item of work (APSS N
e Jack Screws, Props and Acro span beams including all pipe bracings, clamps coupli
c., Complete, laying concrete, vibrating, curing etc. complete but excluding cost of steel
COLUMNS, LINTELS, WATER TANKS, RCC WALLS IN BUILDINGS.

Cum 0.56 1705.10


Cum 0.24 1437.60
Cum 0.40 268.74
MT 0.38 6600.00
KL. 1.20 103.00

1Lt. 0.304 150.00

Day 0.111 534.00


Day 0.222 480.00
Day 1.556 420.00

Cum. 0.444 539.30


340.60 Hour 0.444 68.12

Hour 0.444 1915.00


283.90 Hour 0.444 56.78
Hour 0.444 342.00
Hour 1.333 184.60
158.20 Hour 1.333 31.64

Rs.
6489.20
330.42
6158.78
Rs.
2344.00 (P.No.131, SI.No.1E)
1133.00
1211.00
0.30 =706.88 706.88
20%= 70.27
Charges = Rs. 777.15

Centering Charges vide Item Lift Add


No.1e, P.No.66 & 68 of SSR Charges 13.615%
vide towards
P.No.131 Total contractor
M.L of 's profit &
Labour A.P.Stand O.H.
@ 20%
ard data Charges

1211.00 242.20 -- 8744.98 1190.63


1211.00 242.20 -- 8744.98 1190.63
1332.00 266.40 777.15 9667.33 1316.21
1453.00 290.60 847.84 9883.22 1345.60
1574.00 314.80 918.53 10099.11 1374.99
1695.00 339.00 989.21 10314.99 1404.39
1817.00 363.40 1059.90 10532.08 1433.94
1938.00 387.60 1130.59 10747.97 1463.34
2059.00 411.80 1201.28 10963.86 1492.73
lding pipes, jack props, steel centering plates etc.,.
6489.20 Rs.
2041.00 (P.No.131, SI.No.1G)
341.00
1700.00
Lift Add
Centering Charges vide Item Charges 13.615%
No.1e, P.No.66 & 68 of SSR vide towards
P.No.131 Total contractor
M.L of 's profit &
Labour A.P.Stand O.H.
@ 20%
ard data Charges
1700.00 340.00 -- 8870.20 1207.68
1700.00 340.00 8870.20 1207.68
1870.00 374.00 777.15 9851.35 1341.26
2040.00 408.00 847.84 10126.04 1378.66
2210.00 442.00 918.53 10400.73 1416.06
2380.00 476.00 989.21 10675.41 1453.46
2550.00 510.00 1059.90 10950.10 1490.86
2720.00 544.00 1130.59 11224.79 1528.26
2890.00 578.00 1201.28 11499.48 1565.65
ding pipes, jack props, steel centering plates etc.,.
6489.20
330.42
6158.78
Rs.
2344.00 (P.No.131, SI.No.1E)
1133.00 Lift Add
1211.00 Charges 13.615%
Centering Charges vide Item
No.1e, P.No.66 & 68 of SSR vide towards
M.L P.No.131 Total contractor
Labour
@ 20% of 's profit &
1211.00 242.20 A.P.Stand
-- O.H.
8744.98 1190.63
1211.00 242.20 ard --data 8744.98 Charges
1190.63
1332.00 266.40 777.15 9667.33 1316.21
1453.00 290.60 847.84 9883.22 1345.60
1574.00 314.80 918.53 10099.11 1374.99
1695.00 339.00 989.21 10314.99 1404.39
1817.00 363.40 1059.90 10532.08 1433.94
1938.00 387.60 1130.59 10747.97 1463.34
2059.00 411.80 1201.28 11837.58 1611.68

Using 40 mm gauge hard granite machine crushed metal including cost and conveyanc
amping, cruing charges, taxes etc., complete for foundations.
TN-3.7).

MT 0.1296 6600.00
per chart) Cum. 0.90 1185.10
Cum 0.45 268.74
KL. 1.2 103.00
ty) 300/200 Diesel
Hour 1 352.50

219.70 Hour 1 43.94

Day 0.10 534.00

Day 1.39 420.00


Rs.
fit & Over head charges Rs.
Rs.
Rs.

te of grade M30 corresponding to IS 456 using WEIGH BATCHER of 0.50 Cum (6.00cu
per Cum with 12mm and 20mm size graded machine crushed hard granite metal
ost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate
xes on all materials including all operational, incidental and labour charges such as
uring etc.,complete but excluding cost of steel and its fabrication charges for finished
ttering using adjastable Jack Screws, Props and Acro span beams including all pipe br
es, cross members etc., Complete, laying concrete, curing etc. complete but excluding
em of work. CHAJJAS, Lofts & Racks.

6489.20
330.42
6158.78
0.30 =706.88 706.88 *0.05 35.34

20%= 70.27 *0.05 3.51

Charges = Rs. 777.15 per Cum 38.86


Lift Add
Rs.6204.03 Charges Rs. 13.615%
ntering Charges vide Item No.1F,
P.No.66 & 68 of SSR vide towards
M.L P.No.131 Total contractor
Labour
@ 20% of 's profit &
186.00 37.20 A.P.Stand
-- 1006.84 O.H. 137.08
186.00 37.20 ard --data 1006.84 Charges
137.08
205.00 41.00 38.86 1068.50 145.48
223.00 44.60 42.39 1093.63 148.90
242.00 48.40 45.93 1134.99 154.53
260.00 52.00 49.46 1160.12 157.95
279.00 55.80 53.00 1186.46 161.54
298.00 59.60 56.53 1212.79 165.12
316.00 63.20 60.07 1237.93 168.54
ete of M 30 corresponding to IS 456 using WEIGH BATCHER using minimum cement
size graded machine crushed hard granite metal (coarse aggregate) from approved
ls like cement, fine aggregate (sand) coarse aggregate, water etc., to site and including
operational, incidental and labour charges such as weigh batching, machine mixing
t excluding cost of steel and its fabrication charges for finished item of work
adjastable Jack Screws, Props and Acro span beams including all pipe bracings,
s members etc., Complete, laying concrete, vibrating, curing etc. complete but excludi
d item of work. RCC BEAMS , SLAB.

CSTN-3.16)

Cum 0.56 1705.10


Cum 0.24 1437.60
Cum 0.40 268.74
MT 0.38 6600.00
KL. 1.20 103.00

1Lt. 0.304 150.00

Day 0.033 534.00


Day 0.067 480.00
Day 0.433 420.00

Cum. 0.133 539.30


340.60 Hour 0.133 68.12
Hour 0.133 1915.00
283.90 Hour 0.133 56.78
Hour 0.133 342.00
Hour 1.333 184.60

158.20 Hour 1.333 31.64

Rs.

131, Sl.No.1H)

Lift Add
Centering Charges vide Item Charges 13.615%
No.1.h, P.No.131 of SSR vide towards
P.No.131 Total contractor
M.L of 's profit &
Labour A.P.Stand O.H.
@ 20%
ard data Charges
1426.00 285.20 -- 8706.21 1185.35
1426.00 285.20 -- 8706.21 1185.35
1569.00 313.80 777.15 9654.96 1314.52
1711.00 342.20 847.84 9896.05 1347.35
1854.00 370.80 918.53 10138.34 1380.33
1996.00 399.20 989.21 10379.42 1413.16
2139.00 427.80 1059.90 10621.71 1446.15
2282.00 456.40 1130.59 10864.00 1479.13
2424.00 484.80 1201.28 11105.09 1511.96
Lift Add
ntering Charges vide Item No.1.i, Charges 13.615%
P.No.131of SSR vide towards
P.No.131 Total contractor
M.L of 's profit &
Labour
@ 20% A.P.Stand O.H.
162.00 32.40 ard --data 5414.41 Charges
737.17
178.00 35.60 5433.61 739.79
194.00 38.80 777.15 6229.96 848.21
211.00 42.20 847.84 6321.05 860.61
227.00 45.40 918.53 6410.94 872.85
243.00 48.60 989.21 6500.82 885.09
259.00 51.80 1059.90 6590.71 897.33
275.00 55.00 1130.59 6680.60 909.56
292.00 58.40 1201.28 6771.69 921.97

C roof slab surface with CM(1:3), 20mm thick with 1kg of water proof compound per
luding cost of all materials,, including conveyance charges of materials and inclu
or mixing mortar, laying, rendering smooth and thread lining, curing, rounding off junc
of work.

TN-6-8).

3607.68 0.21 3607.68


2.00 52.00

0.45 445.00
1.05 400.00
2.80 350.00
1600.25 20%
Rs.
Rs.
Lift Charges vide P.No.131 of
A.P.Standard data Add
13.615%
towards
Total contractor
's profit &
M.L O.H.
Labour @ 20% Charges

- 278.19 37.88
3.20 297.39 40.49
3.52 299.31 40.75
3.84 301.23 41.01
4.16 303.15 41.27
4.48 305.07 41.54
4.80 306.99 41.80
5.12 308.91 42.06
5.44 310.83 42.32
Steel bars (Fe 415 Grade as per IS : 1786 and as amended upto date) of different dia
to required size shapes, placing in position with cover blocks of approved materials a
SWG forming grills for reinforcement work as per approved designs and drawings in
, including all wastage such as overlaps, welded joints, chairs spacer bars including c
d all incidental, opeartional labour charges including sales and other taxes on all materia
rs (APSS No.126) (Payment will be made on the basis of weight of fabrication deform
mplete for (8 mm to 40 mm).

TN-4-2).

MT. MT 1.050
Kg 6.000

e, tying and placing in position


Nos 10.00
(P.No.08). Nos 10.00
9050.00 X 20% Nos

Add
13.615%
towards
M.L. @
Total contractor' Sundries
20%
s profit &
O.H.
Charges

- 47445.00 6459.64 0.01


181.00 48531.00 6607.50 0.00
199.10 48639.60 6622.28 0.02
217.20 48748.20 6637.07 0.03
235.30 48856.80 6651.85 0.00
253.40 48965.40 6666.64 0.01
271.50 49074.00 6681.43 0.02
289.60 49182.60 6696.21 0.04
307.70 49291.20 6711.00 0.00
Cement solid blocks of size 290 x150 x 140 mm for manufacturing of flyash solid block
m of 5 kgs. and stone dust including cost and conveyance of all materials, labour c
compressive strength not lessthan 50 kg/sqcm for walls for Superstructure Walls. For

TN-5-17).

y (As per chart) Nos. 110 20.00

2012.03 Cum 2023.68 Cum 0.10 2023.68

Day 0.42 445.00


Day 0.92 400.00
Day 0.70 350.00
Day 2.10 350.00
1,534.90 X 20%
Rs.
Rs.71.76/1Sqm.
0.150 = Rs. 66.20/Cum
0.150 = Rs412.20/Cum
Lift Add
Scaffolding Charges vide Item Charges 13.615%
No.1.a, P.No.66 of SSR vide towards
M.L P.No.131 Total contractor
Labour of 's profit &
@ 20%
A.P.Stand O.H.
0 0 ard 0data 4669.27 635.72
Charges
412.20 82.44 -- 4805.09 654.21
412.20 82.44 153.49 4958.58 675.11
585.20 117.04 168.83 5181.52 705.46
758.00 151.60 184.17 5404.22 735.78
931.33 186.27 199.51 5627.56 766.19
1104.00 220.80 214.85 5850.10 796.49
1277.33 255.47 230.19 6073.44 826.90
1450.00 290.00 245.53 6295.98 857.20
1623.33 324.67 260.87 6519.32 887.60
Cement solid blocks of size 230 x 100 x 140 mm for manufacturing of flyash solid block
m of 5 kgs. and stone dust including cost and conveyance of all materials, labour ch
compressive strength not lessthan 50 kg/sqcm for walls for Superstructure Walls. For

STN-5-17).
y (As per chart) Nos. 245 11.00
Cum 0.10 2815.68

Day 0.42 445.00


Day 0.92 400.00
Day 0.70 350.00
Day 2.10 350.00
1,534.90 X 20%
Rs.
Rs.71.76/1Sqm.
0.1 = Rs. 99.30/Cum
0.1 = Rs.618.30/Cum
Lift Add
Scaffolding Charges vide Item Charges 13.615%
No.1.a, P.No.66 of SSR vide towards
P.No.131 Total contractor
M.L of 's profit &
Labour
@ 40% A.P.Stand O.H.
ard data Charges
618.30 247.32 -- 5783.37 787.41
618.30 247.32 153.49 5936.86 808.30
877.80 351.12 168.83 6315.50 859.86
1137.00 454.80 184.17 6693.72 911.35
1397.00 558.80 199.51 7073.06 963.00
1656.00 662.40 214.85 7451.00 1014.45
1916.00 766.40 230.19 7830.34 1066.10
2175.00 870.00 245.53 8208.28 1117.56
2435.00 974.00 260.87 8587.62 1169.20
lecoat with. Screened sand with sponge finishing including cost and coneyance of all m
abour charges etc., complete for Chajjas

TN-6-2).

per mortar chart 0.15 2815.68

Day 0.45 445.00


Day 1.05 400.00
Day 2.8 350.00
Day
Lift AddRs.
234.27 Charges 13.615%
Scaffolding Charges vide Item vide towards
No.1A, P.No.67 M.L
of SSR P.No.131 Total contractor
Labour of 's profit &
@ 20%
12.55 2.51 A.P.Stand
0.00 251.70 O.H. 34.27
12.55 2.51 ard data
16.00 267.70 Charges
36.45

m thick laid over Granolithic flooring bed when it is green including cost of all ma
charges of materials and including all operational, incidental and labour charges for
lining, curing, rounding off junctions of wall and floor etc,, complete for finished item

STN-10-25). Unit = 1 sqm

Cum 0.21 3607.68

Day 0.66 420.00


Day 1.54 375.00
Day 3.70 320.00
2038.70 X 20%
Rs.
d charges Rs.
Rs.
Rs.
Rs.
Rs.
17.64 3.53 17.60 275.41 37.50
22.73 4.55 19.20 283.12 38.55
27.82 5.56 20.80 290.82 39.60
32.91 6.58 22.40 298.53 40.65
38.00 7.60 24.00 306.24 41.69
43.08 8.62 25.60 313.94 42.74
48.17 9.63 27.20 321.64 43.79
lecoat with. Screened sand with sponge finishing including cost and coneyance of all m
abour charges etc., complete for CEILING.

TN-6-1).

per mortar chart 0.15 3607.68

Day 0.45 445.00


Day 1.05 400.00
Day 2.8 350.00
Day
Lift AddRs.
246.15 Charges 13.615%
Scaffolding Charges vide Item
No.1A, P.No.67 of SSR vide towards
M.L P.No.131 Total contractor
Labour
@ 20% of 's profit &
12.55 2.51 A.P.Stand
0.00 263.58 O.H. 35.89
12.55 2.51 ard data
16.00 279.58 Charges
38.06
17.64 3.53 17.60 287.29 39.11
22.73 4.55 19.20 295.00 40.16
27.82 5.56 20.80 302.70 41.21
32.91 6.58 22.40 310.41 42.26
38.00 7.60 24.00 318.12 43.31
43.08 8.62 25.60 325.82 44.36
48.17 9.63 27.20 333.52 45.41
lecoat with. Screened sand with sponge finishing including cost and coneyance of all m
abour charges etc., complete for Internal Walls.

TN-8-2).

per mortar chart 0.15 2340.48

Day 0.45 445.00


Day 1.05 400.00
Day 2.8 350.00
Day
Lift AddRs.
259.14 Charges 13.615%
Scaffolding Charges vide Item
No.1A, P.No.67 of SSR vide towards
M.L P.No.131 Total contractor
Labour
@ 20% of 's profit &
6.18 1.24 A.P.Stand
0.00 267.55 O.H. 36.43
6.18 1.24 ard data
16.00 283.55 Charges
38.60
8.78 1.76 17.60 288.27 39.25
11.37 2.27 19.20 292.97 39.89
13.97 2.79 20.80 297.69 40.53
16.56 3.31 22.40 302.40 41.17
19.16 3.83 24.00 307.12 41.81
21.75 4.35 25.60 311.83 42.46
24.35 4.87 27.20 316.55 43.10
lecoat with. Screened sand with sponge finishing including cost and coneyance of all m
abour charges etc., complete for External Walls.

TN-8-2).

per mortar chart 0.15 2340.48

Day 0.45 445.00


Day 1.05 400.00
Day 2.8 350.00
Day
Lift AddRs.
227.14 Charges 13.615%
Scaffolding Charges vide Item
No.1A, P.No.67 of SSR vide towards
M.L P.No.131 Total contractor
Labour
@ 40% of 's profit &
0.00 0.00 A.P.Stand
0.00 227.14 O.H. 30.93
0.00 0.00 ard data
16.00 243.14 Charges
33.10
0 0.00 17.60 244.74 33.32
0 0.00 19.20 246.34 33.54
0 0 20.80 247.94 33.76
0 0 22.40 249.54 33.97
0 0 24.00 251.14 34.19
0 0 25.60 252.74 34.41
0 0 27.20 254.34 34.63
han 598 mm x 598 mm, 8 to 10 mm thick glossy finish premium colour normal colour 1s
1:8), 12mm thick over CC bed already laid or RCC roof slab, including neat cement slur
sqm & jointed neatly with white cement paste to full depth mixed with pigment of match
of all materials like cement, sand water and tiles etc., complete, for finished item of wor

TN-9-5). Unit = 1 Sqm

Sqm 10.50 940.00


MT 0.02 6600.00
0.03 6600.00
0.12 338.74
154 Page No.64). Kg 2.00 29.00

Day 0.96 445.00


Day 2.24 400.00
Day 3.30 350.00
2299.2 X 0.25
Rs.
13203.01
Rs.
Rs.

towards
M.L
TOTAL contractor' Total
@ 20%
s profit &
0 1333.50 181.56 1515.06
4.60 1361.09 185.31 1546.40
5.06 1363.84 185.69 1549.53
5.51 1366.59 186.06 1552.65
5.97 1369.34 186.44 1555.77
6.43 1372.08 186.81 1558.89
6.89 1374.83 187.18 1562.02
7.35 1377.58 187.56 1565.14
7.80 1380.33 187.93 1568.26

height/risers of steps with vitrified tiles length equal to flooring stones, set over base
honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with white
to full depth, including cost of all materials like tiles, cement, sand and water etc., comp

STN-9-20). Unit = 1 Sqm

Sqm 10.5 940.00


MT 0.03456 6600.00
MT 0.033 6600.00
0.12 338.74
154 Page No.64). Kg 2.00 29.00

Day 0.96 445.00


Day 2.24 400.00
Day 3.30 350.00
2478.20 X 20%
Rs.
13388.39
Rs.
Rs.
Lift Charges vide
P.No.131 of Add
A.P.Standard data 13.615%
towards
TOTAL contractor' Total
s profit &
O.H.
Charges
Add
13.615%
towards
M.L TOTAL contractor' Total
@ 20% s profit &
O.H.
Charges
-- 1352.23 184.11 1536.34
4.96 1381.97 188.15 1570.12
5.45 1384.93 188.56 1573.49
5.94 1387.89 188.96 1576.86
6.44 1390.86 189.37 1580.22
6.93 1393.82 189.77 1583.59
7.43 1396.79 190.17 1586.96
7.92 1399.75 190.58 1590.33
8.41 1402.71 190.98 1593.69
.3mm thick of 1st quality of all shades set over base coat of cement mortar (1:8), 12 m
including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm &
mixed with pigment of matching shade, including cost of all materials like cement, san
ork.

Sqm 10.50 465.00


MT 0.0216 6600.00
MT 0.033 6600.00
0.12 338.74
154 Page No.64). Kg 2.00 29.00

Day 0.96 445.00

Day 2.24 400.00


Day 3.30 350.00
2478.20 X 20%
Rs.
8315.35
Rs.
Rs.
Lift Charges vide
P.No.131 of Add
A.P.Standard data 13.615%
towards
M.L TOTAL contractor' Total
@ 20% s profit &
O.H.
Charges
-- 839.85 114.35 954.20
4.96 869.59 118.39 987.98
5.45 872.55 118.80 991.35
5.94 875.51 119.20 994.72
6.44 878.48 119.60 998.08
6.93 881.44 120.01 1001.45
7.43 884.41 120.41 1004.82
7.92 887.37 120.82 1008.19
8.41 890.33 121.22 1011.55

plain coloured tiles of 5 to 7 mm thick of any size cement base in C.M.(1:3) Prop. an
e rate of 3.30 Kgs. cement per Sq.mt. mixed with pigment of matching shade of tiles in
the department for finished of work inclusive of all taxes for

o 7mm thick)
Sqm 10.5 691.00
MT 0.0576 6600.00
0.033 6600.00
0.12 338.74
Sl.No.1154 Page No.64). Kg 6.00 29.00

Day 0.77 445.00


Day 0.80 350.00
622.65 X 20%
Rs.
8815.29
Rs.
Rs.
Lift Charges vide
P.No.131 of Add
A.P.Standard data 13.615%
towards
M.L TOTAL contractor' Total
@ 20% s profit &
O.H.
Charges
-- 890.34 121.22 1011.56
1.24 897.80 122.24 1020.04
1.37 898.55 122.34 1020.89
1.49 899.29 122.44 1021.73
1.62 900.04 122.54 1022.58
1.74 900.78 122.64 1023.42
1.86 901.52 122.74 1024.27
1.99 902.27 122.84 1025.11
2.11 903.01 122.95 1025.96
om section made of galvanized steel powder coated (base steel as per IS 513,galvan
ter). The factory made section should be with a powder coating of pure polyester powde
of 1.25 mm. Size of door frame section should be of 105 x 60 mm with a rebate of 38
groove to insert gasket in the frame section, frame section to be filled with polyurethan
nd joined by way be way of welding. Each frame should be provided with : 2mm th
-3 Nos. for single shutter, 6Nos. double shutter. CRCA Electroplates stiffeners of 6 No
x 200 mm x 1.2 mm hold fasts screwed to stiffeners - 6Nos. with split end tail. Nylon
od 1 No. DOOR FRAME FOR WITH OUT SILL OF SIZE 0.91X1.98 M.

Unit- Each

Rmt 4.75 759.00


0.91 = 0.91

Rs.
d charges Rs.
Rs.
Rs.

om section made of galvanized steel powder coated (base steel as per IS 513,galvan
ter). The factory made section should be with a powder coating of pure polyester powde
of 1.25 mm. Size of door frame section should be of 105 x 60 mm with a rebate of 38
groove to insert gasket in the frame section, frame section to be filled with polyurethan
nd joined by way be way of welding. Each frame should be provided with : 2mm th
-3 Nos. for single shutter, 6Nos. double shutter. CRCA Electroplates stiffeners of 6 No
x 200 mm x 1.2 mm hold fasts screwed to stiffeners - 6Nos. with split end tail. Nylon
od 1 No. DOOR FRAME FOR WITH SILL OF SIZE 0.91X1.98 M.

Unit- Each
Rmt 5.66 759.00
0.91 = 1.82

Rs.
d charges Rs.
Rs.
Rs.

om section made of galvanized steel powder coated (base steel as per IS 513,galvan
ter). The factory made section should be with a powder coating of pure polyester powde
of 1.25 mm. Size of door frame section should be of 105 x 60 mm with a rebate of 38
groove to insert gasket in the frame section, frame section to be filled with polyurethan
nd joined by way be way of welding. Each frame should be provided with : 2mm th
-3 Nos. for single shutter, 6Nos. double shutter. CRCA Electroplates stiffeners of 6 No
x 200 mm x 1.2 mm hold fasts screwed to stiffeners - 6Nos. with split end tail. Nylon
od 1 No. DOOR FRAME FOR WITH SILL OF SIZE 0.76X1.98 M.

Unit- Each

Rmt 5.42 759.00


0.76 = 1.52

Rs.
d charges Rs.
Rs.

Rs.
hutter of 30 mm thick with solid bond wood black board type including commercial ply
of M.S.Powder coated make of 1 No. 250 mm long aldrop, 1 No. of 200 mm long aldrop
andle including cost and conveyance of all materials and labour charges etc., complete
r DOOR OF SIZE: 0.91 X 1.98 Mts.

Sqm 1.65

ed Aldrop Nos 1.00

at Aldrop Nos 1.00

der coated Nos 1.00

Nos 1.00

Sqm 1.650

d charges
flushdoor shutter of solid bond wood black board type 30mmthick conforming to
of fixtures of M.S.Powder coated 1 No. 250 mm long aldrop, 1 No. of 200 mm long a
g handle including cost and conveyance of all materials and labour charges etc., comp
nt for DOOR OF SIZE: 0.76 X 1.98 Mts.

Sqm 1.36

ed Aldrop Nos 1.00

at Aldrop Nos 1.00

der coated Nos 1.00

Nos 1.00

Sqm 1.365

d charges

ushdoor shutter of solid bond wood black board type with teak piy on both faces 35m
h faces including cost of fixtures of M.S.Powder coated 1 No. 250 mm long aldrop, 1
r blot, 1 No. 125 mm long handle including cost and conveyance of all materials and
s directed by the department for DOOR OF SIZE: 0.91 X 1.98 Mts.
Sqm 1.36

ed Aldrop Nos 1.00

at Aldrop Nos 1.00

der coated Nos 1.00

Nos 1.00

Sqm 1.365

d charges
ade from extruded sections in over all dimentions of 40 x 48mm having wall thickness
mm complete and Sintex door shutter made from specially Hot Press Moulded SMC
core and PVC Frame Section SMS sheets shall be made from SMC comforming to IS
1.4 mm +0.35 mm on both sides. Core of the door shutter shall be filled with high
f hydraulic injection method shutter frame to be made of PVC extruded section confir
a wall thickness of 1.4 mm +0.3mm on both sides corresponding to sintex code DWU
with special polymeric reinforcement wooden blocks of suitable size. The corners of the
haped angle of size 105 mm x 230 mm corresponding to Sintex code PR-02 the lock r
g overall dimensions of 26 mm x 46 mm 1.5 mm +0.3mm on both sides, with usual p
combining two numbers. Wooden pieces are inserted on the periphery. Suitable M
des of shutter frame the rate inclusive of all taxes and finished item work Color: White
THICK).

Unit - Each

Rmt 4.42

Sqm 1.39

200mm long) Nos 1.00

No.240) Nos 1.00

(IS208) Nos 2.00

Nos 3.00

d charges
Windows with fly mesh made of pre-painted steel (Base steel as per IS 513 of 0.80 mm
SM), finish painted with a polyester paint of 60-65 microns thick and section for outer fra
, section for shutter of 52 x 25 mm x 0.6 mm thick, section for flyshutter of 52 x 25 mm x
uge fly mesh of 304 grade with 144 holes per sq.inch and mullions to have double rebat
for guard bars/grills and the sections cut to length metre joined with corner bracket, cen
grade nylon latch handle, window stopper, 2 nos. of with MS Powder coated /SS ball bea
s fitted with 4 mm thick plain float glass with rubber gaskets including fixing the frames in
nding screws, Including 10 mm Square guard bars with 6 (152.4mm) pitch etc., comple

O.H.Charges

O.H.Charges
O.H.Charges

O.H.Charges
ade of pre-painted steel (Base steel as per IS 513 of 0.80 mm thick galvanized as per IS
olyester paint of 60-65 microns thick and section for outer frame of 80 x 45 mm, centre
mm x 0.6 mm thick, outer frame and mullions to have rebate for glazed shutter with a pr
ngth metre joined with corner bracket, centre mullion fixed with mullion cap, 1 No. of Hig
nos. of with MS Powder coated /SS ball bearing butt Hinges provided per shutter and wi
bber gaskets including fixing the frames in concrete/masonry wall by means of self expa
with 6 (152.4mm) pitch etc., complete for finished item of work., Single openable ventila
outer frame section size of 80 x 45mm, shutter for 0.76X0.61Mt size

O.H.Charges

cement or polymer or cement based of average 1 to 2mm thickness over plastered su


throughly brushing the surface to remove all dirt and remains of loose powdered ma
an & wipe off loose dust ,applying knifing paste filler putty knife/muslin pad ,air dry for
the surface preparation including cost and conveyance of all matrials to work site a
plete for finished item of work for internal walls.

Kg 23.00 43.75

Nos 0.273 510.00


Nos 0.637 400.00
Nos 0.91 350.00
712.53 X 20%
Rs.
O.H.Charges Rs.
Rs.
te per 1 Sqm Rs.
Rs.
Rs.

roof cement paint interior grade-I of approved brand and shade over a base coat of ap
to give an even shade after throughly brushing the surface to remove all dirt and rem
all operational, incidental, labour charges etc., complete for finished item of work as per

Kg 1.00 165.00
day 0.21 510.00
day 0.49 400.00
303.10 X 20%
igh UV Resistant exterior paint
Kg 3.50 52.00
ate 1300/25 = 52.00/-) Kg
day 0.15 510.00
day 0.35 400.00
day 1.50 350.00
741.50 X 20%
Rs.
d charges Rs.
Rs.
te per 1 Sqm Rs.
Rs.
Rs.
ased cement primer of exteriorgrade -II paint of approved brand and shade over a base
coats in all to give an even shade after throughly brushing the surface to remove all d
k site and all operational, incidental, labour charges etc., complete for finished item of w

data no.172 p.no.81

No.488, P.No.38) kg 1 210.00


day 0.21 510.00
day 0.49 400.00
303.10 X 20%
uivalentexterior texture kg 3.50 40.00
ate 1000/25 = 40.00/-) Kg
day 0.15 510.00
day 0.35 400.00
day 1.50 350.00
741.50 X 20%
Rs.
d charges Rs.
Rs.
te per 1 Sqm Rs.

Rs.

Cm. pressure P.V.C.Pipe of Prince / Sudhakar make from roof up to basement level in
d fixed to wall with pipe clips including labour charges etc., complete for RAIN WATER P

84/3 = 161.33) Rmt 1.00 161.33


(18.00/2) No. 1.00 9.00
Rmt 1 70.00
Rs.
d charges Rs.
Rs.
hed Black Grainte stone slab with C.M.(1-1/2:1) prop. Putty to full depth including co
form with machine finishing on all sides and rounding of corners suitable hole for g

nte stone Ra 2352.00/Sqm

19.53/1 Cum

3.00 445.00 1335.00

1.00 400.00 400.00


8.00 350.00 2800.00
907.00
5442.00

O.H.Charges

ack Granite Stone of thick 16 to 18 mm sink thick of size 24" x 18" x 10" with a hole at
veyance of all materials , labour charges , curing etc complete.
s.2352.00

RM x 289.00/1RM
119 at Rs.15.00/1RM 2.44*15

O.H.Charges

evels) polyethylene water storage tank with double layer approved brand & manufacture
aking necessary holes for inlet & outlets and over flow pipes but without fittings & base

O.H.Charges

k in two coats with synthetic enamel paint of approved colour, over one coat of prima
s, incidental charges such as sand paper, cleaning the surface, cost of brushes and pu
Lit 0.70

Nos 0.70

00% on Rs.460.60

m No.516 Lit 1.20

Lit 1.20

d charges

h (1:1:2) using 6mm to 12 mm size hard granite metal laid over CC bed already laid
ceeding 1.5Mt x 1.5Mt. and finishing the top surface to required slopes including cos
etc., complete for finished item of work.

STN-9-13). Unit 1Sqm.

/2 1256.35 Cum 0.17 1256.35


Cum 0.085 338.74
MT 0.12 6600.00
Day 1.25 445.00
Day 0.06 400.00
Day 3.00 350.00
1630.25 X 20%

d charges Rs.
Rs.

Rs.
Rs.
Rs.

0.00 343.18 46.72


stone other than granite including cost and conveyance of all materials, labour charges
MENT.

age No.39 & 40) Unit - 1 Cum.

MT 0.0594
Cum 0.94
Cum 0.16
Cum 0.33

Day 1.2
2
1234 X 20%

d charges
cluding all operational, incidental,
work .in ordinary soils by manual

king output : 10 Cum)

1820.00

1365.00
3185.00
433.64
3618.64
361.86
0.04
361.90

king output : 10 Cum)


1820.00
247.79
2067.79
206.78
0.02
206.80

eading sectioning,
tandered specification including

152.88

31.50
22.61

206.99
28.18
235.17
0.03
235.20
uding cost and conveyance of all

Unit = 1 cum

1069.20
1066.59
120.94
123.60

352.50

43.94

53.40
583.80
3413.96
464.81
0.02
3878.79
ATCHER using minimum cement
oarse aggregate) from approved
e, water etc., to site and including,
batching, machine mixing, laying
hed item of work (APSS No.402
e bracings, clamps couplings pre
but excluding cost of steel and its

Unit = 1 cum

954.85
345.02
107.50
2508.00
123.60

45.60

29.90
26.88
385.14

119.72
15.12

425.13
12.61
75.92
246.07

42.18
0.04
5463.29
5463.29
750.00

94.60
6307.89
858.82
0.03
7166.74

5463.29
1068.00

150.60
6681.89
909.74
0.01
7591.64

5463.29
2476.00

228.20
8167.49
1112.00
0.00
9279.49
ATCHER using minimum cement
oarse aggregate) from approved
, water etc., to site and including,
batching, machine mixing, laying
hed item of work (APSS No.402)
e bracings, clamps couplings pre
but excluding cost of steel and its
LDINGS.

Unit 1 Cum

954.85
345.02
107.50
2508.00
123.60

45.60

59.27
106.56
653.52

239.45
30.25

850.26
25.21
151.85
246.07
42.18
0.01
6489.20

6158.78

Sundires Amount

0.00 9935.61
0.00 9935.61
0.01 10983.55
0.03 11228.85
0.01 11474.11
0.04 11719.42
0.00 11966.02
0.03 12211.34
0.01 12456.60
6489.20

Sundires Amount

0.04 10077.92
0.04 10077.92
0.04 11192.65
0.00 11504.70
0.02 11816.80
0.03 12128.90
0.00 12440.96
0.01 12753.06
0.03 13065.16
6158.78

Sundires Amount

0.00 9935.61
0.00 9935.61
0.02 10983.56
0.04 11228.86
0.01 11474.11
0.02 11719.40
0.02 11966.04
0.00 12211.31
0.04 13449.30

uding cost and conveyance of all

Unit - 1 Cum

855.36
1066.59
120.94
123.60
352.50

43.94

53.40

583.80
3200.12
435.70
0.02
3635.84

HER of 0.50 Cum (6.00cum / Hr)


shed hard granite metal (coarse
e (sand) coarse aggregate, water
d labour charges such as weigh
ation charges for finished item of
eams including all pipe bracings,
c. complete but excluding cost of

Unit -1 Sqm.

per Sqm
307.94

Sundires Amount

0.04 1143.96
0.04 1143.96
0.00 1213.98
0.03 1242.56
0.04 1289.56
0.02 1318.09
0.02 1348.01
0.03 1377.94
0.00 1406.47
R using minimum cement content
aggregate) from approved quarry
r etc., to site and including, sales
batching, machine mixing, laying
finished item of work (APSS
cluding all pipe bracings, clamps
etc. complete but excluding cost

Unit 1 Cum

954.85
345.02
107.50
2508.00
123.60

45.60

17.62
32.16
181.86

71.73
9.06
254.70
7.55
45.49
246.07

42.18
0.03
4993.01

Rs. 4993.01

Sundires Amount

0.03 9891.59
0.03 9891.59
0.01 10969.49
0.00 11243.40
0.02 11518.69
0.02 11792.60
0.04 12067.90
0.01 12343.14
0.00 12617.05
Sundires Amount

0.01 6151.59
0.01 6173.41
0.04 7078.21
0.00 7181.66
0.02 7283.81
0.03 7385.94
0.03 7488.07
0.00 7590.16
0.01 7693.67

water proof compound per bag of


es of materials and including all
curing, rounding off junctions of

Unit = 1 Sqm

757.61
104.00

200.25
420.00
980.00
320.05
2781.91
278.19
Sund -
Amount
ries

- 316.07
0.04 337.92
- 340.06
0.02 342.26
0.04 344.46
0.01 346.62
0.03 348.82
- 350.97
0.02 353.17
upto date) of different diameters
s of approved materials and size
d designs and drawings including
s spacer bars including cost and
d other taxes on all materials etc.,
ght of fabrication deformed bars

Unit -1MT

34500.00 36225.00
60.00 360.00

555.00 5550.00
350.00 3500.00
Rs. 1810.00
Rs. 47445.00

Amount

53904.65
55138.50
55261.90
55385.30
55508.65
55632.05
55755.45
55878.85
56002.20
uring of flyash solid blocks using
of all materials, labour charges,
Superstructure Walls. For Super

Unit = 1 cum

2,200.00
-
202.37
-
186.90
368.00
245.00
735.00
306.98
4,244.25

Sundires Amount

0.01 5305.00
0.02 5459.32
0.03 5633.72
0.03 5887.01
0.01 6140.01
0.02 6393.77
0.03 6646.62
0.03 6900.36
0.04 7153.22
0.00 7406.92
turing of flyash solid blocks using
of all materials, labour charges,,
uperstructure Walls. For Partion

Unit = 1 cum
2,695.00
281.57
-
186.90
368.00
245.00
735.00
306.98
4,818.45

Sundires Amount

0.04 6570.82
0.00 6745.16
0.01 7175.37
0.00 7605.07
0.01 8036.07
0.01 8465.46
0.03 8896.47
0.03 9325.87
0.04 9756.86
st and coneyance of all meterials

422.35

200.25
420.00
980.00
320.05
2342.65

Sundires Amount

0.01 285.98
0.03 304.18

n including cost of all materials,


al and labour charges for mixing
omplete for finished item of work

757.61

277.20
577.50
1184.00
407.74
3204.05
436.23
3640.29
364.03
0.04
364.07
0.02 312.92
0.02 321.68
0.01 330.43
0.00 339.18
0.04 347.97
0.00 356.68
0.04 365.48
st and coneyance of all meterials

541.15

200.25
420.00
980.00
320.05
2461.45

Sundires Amount

0.01 299.48
0.03 317.67
0.03 326.43
0.02 335.18
0.01 343.93
0.00 352.67
0.00 361.43
0.00 370.18
0.04 378.97
st and coneyance of all meterials

351.07

200.25
420.00
980.00
640.10
2591.42

Sundires Amount

0.04 304.01
0.02 322.17
0.00 327.51
0.00 332.86
0.04 338.27
0.04 343.61
0.03 348.97
0.03 354.32
0.02 359.67
st and coneyance of all meterials

351.07

200.25
420.00
980.00
320.05
2271.37

Sundires Amount

0.01 258.08
0.03 276.27
0.02 278.08
0.00 279.88
0.03 281.73
0.01 283.52
0.04 285.37
0.03 287.18
0.01 288.98
m colour normal colour 1st
ncluding neat cement slurry of
xed with pigment of matching
e, for finished item of work.

9870.00
142.56
217.80
40.65
58.00

403.20
840.00
1056.00
574.80
13203.01
132.03
13335.04
1333.50

Sund -
Amount
ries
0.02 1515.08
0.02 1546.42
0.00 1549.53
0.03 1552.68
0.01 1555.78
0.04 1558.93
0.01 1562.03
0.04 1565.18
0.02 1568.28

ing stones, set over base coat of


m and jointed with white cement
sand and water etc., complete for

9870.00
228.10
217.80
40.65
58.00

427.20
896.00
1155.00
495.64
13388.39
133.88
13522.27
1352.23

Sund -
Amount
ries
Sund -
Amount
ries

0.04 1536.38
0.01 1570.13
0.04 1573.53
0.02 1576.88
0.00 1580.22
0.04 1583.63
0.02 1586.98
0.00 1590.33
0.03 1593.72
cement mortar (1:8), 12 mm thick
ad @ 3.3.kgs per sqm & jointed
materials like cement, sand water

Unit = 1 sqm

4882.50
142.56
217.80
40.65
58.00

427.20

896.00
1155.00
495.64
8315.35
83.15
8398.50
839.85

Sund -
Amount
ries

0.04 954.24
0 987.98
0.04 991.39
0.03 994.75
0.04 1042.55
0.04 1046.20
0.01 1049.80
0.00 1053.50
0.03 1057.10

base in C.M.(1:3) Prop. and neat


matching shade of tiles including

Unit = 1 sqm

7255.50
380.16
217.80
40.65
174.00

342.65
280.00
124.53
8815.29
88.15
8903.44
890.34
Sund -
Amount
ries

0.02 1011.58
0.04 1020.08
0.04 1020.93
0 1021.73
0.00 1022.58
0.01 1023.43
0.01 1024.28
0.02 1025.13
0.02 1025.98
teel as per IS 513,galvanized as
g of pure polyester powder of 50-
60 mm with a rebate of 38mm to
be filled with polyurethane foam.
e provided with : 2mm thick MS
roplates stiffeners of 6 Nos. -3 in
. with split end tail. Nylon Aldrop
1X1.98 M.

3605.25

3605.25
490.85
0.00
4096.10

teel as per IS 513,galvanized as


g of pure polyester powder of 50-
60 mm with a rebate of 38mm to
be filled with polyurethane foam.
e provided with : 2mm thick MS
roplates stiffeners of 6 Nos. -3 in
. with split end tail. Nylon Aldrop
8 M.
4295.94

4295.94
584.89
0.02
4880.85

teel as per IS 513,galvanized as


g of pure polyester powder of 50-
60 mm with a rebate of 38mm to
be filled with polyurethane foam.
e provided with : 2mm thick MS
roplates stiffeners of 6 Nos. -3 in
. with split end tail. Nylon Aldrop
98 M.

4113.78

4113.78
560.09
0.03

4673.90
including commercial ply of 3mm
No. of 200 mm long aldrop, 1 No.
our charges etc., complete as per

Unit :: Each

1314.00 2168.10

151.00 151.00

115.00 115.00

56.00 56.00

34.00 34.00

348 574.20

Rs. 114.84
Rs. 3213.14
Rs. 437.47
0.02
Rs. 3650.63
0mmthick conforming to IS2202
, 1 No. of 200 mm long aldrop, 1
labour charges etc., complete as

Unit :: Each

1314.00 1787.04

151.00 151.00

115.00 115.00

56.00 56.00

34.00 34.00

348 475.02

Rs. 95.00
Rs. 2713.06
Rs. 369.38
0.05
Rs. 3082.50

eak piy on both faces 35mmthick


o. 250 mm long aldrop, 1 No. of
yance of all materials and labour
Mts.
Unit :: Each

2188.00 3625.51

151.00 151.00

115.00 115.00

56.00 56.00

34.00 34.00

348 475.02

Rs. 95.00
Rs. 4551.53
Rs. 619.69
0.02
Rs. 5171.25
mm having wall thickness of 1.55
Hot Press Moulded SMC (Sheet
om SMC comforming to IS 13410
shall be filled with high density
C extruded section confirming to
nding to sintex code DWUF 305.
e size. The corners of the shutter
tex code PR-02 the lock rail shall
n both sides, with usual process
he periphery. Suitable MS Tube
d item work Color: White & Grey.

244.00 1078.48

3162.00 4395.18

329.00 329.00

141.00 141.00

126.00 252.00

132.00 396.00

Rs. 6591.66
Rs. 897.45
0.04
Rs. 7489.15

as per IS 513 of 0.80 mm thick


k and section for outer frame of
flyshutter of 52 x 25 mm x 0.6
ions to have double rebate for
ed with corner bracket, centre
owder coated /SS ball bearing
cluding fixing the frames in
2.4mm) pitch etc., complete for

Rs. 10518.67

Rs. 10518.67
Rs. 1432.12
Rs. 0.06
Rs. 11950.85

RS 7846.59

Rs. 7846.59
Rs. 1068.31
0.00
Rs. 8914.90
RS 5020.51

Rs. 5020.51
Rs. 683.54
0.00
Rs. 5704.05

RS 3745.14

Rs. 3745.14
Rs. 509.90
0.01
Rs. 4255.05
m thick galvanized as per IS 277
me of 80 x 45 mm, centre mullion
or glazed shutter with a provision
h mullion cap, 1 No. of High
rovided per shutter and windows
wall by means of self expanding
k., Single openable ventilator
Mt size

RS 2830.28

Rs. 2830.28
Rs. 385.34
0.03
Rs. 3215.65

ickness over plastered surface to


ns of loose powdered materials,
ife/muslin pad ,air dry for 2-3 hrs
all matrials to work site and all

Unit = 1 Sqm

1006.25

139.23
254.80
318.50
142.51
1861.29
253.41
2114.70
211.47
0.03
211.50

de over a base coat of approved


to remove all dirt and remains of
ished item of work as per SS 912

Unit : 1 Sqm.
165.00
107.10
196.00
60.62
182.00

76.50
140.00
525.00
148.30
1600.52
217.91
1818.43
181.84
0.01
181.85
nd and shade over a base coat of
he surface to remove all dirt and
mplete for finished item of work as

Unit : 1 Sqm.
210.00
107.10
196.00
60.62
140.00

76.50
140.00
525.00
148.30
1603.52
218.32
1821.84
182.18
1.88
184.06

of up to basement level including


mplete for RAIN WATER PIPE.

Unit - 1Rmt

161.33
9.00
70.00
240.33
32.72
273.05
y to full depth including cost and
orners suitable hole for gas pipe

Unit : 1 Sq.mt
Rs. 2469.60

Rs. 34.01

Rs. 21.78
Rs. 17.40

Rs. 544.20
Rs. 3086.99
Rs. 420.29
Rs. 0.97
Rs. 3508.25

x 18" x 10" with a hole at bottom


e.

Unit: Each
Rs. 2422.56

Rs. 705.16
36.60
Rs. 300.00

Rs. 3464.32
Rs. 471.66
Rs. 0.02
Rs. 3936.00

ved brand & manufacture with


ut without fittings & base

Unit 1 Each
Rs 4000.00

Rs. 544.60
Rs. 0.00
Rs. 4544.60

ur, over one coat of primary coat


e, cost of brushes and putty etc.,

Unit : 1 Sqm.
158.00 110.60

400.00 280.00
Rs. 56.00
Rs. 4.60

276 331.20

400.00 480.00
96.00
Rs. 1358.40
Rs. 184.95
Rs. 1543.35
Rs. 154.33
0.02
Rs. 154.35

over CC bed already laid or RCC


uired slopes including cost of all

213.58
28.79
792.00
556.25
24.00
1050.00
326.05
2990.67
407.18
3397.85
339.79
3.40
0.00
343.18

0.02 389.92
materials, labour charges, curing

6600 392.04
520.10 488.89
520.10 83.22
268.74 88.69

445 534.00
350 700.00
246.80
2533.63
344.95
0.02
2878.60
ABSTRACT ESTIMATE
Name of the Work: Construction of G+3 houses for
No. of blocks
Unit cost for each flat =Rs
SNo. Qty Description of Item
Earth work excavation for foundations and depositing
on bank for all lifts and with an initial lead of 10m
including all operational, incidental, labour charges
such as shoring incidental, sheeting, planking,
1 454.61
strutting, etc. complete for finished item of work .in
ordinary soils by manual means upto 3.00mt depth
excluding dewatering charges etc. as per SS- 20 B
(APSS 308).

Sand for filling excluding cost seignorage and


conveyance of all materials and labour charges filling
2 56.25
spreading sectioning, watering and ramming etc
complete as per SS Under Footings and Flooring

Filling in Basements with carrted earth from


approved source to site for leveling the road portions
3 462.14 as per standered specification including cost and
conveyance of all material and labour charges etc.,
complete.

Laying PCC work of mix (1 : 4 : 8) prop. Using 40 mm


gauge hard granite machine crushed metal including
4 51.53 cost and conveyance of all materials, machine
mixing, labour charges, tamping, curing, taxes etc.,
complete for foundations.
Supply and placing of the Design Mix Concrete of
grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380 Kg.
per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate ( sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
5 66.84
mixing, laying concrete, Vibrating, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402 including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work.For
FOOTINGS (Below Plinth).
Supply and placing of the Design Mix Concrete of
grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380 Kg.
per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate ( sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
6 7.59
mixing, laying concrete, Vibrating, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402 including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work. For
PEDESTALS (Below Plinth).
Supply and placing of the Design Mix Concrete of
grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380 Kg.
per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate ( sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
7 21.49
mixing, laying concrete, Vibrating, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402 including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work. For
Pinth Beams
Supply and placing of the Design Mix Concrete of
grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380 Kg.
per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
8 labour charges such as weigh batching, machine
mixing, laying concrete, vibrating, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402) including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for steps

1.62 Ground floor


1.62 First Floor
1.62 2nd Floor
1.62 3rd Floor
1.62 4th Floor
Supply and placing of the Design Mix Concrete of
grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380 Kg.
per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
9
mixing, laying concrete, vibrating, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402) including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work.
COLUMNS,
19.92 Ground Floor
13.71 First Floor
13.71 2nd Floor
13.71 3rd Floor
2.32 4th Floor Head Room
Supply and placing of the Design Mix Concrete of
grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380 Kg.
per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
10 labour charges such as weigh batching, machine
mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for
finished item of work (APSS No.402) including
centering shuttering using adjastable Jack Screws,
Props and Acro span beams including all pipe
bracings, clamps couplings pre fabricated steel H-
frames, cross members etc., Complete, laying
concrete, curing etc. complete but excluding cost of
steel and its fabrication charges for finished item of
work.. For Lintels

a 1.55 Ground Floor


b 1.55 First Floor
c 1.55 2nd Floor
d 1.55 3rd Floor

Laying PCC work of mix (1 : 5 : 10) prop. Using 40


mm gauge hard granite machine crushed metal
including cost and conveyance of all materials,
11 machine mixing, labour charges, tamping, cruing
charges, taxes etc., complete for flooring concrete

20.93 Ground Floor


Supply and placing of the Design Mix Concrete of
grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380 Kg.
per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
12 labour charges such as weigh batching, machine
mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for
finished item of work (APSS No.402) including
centering shuttering using adjastable Jack Screws,
Props and Acro span beams including all pipe
bracings, clamps couplings pre fabricated steel H-
frames, cross members etc., Complete, laying
concrete, curing etc. complete but excluding cost of
steel and its fabrication charges for finished item of
work. CHAJJAS.

a 9.83 Ground Floor


b 9.83 First Floor
c 9.83 2nd Floor
d 9.83 3rd Floor
Supply and placing of the Design Mix Concrete of
grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380 Kg.
per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
13 labour charges such as weigh batching, machine
mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for
finished item of work (APSS No.402) including
centering shuttering using adjastable Jack Screws,
Props and Acro span beams including all pipe
bracings, clamps couplings pre fabricated steel H-
frames, cross members etc., Complete, laying
concrete, curing etc. complete but excluding cost of
steel and its fabrication charges for finished item of
work for Lofts & Racks.

For Lofts
a 47.14 Ground Floor
b 47.14 First Floor
c 47.14 2nd Floor
d 47.14 3rd Floor
For Racks
a 70.06 Ground Floor
b 70.06 First Floor
c 70.06 2nd Floor
d 70.06 3rd Floor
Supply and placing of the Design Mix Concrete of M
30 corresponding to IS 456 using WEIGH BATCHER
using minimum cement content of 380 Kg. per Cum
with 12mm and 20mm size graded machine crushed
hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials
like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including, sales & other taxes
on all materials including all operational, incidental
and labour charges such as weigh batching, machine
14
mixing, laying concrete, vibrate, curing etc.,complete
but excluding cost of steel and its fabrication charges
for finished item of work (APSS No.402)including
centering shuttering using adjastable Jack Screws,
Props and Acro span beams including all pipe
bracings, clamps couplings pre fabricated steel H-
frames, cross members etc., Complete, laying
concrete, vibrating, curing etc. complete but
excluding cost of steel and its fabrication charges for
finished item of work. RCC ROOF BEAMS

22.63 Ground floor


22.63 First Floor
22.63 2nd Floor
22.63 3rd Floor
1.06 4th floorHead room
Supply and placing of the Design Mix Concrete of M
30 corresponding to IS 456 using WEIGH BATCHER
using minimum cement content of 380 Kg. per Cum
with 12mm and 20mm size graded machine crushed
hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials
like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including, sales & other taxes
on all materials including all operational, incidental
and labour charges such as weigh batching, machine
15
mixing, laying concrete, vibrate, curing etc.,complete
but excluding cost of steel and its fabrication charges
for finished item of work (APSS No.402)including
centering shuttering using adjastable Jack Screws,
Props and Acro span beams including all pipe
bracings, clamps couplings pre fabricated steel H-
frames, cross members etc., Complete, laying
concrete, vibrating, curing etc. complete but
excluding cost of steel and its fabrication charges for
finished item of work. RCC ROOF SLABS

31.10 Ground floor


31.10 First Floor
31.10 2nd Floor
31.10 3rd Floor
3.02 4th floorHead room
Supply and placing of the Design Mix Concrete of M
30 corresponding to IS 456 using WEIGH BATCHER
using minimum cement content of 380 Kg. per Cum
with 12mm and 20mm size graded machine crushed
hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials
like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including, sales & other taxes
on all materials including all operational, incidental
and labour charges such as weigh batching, machine
16
mixing, laying concrete, vibrate, curing etc.,complete
but excluding cost of steel and its fabrication charges
for finished item of work (APSS No.402)including
centering shuttering using adjastable Jack Screws,
Props and Acro span beams including all pipe
bracings, clamps couplings pre fabricated steel H-
frames, cross members etc., Complete, laying
concrete, vibrating, curing etc. complete but
excluding cost of steel and its fabrication charges for
finished item of work.. For Waist Slabs

a 1.89 Ground Floor


b 1.89 First Floor
c 1.89 2nd Floor
d 1.89 3rd Floor
e 1.89 4th Floor
Providing impervious coat to exposed RCC roof slab
surface with CM(1:3), 20mm thick with 1kg of water
proof compound per bag of cement laid over roof
when it is green including cost of all materials,,
17 346.50 including conveyance charges of materials and
including all operational, incidental and labour
charges for mixing mortar, laying, rendering smooth
and thread lining, curing, rounding off junctions of
wall and slab etc,, complete for finished item of work

Providing High Yield Strength Deformed Steel bars


(Fe 415 Grade as per IS : 1786 and as amended
upto date) of different diameters including labour
charges for cutting bending to required size shapes,
placing in position with cover blocks of approved
materials and size and tying firmly with M.S. Binding
wire of 20 SWG forming grills for reinforcement work
as per approved designs and drawings including cost
and conveyance of deformed steel bars, including all
18
wastage such as overlaps, welded joints, chairs
spacer bars including cost and conveyance of
binding wire cover blocks and all incidental,
opeartional labour charges including sales and other
taxes on all materials etc., complete for finished item
of work in all floors (APSS No.126) (Payment will be
made on the basis of weight of fabrication deformed
bars only) (No re-rolled steel shall be allowed)
complete for (8 mm to 40 mm).

a 13.33 Ground Floor


b 5.84 First Floor
c 5.84 2nd Floor
d 5.84 3rd Floor
e 0.65 4th Floor

Masonry work in CM (1:6) prop with Flyash Cement


solid blocks of size 290 x 150 x 140 mm for
manufacturing of flyash solid blocks using flyash of
80 kgs, cement of 15 kgs.Gypsum of 5 kgs. and
19 stone dust including cost and conveyance of all
materials, labour charges, , scaffolding and curing
etc., complete with a compressive strength not
lessthan 50 kg/sqcm for walls for Foundations and
Superstructure Walls.

59.96 Below PB
60.31 Ground Floor
60.31 First Floor
60.31 2nd Floor
60.31 3rd Floor
15.05 4 th Floor Stair Case Head room

Masonry work in CM (1:4) prop with Flyash Cement


solid blocks of size 230 x 100 x 140 mm for
manufacturing of flyash solid blocks using flyash of
80 kgs, cement of 15 kgs.Gypsum of 5 kgs. and
20 stone dust including cost and conveyance of all
materials, labour charges,, scaffolding and curing
etc., complete with a compressive strength not
lessthan 50 kg/sqcm for walls for Superstructure
Walls. For Partion walls..

a 32.49 Ground Floor


b 33.02 First Floor
c 33.02 2nd Floor
d 33.02 3rd Floor
e 5.11 4th floor
Plastering with CM (1:3), 12 mm thick in singlecoat
with. Screened sand with sponge finishing including
21 cost and coneyance of all meterials hacking surface,
scaffolding, leads, lifts and labour charges etc.,
complete for CEILING.

a 301.35 Ground Floor


b 301.35 First Floor
c 301.35 2nd Floor
d 301.35 3rd Floor
e 25.50 4th Floor

Plastering with CM (1:5), 12 mm thick in singlecoat


with. Screened sand with sponge finishing including
22 cost and coneyance of all meterials hacking surface,
scaffolding, leads, lifts and labour charges etc.,
complete for Internal Walls.

a 1173.32 Ground Floor


b 1173.32 First Floor
c 1173.32 2nd Floor
d 1173.32 3rd Floor
e 63.84 4th Floor

Plastering with CM (1:5), 12 mm thick in singlecoat


with. Screened sand with sponge finishing including
23 cost and coneyance of all meterials hacking surface,
scaffolding, leads, lifts and labour charges etc.,
complete for Exterior Walls.

a 716.50 Ground Floor


b 726.90 First Floor
c 726.90 2nd Floor
d 726.90 3rd Floor
e 97.00 4th Floor

Flooring with vitrified tiles of size not less than 598


mm x 598 mm, 8 to 10 mm thick glossy finish
premium colour normal colour 1st quality set over
base coat of cement mortar (1:8), 12mm thick over
CC bed already laid or RCC roof slab, including neat
24 cement slurry of honey like consistency spread @
3.3.kgs per sqm & jointed neatly with white cement
paste to full depth mixed with pigment of matching
shade, Pointing with CM (1:3) including cost of all
materials like cement, sand water and tiles etc.,
complete, for finished item of work.

a 266.18 Ground Floor


b 266.18 First Floor
c 266.18 2nd Floor
d 266.18 3rd Floor
e 25.50 4th Floor
Providing skirting to internal walls to 10 cm
height/risers of steps with vitrified tiles length equal to
flooring stones, set over base coat of CM (1:5) 12
mm thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per sqm
25 and jointed with white cement paste mixed with
pigment of matching shade to full depth, including
cost of all materials like tiles, cement, sand and
water etc., complete for finished item of work.

a 27.94 Ground Floor


b 27.94 First Floor
c 27.94 2nd Floor
d 27.94 3rd Floor
e 7.12 4th Floor

Flooring with Non Skid ceramic tiles of 7.3mm thick


of 1st quality of all shades set over base coat of
cement mortar (1:8), 12 mm thick over CC bed
already laid or RCC roof slab, including neat cement
slurry of honey like consistency spread @ 3.3.kgs per
26 sqm & jointed neatly with white cement paste to full
depth mixed with pigment of matching shade,
including cost of all materials like cement, sand water
and tiles etc., complete, for finished item of work.

a 12.16 Ground Floor


b 12.16 First Floor
c 12.16 2nd Floor
d 12.16 3rd Floor
Dadoing walls with 1st quality of glazed plain
coloured tiles of 5 to 7 mm thick of any size cement
base in C.M.(1:3) Prop. and neat cement slurry of
honey like consistency at the rate of 3.30 Kgs.
cement per Sq.mt. mixed with pigment of matching
27
shade of tiles including charges, curing etc.,
complete as directed by the department for finished
of work inclusive of all taxes .for BATH ROOMS
AND KITCHEN.

a 77.04 Ground Floor


b 77.04 First Floor
c 77.04 2nd Floor
d 77.04 3rd Floor
Providing and fixing door frame fabricated from
section made of galvanized steel powder coated
(base steel as per IS 513,galvanized as per IS 217
with zinc of 120 grams/square meter). The factory
made section should be with a powder coating of
pure polyester powder of 50-60 microns thick with
total coated thickness of 1.25 mm. Size of door frame
section should be of 105 x 60 mm with a rebate of
38mm to accommodate 30 mm thick door shutter
with groove to insert gasket in the frame section,
frame section to be filled with polyurethane foam. the
28 64.00
frame section should be cut to length and joined by
way be way of welding. Each frame should be
provided with : 2mm thick MS powder coated butt
hinges of 100 mm long -3 Nos. for single shutter,
6Nos. double shutter. CRCA Electroplates stiffeners
of 6 Nos. -3 in each vertical for double shrtter and
40mm x 200 mm x 1.2 mm hold fasts screwed to
stiffeners - 6Nos. with split end tail. Nylon Aldrop
Receiver -1No. for single shutter frame. Tie Rod 1
No. DOOR FRAME FOR WITH OUT SILL OF SIZE
0.91X1.98 M.
Providing and fixing door frame fabricated from
section made of galvanized steel powder coated
(base steel as per IS 513,galvanized as per IS 217
with zinc of 120 grams/square meter). The factory
made section should be with a powder coating of
pure polyester powder of 50-60 microns thick with
total coated thickness of 1.25 mm. Size of door frame
section should be of 105 x 60 mm with a rebate of
38mm to accommodate 30 mm thick door shutter
with groove to insert gasket in the frame section,
frame section to be filled with polyurethane foam. the
29 frame section should be cut to length and joined by
way be way of welding. Each frame should be
provided with : 2mm thick MS powder coated butt
hinges of 100 mm long -3 Nos. for single shutter,
6Nos. double shutter. CRCA Electroplates stiffeners
of 6 Nos. -3 in each vertical for double shrtter and
40mm x 200 mm x 1.2 mm hold fasts screwed to
stiffeners - 6Nos. with split end tail. Nylon Aldrop
Receiver -1No. for single shutter frame. Tie Rod 1
No. DOOR FRAME FOR WITH SILL OF
SIZE0.91X1.98 M.

32 Main Door 0.91x1.98


32 Kitchen Door 0.76x1.98
2 Stair case Head rooms 0.91x1.98
Supply and fixing of Flush door single leaf shutter of
30 mm thick with solid bond wood black board type
including commercial ply of 3mm thick on both faces
including cost of fixtures of M.S.Powder coated make
of 1 No. 250 mm long aldrop, 1 No. of 200 mm long
aldrop, 1 No. of 200 mm tower blot, 1 No. 125 mm
30 long handle including cost and conveyance of all
materials and labour charges etc., complete as per
drawing and as directed by the department for DOOR
OF SIZE: 0.76 X 1.98 Mts.

64 Internal Door 0.91x1.98


32 Internal Door 0.76 X 1.98
2 For Head Room 0.91X1.98
Supply and fixing of Flush door single leaf shutter of
35 mm thick with solid bond wood black board type
including teak ply of 3mm thick on both faces
including cost of fixtures of M.S.Powder coated make
of 1 No. 250 mm long aldrop, 1 No. of 200 mm long
aldrop, 1 No. of 200 mm tower blot, 1 No. 125 mm
23 long handle including cost and conveyance of all
materials and labour charges etc., complete as per
drawing and as directed by the department for DOOR
OF SIZE: 0.91 X 1.98 Mts.

32.00 Internal Door 0.91 X 1.98


Supplying and fixing of PVC Door frames made from
extruded sections in over all dimentions of 40 x
48mm having wall thickness of 1.55 mm. wiht usual
porcess veriation of +/- 0.3mm complete and Sintex
door shutter made from specially Hot Press Moulded
SMC (Sheet moulding coumpound sheets,
Polyurethene core and PVC Frame Section SMS
sheets shall be made from SMC comforming to IS
13410 sheet shall have an average thickness of 1.4
mm +0.35 mm on both sides. Core of the door
shutter shall be filled with high density polyurethane
31 foam , injected wiht the help of hydraulic injection
method shutter frame to be made of PVC extruded
section confirming to IS:10151 :1982 of size 26 mm x
46 mm with a wall thickness of 1.4 mm +0.3mm on
both sides corresponding to sintex code DWUF 305.
The hardware locations shall be reinforced with
special polymeric reinforcement wooden blocks of
suitable size. The corners of the shutter frame shall
be reinforced with Polymeric 'L' shaped angle of size
105 mm x 230 mm corresponding to Sintex code PR-
02 the lock rail shall be made from PVC extruded
sections having overall dimensions of 26 mm x 46
32.00 Door of Size 0.76x1.98
Providing and fixing of Openable / Casement
Windows with fly proof mesh made of pre-painted
steel (Base steel as per IS 513 of 0.80 mm. thick
galvanized as per IS-277 with Zinc of 120 GSM),
finish painted with a polyester paint of 60-65 microns
thick and section for outer frame fo 100 x 45 mm.,
centre mullion of 100x60 mm, section for shutter of
52 x 25 mm x 0.6 mm thick, section for fly-shutter of
52 x 25 m x 0.6 mm thick and fitted with stainless
steel 32 gauge fly mesh of 304 grade with 144 holes
per Sq.inch and mullions to have double rebate for
32 glazed shutter and fly-shutter with a provision for
guard bars/grills and the sections cut to length metre
joined with corner bracket, centre mullion fixed with
mullion cap, 1 No.of High grade nylon latch handle,
window stopper, 2 Nos. of with MS powder coated/
SS ball bearing butt Hinges provided per shutter and
windows fitted with 4 mm thick plain float glass with
rubber gaskets including fixing the frames in
concrete/ masonry wall by means of self expanding
screws, including 10 mm square guard bars with 6"
(152.4mm) pitch etc., complete for finished item of
work. Windows (B) 1.52 x 1.22 Size.
a 32 Window Size W 1.22x1.22
b 48 Window Size W1 0.91x1.22
c 8 Window Size W1 0.91x1.22
d 8 Window Size W2 0.61x1.22
e 32 Window Size KW 0.61x0.91
Providing and fixing of top hung Ventilators made of
pre-painted steel (Base steel as per IS 513of 0.80mm
thick galvanized as per IS 277 with Zinc of 120
GSM), finish painted with a polyester paint of 60-65
microns thick and section for outer frame of 80 x
45mm, centre mullion of 80 x 60mm, section for
shutter of 52 x 25mm x 0.6mm thick, outer frame and
mullions to have rebate for glazed shutter with a
provision for guard bars/ grills and the sections cut to
length metre joined with corner bracket, centre
mullion fixed with mullion cap, 1No. of High grade
33 nylon latch handle, window stopper, 2 Nos. of with
MS powder coated / SS ball bearing but hinges
provided per shutter and windows fitted with 4 mm
thick plain float glass with rubber gaskets including
fixing the frames in concrete / masonry wall by
means of self expanding screws, including 10mm
square guard bars with 6" (152.4mm) pitch etc.,
complete for finished item of work. Single fixed
louvers ventilator size of 2'-0" x 2'-0" (609.6 x 609.6
mm) outer frame box section size of 80 x
45mm.Ventilator window 2'-6" x 1'-6" . Outer frame
section size 72 x 0mm shutter frame section size of
27 32.00 Ventilator V 0.76x0.61
Providing and applying of wall putty of white cement
or polymer or cement based of average 1 to 2mm
thickness over plastered surface to prepare the
surface even and smooth after throughly brushing the
surface to remove all dirt and remains of loose
powdered materials, applying emery paper ,sand the
surface ,clean & wipe off loose dust ,applying knifing
34 paste filler putty knife/muslin pad ,air dry for 2-3 hrs
sand with 180 and 320no,emery paper for the
surface preparation including cost and conveyance of
all matrials to work site and all operational
,incidental,labour chages etc complete for finished
item of work for internal walls.

a 1474.67 Ground Floor


b 1474.67 First Floor
c 1474.67 2nd Floor
d 1474.67 3rd Floor
e 63.84 4th Floor Internal Plastering qty
Painting to new walls with 2 coats of water proof
cement paint interior grade-I of approved brand and
shade over a base coat of approved cement primer
grade I making 3 coats in all to give an even shade
after throughly brushing the surface to remove all dirt
35 and remains of loose ppowdered materials to work
site and all operational, incidental, labour charges
etc., complete for finished item of work as per SS 912
for internal walls.

a 1474.67 Ground Floor


b 1474.67 First Floor
c 1474.67 2nd Floor
d 1474.67 3rd Floor
e 63.84 4th Floor Internal Plastering qty

Painting to new walls with 2 coats of water based


cement primer of exteriorgrade -II paint of approved
brand and shade over a base coat of approved
cement primer grade-2 making 3 coats in all to give
an even shade after throughly brushing the surface to
36 remove all dirt and remains of loose ppowdered
materials to work site and all operational, incidental,
labour charges etc., complete for finished item of
work as per SS 912 for exterior walls

a 716.50 Ground Floor


b 716.50 First Floor
c 716.50 2nd Floor
d 716.50 3rd Floor
97.00 4th Floor ExternaWall Plastering Qty

Supply and fixing 110 mm dia 4.00 Kg./Sq.Cm.


pressure P.V.C.Pipe of Prince / Sudhakar make from
37 102.40 roof up to basement level including plain bend clips
and shoe as per ISI. Standard fixed to wall with pipe
clips including labour charges etc., complete for
RAIN WATER PIPE.

Supply and fixing of 16 to 18 mm thick polished


Black Grainte stone slab with C.M.(1-1/2:1) prop.
Putty to full depth including cost and conveyance of
38 all materials for Kitchen Plotform with machine
finishing on all sides and rounding of corners
suitable hole for gas pipe connection etc., complete

a 9.60 Ground Floor


b 9.60 First Floor
c 9.60 2nd Floor
d 9.60 3rd Floor

Supplying and fixing of sink with polished Black


Granite Stone of thick 16 to 18 mm sink thick of size
39 32.00 24" x 18" x 10" with a hole at bottom and waste water
pipe including cost and conveyance of all materials ,
labour charges , curing etc complete.

Providing & placing on terrace (at all floors levels)


polyethylene water storage tank with double layer
approved brand & manufacture with cover and
40 8 suitable locking arrangement & making necessary
holes for inlet & outlets and over flow pipes but
without fittings & base supports for tanks.

PAINTING to new WOOD work / Iron work in two


coats with synthetic enamel paint of approved colour,
over one coat of primary coat including cost and
41 conveyance of all materials, incidental charges such
as sand paper, cleaning the surface, cost of brushes
and putty etc., complete. (Three coats).

a 124.38 Ground Floor


b 124.38 First Floor
c 124.38 2nd Floor
d 124.38 3rd Floor
e 8.20 4th Floor
Granolithic concrete flooring 20 mm thick with (1:1:2)
using 6mm to 12 mm size hard granite metal laid
over CC bed already laid or RCC Roof slab in
alternate panels of size not exceeding 1.5Mt x 1.5Mt.
and finishing the top surface to required slopes
including cost of all materials like cement, metal,
sand and water etc., complete for finished item of
42 work.
a 98.63 All round
TOTAL
Add L.S for unforceen items
Say. TOTAL:
STRACT ESTIMATE
Construction of G+3 houses for HFA
No. of blocks

Rate Unit Amount

361.90 1 Cum 164522.64

490.55 1 Cum 27591.79

235.20 1 Cum 108693.76

3878.79 1 Cum 199878.51


7166.74 1 Cum 479046.40
7591.64 1 Cum 57649.02
9279.49 1 Cum 199423.11
9935.61 1Cum 16095.69
9935.61 1Cum 16095.69
10983.55 1Cum 17793.35
11228.85 1Cum 18190.74
11474.11 1Cum 18588.06
10077.92 1Cum 200789.96
10077.92 1Cum 138206.08
11192.65 1Cum 153493.20
11504.70 1Cum 157772.58
11816.80 1Cum 27396.07
9935.61 1 Cum 15404.17
9935.61 1 Cum 15404.17
10983.56 1 Cum 17028.91
11228.86 1 Cum 17409.22

3635.84 Cum 76087.81


1143.96 1 Sqm 11242.84
1143.96 1 Sqm 11242.84
1213.98 1 Sqm 11931.00
1242.56 1 Sqm 12211.88
0.00
1143.96 1 Sqm 53927.19
1143.96 1 Sqm 53927.19
1213.98 1 Sqm 57227.99
1242.56 1 Sqm 58575.27
0.00
1143.96 1 Sqm 80141.26
1143.96 1 Sqm 80141.26
1213.98 1 Sqm 85046.58
1242.56 1 Sqm 87048.78
9891.59 1 Cum 223893.77
9891.59 1 Cum 223893.77
10969.49 1 Cum 248291.77
11243.40 1 Cum 254491.66
11518.69 1 Cum 12186.77
6151.59 1 Cum 191299.78
6173.41 1 Cum 191978.33
7078.21 1 Cum 220115.45
7181.66 1 Cum 223332.50
7283.81 1 Cum 22026.24
6151.59 1 Cum 11626.51
6173.41 1 Cum 11667.74
7078.21 1 Cum 13377.82
7181.66 1 Cum 13573.34
7283.81 1 Cum 13766.40
344.46 1 Sqm 119353.94

53904.65 MT 718520.85
55138.50 MT 322049.99
55261.90 MT 322770.74
55385.30 MT 323491.49
55508.65 MT 35880.79

0.00

5305.00 1 Cum 318111.47


5459.32 1 Cum 329233.27
5633.72 1 Cum 339750.75
5887.01 1 Cum 355025.82
6140.01 1 Cum 370283.40
6393.77 1 Cum 96206.51

6570.82 1 Cum 213469.91


6745.16 1 Cum 222742.72
7175.37 1 Cum 236949.37
7605.07 1 Cum 251139.18
8036.07 1 Cum 41031.52
299.48 Sqm 90247.94
317.67 Sqm 95729.47
326.43 Sqm 98369.29
335.18 Sqm 101006.09
343.93 Sqm 8770.14

304.01 Sqm 356702.47


322.17 Sqm 378010.05
327.51 Sqm 384275.61
332.86 Sqm 390552.89
338.27 Sqm 21595.52

258.08 Sqm 184914.11


276.27 Sqm 200819.56
278.08 Sqm 202135.24
279.88 Sqm 203443.65
281.73 Sqm 27327.86

1515.08 Sqm 403279.28


1546.42 Sqm 411622.36
1549.53 Sqm 412448.07
1552.68 Sqm 413287.10
1555.78 Sqm 39672.42

1536.38 Sqm 42932.60


1570.13 Sqm 43875.71
1573.53 Sqm 43970.72
1576.88 Sqm 44064.33
1580.22 Sqm 11251.17

954.24 Sqm 11603.56


987.98 Sqm 12013.84
991.39 Sqm 12055.30
994.75 Sqm 12096.16

1011.58 Sqm 77928.89


1020.08 Sqm 78583.70
1020.93 Sqm 78649.18
1021.73 Sqm 78710.81
4096.10 Nos 262150.40
4880.85 Nos 156187.20
4673.90 Nos 149564.80
4880.85 Nos 9761.70
0.00

3650.63 Nos 233640.32


3082.50 Nos 98640.00
3650.63 Nos 7301.26

5171.25 Nos 165480.00


7489.15 239652.80
11950.85 Nos 382427.17
8914.90 Nos 427915.35
8914.90 Nos 71319.23
5704.05 Nos 45632.40
4255.05 Nos 136161.63
3215.65 Nos 102900.81
211.50 Sqm 311893.47
211.50 Sqm 311893.47
211.50 Sqm 311893.47
211.50 Sqm 311893.47
211.50 Sqm 13502.58

181.85 Sqm 268169.39


181.85 Sqm 268169.39
181.85 Sqm 268169.39
181.85 Sqm 268169.39
181.85 Sqm 11609.67

207.65 Sqm 148781.06


207.65 Sqm 148781.06
207.65 Sqm 148781.06
207.65 Sqm 148781.06
207.65 Sqm 20142.30

273.05 Rmt 27960.32

3508.25 Sqm 33679.24


3508.25 Sqm 33679.24
3508.25 Sqm 33679.24
3508.25 Sqm 33679.24

3936.00 Nos 125952.00

4544.60 Nos 36356.80

154.35 Sqm 19198.61


154.35 Sqm 19198.61
154.35 Sqm 19198.61
154.35 Sqm 19198.61
154.35 Sqm 1265.24
389.92 Sqm 38457.03
20,099,571.72
57,285.32
20,156,857.04
ABSTRACT FOR INTERNAL ELECTRIFICATION
Name of Work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at Maddila
Visakhapatnam in the place of existing A & B staff quarters.

Sl.
Quantity Description of item Rate Unit
No.

Wiring with 2 runs of 14/0.3 mm. (1.00 Sqmm.)P.V.C.


insulated FR flexible copper cable (ISI Make) in the existing
pipe with 6 A Module Modular Switch, Ceiling rose control
1 460.000 with suitable gang metallic box concealed including all 674.85 Each
labour charges etc., complete for Light & Bell Points in
Residential Buildings. (Make GM four - five/Legrand Arteor /
schneider Zencelo / MK blenge).

Supply and fixing of ISI 20mm outer medium dia (1.55 mm


thick) grade with IS 9537part - 3 , rigid 4make Sudhakar /
Modi / Atul P.V.C pipe concealed in wall with all required
2 900.000 79.05 1RMT
accessories including masonary work for light, fan and
separate plug point with well seasoned wooden deep box
including all labour charges etc. complete.

Supply and fixing of 25mm dia 1.8 mm thick Surface P.V.C


pipe (ISI MARK ) with all accessories fixing on chromium
3 620.000 81.60 1 RMT
plated metallic base saddles including all labour charges
etc. complete for run of mains.
Supply and fixing of 25mm dia 2.2 mm thick P.V.C pipe (ISI
MARK) concealed in Roof slabs with all required
4 3250.000 76.45 1 RMT
accessories including masonary work and labour charges
etc. complete.

Supplying and run of 2 of 36/0.3mm (2.5 Sqmm.) F.R.


LS/HFFR PVC insulated 1100 V grade as per IS 694 / 1990
5 860.000 insulated Makes finolex / RR Kabel flexible Copper cable of 76.30 1 RMT
makes finolex / RR kabel in existing pipe for MAINS
including all labour charges etc., complete.

Supply and fixing of 6A, 3 pin plug socket with 6 A Modular


type switch control with suiteble gang metallic flush box with
2mts of 1 sq mm PVC insulated copper conductor single
6 100.000 core standard wire on acommon board with a run of 1.0 sq 355.85 Each
mm PVC insulated copper conductor single core standard
wire for earth continuity along with labour charges etc.,
complete.

Supply and fixing of BATTEN HOLDER/ SLANTING


HOLDER in lieu of ceiling rose of light point complete with
7 160.000 all connections and all labour charges with 40 W Bulb etc., 98.75 Each
complete (for New installation) connections. (makes
Anchor/Gold medal)

ABS-Int.Elec.
Sl.
Quantity Description of item Rate Unit
No.
Supply and fixing of Modular (4 module box ) Type 16A/ 6A
one way combi socket modular socket with shutter of and
16A/10A module flush fuse with neon indicator duly on
8 100.000 349.95 Each
recessed in wall with suitable gang metalic flush box
including earth connection and all labour chargs
etc.,complete.

Supply and fixing Distribution board with 20 A single phase


plug and socket, in sheet enclosure with 10/16/32A SP MCB
9 10.000 including internal conneciton and labour charges for 1736.02 Each
surface/flush mounting etc., complete. (Concailed in wall) for
A.C. Point.

Provding Independent earthing for sophisticated Electronic


equipment with 600 mm x 600mm x 3.15mm thick copper
plate rigidly fixed to 40mm dia G.I. Pipe of 0.3mtr., length
connected with reducer providing G.I funnel with wiremesh
as per National Electric Code including C.C.Chamber of size
10 2.000 2342.78 Each
400m x 400 m x 400mm covered with R.C.C. slab filling with
salt and charcoal giving earth connection from electrode G.I.
strip of 25mm x 6mm x 200mm length with all accessories
and labour chargesd complete as per IS specification
732/1982 (Part II).

Supply and erectiong of Modular type Telephone socket &


jack with modular cover frame in a moduler metallic box
11 20.000 including cost and conveyance of all meterials and labour 299.50 Each
charges etc., complete.(Makes GM four five/Legrand
Arteor / Schneider zen celo/MK blenge).

Supply and laying of 2 pair Telephone 0.50 mm. copper wire


of make finolex / delton/surabi/polycab in the existing PVC
12 200.000 21.17 1 RMT
conduct pipe with labour charges etc., complete for finshing
item of work.

Supply and Fixing of Modular type conceiled type Television


socket & jack with White mounting plate housed in a
13 20.000 298.32 Each
module metallic flush box including cost and conveyance of
all meterials and labour charges etc., complete.

Supply and laying of 2 pair Television wire of RG - 6 coaxil


14 200.000 cable in the existing PVC conduct pipe with labour charges 29.01 1 RMT
etc., complete for finshing item of work.

Supplying run of 2 of 56/0.03 mm (4 Sq.mm) FRLS/ HFFR


PVC. Insulated flexible copper 1100 V grade as IS 694/1990
15 1040.000 115.93 1 RMT
cable in existing pipe for mains including all labour charges
etc. complete. For run of mains.(finolex/RR kabel).

Supplying and fixing TPN distibution bord with IP-20


proteciton suitable for 3 phase ELCB/ RCCB/FP isolator as
16 40.000 incomer and 10 KA TP SP MCBs as outing going including 8420.05 Each
internal connections and labour charges for surface/Flush
mounting etc., complete.

ABS-Int.Elec.
Sl.
Quantity Description of item Rate Unit
No.
Supplying and fixing of Electronic Regulators 400 w socket
type common switch board with earth continuity including
17 100.000 316.11 Each
wire leads, earth connections along with all labour charges
etc., complete.

Supplying and erecting the following PVC armoured cable


1100 V grade with ISI mark standed/soild alluminium in soil
upto 0.9 M deep embedding the cable complete with sand
bed of 20 Cms. Thick layer and bricks placed on top of the
calbe with wise and sides all over the run and back filling the
18 150.000 excavated earth with outstones and hard materials and 626.05 1 RMT
making the surface proper with 15 Cms. crown on the top
duly providing route indicators including connections like
brass glands, AL lugs etc., complete.(makes polycab / KE1 /
RPG/ finolex / havells / paragon/ Vguard / fortunart /
gloster / suncab).

Supply, insallation, testing and commissioning of floor


mounting type meter panel board with alluminium bus bars
fabricated with 16 Duage CRCA sheet in standard sections
suitable for TNP bus bars with bus bars of equal size in all
phases and neutral equipped wiht bus bar chambers and
cable chambers. The painting of the complete system shall
be powder coated duly processing the pabel in 7 tank
19 1.000 78672.80 Each
process. The panel shall be suitable for accomdating the
following switch gear including supply of all components,
hard wares etc., including all necessary civil works,
adequate reinforcement foundation bolts, suitable GI earth
strip, suitable MS base channel, door loop earthings, bus
bars should be colour sleeved wiht heat shrinkable sleeves
for phase and neutral duly supported at reqular

intervels by SMC supports and bus bar to switch inter


connections shall have bimettalic washers and all cables
shall have proper cable entry, danger board, feeder
identification marks, rigid inter connections, cadmium plated
blots and nuts and shall be installed and performed trench
and consisting of the following as required and as per IS
standards for main power control center.

Supply run of 1 of 14 / 0.30 mm (1 Sq.mm) FRLS/HFFR


PVC. Insulated 1100V grade flexible copper cable in existing
20 860.000 11.95 1 RMT
pipe for mains including all labour charges etc. complete.
For run of mains.

Supply run of 1 of 36 / 0.30 mm (2.5 Sq.mm) FRLS/HFFR


PVC. Insulated1100v gradeflexible copper cable in existing
21 1040.000 28.55 1 RMT
pipe for mains including all labour charges etc. complete.
For run of mains for earthing.

Total Rs.

ABS-Int.Elec.
Sl.
Quantity Description of item Rate Unit
No.
Add L.S Rs.
Total Rs.

ABS-Int.Elec.
FOR INTERNAL ELECTRIFICATION
ommercial Complex (Cellar+Ground+4Floors) at Maddilapalem,
in the place of existing A & B staff quarters.

Amount

310,431.00

71,145.00

50,592.00

248,462.50

65,618.00

35,585.00

15,800.00

ABS-Int.Elec.
Amount

34,995.00

17,360.20

4,685.56

5,990.00

4,234.00

5,966.40

5,802.00

120,567.20

336,802.00

ABS-Int.Elec.
Amount

31,611.00

93,907.50

78,672.80

10,277.00

29,692.00

1,578,196.16

ABS-Int.Elec.
Amount

23,333.40
1,601,529.56

ABS-Int.Elec.
DETAILED ESTIMATE (Internal Electrical)
Name of work : Construction of Commercial Complex (Cellar+Ground+4Floors) at
. Maddilapalem, Visakhapatnam in the place of existing A & B
quarters.

Sl.
Description of Item Nos. L B D
No.

Wiring with 2 runs of 14/0.3 mm. (1.00


Sqmm.)P.V.C. insulated FR flexible copper cable (ISI
Make) in the existing pipe with 6 A Module Modular
Switch, Ceiling rose control with suitable gang
1
metallic box concealed including all labour charges
etc., complete for Light & Bell Points in
Residential Buildings. (Make GM four - five/Legrand
Arteor / schneider Zencelo / MK blenge).

Cellar floor 1 x 20
Ground,1St,2nd,3rd,4th floor
light point 14 x 10 -- -- --
Fan point 2 x 5 x 10
Tube point 5 x 10 -- -- --
3/2 pin point 8 x 10 -- -- --
T.V 4 x 5 -- -- --
Bath room 2 x 4x 5
Carridor, Mid landing 2 x 5 -- -- --
Total Total :

Supply and fixing of ISI 20mm outer medium dia


(1.55 mm thick) grade with IS 9537part - 3 , rigid
4make Sudhakar / Modi / Atul P.V.C pipe concealed
2 in wall with all required accessories including
masonary work for light, fan and separate plug point
with well seasoned wooden deep box including all
labour charges etc. complete.

1St,2nd,3rd,4th floor 2x 5 60.00 --


Cellar ,Carridor & Stair case 1x 5 60.00 -- --
Total Total :

Supply and fixing of 25mm dia 1.8 mm thick Surface


P.V.C pipe (ISI MARK ) with all accessories fixing on
3
chromium plated metallic base saddles including all
labour charges etc. complete for run of mains.

1St,2nd,3rd,4th floor 1x 4 125.00 --


Cellar ,G.F.Carridor & Stair case 1x 2 60.00 -- --
Total Total :

Det-Int.Elec.
Supply and fixing of 25mm dia 2.2 mm thick P.V.C
pipe (ISI MARK) concealed in Roof slabs with all
4
required accessories including masonary work and
labour charges etc. complete.

1St,2nd,3rd,4th,5th floor 1x 5 530.00 --


Cellar ,Stilt ,Carridor & Stair case 1x 2 300.00 -- --
Total Total :

Supplying and run of 2 of 36/0.3mm (2.5 Sqmm.)


F.R. LS/HFFR PVC insulated 1100 V grade as per
IS 694 / 1990 insulated Makes finolex / RR Kabel
5
flexible Copper cable of makes finolex / RR kabel in
existing pipe for MAINS including all labour charges
etc., complete.

1St,2nd,3rd,4th floor 1x 4 165.00 --


Cellar , Carridor & Stair case 1x 2 100.00 -- --
Total Total :

Supply and fixing of 6A, 3 pin plug socket with 6 A


Modular type switch control with suiteble gang
metallic flush box with 2mts of 1 sq mm PVC
insulated copper conductor single core standard
6
wire on acommon board with a run of 1.0 sq mm
PVC insulated copper conductor single core
standard wire for earth continuity along with labour
charges etc., complete.

1St,2nd,3rd,4th floor 2x 5x 8 -- -- --
Cellar, Carridor & Stair case 2 x 10 -- -- --
Total Total :

Supply and fixing of BATTEN HOLDER/ SLANTING


HOLDER in lieu of ceiling rose of light point
7 complete with all connections and all labour charges
with 40 W Bulb etc., complete (for New installation)
connections. (makes Anchor/Gold medal)

Cellar, Carridor & Stair case 1 x 20 -- -- --


1St,2nd,3rd,4th floor 14 x 10
Total :

Det-Int.Elec.
Supply and fixing of Modular (4 module box ) Type
16A/ 6A one way combi socket modular socket with
shutter of and 16A/10A module flush fuse with neon
8
indicator duly on recessed in wall with suitable gang
metalic flush box including earth connection and all
labour chargs etc.,complete.

1St,2nd,3rd,4th,5th floor 2x 5 x 10 -- -- --

Supply and fixing Distribution board with 20 A single


phase plug and socket, in sheet enclosure with
9 10/16/32A SP MCB including internal conneciton
and labour charges for surface/flush mounting etc.,
complete. (Concailed in wall) for A.C. Point.

For AC 16 A MCB 2x 5 -- -- --

Provding Independent earthing for sophisticated


Electronic equipment with 600 mm x 600mm x
3.15mm thick copper plate rigidly fixed to 40mm dia
G.I. Pipe of 0.3mtr., length connected with reducer
providing G.I funnel with wiremesh as per National
10 Electric Code including C.C.Chamber of size 400m x
400 m x 400mm covered with R.C.C. slab filling with
salt and charcoal giving earth connection from
electrode G.I. strip of 25mm x 6mm x 200mm length
with all accessories and labour chargesd complete
as per IS specification 732/1982 (Part II).

For Flats 1x 2 -- -- --

Supply and erectiong of Modular type Telephone


socket & jack with modular cover frame in a
moduler metallic box including cost and conveyance
11
of all meterials and labour charges etc., complete.
(Makes GM four five/Legrand Arteor / Schneider zen
celo/MK blenge).

Telephone socket jack 2x 5x 2 -- -- --

Supply and laying of 2 pair Telephone 0.50 mm.


copper wire of make finolex / delton/surabi/polycab
12
in the existing PVC conduct pipe with labour charges
etc., complete for finshing item of work.

Telephone Wire internal 2x 5x 2 10.00 -- --

Det-Int.Elec.
Supply and Fixing of Modular type conceiled type
Television socket & jack with White mounting plate
13 housed in a module metallic flush box including
cost and conveyance of all meterials and labour
charges etc., complete.
Television socket jack 2x 2x 5 -- -- --
Supply and laying of 2 pair Television wire of RG - 6
coaxil cable in the existing PVC conduct pipe with
14
labour charges etc., complete for finshing item of
work.
Television Wire internal 2x 5x 2 10.00 -- --

Supplying run of 2 of 56/0.03 mm (4 Sq.mm) FRLS/


HFFR PVC. Insulated flexible copper 1100 V grade
15 as IS 694/1990 cable in existing pipe for mains
including all labour charges etc. complete. For run
of mains.(finolex/RR kabel).

1St,2nd,3rd,4th floor 8x 2x 5 13.00 -- --


Supplying and fixing TPN distibution bord with IP-20
proteciton suitable for 3 phase ELCB/ RCCB/FP
isolator as incomer and 10 KA TP SP MCBs as
16
outing going including internal connections and
labour charges for surface/Flush mounting etc.,
complete.
1St,2nd,3rd,4th floor 4x 2x 5 -- -- --

Supplying and fixing of Electronic Regulators 400 w


socket type common switch board with earth
17
continuity including wire leads, earth connections
along with all labour charges etc., complete.

Electronic Regulator 5 x 10 x 2 -- -- --

Supplying and erecting the following PVC armoured


cable 1100 V grade with ISI mark standed/soild
alluminium in soil upto 0.9 M deep embedding the
cable complete with sand bed of 20 Cms. Thick
layer and bricks placed on top of the calbe with wise
and sides all over the run and back filling the
18 excavated earth with outstones and hard materials
and making the surface proper with 15 Cms. crown
on the top duly providing route indicators including
connections like brass glands, AL lugs etc.,
complete.(makes polycab / KE1 / RPG/ finolex /
havells / paragon/ Vguard / fortunart / gloster /
suncab).

PVC armoured cable 1100 V grade 1x 2 75.00 -- --


with ISI mark standed/soild alluminium

Det-Int.Elec.
Supply, insallation, testing and commissioning of floor
mounting type meter panel board with alluminium bus
bars fabricated with 16 Duage CRCA sheet in standard
sections suitable for TNP bus bars with bus bars of equal
size in all phases and neutral equipped wiht bus bar
chambers and cable chambers. The painting of the
complete system shall be powder coated duly processing
the pabel in 7 tank process. The panel shall be suitable
for accomdating the following switch gear including
supply of all components, hard wares etc., including all
necessary civil works, adequate reinforcement foundation
19 bolts, suitable GI earth strip, suitable MS base channel,
door loop earthings, bus bars should be colour sleeved
wiht heat shrinkable sleeves for phase and neutral duly
supported at reqular intervels by SMC supports and bus
bar to switch inter connections shall have bimettalic
washers and all cables shall have proper cable entry,
danger board, feeder identification marks, rigid inter
connections, cadmium plated blots and nuts and shall be
installed and performed trench and consisting of the
following as required and as per IS standards for main
power control center.

1x 1 1 -- --

Supply run of 1 of 14 / 0.30 mm (1 Sq.mm)


FRLS/HFFR PVC. Insulated 1100V grade flexible
20
copper cable in existing pipe for mains including all
labour charges etc. complete. For run of mains.

1x 1 860 -- --
Supply run of 1 of 36 / 0.30 mm (2.5 Sq.mm)
FRLS/HFFR PVC. Insulated1100v gradeflexible
21 copper cable in existing pipe for mains including all
labour charges etc. complete. For run of mains for
earthing.
1x 1 1040 -- --

Det-Int.Elec.
ESTIMATE (Internal Electrical)
rcial Complex (Cellar+Ground+4Floors) at
palem, Visakhapatnam in the place of existing A & B staff

Quantity

20.000

140.000
100.000
50.000
80.000
20.000
40.000
10.000
460.000 Rmt

600.000
300.000
900.000 Rmt

500.000
120.000
620.000 Rmt

Det-Int.Elec.
2650.000
600.000
3250.000 Rmt

660.000
200.000
860.000 Rmt

80.000
20.000
100.000 Nos

20.000
140.000
160.000 Nos

Det-Int.Elec.
100.000 Nos

10.000 Nos

2.000 Nos

20.000 Nos

200.000 Rmt

Det-Int.Elec.
20.000 Nos

200.000 Rmt

1040.000 Rmt

40.000 Nos

100.000 Nos

150.000 Rmt

Det-Int.Elec.
1.000 Nos

860.000 Rmt

1040.000 Rmt

Det-Int.Elec.
ABSTRACT FOR CIRCULAR SUMP

Name of Work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at Maddila


Visakhapatnam in the place of existing A & B staff quarters.

Sl. Qty. Description of item Rate Unit


No.

Earth work excavation for foundations and depositing on


bank for all lifts and with an initial lead of 10m including all
operational, incidental, labour charges such as shoring
1 19.251 incidental, sheeting, planking, strutting, etc. complete for 132.35 1 Cum.
finished item of work .in ordinary soils by manual means
upto 3.00mt depth excluding dewatering charges etc. as per
SS- 20 B (APSS 308)

Filling sand cushion in the foundations below bed concrete


2 2.984 as per standered specifications including cost of sand and 1836.75 1 Cum.
labour charges etc., complete.
Laying PCC work of mix (1 : 4 : 8) proop. Using 40 mm
gauge hard granite machine crushed metal including cost
3 2.214 and conveyance of all materials, machine mixing, labour 4474.10 1 Cum.
charges, tamping, curing, taxes etc., complete for
foundations.

Filling with useful available excavated earth (excluding rock)


in trenches, sides of foundations and basement with initial
lead in layers not exceeding 15 cm thick,consolidating each
4 3.802 deposited layer by watering and ramming including cost and 278.75 1 Cum.
conveyance of water to work site and all operational,
incidental, labour charges, hire charges of T & P etc.,
complete for finisheditem of work. (APSS NO. 309 & 310).

Supply and placing of the Design Mix Concrete of grade


M30 corresponding to IS 456 using WEIGH BATCHER
using minimum cement content of 380 Kg. per Cum with
12mm and 20mm size graded machine crushed hard
granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement,
fine aggregate ( sand) coarse aggregate, water etc., to site
5 1.925 9893.65 1 Cum.
and including, sales & other taxes on all materials including
all operational, incidental and labour charges such as weigh
batching, machine mixing, laying concrete, Vibrating, curing
etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No.402 including
centering shuttering using adjastable Jack Screws, Props
and Acro span beams

including all pipe bracings, clamps couplings pre fabricated


steel H-frames, cross members etc., Complete, laying
concrete, vibrating, curing etc. complete but excluding cost
of steel and its fabrication charges for finished item of work
for Bottom Slab.

ABS-Cir.Sump
Sl. Qty. Description of item Rate Unit
No.

Supply and placing of the Design Mix Concrete of grade


M30 corresponding to IS 456 using WEIGH BATCHER
using minimum cement content of 380 Kg. per Cum with
12mm and 20mm size graded machine crushed hard
granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement,
fine aggregate (sand) coarse aggregate, water etc., to site
and including, sales & other taxes on all materials including
all operational, incidental and labour charges such as weigh
6 3.394 batching, machine mixing, laying concrete, vibrating, curing 15632.71 1 Cum.
etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No.402) including
centering shuttering using adjastable Jack Screws, Props
and Acro span beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross members
etc., Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its fabrication
charges for finished item of work FOR CIRCULAR SUMP
SIDE WALLS 200 mm. thick.

Supply and placing of the Design Mix Concrete of M 30


corresponding to IS 456 using WEIGH BATCHER using
minimum cement content of 380 Kg. per Cum with 12mm
and 20mm size graded machine crushed hard granite metal
(coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including,
sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching,
7 0.991 machine mixing, laying concrete, vibrate, curing 10293.55 1 Cum.
etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No.402)including
centering shuttering using adjastable Jack Screws, Props
and Acro span beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross members
etc., Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its fabrication
charges for finished item of work FOR CIRCULAR SUMP
COVER SLAB.

ABS-Cir.Sump
Sl. Qty. Description of item Rate Unit
No.

Providing High Yield Strength Deformed Steel bars (Fe 415


Grade as per IS : 1786 and as amended upto date) of
different diameters including labour charges for cutting
bending to required size shapes, placing in position with
cover blocks of approved materials and size and tying firmly
with M.S. Binding wire of 20 SWG forming grills for
reinforcement work as per approved designs and drawings
including cost and conveyance of deformed steel bars,
8 0.757 63465.35 1 M.T.
including all wastage such as overlaps, welded joints, chairs
spacer bars including cost and conveyance of binding wire
cover blocks and all incidental, opeartional labour charges
including sales and other taxes on all materials etc.,
complete for finished item of work in all floors (APSS
No.126) (Payment will be made on the basis of weight of
fabrication deformed bars only) (No re-rolled steel shall be
allowed) complete for (8 mm to 40 mm).

Providing impervious coat to exposed RCC roof slab surface


with CM(1:3), 20mm thick with 1kg of water proof compound
per bag of cement laid over roof when it is green including
cost of all materials,, including conveyance charges of
9 27.234 447.70 1Sq.mtr.
materials and including all operational, incidental and labour
charges for mixing mortar, laying, rendering smooth and
thread lining, curing, rounding off junctions of wall and slab
etc,, complete for finished item of work.

Plastering with CM (1:4), 12 mm thick in singlecoat with.


Screened sand with sponge finishing including cost and 1 Sq.
10 19.570 173.60
coneyance of all meterials hacking surface, scaffolding, mtr.
leads, lifts and labour charges etc., complete for CEILING.

Supplying and fixing 50.8 Cm dia C.I. Man hole frame &
11 1.000 cover for chamber (Medium weight ) as per IS:1726-40Kgs. 3048.30 Each
For Circular Sump.
Total:
Add L.S for unforceen items
Cost of sump

ABS-Cir.Sump
STRACT FOR CIRCULAR SUMP

ommercial Complex (Cellar+Ground+4Floors) at Maddilapalem,


in the place of existing A & B staff quarters.

Amount

2,547.87

5,480.86

9,905.66

1,059.81

19,045.28

ABS-Cir.Sump
Amount

53,057.42

10,200.91

ABS-Cir.Sump
Amount

48,043.27

12,192.66

3,397.35

3,048.30

167,979.39
7,020.61
175,000.00

ABS-Cir.Sump
DETAILED ESTIMATE FOR SUMP
Name of work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at Maddi
Visakhapatnam in the place of existing A & B staff quarters.
Sl.
Description of item Nos. L B D
No.

Earth work excavation for foundations and


depositing on bank for all lifts and with an initial lead
of 10m including all operational, incidental, labour
charges such as shoring incidental, sheeting,
1
planking, strutting, etc. complete for finished item of
work .in ordinary soils by manual means upto 3.00mt
depth excluding dewatering charges etc. as per SS-
20 B (APSS 308)

Sump earth work 1x 1 3.143 3.063 2.00

Filling sand cushion in the foundations below bed


2 concrete as per standered specifications including
cost of sand and labour charges etc., complete.

For Sump 1x 1 3.143 3.063 0.31

Laying PCC work of mix (1 : 4 : 8) proop. Using 40


mm gauge hard granite machine crushed metal
3 including cost and conveyance of all materials,
machine mixing, labour charges, tamping, curing,
taxes etc., complete for foundations.

For Sump 1x 1 3.143 3.063 0.23

Filling with useful available excavated earth


(excluding rock) in trenches, sides of foundations
and basement with initial lead in layers not
exceeding 15 cm thick, consolidating each deposited
4 layer by watering and ramming including cost and
conveyance of water to work site and all operational,
incidental, labour charges, hire charges of T & P
etc., complete for finished item of work. (APSS NO.
309 & 310).

1x 1 3.143 0.960 1.26

Det-Cir.Sump
Sl.
Description of item Nos. L B D
No.

Supply and placing of the Design Mix Concrete of


grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380
Kg. per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate ( sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
5
mixing, laying concrete, Vibrating, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402 including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work for
Bottom Slab.

For Sump Bottom conrete 1x 1 3.143 3.063 0.200

Supply and placing of the Design Mix Concrete of


grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380
Kg. per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
6
mixing, laying concrete, vibrating, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402) including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work FOR
CIRCULAR SUMP SIDE WALLS 200 mm. thick.

c For Sump side wall concrete 1x 1 3.143 0.540 2.00

Det-Cir.Sump
Sl.
Description of item Nos. L B D
No.

Supply and placing of the Design Mix Concrete of M


30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380
Kg. per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
7
mixing, laying concrete, vibrate, curing etc.,complete
but excluding cost of steel and its fabrication
charges for finished item of work (APSS
No.402)including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work FOR
CIRCULAR SUMP COVER SLAB.

Sump slab 1x 1 3.143 2.103 0.15

Providing High Yield Strength Deformed Steel bars


(Fe 415 Grade as per IS : 1786 and as amended
upto date) of different diameters including labour
charges for cutting bending to required size shapes,
placing in position with cover blocks of approved
materials and size and tying firmly with M.S. Binding
wire of 20 SWG forming grills for reinforcement work
as per approved designs and drawings including
cost and conveyance of deformed steel bars,
8
including all wastage such as overlaps, welded
joints, chairs spacer bars including cost and
conveyance of binding wire cover blocks and all
incidental, opeartional labour charges including
sales and other taxes on all materials etc., complete
for finished item of work in all floors (APSS No.126)
(Payment will be made on the basis of weight of
fabrication deformed bars only) (No re-rolled steel
shall be allowed) complete for (8 mm to 40 mm).

For Sump Bottom Qty as above 1.925 0.120 MT/1Cum


For sump side walls Qty as above 3.394 0.120 MT/1Cum
For sump slab Qty as above 0.991 0.120 MT/1Cum
Total Total :

Det-Cir.Sump
Sl.
Description of item Nos. L B D
No.

Providing impervious coat to exposed RCC roof slab


surface with CM(1:3), 20mm thick with 1kg of water
proof compound per bag of cement laid over roof
when it is green including cost of all materials,,
including conveyance charges of materials and
9
including all operational, incidental and labour
charges for mixing mortar, laying, rendering smooth
and thread lining, curing, rounding off junctions of
wall and slab etc,, complete for finished item of
work.

Sump In side 1x 1 3.143 2.50 2.00


Sump bottom 1x 1 3.143 1.250 1.25
Sump Top 1x 1 3.143 1.450 1.45
Total Total :
Plastering with CM (1:4), 12 mm thick in singlecoat
with. Screened sand with sponge finishing including
10 cost and coneyance of all meterials hacking surface,
scaffolding, leads, lifts and labour charges etc.,
complete for CEILING.

Sump out side walls 1x 1 3.143 2.90 2.15

Supplying and fixing 50.8 Cm dia C.I. Man hole


11 frame & cover for chamber (Medium weight ) as per
IS:1726-40Kgs. For Circular Sump.

1x 1 -- --

Det-Cir.Sump
AILED ESTIMATE FOR SUMP
mmercial Complex (Cellar+Ground+4Floors) at Maddilapalem,
the place of existing A & B staff quarters.

Qty

19.251 Cum.

2.984 Cum.

2.214 Cum.

3.802 Cum.

Det-Cir.Sump
Qty

1.925 Cum.

3.394 Cum.

Det-Cir.Sump
Qty

0.991 Cum.

0.231
0.407
0.119
0.757 MT

Det-Cir.Sump
Qty

15.715
4.911
6.608
27.234 Sqm

19.570 Sqm

1.000 Nos

Det-Cir.Sump
DATAS FOR CIRCULAR SUMP

As per Common SSR 2015-2016


Name of Work :- Construction of Commercial Complex
(Cellar+Ground+4Floors) at Maddilapalem, Visakhapatnam in the place
of existing A & B staff quarters.

1 Earth work excavation for foundations and depositing on bank for all lifts and with an initial lead
of 10m including all operational, incidental, labour charges such as shoring incidental, sheeting,
planking, strutting, etc. complete for finished item of work .in ordinary soils by manual means
upto 3.00mt depth excluding dewatering charges etc. as per SS- 20 B (APSS 308)

Unit 1 Cum

Rate Rs. 132.35 per 1 Cum

As per Civil Data No.1B

Data-Cir.Sump
2 Filling sand cushion in the foundations below bed concrete as per standered specifications
including cost of sand and labour charges etc., complete.
Sand filling
A.P.Standard Data No.16 (Page No.18)
Unit = cum
A.Labour
Man Mazdoor Day 0.31 320.00 99.20
Add: M.L 40% on 99.20 39.68

B.Material
Sand Cum 1 1467.43 1467.43
Water 0.10 x 103 per 1KL Lit 0.1 103 10.30
Total Rs. 1616.61
C. Add 13.615 % contractor's Profit & Over Head charges 220.10
Sundries 0.04
Total Rs. 1836.75

Data-Cir.Sump
3 Laying PCC work of mix (1 : 4 : 8) proop. Using 40 mm gauge hard granite machine crushed
metal including cost and conveyance of all materials, machine mixing, labour charges, tamping,
curing, taxes etc., complete for foundations.

Unit 1 Cum

Rate Rs. 4474.10 per 1 Cum

As per Civil Data No.2

Data-Cir.Sump
4 Filling with useful available excavated earth (excluding rock) in trenches, sides of foundations
and basement with initial lead in layers not exceeding 15 cm thick,consolidating each deposited
layer by watering and ramming including cost and conveyance of water to work site and all
operational, incidental, labour charges, hire charges of T & P etc., complete for finisheditem of
work. (APSS NO. 309 & 310).

Unit 1 Cum

Rate Rs. 278.75 per 1 Cum

As per Civil Data No.5

Data-Cir.Sump
5 Supply and placing of the Design Mix Concrete of grade M30 corresponding to IS 456 using
WEIGH BATCHER using minimum cement content of 380 Kg. per Cum with 12mm and 20mm
size graded machine crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate ( sand) coarse
aggregate, water etc., to site and including, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching, machine mixing, laying
concrete, Vibrating, curing etc.,complete but excluding cost of steel and its fabrication charges
for finished item of work (APSS No.402 including centering shuttering using adjastable Jack
Screws, Props and Acro span beams including all pipe bracings, clamps couplings pre
fabricated steel H-frames, cross members etc., Complete, laying concrete, vibrating, curing
etc. complete but excluding cost of steel and its fabrication charges for finished item of work for
Bottom Slab.

Unit 1 Cum

Rate Rs. 9893.65 per 1 Cum

As per Civil Data No.3A

Data-Cir.Sump
6 Supply and placing of the Design Mix Concrete of grade M30 corresponding to IS 456 using
WEIGH BATCHER using minimum cement content of 380 Kg. per Cum with 12mm and 20mm
size graded machine crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching, machine mixing, laying
concrete, vibrating, curing etc.,complete but excluding cost of steel and its fabrication charges
for finished item of work (APSS No.402) including centering shuttering using adjastable Jack
Screws, Props and Acro span beams including all pipe bracings, clamps couplings pre
fabricated steel H-frames, cross members etc., Complete, laying concrete, vibrating, curing
etc. complete but excluding cost of steel and its fabrication charges for finished item of work
FOR CIRCULAR SUMP SIDE WALLS 200 mm. thick.

A.P.Standard Data No.31 B Unit 1 Cum

1 Cum M30 grade concrete vide Civil Data No.4 Cum 1.00 8184.35 8184.35
1.00 Cum centering charges as per Sl. No.31.5, Page
No.267. @ Rs.1115/0.2 Cum 1.00 5575 5575.00
Total Rs. 13759.35
Add 13.615 % contractor's Profit & Over Head charges 1873.34
Sundries 0.02
Total Rs. 15632.71

Data-Cir.Sump
7 Supply and placing of the Design Mix Concrete of M 30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380 Kg. per Cum with 12mm and 20mm size
graded machine crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching, machine mixing, laying
concrete, vibrate, curing etc.,complete but excluding cost of steel and its fabrication charges for
finished item of work (APSS No.402)including centering shuttering using adjastable Jack
Screws, Props and Acro span beams including all pipe bracings, clamps couplings pre
fabricated steel H-frames, cross members etc., Complete, laying concrete, vibrating, curing
etc. complete but excluding cost of steel and its fabrication charges for finished item of work
FOR CIRCULAR SUMP COVER SLAB.

Unit 1 Cum

Rate Rs. 10293.55 per 1 Cum

As per Civil Data No.8A

Data-Cir.Sump
8 Providing High Yield Strength Deformed Steel bars (Fe 415 Grade as per IS : 1786 and as
amended upto date) of different diameters including labour charges for cutting bending to
required size shapes, placing in position with cover blocks of approved materials and size and
tying firmly with M.S. Binding wire of 20 SWG forming grills for reinforcement work as per
approved designs and drawings including cost and conveyance of deformed steel bars,
including all wastage such as overlaps, welded joints, chairs spacer bars including cost and
conveyance of binding wire cover blocks and all incidental, opeartional labour charges
including sales and other taxes on all materials etc., complete for finished item of work in all
floors (APSS No.126) (Payment will be made on the basis of weight of fabrication deformed
bars only) (No re-rolled steel shall be allowed) complete for (8 mm to 40 mm).

Unit 1 MT

Rate Rs. 63465.35 per 1 MT

As per Civil Data No.10

Data-Cir.Sump
9 Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm thick with 1kg
of water proof compound per bag of cement laid over roof when it is green including cost of all
materials,, including conveyance charges of materials and including all operational, incidental
and labour charges for mixing mortar, laying, rendering smooth and thread lining, curing,
rounding off junctions of wall and slab etc,, complete for finished item of work.

Unit 1 Sqm.

Rate Rs. 447.70 per 1 Sqm

As per Civil Data No.9

Data-Cir.Sump
10 Plastering with CM (1:4), 12 mm thick in singlecoat with. Screened sand with sponge finishing
including cost and coneyance of all meterials hacking surface, scaffolding, leads, lifts and
labour charges etc., complete for CEILING.

Unit 1 Sqm.

Rate Rs. 173.60 per 1 Sqm

As per Civil Data No.13

Data-Cir.Sump
11 Supplying and fixing 50.8 Cm dia C.I. Man hole frame & cover for chamber (Medium weight ) as
per IS:1726-40Kgs. For Circular Sump.

Unit : Each

1 No. cost of 50.8 Cm. dia C.I Man hole frame &cover No. 1 2683 2683.00
vide P.No.87 of Item No.687
Add 13.615 % contractor's Profit & Over Head charges 365.29
Sundries 0.01
Total Rs. 3048.30

Data-Cir.Sump
ABSTRACT FOR COMPOUND WALL

Name of Work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at Maddila


Visakhapatnam in the place of existing A & B staff quarters.

Sl.
Quantity Description of item Rate Unit
No.
Earth work excavation for foundations and depositing on
bank for all lifts and with aninitial lead of 10m including all
operational, incidental, labour charges such as shoring
1 52.929 206.80 1 Cum.
sheeting, planking, strutting, etc. complete for finished item of
work excluding dewatering charges etc. as per SS- 20 B
(APSS 308).

Laying PCC work of mix (1 : 5 : 10) prop. Using 40 mm


gauge hard granite machine crushed metal including cost
2 8.725 and conveyance of all materials, machine mixing, labour 3635.84 1 Cum.
charges, tamping, cruing charges, taxes etc., complete for
foundations.

Supply and placing of the Design Mix Concrete of grade M30


corresponding to IS 456 using WEIGH BATCHER using
minimum cement content of 380 Kg. per Cum with 12mm and
20mm size graded machine crushed hard granite metal
(coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate
( sand) coarse aggregate, water etc., to site and including,
sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching,
3 0.762 9279.49 1 Cum.
machine mixing, laying concrete, Vibrating, curing
etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No.402 including
centering shuttering using adjastable Jack Screws, Props
and Acro span beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc. complete
but excluding cost of steel and its fabrication charges for
finished item of work. FOOTINGS.

ABS-Comp.wall
Sl.
Quantity Description of item Rate Unit
No.

Supply and placing of the Design Mix Concrete of grade M30


corresponding to IS 456 using WEIGH BATCHER using
minimum cement content of 380 Kg. per Cum with 12mm
and 20mm size graded machine crushed hard granite metal
(coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including,
sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching,
4 0.531 12390.15 1 Cum.
machine mixing, laying concrete, vibrating, curing
etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No.402) including
centering shuttering using adjastable Jack Screws, Props
and Acro span beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc. complete
but excluding cost of steel and its fabrication charges for
finished item of work. COLUMNS.

R.R.Masonary Bin C.M.(1:8) Prop. using hard stone other


than granite including cost and conveyance of all materials,
5 35.613 2904.86 1 Cum.
labour charges, curing etc., complete for FOUNDATION AND
BASEMENT.

Masonry work in CM (1:6) prop with Flyash Cement solid


blocks of size 290 x 225 x 140 mm for manufacturing of
flyash solid blocks using flyash of 80 kgs, cement of 15
kgs.Gypsum of 5 kgs. and stone dust including cost and
6 33.334 5746.82 1 Cum.
conveyance of all materials, labour charges, , scaffolding and
curing etc., complete with a compressive strength not
lessthan 50 kg/sqcm for walls for Superstructure Walls.
Foundations and Basements.

Plastering with CM (1:4), 12 mm thick in singlecoat with.


Screened sand with sponge finishing including cost and
7 311.795 coneyance of all meterials hacking surface, scaffolding, 285.98 1 Sq.Mts.
leads, lifts and labour charges etc., complete for INTERIOR
AND EXTERIOR WALLS.

White washing two coats with approved quality of white


cement to give an even shade after thoroughly brushing the
surface to remove all dirt and remains of loose powdered
8 311.795 materials including cost of all materials, labour charges and 37.90 1 Sq.Mts.
incidental such as scaffolding, lift charges etc., complete for
finished item of work, but excluding conveyance charges of
materials

ABS-Comp.wall
Sl.
Quantity Description of item Rate Unit
No.

PAINTING to new WOOD work / Iron work in two coats with


synthetic enamel paint of approved colour, over one coat of
9 22.326 ( primary coat including cost and conveyance of all materials, 154.35 1 Cum.
incidental charges such as sand paper, cleaning the surface,
cost of brushes and putty etc., complete. (Three coats).

Suppying and fixing of MS gate of size 2.45m x 1.83m with


50 mm dia MS pipe "C" class alround the gate suitable hold
fasts 4 nos., so as to fixe in the compound wall, 1 no. of
300mm long MS powder coated aldrop, 2 nos. of powder
coated tower bolts 30 mm long and fixing of 4 mm thich MS
10 2.000 21900.00 Each
sheet centntrally fixed with 12 mm square pipes welded
vertically and diagnally, painting wiht 1 coat of read oxide
primary coat and 2 coats of synthetic enamel paint including
cost and conveyance of all materials, fabrication welding etc.,
complete as directed by the department.

Providing High Yield Strength Deformed Steel bars (Fe 415


Grade as per IS: 432 and as amended upto date) of different
diameters including labour charges for cutting, bending to
required size and shapes, placing in position with cover
blocks of approved materials and size and tying firmly with
M.S. Binding wire of 20 SWG forming grills for reinforcement
work as per approved designs and drawings including cost
and conveyance of deformed steel bars, including all
11 0.194 55138.50 M.T
wastage such as overlaps, welded joints, chairs spacer bars
including cost and conveyance of binding wire cover blocks
and all incidental, opeartional, labour charges such as cutting
bending placing in position, tying etc., including sales and
other taxes on all materials etc., complete for finished item of
work in all floors (APSS No.126) (Payment will be made on
the basis of weight of fabrication deformed bars only) (No re-
rolled steel shall be allowed) complete for (8 mm to 40 mm).

Total:
Add Unforcein items
Say.

ABS-Comp.wall
RACT FOR COMPOUND WALL

ommercial Complex (Cellar+Ground+4Floors) at Maddilapalem,


n the place of existing A & B staff quarters.

Amount

10,945.72

31,722.70

7,070.97

ABS-Comp.wall
Amount

6,579.17

103,450.78

191,564.50

89,167.13

11,817.03

ABS-Comp.wall
Amount

3,446.02

43,800.00

10,696.87

510,260.89
4,122.95
514,383.84

ABS-Comp.wall
COMPOUND WALL (Detailed Estimate)

Name of work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at Maddil


Visakhapatnam in the place of existing A & B staff quarters.
Sl.
Description of item Nos. L B D
No.

Earth work excavation for foundations and


depositing on bank for all lifts and with aninitial lead
of 10m including all operational, incidental, labour
1 charges such as shoring incidental, sheeting,
planking, strutting, etc. complete for finished item of
work excluding dewatering charges etc. as per SS-
20 B (APSS 308).

for alround the building 1x 1 95.35 0.61 0.91


Total :

Laying PCC work of mix (1 : 5 : 10) prop. Using 40


mm gauge hard granite machine crushed metal
2 including cost and conveyance of all materials,
machine mixing, labour charges, tamping, cruing
charges, taxes etc., complete for foundations.

for alround the building 1x 1 95.35 0.61 0.15


Total :

Supply and placing of the Design Mix Concrete of


grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380
Kg. per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate ( sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
3
mixing, laying concrete, Vibrating, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402 including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work.
FOOTINGS.

Gate Footing 2x 2 0.91 0.91 0.23


Total :

Det-Comp.wall
Supply and placing of the Design Mix Concrete of
grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380
Kg. per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
4
mixing, laying concrete, vibrating, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402) including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work.
COLUMNS.

Gate Columns 2x 2 0.23 0.23 2.51


Total: Total :

R.R.Masonary Bin C.M.(1:8) Prop. using hard stone


other than granite including cost and conveyance of
5
all materials, labour charges, curing etc., complete
for FOUNDATION AND BASEMENT.

For first footing


for alround the building 1x 1 95.35 0.45 0.45
For 2nd Footing
for alround the building 1x 1 95.35 0.38 0.45
Total: Total :

Masonry work in CM (1:6) prop with Flyash Cement


solid blocks of size 290 x 225 x 140 mm for
manufacturing of flyash solid blocks using flyash of
80 kgs, cement of 15 kgs.Gypsum of 5 kgs. and
6 stone dust including cost and conveyance of all
materials, labour charges, , scaffolding and curing
etc., complete with a compressive strength not
lessthan 50 kg/sqcm for walls for Superstructure
Walls. Foundations and Basements.

for alround the building 1x 1 95.35 0.23 1.52


Total: Total :

Det-Comp.wall
Plastering with CM (1:4), 12 mm thick in singlecoat
with. Screened sand with sponge finishing including
cost and coneyance of all meterials hacking
7
surface, scaffolding, leads, lifts and labour charges
etc., complete for INTERIOR AND EXTERIOR
WALLS.
compound wall bothsides&top 1x 1 95.35 -- 3.27
Total: Total :
White washing two coats with approved quality of
white cement to give an even shade after
thoroughly brushing the surface to remove all dirt
and remains of loose powdered materials including
8
cost of all materials, labour charges and incidental
such as scaffolding, lift charges etc., complete for
finished item of work, but excluding conveyance
charges of materials
Qty. as per plastering qty. -- -- --
PAINTING to new WOOD work / Iron work in two
coats with synthetic enamel paint of approved
colour, over one coat of ( primary coat including
9 cost and conveyance of all materials, incidental
charges such as sand paper, cleaning the surface,
cost of brushes and putty etc., complete. (Three
coats).
For Gates 2x 2 3.05 -- 1.83
Total :

Suppying and fixing of MS gate of size 2.45m x


1.83m with 50 mm dia MS pipe "C" class alround
the gate suitable hold fasts 4 nos., so as to fixe in
the compound wall, 1 no. of 300mm long MS
powder coated aldrop, 2 nos. of powder coated
tower bolts 30 mm long and fixing of 4 mm thich MS
10
sheet centntrally fixed with 12 mm square pipes
welded vertically and diagnally, painting wiht 1 coat
of read oxide primary coat and 2 coats of synthetic
enamel paint including cost and conveyance of all
materials, fabrication welding etc., complete as
directed by the department.

Gate of size 2.45 x 1.83 mtr. 1x 2 -- -- -


Total :

Det-Comp.wall
Providing High Yield Strength Deformed Steel bars
(Fe 415 Grade as per IS: 432 and as amended upto
date) of different diameters including labour charges
for cutting, bending to required size and shapes,
placing in position with cover blocks of approved
materials and size and tying firmly with M.S. Binding
wire of 20 SWG forming grills for reinforcement
work as per approved designs and drawings
including cost and conveyance of deformed steel
bars, including all wastage such as overlaps,
11
welded joints, chairs spacer bars including cost and
conveyance of binding wire cover blocks and all
incidental, opeartional, labour charges such as
cutting bending placing in position, tying etc.,
including sales and other taxes on all materials etc.,
complete for finished item of work in all floors
(APSS No.126) (Payment will be made on the basis
of weight of fabrication deformed bars only) (No re-
rolled steel shall be allowed) complete for (8 mm to
40 mm).

Ground floor
Footings (Qty as above) 0.762 0.150 MT/1Cum
Columns (Qty as above) 0.531 0.150 MT/1Cum
Total Total :

Det-Comp.wall
MPOUND WALL (Detailed Estimate)

ommercial Complex (Cellar+Ground+4Floors) at Maddilapalem,


in the place of existing A & B staff quarters.

Qty

52.929
52.929 Cum

8.725
8.725 Cum

0.762
0.762 Cum

Det-Comp.wall
0.531
0.531 Cum

19.308

16.305
35.613 Cum

33.334
33.334 Cum

Det-Comp.wall
311.795
311.795 Sqm

311.795 Sqm

22.326
22.326 Sqm

2.000
2.000 Nos

Det-Comp.wall
0.114
0.080
0.194 MT

Det-Comp.wall
ABSTRACT FOR SEPTIC TANK.

Name of Work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at Maddila


Visakhapatnam in the place of existing A & B staff quarters.

Sl.
QTY. Description of item RATE UNIT
No.

Earth work excavation for foundations and depositing on


bank for all lifts and with an initial lead of 10m including all
operational, incidental, labour charges such as shoring
1 74.586 incidental, sheeting, planking, strutting, etc. complete for 206.80 1 Cum.
finished item of work .in ordinary soils by manual means
upto 3.00mt depth excluding dewatering charges etc. as per
SS- 20 B (APSS 308)

Laying PCC work of mix (1 : 5 : 10) prop. Using 40 mm


gauge hard granite machine crushed metal including cost
2 5.228 and conveyance of all materials, machine mixing, labour 3322.25 1 Cum.
charges, tamping, cruing charges, taxes etc., complete for
foundations.

Supply and placing of the Design Mix Concrete of grade


M30 corresponding to IS 456 using WEIGH BATCHER
using minimum cement content of 380 Kg. per Cum with
12mm and 20mm size graded machine crushed hard
granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement,
fine aggregate (sand) coarse aggregate, water etc., to site
and including, sales & other taxes on all materials including
all operational, incidental and labour charges such as weigh
3 13.082 batching, machine mixing, laying concrete, vibrating, curing 14806.50 1 Cum.
etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No.402) including
centering shuttering using adjastable Jack Screws, Props
and Acro span beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross members
etc., Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its fabrication
charges for finished item of work FOR SEPTIC TANK SIDE
WALLS .

ABS-S.Tank
Sl.
QTY. Description of item RATE UNIT
No.

Supply and placing of the Design Mix Concrete of M 30


corresponding to IS 456 using WEIGH BATCHER using
minimum cement content of 380 Kg. per Cum with 12mm
and 20mm size graded machine crushed hard granite metal
(coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including,
sales & other taxes on all materials including all operational,
incidental and labour charges such as weigh batching,
4 2.097 machine mixing, laying concrete, vibrate, curing 6346.40 1 Cum.
etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No.402)including
centering shuttering using adjastable Jack Screws, Props
and Acro span beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross members
etc., Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its fabrication
charges for finished item of work PRECAST SLABS FOR
COVER OF SEPTIC TANK.

Providing impervious coat to exposed RCC roof slab surface


with CM(1:3), 20mm thick with 1kg of water proof compound
per bag of cement laid over roof when it is green including
cost of all materials,, including conveyance charges of
5 20.130 447.70 1 Cum.
materials and including all operational, incidental and labour
charges for mixing mortar, laying, rendering smooth and
thread lining, curing, rounding off junctions of wall and slab
etc,, complete for finished item of wor IN SIDE WALLS.

Plastering with CM (1:4), 12 mm thick in singlecoat with.


Screened sand with sponge finishing including cost and
6 115.299 coneyance of all meterials hacking surface, scaffolding, 285.98 `1Sqm
leads, lifts and labour charges etc., complete for OUT SIDE
WALLS.

Filling with useful available excavated earth (excluding rock)


in trenches, sides of foundations and basement with initial
lead in layers not exceeding 15 cm thick,consolidating each
7 17.604 deposited layer by watering and ramming including cost and 24.65 1 Cum.
conveyance of water to work site and all operational,
incidental, labour charges, hire charges of T & P etc.,
complete for finisheditem of work. (APSS NO. 309 & 310).

ABS-S.Tank
Sl.
QTY. Description of item RATE UNIT
No.

Providing High Yield Strength Deformed Steel bars (Fe 415


Grade as per IS: 432 and as amended upto date) of
different diameters including labour charges for cutting,
bending to required size and shapes, placing in position with
cover blocks of approved materials and size and tying firmly
with M.S. Binding wire of 20 SWG forming grills for
reinforcement work as per approved designs and drawings
including cost and conveyance of deformed steel bars,
8 1.518 including all wastage such as overlaps, welded joints, chairs 55138.50 1 M.T.
spacer bars including cost and conveyance of binding wire
cover blocks and all incidental, opeartional, labour charges
such as cutting bending placing in position, tying etc.,
including sales and other taxes on all materials etc.,
complete for finished item of work in all floors (APSS
No.126) (Payment will be made on the basis of weight of
fabrication deformed bars only) (No re-rolled steel shall be
allowed) complete for (8 mm to 40 mm).

Supplying and fixing of 100 mm dia P.V.C. Plain Tee of


Prince / Sudhakar make in position with air tight jointing
9 4.000 materials including cost and conveyance of all materials, 122.70 Nos.
labour charges, fixing etc., complete as directed by the
department.

Masonry work in CM (1:4) prop with Flyash Cement solid


blocks of size 230 x 100 x 140 mm for manufacturing of
flyash solid blocks using flyash of 80 kgs, cement of 15
kgs.Gypsum of 5 kgs. and stone dust including cost and
10 0.670 6570.82 Cum.
conveyance of all materials, labour charges,, scaffolding and
curing etc., complete with a compressive strength not
lessthan 50 kg/sqcm for walls for Superstructure Walls for
Baffle walls.

Plastering with CM in 2 coats of 12 mm thick, base coat in


CM (1:4) of 8mm thick and top coat in CM (1:2) of 4mm
thick with sponze finishing to suit including cost and
11 13.762 conveyance of all materials and water to work site and all 402.65 Sqm.
operational incidental labour charges such as mixing mortar,
lift charges, curring etc., complete for finished item of work
as per SS No. 901, 904 for Baffel walls.

Total:
Add L.S
Say.

ABS-S.Tank
STRACT FOR SEPTIC TANK.

ommercial Complex (Cellar+Ground+4Floors) at Maddilapalem,


in the place of existing A & B staff quarters.

AMOUNT

15,424.38

17,368.72

193,698.63

ABS-S.Tank
AMOUNT

13,308.40

9,012.20

32,973.21

433.94

ABS-S.Tank
AMOUNT

83,700.24

490.82

4,402.45

5,541.20

376,354.20
11,865.45
388,219.65

ABS-S.Tank
DETAILED ESTIMATE FOR SEPTIC TANK
Name of work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at Ma
Visakhapatnam in the place of existing A & B staff quarters.
Sl.
Description of item Nos. L B D
No.
1 Earth work excavation for foundations and
depositing on bank for all lifts and with an initial lead
of 10m including all operational, incidental, labour
charges such as shoring incidental, sheeting,
planking, strutting, etc. complete for finished item of
work .in ordinary soils by manual means upto
3.00mt depth excluding dewatering charges etc. as
per SS- 20 B (APSS 308)

For septic tank 1x 1 12.06 2.89 2.14


2 Laying PCC work of mix (1 : 5 : 10) prop. Using 40
mm gauge hard granite machine crushed metal
including cost and conveyance of all materials,
machine mixing, labour charges, tamping, cruing
charges, taxes etc., complete for foundations.
Septic tank concrete 1x 1 12.06 2.89 0.15
3 Supply and placing of the Design Mix Concrete of
grade M30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380
Kg. per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
mixing, laying concrete, vibrating, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402) including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work FOR
SEPTIC TANK SIDE WALLS .
Septic tank long walls 1x 2 11.46 0.23 2.14
Septic tank short walls 1x 2 1.83 0.23 2.14
Total Total :

Det-S.Tank
Sl.
Description of item Nos. L B D
No.
4 Supply and placing of the Design Mix Concrete of M
30 corresponding to IS 456 using WEIGH
BATCHER using minimum cement content of 380
Kg. per Cum with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
mixing, laying concrete, vibrate, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402)including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross
members etc., Complete, laying concrete, vibrating,
curing etc. complete but excluding cost of steel and
its fabrication charges for finished item of work
PRECASTE SLABS FOR COVER OF SEPTIC
TANK.
Cover slab 1x 1 11.46 1.83 0.10

5 Providing impervious coat to exposed RCC roof


slab surface with CM(1:3), 20mm thick with 1kg of
water proof compound per bag of cement laid over
roof when it is green including cost of all materials,,
including conveyance charges of materials and
including all operational, incidental and labour
charges for mixing mortar, laying, rendering smooth
and thread lining, curing, rounding off junctions of
wall and slab etc,, complete for finished item of work
for Septick tank bottom.
Inside Tank Bottom 1 x 1 11.00 1.83
6 Plastering with CM (1:4), 12 mm thick in singlecoat
with. Screened sand with sponge finishing including
cost and coneyance of all meterials hacking
surface, scaffolding, leads, lifts and labour charges
etc., complete for WALLS.
Inside tank long walls 1 x 1 11.00 2.14
Inside tank short walls 1 x 1 1.83 2.14
Out side plastering 1 x 1 27.50 -- 2.24
Slab Top 1 x 1 11.46 -- 2.29
Total Total :

Det-S.Tank
Sl.
Description of item Nos. L B D
No.
7 Filling with useful available excavated earth
(excluding rock) in trenches, sides of foundations
and basement with initial lead in layers not
exceeding 15 cm thick,consolidating each deposited
layer by watering and ramming including cost and
conveyance of water to work site and all
operational, incidental, labour charges, hire charges
of T & P etc., complete for finisheditem of work.
(APSS NO. 309 & 310).
Balance 1x 1 28.68 0.31 1.98
8 Providing High Yield Strength Deformed Steel bars
(Fe 415 Grade as per IS: 432 and as amended upto
date) of different diameters including labour charges
for cutting, bending to required size and shapes,
placing in position with cover blocks of approved
materials and size and tying firmly with M.S. Binding
wire of 20 SWG forming grills for reinforcement
work as per approved designs and drawings
including cost and conveyance of deformed steel
bars, including all wastage such as overlaps,
welded joints, chairs spacer bars including cost and
conveyance of binding wire cover blocks and all
incidental, opeartional, labour charges such as
cutting bending placing in position, tying etc.,
including sales and other taxes on all materials etc.,
complete for finished item of work in all floors
(APSS No.126) (Payment will be made on the basis
of weight of fabrication deformed bars only) (No re-
rolled steel shall be allowed) complete for (8 mm to
40 mm).

--
9
Supplying and fixing of 100 mm dia P.V.C. Plain Tee
of Prince / Sudhakar make in position with air tight
jointing materials including cost and conveyance of
all materials, labour charges, fixing etc., complete
as directed by the department.

Supply and fixing of 101.60MM S.W.G. 1 st class 1x 4 -- --


10 Tee of approved make in position with air tight
Masonryjoints,
cement work inincluding
CM (1:4)cost
propand conveyance
with of all
Flyash Cement
materials, etc., complete for INLET AND
solid blocks of size 230 x 100 x 140 mm for OUTLET
CONNECTION
manufacturing of flyashFOR
solidSEPTIC TANK.flyash of
blocks using
80 kgs, cement of 15 kgs.Gypsum of 5 kgs. and
stone dust including cost and conveyance of all
materials, labour charges,, scaffolding and curing
etc., complete with a compressive strength not
lessthan 50 kg/sqcm for walls for Superstructure
Walls for Baffle walls.

Det-S.Tank
Sl.
Description of item Nos. L B D
No.
1x 2 1.83 0.10 1.83
11
Plastering with CM in 2 coats of 12 mm thick, base
coat in CM (1:4) of 8mm thick and top coat in CM
(1:2) of 4mm thick with sponze finishing to suit
including cost and conveyance of all materials and
water to work site and all operational incidental
labour charges such as mixing mortar, lift charges,
curring etc., complete for finished item of work as
per SS No. 901, 904 for Baffel walls.

1x 2 1.83 0.10 --
2x 2 1.83 1.83 --
Total Total :

Det-S.Tank
LED ESTIMATE FOR SEPTIC TANK
ommercial Complex (Cellar+Ground+4Floors) at Maddilapalem,
in the place of existing A & B staff quarters.

Qty

74.586 Cum.

5.228 Cum.

11.281
1.801
13.082 Cum

Det-S.Tank
Qty

2.097 Cum.

20.130 Sqm

23.540
3.916
61.600
26.243
115.299 Sqm

Det-S.Tank
Qty

17.604 Cum

1.518 MT

4.000 Nos

Det-S.Tank
Qty

0.670 Cum

0.366 Sqm
13.396 Sqm
13.762 Sqm

Det-S.Tank
ABSTRACT FOR DISMANTLING
Name of Work :- Construction of Commercial Complex (Cellar+Ground+4Floors) at
Maddilapalem, Visakhapatnam in the place of existing A & B staff quarters.

Sl.
Quantity Description of item Rate Unit
No.

Demolition inlcuding stacking of serviceable materials


1 52.799 and disposal of unserviceable materials with in 100 2198.90 1 Cum.
meters lead.

Demolition inlcuding stacking of serviceable materials


2 232.776 and disposal of unserviceable materials with in 100 2081.80 1 Cum.
meters lead.

Dismantling door windows and clear storey windows


ventilators etc., (wood or steel) shutters including
3 144.392 chowkhats architraves holdfast and other attachments 191.30 1 Cum.
etc., complete and stacking them with in 100 meters
lead.
Total:
Cost of useful materials that are Approx.
4 Qty Amount
obtained while dismantling. Rate
Door of Size : 1.05 x 1.98mts 4 400.00 1,600.00
Door of Size : 0.91 x 1.98mts 12 350.00 4,200.00
Door of Size : 0.76 x 1.98mts 24 300.00 7,200.00
Window of Size : 1.50 x 1.20mts 4 400.00 1,600.00

Window of Size : 1.20 x 1.20mts 8 300.00 2,400.00

Window of Size : 0.91 x 1.20mts 21 200.00 4,200.00


Iron Grill -- LS 2,000.00
Old Steel -- LS 50,000.00
Total : 73,200.00
Add L.S for Unforceen items
Say. Total

ABS-Dism
ABSTRACT FOR DISMANTLING
tion of Commercial Complex (Cellar+Ground+4Floors) at
hapatnam in the place of existing A & B staff quarters.

Amount

116,099.72

484,593.08

27,622.19

628,314.99

-73,200.00
4,885.01
560,000.00

ABS-Dism
DATAS FOR DISMANTLING

As per Common SSR 2015-16

Name of Work :- Construction of Commercial Complex


(Cellar+Ground+4Floors) at Maddilapalem, Visakhapatnam in the place of
existing A & B staff quarters.

1 Demolition inlcuding stacking of serviceable materials and disposal of unserviceable materials with
100 meters lead.
RCC work Standard data No.298
Unit - 1 Cum.
Labour
Mazdoor (Unskilled) Day 4.32 320.00
Add: M.L 40% on labour charges 1382.40 X 40%

Total Rs.
Add 13.615 % contractor's Profit & Over Head charges
Sundries
Total Rs.

Data-Dism
2 Demolition inlcuding stacking of serviceable materials and disposal of unserviceable materials with
100 meters lead.

Brick work Standard data No.299


Unit - 1 Cum.
Labour
Mazdoor (Unskilled) Day 4.09 320.00
Add: M.L 40% on labour charges 1308.80 X 40%
Total Rs.
Add 13.615 % contractor's Profit & Over Head charges
Sundries
Total Rs.

Data-Dism
3 Dismantling door windows and clear storey windows ventilators etc., (wood or steel) shutters includ
chowkhats architraves holdfast and other attachments etc., complete and stacking them with in 100
meters lead.

Standard data No.301


Unit - 1 Sqm.
Labour
Mason IInd class Day 0.10 375.00
Black smith 2nd class Day 0.05 375.00
Mazdoor (Unskilled) Day 0.20 320.00
Add: M.L 40% on labour charges 120.25 X 40%
Total Rs.
Add 13.615 % contractor's Profit & Over Head charges
Sundries
Total Rs.

Data-Dism
4 Extra over item 14.2 ii for cutting steel bars in RCC of RB work (Sectional area of RCC or RB work
be measured) details of cost for 1 Sqm. of sectional area.

Standard data No.300


Unit - 1 Sqm.
Labour
Black smith 2nd class Day 0.50 375.00
Mazdoor (Unskilled) Day 0.50 320.00
Add: M.L 40% on labour charges 347.50 X 40%
Total Rs.
Add 13.615 % contractor's Profit & Over Head charges
Sundries
Total Rs.

Data-Dism
DATAS FOR DISMANTLING

As per Common SSR 2015-16

:- Construction of Commercial Complex


s) at Maddilapalem, Visakhapatnam in the place of
existing A & B staff quarters.

of serviceable materials and disposal of unserviceable materials with in

1382.40
552.96

1935.36
263.50
0.04
2198.90

Data-Dism
of serviceable materials and disposal of unserviceable materials with in

1308.80
523.52
1832.32
249.47
0.01
2081.80

Data-Dism
d clear storey windows ventilators etc., (wood or steel) shutters including
st and other attachments etc., complete and stacking them with in 100

37.50
18.75
64.00
48.10
168.35
22.92
0.03
191.30

Data-Dism
ing steel bars in RCC of RB work (Sectional area of RCC or RB work to
or 1 Sqm. of sectional area.

187.50
160.00
139.00
486.50
66.24
0.01
552.75

Data-Dism
LEAD CHART

(As per Common S.S.R. 2015-2016)


Name of work :- Construction of Commercial Complex (Cellar + Ground + 4Floors) at Maddilapalem, Visakhapatnam in the place o
quarters.

Deduct
Net
Sl. Source of Lead in Conveyance 13.615%
Description of material Unit Initial cost Conveyance
No. supply K.M. charges contractor
charges
profit
1 2 3 4 5 6 7 8 9
1 6 MM Hard granite metal Aganampudi 27 1 Cum 735.00 343.10 -41.12 301.98
2 10 mm hard granite metal Aganampudi 27 1 Cum 935.00 343.10 -41.12 301.98
3 12.5 mm hard granite metal Aganampudi 27 1 Cum 1097.50 343.10 -41.12 301.98
4 20 mm hard granite metal Aganampudi 27 1 Cum 1365.00 343.10 -41.12 301.98
5 40 mm hard granite metal Aganampudi 27 1 Cum 845.00 343.10 -41.12 301.98
6 Sand for concrete(unscreened) Srikakulam 104 1 Cum 610.00 1144.60 -137.17 1007.43
7 Sand for filling Srikakulam 104 1 Cum 460.00 1144.60 -137.17 1007.43
8 Sand for mortar Srikakulam 104 1 Cum 677.00 1144.60 -137.17 1007.43
9 Gravel/quarryspot Yandada 8 1 Cum 103.00 107.50 -12.89 94.61
10 Rough stone (RR Masonary OTG) Yandada 8 1 Cum 180.00 107.50 -12.89 94.61
11 Filling earth Yandada 8 1 Cum 107.50 -12.89 94.61
12 Steel (HYSD Bars) Local 1 MT. 42000.00 GO RT No.419 June-2015 rate
13 Cement Local 1 MT. 5873.00
Flyash Lime Solid Bricks
14 size: 29 x 22.5 x 14 Cm. Parawada 33 Each 24.00
50 Kgs./1 Sq.Cm.
Flyash Lime Solid Bricks
15 Size 29 x 10 x 14 Cm. Parawada 33 Each 11.00
50 Kgs./1 Sq.Cm.

Certificate:

LEAD CHART
Certified that the lead charges are calculated as per guidelines at serial No.15 and 16 of Preamble of SOR 2015-16.Hence 1.00 km lead de

LEAD CHART
LEAD CHART

er Common S.S.R. 2015-2016)


r + Ground + 4Floors) at Maddilapalem, Visakhapatnam in the place of existing A & B staff
quarters.

GRAND
Reference
TOTAL

10 11
Item No.33a, P.No.245 1036.98
Item No.33b, P.No.245 1236.98
Item No.33c, P.No.246 1399.48
Item No.33d, P.No.246 1666.98
Item No.33f, P.No.246 1146.98
Item No.36a, P.No.249 1617.43
Item No.36b, P.No.249 1467.43
Item No36c, P.No.249 1684.43
Item No.34, P.No.249 197.61
Item No.22a, P.No.244 274.61
94.61
GO RT No.419 June-2015 rate 42000.00
5873.00

Item No.10, P.No.1 24.00

Item No.13, P.No.1 11.00

LEAD CHART
serial No.15 and 16 of Preamble of SOR 2015-16.Hence 1.00 km lead deducted from total lead.

LEAD CHART
M O R TAR C HAR T
(As per Common S.S.R. 2015-16)
Name of work : Construction of Commercial Complex (Cellar+Ground+4Floors) at
. Maddilapalem, Visakhapatnam in the place of existing A & B
staff Rate of .cement :Rs.5873/-quarters.
Per M.T.

Index Sl. Quantity Rate Amount


MORTARS Unit
Code No.
1 2 3 4 5 6.000 7
BLD-CSTN Cement mortar (1:1)
1-1 1 Unit : 1 Cum
A) MATERIALS
Cement Kg. 1440.00 5.873 8457.12
Sandscreened (Including 5% wastage) Cum. 1.05 1684.430 1768.65
C) LABOUR
Man mazdoor for mixing motar (320 +
Day 0.20 448.000 89.60
40%)
Grand total 10315.37
BLD-CSTN Cement mortar (1:1.5)
1-2 2 Unit : 1 Cum
A) MATERIALS
Cement Kg. 960.00 5.873 5638.08
Sandscreened (Including 5% wastage) Cum. 1.05 1684.430 1768.65
C) LABOUR
Man mazdoor for mixing motar (320 +
Day 0.20 448.000 89.60
40%)
Grand total 7496.33
BLD-CSTN Cement mortar (1:2)
1-3 3 Unit : 1 Cum
A) MATERIALS
Cement Kg. 720.00 5.873 4228.56
Sandscreened (Including 5% wastage) Cum. 1.05 1684.430 1768.65
C) LABOUR
Man mazdoor for mixing motar (320 +
Day 0.20 448.000 89.60
40%)
Grand total 6086.81
BLD-CSTN Cement mortar (1:3)
1-4 4 Unit : 1 Cum
A) MATERIALS
Cement Kg. 480.00 5.873 2819.04
Sandscreened (Including 5% wastage) Cum. 1.05 1684.430 1768.65
C) LABOUR
Man mazdoor for mixing motar (320 +
Day 0.20 448.000 89.60
40%)
Grand total 4677.29
BLD-CSTN Cement mortar (1:4)
1-5 5 Unit : 1 Cum
A) MATERIALS
Cement Kg. 360.00 5.873 2114.28
Sandscreened (Including 5% wastage) Cum. 1.05 1684.430 1768.65
C) LABOUR

MORTAR
Index Sl. Quantity Rate Amount
MORTARS Unit
Code No.
1 2 3 4 5 6.000 7
Man mazdoor for mixing motar (320 +
Day 0.20 448.000 89.60
40%)
Grand total 3972.53
BLD-CSTN Cement mortar (1:5)
1-6 6 Unit : 1 Cum
A) MATERIALS
Cement Kg. 288.00 5.873 1691.42
Sandscreened (Including 5% wastage) Cum. 1.05 1684.430 1768.65
C) LABOUR
Man mazdoor for mixing motar (320 +
Day 0.20 448.000 89.60
40%)
Grand total 3549.68
BLD-CSTN Cement mortar (1:6)
1-7 7 Unit : 1 Cum
A) MATERIALS
Cement Kg. 240.00 5.873 1409.52
Sandscreened (Including 5% wastage) Cum. 1.05 1684.430 1768.65
C) LABOUR
Man mazdoor for mixing motar (320 +
Day 0.20 448.000 89.60
40%)
Grand total 3267.77
BLD-CSTN Cement mortar (1:8)
1-8 8 Unit : 1 Cum
A) MATERIALS
Cement Kg. 180.00 5.873 1057.14
Sandscreened (Including 5% wastage) Cum. 1.05 1684.430 1768.65
C) LABOUR
Man mazdoor for mixing motar (320 +
Day 0.20 448.000 89.60
40%)
Grand total 2915.39

MORTAR
ABSTRACT FOR INTERNAL WATER SUPPLY AND SANITARY
Name of Work :- Construction of G+7 Flats Under Affordable Housing.Scheme in partnership at
Balaga(V) ,Srikakulam (M) ,Srikakulam (Dist).
Sl.
Quantity Description of item Rate Unit
No.

Supply and laying of ASHIRVAD/ Ajay/ Astral flowguard or


equivalent CPVC pipes conforming to (IS 15778:2007) with
malleable specials to meet the requirement of ASTMD-2846
and are produced in CTS (copper tube sizes 1/2" ton 2")
such as Tees, Elbows, Check nuts, unions, bushes, etc.,
Solvent Cement including fixing in walls ceiling floors
1
including for necessary exacavation in all sorts of soils,
chasing in the walls etc., refilling consolidation with the
excavated earth & Making bores in cement mortar and
complete. When making a transition use metal threads
fittings, including all taxes for finished item of work as
directed by the Engineer in charge. Sump to over head tank.

A 429.600 54 mm dia OD pipe 596.50 RMT


B 745.600 28.60mm dia OD pipe 240.90 RMT
Supplying and Fixing of 12.70mm NP short bib tap indian
make heavy duty, Seiko or equivalent fancy type deluxe with
2 64.000 necessary fittings etc., complete including cost and 293.15 EACH
conveyance of all materials, all taxes and all labour charges
for finished item.
Supplying and Fixing of 12.70mm NP long body Bib tap
indian, Seiko/Nice or equivalent fancy type deluxe with
3 192.000 necessary fittings etc., complete including cost and 723.75 EACH
conveyance of all materials, all taxes and all labour charges
for finished item.
Supplying and fixing of 50 mm dia G.M.Peet Valve as per
I.S.778 1st Class of approved make Zoloto including cost
4 64.000 4216.25 EACH
and conceyance of all materials, labour charges etc.,
complete.
Supplying and Fixing of 12.70mm NP Angle stop cock
indian make 400gms, Seiko or equivalent fancy type deluxe
5 192.000 with necessary fittings etc., complete including cost and 538.55 EACH
conveyance of all materials, all taxes and all labour charges
for finished item of work in all floors.

Supply and fixing of 38.1 mm C.P. waste coupling Half or


6 128.000 269.30 EACH
Full Thead 1st Quality Indian make Parryware of equivalent.
SANITARY FITTINGS
Supply and Fixing Orissa Pan white glazed W.C.1st quality
7 64.000 ISI marked conforming to IS 2556-Part-3-1981 with "P" Or 4077.00 EACH
"S" Trap. 580 mm x 440 mm.

Supplying & Fixing Indian make Flat Back Wash Hand Basin
(HSW/Parryware/Neycer) 1st quality with single C.P.Pillar
cock, conforming to IS:2556-Part-4-1972 with waste fittings
like 38.10mm waste coupling, rubber plug, chain, 32 mm
nominal size C.P fitting with parallel pipe thread conforming
to IS/:2963-1979 and fitted with 12.70mm dia. Chromium
Plated Pillar tap of 1st quality Indian make 400 grams
8 64.000 Seiko / Esso or equivalent etc., complete with standard CI 1761.05 EACH
brackets including wooden block, 31.75 mm PVC flexible
waste pipe of 914.4mm long, 15mm inlet PVC connection
with unions complete, including cutting and making good the
walls where ever required for the following sizes etc.,
complete for different floors, including cost, all taxes and
conveyance of all materials and all labour charges etc.,
complete for finished item of work.

Supplying and fixing of 3" dia P.V.C Nanhay Trap prince /


Sudhakar or any ISI Brand with jally including cost and
9 224.000 115.90 EACH
conveyance of all material and labour charges etc.,
complete.
Supplying and fixing 110 mm (4") dia., PVC Vent pipe of
Prince /Sudhakar make and jointing and making holes and
10 347.240 redoing the same in good condition including cost and 273.05 1 RMT
conveyance of material, Labour charges Fixing etc.,
complete.
Supplying and fixing 160 mm (6") dia., PVC pipe of
Prince /Sudhakar make of 4 Kg/ Sq.Cm. and jointing and
11 64.430 making holes and redoing the same in good condition 536.10 1 RMT
including cost and conveyance of material, Labour charges
Fixing etc., complete.
Supplying and fixing 75 mm (3") dia., PVC Pipe of Prince
/Sudhakar make of 4 Kg/Sq.Cm. and jointing and making
12 422.120 holes and redoing the same in good condition including cost 207.95 1 RMT
and conveyance of material, Labour charges Fixing etc.,
complete.
Supplying and fixing 150 mm x 100 mm SWG GULLY TRAP
of ISI make conforming to ISI 651 & 4127 with C.I Grating
13 48.000 288.60 EACH
including Cost and Conveyance of all materials etc.,
complete.
Constructing brick masonry inspection chamber of size
457.2 mm x 457.2 mm (1'6"x1'6") in CM 1:6 prop. upto
914.4 mm (3'0") and fitted with light weight 457.2 mm x
14 8.000 3109.69 EACH
457.2 mm (1'6"x1'6") C.I frame and cover of 20 Kg.
including cost all taxes and conveyance of all materials etc.,
complete for finished item of work.
Supplying and fixing 110mm dia., PVC Vent Cowl of
Prince/Sudhakar make suitable for Vent pipe with air tight
15 8.000 21.60 EACH
joint including cost and of all material, Labour charges Fixing
etc., complete.
Constructing 904.0 mm (30) dia brick masonry inspection
chamber as per IS - 4111: Part-1:1986 with cement mortar
(1:6) prop using 2nd Class Clay Bricks of 225 mm thick from
approved source having a minimum crushing strength of 5
N/sq.mm including plastering with cement mortar 1:3 prop;
thick both inside and outside fitted with 20 dia RCC
manhole covers and frames including excavating pits up to a
depth of 904 mm (3'-0") in all sorts of soils (exculding rock)
16 3.000 8881.30 EACH
and laying cement conrete (1:4:8) 150 mm thick using 40
mm HBG Metal and P.C.C. 1:2:4 benching and channel 100
mm thick as per Standard specification and including cost
and conveyance of all materials like cement, sand, bricks,
water etc., to site, cost of on all materials and all incidental
and operational, labour charges like mixing cement mortar,
constructing masonry, lift charges, curing etc., complete for
finished item of work as per Standard specification.

Supplying and fixing of 110.00 mm dia P.V.C. Door Bends


Prince/Sudhakar are equivalent make suitable for bath room
17 64.000 conneciton including cost and conveyance of all materials 94.30 EACH
jointing labour chareges for fixing etc. complete as directed
by the Department.
Supplying and fixing of 110 mm dia P.V.C. Door Single Tee
Prince/ Sudhakar are equivalent make suitable for bath
18 64.000 room conneciton including cost and conveyance of all 147.70 EACH
materials jointing labour chareges for fixing etc. complete as
directed by the Department.
Supplying and fixing of 76.20 mm dia P.V.C. Door Bends
Prince/Sudhakar are equivalent make suitable for bath room
19 192.000 conneciton including cost and conveyance of all materials 76.15 EACH
jointing labour chareges for fixing etc. complete as directed
by the Department.
Supplying and fixing of 75 mm dia P.V.C. Door Tee
Prince/Sudhakar are equivalent make suitable for bath room
20 192.000 conneciton including cost and conveyance of all materials 82.95 EACH
jointing labour chareges for fixing etc. complete as directed
by the Department.
Constructing Brick masonry chamber over the gully trap or
peet valve and fitted with 304.8 x 228.6 m size CI frame and
21 48.000 538.55 EACH
hinged cover including plastering and finishing etc.,
complete.
Supplying and fixing of 110 mm dia P.V.C.Single 'Y' junction
with Door Prince/Sudhakar are equelent make suitable for
22 64.000 bath room connection including cost and conveyance of all 84.10 Nos
materials jointing labout charges for fixing etc.,complete as
directed by the Department.
Supplying and fixing of 76.20 mm dia P.V.C.Single 'Y'
junction with Door Prince/Sudhakar are equelent make
23 192.000 suitable for bath room connection including cost and 44.35 Nos
conveyance of all materials jointing labout charges for fixing
etc.,complete as directed by the Department.

TOTAL
Add L.S for unforceen items
Say. TOTAL:
D SANITARY
eme in partnership at

Amount

256,256.40
179,615.04

18,761.60

138,960.00

269,840.00

103,401.60

34,470.40
260,928.04

112,707.20

25,961.60

94,813.88

34,540.92

87,779.85

13,852.80
24,877.56

172.80
26,643.90

6,035.20

9,452.80

14,620.80

15,926.20

25,850.40

5,382.40
8,515.20

1,769,366.59
633.41
1,770,000.00
DATAS INTERNAL WS & SF

As per Common SSR 2016-2017

Name of Work :- PATRUNIVALASA,(v) SRIKAKULAM

WATER SUPPLY WORK

Supply and laying of ASHIRVAD/Ajay/Astral flowguard or equivalent CPVC


conforming to (IS 15778:2007) with malleable specials to meet the requireme
ASTMD-2846 and are produced in CTS (copper tube sizes 1/2" ton 2") suc
Tees, Elbows, Check nuts, unions, bushes, etc., Solvent Cement including
1 in walls ceiling floors including for necessary exacavation in all sorts of
chasing in the walls etc., refilling consolidation with the excavated earth & M
bores in cement mortar and complete. When making a transition use m
threads fittings, including all taxes for finished item of work as directed b
Engineer in charge. Sump to over head tank.

A For 54 mm dia OD pipe SDR 13.5

1.00 RMT Cost of pipe as per SSR Item No.819 P.No.91 Rs.
Add 13.615 % contractor's Profit & Over Head charges
sundries
total Rs.
B For 28.60 mm dia OD pipe SDR 13.5

1.00 RMT Cost of pipe as per SSR Item No.816 , P.No.9 Rs.

Add 13.615 % contractor's Profit & Over Head charges

Sundries

Total Rs.

Data-int.WS
C For 15.90 mm dia OD pipe SDR 13.5

1.00 RMT Cost of pipe as per SSR Item No.814 P.No.91 Rs.

Add 13.615 % contractor's Profit & Over Head charges

Sundries

Total Rs.

Data-int.WS
d For 34.90 mm dia OD pipe SDR 13.5

1.00 RMT Cost of pipe as per SSR Item No.817 P.No.91 Rs.
Add 13.615 % contractor's Profit & Over Head charges
sundries
total Rs.

Supplying and Fixing of 12.70mm NP short bib tap indian make heavy duty, S
or equivalent fancy type deluxe with necessary fittings etc., complete inclu
2
cost and conveyance of all materials, all taxes and all labour charges for fin
item.

Unit: Each

1 No. cost of 12.70 mm NP. Bib Tap


vide Item no.182, P.No.150 Rs.
Add 13.615 % contractor's Profit & Over Head charges
Sundries
Total Rs.

Supplying and Fixing of 12.70mm NP long body Bib tap indian, fancy type d
3 with necessary fittings etc., complete including cost and conveyance o
materials, all taxes and all labour charges for finished item.

Unit: Each
1 No. cost of 12.7 mm NP. Long body Bib Tap
vide Item no.194, P.No.150 Rs.
Add 13.615 % contractor's Profit & Over Head charges
Sundries
Total Rs.

Supplying and fixing of50 mm dia G.M.Peet Valve as per I.S.778 1st Cla
4 approved make Zoloto including cost and conceyance of all materials, la
charges etc., complete.

Data-int.WS
Unit: Each

1 No. cost of G.M.Peet valve vide item No.236 P.No.152 Rs.


Add 13.615 % contractor's Profit & Over Head charges
Sundries
Total Rs.

Data-int.WS
Supplying and Fixing of 12.70mm NP Angle stop cock indian make 400
Seiko or equivalent fancy type deluxe with necessary fittings etc., com
5
including cost and conveyance of all materials, all taxes and all labour charge
finished item of work in all floors.

Unit: Each

1 No. cost of 12.70 mm Angle stop cock Rs.

vide item No.178 P.No.78

Add 13.615 % contractor's Profit & Over Head charges

Sundries

Total Rs.

Data-int.WS
Supply and fixing of 38.1 mm C.P. waste coupling Half or Full Thead 1st Q
6
Indian make Parryware of equivalent.

Unit: Each

1 No. cost of 38.10 mm C.P waste coupling Rs.


(vide Item No.204, P.No.151
Add 13.615 % contractor's Profit & Over Head charges
Sundries
Total Rs.

Supplying & Fixing Orissa Pan white glazed W.C 1st quality ISI ma
conforming to IS:2556-Part-3-1981 with "P" or "S" trap Hindware/ Parryw
Neycer - ISI Mark: 580 mm x 440 mm
7
1 No. cost of Orissa Pan White glazed W
C vide P.No.122 Item No.136 Rs.
Add M.L. 20%% on labour charges vide
item low
1 No. P.V.C. No.138
level at Rs 377.00
system flush tank 10 Rs.
Lt lt.capacity vide item No.342, P.No 132 Rs.

1 No.12.70 mm N.P Angle Stop cock vide


Item No.178, P.No.126 Rs.
Total Rs.

Add.13.615% towards Contractor Profit


& O.H.Charges Rs.
Add sundries Rs.
Total Rs.

Supplying & Fixing Indian make Flat Back Wash Hand Basin of size 450x30
1st quality with single C.P.Pillar cock, conforming to IS:2556-Part-4-1972
waste fittings like 38.10mm waste coupling, rubber plug, chain, 32 mm no
size C.P fitting with parallel pipe thread conforming to IS/:2963-1979 and
with 12.70mm dia. Chromium Plated Pillar tap of 1st quality Indian make
8 grams Seiko / Esso or equivalent etc., complete with standard CI bra
including wooden block, 31.75 mm PVC flexible waste pipe of 914.4mm
15mm inlet PVC connection with unions complete, including cutting and m
good the walls where ever required for the following sizes etc., complet
different floors, including cost, all taxes and conveyance of all materials an
labour charges etc., complete for finished item of work.
Data-int.WS
DATAS INTERNAL WS & SF

s per Common SSR 2016-2017

VALASA,(v) SRIKAKULAM .

SHIRVAD/Ajay/Astral flowguard or equivalent CPVC pipes


8:2007) with malleable specials to meet the requirement of
produced in CTS (copper tube sizes 1/2" ton 2") such as
uts, unions, bushes, etc., Solvent Cement including fixing
ncluding for necessary exacavation in all sorts of soils,
., refilling consolidation with the excavated earth & Making
ar and complete. When making a transition use metal
ng all taxes for finished item of work as directed by the
mp to over head tank.

525.00
71.48
0.02
596.50
pipe SDR 13.5

212.00

28.86

0.04

240.90

Data-int.WS
pipe SDR 13.5

141.00

19.19

0.01

160.20

Data-int.WS
289.00
39.35
0.04
328.39

12.70mm NP short bib tap indian make heavy duty, Seiko


e deluxe with necessary fittings etc., complete including
f all materials, all taxes and all labour charges for finished

258.00
35.13
0.02
293.15

12.70mm NP long body Bib tap indian, fancy type deluxe


etc., complete including cost and conveyance of all
all labour charges for finished item.

637.00
86.73
0.02
723.75

50 mm dia G.M.Peet Valve as per I.S.778 1st Class of


o including cost and conceyance of all materials, labour

Data-int.WS
3,711.00
505.25
-
4,216.25

Data-int.WS
of 12.70mm NP Angle stop cock indian make 400gms,
ncy type deluxe with necessary fittings etc., complete
eyance of all materials, all taxes and all labour charges for
all floors.

474.00

64.54

0.01

538.55

Data-int.WS
.1 mm C.P. waste coupling Half or Full Thead 1st Quality
of equivalent.

237.00

32.27
0.03
269.30

Orissa Pan white glazed W.C 1st quality ISI marked


-Part-3-1981 with "P" or "S" trap Hindware/ Parryware/
mm x 440 mm

1584.00

75.40
1455.00

474.00
3588.40

488.56
0.04
4077.00

an make Flat Back Wash Hand Basin of size 450x300mm


C.P.Pillar cock, conforming to IS:2556-Part-4-1972 with
0mm waste coupling, rubber plug, chain, 32 mm nominal
rallel pipe thread conforming to IS/:2963-1979 and fitted
omium Plated Pillar tap of 1st quality Indian make 400
or equivalent etc., complete with standard CI brackets
k, 31.75 mm PVC flexible waste pipe of 914.4mm long,
ction with unions complete, including cutting and making
ever required for the following sizes etc., complete for
g cost, all taxes and conveyance of all materials and all
mplete for finished item of work.
Data-int.WS
ABSTRACT FOR INTERNAL ELECTRIFICAT
Name of Work :- Construction of G+7 Flats Under Affordable Housin
Balaga(V) ,Srikakulam (M) ,Srikakulam (Di

Sl.
Quantity
No.

1 960.000

2 960.000

3 1782.760

4 1153.440
5 192.000

6 448.000

7 320.000

8 64.000

9 4.000
10 1500.640

11 112.000

12 120.000
13 2.000

14 4.000

15 64.000

16 1817.600
ABSTRACT FOR INTERNAL ELECTRIFICATION
of Work :- Construction of G+7 Flats Under Affordable Housing.Scheme in part
Balaga(V) ,Srikakulam (M) ,Srikakulam (Dist).

Description of item Rate

Wiring with 2 runs of 14/0.3 mm. (1.00


Sqmm.)P.V.C. insulated FR flexible copper cable (ISI
Make) in the existing pipe with 6 A Module Modular
Switch, Ceiling rose control with suitable gang
674.85
metallic box concealed including all labour charges
etc., complete for Light & Bell Points in Residential
Buildings. (Make GM four - five/Legrand Arteor /
schneider Zencelo / MK blenge).

Supply and fixing of ISI 20mm outer medium dia


(1.55 mm thick) grade with IS 9537part - 3 , rigid
4make Sudhakar / Modi / Atul P.V.C pipe concealed
in wall with all required accessories including 79.05
masonary work for light, fan and separate plug point
with well seasoned wooden deep box including all
labour charges etc. complete.

Supply and fixing of 25mm dia 1.8 mm thick Surface


P.V.C pipe (ISI MARK ) with all accessories fixing on
81.60
chromium plated metallic base saddles including all
labour charges etc. complete for run of mains.

Supplying and run of 2 of 36/0.3mm (2.5 Sqmm.)


F.R. LS/HFFR PVC insulated 1100 V grade as per
IS 694 / 1990 insulated Makes finolex / RR Kabel
76.45
flexible Copper cable of makes finolex / RR kabel in
existing pipe for MAINS including all labour charges
etc., complete.
Supply and fixing of 6A, 3 pin plug socket with 6 A
Modular type switch control with suiteble gang
metallic flush box with 2mts of 1 sq mm PVC
insulated copper conductor single core standard wire
349.95
on acommon board with a run of 1.0 sq mm PVC
insulated copper conductor single core standard wire
for earth continuity along with labour charges etc.,
complete.

Supply and fixing of BATTEN HOLDER/ SLANTING


HOLDER in lieu of ceiling rose of light point
complete with all connections and all labour charges 98.75
with 40 W Bulb etc., complete (for New installation)
connections. (makes Anchor/Gold medal)

Supply and fixing of Modular (4 module box ) Type


16A/ 6A one way combi socket modular socket with
shutter of and 16A/10A module flush fuse with neon
659.90
indicator duly on recessed in wall with suitable gang
metalic flush box including earth connection and all
labour chargs etc.,complete.

Supply and fixing Distribution board with 20 A single


phase plug and socket, in sheet enclosure with
10/16/32A SP MCB including internal conneciton and 1736.00
labour charges for surface/flush mounting etc.,
complete. (Concailed in wall) for A.C. Point.

Provding Independent earthing by excavting a


treanch to a depth of 2.10Mts in all soils as per size
specified in data us 40mm dia B class G.I. Pipe of
2.50mtr., length with necesary acesseries with hume
2342.78
pipe ring duly providing staggered holes including
filling with equiel proportation of salt and char coal in
layers and all labour charges etc complete for small
quarters.
Supplying run of 2 of 56/0.03 mm (4 Sq.mm) FRLS/
HFFR PVC. Insulated flexible copper 1100 V grade
as IS 694/1990 cable in existing pipe for mains 115.93
including all labour charges etc. complete. For run
of mains.(finolex/RR kabel).

Supplying and fixing of Electronic Regulators 400 w


socket type common switch board with earth
308.56
continuity including wire leads, earth connections
along with all labour charges etc., complete.

Supplying and erecting the following PVC armoured


cable 1100 V grade with ISI mark standed/soild
alluminium in soil upto 0.9 M deep embedding the
cable complete with sand bed of 20 Cms. Thick layer
and bricks placed on top of the calbe with wise and
sides all over the run and back filling the excavated
618.60
earth with outstones and hard materials and making
the surface proper with 15 Cms. crown on the top
duly providing route indicators including connections
like brass glands, AL lugs etc., complete.(makes
polycab / KE1 / RPG/ finolex / havells / paragon/
Vguard / fortunart / gloster / suncab).
Supply, insallation, testing and commissioning of
floor mounting type meter panel board with
alluminium bus bars fabricated with 16 Guage CRCA
sheet in standard sections suitable for TNP bus bars
with bus bars of equal size in all phases and neutral
equipped wiht bus bar chambers and cable
chambers. The painting of the complete system shall
be powder coated duly processing the pabel in 7
tank process. The panel shall be suitable for
accomdating the following switch gear including
supply of all components, hard wares etc., including
all necessary civil works, adequate reinforcement
79468.10
foundation bolts, suitable GI earth strip, suitable MS
base channel, door loop earthings, bus bars should
be colour sleeved wiht heat shrinkable sleeves for
phase and neutral duly supported at reqular intervels
by SMC supports and bus bar to switch inter
connections shall have bimettalic washers and all
cables shall have proper cable entry, danger board,
feeder identification marks, rigid inter connections,
cadmium plated blots and nuts and shall be installed
and performed trench and consisting of the following
as required and as per IS standards for main power
control center.
Supply and Errecting of Pannel Mounting 125 A, 4
11548.10
Pole, 25 K, MCCB for Pannel Board.

Supply and Fixing of 4 way SPN Distribution Board


7283.90
with DP-20 protection single phase

Supply run of 1 of 14 / 0.30 mm (1 Sq.mm)


FRLS/HFFR PVC. Insulated 1100V grade flexible
11.95
copper cable in existing pipe for mains including all
labour charges etc. complete. For run of mains.

Total
Add L.S
Total
ON
.Scheme in partnership at
).

Unit Amount

Each 647,856.00

1RMT 75,888.00

1 RMT 145,473.22

1 RMT 88,180.49
Each 67,190.40

Each 44,240.00

Each 211,166.69

Each 111,104.00

Each 9,371.12
1 RMT 173,969.20

Each 34,558.72

1 RMT 74,232.00
Each 158,936.19

-
46,192.41

NO 466,169.60

1 RMT 21,720.32

Rs. 2,376,248.36
Rs. 23,751.64
Rs. 2,400,000.00
DATAS FOR ELECTRICAL

As per Common SSR 2016-17.

Name of Work :- Construction of G+7 Flats Under Affordable Housing


Balaga(V) ,Srikakulam (M) ,Srikakulam (Dist)

Wiring with 2 runs of 14/0.3 mm. (1.00 Sqmm.)P.V.C. insulated FR flexib


in the existing pipe with 6 A Module Modular Switch, Ceiling rose contro
1
box concealed including all labour charges etc., complete for Light & Be
Buildings. (Make GM four - five/Legrand Arteor / schneider Zencelo / MK

A.P.Standard Data No.2.1.2, P.No.163


Taking Out put -7 Points
Unit Qty
Material :-
14/0.3mm PVC FR flexible copper wire (Finolex / RR 100 M 1.00
(P.No.198, item No.120)
6A 1way Modular Switch Each 7.00
(P.No.207,Item No. 213)
6 A 2 way Ceiling Rose Each 7.00
(P.No.108, Item No. 214)
1 Modular Concealed metal box Each 7.00
(P.No.104, Item No. 100)
1 Modular White mounting plate cover & frame Each 7.00
(P.No.111, Item No. 290)
Labour charges :-
Skilled Electrician (pno: 212 sl no : 1408) Day 0.70
Semi skilled Elecri (pno: 212 sl no : 1409) Day 1.40
Helpers ( Rs.345.0(pno: 212 sl no : 1415) Day 0.70
20% Labour compon 1200.50 X 20%
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Add sundries
Total
Rate per each point

Data-Int.Elec.
sundries
Total

Supply and fixing of ISI 20mm outer medium dia (1.55 mm thick) grade w
4make Sudhakar / Modi / Atul P.V.C pipe concealed in wall with all requir
2
masonary work for light, fan and separate plug point with well seasoned
all labour charges etc. complete.

A.P.Standard Data No.1.4.1 (b), P.No.159 Unit : 1 Rmt.


Taking Out put -100 M
Unit Qty
Material :-
20 mm dia 1.55mm thick PVC pipe 100 M 100.00
(P.No.102, item No.52)
U'Links 100 Nos. 2.00
(P.No.167,It.No.1341)
20 mm dia 1,2,3, &4 way deep junction box of size Each 12.00
(P.No.104, It.No.89)
19/20mm dia PVC Bends (19/20mm) Each 12.00
(P.No.104, It.No.94)
Cement MT 0.05
Labour charges :-
Skilled Electrician (pno: 212 sl no : 1408) Day 2.00
Semi skilled Elecri (pno: 212 sl no : 1409) Day 2.00
Helpers ( Rs400.00(pno: 212 sl no : 1415) Day 2.00
Mason 1st Class Day 2.00
20% Labour compo 3520.00 X 20%
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Total
Rate per 1 Rmt
sundries
Total

Data-Int.Elec.
Supply and fixing of 25mm dia 1.8 mm thick Surface P.V.C pipe (ISI MAR
3 fixing on chromium plated metallic base saddles including all labour char
mains.
A.P.Standard Data No.1.3.2, P.No.157
Taking Out put -100 M
Unit Qty
Material :-
25 mm dia 1.8mm thick PVC pipe 100 M 100.00
(P.No.103, item No.54)
Rawl Plugs 100 Nos. 2.00
(P.No.167,It.No.1340)
35 mm Screws(35/38mm) 100 Nos. 2.00
(P.No.104, It. No.134)
Chromium Plated saddles with base Each 200.00
(P.No.102, It.No.35) Rs.220.00/100No.=Rs.2.20
25 mm 1,2,3 & 4 way Junction boxes Each 12.00
(P.No.104, It.No.90)
25 mm PVC Bends Each 12.00
(P.No.104, It.No.95)
Cement MT 0.025
Labour charges :-
Skilled Electrician Day 2.00
Semi skilled Elecrician Day 2.00
Helpers Day 2.00
20% Labour compo 2630.00 X 20%
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Total
Rate per 1 Rmt
sundries
Total

Supply and fixing of 25mm dia 2.2 mm thick P.V.C pipe (ISI MARK) con
4
required accessories including masonary work and labour charges etc. c

A.P.Standard Data No.1.4.2 (C), P.No.161

Data-Int.Elec.
Taking Out put -100 M
Unit Qty
Material :-
25 mm dia 2.2 mm thick PVC pipe 100 M 100.00
(P.No.103, item No.55)
25 mm dia 1,2,3, & 4 way deep junction
Each 12.00
box (P.No.104,It.No.90).
25 mm PVC Bends Each 12.00
(P.No.104, It.No.95)
Labour charges :-
Skilled Electrician Day 2.00
Semi skilled Elecrician Day 2.00
Helpers Day 2.00
20% Labour compo 2630.00 X 20%
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Total
Rate per 1 Rmt
sundries
Total

Supply and fixing of 6A, 3/2 pin plate socket with 6 A Modular type switc
metalic flush box with 2 mts of 1 sqqmm PVC insulated copper conducto
5
on a common board with a run of 1.0 sqmm PVC insulated copper condu
wire for earth continuity along with labor charges etc.., complete

Unit - Each
A.P.Standard Data No.2.1.4 , P.No.165
Taking Out put -Each.
Unit Qty
Material :-
3/2 pin 6A Modular Socket Each 1.00
(P.No.182, item No.261)
6A 1 way Modular switch Each 1.00
Labour charges :-
Skilled Electrician Day 0.07
Helpers Day 0.07

Data-Int.Elec.
20% Labour compo 62.51 X 20%
Total
Add.13.615% towards Contractor Profit & O.H.Charges
sundries
Total

Supply and fixing of BATTEN HOLDER/ SLANTING HOLDER in lieu of


6 complete with all connections and all labour charges with 40 W Bulb etc.
installation) connections. (makes Anchor/Gold medal)

Unit -Each
A.P.Standard Data No.2.1.7 , P.No.165
Taking Out put -Each.
Unit Qty
Material :-
PVC Batten holder (Anchor/ Gold medal) Each 1.00
(P.No.108, item No.215)
40 W Bulb Each 1.00
(P.No.132, item No.729)
Labour charges :-
Skilled Electrician Day 0.05
Helpers Day 0.05
20% Labour compo 45.75 X 20%
Total
Add.13.615% towards Contractor Profit & O.H.Charges
sundries
Total

7 Supply and fixing of Modular (4 module box ) Type 16A/ 6A one way com
with shutter of and 16A/10A module flush fuse with neon indicator duly on
suitable gang metalic flush box including earth connection and all labou

Unit - Each
A.P.Standard Data No.2.1.6 , P.No.165
Taking Out put -Each

Data-Int.Elec.
Unit Qty
Material :-
4 way Modular type metal box concealed Each 1.00
(P.No.176, item No.102)
16 A & 6 A muilt socket - 3pin Modular type Each 1.00
(P.No.183, item No.270)
16 A Modulae type 3 pin/6A 3 pin plug socket (5 in 1) Each 1.00
(P.No.183, item No.265)
Labour charges :-
Skilled Electrician Day 0.10
Semi skilled Elecrician Day 0.10
Helpers ( Rs 400.00) Day 0.10
20% Labour component
131.5 x 20 %
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Add sundries
Total
Rate per Each Point Rs.659.90

Supply and fixing Distribution board with 20 A single phase plug and
8 with 10/16/32A SP MCB including internal conneciton and labour charges
etc., complete. (Concailed in wall) for A.C. Point.

A.P.Standard Data No.4.4.9 , P.No.185


Taking Out put -Each.
Unit Qty
Material :-
Distrubution board with 20A Single Phase
Nos. 1.00
plug and socket
(P.No.122, item No.506)
10/16/32 A SP MCB Nos. 1.00
(P.No.118, item No.424)
Cement MT 0.0125
Labour charges :-

Data-Int.Elec.
Skilled Electrician Day 0.25
Semi skilled Elecrician Day 0.25
Helpers Day 0.25
20% Labour compo 328.75 X 20%
Sundries such as T.W.Plugs, Screws etc.,
Total
Add.13.615% towards Contractor Profit & O.H.Charges
sundries
Total

Provding Independent earthing by excavting a treanch to a depth of 2.10


specified in data us 40mm dia B class G.I. Pipe of 2.50mtr., length with n
9
hume pipe ring duly providing staggered holes including filling with equie
char coal in layers and all labour charges etc complete for small quarters

A.P.Standard Data No.5.1.1 , P.No.186


Material :-

Earth Work Excavation of Hard gravel Soil with small


boulder for trench 1st step of size 1.5 x 0.6 x 0.9 m cum 0.85
(5'x2'x3')

Earth Work Excavation of Hard gravel Soil with small


boulder for trench 2nd step of size 1.2 x 0.6 x 1.2m cum 0.90
(4'x2'x4') (Page No.168, Sl.No.1386)

20% extra for narrow trench & pit back filling with
x 20%
sand, coke and salt etc.,. On Rs. 192.50
40mm dia G.I pipe (Medium) (P.No.80, Item 298 Rs.
Mtr. 2.50
355.00 - 67.00 (Labour charges ) = 288.00

25mm. x 6mm. x 200mm. length G.I Strip (Flat) with


Kg. 0.75
4 Nos. Holes of 12mm dia. (Item No.1375,P.No.168).

Drilling of staggered holes of 12mm dia to G.I pipe.


Each 16.00
(P.No.168, Item No.1370).
G.I Bolts, Nuts and Washers. (P.No.168, Item
Set 4.00
No.1394).

Data-Int.Elec.
Hard Coke. (P.No.167, Item No.1347). Kg. 40.00
Salt. (P.No.167, Item No.1348). Kg. 20.00
Semi Skilled Electrician Day 0.50
Helpers 0.50
Add 20% Labour component
Total
Add.13.615% towards Contractor Profit & O.H.Charges
sundries
Total

Supplying run of 2 of 56/0.03 mm (4 Sq.mm) FRLS/ HFFR PVC. Insul


10 grade as IS 694/1990 cable in existing pipe for mains including all labour
run of mains.(finolex/RR kabel).

A.P.Standard Data No.3.1.5 , P.No.169 Unit - 1 Rmt.


Taking Out put -100 M.
Unit Qty
Material :-
56/0.3 mm (4 Sqmm) FR PVC flexibel 100 M 2.00
copper wire.
(P.No.105, item No.140)
Labour charges :-
Skilled Electrician Day 1.00
Semi skilled Elecrician Day 3.00
Helpers Day 1.00
20% Labour compo 2115.00 X 20%
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Add sundries
Total
Rate per 1 Rmt
Total Rate for 1 Rmt

Data-Int.Elec.
Supplying and fixing of Electronic Regulators 400 w socket type comm
11
continuity including wire leads, earth connections along with all labour ch

Taking Out put -Each. Unit - Each


Unit Qty
Material :-
of (makes GMG home / Gold medal olive /
Each 1.000
Million zoom /Anchor Penta cherry/ Great
(P.No.108, item No.213)

Labour charges :-
Skilled Electrician Day 0.067
Helpers Day 0.067
40% Labour compo 61.31 X 20%
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Sundries
Total

Supplying and erecting the following PVC armoured cable 1100 V grade
alluminium in soil upto 0.9 M deep embedding the cable complete with sa
layer and bricks placed on top of the calbe with wise and sides all over th
12 excavated earth with outstones and hard materials and making the surfa
crown on the top duly providing route indicators including connections lik
complete.(makes polycab / KE1 / RPG/ finolex / havells / paragon/ Vguar
suncab).

A.P.Standard Data No.15.3.7, P.No.267 Unit - Each

Material
Cost of 95 Sq.mm 3.5 core XLPE insulated Unit Qty
1100 grade armoured arroured alluminium Rmt 1.000
cable
Labou(Page No.142, Item No :893)
r
Skilled Electrician Day 0.066
Helpers Day 0.066
20% Labour compo 60.39 X 20%
Total

Data-Int.Elec.
Add.13.615% towards Contractor Profit & O.H.Charges
Sundries
Total

13

Supply, insallation, testing and commissioning of floor mounting ty


alluminium bus bars fabricated with 16 Guage CRCA sheet in standard s
bars with bus bars of equal size in all phases and neutral equipped wiht
chambers. The painting of the complete system shall be powder coated
7 tank process. The panel shall be suitable for accomdating the foll
supply of all components, hard wares etc., including all necess
reinforcement foundation bolts, suitable GI earth strip, suitable MS
earthings, bus bars should be colour sleeved wiht heat shrinkable sleeve
supported at reqular intervels by SMC supports and bus bar to switch
bimettalic washers and all cables shall have proper cable entry, dange
marks, rigid inter connections, cadmium plated blots and nuts and shal
trench and consisting of the following as required and as per IS stand
center.
200A Alluminium bus bar with colour code (0.10A/Sq.mm.)
Internal wiring with apporved make cable
Earthing Flat providing 25x6mm G.I.flat
Incommer 200A TPN SFU with DIN type HRC fuse units - 1No. (Standard
200 A HRC fuses
Outgoing :32A porcelin fuse units
32A Nutralinks - 21No.
Bus bar insulators
connections 10% item of work including
for finished
transportation charges 5%
Total Say
(P.No.161 item No.1215) Sqm 3565
a panel board size 48"x134"x5"/10"
Back sheet----------------------------134"x48" = 6432.00
Top,Bottom,& middle---------120"x7 1/2"x4 =3600
Top,Bottom,& middle---------121/2"x18"x3= 675
Vertical left ------------- ------48"x7 1/2"x1= 360
Vertical right -----------------48"x12 1/2"x2= 1200
Horizontal channel-------- 120"x3"x2= 720
Vertical meter partition-----19"x71/2"x18= 2565

Data-Int.Elec.
fuse box doors----------- ---- 8"x13"20= 2080
fuse box doors----------------------8"x19"x1= 152
Bus bar doors----------------------11"x16"x2= 352
SFU box door---------- -----------13"x19"x1= 247
Total--------18383.00sq inch or 11.859 sqmt each 11.86
b 200 amps TPN Switch disconnector fuse unit cubical
type without fuses of makes (Page No.=112, Item
No.=305).
each 1.00
c 200 amps HRC fuse links 3nos (Page
no.=115, Itemno.=349).

each 3.00
d supply and erection of analog LED
indicator lamps on the existing box /
pannel board (Page no=162, Item
no=1225)
each 3.00
e supply of 32A 240V porcelain rewirwble
fuse units (Page No.=114, Item
No.=353).
each 63.00
f supply of 32amps nutral links L.S P140
IT.325 (Page No.=114, Item No.=347).

each 21.00
g supply of 84/0.3mm (6.0 sqmm)
FR/FRLS PVC insulate copper cable
(Page No.=105, Item no.=141).
MTS 84.00
h 40x6mm aluminium bus bar
(1mtr=0.644kgs) 16x0.644 (Page
No=168, Item No=1376).
kg. 10.30
i Epoxy insulators l.S each 32.00
j 3mm thickhylam sheet size of
12"x15"( Page No.168, Item No
1385).0116*945=109.62
Sqmt 21.00
Total

Data-Int.Elec.
Add.13.615% towards Contractor Profit & O.H.Charges
Sundries
Total

Supply and Errecting of Pannel Mounting 125 A, 4 Pole, 25 K, MCCB for


14
complete.
A.P.Standard Data No.4.3.4 , P.No.176 Unit - 1 each
Taking Out put -each.
Unit Qty
Material :-
cost of 125 A , 4 pole 25 Ka panel mounting MCCB Each 1.00
b) Labour Charges
skilled Electrician day 0.167
Semi Skilled electrician day 0.167
Helpers day 0.333
Add 20 % on MA 286.01 20%
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Sundries LS
Rate Per Each

Supply run of 1 of 14 / 0.30 mm (1 Sq.mm) FRLS/HFFR PVC. Insulate


14
copper cable in existing pipe for mains including all labour charges etc. c

A.P.Standard Data No.3.1.2 , P.No.168 Unit - 1 Rmt.


Taking Out put -100 M.
Unit Qty
Material :-
14 / 0.3 mm (1 Sqmm) FR PVC flexibel copper wire. 100 M 1.00
(P.No104, item No.137)
Add.13.615% towards Contractor Profit & O.H.Charges
Total
Rate per 1 RMT
Sundries

Data-Int.Elec.
Total

Supplyong and fixing 4 way SPN, D.B. with IP-20 Protection suitable. F
15
insulator as in commer for 1 Phase ELCB/RCCB/FP isolator as incomme

40 A , 4 pole RCCB 30m A of makes Legrand / SchneiEach 1.00


(P.No.119, item No.458)
10 KA -6-32A 10KA SP MCB C/D curve ISI mark of (mEach 12.00
(P.No.117, Item No.408).
Labour charges :-
Skilled Electrician Day 0.50
Semi skilled Elecrician Day 0.50
Helpers Day 1.00
20% Labour compo 857.50 X 20%
Total
Add.13.615% towards Contractor Profit & O.H.Charges
Add sundries
Total

Data-Int.Elec.
AS FOR ELECTRICAL

Common SSR 2016-17.

ats Under Affordable Housing.Scheme in partnership at


kakulam (M) ,Srikakulam (Dist).

Sqmm.)P.V.C. insulated FR flexible copper cable (ISI Make)


dular Switch, Ceiling rose control with suitable gang metallic
ges etc., complete for Light & Bell Points in Residential
Arteor / schneider Zencelo / MK blenge).

Unit - Each

Rate Amount

1051.00 1051.00

92.00 644.00

21.00 147.00

60.00 420.00

65.00 455.00

515.00 360.50
400.00 560.00
400.00 280.00
240.10
Rs. 4157.60
Rs. 566.06
Rs. 0.04
Rs 4723.70
Rs. 674.81

Data-Int.Elec.
Rs. 0.04
Rs. 674.85

dium dia (1.55 mm thick) grade with IS 9537part - 3 , rigid


e concealed in wall with all required accessories including
te plug point with well seasoned wooden deep box including

Rate Amount

20.00 2000.00

44.00 88.00

22.00 264.00

4.00 48.00

6600.00 330.00

515.00 1030.00
400.00 800.00
400.00 800.00
445.00 890.00
704.00
Rs. 6954.00
Rs. 946.79
Rs 7900.79
Rs. 79.01
Rs. 0.04
Rs. 79.05

Data-Int.Elec.
hick Surface P.V.C pipe (ISI MARK ) with all accessories
saddles including all labour charges etc. complete for run of

Unit - 1 Rmt

Rate Amount

28.00 2800.00

28.00 56.00

96.00 192.00

2.20 440.00

25.00 300.00

6.00 72.00

6600.00 165.00

515.00 1030.00
400.00 800.00
400.00 800.00
526.00
Rs. 7181.00
Rs. 977.69
Rs 8158.69
Rs. 81.59
Rs. 0.01
Rs. 81.60

hick P.V.C pipe (ISI MARK) concealed in Roof slabs with all
y work and labour charges etc. complete.

Unit - 1 Rmt

Data-Int.Elec.
Rate Amount

32.00 3200.00

25.00 300.00
6.00 72.00

515.00 1030.00
400.00 800.00
400.00 800.00
526.00
Rs. 6728.00
Rs. 916.02
Rs 7644.02
Rs. 76.44
Rs. 0.01
Rs. 76.45

cket with 6 A Modular type switch control with suitable gang


PVC insulated copper conductor single core standard wire
mm PVC insulated copper conductor single core standard
charges etc.., complete

Rate Amount

141.00 141.00

92.00 92.00

515.00 34.51
400.00 28.00

Data-Int.Elec.
12.50
Rs. 308.01
Rs. 41.94
Rs. 0.00
Rs. 349.95

SLANTING HOLDER in lieu of ceiling rose of light point


our charges with 40 W Bulb etc., complete (for New
/Gold medal)

Rate Amount

20.00 20.00

12.00 12.00

515.00 25.75
400.00 20.00
9.15
Rs. 86.90
Rs. 11.83
Rs. 0.02
Rs. 98.75

box ) Type 16A/ 6A one way combi socket modular socket


h fuse with neon indicator duly on recessed in wall with
g earth connection and all labour chargs etc.,complete.

Data-Int.Elec.
Rate Amount

101.00 101.00

196.00 196.00

126.00 126.00

515.00 51.50
400.00 40.00
400.00 40.00

26.30
580.80
Rs. 79.08
Rs. 0.02
Rs. 659.90

th 20 A single phase plug and socket, in sheet enclosure


al conneciton and labour charges for surface/flush mounting
C. Point.

Unit Each

Rate Amount

901.00 901.00

121.00 121.00

6600.00 82.50

Data-Int.Elec.
515.00 128.75
400.00 100.00
400.00 100.00
65.75
28.96
Rs. 1527.96
Rs. 208.03
Rs. 0.01
Rs. 1736.00

ting a treanch to a depth of 2.10Mts in all soils as per size


.I. Pipe of 2.50mtr., length with necesary acesseries with
holes including filling with equiel proportation of salt and
s etc complete for small quarters.

Unit-Each

110.00 93.50

110.00 99.00

38.50

288.00 720.00

68.00 51.00

6.00 96.00

11.00 44.00

Data-Int.Elec.
9.00 360.00
4.00 80.00
400.00 200.00
400.00 200.00
80.00
Rs. 2062.00
Rs. 280.74
Rs. 0.04
Rs. 2342.78

q.mm) FRLS/ HFFR PVC. Insulated flexible copper 1100 V


ipe for mains including all labour charges etc. complete. For

Rate Amount

3833.00 7666.00

515.00 515.00
400.00 1200.00
400.00 400.00
423.00
Rs 10204.00
Rs. 1389.27
Rs. 0.03
Rs 11593.30
Rs. 115.93
Rs. 115.93

Data-Int.Elec.
ulators 400 w socket type common switch board with earth
nnections along with all labour charges etc., complete.

Rate Amount

198.00 198.00

515.00 34.51
400.00 26.80
12.26
Rs. 271.57
Rs. 36.97
0.02
Rs. 308.56

C armoured cable 1100 V grade with ISI mark standed/soild


dding the cable complete with sand bed of 20 Cms. Thick
be with wise and sides all over the run and back filling the
d materials and making the surface proper with 15 Cms.
dicators including connections like brass glands, AL lugs etc.,
inolex / havells / paragon/ Vguard / fortunart / gloster /

Rate Amount
472.00 472.00

515.00 33.99
400.00 26.40
12.08
Rs. 544.47

Data-Int.Elec.
Rs. 74.13
0.00
Rs. 618.60

issioning of floor mounting type meter panel board with


Guage CRCA sheet in standard sections suitable for TNP bus
ases and neutral equipped wiht bus bar chambers and cable
system shall be powder coated duly processing the pabel in
uitable for accomdating the following switch gear including
res etc., including all necessary civil works, adequate
e GI earth strip, suitable MS base channel, door loop
eved wiht heat shrinkable sleeves for phase and neutral duly
supports and bus bar to switch inter connections shall have
have proper cable entry, danger board, feeder identification
m plated blots and nuts and shall be installed and performed
as required and as per IS standards for main power control

HRC fuse units - 1No. (Standard by Havels make)

Data-Int.Elec.
3565.00 42277.34

8215.00 8215.00

270.00 810.00

135.00 405.00

100.00 6300.00

50.00 1050.00

5828.00 4895.52

234.00 2410.20
40.00 1280.00

109.62 2302.02
69945.08

Data-Int.Elec.
9523.02
0.00
Rs 79468.10

g 125 A, 4 Pole, 25 K, MCCB for Pannel Board.charges etc.

Rate Amount

9821.00 9821.00

515 86.01
400 66.80
400 133.20
57.20
10164.21
1383.86
0.04
11548.10

mm) FRLS/HFFR PVC. Insulated 1100V grade flexible


ncluding all labour charges etc. complete. For run of mains.

Rate Amount

1051.00 1051.00

Rs. 143.09
Rs. 1194.09
Rs 11.94
0.01

Data-Int.Elec.
Rs. 11.95

with IP-20 Protection suitable. For 1ph ELCB/RCCB/FD


B/RCCB/FP isolator as incommer.

2970.00 2970.00

201.00 2412.00

515.00 257.50
400.00 200.00
400.00 400.00
171.50
Rs 6411.00
Rs. 872.86
Rs. 0.04
Rs 7283.90

Data-Int.Elec.
DATAS FOR COMPOUND WALL

As per Common SSR 2016-17.

Name of Work :- PATRUNIVALASA, SRIKAKULAM

1 Earth work excavation for foundations and depositing on bank for all lifts and with aninitial lead
of 10m including all operational, incidental, labour charges such as shoring incidental, labour
charges such as shoring sheeting, planking, strutting, etc. complete for finished item of work
excluding dewatering charges etc. as per SS- 20 B (APSS 308).

Unit 1 Cum

Rate Rs. 206.80 per 1 Cum

As per Civil Data No.1A.

Data-Comp.Wall
2 Laying PCC work of mix (1 : 5 : 10) prop. Using 40 mm gauge hard granite machine crushed
metal including cost and conveyance of all materials, machine mixing, labour charges, tamping,
cruing charges, taxes etc., complete for foundations.

Unit 1 Cum

Rate Rs. 3635.84 per 1 Cum

As per Civil Data No.11

Data-Comp.Wall
3 Supply and placing of the Design Mix Concrete of grade M30 corresponding to IS 456 using
WEIGH BATCHER using minimum cement content of 380 Kg. per Cum with 12mm and 20mm
size graded machine crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate ( sand) coarse
aggregate, water etc., to site and including, sales & other taxes on all materials including all
operational, incidental and labour charges such as weigh batching, machine mixing, laying
concrete, Vibrating, curing etc.,complete but excluding cost of steel and its fabrication charges
for finished item of work (APSS No.402 including centering shuttering using adjastable Jack
Screws, Props and Acro span beams including all pipe bracings, clamps couplings pre
fabricated steel H-frames, cross members etc., Complete, laying concrete, vibrating, curing
etc. complete but excluding cost of steel and its fabrication charges for finished item of work.
PLINTH BEAM

Unit 1 Cum

Rate Rs. 9279.49 per 1 Cum

As per Civil Data No.7

Data-Comp.Wall
4 R.R.Masonary in C.M.(1:8) Prop. using hard stone other than granite including cost and
conveyance of all materials, labour charges, curing etc., complete for FOUNDATION AND
BASEMENT.

A.P.Standard Data No.68 (Page No.39 & 40) Unit - 1 Cum.

MATERIALS :
Cement MT 0.0594 6600.00 392.04
Rough Stone as per chart Cum 0.94 520.10 488.89
Bond stone Cum 0.16 520.10 83.22
Sand Cum 0.33 338.74 111.79

LABOUR
Mason 1st class Day 1.2 445.00 534.00
Man Mazdoor 2 350.00 700.00
Add M.L 20% on labour 1234.00 X 20% 246.80
Total Rs. 2556.73
Add 13.615% contractor's Profit & Over Head charges Rs. 348.10
Sundries. Rs. 0.03
Total Rs. 2904.86

Data-Comp.Wall
5 Masonry work in CM (1:6) prop with Flyash Cement solid blocks of size 290 x 225 x 140 mm for
manufacturing of flyash solid blocks using flyash of 80 kgs, cement of 15 kgs.Gypsum of 5 kgs.
and stone dust including cost and conveyance of all materials, labour charges, , scaffolding and
curing etc., complete with a compressive strength not lessthan 50 kg/sqcm for walls for
Superstructure

Unit 1 Cum

Rate Rs. 5746.82 per 1 Cum

As per Civil Data No. 16

Data-Comp.Wall
6 Plastering with CM (1:4), 12 mm thick in singlecoat with. Screened sand with sponge finishing
including cost and coneyance of all meterials hacking surface, scaffolding, leads, lifts and
labour charges etc., complete for INTERIOR AND EXTERIOR WALLS.

Unit 1 Sq.mtr.

Rate Rs. 285.98 per 1 Sqm

As per Civil Data No.18

Data-Comp.Wall
7 White washing two coats with approved quality of white cement to give an even shade after
thoroughly brushing the surface to remove all dirt and remains of loose powdered materials
including cost of all materials, labour charges and incidental such as scaffolding, lift charges
etc., complete for finished item of work, but excluding conveyance charges of materials

Unit : 1 Sqm.

A.P.Standard Data No.162

MATERIALS :
Whiting / White Cement (Page No.64, Sl.No.115 Kg 2.00 29.00 58.00
Gum, conjee water, or prickly pear juice
including necessary fire wood L.S LS 9.05
LABOUR
Brick Layers / Painter Day 0.21 510.00 107.10
Mazdoor (unskilled) 0.32 350.00 112.00
Add M.L 20% on labour charges 219.10 X 20% 43.82
Total Rs. 329.97
Sundries including brushes, ladders, etc., at 1% Rs. 3.30
Total Rs. 333.27
Add 13.615 % contractor's Profit & Over Head charges Rs. 45.37
Total Rs. 378.64
Rate for 1 Sqm Rs. 37.86
sundries Rs. 0.04
Total Rs. 37.90

Data-Comp.Wall
8 PAINTING to new WOOD work / Iron work in two coats with synthetic enamel paint of
approved colour, over one coat of ( primary coat including cost and conveyance of all materials,
incidental charges such as sand paper, cleaning the surface, cost of brushes and putty etc.,
complete. (Three coats).

Unit 1sqm

Rate Rs. 154.35 per 1 Sqm

As per Civil Data No.39

Data-Comp.Wall
9 Providing High Yield Strength Deformed Steel bars (Fe 415 Grade as per IS: 432 and as
amended upto date) of different diameters including labour charges for cutting, bending to
required size and shapes, placing in position with cover blocks of approved materials and size
and tying firmly with M.S. Binding wire of 20 SWG forming grills for reinforcement work as per
approved designs and drawings including cost and conveyance of deformed steel bars,
including all wastage such as overlaps, welded joints, chairs spacer bars including cost and
conveyance of binding wire cover blocks and all incidental, opeartional, labour charges such as
cutting bending placing in position, tying etc., including sales and other taxes on all materials
etc., complete for finished item of work in all floors (APSS No.126) (Payment will be made on
the basis of weight of fabrication deformed bars only) (No re-rolled steel shall be allowed)
complete for (8 mm to 40 mm).

Unit 1 M.T

Rate Rs. 55138.50 per 1 MT

As per Civil Data No.15

Data-Comp.Wall
ABSTRACT FOR SEPTIC TANK.

Name of Work :- Construction of EWS (G+7) Flats.

Sl.
QTY. Description of item RATE
No.

Earth work excavation for foundations and


depositing on bank for all lifts and with an initial
lead of 10m including all operational, incidental,
labour charges such as shoring incidental,
1 107.12 sheeting, planking, strutting, etc. complete for 206.80
finished item of work .in ordinary soils by
manual means upto 3.00mt depth excluding
dewatering charges etc. as per SS- 20 B
(APSS 308)

Laying PCC work of mix (1 : 5 : 10) prop. Using


40 mm gauge hard granite machine crushed
metal including cost and conveyance of all
2 12.96 3322.25
materials, machine mixing, labour charges,
tamping, cruing charges, taxes etc., complete
for foundations.
Supply and placing of the Design Mix Concrete
of grade M30 corresponding to IS 456 using
WEIGH BATCHER with 12mm and 20mm
size graded machine crushed hard granite
metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials
like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including,
sales & other taxes on all materials including all
operational, incidental and labour charges such
as weigh batching, machine mixing, laying
3 16.00 concrete, vibrating, curing etc.,complete but 6346.40
excluding cost of steel and its fabrication
charges for finished item of work (APSS
No.402) including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross
members etc., Complete, laying concrete,
vibrating, curing etc. complete but excluding
cost of steel and its fabrication charges for
finished item of work FOR SEPTIC TANK
BOTTOM SLAB .
Supply and placing of the Design Mix Concrete
of grade M30 corresponding to IS 456 using
WEIGH BATCHER with 12mm and 20mm
size graded machine crushed hard granite
metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials
like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including,
sales & other taxes on all materials including all
operational, incidental and labour charges such
as weigh batching, machine mixing, laying
4 9.62 concrete, vibrating, curing etc.,complete but 8764.15
excluding cost of steel and its fabrication
charges for finished item of work (APSS
No.402) including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross
members etc., Complete, laying concrete,
vibrating, curing etc. complete but excluding
cost of steel and its fabrication charges for
finished item of work FOR SEPTIC TANK
SIDE WALLS .
Supply and placing of the Design Mix Concrete
of M 30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost
and conveyance of all materials like cement,
fine aggregate (sand) coarse aggregate, water
etc., to site and including, sales & other taxes
on all materials including all operational,
incidental and labour charges such as weigh
batching, machine mixing, laying concrete,
5 8.81 6346.40
vibrate, curing etc.,complete but excluding cost
of steel and its fabrication charges for finished
item of work (APSS No.402)including centering
shuttering using adjastable Jack Screws, Props
and Acro span beams including all pipe
bracings, clamps couplings pre fabricated steel
H-frames, cross members etc., Complete,
laying concrete, vibrating, curing etc. complete
but excluding cost of steel and its fabrication
charges for finished item of work PRECAST
SLABS FOR COVER OF SEPTIC TANK.
Supply and placing of the Design Mix Concrete
of grade M30 corresponding to IS 456 using
WEIGH BATCHER with 12mm and 20mm
size graded machine crushed hard granite
metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials
like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including,
sales & other taxes on all materials including all
operational, incidental and labour charges such
as weigh batching, machine mixing, laying
6 1.18 concrete, vibrating, curing etc.,complete but 9071.25
excluding cost of steel and its fabrication
charges for finished item of work (APSS
No.402) including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross
members etc., Complete, laying concrete,
vibrating, curing etc. complete but excluding
cost of steel and its fabrication charges for
finished item of work FOR SEPTIC TANK
BEAMS .

Plastering with CM (1:4), 12 mm thick in


singlecoat with. Screened sand with sponge
finishing including cost and coneyance of all
7 231.18 272.00
meterials hacking surface, scaffolding, leads,
lifts and labour charges etc., complete for OUT
SIDE WALLS.
Providing High Yield Strength Deformed Steel
bars (Fe 415 Grade as per IS: 432 and as
amended upto date) of different diameters
including labour charges for cutting, bending to
required size and shapes, placing in position
with cover blocks of approved materials and
size and tying firmly with M.S. Binding wire of
20 SWG forming grills for reinforcement work
as per approved designs and drawings
including cost and conveyance of deformed
steel bars, including all wastage such as
8 2.29 53904.65
overlaps, welded joints, chairs spacer bars
including cost and conveyance of binding wire
cover blocks and all incidental, opeartional,
labour charges such as cutting bending
placing in position, tying etc., including sales
and other taxes on all materials etc., complete
for finished item of work in all floors (APSS
No.126) (Payment will be made on the basis of
weight of fabrication deformed bars only) (No
re-rolled steel shall be allowed) complete for (8
mm to 40 mm).

Filling with useful available excavated earth


(excluding rock) in trenches, sides of
foundations and basement with initial lead in
layers not exceeding 15 cm thick,consolidating
each deposited layer by watering and ramming
9 16.58 24.65
including cost and conveyance of water to work
site and all operational, incidental, labour
charges, hire charges of T & P etc., complete
for finisheditem of work. (APSS NO. 309 &
310).
Supplying and fixing of 100 mm dia P.V.C. Plain
Tee of Prince / Sudhakar make in position
with air tight jointing materials including cost
10 1.00 122.70
and conveyance of all materials, labour
charges, fixing etc., complete as directed by
the department.

Masonry work in CM (1:4) prop with Flyash


Cement solid blocks of size 230 x 100 x 140
mm for manufacturing of flyash solid blocks
using flyash of 80 kgs, cement of 15
kgs.Gypsum of 5 kgs. and stone dust including
11 0.32 6337.00
cost and conveyance of all materials, labour
charges,, scaffolding and curing etc., complete
with a compressive strength not lessthan 50
kg/sqcm for walls for Superstructure Walls for
Baffle walls.

Total:
Add L.S
Say.
) Flats.

UNIT AMOUNT

1 Cum. 22,153.24

1 Cum. 43,053.04
Cum. 101,542.40
1 Cum. 84,328.65
1 Cum. 55,904.17
Cum. 10,685.93

`1Sqm 62,882.05
1 M.T. 123,629.24

Cum. 408.80
No 122.70

Cum. 2,027.84

506,738.05
3,261.95
510,000.00
DETAILED ESTIMATE FOR SEPTIC TANK
Name of work :- Construction of EWS (G+7) FLATS

Sl.
Description of item Nos. L B D
No.
1 Earth work excavation for foundations and
depositing on bank for all lifts and with an initial lead
of 10m including all operational, incidental, labour
charges such as shoring incidental, sheeting,
planking, strutting, etc. complete for finished item of
work .in ordinary soils by manual means upto
3.00mt depth excluding dewatering charges etc. as
per SS- 20 B (APSS 308)

For septic tank 1x 1 16.30 5.30 1.24


2 Laying PCC work of mix (1 : 5 : 10) prop. Using 40
mm gauge hard granite machine crushed metal
including cost and conveyance of all materials,
machine mixing, labour charges, tamping, cruing
charges, taxes etc., complete for foundations.
Septic tank concrete 1x 1 16.30 5.30 0.15

Supply and placing of the Design Mix Concrete of M


30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
3 mixing, laying concrete, vibrate, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402)including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross
members etc., Complete, laying concrete, vibrating,
curing etc. complete but excluding cost of steel and
its fabrication charges for finished item of work
bottom SLAB FOR SEPTIC TANK.
bottom slab 1x 1 16 5.00 0.2

4 Supply and placing of the Design Mix Concrete of


grade M30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
mixing, laying concrete, vibrating, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402) including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work FOR
SEPTIC TANK SIDE WALLS .
Septic tank long walls 1x 2 15.40 0.20 1.24
Septic tank short walls 1x 2 4.00 0.20 1.24
Total Total :
5 Supply and placing of the Design Mix Concrete of M
30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
mixing, laying concrete, vibrate, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402)including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross
members etc., Complete, laying concrete, vibrating,
curing etc. complete but excluding cost of steel and
its fabrication charges for finished item of work
SLAB FOR COVER OF SEPTIC TANK.
Cover slab 1x 1 15.40 4.40 0.13
6 Supply and placing of the Design Mix Concrete of M
30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
mixing, laying concrete, vibrate, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402)including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross
members etc., Complete, laying concrete, vibrating,
curing etc. complete but excluding cost of steel and
its fabrication charges for finished item of work
FOR BEAMS.
1x 4 4.00 0.23 0.32

7 Plastering with CM (1:4), 12 mm thick in singlecoat


with. Screened sand with sponge finishing including
cost and coneyance of all meterials hacking
surface, scaffolding, leads, lifts and labour charges
etc., complete for WALLS.
Bottom 1 x 1 15.00 4
L Walls 1 x 2 15.00 1.24
S Walls 1 x 2 4.00 1.24
Baffle Walls 1 x 2 4.00 0.9
Septic top 1 x 1 15.40 4.4
Out Side L Wall 1 x 2 15.40 1.24
Out Side S Wall 1 x 2 4.40 1.24
Total Total :
8 Providing High Yield Strength Deformed Steel bars
(Fe 415 Grade as per IS: 432 and as amended upto
date) of different diameters including labour charges
for cutting, bending to required size and shapes,
placing in position with cover blocks of approved
materials and size and tying firmly with M.S. Binding
wire of 20 SWG forming grills for reinforcement
work as per approved designs and drawings
including cost and conveyance of deformed steel
bars, including all wastage such as overlaps,
welded joints, chairs spacer bars including cost and
conveyance of binding wire cover blocks and all
incidental, opeartional, labour charges such as
cutting bending placing in position, tying etc.,
including sales and other taxes on all materials etc.,
complete for finished item of work in all floors
(APSS No.126) (Payment will be made on the basis
of weight of fabrication deformed bars only) (No re-
rolled steel shall be allowed) complete for (8 mm to
40 mm).

total qty 32.764x70kgs/cum --


9 Filling with useful available excavated earth
(excluding rock) in trenches, sides of foundations
and basement with initial lead in layers not
exceeding 15 cm thick,consolidating each deposited
layer by watering and ramming including cost and
conveyance of water to work site and all
operational, incidental, labour charges, hire charges
of T & P etc., complete for finisheditem of work.
(APSS NO. 309 & 310).

1 x 1 16.30 5.3 0.89


1 x 1 15.40 4.4 0.89
Total :

10 Supplying and fixing of 100 mm dia P.V.C. Plain Tee


of Prince / Sudhakar make in position with air tight
jointing materials including cost and conveyance of
all materials, labour charges, fixing etc., complete 1 x 1
as directed by the department.
11
Masonry work in CM (1:4) prop with Flyash Cement
solid blocks of size 230 x 100 x 140 mm for
manufacturing of flyash solid blocks using flyash of
80 kgs, cement of 15 kgs.Gypsum of 5 kgs. and
stone dust including cost and conveyance of all
materials, labour charges,, scaffolding and curing
etc., complete with a compressive strength not
lessthan 50 kg/sqcm for walls for Superstructure
Walls for Baffle walls.

baffle walls 1x 2 4 0.10 0.4


ATS

Qty

107.124 Cum.

12.959 Cum.
16.000 cum

7.638
1.984
9.622 Cum
8.809 Cum.
1.178 Cum
1.178 Cum

60.000
37.200
9.920
7.200
67.760
38.192
10.912
231.18 Sqm
2.293 MT

76.887
-60.306
16.58 Sqm

1.000 Nos
0.320 Cum
DATAS FOR SEPTIC TANK

As per Common SSR 2016-17

Name of Work :- PATRUNIVALASA, SRIKAKULAM

Earth work excavation for foundations and depositing on bank for all lifts and with an initial
lead of 10m including all operational, incidental, labour charges such as shoring incidental,
1 sheeting, planking, strutting, etc. complete for finished item of work .in ordinary soils by
manual means upto 3.00mt depth excluding dewatering charges etc. as per SS- 20 B (APSS
308)

Unit 1 Cum

Rate Rs. 206.80 per 1 Cum

As per Civil Data No.1A

Data-S.Tank
Laying PCC work of mix (1 : 5 : 10) prop. Using 40 mm gauge hard granite machine crushed
2 metal including cost and conveyance of all materials, machine mixing, labour charges,
tamping, cruing charges, taxes etc., complete for foundations.

Unit 1 Cum

Rate Rs. 3322.25 per 1 Cum

As per Civil Data No.12

Data-S.Tank
Supply and placing of the Design Mix Concrete of grade M30 corresponding to IS 456 using
WEIGH BATCHER using minimum cement content of 400 Kg. per Cum with 12mm and
20mm size graded machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine aggregate (sand)
coarse aggregate, water etc., to site and including , sales & other taxes on all materials
including all operational, incidental and labour charges such as weigh batching, machine
mixing, laying concrete, Vibrating, curing etc.,complete but excluding cost of steel and its
3 fabrication charges for finished item of work (APSS No.402) including centering shuttering
using adjastable Jack Screws, Props and Acro span beams including all pipe bracings,
clamps couplings pre fabricated steel H-frames, cross members etc., Complete, laying
concrete, vibrating, curing etc. complete but excluding cost of steel and its fabrication charges
for finished item of work. BOTOM SLAB (Below Plinth).

Unit 1 Cum

6346.40

As per Civil Data No. 06

4 Supply and placing of the Design Mix Concrete of M 30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and conveyance of all materials like cement,
fine aggregate sand) coarse aggregate, water etc., to site and including , sales & other taxes
on all materials including all operational, incidental and labour charges such as weigh
batching, machine mixing, laying concrete, vibrate, curing etc.,complete but excluding cost of
steel and its fabrication charges for finished item of work (APSS No.402)with minimum cement
content as per IS code from standard suppliers approved by the department including
centering shuttering using adjastable Jack Screws, Props and Acro span beams including all
pipe brancings, clamps couplings pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc. complete but excluding cost of steel and its
fabrication charges for finished item of work FOR SIde walls.

A.P.Standard Data No.31 B Unit 1 Cum


1 Cum M30 grade concrete vide civil data No.4 Rs. 5767.20
1.00 Cum centring chages as per P.No.7, Item
Ph 31 b(4) Rs.876 /0.45 Rs. 1946.67
Total Rs. 7713.87
Add Over haeds & Contractors profit at 13.615% Rs. 1050.24
Add sundries 0.04
Total Rs. 8764.15

Data-S.Tank
Supply and placing of the Design Mix Concrete of M 30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and conveyance of all materials like cement,
fine aggregate (sand) coarse aggregate, water etc., to site and including, sales & other taxes
on all materials including all operational, incidental and labour charges such as weigh
5 batching, machine mixing, laying concrete, vibrate, curing etc.,complete but excluding cost of
steel and its fabrication charges for finished item of work (APSS No.402)including centering
shuttering using adjastable Jack Screws, Props and Acro span beams including all pipe
bracings, clamps couplings pre fabricated steel H-frames, cross members etc., Complete,
laying concrete, vibrating, curing etc. complete but excluding cost of steel and its fabrication
charges for finished item of work PRECAST SLABS FOR COVER OF SEPTIC TANK.

Unit 1 Cum

Rate Rs. 6346.40 per 1 Cum

As per Civil Data No. 06

Supply and placing of the Design Mix Concrete of M 30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and conveyance of all materials like cement,
fine aggregate (sand) coarse aggregate, water etc., to site and including, sales & other taxes
on all materials including all operational, incidental and labour charges such as weigh
6 batching, machine mixing, laying concrete, vibrate, curing etc.,complete but excluding cost of
steel and its fabrication charges for finished item of work (APSS No.402)including centering
shuttering using adjastable Jack Screws, Props and Acro span beams including all pipe
bracings, clamps couplings pre fabricated steel H-frames, cross members etc., Complete,
laying concrete, vibrating, curing etc. complete but excluding cost of steel and its fabrication
charges for finished item of work. RCC BEAMS FOR SEPTCI TANK

Unit 1 Cum

Rate Rs. 9071.25 per 1 Cum

As per Civil Data No.14

Plastering with CM (1:4), 12 mm thick in singlecoat with. Screened sand with sponge finishing
7 including cost and coneyance of all meterials hacking surface, scaffolding, leads, lifts and
labour charges etc., complete for OUT SIDE WALLS.

Data-S.Tank
Unit 1 Sq.mtr.

Rate Rs. 272.00 per 1 Sqm

As per Civil Data No.21

Providing High Yield Strength Deformed Steel bars (Fe 415 Grade as per IS: 432 and as
amended upto date) of different diameters including labour charges for cutting, bending to
required size and shapes, placing in position with cover blocks of approved materials and size
and tying firmly with M.S. Binding wire of 20 SWG forming grills for reinforcement work as per
approved designs and drawings including cost and conveyance of deformed steel bars,
8 including all wastage such as overlaps, welded joints, chairs spacer bars including cost and
conveyance of binding wire cover blocks and all incidental, opeartional, labour charges such
as cutting bending placing in position, tying etc., including sales and other taxes on all
materials etc., complete for finished item of work in all floors (APSS No.126) (Payment will be
made on the basis of weight of fabrication deformed bars only) (No re-rolled steel shall be
allowed) complete for (8 mm to 40 mm).

Unit 1 M.T

Rate Rs. 53904.65 per 1 MT

As per Civil Data No.17

Filling with useful available excavated earth (excluding rock) in trenches, sides of foundations
and basement with initial lead in layers not exceeding 15 cm thick,consolidating each
deposited layer by watering and ramming including cost and conveyance of water to work site
9
and all operational, incidental, labour charges, hire charges of T & P etc., complete for
finisheditem of work. (APSS NO. 309 & 310) OUT
PUT : 6 CUM.

A.P.Standard Data No.17. ( Taking out put as 6 Cum)


A.Labour
Man Mazdoor (including area allowance) Day 0.31 420 130.20
Contractor's Profit &
Add 0.13615 Rs. 17.73
Over head charges
Total (for 6.00 Cum) Rs. 147.93
Rate per 1 Cum Rs. 24.65
sundries 0.00
Rs. 24.65

Supplying and fixing of 100 mm dia P.V.C. Plain Tee of Prince / Sudhakar make in position
10 with air tight jointing materials including cost and conveyance of all materials, labour charges,
fixing etc., complete as directed by the department.

Unit : Each

110 mm dia plain Tee vide P.No.82 of item No.403. Rs. 108.00

Data-S.Tank
Add 13.615% contractor's Profit & Over Head charges 14.70
Sundries
Total Rs. 122.70

Masonry work in CM (1:4) prop with Flyash Cement solid blocks of size 230 x 100 x 140 mm
for manufacturing of flyash solid blocks using flyash of 80 kgs, cement of 15 kgs.Gypsum of 5
11 kgs. and stone dust including cost and conveyance of all materials, labour charges,,
scaffolding and curing etc., complete with a compressive strength not lessthan 50 kg/sqcm for
walls for Superstructure Walls for Baffle walls.

Unit : Cum.

Rate Rs. 6337.00 per 1 Cum

As per Civil Data No.20

Data-S.Tank
ABSTRACT FOR CIRCULAR SUMP
Name of Work :- Construction of G+7 Flats Under Affordable Housing.Schem
partnership at Balaga(V) ,Srikakulam (M) ,Srikakulam (Dist).
Sl. Qty. Description of item Rate
No.

Earth work excavation for foundations and


depositing on bank for all lifts and with an initial
lead of 10m including all operational, incidental,
labour charges such as shoring incidental,
1 22.117 206.80
sheeting, planking, strutting, etc. complete for
finished item of work .in ordinary soils by manual
means upto 3.00mt depth excluding dewatering
charges etc. as per SS- 20 B (APSS 308)

Laying PCC work of mix (1 : 4 : 8) proop. Using


40 mm gauge hard granite machine crushed
metal including cost and conveyance of all
2 2.212 3498.90
materials, machine mixing, labour charges,
tamping, curing, taxes etc., complete for
foundations.

Filling with useful available excavated earth


(excluding rock) in trenches, sides of foundations
and basement with initial lead in layers not
exceeding 15 cm thick,consolidating each
3 6.679 deposited layer by watering and ramming 24.65
including cost and conveyance of water to work
site and all operational, incidental, labour
charges, hire charges of T & P etc., complete for
finisheditem of work. (APSS NO. 309 & 310).
Supply and placing of the Design Mix Concrete of
grade M30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost
and conveyance of all materials like cement, fine
aggregate ( sand) coarse aggregate, water etc.,
to site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
4 1.923 mixing, laying concrete, Vibrating, curing 6346.40
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work
(APSS No.402 including centering shuttering
using adjastable Jack Screws, Props and Acro
span beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross
members etc., Complete, laying concrete,
vibrating, curing etc. complete but excluding cost
of steel and its fabrication charges for finished
item of work for Bottom Slab.
Supply and placing of the Design Mix Concrete of
grade M30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost
and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
mixing, laying concrete, vibrating, curing
5 2.591 12886.45
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work
(APSS No.402) including centering shuttering
using adjastable Jack Screws, Props and Acro
span beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross
members etc., Complete, laying concrete,
vibrating, curing etc. complete but excluding cost
of steel and its fabrication charges for finished
item of work FOR CIRCULAR SUMP SIDE
WALLS.
Supply and placing of the Design Mix Concrete of
M 30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost
and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
mixing, laying concrete, vibrate, curing
6 0.990 6346.40
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work
(APSS No.402)including centering shuttering
using adjastable Jack Screws, Props and Acro
span beams including all pipe bracings, clamps
couplings pre fabricated steel H-frames, cross
members etc., Complete, laying concrete,
vibrating, curing etc. complete but excluding cost
of steel and its fabrication charges for finished
item of work FOR CIRCULAR SUMP COVER
SLAB.
Providing High Yield Strength Deformed Steel
bars (Fe 415 Grade as per IS : 1786 and as
amended upto date) of different diameters
including labour charges for cutting bending to
required size shapes, placing in position with
cover blocks of approved materials and size and
tying firmly with M.S. Binding wire of 20 SWG
forming grills for reinforcement work as per
approved designs and drawings including cost
7 0.660 and conveyance of deformed steel bars, including 53904.65
all wastage such as overlaps, welded joints,
chairs spacer bars including cost and conveyance
of binding wire cover blocks and all incidental,
opeartional labour charges including sales and
other taxes on all materials etc., complete for
finished item of work in all floors (APSS No.126)
(Payment will be made on the basis of weight of
fabrication deformed bars only) (No re-rolled steel
shall be allowed) complete for (8 mm to 40 mm).

Providing impervious coat to exposed RCC roof


slab surface with CM(1:3), 20mm thick with 1kg of
water proof compound per bag of cement laid
over roof when it is green including cost of all
materials,, including conveyance charges of
8 66.411 291.35
materials and including all operational, incidental
and labour charges for mixing mortar, laying,
rendering smooth and thread lining, curing,
rounding off junctions of wall and slab etc,,
complete for finished item of work.

Plastering with CM (1:4), 12 mm thick in


singlecoat with. Screened sand with sponge
9 20.944 finishing including cost and coneyance of all 272.00
meterials hacking surface, scaffolding, leads, lifts
and labour charges etc., complete.
Supplying and fixing 50.8 Cm dia C.I. Man hole
10 1.000 frame & cover for chamber (Medium weight ) as 3129.20
per IS:1726-40Kgs. For Circular Sump.

Total:
Add L.S for unforceen items
Cost of sump
ble Housing.Scheme in
kulam (Dist).
Unit Amount

1 Cum. 4,573.87

1
7,738.65
Cum.

1 Cum. 164.67
1
12,205.71
Cum.
1
33,382.35
Cum.
1
6,284.70
Cum.
1 M.T. 35,577.07

1Sq.m
19,348.84
tr.

1 Sq.
5,696.71
mtr.
Each 3,129.20

128,101.77
1,898.23
130,000.00
DETAILED ESTIMATE FOR SUMP

Name of Work :- Construction of G+7 Flats Under Affordable Housing.Scheme in partnership at


(M) ,Srikakulam (Dist).

Sl.
Description of item Nos. L
No.

Earth work excavation for foundations and


depositing on bank for all lifts and with an initial lead
of 10m including all operational, incidental, labour
charges such as shoring incidental, sheeting,
1
planking, strutting, etc. complete for finished item of
work .in ordinary soils by manual means upto 3.00mt
depth excluding dewatering charges etc. as per SS-
20 B (APSS 308)

Sump earth work 1x 1 3.14/4X3.5X3.5X2.3

Laying PCC work of mix (1 : 4 : 8) proop. Using 40


mm gauge hard granite machine crushed metal
2 including cost and conveyance of all materials,
machine mixing, labour charges, tamping, curing,
taxes etc., complete for foundations.

For Sump 1x 1 3.14/4X3.5X3.5X0.23

Filling with useful available excavated earth


(excluding rock) in trenches, sides of foundations
and basement with initial lead in layers not
exceeding 15 cm thick, consolidating each deposited
3 layer by watering and ramming including cost and
conveyance of water to work site and all operational,
incidental, labour charges, hire charges of T & P
etc., complete for finished item of work. (APSS NO.
309 & 310).

1x 1 3.14/4 (3.6 X 3.60 - 2.9 X 2.90)X


Supply and placing of the Design Mix Concrete of
grade M30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate ( sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
4 mixing, laying concrete, Vibrating, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402 including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work for
Bottom Slab.

For Sump Bottom conrete 1x 1 3.14/4 X 3.5 X3.5X0.20

Supply and placing of the Design Mix Concrete of


grade M30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
5 mixing, laying concrete, vibrating, curing
etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No.402) including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work FOR
CIRCULAR SUMP SIDE WALLS 200 mm. thick.

c For Sump side wall concrete 1x 1 3.14/4 (2.90 X 2.90 - 2.60 X 2.60)
Supply and placing of the Design Mix Concrete of M
30 corresponding to IS 456 using WEIGH
BATCHER with 12mm and 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site and including, sales & other taxes on all
materials including all operational, incidental and
labour charges such as weigh batching, machine
6 mixing, laying concrete, vibrate, curing etc.,complete
but excluding cost of steel and its fabrication
charges for finished item of work (APSS
No.402)including centering shuttering using
adjastable Jack Screws, Props and Acro span
beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc.,
Complete, laying concrete, vibrating, curing etc.
complete but excluding cost of steel and its
fabrication charges for finished item of work FOR
CIRCULAR SUMP COVER SLAB.

Sump slab 1x 1 3.14/4 X2.9X2.9X0.15

Providing High Yield Strength Deformed Steel bars


(Fe 415 Grade as per IS : 1786 and as amended
upto date) of different diameters including labour
charges for cutting bending to required size shapes,
placing in position with cover blocks of approved
materials and size and tying firmly with M.S. Binding
wire of 20 SWG forming grills for reinforcement work
as per approved designs and drawings including
cost and conveyance of deformed steel bars,
7
including all wastage such as overlaps, welded
joints, chairs spacer bars including cost and
conveyance of binding wire cover blocks and all
incidental, opeartional labour charges including
sales and other taxes on all materials etc., complete
for finished item of work in all floors (APSS No.126)
(Payment will be made on the basis of weight of
fabrication deformed bars only) (No re-rolled steel
shall be allowed) complete for (8 mm to 40 mm).

For Sump Bottom Qty as above 1.923


For sump side walls Qty as above 2.591
For sump slab Qty as above 0.990
Total
Providing impervious coat to exposed RCC roof slab
surface with CM(1:3), 20mm thick with 1kg of water
proof compound per bag of cement laid over roof
when it is green including cost of all materials,,
including conveyance charges of materials and
8
including all operational, incidental and labour
charges for mixing mortar, laying, rendering smooth
and thread lining, curing, rounding off junctions of
wall and slab etc,, complete for finished item of
work.

Sump In side 1x 1 3.14X2.60X2.30


Sump bottom 1x 1 3.14X2.6X2.60
Sump Top 1x 1 3.14x2.9x2.9
Total
Plastering with CM (1:4), 12 mm thick in singlecoat
with. Screened sand with sponge finishing including
9 cost and coneyance of all meterials hacking surface,
scaffolding, leads, lifts and labour charges etc.,
complete.

Sump out side walls 1x 1 3.14X2.9X2.3

Supplying and fixing 50.8 Cm dia C.I. Man hole


10 frame & cover for chamber (Medium weight ) as per
IS:1726-40Kgs. For Circular Sump.

1x 1 --
MP

cheme in partnership at Balaga(V) ,Srikakulam

B D Qty

3.14/4X3.5X3.5X2.3 22.12 Cum.

3.14/4X3.5X3.5X0.23 2.212 Cum.

4 (3.6 X 3.60 - 2.9 X 2.90)X1.87 6.679 Cum.


3.14/4 X 3.5 X3.5X0.20 1.923 Cum.

(2.90 X 2.90 - 2.60 X 2.60)X2.30 2.591 Cum.


3.14/4 X2.9X2.9X0.15 0.990 Cum.

120 Kgs/Cum 0.231 MT


120 Kgs/Cum 0.311 MT
120 Kgs/Cum 0.119 MT
Total : 0.660 MT
3.14X2.60X2.30 18.777 Sqm
3.14X2.6X2.60 21.226 Sqm
3.14x2.9x2.9 26.407 Sqm
Total : 66.411 Sqm

3.14X2.9X2.3 20.944 Sqm

-- 1.000 Nos
DATAS FOR SUMP

As per Common SSR 2016-17

Name of Work :- Construction of G+7 Flats Under Affordable Housing.Scheme in


partnership at Balaga(V) ,Srikakulam (M) ,Srikakulam (Dist).

Earth work excavation for foundations and depositing on bank for all lifts and with an
initial lead of 10m including all operational, incidental, labour charges such as shoring
1 incidental, sheeting, planking, strutting, etc. complete for finished item of work .in
ordinary soils by manual means upto 3.00mt depth excluding dewatering charges etc.
as per SS- 20 B (APSS 308)

Unit 1 Cum

Rate Rs. 206.80 per 1 Cum

As per Civil Data No.1A

2 Laying PCC work of mix (1 : 4 : 8) proof. Using 40 mm gauge hard granite machine
crushed metal including cost and conveyance of all materials, machine mixing, labour
charges, tamping, cruing seinarge charges, taxes etc., complete.

Unit 1 Cum

3498.90

As per Civil Data No.4

Filling with useful available excavated earth (excluding rock) in trenches, sides of
foundations and basement with initial lead in layers not exceeding 15 cm
3 thick,consolidating each deposited layer by watering and ramming including cost and
conveyance of water to work site and all operational, incidental, labour charges, hire
charges of T & P etc., complete for finisheditem of work. (APSS NO. 309 & 310).

Unit 1 Cum.
Rate Rs. 24.65 per 1 Cum

As per Septic Tank Data No.9


Supply and placing of the Design Mix Concrete of grade M30 corresponding to IS 456
with 12mm and 20mm size graded machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate, water etc., to site and including ,
sales & other taxes on all materials including all operational, incidental and labour
charges such as weigh batching, machine mixing, laying concrete, Vibrating, curing
etc.,complete but excluding cost of steel and its fabrication charges for finished item of
work (APSS No.402) including centering shuttering using adjastable Jack Screws,
4 Props and Acro span beams including all pipe bracings, clamps couplings pre
fabricated steel H-frames, cross members etc., Complete, laying concrete, vibrating,
curing etc. complete but excluding cost of steel and its fabrication charges for finished
item of work. BOTOM SLAB (Below Plinth).

Unit 1 Cum

Rate per Cum Rs. 6346.40

As per Civil Data No. 06

5 Supply and placing of the Design Mix Concrete of M 30 corresponding to IS 456 using
WEIGH BATCHER with 12mm and 20mm size graded machine crushed hard granite
metal (coarse aggregate) from approved quarry including cost and conveyance of all
materials like cement, fine aggregate sand) coarse aggregate, water etc., to site and
including , sales & other taxes on all materials including all operational, incidental and
labour charges such as weigh batching, machine mixing, laying concrete, vibrate,
curing etc.,complete but excluding cost of steel and its fabrication charges for finished
item of work (APSS No.402)with minimum cement content as per IS code from
standard suppliers approved by the department including centering shuttering using
adjastable Jack Screws, Props and Acro span beams including all pipe brancings,
clamps couplings pre fabricated steel H-frames, cross members etc., Complete, laying
concrete, vibrating, curing etc. complete but excluding cost of steel and its fabrication
charges for finished item of work FOR CIRCULAR SUMP SIDE WALLS
.

A.P.Standard Data No.31 B Unit 1 Cum


1 Cum M30 grade concrete vide civil data No.4 Rs. 5767.20
1.00 Cum centring chages as per
1/0.2 x 1115 vide p n7 item no 31 a Rs. 5575.00
Total Rs. 11342.20
Add Over haeds & Contractors profit at 13.615% Rs. 1544.24
Add sundries 0.01
Total Rs. 12886.45
6 Supply and placing of the Design Mix Concrete of M 30 corresponding to IS 456 using
WEIGH BATCHER with 12mm and 20mm size graded machine crushed hard granite
metal (coarse aggregate) from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site and
including , sales & other taxes on all materials including all operational, incidental and
labour charges such as weigh batching, machine mixing, laying concrete, vibrate,
curing etc.,complete but excluding cost of steel and its fabrication charges for finished
item of work (APSS No.402)including centering shuttering using adjastable Jack
Screws, Props and Acro span beams including all pipe bracings, clamps couplings
pre fabricated steel H-frames, cross members etc., Complete, laying concrete,
vibrating, curing etc. complete but excluding cost of steel and its fabrication charges
for finished item of work. RCC SLABS.

Unit : 1 Cum.

Rateper 1 Cum Rs. 6346.40

As per Civil Data No. 06

Providing High Yield Strength Deformed Steel bars (Fe 415 Grade as per IS: 432 and
as amended upto date) of different diameters including labour charges for cutting,
bending to required size and shapes, placing in position with cover blocks of approved
materials and size and tying firmly with M.S. Binding wire of 20 SWG forming grills for
reinforcement work as per approved designs and drawings including cost and
conveyance of deformed steel bars, including all wastage such as overlaps, welded
7
joints, chairs spacer bars including cost and conveyance of binding wire cover blocks
and all incidental, opeartional, labour charges such as cutting bending placing in
position, tying etc., including sales and other taxes on all materials etc., complete for
finished item of work in all floors (APSS No.126) (Payment will be made on the basis
of weight of fabrication deformed bars only) (No re-rolled steel shall be allowed)
complete for (8 mm to 40 mm).

Unit 1 M.T

Rate Rs. 53904.65 per 1 MT

As per Civil Data No.17


ProvidingPlastering to RCC roof slab surface with CM(1:3), 20mm thick with 1kg of
water proof compound per bag of cement laid over roof when it is green including cost
of all materials,, including conveyance charges of materials and including all
operational, incidental and labour charges for mixing mortar, laying, rendering smooth
and thread lining, curing, rounding off junctions of wall and slab etc,, complete for
finished item of work IN SIDE WALLS.
8

Unit 1 Sqm

Rate Rs. 291.35 per 1 Sqm

As per Civil Data No.16

Plastering with CM (1:4), 12 mm thick in singlecoat with. Screened sand with sponge
9 finishing including cost and coneyance of all meterials hacking surface, scaffolding,
leads, lifts and labour charges etc., complete for OUT SIDE WALLS.

Unit 1 Sq.mtr.

Rate Rs. 272.00 per 1 Sqm

As per Civil Data No.21

Supplying and fixing 50.8 Cm dia C.I. Man hole frame & cover for chamber (Medium
weight ) as per IS:1726-40Kgs. For Circular Sump
10
Each
1 No. cost of 50.8 Cm. dia C.I Man hole frame &cover Rs. 2683.00
vide p.No166 of Item No.687
Add M.L.240% on labour charges at Rs.356.00
vide p.No.166 of Item No.688 Rs. 71.20
Total Rs. 2754.20
Add Over haeds & Contractors profit at 13.615% Rs. 374.98
Sundries 0.02
Total Rs. 3129.20
D A T A S 2016-2017

1 Formation of embankment with gravel, spreading gravel, sectioning a


operational charges of T&P complete for finished item of work as per
305 (4th revision) (Payment will be made based on level for finished it

SD-RBR-EECD-4-ii.P.No.298 (of part 2 R&B |SSR)


Taking output =10 cum
a) Labour
Mate day
Mazdoor (Unskilled) day
b) Machinery
Dozer D-50 for spreading @200 cum per hour hour
P.No.256,Sl.No.2 R&B

Mortor grader for grading @100 cum per hour hour


P.No.256, Sl.No.3 R&B

Water tanker 6 kl capacity P.No.256, Sl.No.10 R&B hour


Vibratory Roller 80-100 KN @100 cum per hour hour
(P.No.256, Sl.No.7) R&B

c) Material
Water kl
Cost of gravel as per lead chart cum
Cost for 10 cum
Rate per cum
Add 13.615 % towards overheads & Contractors profit
Sundries
Rate per 1 cum
2 Providing Modified penetration mecadam (MPM) Roads using 40 m
Cum/Sq.mtr and with required quantity of 12 mm size stone chips at 0.018
and 60/70 grade bitumen 2 Kg. per Sq.mts including removal of the loos
trimming the edges to provide firm vertical faces, cleaning, applying tack
duly ramping to fill voids and compacting with three wheel statick roller o
charges of Hydrallic self propelled chip spreader both for agreegates and
bitumen pressure distributer and power roller etc., complete for compacted

Taking out put 4500 Sq.mts


1 Bitumen 60 /70 grade
a) Labour
Mazdoor (Unskilled) Day 8.00
Mazdoor (Skilled) Day 2.40
Add M.L. @ 20% on labour charges 3640
B) Machinery
Hydraulic self propelled chips spreader Hour 6.00
vide p no 28 item no 25
Bitumen pressure distributer Hour 2.57
vide p no 27 item no 17
Tipper 5.50 Cum capacity Hour 10.00
vide p no43 item no 54
Add: M.L. 20% on labour Rs177.50x 20 % = Rs 35.50
Three wheeler roller 8 to 10 T Hour 33.75
vide p no43 item no 50
Add: M.L. 20% on labour Rs 210.90 x 20 % = Rs.42.18
Front end loader (1 Cum bucket capacity) Hour 6.00
vide p no 27 item no 5
C) Material
Bitumen @ 2Kg. Per Sq,mtr. T 9.00
40 mm size hand broken metal Cum 405.00
0.09 to 11.2 mm size stone chips Cum 81.00
Total
Add Over heads & Contractors profit at 13.615%
Sundries
Total
Rate for 1 Sq.mtr = R 909604.01 /4500=164.99
3 Providing and applying Tack coat bitumen Emulsion (medium setting
pressure detributor at the rate of 0.20 Kg./1 Sq.mtr on the prepared bitu
cleaned with mechanical broom for the finshed item of work as per mort
(4th revision) and directed by the department.

a Take output 3,500/- Sq.Mts.


Labour
Mazdoor (Unskilled) Day 2.08
Add M.L. 20 % on labour
b Machinary
Mechanically broom, Hydraulic at 1250 Sq.mtr Hour 2.80
Per hour Air compressor 250 CMF
P.No.27, Item No. 16
Emlusion pressure distrubutor at 1750 Sq.mtr. Hour 2.00
Per hour P.No.27, Item No.18
c Materials
Bituminum at 0.20 kg/Sq.Mt. At the rate T 0.70
Add sundries
Total (A+B+C)
Add Over haeds & Contractors profit at 13.615%
Sundries
Total

Say Rs 7.81
4 Providing laying of close graded premix surface materials mixed seal surf
by hot mix plant using hard blasted granite crushed aggregates of 13.2 mm
per table 500-26 of specification 512 of MoRTH & H (4th revision) pre mix
60/70 grade at 19 Kgs per 10 Sqm are including cost and transporting the
with mechanical paver finisher to the require grade, leavel and alignm
wheeled roller 8 to 10 tonnes as per MoRTH & H specifications 512 (4
finished item of work in all respects as directed by the Engineer-in-|Charge

Unit - 1Sq.Mtr
Taking out Put 500 Sq.mts.
A) Labour
Mazdoor (Unskilled) Day 21.00
Mazdoor (Skilled) Day 8.40
Total
Add M.L @ 20 % on labour charges Rs 9408.00
B) Machinary
Mix all hour 6.00
Oil fired bitumen boiler hour 6.00
P.No.28, Item No. 29
Three wheeler roller 8 to 10 T Hour 6.00
page No.43, item No.50 of S.S.R
Add: M.L. 20% on labour Rs 210.90 x 20 % = Rs 42.18
Bitumen @ 22Kg. Per 10 Sq,mtr. T 1.10
Stone chips 13.20 to 9.00 Cum 13.50
Add Over haeds & Contractors profit at 13.615%
Add sundries
Total
Rate for 1 Sq.mtr =
7 Earthen Embeankment with carrted earth from approved source to site for
as per standered specification including cost and conveyance of all materia
complete.

1 K.M lead charges vide P.No.226


1 Cum filling charges data no
Total
Add Over haeds & Contractors profit at 13.615%
sundries
Total
2016-2017

eading gravel, sectioning and with Vi d


nished item of work as per MoRT&H specification
ased on level for finished item of work.

part 2 R&B |SSR) Unit = Cum

0.10 350.00 35.00

0.05 1649.00 82.45

0.10 3220.00 322.00

0.40 630.00 252.00


0.10 2609.10 260.91

0.24 103.00 24.72


10.00 321.10 3211.00
4188.08
592.64
80.69
0.02
673.35
(MPM) Roads using 40 mm HBG metal of 0.09
mm size stone chips at 0.018 Cum\Sq.mts as key chips
ncluding removal of the loos material in the pot holes,
aces, cleaning, applying tack coat filling the pot holes
h three wheel statick roller of 8 to 10 T including hire
der both for agreegates and key agreegrates and also
etc., complete for compacted thickness of 75mm.

Unit - Sq.mtr.
350.00 Rs. 2800.00
350.00 Rs. 840.00
Rs. 728.00

2695.00 Rs. 16170.00

1500.00 Rs. 3855.00

924.10 Rs. 9241.00

Rs. 35.50
1122.10 Rs. 37870.88

Rs. 42.18
1650.00 Rs. 9900.00

29172.98 Rs. 262556.83


928.10 Rs. 375878.85
996.10 Rs. 80683.77
Rs. 800602.01
Rs. 109001.96
Rs. 0.04
Rs. 909604.01

Say Rs 164.99
Emulsion (medium setting ) (Bulk) using emulsion
Sq.mtr on the prepared bitumen by Granular surface
ed item of work as per morth and H specification 503

Unit - 1 Sq.mtr.

350.00 Rs. 728.00


Rs. 145.60

375.00 Rs. 1050.00

860.00 Rs. 1720.00

29172.98 Rs. 20421.09


Rs. 24064.69
Rs. 3276.41
Rs. 0.03
Rs. 27341.12
Rs. 7.81
/ 1 Sqm
ace materials mixed seal surfacing of 20 mm thickness
ushed aggregates of 13.2 mm to 0.09 mm (Type 'B') as
TH & H (4th revision) pre mixed with Bituminous binder
ng cost and transporting the hot mix to work site, laying
re grade, leavel and alignment, rolling with smooth
TH & H specifications 512 (4th revision) complete for
d by the Engineer-in-|Charge.

Unit - 1Sq.Mtr

350.00 Rs. 7350.00


350.00 Rs. 2940.00

Rs. 2058.00

200.80 Rs. 1204.80


219.00 Rs. 1314.00

1122.10 Rs. 6732.60

Rs. 42.18
29172.98 Rs. 32090.28
693.40 Rs. 9360.90
Rs. 1274.49
Rs. 0.04
Rs. 64367.29
Rs. 128.73
m approved source to site for leveling the road portions
and conveyance of all material and labour charges etc.,

Unit 1 Cum
Rs. 31.50
Rs. 28.50
Rs. 60.00
Rs. 8.17
0.03
68.20

You might also like