PROJECT TIMETABLE

The project will be one year and four months before it can start the
operation
ACTIVITIES DURATION
1. Preparation of Feasibility Study September 2016- December 2016

2. Putting up of Equity September 2016- October 2016


3. Project Site Location November 2016

4. Cleaning of Financing November 2016- August 2017


5. Business Registration March 2017-April 2017
6 Hiring and Training of Personnel March 2017-August 2017
7. Plant Site Location March 2017

8. Building Construction June 2017- September 2017


9. Cleaning and Disinfecting September 2017- November 2017
10 Procurement of Input Materials November 2017- December 2017

.
11. Installation of Equipment December 2017
12 Commencement of Operations January 2018

.
ACTIVITIES 2016 2017 2018

S O N D J F M A M J J A S O N D J F M A

1. Preparation of Feasibility Study

2. Putting up of Equity

3. Project Site Location

4. Cleaning of Financing

5. Business Registration

6 Hiring and Training of Personnel

7. Plant Site Location

8. Building Construction

9. Cleaning and Disinfecting

10. Procurement of Input Materials

11. Installation of Equipment

12. Commencement of Operations


ACTIVITIES Activity Symbol Duration Immediate

(Months) Predecessor
1. Preparation of Feasibility Study A 6 NONE

2. Putting up of Equity B 2 NONE


3. Project Site Location C 1 B

4. Cleaning of Financing D 6 B
5. Business Registration E 2 A
6 Hiring and Training of Personnel F 4 D&E
7. Plant Site Location G 1 D&E

8. Building Construction H 5 G
9. Cleaning and Disinfecting I 3 H
10 Procurement of Input Materials J 3 F

.
11. Installation of Equipment K 1 J
12 Commencement of Operations L K