No. Description Target Date Action by Remarks
PT. SBS (terlampir):
5.0 ENGINEERING
REQUIREMENT:
Data Sheet:
-SNO-M-DS-53-004 Rev.0 (Data Sheet Instrument Air
Receiver)
-SNO-M-DS-53-005 Rev.C (Datasheet for Diesel Storage
Tank) 07 Juni 2016 PT. PPS
Specification: SNO-M-ES-53-002 Rev.B
Design Code & Standard: ASME Sect.VIII Div.1 (2015)
Design Wind Speed: As Per Specification
Seismic Zone: As Per Specification
PWHT: N/A
Dokumen submit melalui 4 cycle (IFR, IFA, AFC, As Built) PT. SBS Confirm
Mechanical Data Sheet (MDS) will updated by PT.SBS after
final design / calculation. PT. SBS Confirm
Scope of design platform & Ladder c/w grating PT. SBS Confirm
Engineering drawing used dual unit imperial (metric) PT. SBS Confirm
Cut hole for nozzle and welding circum. shall have approved
by PPS engineering prior to execution, PT. SBS shall notify to PT. SBS Confirm
PPS.
SDRL/VDRL:
Page 2 of 3
No. Description Target Date Action by Remarks
Progress Report:
Bi-Weekly sebelum fabrikasi dan Weekly selama fabrikasi. PT. SBS Confirm
Sub Vendor List:
PT. SBS akan mengirimkan Sub-Vendors List untuk material 13 Juni 16 PT. SBS
pressure parts.
Pre Inspection Meeting (PIM): 29 Juli 16 PT. SBS
10.0 OTHERS
FINAL DOCUMENT:
1. Hard Copy: 1 Original & 4 copies for hard copied
2. Soft Copy: 2 flash disks of soft copied
3. For the purpose of SKPP MIGAS (Instrument Air Receiver), PT. SBS Confirm
Manufacturer will provide original final document and 1 copy
at latest 2 (two) weeks after Hydrotest.
Final document shall be submitted at the latest 2 (two) weeks
PT. SBS Confirm
after Inspection (IRN)
PT. SURYA BESINDO SAKTI PT. PRATIWI PUTRI SULUNG JOB PMTS
( ) ( ) ( )
Page 3 of 3