ASampleConstructionScheduleandCustomHomeBuildingTimeLine

ASampleConstructionScheduleandCustomHomeBuildingTimeLine
ASampleResidentialConstructionSchedule(fora6,000squarefootcustomhome)
IstheMicrosoftProjecttemplatefileusedtocreatethisnewhouseconstructionscheduleforsale?
Yes,anumberofprofessionalcustomhomebuildersandresidentialprojectmanagershaveaskedtobuytheMicrosoftProjectfilethatwasusedto
createthenewhouseconstructionscheduleshownonthispage.Inresponsetotheserequests,weareprovidingsampleconstructionschedulingfiles
foryoutoreviewsothatyoucandetermineifyourresidentialconstructioncompanymightbenefitfromusingaschedulingprogramtohelpmanage
yourhomebuildingbusiness.

[downloadsamplefiles]
Howlongdoesittaketobuildahouse?Scrolldownthispagetoseeanexampleofatypicalconstructionscheduleforalargecustomhome.Itwas
producedusingMicrosoftProjectschedulingsoftwareandincludesmost,butnotall,oftheactivitiesinvolvedintheprocessofbuildinganewhouse
inMaryland.Sampleconstructiondrawshavebeenincludedforreferencepurposes,althoughindividuallenders&mortgagecompanieswillmost
likelyhavetheirowndrawschedules.
Noticethatbecauseconstructiondrawsfromthelendertypicallyfollowthecompletionofvariousphases,ormilestones,thecashflowonaprojectcan
beveryirregular.Whilethemoneyflowingoutofaconstructioncompanyforemployeesalaries,benefits,officespace,vehicles,insurance,
equipmentandothercompanyexpenses,typicallyoccursonaregularcalendarbasedtimeline,themoneyusedtopaytheseexpensesfollowsan
eventdrivenschedule.Therefore,besidesthe"normal"unplannedeventsthatcanaffecttheprogressofahomebuildingproject,itisnotuncommon
forhomebuilderstorearrangeconstructionschedulesinordertogainaccesstodrawmoneysothattheyareabletopaysubcontractorsand
suppliersinatimelymanner.Bytheway,thisisgenerallyagoodthing(providedyouhaveanhonestbuilder)becausesubcontractorstendtofollow
themoneyandhappysubsarealmostalwayspreferabletounhappyones:)

Willyourhousetakethislongtobuild?
Probablynotmosthomebuildingprojectswilltakelesstime,butsomewilltakeevenmore.Forexample,thetimelineforasmallerhouse,withfew
http://www.b4ubuild.com/resources/schedule/6kproj.shtml

1/13

4/30/2016

ASampleConstructionScheduleandCustomHomeBuildingTimeLine

optionsandlessdetailedfinishes,whichhasbeenbuiltmanytimesbeforebyprofessionalbuilders,mightbeasshortas8to12weeks.However,6to
9monthsfromstarttofinishisprobablyamorerealisticaverage(averageisnotagoodwordforatypicalhomeowner).Whilealargerhouse,with
moreoptions,customfeatures,fancierfinishes,andmoreownerinvolvementespeciallyiftheownerhaslittleconstructionexperiencemayvery
welltake11/2to2yearstocomplete.Thenagain,ifyoubuildyourownhouse,andmakethecommonmistakeofmovinginbeforeeverylastdetailis
finished,well,youmightbelookingatdecadesinsteadofmonthsoryearsIspeakfromexperience,butit'sjustalittletriminthepowderroom,and
ashortpieceofbaseboardbehindthemasterbathdoor,andasmallpieceofmoldinginthehallwaylinencloset,and....
Theactualscheduleofcompletionforyourspecificprojectwillvarybaseduponmanyfactorsincluding,butnotlimitedto,sizeanddegreeofdifficulty
ofthestructure,siteandweatherconditions,materialandcontractoravailability,crewsizes,effectiveschedulingandcommunication,theknowledge
andexperienceofthosemanagingtheproject,andperhapsmostsignificantly,thenumber,timeliness,andcomplexityofthechangesyouwill
inevitablymaketotheoriginalcontractafterconstructionhasalreadybegun.
Goodluckwithyourproject,thankyouforvisitingB4UBUILD.COM,andhavefunbuilding!

ID

OutlineNumber

Name

Duration

Predecessors

Start

Finish

Contracts

0.00d

Thu6/5/12

Thu6/5/12

1.1

SupplyLotSaleAgreement

0.00d

Thu6/5/12

Thu6/5/12

1.2

SupplyConstructionAgreement

0.00d

Thu6/5/12

Thu6/5/12

1.3

SupplyContractPlans

0.00d

Thu6/5/12

Thu6/5/12

1.4

SupplyContractSpecifications

0.00d

Thu6/5/12

Thu6/5/12

1.5

SupplyContractSitePlan

0.00d

Thu6/5/12

Thu6/5/12

1.6

SecureFinancing

0.00d

Thu6/5/12

Thu6/5/12

1.7

ConstructionLoanSettlement

0.00d

Thu6/5/12

Thu6/5/12

DocumentReview&Revision

25.00d

Thu6/5/12

Wed7/9/12

http://www.b4ubuild.com/resources/schedule/6kproj.shtml

2/13

4/30/2016

ASampleConstructionScheduleandCustomHomeBuildingTimeLine

DocumentReview&Revision

25.00d

Thu6/5/12

Wed7/9/12

10

2.1

Review&FinalizePlans

15.00d

Thu6/5/12

Wed6/25/12

11

2.2

Review&FinalizeSpecifications

20.00d

Thu6/5/12

Wed7/2/12

12

2.3

Review&FinalizeSitePlan

1.00d

6,10

Thu6/26/12

Thu6/26/12

13

2.4

PrintConstructionDrawings

5.00d

10,11,12

Thu7/3/12

Wed7/9/12

14

2.5

ApproveRevisedPlans

0.00d

13

Wed7/9/12

Wed7/9/12

15

2.6

ApproveRevisedSpecifications

0.00d

13

Wed7/9/12

Wed7/9/12

16

2.7

ApproveRevisedSitePlan

0.00d

13

Wed7/9/12

Wed7/9/12

17

Bids&Contracts

24.00d

Thu7/10/12

Tue8/12/12

18

3.1

MakeCopiesofPlans

3.00d

14

Thu7/10/12

Mon7/14/12

19

3.2

MakeCopiesofSpecifications

2.00d

15

Thu7/10/12

Fri7/11/12

20

3.3

DistributePlans&Specifications

1.00d

18,19

Tue7/15/12

Tue7/15/12

21

3.4

ReceiveBids

10.00d

20

Wed7/16/12

Tue7/29/12

22

3.5

ReviewBids

5.00d

Wed7/30/12

Tue8/5/12

25

3.6

ExecuteSubcontractorAgreements

5.00d

23

Wed8/6/12

Tue8/12/12

26

Grading&BuildingPermits

17.00d

Thu7/10/12

Fri8/1/12

27

4.1

Schedulelotstakeout

1.00d

13

Thu7/10/12

Thu7/10/12

28

4.2

Stakelot

1.00d

27FS+3d

Wed7/16/12

Wed7/16/12

http://www.b4ubuild.com/resources/schedule/6kproj.shtml

3/13

4/30/2016

ASampleConstructionScheduleandCustomHomeBuildingTimeLine

29

4.3

FileGradingPermitApplication

1.00d

16

Thu7/10/12

Thu7/10/12

30

4.4

FileBuildingPermitApplication

3.00d

14,15,16

Thu7/10/12

Mon7/14/12

31

4.5

PostLotIdentification

1.00d

28,29,30

Thu7/17/12

Thu7/17/12

32

4.6

MeetSed.ControlInsp.

1.00d

29FS+2d,28,31

Fri7/18/12

Fri7/18/12

33

4.7

WalkLotw/Owner

1.00d

32

Mon7/21/12

Mon7/21/12

34

4.8

InstallConstructionEntrance

1.00d

32,33

Tue7/22/12

Tue7/22/12

35

4.9

InstallSedimentControls

2.00d

32,33

Tue7/22/12

Wed7/23/12

36

4.10

SedimentControlInsp.

1.00d

34,35

Thu7/24/12

Thu7/24/12

37

4.11

GradingPermitIssued

1.00d

36

Fri7/25/12

Fri7/25/12

38

4.12

CountyPermitProcess

10.00d

30

Tue7/15/12

Mon7/28/12

39

4.13

BuildingPermitApproved

1.00d

38,37

Tue7/29/12

Tue7/29/12

40

4.14

PayPermitFeesandExciseTaxes

1.00d

39FS+2d

Fri8/1/12

Fri8/1/12

41

4.15

BuildingPermitIssued

0.00d

40

Fri8/1/12

Fri8/1/12

42

SiteWork

7.00d

Mon7/28/12

Tue8/5/12

43

5.1

ClearLot

3.00d

37

Mon7/28/12

Wed7/30/12

44

5.2

StripTopsoil&Stockpile

1.00d

43

Thu7/31/12

Thu7/31/12

45

5.3

StakeLotforExcavation

1.00d

43

Thu7/31/12

Thu7/31/12

46

5.4

Roughgradelot

1.00d

43,45

Fri8/1/12

Fri8/1/12

http://www.b4ubuild.com/resources/schedule/6kproj.shtml

4/13

4/30/2016

46

5.4

Roughgradelot

47

5.5

48

ASampleConstructionScheduleandCustomHomeBuildingTimeLine

1.00d

43,45

Fri8/1/12

Fri8/1/12

Excavateforfoundation

2.00d

39,45,43,46

Mon8/4/12

Tue8/5/12

Foundation

24.00d

Wed8/6/12

Mon9/8/12

49

6.1

Layoutfootings

1.00d

47

Wed8/6/12

Wed8/6/12

50

6.2

DigFootings&InstallReinforcing

1.00d

49

Thu8/7/12

Thu8/7/12

51

6.3

FootingInspection

0.00d

50

Thu8/7/12

Thu8/7/12

52

6.4

Pourfootings

1.00d

51

Fri8/8/12

Fri8/8/12

53

6.5

PinFootings

1.00d

52

Mon8/11/12

Mon8/11/12

54

6.6

StockBlock,Mortar,Sand

1.00d

53

Tue8/12/12

Tue8/12/12

55

6.7

BuildBlockFoundation

15.00d

53,54

Wed8/13/12

Tue9/2/12

56

6.8

FoundationCertification

0.00d

55

Tue9/2/12

Tue9/2/12

57

6.9

Draw#1(LocationSurvey)

0.00d

56

Tue9/2/12

Tue9/2/12

58

6.10

FillBlockCoresw/Concrete

1.00d

55

Wed9/3/12

Wed9/3/12

59

6.11

SteelDelivery

1.00d

58

Thu9/4/12

Thu9/4/12

60

6.12

SetLintels,Bolts,CapBlock

2.00d

59

Fri9/5/12

Mon9/8/12

61

6.13

LumberDelivery

1.00d

58

Thu9/4/12

Thu9/4/12

62

6.14

WaterproofingandDrainTile

1.00d

61

Fri9/5/12

Fri9/5/12

63

RoughCarpentry

44.00d

Tue9/9/12

Fri11/7/12

http://www.b4ubuild.com/resources/schedule/6kproj.shtml

5/13

4/30/2016

ASampleConstructionScheduleandCustomHomeBuildingTimeLine

64

7.1

SetSteel

1.00d

60

Tue9/9/12

Tue9/9/12

65

7.2

1stFloorDeckFraming

4.00d

64

Wed9/10/12

Mon9/15/12

66

7.3

1stFloorWallFraming

4.00d

65

Tue9/16/12

Fri9/19/12

67

7.4

Draw#2(FirstFloorDeck)

0.00d

66

Fri9/19/12

Fri9/19/12

68

7.5

2ndFloorDeckFraming

2.00d

67

Mon9/22/12

Tue9/23/12

69

7.6

Draw#3(SecondFloorDeck)

0.00d

68

Tue9/23/12

Tue9/23/12

70

7.7

2ndFloorWallFraming

3.00d

69

Wed9/24/12

Fri9/26/12

71

7.8

SetRoofTrusses

2.00d

70

Mon9/29/12

Tue9/30/12

72

7.9

FrameRoof

7.00d

71

Wed10/1/12

Thu10/9/12

73

7.10

InstallRoofPlywood

5.00d

72

Fri10/10/12

Thu10/16/12

74

7.11

InstallWindows&Doors

2.00d

73,111

Wed10/22/12

Thu10/23/12

75

7.12

FrameBasement

3.00d

72,81

Fri10/10/12

Tue10/14/12

76

7.13

FrameBasementBulkheads

2.00d

75,87,93

Thu11/6/12

Fri11/7/12

77

ConcreteSlabs

8.00d

Thu9/18/12

Mon9/29/12

78

8.1

BasementSlabPreparation

2.00d

65,91

Thu9/18/12

Fri9/19/12

79

8.2

TermiteTreatmentBasmentSlab

1.00d

78

Mon9/22/12

Mon9/22/12

80

8.3

SlabInspection

1.00d

79

Tue9/23/12

Tue9/23/12

81

8.4

PourBasementSlab

1.00d

80

Wed9/24/12

Wed9/24/12

http://www.b4ubuild.com/resources/schedule/6kproj.shtml

6/13

4/30/2016

81

8.4

PourBasementSlab

82

8.5

83

ASampleConstructionScheduleandCustomHomeBuildingTimeLine

1.00d

80

Wed9/24/12

Wed9/24/12

PrepGarageSlab

1.00d

81

Thu9/25/12

Thu9/25/12

8.6

TermiteTreatmentGarageSlab

1.00d

82

Fri9/26/12

Fri9/26/12

84

8.7

PourGarageSlab

1.00d

83

Mon9/29/12

Mon9/29/12

85

H.V.A.C.

17.00d

Fri10/10/12

Mon11/3/12

86

9.1

HVACLayout&Measure

1.00d

72

Fri10/10/12

Fri10/10/12

87

9.2

HVACRoughin

5.00d

86,111

Wed10/22/12

Tue10/28/12

88

9.3

HVACSetIndoorUnits

2.00d

81,87

Wed10/29/12

Thu10/30/12

89

9.4

HVACTemporaryHeat

2.00d

88

Fri10/31/12

Mon11/3/12

90

10

PlumbingRoughin

37.00d

Tue9/16/12

Wed11/5/12

91

10.1

PlumbingSubslab

2.00d

65

Tue9/16/12

Wed9/17/12

92

10.2

PlumbingLayout

1.00d

91,87

Wed10/29/12

Wed10/29/12

93

10.3

Plumbingroughin

5.00d

92

Thu10/30/12

Wed11/5/12

94

11

CountyPlumbingSubslabInspection

0.00d

91

Wed9/17/12

Wed9/17/12

95

12

CountyPlumbingRoughinInspection

0.00d

93

Wed11/5/12

Wed11/5/12

96

13

ElectricRoughin

19.00d

Fri10/24/12

Wed11/19/12

97

13.1

SetElectricBoxes

2.00d

74

Fri10/24/12

Mon10/27/12

98

13.2

InstallElectricServicePanel

2.00d

97

Tue10/28/12

Wed10/29/12

http://www.b4ubuild.com/resources/schedule/6kproj.shtml

7/13

4/30/2016

ASampleConstructionScheduleandCustomHomeBuildingTimeLine

99

13.3

ElectricalWalkthrough

1.00d

98

Thu10/30/12

Thu10/30/12

100

13.4

ElectricalRoughwire

14.00d

99

Fri10/31/12

Wed11/19/12

101

14

SpecialtyRoughins

5.00d

Thu11/20/12

Wed11/26/12

102

14.1

CentralVacuumRoughin

5.00d

100

Thu11/20/12

Wed11/26/12

103

14.2

AlarmSystemRoughin

5.00d

100

Thu11/20/12

Wed11/26/12

104

14.3

TelephoneSystemRoughin

5.00d

100

Thu11/20/12

Wed11/26/12

105

14.4

TelevisionSystemRoughin

5.00d

100

Thu11/20/12

Wed11/26/12

106

14.5

AudioVisualRoughin

5.00d

100

Thu11/20/12

Wed11/26/12

107

15

CountyElectricalinspection

0.00d

96,101

Wed11/26/12

Wed11/26/12

108

16

Draw#5(Roughinscomplete)

0.00d

95,107

Wed11/26/12

Wed11/26/12

109

17

CountyFramingInspection

0.00d

95FS+1d,107FS+1d

Thu11/27/12

Thu11/27/12

110

18

Roofing

68.00d

Fri10/17/12

Tue1/20/13

111

18.1

RoofingPaperInstalled

3.00d

73

Fri10/17/12

Tue10/21/12

112

18.2

Draw#4(Roof,windows,doors)

0.00d

74,111

Thu10/23/12

Thu10/23/12

113

18.3

StockRoofShingles

1.00d

112

Fri10/24/12

Fri10/24/12

114

18.4

InstallRoofShingles

7.00d

113,119

Mon1/12/13

Tue1/20/13

115

19

ExteriorFinishes

56.00d

Fri10/24/12

Fri1/9/13

116

19.1

Siding

3.00d

74

Fri10/24/12

Tue10/28/12

http://www.b4ubuild.com/resources/schedule/6kproj.shtml

8/13

4/30/2016

116

19.1

Siding

117

19.2

118

ASampleConstructionScheduleandCustomHomeBuildingTimeLine

3.00d

74

Fri10/24/12

Tue10/28/12

ExteriorTrim

7.00d

116

Wed10/29/12

Thu11/6/12

19.3

BrickArchForms

1.00d

117

Fri11/7/12

Fri11/7/12

119

19.4

BrickVeneer

45.00d

118

Mon11/10/12

Fri1/9/13

120

20

Insulation

5.00d

Fri11/28/12

Thu12/4/12

121

20.1

Caulk&AirSeal

1.00d

109

Fri11/28/12

Fri11/28/12

122

20.2

Draft&FireStop

1.00d

121

Mon12/1/12

Mon12/1/12

123

20.3

BattInsulation

3.00d

121,122

Tue12/2/12

Thu12/4/12

124

21

CountyInsulationInspection

0.00d

123,120

Thu12/4/12

Thu12/4/12

125

22

BGEEnergyWiseInspection

0.00d

124

Thu12/4/12

Thu12/4/12

126

23

Drywall

26.00d

Fri12/5/12

Fri1/9/13

127

23.1

StockDrywall

1.00d

124

Fri12/5/12

Fri12/5/12

128

23.2

HangDrywall

5.00d

127

Mon12/8/12

Fri12/12/12

129

23.3

RemoveScrapDrywall

1.00d

128

Mon12/15/12

Mon12/15/12

130

23.4

TapeandFinishDrywall

15.00d

128,129

Tue12/16/12

Mon1/5/13

131

23.5

SandDrywall

1.00d

130

Tue1/6/13

Tue1/6/13

132

23.6

DrywallPointup

3.00d

131

Wed1/7/13

Fri1/9/13

133

24

Draw#6(Insulation&drywallapplied)

0.00d

128,126

Fri1/9/13

Fri1/9/13

http://www.b4ubuild.com/resources/schedule/6kproj.shtml

9/13

4/30/2016

ASampleConstructionScheduleandCustomHomeBuildingTimeLine

134

25

FloorFinishes

76.00d

Tue1/13/13

Tue4/28/13

135

25.1

CeramicTile

15.00d

142

Tue1/13/13

Mon2/2/13

136

25.2

InstallHardwoodFloor

4.00d

146

Fri3/27/13

Wed4/1/13

137

25.3

Sand,Stain,SealHardwood

5.00d

196

Thu4/16/13

Wed4/22/13

138

25.4

InstallCarpet

4.00d

137

Thu4/23/13

Tue4/28/13

139

25.5

FinalCoatHardwood

2.00d

196

Thu4/16/13

Fri4/17/13

140

26

Paint

59.00d

Wed1/7/13

Mon3/30/13

141

26.1

PrepDrywallforPrimeCoat

2.00d

131

Wed1/7/13

Thu1/8/13

142

26.2

PrimePaintDrywall

2.00d

141

Fri1/9/13

Mon1/12/13

143

26.3

PrepTrimforPrimeCoat

2.00d

142,152

Wed1/21/13

Thu1/22/13

144

26.4

PrimeTrim

2.00d

143

Fri1/23/13

Mon1/26/13

145

26.5

FinishCoatTrim

10.00d

144,156

Mon2/23/13

Fri3/6/13

146

26.6

FinishCoatDrywall

14.00d

145,132

Mon3/9/13

Thu3/26/13

147

26.7

CaulkExteriorWindows&Doors

1.00d

146,117

Fri3/27/13

Fri3/27/13

148

26.8

FinishCoatExteriorTrim&Siding

1.00d

147

Mon3/30/13

Mon3/30/13

149

27

Draw#7(Roofing,masonry,siding)

0.00d

114,157

Tue3/31/13

Tue3/31/13

150

28

InteriorTrim

29.00d

Tue1/13/13

Fri2/20/13

151

28.1

InteriorTrimDelivery

1.00d

142

Tue1/13/13

Tue1/13/13

http://www.b4ubuild.com/resources/schedule/6kproj.shtml

10/13

4/30/2016

151

28.1

InteriorTrimDelivery

152

28.2

153

ASampleConstructionScheduleandCustomHomeBuildingTimeLine

1.00d

142

Tue1/13/13

Tue1/13/13

InstallInteriorDoors

5.00d

151

Wed1/14/13

Tue1/20/13

28.3

InstallInteriorTrim

15.00d

152

Wed1/21/13

Tue2/10/13

154

28.4

InstallCabinetry

5.00d

153

Wed2/11/13

Tue2/17/13

155

28.5

InstallAppliances

1.00d

154

Wed2/18/13

Wed2/18/13

156

28.6

1stPunchoutInteriorTrim

2.00d

155,144

Thu2/19/13

Fri2/20/13

157

29

H.V.A.C.Trim

1.00d

140

Tue3/31/13

Tue3/31/13

158

29.1

InstallGrills&RegistersforPaint

1.00d

131

Tue3/31/13

Tue3/31/13

159

29.2

SetOutdoorUnits

1.00d

165

Tue3/31/13

Tue3/31/13

160

30

PlumbingTrim

5.00d

Thu4/2/13

Wed4/8/13

161

30.1

SetFixtures

4.00d

135,136,146,154

Thu4/2/13

Tue4/7/13

162

30.2

ConnectAppliances

1.00d

161

Wed4/8/13

Wed4/8/13

163

31

CountyFinalPlumbingInspection

0.00d

160

Wed4/8/13

Wed4/8/13

164

32

ExteriorLandscaping

32.00d

Mon1/12/13

Tue2/24/13

165

32.1

RoughFinalGrade

1.00d

119

Mon1/12/13

Mon1/12/13

166

32.2

Patios

7.00d

165,119

Tue1/13/13

Wed1/21/13

167

32.3

Porches

5.00d

166,119

Thu1/22/13

Wed1/28/13

168

32.4

Sidewalks

7.00d

167,119

Thu1/29/13

Fri2/6/13

http://www.b4ubuild.com/resources/schedule/6kproj.shtml

11/13

4/30/2016

ASampleConstructionScheduleandCustomHomeBuildingTimeLine

169

32.5

Decks

7.00d

168,119

Mon2/9/13

Tue2/17/13

170

32.6

Driveways

2.00d

165,169

Wed2/18/13

Thu2/19/13

171

32.7

FinalGradeandSeed

3.00d

170,166,167,168

Fri2/20/13

Tue2/24/13

172

33

ElectricalFinalTrim

160.00d

Thu6/5/12

Wed1/14/13

173

33.1

Switch&Plug

2.00d

142,100

Tue1/13/13

Wed1/14/13

174

33.2

InstallFixtures

1.00d

Thu6/5/12

Thu6/5/12

175

33.3

ConnectAppliances

1.00d

Thu6/5/12

Thu6/5/12

176

34

Hardware

12.00d

Fri3/27/13

Mon4/13/13

177

34.1

DoorHardware

2.00d

145,146

Fri3/27/13

Mon3/30/13

178

34.2

BathHardware

2.00d

145,146

Fri3/27/13

Mon3/30/13

179

34.3

Mirrors

5.00d

178

Tue3/31/13

Mon4/6/13

180

34.4

ShowerDoors

10.00d

178

Tue3/31/13

Mon4/13/13

181

35

Draw#8(Primepaint,cabinets,doors)

0.00d

142,152,154

Tue2/17/13

Tue2/17/13

182

36

Draw#9(Trim,furnace,hrdwd,tile,rails)

0.00d

153,181

Tue2/17/13

Tue2/17/13

183

37

Draw#10(Plumbing&elec.trim,finalpaint)

0.00d

146,182

Thu3/26/13

Thu3/26/13

184

38

FinalBuildingInspection

0.00d

183

Thu3/26/13

Thu3/26/13

185

39

Use&OccupancyCertificate

0.00d

184FS+3d

Tue3/31/13

Tue3/31/13

186

40

FirstWalkthru

0.00d

185

Tue3/31/13

Tue3/31/13

http://www.b4ubuild.com/resources/schedule/6kproj.shtml

12/13

4/30/2016

186

40

FirstWalkthru

187

41

188

ASampleConstructionScheduleandCustomHomeBuildingTimeLine

0.00d

185

Tue3/31/13

Tue3/31/13

Draw#11(Finalpaymentpercontract)

0.00d

186

Tue3/31/13

Tue3/31/13

42

FinalPunchout

9.00d

Wed4/1/13

Mon4/13/13

189

42.1

PunchOutWalkthruList

4.00d

186

Wed4/1/13

Mon4/6/13

190

42.2

TrimandAdjustDoors

2.00d

184,189

Tue4/7/13

Wed4/8/13

191

42.3

PaintTouchup

3.00d

190

Thu4/9/13

Mon4/13/13

192

43

Cleaning

14.00d

Fri3/27/13

Wed4/15/13

193

43.1

Windows

3.00d

145,146

Fri3/27/13

Tue3/31/13

194

43.2

RoughClean

3.00d

193

Wed4/1/13

Fri4/3/13

195

43.3

FinalClean

2.00d

176,188

Tue4/14/13

Wed4/15/13

196

44

FinalWalkthrough

0.00d

187,188,192

Wed4/15/13

Wed4/15/13

197

45

Movein

0.00d

196FS+1d

Thu4/16/13

Thu4/16/13

http://www.b4ubuild.com/resources/schedule/6kproj.shtml