Professional Documents
Culture Documents
Session Objectives
Course: Civil Engineering
Project Management and Engineering Economics
UNIT II
Session
Session Objective
Segregate /spilling into a group and defining shoot form goal to achieve small
group of activities.
Able to plot a WBS or activities of project on time - vs. activity and finding project
duration.
10
11
12
Defining critical path of project.
13
14
A calculating a slag duration in non critical activities and identifying type of float.
15
16
17
agencies.
Development of control & information system.
Project of a house
Level 1
House
Masonry work
Carpentry work
Survey & land leveling
Electric Water
fittings& Sanitary fittings Finishing
Level 2
projects
A particular activity is shown by one bar without its sub-activities
So effective control on activities cannot be achieved.
But for effective control of activity stages can be marked on activity bar( called
milestones)
2. Review of project progress:
- Bar chart does not show the progress of work so can not be used as a control
-
device
For proper control it is necessary to know the progress at a particular instant of
time
This can be done by showing the progress of by hatched lines on activity bar &
rescheduling
Such rescheduling cannot be reflected in bar chart
Forward Planning:
In this method a planner starts from the initial event & builds up the events &
activities logically & sequentially until end event is reached. In this method planner
asks himself the following questions:
-what event comes next?
-what are dependent events?
-what events can take place concurrently?
2.
Backward planning:
In this method planner starts with end event & arranges the events
&
activities until the initial event is reached. Planner asks himself it we want to achieve
this, what events or activities should have taken place?
3. Combined planning:
In practice this method is followed. At any stage planner may need to traverse
the network back & forth several times until it is found to be satisfactory. The planner
must ask himself the following questions:
-what event or events must be completed before the particular event can start?
-what event or events follows this?
-what activities can be accomplished simultaneously?
precedence relationships
Nodes are represented by squares or rectangles, but circles may also be
used
Activity number & description are written within bxes representing the
nodes
Eliminates the dummy activity
3. Network logica. This denotes the technical dependencies among the activities.
e.g. Network logic in the network drawn below is that activity A must be
completed before activity B can be started.
A
1
B
2
4. Dummya. It is similar to an activity but it does not consume any resources. Interdependence
of activities or events can be clearly shown.
5. Types of event-
C
D
4
7
Burst event
Merge eventPAINT
Successor event- the event that follows a particular event in the sequence of their
2.
4.
o
o
o
o
o
o
CPM
No.
1
2
3
4
5
Time
estimates
for
PERT
completion
of Time
estimates
are
not
so
Critical path is the time wise longest path A critical path is the path that
in a network
joins the critical events
Critical path is determined on the basis of Critical path is determined on
minimum float for each activity
III)
It is the earliest time at which the event can occur. It is the time by which all the
activities discharging into event under consideration are completed. It is also called as
earliest occurrence time.
Latest event timeThe latest time by which an event must occur to keep the project on schedule. It is
also called as latest allowable occurrence time.
Earliest start time (EST)The time by which the activity can start. This is equal to earliest event time of the
tail event of activity.
Earliest finish time (EFT)The earliest time by which it by which it can be completed.
Latest Start Time (LST)The latest time by which the activity can start without delaying the completion of
project as a whole.
Latest Finish Time (LFT)The latest time by which the activity can be completed without delaying the
project.
Total float
Free float
Independent float
Interfering float
Total float It is the time span by which the starting & the finishing of an activity can
be delayed without affecting the overall completion of the project. It is
sometimes found that certain activities have a difference between the
maximum time available for completion & their actual duration. This
2.9.2
2.9.3
2.9.4
based on the assumption that all activities start at their earliest time.
Independent float It is the excess time available if the preceding activity ends as late as
possible & the succeeding activity starts as early as possible.
Interfering float- It is the difference between total float & free float.
A
B
If time lag or lead is started then activity B cannot be finished earlier than the
interval after the finishing of activity.
e.g. Priming the walls of a house, next activity involves in selecting purchasing
& finally delivering the wall paper . it is important not to hang the paper until the
wall primer has dried for 24 hours.
A
B
Activity B cannot be started & cannot be finished earlier than the stated time
lag/lead after the start & finish of the activity A. This sequence is used ti
define overlapping independent activities
E.g. Both activities are two major cruising activities in prepaid week long
ocean cruise, the total time cannot less than the promised week.
work efforts.
Project is composed of many diversified activities.
PERT is a technique that statistically presents knowledge
about these
An estimate is made of not only the most probable time required to complete the
activity but some measures of uncertainties.
Probable time is incorporated with pessimistic estimate & optimistic estimates
They help to take uncertainty into account
2.11.3.1 The optimistic time:
This is the shortest possible time in which activities can be completed
We can complete the activity if everything is perfect
Optimistic time denoted by t0
2.11.3.2 Pessimistic time estimates:
Best guess of maximum time that would be required to complete the activity
It is long time when everything go wrong
This estimate does not include possible effects of highly unusual disasters
It is denoted by tp
2.11.3.3 Most likely time estimate:
It is most probable time, require for activity would most often require if normal
conditions prevail
This lies between optimistic & pessimistic time
It reflects a situation where conditions are normal
It is denoted by tL.
2.11.4 Frequency distribution:
Wide range in time estimates represents greater uncertainty & hence less
confidence, our ability to correctly anticipate the actual time that activity
will require
2.11.5 Mean, variance, standard deviation:
MEAN: Algebraic sum of time durations taken by various activities divided by
number of activities tm= t/n
DEVIATION: Difference between time under consideration & mean time
= t-tm
VARIANCE: It is mean of squared deviation. Degree of uncertainty is indicated
by variance.
2 = 2 / n
STANDARD DEVIATION: It is simply square root of variance
= (2 / n)1/2
2.11.6 Beta distribution:
It is a type of probability distribution which fit for PERT analysis
PERT is interested in finding that type of probability distribution which
satisfies the following conditions:
Distribution should have small probability of reaching the most optimistic
time
Small probability of reaching the most pessimistic time
Distribution should have one & only one most likely time
Distribution should be that the amount of uncertainty in the estimating can be
measured easily.
Standard deviation - =( tp-t0)/6
Variance = 2 = ((tp-t0 )/6)2
Expected time = (t0+4tL+tP)/6
Que.1 What is Gantt Chart? Explain with suitable example. State its merits and demerits.
Que.2 Define the term
1. Activity
2. Event
3. Critical Event
4. Critical Path
5. Optimistic Time to
6. Most likely time tm
7. Pessimistic time tp
8. Slag or float
9. Total float
10. Free Float
11. Independent float
12. Interdependent float
13. Dummy Activity
14. Critical activity
15. Concerned activity
16. Preceding activity
17. Succeeding activity
Que. 8 A small construction work comprises the following activities. The duration and restraints
are given below:
Activity
Duration(weeks)
Restraints
Starting activity
Starting activity
C follows A
D follows B
E follows C and D
F follows C and D
G follows E
H follows F
I follows G and F
J follows H and I
a) Draw CPM network and calculate total project duration. Show the critical path.
b) Calculate EST, EFT, LST, LFT, total float, free float for the activities.
Que. 9 A project consists of 8 activities. Precedence relation and activity times are given below.
Draw thye network diagram and compute the critical path for the activities.
Activity
Immediate predecessor
Activity time(weeks)
12
20
28
12
P,Q
28
T,S
12
U,V
Session outcome
1. Able to achieve short term goals by splitting the activities into groups.
2. Able to plot WBS or activities of project on time vs. activity for finding project duration
3. Able to correlate the activities and project duration by using advance techniques to
overcome the limitation of the bar chart.
4. Able to identify the critical activities and critical duration.
5. Able to define critical path of project.
6. Able to calculate slag duration in non critical activities and identify type of float.