You are on page 1of 11

INTERNATIONAL JOURNAL FOR RESEARCH IN EMERGING SCIENCE AND TECHNOLOGY, VOLUME-2, ISSUE-7, JULY-2015

E-ISSN: 2349-7610

A Case Study on SCADA Implementation in


220 kV Substation
Vinuta V Koluragi1
M.Tech(Power and Energy Systems)
Assisstant Professor
B.L.D.E.As V P Dr P. G. Halakatti College of Engg. & Tech., Bijapur.

ABSTRACT
Development of nation depends upon electricity energy and at present scenario there is large gap between electric generation and
load. This gap can be filled with proper control, monitoring and coordinating the distribution components at power sector. In this
view, Automation of power distribution system has increasingly been adopted by power utilities worldwide in recent years. As
part of its efforts to provide a more reliable supply to the customer and to enhance operational efficiency, the automation of the
power system can be achieved by SCADA (Supervisory Control And Data Acquisition). It is a boon to the automation concept of
dynamic technology. Karnataka Power Transmission Corporation Limited (KPTCL) has undertaken steps to automate existing
substation and new substation by use of most advanced controlling and monitoring technology ABB SCADA. Karnataka Power
Transmission Corporation Limited, presently with the help of SCADA covers major generating stations and Independent Power
Producers (IPP), receiving stations ranging from 33kV to 400kV, collects data from all feeders from 11 KV to 400 KV, upgrades
information to Load Despatch Center (LDC). Real time data acquisition from all interface points by SCADA, helps to perform
energy billing, energy audit and Availability Based Tariff (ABT) functions, and Sub-system to perform Open Access operations.
Keywords: Real Time Monitoring and Controlling, SCADA, RTU, ABT.
NOMENCLATURE

SCADA

: Supervisory Control And Data Acquisition

RTU

: Remote Terminal Unit

ABT

: Availability Based Tariff

operation

1. INTRODUCTION

are

the

major

operating

concerns.

Online

Karnataka Power Transmission Corporation Limited is a

monitoring, operation and control of the modern day power

registered company under the Companies Act, 1956 was

systems have become impossible without computer aided

incorporated on 28-7-1999 and is a company wholly owned by

monitoring & dispatching systems. The basic requirement to

the Government of Karnataka with an authorized share capital

fulfill these needs is SCADA.

of Rs. 1000 crores. KPTCL was formed on 01-08-1999 by

The ability to perform operations at an unattended location

carving out the Transmission and Distribution functions of the

from an attended station or operating center and to have a

erstwhile Karnataka Electricity Board [5].

definite indication that the operations have been successfully

Present day power systems have large interconnected

carried out can provide significant cost saving in the operation

networks. The success of the recently evolving electricity

of a system. This is exactly what is achieved through the

market structure will heavily depend on modern information

SCADA system. A formal definition of SCADA system, as

systems and online decision tools. Maintaining system

recommended by IEEE [1], is A collection of equipment that

security, reliability, quality, stability and ensuring economic

will provide an operator at a remote location with sufficient

VOLUME-2, ISSUE-7, JULY-2015

COPYRIGHT 2015 IJREST, ALL RIGHT RESERVED

57

INTERNATIONAL JOURNAL FOR RESEARCH IN EMERGING SCIENCE AND TECHNOLOGY, VOLUME-2, ISSUE-7, JULY-2015

E-ISSN: 2349-7610

information to determine the status of particular equipment or

2.1 Process Level Function: extracts the information from

a process and cause actions to take place regarding that

sensors/transducers in the substation and to send them to upper

equipment or process without being physically present.

level device, called bay level device. The other major task of

SCADA provides open architecture rather than a vendor

process level function is to receive the control command from

controlled proprietary environment. It interfaces hardware and

bay level device and execute it at the appropriate switch level.

software, and it includes functionality such as trending, alarm


handling, logging archiving, report generation, and facilitation
of automation. Thus SCADA has been used has powerful tool
for power system automation, that refers to automatic
switching, regulating, controlling, logging, protection etc. of
electric power flow without human intervention.

2.2 Bay Level Functions: acquire the data from the bay
and then mainly act on the primary (power circuit) equipment
of the bay. The different conceptual subparts of a substation
are encircled by line in figure 2.
Station Level Functions: are of two types.
2.2.1 Process Related Functions act on the data from

2. SCADA IMPLEMENTATION IN 220KV

multiple bays or substation level database. These functions are

SUBSTATION

used to submit the control commands for the primary

200/110/11kV Shivgiri substation Bijapur is newly installed

equipment (Circuit breakers) and collect the substation data

substation. Under IES project, automation of new substation is

like voltage, current, power factor etc. from the bay level

done through Substation Automation System (SAS) using IEC

devices. Each bay includes one primary equipment such as

61850. The functions performed by Substation Automation

transformers, feeders etc.

(SA) system are in, general, switch control, data monitoring,

2.2.2

protection etc. In IEC-61850, these functions are broken into

interface of the substation automation system to the local

low-level functions called sub-functions. Each sub-function is

station operator HMI (Human Machine Interface), to a remote

performed by the IED installed in the substation. Each IED

control centre for monitoring and maintenance.

Interface

Related Functions

enable

interactive

can perform one or many sub functions. A set of sub-functions


is integrated together to realize a substation automation

There are basically two types of equipment in a substation:

function. These communicate with each other through Local

(i) Primary equipments and (ii) Secondary equipments.

Area Network in the substation. Specific syntax and semantics

2.3.2.1 Primary Equipments Include

are defined for communication between sub-functions. All the


possible sub-functions have been standardized in IEC61850.Information produced and required by each substation
is given in the IEC-61850 standard [1].
The sub functions are assigned at three levels as shown in
figure 1: (i) Process level (ii) Bay level (iii) Station level

Fig 2: Conceptual Substation Bays [1]


transformer, switchgear etc. Secondary equipments include
protection, control and communication equipments. Further,
secondary equipments are categorized into three levels in IECFig 1: Levels defined in IEC 61850 [1]
VOLUME-2, ISSUE-7, JULY-2015

61850 standards. These are station level, bay level, and

COPYRIGHT 2015 IJREST, ALL RIGHT RESERVED

58

INTERNATIONAL JOURNAL FOR RESEARCH IN EMERGING SCIENCE AND TECHNOLOGY, VOLUME-2, ISSUE-7, JULY-2015

E-ISSN: 2349-7610

process level equipments. A conceptual substation automation

RET670-Transformer Protection IED: It is used for reliable

system based on the IEC 61850 standard is evolved and

protection & control of all types of power transformers and

depicted in figure 3.

reactors. Also it provides protection solution for any type of


transformer & shunt reactor application. It gives freedom to
select functionality according to our needs, basic functionality
is included and pre configured. A single RET670 can integrate
complete protection & control functionality for a transformer
& a connected transmission line. The distance protection
function can also be used as back up protection for faults with
in transformer & in connected lines. In all, RET670 increases
reliability and profitability of entire power system. Figure 4
shows RET670 IED.

Fig 3: Conceptual Substation Automation Topology [1]


With this conceptual view at 220kV substation Bijapur there
are 8 bays divided. Control and monitoring operation is
carried out both remotely and locally. At substation 4 IEDs are
used for collecting information and OFC is used for local
communication, for remote communication Ethernet and

Fig 4: RET670-Tansformer protection IED [8]

VSAT is used. SAS consists of Bay Control & Protection

It is designed to operate correctly over a wide frequency range

Panel and Protection Panel, they are manufactured by ABB.

in order to accommodate power system frequency variations

Control & Relay panels and Protection panel are inbuilt in

during disturbances. RET670 features also several function for

ABB panel.

local and remote apparatus control on all sides of transformer.

2.2.2.2. SCADA Equipments to Substation:


220/110/11kV substation control room is provided with Bay
Control & Protection panel and Protection panel by ABB. All
the ABB panels are equipped with 4 IEDs used for protection

It provides a large HMI for local control and instantly


accessing important data, such as settings, events and
disturbance information. 30 apparatuses can be controlled and
visualized. Large HMI provides overview of quick status of

and control. ABBs IED 670 series provides reliable, efficient

substation with position indications and service values [6].

and flexible protection, monitoring and control for all

REC670-Bay Control IED: It provides optimized control and

applications in sub-transmission and transmission systems.

reliable operation of switch yard. It provides pre configured

IED provides a common powerful hardware platform and an

control solution for any type of switch gear and different

extensive hardware-independent, modular function library.

switch gear configuration. REC670 enables the manual control

Setting, commissioning and maintenance procedures of all

of a tap-changer from a Substation Automation system. It also

IED are fast and simple. All are similar hence user can learn

integrates advanced voltage control for transformers in a

about one to know them all. These can communicate easily

substation in a single IED. This eliminates the need for

with IEC61850.

dedicated voltage control devices in cases where the

List of Intelligent Electronic Device (IED) 670:

transformer protection is not equipped with voltage control.

1.

RET670-Transformer Protection IED.

The REC670 IEDs feature a large HMI for local control and

2.

REC670-Bay Control IED.

instant access to important data, such as settings, events and

3.

REL670-Line Distance Protection IED.

disturbance information. The control is based on the select

4.

REB670-Busbar Differential Protection IED.

before operate principle to ensure secure operation and to


avoid human mistakes. Control screen can be selected as

VOLUME-2, ISSUE-7, JULY-2015

COPYRIGHT 2015 IJREST, ALL RIGHT RESERVED

59

INTERNATIONAL JOURNAL FOR RESEARCH IN EMERGING SCIENCE AND TECHNOLOGY, VOLUME-2, ISSUE-7, JULY-2015

E-ISSN: 2349-7610

default screen. Control commands can be directly executed


and important measurements can be read. All measurements
are available in IED can be shown on HMI. Graphical display
can be configured as it is at substation. Figure 5 shows
REC670 IED.

Fig 6: REL670-Line distance protection IED [8]


independent, which ensures high reliability for all types of
lines. The distance and earth-fault protection functions can
communicate with remote end in any communication scheme.
It offers full control and interlocking functionality required for

Fig 5: REC670 -Bay control IED [8]

control of apparatuses in a substation. The integrated HMI


REC670 is able to handle a large number of analog signals
from CTs and VTs. The outstanding I/O capability enables
control of several bays with complete measurement with only
one IED. One REC670 IED is capable of handling control of
all apparatuses in one entire diameter in 1 breaker

allows secure and quick local control for stand-alone


applications and provides back-up control for substation
automation systems. REL670 provides efficient substation
automation solutions in terms of performance, redundancy and
cost for any high voltage application [6].

arrangement including breaker failure protection for all


REB670-Busbar Differential Protection IED: It is designed

breakers [6].

for the protection and monitoring of bus bars. REB670


REL670-Line Distance Protection IED: It provides versatile
protection,

monitoring

maximum

flexibility

and
and

control

functionality

performance

optimized

with
for

transmission overhead lines and cables. The powerful IED


provides distance protection for double circuit, parallel
operating and series compensated lines. REL670 IEDs are able
to protect and control several objects, for instance a
combination of a line and a transformer with a single IED. As
a result, this IED increases both the reliability and profitability
of entire power system. REL670 provides both customized

protects single and double bus bars with or without transfer


bus, double circuit breaker or one-and-half circuit breaker
arrangements. It provides selective, reliable and fast fault
clearance for all types of internal phase-to-phase and phase-toearth faults in solidly earthed or low-impedance earthed power
systems. At the same time, it maintains complete stability for
external faults, even when heavy CT saturation occurs. It can
also handle all internal multi-phase faults in isolated or highimpedance earthed power systems [6]. Figure 7 shows
REB670 IED.

and pre-configured protection solutions. The pre-configured


IEDs are equipped with complete functionality adapted for
four different configuration alternatives: single pole breaker or
multi-breaker arrangements with single or three phase
tripping. Figure 28 shows REL670 IED.
REL670 provides protection of power lines with high
sensitivity

and

low

requirement

on

remote

end

communication. Measurements and setting of all five zones


with six setting groups are made completely

VOLUME-2, ISSUE-7, JULY-2015

Fig 7: REB670-Bus bar differential protection IED [8]


2.2.2.3. SCADA Connections:

COPYRIGHT 2015 IJREST, ALL RIGHT RESERVED

60

INTERNATIONAL JOURNAL FOR RESEARCH IN EMERGING SCIENCE AND TECHNOLOGY, VOLUME-2, ISSUE-7, JULY-2015

At 220/110/11kV substation, Substation Automation System

E-ISSN: 2349-7610

11kV feeder

(SAS) consists of 27 panels for protection and bay control.


Layout of panels at control room is shown in figure 8.

Feeder

Feeder

Feeder

B&P - Bay Control & Protection Panel

1&2

3&4

5&6

P - Protection Panel

B&P

B&P

B&P

BBA - Bus Bar Protection Panel

INDI 1 Indi line 1

INDI 2 Indi line 2

TRF 1 HV Transformer 1 HV side

TRF 1 LV Transformer 1 LV side

TRF 2 HV Transformer 2 HV side

TRF 2 LV Transformer 2 LV side

BGD 1 Basavan Bagewadi line 1

BGD 2 Basavan Bagewadi line 2

Fig 8: Layout of panels at Control center at 220/110/11kV


substation
IES project provides Ruzzegged com (Ethernet) Switch, 3
personal computers DRPC, SAS1 and SAS2, printer, event
list recorder and for communication VSAT, OFC. Connection
of ABB panels is shown in figure 9. There are 8 bays at
substation; at each bay have one ruzzegged com switch which
connects all bay information to main SAS through OFC.
Information from SAS can be monitored and controlled
locally and also information is sent to Master Control center

For SAS

SAS

(MCC).
SUX
Station
Auxiliary
Bay
Control
Panel

2BBA1
220kV Bus
Bar
Protection
Panel

2BBA2
220kV Bus
Bar
Protection
Panel

220kV line

I
N
D
I1
P

I
N
D
I
1
B
&
P

I
N
D
I
2
P

I
N
D
I
2
B
&
P

Bus
Coupler
B&P

T
R
F
1
H
V
B
&
P

T
R
F
1
L
V
B
&
P

Fig 9: Connection of ABB panels at substation


As shown in figure 9 communication network used is StarRing topology. This topology has potential to provide time

BGD
2
P

BGD 2
B&P

BGD
1
P

BGD
1
B&P

TRF
2
HV
B&P

TRF
2
LV
B&P

delay within allowable range and also offers the better


reliability of the process bus.
2.2.2.4. SCADA Operations:
Local operator at substation control room observes and

110kV line

monitors 220kV, 110kV and 11kV lines. Single line diagram


11kV
Bank
B&P

10 MAV
TRF HV
110/11kV
IE 2
B&P

VOLUME-2, ISSUE-7, JULY-2015

monitoring screen display of 220/110/11kV, 110kV and 11kV


110kV
BGD B&P
Bijapur
B&P

110kV Bus
Coupler
IE 1
B&P

line is shown in figure 10(a), 10(b) and 10(c) respectively.


Overview of 220/110/11kV substation Bijapur is monitored by
monitored by operator at control room. Same single line

COPYRIGHT 2015 IJREST, ALL RIGHT RESERVED

61

INTERNATIONAL JOURNAL FOR RESEARCH IN EMERGING SCIENCE AND TECHNOLOGY, VOLUME-2, ISSUE-7, JULY-2015

E-ISSN: 2349-7610

diagram is displayed at remote control center. In single


diagram display of SCADA screen symbols of Lighting
Arrestor (LA), Gang or Group Operated switch (GOS) and
Circuit Breaker (CB) are used. Table 1 shows symbols used
for SCADA.
Table 1: Symbols used in SCADA Screen
Sl

Equipment

Symbols

No.

Identity
No.

Lighting

89CE

Arrestor
(LA)
grounding
Fig 10(B): Single Line Diagram Display of 110kv Line at
Control Room

Gang or
2

Group

89D

Operated
switch
(GOS)

Circuit

52

Breaker
(CB)

Fig 10(C): Single Line Diagram Display of 11kv Line at


Control Room.
At present operator at substation operates 11kV circuit
breakers at control room. He note down the measurement
values displayed on monitoring screen as shown on figure 11.
Real time values are noted at every one hour and daily load is
generated. Also SAS provides facility of event recording and
alarms for operator.
There is also facility to operate GOS remotely. With the help
of IED fault can be recorded. 100 disturbance records can be
Fig 10(A): Single Line Diagram Display of 220/110/11kv

maintained with time and date. Indication during disturbances

Line at Control Room

is displayed which helps operator to carry out precaution or


solve the problem.

VOLUME-2, ISSUE-7, JULY-2015

COPYRIGHT 2015 IJREST, ALL RIGHT RESERVED

62

INTERNATIONAL JOURNAL FOR RESEARCH IN EMERGING SCIENCE AND TECHNOLOGY, VOLUME-2, ISSUE-7, JULY-2015

E-ISSN: 2349-7610

breaker, Supervisory control is required switch off or switch


on a consumer, Supervisory control is required to control the
generation as and when control is extended.
Scenario of power system without control centers:

There was no Grid Discipline.

Due to indiscipline there was problem of low voltage


and low frequency.

There were frequent Grid failures.

Non optimum utilization of available resources.

There was no real time availability of data/ events


occurring.

Fig 11(a):220kV measurement values.

Inefficient

Power

System

Operation

&

Load

Management

Due to no regulation wide gap in Demand - Supply


position.

Low voltages at Consumer end.

To overcome all problems India undergone Grid Discipline


through SCADA. In this view all Generation station, receiving
station and distribution station were integrated in project. Thus
data from 110kV & 220/110/11kV substation Bijapur are sent
to LDC for further operation. LDCs architecture, function is
Fig 11(b):110kV measurement values.
Table 2 gives the incoming and outgoing voltage, current,
active & reactive power, power factor and frequency observed
on 220kV measurement monitoring screen on 07/07/2011 time

briefly explained in this section.


Indian Power System Load Despatch Centers is divided into

At National level

11.00.08.

2.3. Load Despatch Center:

National Load Despatch Centre (NLDC)

At Regional Level

Load Despatch Center (LDC) is the hub for load despatch and

Five Regional grids

control, it requires acquiring all data from generation and

Regional Load Despatch Centers (RLDC)

substation to match generation and load. LDC requires data


with respect to available generation and load to be attended.

At State Level

As such real time data is required from all Generating stations;

State Load Despatch Centre (SLDC)

real time data is required from receiving stations; real time

SLDCs at each state

data is required from Interface points from where power is


delivered to Distribution companies or Consumers. LDC also

A typical architecture of an Energy management system is

has to exercise control over the receiving stations, and

shown in figure 12.

consumers and if necessary the Generators also. As such,

Table 2: 220Kv Measurement Monitoring Values

Supervisory control is required to shed loads by opening a

VOLUME-2, ISSUE-7, JULY-2015

COPYRIGHT 2015 IJREST, ALL RIGHT RESERVED

63

INTERNATIONAL JOURNAL FOR RESEARCH IN EMERGING SCIENCE AND TECHNOLOGY, VOLUME-2, ISSUE-7, JULY-2015

DATE

TIME

INDI-1

INDI-2

07/07/2011

11.00.08

201

202

Voltage in

Vry

215.01

214.67

Vyb

217.42

Vbr

BC 203

E-ISSN: 2349-7610

TRAFO-

BGWD-

BGWD-

TRAFO-

1 204

1 206

2 207

2 208

215.02

215.16

215.05

214.48

215.18

217.59

217.76

217.37

217.63

217.21

217.37

213.46

213.22

213.45

213.13

214.17

213.67

213.75

L1

0.00

87.40

0.00

50.23

186.78

0.00

49.56

L2

0.00

89.90

0.00

51.67

192.67

0.00

51.32

L3

0.00

91.26

0.00

50.48

191.50

0.00

49.75

MW

0.00

30.55

0.00

17.97

-66.39

0.00

17.75

MVAR

0.00

13.54

0.00

5.95

-25.57

0.00

5.87

0.00

0.91

0.00

0.95

0.93

0.00

0.95

49.91

49.90

49.9

49.90

49.90

49.90

49.89

kV

Current in
Ampere

Active
power
Reactive
power
Power
factor
Frequency

Hz

Northern Regional Load Despatch Center (NRLDC)

Eastern Regional Load Despatch Center (ERLDC)

Southern Regional Load Despatch Center (SRLDC)

Western Regional Load Despatch Center (WRLDC)

Northern Eastern Regional Load Despatch Center


(NERLDC)

Southern region consists of 5 State Load Despatch Centers,


they are

Pondicherry

Fig 12: A Typical Architecture of an Energy Management

Tamilnadu

System

Kerala

Karnataka

Andhra

As shown in figure 34 data collected from all substations


through SAS or RTU is sent to Area control center (ACC) and
then same data is communicated to Regional Control Center

Central generation plants, State generation plants and

(RCC).National control center will look after the whole grid.

Independent Plant Producers (IPP) connect to common Power

There are 5 Regional Load Despatch Center, they are

Grid of India. As objective of LDC is to match generation and

VOLUME-2, ISSUE-7, JULY-2015

COPYRIGHT 2015 IJREST, ALL RIGHT RESERVED

64

INTERNATIONAL JOURNAL FOR RESEARCH IN EMERGING SCIENCE AND TECHNOLOGY, VOLUME-2, ISSUE-7, JULY-2015

E-ISSN: 2349-7610

load, there is need to continuously monitor and control.

At LDC, operator can observe generation, power flow,

Karnataka states Load Despatch Center is situated at

schedule and actual energy available etc as depicted in figure

Bangalore. At SLDC Control center, Grid connection of

13.

southern region is observed. Role of SLDC is to collect

2. Open Access Monitoring: IPP can go for open access if

information from electrical companies of Karnataka and send

they wish SCADA also provides information about open

data to SRLDC. Generation and load of state is monitored and

access monitoring screen for operator.

controlled by SLDC. SLDCs send the requisition of load to the

3. ABT monitoring Screen: At KPTCL tariff is basically

SRLDCs, against their entitlements out of available power

classified into 3 components, they are; Energy consumption,

from Central Sector Generation and the SRLDCs allocate total

Maximum demand and Unscheduled Interruption (UI).

available power to various states in the ratio of their

UI component is dependent on frequency, when load exceeds

entitlements. According to available power SLDCs schedule

generation frequency decreases depend on decrease in

power for state previous day & ESCOMs had to operate

frequency additional charges are penalized. Figure 14 shows

according to schedule. If there is any problem at generation

ABT Monitoring Screen at control center. UI charges are

then it informed to SLDCs by revising. SLDCs control state

decided by CEA.

generators according to load. Data acquired at SLDC is used


for Energy auditing, Energy billing and Availability Based
Tariff (ABT).
SRLDC collects data from SLDC and controls Central
Generation. NLDC monitors all SRLDC and communicate
with Central electricity Authority (CEA).
2.3.1. SCADA Application at LDC:
1. Network application overview: The SCADA systems
caters to the whole of Karnataka state which has five
Distribution companies and 23 major generating stations and
major IPPs and Central Generation Share. Figure 35 shows
monitoring screen at control center for Karnataka state.

Fig 14: ABT Monitoring Screen [4]


As SCADA is integration of hardware and software, care must
be taken that there exist proper synchronization between them.
RTU 560A at 110/11kV substation City Bijapur is digital
equipment no maintenance is required but proper cleaning of
panel has to be carried out. Minor work for adaptability of
SCADA at 110/11kV substation were improvement of
earthing, Restoration of control desk (this includes, providing
indication lamps, closing coils and TNC switches) and Wiring
of breaker position indication in 11kv.
2.4. Maintenance:
Improvement of earthing is done by providing one CI pipe
electrode as per KPTCL standard CI earthing 50 x 6 mm MS

Fig 13: Monitoring screen for Karnataka state LDC [4]

flat for connection to earth mat 50 x 6 mm GI flat for raisers


new RTU is connected to same earth with other C&R panel.
Figure 15 shows connection for improvement of earthing.

VOLUME-2, ISSUE-7, JULY-2015

COPYRIGHT 2015 IJREST, ALL RIGHT RESERVED

65

INTERNATIONAL JOURNAL FOR RESEARCH IN EMERGING SCIENCE AND TECHNOLOGY, VOLUME-2, ISSUE-7, JULY-2015

E-ISSN: 2349-7610

Real time data acquisition from all interface points by SCADA


such as voltage, current, frequency, active power, reactive
power and power factor. Operators at all substations will send
their respective load and energy required to the LDC. LDC
sends the required total load required by to SRLDC. SRLDC
according to available generation prepares load schedule and
send to LDC, this schedule must be followed by all stations.
During generation failure, availability of generation will be
Fig 15: Connection for improvement of earthing

updated to LDC; LDC will inform further it to all substations


so that proper load control can be carried out without any

When earth mat is not provided at substation, earth resistance

interruption of power.

for SCADA has to note down after installation work at

observed and controlled, thus large gap between generation

particular substation. Table 3 gives SCADA earth resistance at

and load is reduced. It also helps to perform energy billing,

110/11kV substation Atarga during visit with ABB committee

energy audit and Availability Based Tariff(ABT) functions,

on 08/07/2011. UPS for RTU 560A will under go test for

and Sub-system to perform Open Access operations at

battery back up condition.

LDC.SCADA has facilities to record data, event list,

Table 3 : Earth resistance for SCADA


Resistance in /V

Sl No.

Equipment

SCADA CI Pipe

0.28/0.6V

VSAT GI pipe

0.29/0.6V

RTU Panel

0.23/0.5V

C&R panel

0.25/0.4V

110kV TRF

0.6/0.9V

11kV TRF

1.0/0.9V

disturbance records, and trip values during fault etc., with help
of these facilities operator at substation can analyze fault, if
any mistakes in recording readings can be easily sorted out.
Thus concluding that a full fledge SCADA system is very
much necessary for monitoring, controlling, fault detection
and prevention and to make restoration power supply activities
easier and faster.

REFERENCES
[1]

KPTCL training report Remote Substation Monitoring


And Control through SCADA, 05-09 October 2009.

3. CONCLUSION
Power Systems are large complex systems covering vast areas

In this way the total grid can be

[2]

Paper presented

[3]

Martin

Chartrand,

Dual

Redundant

Controller

National grids and highly nonlinear, high order system. Many

Systems, Control Microsystems White Paper, October

process operations need to be coordinated and millions of

2004.

devices requiring harmonious interplay. The Energy flows

[4]

Chandrashekar, Mallakkappa S Integrated Extended

from various Generating stations to various Receiving Sub

SCADA project KPTCL IES Summary, October 31

stations via Transmission networks. On line monitoring,

2007.

operation and control of the modern day power systems is

[5]

Manuals and website

required for maintaining system security, reliability, quality,

[6]

ABB RTU 560A Manual.

stability and ensuring economic operation,. The basic

[7]

www.kptcl.com and www.abb.com

requirement is of power system automation which is achieved

BIOGRAPHY

by SCADA.
SCADA covers major generating stations and Independent

Ms. Vinuta V Koluragi

Power Producers (IPP), receiving stations ranging from 33kV

Bijapur, Karnataka, India. on 13th

to 400kV, collects data from all feeders from 11 KV to 400

1987.

KV, upgrades information to Load Despatch Center (LDC).

Electrical & Electronics from B.L.D.E.As

VOLUME-2, ISSUE-7, JULY-2015

COPYRIGHT 2015 IJREST, ALL RIGHT RESERVED

She

obtained

B.E

was born in

degree

July
in

66

INTERNATIONAL JOURNAL FOR RESEARCH IN EMERGING SCIENCE AND TECHNOLOGY, VOLUME-2, ISSUE-7, JULY-2015

E-ISSN: 2349-7610

Bijapur under VTU, Belgaum. She obtained M.Tech degree


in Power & Energy System from BEC Bagalkot under VTU,
Belgaum.
She is currently working as Assisstant Professor at
B.L.D.E.As V P Dr P. G. Halakatti College of Engg. &
Tech., Bijapur. Her areas of interest are Renewable Energy
Systems, PLC and SCADA,Control Systems, Power systems.

VOLUME-2, ISSUE-7, JULY-2015

COPYRIGHT 2015 IJREST, ALL RIGHT RESERVED

67

You might also like