Professional Documents
Culture Documents
10/26/2016
OUTLINE
Konversi Energi
Primer Menjadi
Energi Listrik
Produk
Penjualan &
Penyaluran Produk
Revenue/
Penghasilan
Energi Primer/
Sumber Energi
Terbarukan
Teknologi
Pembangkit Listrik
Tenaga Listrik
Titik Koneksi,
Jaringan Listrik PLN
Pembayaran PLN
PLTBG
IDR/USD as FIT
Regulation
Resources Owner
Developers
Resources Owner
FEEDSTOCK (POME)
Private / BUMN /
Public
Own Project
(In-House or Turn-Key)
BOO Scheme
(Built-Own-Operate)
Third Party
Project Developer
Mechanism
BOOT Scheme
(Built-Own-OperateTransfer
OUTLINE
Studi
Interkoneksi
Pengurusan
Ijin, Akusisi
Lahan
6 ~12 bulan
12 ~ 18 bulan
PJBL/PPA
12 bulan
Detail
Engineering
Design
Financing
Procurement
Equitas
Konsep/
Basic Desain
Perijinan &
Lahan
EPC Kontrak
Draft
O&M Kontrak
Draft
Typically 15 ~ 20 years
O&M
COD
Production
Construction
Fuel Supply
Agreement
Draft
Construction Stage
Operational
Stage
RISK MANAGEMENT and DUE DILIGENCE MUST BE DONE IN ALL STAGES OF THE PROJECTS!!
6 - 12 months
6 - 12 months
12 18 months
Typically 15 ~ 20 years
1.
2.
3.
Feasibility Study
4.
5.
6.
7.
8.
Land Acquisition
OUTLINE
Independent
Environment & SocioCulture Consultant
konsultan ahli
lingkungan,sosio-kultur
harus nasional/lokal
FIELD REVIEW/CHECK
Independent
Specilist
spesialis ahli project biogas yang
9
berpengalaman nasional/internasional
Independent
Environment & SocioCulture Consultant
konsultan ahli
lingkungan,sosio-kultur
harus nasional/lokal
PROPER DUE
DILIGENCE
MANFAAT:
Mendapatkan proposal proyek dan pengembang proyek yang dapat
diandalkan dalam mengembangkan/mewujudkan proyek.
Note:
Due Diligence/Uji Tuntas adalah suatu proses yang berulang yang harus dilakukan oleh
lender/investor untuk sampai pada tahap dimana lender/investor yakin dan puas bahwa
tidak ada lagi gap/resiko signifikan pada proposal proyek yang diajukan oleh pengembang
dan lender/investor yakin bahwa pengembang akan mampu mewujudkan proyeknya
sesuai dengan target dan jadwal yang ditentukan, dan project tersebut mampu beroperasi
dan menghasilkan revenue sesuai dengan yang diperkirakan sehingga pada akhirnya
lender/investor sampai pada keputusan untuk membiayai proyek.
12
13
FUEL
SUPPLIER
Fuel Supply
Agreement
Partner 2
Shareholders
Agreement
Deliver or pay
Agreement
LENDERS
Loan Agreement
PLN
Other
equity
investors
POWER
PURCHASER
Power Purchase
Agreement
Project
Vehicle
Permits &
Licenses
HOST
GOVERNMENT
Permits (IUPTL, Principal
Permit, IMB, UKL-UPL, Etc)
Loan Proceeds
Construction
Contract
Insurance
Agreement
O & M Contract
Sub-contractor
MAIN
CONTRACTOR
INSURANCE
COMPANY
EPC
Limited
Guarantees
O&M
OPERATOR
PLN
POWER
PURCHASER
LENDERS
Loan Agreement
Loan Repayment
Power Purchase
Agreement
Project
Sponsor
Loan Proceeds
Sales Proceeds
Construction
Contract
Sub-contractor
MAIN
CONTRACTOR
Loan Proceeds
EPC
15
GENERAL CHARATERISITICS
A small commercial project: The capacity of small scale Biogas Project
capacity is around 0.5 MW to 3 MW.
A dedicated Power Plant: A small scale IPP Biogas Power Plant that
connects and serves to PLN as a Sole Of Taker within TAKE OR PAY
PPA type or TAKE AND PAY PPA type.
17
Corporate Licenses
a.
b.
c.
d.
e.
f.
Shareholders review
a.
b.
c.
d.
Shareholders Agreement
Shareholders structure changes
Shareholders s structure changes
Voting procedures
Check
Yes
No
a.
b.
c.
CV of each manager
CV of each board member
Relevance of background experience
Proforma review
a.
b.
c.
d.
e.
a.
b.
c.
a.
b.
c.
Check
22
a.
b.
c.
d.
Agreement in place ?
Located in protected forest land?
Any guarantee on available capacity
Fair reward and penalty clause on meeting contracted
capacity
a.
b.
c.
d.
e.
f.
Interconnection requirements
Agreement and planned facilities
Testing and Commissioning Date & Procedures
Interconnection point review
Transaction point review
Power meter review
a.
b.
c.
Check
Yes
No
PPA review
a.
b.
c.
d.
PPA in place ?
Type of PPA contract: (take-or-pay contract)?
Any guarantee on available capacity
Fair reward and penalty clause on meeting contracted
capacity
a.
b.
c.
d.
e.
f.
a.
b.
c.
a.
b.
c.
d.
FSA in place?
Supply guarantee
FOB/CIF price structure
Review of transportation methodology
Check
Yes
No
25
26
Check , evaluate and review Project Access Plans & related Issues
10
Evaluate & review Cost Estimate & cash flow, and Project scheduling
11
12
Evaluate & review Project organization & quality control and O&M plan
Note
No
a.
a.
b.
c.
d.
e.
Is FS in place?
Is FS updated with the newest information?
Review of project layout
Review of general design
Review of DED by Technical specialists/consultants
a.
b.
a.
b.
c.
d.
e.
f.
Check
Yes
No
28
29
AMDAL/UKL-UPL in place?
UKL/UPL addresses and mitigates the environmental and
social risks
Critical socio-environmental issues addressed for project
development and operation
Critical socio-environmental issues reflected in the project
cost
a.
a.
b.
c.
4
a.
Check
Yes
No
31
32
Note
Note
Check that the financial model assumptions,
costs and revenues are reasonable and
realistic (e.g. the price of CER/carbon credit);
comparisons may be made with other project
investments, best practices, or in accordance
with the accounting standard. The Bank will
take input from engineer about project output
and project cash flow
Note
Review that the project has adequate cash
flow to pay for the operational cost, debt
(interest and principal), taxes, and dividend
Bank would want to ensure that PPA tariff
would be able to cover the project cost and
return on equity to project sponsor during the
term of the PPA
PPA tariff should be able to cover the
operational and maintenance cost that are
influenced by inflation
For biomass project, feedstock supply risk,
including prices should also be reflected in the
PPA tariff (however, the current price regime
does not provide a basis for tariff indexation.
35
EPC Cost:
Financing Cost:
Other Cost:
OPEX:
Operating Labor
General Administration & Others
Insurance
Digester Service & Maintenance
Gas Engine Service & Maintenance
36
Digester System
Unit Cost / MW
(USD Million)
CAL System
1.5 3
CSTR System
2.5 3.5
Install Capacity
1 MW
2,000,000
1.5 MW
2,500,000
2 MW
3,500,000
Capital Expenditures:
Project Development Cost
Site Preparation & Civil Work
Digester System, Piping & Flaring
Gas Cleaning & Pumps System
Gas-Engines & Generator
Controller & Electrikal System
Balance of Plants
Grid Interconection System
Other Cost (IDC & Insurance)
2%
5%
34%
11%
17%
10%
11%
4%
5%
100%
Operational Expenditures:
Operating Labour
General Administration & Others
Insurance
Digester Service & Maintenance
Gas Engine Service & Maintenance
25%
14%
5%
17%
39%
100%
Information
a.
b.
c.
2
a.
b.
c.
d.
Check
Yes
No
Financing plan
a.
a.
39
No
5
a.
b.
a.
a.
Check
Yes
No
40
No
9
Check
Yes
No
41
OUTLINE
Resiko-resiko baru
tambahan yg
terindentifikasi
Rencana-rencana
baru Mitigasi
Resiko
Independent
Environment & SocioCulture Consultant
konsultan ahli
lingkungan,sosio-kultur
harus nasional/lokal
FIELD REVIEW/CHECK
Independent Law
Consultant
konsultan ahli hukum
harus nasional
Independent
Specilist
spesialis ahli project biogas yang
43
berpengalaman nasional/internasional
Sosial
- Alokasi Resiko:
Contracts
Insurance
Management
+
SUITABLE ANAEROBIC DIGESTION TECHNOOGY
+
SUITABLE GAS HANDLING & SCRUBBING TECHNOLOGY
+
HIGH RELIABILITY & PERFORMANCE RECIPROCATING
GAS ENGINE
+
HIGH RELIABILITY GRID INTERCONNECTION
=
LONG LASTING, LOW COST INCOME STREAM + OTHER
BENEFIT
Mitigasi
Alokasi
Resiko proyek di
alokasikan melalui
KONTRAK-KONTRAK:
- BOO/BOT/BOOT
agreement
- EPC contract
- Owner Financial Ability
- Insurance
- PPA
- Land Contracts
- Engineer
- Local Authorities
Identifikasi
- Detail POME &
BIOGAS Analysis
- Analisa Geoteknik
yang cukup akurat
- Concept Design
- Batasan Lingkungan
dan Sosial
- Local Political Risk
- Kebutuhan Equity
Mitigasi
Alokasi
RESIKO OPERASI