You are on page 1of 13

DRAFT

COLLECTION SYSTEM MASTER PLAN

ST U D Y A R E A 6

Preserving Bends Water Environment

CITY OF BEND COLLECTION SYSTEM MASTER PLAN

INTRODUCTION

STUDY AREA 6
TABLE OF CONTENTS
Introduction ....................................................................................................................................................
Study Area 5 ...................................................................................................................................................
Existing Sewers ........................................................................................................................................
Projects for Unserved Areas .........................................................................................................................
Criteria for Lateral Sewers .......................................................................................................................
Sanitary Sewer Project Development ...........................................................................................................
Pump Stations ................................................................................................................................................
Drake .....................................................................................................................................
Linster ...................................................................................................................................
Pacific....................................................................................................................................
Pioneer...................................................................................................................................
Underwood ............................................................................................................................
Pump Station Upgrades ...........................................................................................................................
Drake Pump Station Replacement ........................................................................................
Removal of Existing Pump Stations .......................................................................................................
System Capacity Deficiencies .......................................................................................................................
Existing Capacity Deficiencies ................................................................................................................
Future Capacity Deficiencies ..................................................................................................................
New Pump Station ....................................................................................................................................

1
1
2
2
3
3
3
3
3
6
6
6
6
6
6
6
6
6
6

APPENDIX
Figure A.6-1 Study Area 6 Proposed Sanitary Sewer Layout with Topo .........................
Figure A.6-2 Study Area 6 Proposed Sanitary Sewer Layout with Topo .........................

A-1
A-2

FIGURES
Figure 6-1 Master Plan Study Areas .................................................................................
Figure 6-2 Study Area 6 Proposed Sanitary Sewer Layout ...............................................
Figure 6-3 Study Area 6 Current Pump Station Service Areas .........................................
Figure 6-4 Study Area 6 Capacity Deficiencies ................................................................

2
4
5
7

TABLES
Table 6-1 Study Area 6 Characteristics..............................................................................
Table 6-2 Study Area 6 Population & Flows ....................................................................
Table 6-3 Study Area 6 Gravity Sewer Statistics ..............................................................
Table 6-4 Study Area 6 Proposed Sanitary Sewer System Projects ..................................
Table 6-5 Study Area 6 Pump Station Existing Installed Information ..............................
Table 6-6 Study Area 6 Recommended Pump Station Upgrades ......................................
Table 6-7 New Pump Station ............................................................................................
Table 6-8 Study Area 6 System Deficiencies Capital Project Cost Estimates ..................

MWH 2006

STUDY AREA 6

2
2
2
3
3
6
7
8

The City of Bend is the provider of wastewater collection and treatment service within the City of Bend
Urban Growth Boundary (UGB). The 2006 Collection System Master Plan was developed in cooperation
with the City of Bend Public Works Department to provide the roadmap for the providing service to all
existing users, existing developed areas that have not yet connected to the system and for new
development.. This includes areas outside of the UGB but within the Urban Area Reserve (UAR). The
key principles that the plan was based on were:
z Protect the public health and maintain the quality of the water environment within and around the
City of Bend.
z Provide ongoing system capacity and reliability to minimize the risk of Sanitary Sewer Overflows
(SSOs).
z Provide planning based on approved General Plan
z Expand existing system using a phased approach as capacity and/or service is needed.
z Provide capacity for service to existing developed areas that currently are not provided with
sanitary service.
z Provide service to development.
The results and recommendations of the Master Plan are summarized in the 2006 Collection System
Master Plan Report. In addition to the Master Plan Report, nine Study Area Plans were developed to
provide a detailed summary of the plans for providing sanitary service to each parcel. This includes a plan
for local gravity sewers, recommendations on the long-term operation of each pump station and the
correction of current and long-term system capacity deficiencies.

STUDY AREA 6
The planning area which includes both the areas of the UGB and the UAR is shown in Figure 6-1
Master Plan Study Areas. To organize and simplify the presentation of the information developed in the
Master Plan, the planning area has been divided into nine Study Areas. This document provides the
information for Study Area 6, which is the central portion of the City located on the east side of the
Deschutes River. This area is highlighted and labeled in Figure 6-1.
Study Area 6 consists of 1218 acres with only 833 acres classified as developable land. The remaining
area will not be developed as it consists of streets, utility corridors, areas zoned as public facilities and
unbuildable lands. This area currently provides sewer service to 2212 parcels. There are a total of 836
parcels that are not being served, of which 273 parcels are currently developed, but using septic systems.
The characteristics of Study Area 6 are summarized in Table 6-1.
As shown by these characteristics, 73% of the parcels and 73% of the planning area are developed. These
characteristics show that there will be relatively lower levels of growth in this area than in other parts of
the city. Based on the 2005 housing data and the build-out zoning and densities of the approved General
Plan, it is anticipated that the base wastewater flows generated in this area will increase from the current
0.436-mgd to 0.950-mgd. This base flow relates to an estimated peak flow of 2.68-mgd. This area also has

CITY OF BEND COLLECTION SYSTEM MASTER PLAN

STUDY AREA 6

Table 6-1
Study Area 6 Characteristics
Area
(acres)
1218

Served
Parcels
Number
2212

Area
(acres)
611

Total
Unserved Parcels
Area
Number
(acres)
836
223

Developed
Unserved Parcels
Area
Number
(acres)
273
28

Note: Data summary as of May 2005.

connected roof drains in the downtown area that may contribute to higher peak flow than have been
estimated. The population and flows for the study are shown in Table 6-2.
Table 6-2
Study Area 6 Population & Flows
Served Parcels

Unserved Parcels
Flow
Population
(mgd)

Condition

Flow
Population
(mgd)
Existing Urban Growth Boundary Only (City Limits)
2005
5455
0.436
Build-out
11,866
0.95
Planning Area (UGB + UAR)
Build-out
11,866
0.95

1042
-

0.083
-

Note: Data summary as of May 2005.

EXISTING SEWERS
Study Area 6 currently has 30.8-miles of gravity sewers
ranging in size from 6-inches in diameter to 36-inches in
diameter. A summary of the total length of gravity
sewer by line size is summarized in Table 6-3. 23.4miles or 76% of these gravity sewers are 6 and 8-inch
lines serving local neighborhoods. There are only 7.4miles of trunk sewers that are 10-inch or larger.
CRITERIA FOR LATERAL SEWERS
Determination of the feasibility of gravity sewer laterals
to service currently unsewered areas in the Bend system
depends on several factors. These include:
z The depth of the existing connection manhole or
cleanout
z The distance from the connecting manhole to the
most distant property parcel to be served

Table 6-3
Study Area 6
Gravity Sewer Statistics
Line
Diameter
(inches)

Feet

Miles

6
8
10
12
15
16
18
21
24
27
30
36

8587
115288
9940
7682
3014
4663
2013
2862
592
3996
2281
1854

1.6
21.8
1.9
1.5
0.6
0.9
0.4
0.5
0.1
0.8
0.4
0.4

Length

Percent
of Total
5.3
70.8
6.1
4.7
1.9
2.9
1.2
1.8
0.4
2.5
1.4
1.1

Note: Data summary as of May 2005

z The average slope of the terrain between the parcel to be served and the connecting manhole
z Minimum grades used for gravity sewers (i.e. 8 @ 0.004 ft/ft, 12 @ 0.0028 ft/ft, etc) to allow a
minimum velocity of 2 ft/sec
Figure 6-1 Master Plan Study Areas
MWH 2006

CITY OF BEND COLLECTION SYSTEM MASTER PLAN

z The depth of gravity sewer designs will not be driven by the existence or potential existence of
basements in structures.

Table 6-4
Study Area 6 New Sewer Systems
Capital Project Cost Estimates Study

z Gravity sewer service is possible when the finished floor of the structure to be serviced is at least 3
feet above the invert of the main in the street.
z Surface features or conflicting utilities that would prevent the installation of gravity sewers were
not evaluated.
The existing topography within the UGB is limited to 2-foot contours. The inverts for existing manhole or
cleanouts were not always available; therefore some assumptions were made regarding the feasibility of
extending gravity sewers to the unsewered parcels. The proposed sanitary sewer layouts for projects to
provide service to the unsewered areas within the UGB were developed within the guidelines and
limitations of the available information. Confirming field work to ascertain the elevation difference
between the connecting manhole and the parcel(s) to be served, along with confirmation of the connecting
manhole depth, must be done prior to design of these proposed projects.

SANITARY SEWER PROJECT DEVELOPMENT


The sanitary sewer projects are shown in Figure 6-2 Study Area 6 Proposed Sanitary Sewer Layout.
Each project has been given a Project ID. The Project ID is based on the number format of X-Y. This
number is based on the following codes:
z X Study Area Number
z Y Project Number within the Study Area
This Project ID system will be used to identify each of these projects during system development. Each
project has been summarized in Table 6-4. A more detailed figure of the study area proposed projects
with the 2-foot topography overlay is provided in the Appendix.

STUDY AREA 6

Length
(feet)
473
1,387
335
395
180
235
525
344
281
443
124
1,297
85
155
185
724
100
280
239
387

Project ID
6.01
6.02
6.03
6.04
6.05
6.06
6.07
6.08
6.09
6.10
6.11
6.12
6.13
6.14
6.15
6.16
6.17
6.18
6.19
6.20

Diameter
(inches)
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8

Notes
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area
Provides sewers to unsewered area

PUMP STATIONS
Table 6-5
Study Area 6 Pump Stations
Existing Installed Information

Study Area 6 currently has five pump stations. The service area for each of these pump stations is shown
in Figure 6-3. A list of the pump stations is shown in Table 6-5. The following terms are used in the
table to define each pump station:
z Modeled Yes in this column means that pump station is included in the INFOSWMM hydraulic
model. No means it has not been included in the model
z Firm Capacity The firm capacity is the capacity of the station with one pump out of service to act
as a redundant pump. This is a regulatory requirement.
z Installed Capacity The installed capacity is the pump station capacity with all pumps operating.
z Base Flow The base flow is the winter season flow based on area zoning.

Force Main
Diameter
Length
(in)
(ft)

Modeled

Number
Of
Pumps

Firm
Capacity
(gpm)

DRAKE

650

557

LINSTER

100

1854

PACIFIC

50

398

PIONEER

60

UNDERWOOD

150

564

Pump Station
Name

z RDII Flow RDII flow is the flow based on inflow into the system during heavy rainfall.
z Peak Hour Flow The peak hour flow will be the base flow multiplied by a diurnal peaking factor
of 1.8 and the seasonal peaking factor of 1.25

MWH 2006

Drake
The Drake Pump Station serves an area of 155 acres. This station service area is currently 53% sewered
serving 654 of the 1228 potential build-out dwelling units. The current (2005) estimated base flow for this
3

CITY OF BEND COLLECTION SYSTEM MASTER PLAN

MWH 2006

STUDY AREA 6

CITY OF BEND COLLECTION SYSTEM MASTER PLAN

MWH 2006

STUDY AREA 6

CITY OF BEND COLLECTION SYSTEM MASTER PLAN

station is 89-gpm with a peak hour flow of 233-gpm. The build-out estimated base flow for this station is
177-gpm with a peak flow of 446-gpm. The force main for this pump station is a 557-foot long 6-inch
line. The design velocity in this force main under firm pumping conditions is 7.4-fps. The design TDH
for this station is currently 64-feet. The existing station capacity of 650-gpm will meet the long-term
requirements of the service area, but the station is in poor physical condition. It is recommended that this
station be replaced with a new pump station located in the same area.

REMOVAL OF EXISTING PUMP STATIONS


Each of the existing pump stations was evaluated to determine if they could be removed from service by
construction a gravity sewer. None of the pump stations in Study Area 6 can be cost-effectively removed
from service.
Table 6-6
Recommended Pump Station Upgrades

Linster
The Linster Pump Station serves an area of 23 acres. This station service area is currently 68% sewered
serving 199 of the 292 potential build-out dwelling units. The current (2005) estimated base flow for this
station is 25-gpm with a peak hour flow of 61-gpm. The build-out estimated base flow for this station is
37-gpm with a peak flow of 88-gpm. The force main for this pump station is an 1854-foot long 4-inch
line. The design velocity in this force main under firm pumping conditions is 2.6-fps. The existing station
capacity of 100-gpm will meet the long-term requirements of the service area.
Pacific
The Pacific Pump Station serves an area of 8 acres. This station serves a commercial area. The build-out
estimated flow for this station is a peak flow of 11-gpm. The force main for this pump station is a 480foot long 2-inch line. The design velocity in this force main under firm pumping conditions is 5.1-fps.
The design TDH for this station is currently 34-feet. The existing station capacity of 50-gpm should meet
the long-term requirements of the service area.
Pioneer
The Pioneer Pump Station serves an area of 8 acres. This station serves the restroom facilities a Pioneer
Park. The existing station capacity of 60-gpm should meet the long-term requirements of the service area.
Underwood
The Underwood Pump Station serves an area of 16 acres. This station serves a commercial area. The
build-out estimated flow for this station is a peak flow of 35-gpm. The force main for this pump station is
a 564-foot long 4-inch line. The design velocity in this force main under firm pumping conditions is 3.8fps. The design TDH for this station is currently 18-feet. The existing station capacity of 150-gpm will
meet the long-term requirements of the service area.

STUDY AREA 6

Project ID

Pump Station Name

Upgrade

Cost
($)

Period

6.PS01

Drake Pump Station

Replace Drake Pump Station with new


station

$363,000

2006 - 2010

SYSTEM DEFICIENCIES
The Citys Collection System was evaluated to determine if there were any deficiencies under existing and
build-out flows. The analysis was performed using the calibrated 2005 INFOSWMM hydraulic model.
Each deficiency was analyzed to determine how the deficiency could be eliminated. Alternative methods
that were evaluated to eliminate each deficiency were: 1) Rerouting of flow to other points in the system,
2) Upsizing the existing lines and 3) Parallel sewers. The most cost effective alternative was identified as
a capital project for removal of the deficiency. Capacity deficiencies under existing and build-out flows
are shown schematically in Figure 6-4. The line segments shown in this figure are those that were
modeled in the INFOSWMM hydraulic model.
EXISTING
This analysis showed two existing capacity deficiencies in Study Area 6. These capacity deficiencies are
defined as Capital Projects 6-1 and 6-2. The line segments and the breakdown of the estimated cost for the
projects to correct these deficiencies are shown in Table 6-8. These projects will provide adequate
capacity to meet the required capacity through system build-out.
FUTURE
The system was also evaluated under build-out flow conditions with the proposed interceptor system. No
future capacity deficiencies were found.

PUMP STATION UPGRADES

NEW PUMP STATION

Pump station upgrades will be required to ensure that adequate pumping capacity is available to ensure
that there are no Sanitary Sewer Overflows (SSOs) in the system. The station capacity has been developed
to ensure that adequate redundancy is provided. There are no pump station upgrades required for capacity
increases. The only system upgrade that is recommended is the replacement of the Drake Pump Station
due to poor physical condition. This recommended pump station upgrade is shown in Table 6-6.

One of the primary goals of the master plan was to implement gravity solutions whenever possible. In
some cases, pump stations are required due to topography. A pump station was removed at 4th and
Addison in 2001. This station was replaced with a manhole and 14.6-feet of 21-inch PVC line. The flow
enters this manhole 4.5-feet lower than it exits the manhole. This results in the surcharge of 1200-feet of
gravity sewer upstream of the manhole. The upstream gravity sewer is located in an area that would be m
station is 89-gpm with a peak hour flow of 233-gpm. The build-out estimated base flow for this station is
177-gpm with a peak flow of 446-gpm. The force main for this pump station is a 557-foot long 6-inch
line. The design velocity in this force main under firm pumping conditions is 7.4-fps. The design TDH
for this station is currently 64-feet. The existing station capacity of 650-gpm will meet the long-term
requirements of the service area, but the station is in poor physical condition. It is recommended that this
station be replaced with a new pump station located in the same area.

Drake Pump Station Replacement


This physical condition of this station is questionable for long-term operation. The station has undergone
multiple modifications over its service life and the capability of the existing infrastructure has been
maximized. The City needs to evaluate and incorporate into their CIP the replacement of the current
station. The estimated cost to construct a new station is $363,000 not including land and easements for the
new station.

MWH 2006

CITY OF BEND COLLECTION SYSTEM MASTER PLAN

STUDY AREA 6

Linster
The Linster Pump Station serves an area of 23 acres. This station service area is currently 68% sewered
serving 199 of the 292 potential build-out dwelling units. The current (2005) estimated base flow for this
station is 25-gpm with a peak hour flow of 61-gpm. The build-out estimated base flow for this station is
37-gpm with a peak flow of 88-gpm. The force main for this pump station is an 1854-foot long 4-inch
line. The design velocity in this force main under firm pumping conditions is 2.6-fps. The existing station
capacity of 100-gpm will meet the long-term requirements of the service area make it extremely difficult
to replace the upstream gravity sewer at a new grade. This would require replacing up to 2700-feet of
gravity sewer and a bore under Highway 97. For this reason, it is recommended that a new pump station
be constructed to lift the flow and eliminate the system surcharging. This pump station will need to pump
a peak flow of 300-gpm at system build-out. The estimated cost of this station is $575,000, including an
estimated cost for land of $200,000. The project to add this new station is summarized in Table 6-7.
Table 6-7
New Pump Station
Project ID

Pump Station Name

Upgrade

Cost
($)

Period

$575,000

2006 - 2010

th

6.3

MWH 2006

New Station

Correct grade problem at 4 and


Addison

CITY OF BEND COLLECTION SYSTEM MASTER PLAN

STUDY AREA 6

Table 6-8
Study Area 6 System Deficiencies
Capital Project Cost Estimates
Quantities
Project
ID

6.1
6.2

Manhole ID
From

Manhole ID
To

Existing
Diameter
(in)

E1A-5
Total
1913-SW.17
E6.1-1
Total

E1A-4
E6.1-1
A-1
-

8
12
16
-

Unit Costs ($)

Total

Upgraded
Diameter
(in)

Length
(ft)

Manholes
(#)

Materials
($/ft)

Installation
($/ft)

Bypass
Pumping
($/ft)

Manholes
($/each)

Reconnection
($/each)

Restoration
($/ft)

Subtotal
($)

Engr/Legal/
Admin
@40%

Contingency
@30%

Total
($)

12
15
15
-

95
2235
195
-

0
6
0
-

12.75
18.80
18.80
-

72.00
77.00
77.00
-

11.60
11.60
11.60
-

3640
3640
3640
-

1000
1000
1000
-

7.35
7.88
7.88
-

12,616
12,616
322,689
28,154
350,843

5,046
5,046
129,076
11,262
140,338

5,299
5,299
135,530
11,825
147,355

22,961
22,961
587,295
51,240
638,535

Construction Costs based on ENR-CCI of 8449

MWH 2006

CITY OF BEND COLLECTION SYSTEM MASTER PLAN

STUDY AREA 6

APPENDIX

MWH 2006

3534
0

3558

3582

36
36

366

70
36

3708

2
36
8

4
374

2
6
37
4

3718

37 2

3748
3764 3774 3728
808
3794 379
6 3 0
87
2
3
2
4
38 384 4 3920
0
4
39
396
8
0
40

375
8

375
3768 37 6
76
3798 3 7 9
0
38
38 5 0
94
39
72

366 2

3658

3678
368 6
367 3670
4
3690
370 6
368
371 0
4

3652

2
365

3568
3562

6
358

3624

3630

3660

3618

361 4

3548

50
35

6
358

362
0

3610

3608

3528

3572

3584
3584

3580

3584

358
6

3546

4
35
7

3562

3584

4
36
0

3594

3592
3596

3630

362 6

3626

3618

3610

3618

3614 3616
3618
3612

3616

3608

3644

3612

3624
36
16

616

3622
3

36
3

3618 3624
3616

3602
3594

36
24
36
20

3638 3636

3644
3640

361 2

3606

35
8

361
6
3604

3598
3636

361 4

4
361
3614
36
16

3622

3616
3614
3614 3620

08

362

359
6

353

3558 3546

8
3606
8

3620

36

3750

3736

362

3596

68

35

356
35 8
70
35
7

359
8
36
06

3610

3600
361
6
14
36

3598

3602

3596

35
3578

36
18

24
36

3570
3592

0
35
3534
3550
52
8
3
3
5
552 4
36
2
02
35
3544 35
9
38
4
35
3582 3584 3582
9
8
3
3
5
5
7
88
6
3592
359
3594
6
35
35
3586
3584 3606
35
48
3
44
3 5 9 4 59 4
360 3
56
6
5
7H4
3592 3
36
592
igh3
02
359
58
4
359 w
35
a0y
3586 3
3588
4
46
58 8
358 97
8
3606
35 35
3576
68
58
357
6
357
36
0
3
562
00
357
2
3562 3556
3602
3576
3606
3604
3566
35
98
360
3562
0

48

35
68

35
68

0
36
62

3632

3564

3728

360

3784 3786

3878
3874
384 6

36
2

3730
8

22

363
6
36
04 3
3568
6

384
8

3678 3692

35
7

379 8

3710
3680
366 4

396 0

37
1

3
3904 3 928
91
2
00

54

39

40

6
39
8
39

58

38

3860 3
858
38
3842
54
3 82
6

3942

3984

406

40
3

40
76

90

40
40
40
18

4032

409

8
40
7

0
10
3994 4004 4016
3988
3978 3976
3956 3964

40
46
4024 40
34

40
40 58
50

4082

410
4 09 6 6

41
10

41
0

37

04

14

36

37

37
0
3716 4
373 372
2
2

24
37

Figure A.6-1
Study Area 6
Proposed Sanitary Sewer Layouts

76

36
8

4
37

72

373 4
08
96
37 36
94
36

36

35
9

372

373

20

02
37

3600

36

00

37

3638

37 3712
32
3730
374 6

3698

8
36

4
366

363

3666

36
94 3670

369
2
9
36

37

36
52

42
36

36
0

8
366

8
363
3654

26

3650

37

3634

38
36

6
362
6
3
6
6
3
36 3
3652 3646

358 2
3606

362

3
36

36 3
84 0
382 2

38

h
g

h
g

3652

3616

6.07

3652

6
362
6

0
354

3580

6.08

3640 3638

3616

2,000 Feet

3612

44

24

355 8
35
60

3570

3586

3652

3632

3608

3614

3 62 8

361 8

36
1

35

3
36

3612

06

3616

3636

362
3604

3536

36

h
g

3654
48
36

3556

3578

6.06

3628

42
35

3580
3582

358

8
36

00

1,000

358

3656

3626
3630

3620

3616

3580

360 2

44
36

1
36

35
26

3560

357 8
358
2

3628

361
2

36

22

3618

3628

3
3562

359

36

3626

3564

3604 3602

3
3598 606

3560
3556

3526
4
352

38
35

6
50 355
2
354 35
8
5
3566
5
3
6
55

0
362

362

3582

h
g

358

h
g

3578

352
8

6.03

h
g

8
35

3600

3612 6.13

358 4

3578

3592
2

3576

88
35
359

6.02

9
35

1
36

3588

4
358

18

360
361 0

3614

3610

361 0

6
3620 3

68

355

3576

3 58 4

35
94

3620
3612 3622

3634 3628

3606

361 6

3628

h
g

360

6
35

3574

360 0

360

02
36

h
g

3608

6.12

h
g

90
35

36
18

4
361

h
g

35 357
84

80
35

9
35

3592

18
6 10
3 6 361 3 6

2
358
4

3580

76

92

3570

64
35

3580

358

3576

3578

35

598
63
359
8
358

3588

3580

3600

35

35
3582

3560

353

h
g

3586
84 3574
35
35
76

6
352
2

36
0

360

6.01

72

02
36

2
360

358 6

35

80

6
35

6
35

352

3546

3602

6.04

6.11

3632

18
36
362 6

35

35
58

3560

3566

353

82
35

Deschutes River

No Planned Development

3618

Connection Points

School

3642

3626
40
36

Parks (No Planned Sewer Expansion)

3606

12

06

Proposed Sewer Projects

Existing Sanitary Sewer Lines

3582

3596

0
359

35
80

3624

357 6

3604

54
35

6.14

4
359

96
35

78

3576
357
3 57 6 4

3572
3550

h
g

34
36

3620

36

84

357 2
3572

64
35

6.05

8
361
3630

4 590
359 3

6.09

3628

h
g

98

3610
98
35 3596 3598

98

12

10 360
8
363
60
6

35

35

4
361

36

3612
36
18

355

3564

35

3604

h
g
6.10 h
g

361 8

3586
35

3596

360

0
36

36
00

360

3576

3616

0 2 594
36
3

3606 3604

12
36

3570
0
356
3616 3656
3568
3612 0
365
0
3652 3682 370
6
368

3740

36
02

0
361

6
35

362

3608

3608

3606

3574

357

37 3

365 8
6
367
0
3606

3664

3610

3606

38
35
3540

3622

3608

36

360
3614

08
36

361

3628

54
35

82
35 3
572

96
35

36
00

3608

4
357 3572
6

3774

372

88

72

3554

3548

8
352

3586

3638

8
64 36
3640 3642 3 36

3654

8
356
3564

2
360

6
59

36
36

3674

356 2

54

3734

3668

3660
364 6

3606

6
366

Dr

37

37
22

7
35

7
35

04

96

3712

3714

360
0

37
4

sh

3814

3742

363

371

Wa

6
70
in3ton

3736

3738

3702

36
1 6 361 4

62

Mt

3782
3770

3732

37
08

3656

50
36

92 3802

388
24
2
39
8
388 4
6
3838
3866 38 3844
383 4
383 2
3830 3816
3806
3804 3800
3790
88
37
3756

64
37

36

32
37

37

3832

3644

3590

37
6
3796 0

6
98 3

88

4
37

02

8
3944 393
2
393
3908

3732

6
366

37

0
375

37
48

3746

377

72
35
64
35
570
3
10
36
4
363 3670
3690
4
368
3716

84

378
8

36

372 8

3862 4
8
38
2 2
389 92
63
392

98
39

3974

94

37

08
38
28
38
72
38

40

3
39 992
66
394 3982
6
3936 3934
391 3962
8 39
3
38 0
96
3902
386
8

3850

94

8
402 4014

0 402
6

3968

3898

4052

3820

76
4
12
37
37
382 0 38
2
0
7
1
2
37
0
38
38
52
378 66
37
37
68
37
48
37

38 38
56 18

395 2

64
40
4054

70
38 852
3

38
391 6
0
395

40
42

402

4076

40
72

30
40

08

399
90
3 9 4 01 2

8
8
06
4
404
80
6
40
4044 405
74
6 6 40
40
409 0
86
4084 40 0 4104
0
41
2 4118
411 6
412

41

06
40 0
8
40
39
39 910 76
8
8
3
4
0 39
6 3
8
7
6
8
0 3
39
39

3724

3
40

3836

62
40

3880

3914

7
40

3958

4114

98
40 88
40

92

4000

40

366 2

36
60 3656
3664

3652

3646

12
36

3620

3618

3622

3616

3620

3630

3658
3662

3622

3644

3626

3678 3676

36 3
54 656

8
366

3674

8
36
5

3654

86
36

3688

3690

3702

3696 3690

3688

3688

3688

3686

36

3688

3684

78

3672

3670

3678

3688

3652

3646

3648

3646
3658

3664

3660

6
363

365 0

3664 3654 3650

36
8

365

3648

3658

3602

3630
3640

3620

14
36

363
2
3 63 0

36
28

3638

42
3654 3652

36

3612

361
0
3612

3616

3616

3608

3612

3616
3624
3626

4
36
3

3636
3634 3636

46
3644

Hw y 9 7

3698
3698

369
2

0
36
3

3600

3610

3624

3618

3624
3626

3618
3622
3622

3622

3628

36

3628

3632

3620

363
2
36
42

365
0

52
36

36
3

3642

3628

3628

3634

24
36
4
360

360
6

361 2

8
3638

362
8
362
8
16
36

20
36

36
24

3640

36
36

36
04

35
8

35
9

35
90

06
36

36
20

34
36

36
40

4
36
3

36
32

3624

3602

3604
3600

20
36

36
1

36
08

0
36
3
360
6
3628

06

36
3

3630

36
1

3596
361

3624

362 8
364
4

3636
3658

22

98
35
96

35
3600

359 6

3632

36

0
36
0
3604

3620

3650

6
359

3616

2
364

2
366

36

36
40
36
38
4
36
5

3672

3676

368
4

36
66

3646
3646

Figure A.6-2
Study Area 6
Proposed Sanitary Sewer Layouts

368 8

86
36
80
36

82
36

3680

8
36

76

3692
3688

74

36
7

80

3674
3676

8 3688
368
3674

3688

367

36
5

0
366
82

36

36
7

76

3686

365
0

66
36

36

3690

3688
3686

3688

36

3656

2 3666

76

3682 36
82

3686
3672

36
68

36

3678

6
36

72

62
36

36

3678

3684

368

3672

36

36

3670
76
36
7
36

6
36

3650

3654

3656

3664

366

4
366

3666

3654
36
58
3648
36
58

74
36

3652

Franklin Road

3640

36
80

3644

3656

3668

44

44
36

40

3620

3620

362 8

368

36

3630

3620

50
36

36
368 98
4

3 66 8

367 4

44
36
365 4 4 2

36

36 0 4

363

3634

72

3666

3638

3622

3608

36
18 3626

36

3648

36

3642

36
74
36
64

3652

50
36

363 6

3606

3634

3676

36

2,000 Feet

3610

3600

362 8

20

h
g

3652
48

36
32

3630

3626

6.18

14
36

3618

3634
Greenwood
Road

363

0
4
366
365
68
6
660 3678 3
3656 3
66
4
3676 36
3656 367
366 0
67 0
368 0 3
0

1,000

5
36

3668

365

3640

6 61
360 3

36

8
361

6.17

3604

22

3638

46
36

46
36

3652

3632 3632 3628

3640

3610 3626
3630

3620 3618

3618

3614
362 2

362 6

3622

366
6

3606
361

360

3610

3610

3628

362
0

h
g

3674

3630

3612

360

22
3622 3612 36

6.20

h
g

364

36

3608

3636

6
3638 365

2
363

6
360

3622

52
36

No Planned Development

54

3640

14
2 4 36

Deschutes River

3604

360 2

3604

Connection Points

School

06

3626

3626

3634

28

36

34

3630

3610

360

3626

36

02
36
3602

02
36

360

3628

36

3626

22
36
6

3602

36

3634

3606

3656
364

6
364

364

363
362
62
8 36
28 8

Parks (No Planned Sewer Expansion)

365 4

8
364
0
3648
48
6
3
2
365 3650 3648

3646

28

Proposed Sewer Projects

Existing Sanitary Sewer Lines

44

3626

2
36

36

63 4

4
360

24

3658 3660

36

365 0

36

3630

363 6

26

32

56
36

0
36

9
35

3638

3638

36

36
3652

36
0

2 640
364 3
3642

3628

26

3642 3642
3644

3638

h
g

3640

360

3648

72
36

369

h
g

36
5

22
36

3 61 0

56

3642

36

28 364
2
36

6.19
363 4

365

36

3640

58

364 6

40
36

3640 3640 36
36
3624
3638
36
06

0
363
3634

3650

2
363 6

3634 3632

3624

36
24
4
2
3626
36
36
26

k k

3630

h
g

h
g

3628

6.16

36
24

3634

36
30

0
363
363

96
35

359

3622

362

36
12

3596

3618
3624

3642

365

35
98

h
g

36
36

35 9

0
36

3610

36

58
36
3672
3666 3668
3680 3682

0
365

94

6.15

3606

18
36

4
359

1
36

8
360
6
0
36

08
36

3608

358 2

3636

9
35

35

0
358

78
35
86
35

h
g
3614

6.14

8
361
3634

36 2
0
36

3584

3640

3600

59 8
35 9 8 3

3616

3620

3704

3644

3590
35
92

363

10
36

3616 3612

3648

3652

3656
8
366

3604

4
360

364 6

36
4

3610
36 1 0

3602

3608

3682
7
36

0
62

3642

04

3612

0
36

3608

366 2
3658

3606
3610

96
35

3646

3610

9
35

357 6

3612

0
36

2
360

3608

3616

6
36

36
8

3604
3606 360
8

3618

3632
0
360

4
3602

3606

366 0
3668
0
367
8
367

3692

4
366

3596

3644 36
42

360

14
36

48
36

14
36

3620

0
36

3658

64
36 674
3
80
36
36
88

7
36

72

3608

3616

3
3648 634

58

36

3608

362 2

3656
36

3 66 6

359 6

363 6

3606

3656

3696

12
36

0
3702 3726
376 48 38
3716 3714
24
3688 3700
7 37
7
96
2
3
0
5
36
373 3
37
3664
3732
36 7 4
6
0
3 7 2 3712
5
36
3718
3698
3632
3706 3708
3686 3676 3666 660
3684
3
365 2
3614
3654 3662 3658
362 8
3630
3606

3770 3774
3756 3762
3740 375
0
3720 3728
3704 3710
3
3668 694

You might also like