SUB-ESTIMATE NO.

:6 :
VERTICAL LIFT GATE WITH HOISTING AND ELECTRIFICATION
Sr. No.

Description of Item

Design, fabrication, supply, erection and


commissioning
of
embedded
parts
consisting of sill beam, wheel tracks, seal
seats, guide rails for both side roller system
etc., with all accessories for vertical lift
barrage gate including cost of all materials,
machinery,
labour,
cutting,
aligning,
anchoring, welding, finishing, cleaning,
applying one coat of zinc rich epoxy primer
and four coats of marine paint etc.,
complete as per specifications and approved
drawings with all leads and lifts.
(As per RA based on IMC-2
Ahmedabad SOR- 2013-14)

Unit

Quantity

Ton

1381

Design, fabrication, supply, erection, testing


and commissioning of fixed wheel type
vertical lift gate consisting of skin plate,
vertical and horizontal girders, wheels
assembly with both side roller system,
stiffeners, lifting brackets, guide shoes,
rubber seals, etc., with all accessories for
barrage
including cost of all materials,
machinery,
labour,
cutting,
aligning,
welding, finishing, cleaning, applying one
coat of zinc rich epoxy primer and three
coats of marine paint, seal fixing, etc.,
complete as per specifications and approved
drawings with all leads and lifts.
(As per RA based on IMC-2
Ahmedabad SOR- 2013-14)

Design, fabrication, supply, erection and


commissioning
of
embedded
parts
consisting of sill beam, slide tracks, seal
seats, guide rails, etc., with all accessories
for spillway stop log gate elements including
cost of all materials, machinery, labour,
cutting,
welding,
aligning,
anchoring,
finishing, cleaning, applying one coat of zinc
rich epoxy primer and four coats of marine
paint, seal fixing, etc., complete as per
specifications and approved drawings with
all leads and lifts. (As per RA based on IMC2 Ahmedabad SOR- 2013-14)

Ton

9468

Ton

782

Design, fabrication, supply, erection, testing


and commissioning of Radial sliding type all
interchangeable (except bottom element)
stop log elements consisting of skin plate,
horizontal and vertical girders, stiffeners,
lifting pins, bronze padded slide blocks,
guide shoes, rubber seals, clamps, dogging
sets etc., with all accessories for spillway
including cost of all materials, machinery,
labour, cutting, aligning, welding, finishing,
cleaning, applying one coat of zinc rich
epoxy primer and three coats of marine
paint, seal fixing, etc., complete as per
specifications and approved drawings with
all leads and lifts.
(As per SOR Item No7.6 P-145 of WRD Karnataka for 2013-14)

Design, fabrication, supply, erection, testing


and commissioning of automatic lifting
beam with all accessories for handling,
lowering and lifting of spillway stop log gate
elements including cost of all materials,
machinery,
labour,
cutting,
aligning,
welding, finishing, cleaning, applying one
coat of zinc rich epoxy primer and three
coats of marine paint etc., complete as per
specifications and drawings with all leads
and lifts. (As per RA based on IMC-2
Ahmedabad SOR- 2013-14)

Ton

998

Ton

10

Design, fabrication, supply,


erection,
testing and
commissioning of adequate
capacity Class-II type moving gantry
crane consisting of rail mounted gantry
frame, top platform with hand railing,
long/ cross travel arrangements, rope
drums, gear systems, electric motors,
electromagnetic brake system, cabin,
control panel, wire rope, ladder, motorised
cable reeling drum etc., with
all
accessories for operating spillway stop log
gate elements and river sluice/ canal sluice
emergency gates
including cost of
all
materials,
machinery,
labour,
cutting, Ton Capacity
bending, aligning, anchoring, welding,
finishing, cleaning, applying two coats of
zinc chromate red oxide primer and three
coats of approved synthetic enamel paint
etc., complete with all leads and lifts.
(Market Rate ) 2013-14

300

Design, fabrication, supply, erection and


commissioning of rail track using 45 kg/m
standard rails on spillway bridge for
movement of gantry crane for handling and
operating spillway stop log gate elements/
river
sluice/ canal sluice emergency gate
including cost of all materials, machinery,
labour,
aligning,
anchoring,
welding,
cleaning etc., complete as
per
specifications and approved drawings with
all leads and lifts.
(As per SOR Item No7.9 P-146 of WRD Karnataka for 2013-14)

Rm

3330

Design, fabrication, supply,


erection,
testing and
commissioning of adequate
capacity hydraulic hoist consisting of rope
drum hoist consisting of hoist platform, rope
drum, pully, gear system, electric motor,
electro magnetic break system, manual
operation assembly, wire rope, position
indicator, control panel, etc., with all
accessories for operating vertical lift roller
gates
for barrage including cost of all
materials, machinery, labour, gates for
barrage including cost of all
materials,
machinery,
labour,
cutting,
bending,
aligning, anchoring, welding, finishing,
cleaning, applying two coats of zinc
chromate red oxide primer and three coats
of approved synthetic enamel paint etc.,
complete with all leads and lifts. (As per RA
based on IMC-2 Ahmedabad SOR- 2013-14)

Ton

14203

10

11

12

13

Design, fabrication, supply, erection and


commissioning
of structural steel hoist
bridge consisting of columns, beams,
bracings, stiffeners, ties, chequered plate
covering, hand railing, ladder etc., with all
other accessories for supporting rope drum
hoist for opening barrage gates including
cost of all materials, machinery, labour,
cutting,
aligning,
anchoring,
welding,
finishing, cleaning, applying two coats of
zinc chromate red oxide primer and three
coats of synthetic enamel paint etc.,
complete with all leads and lifts.
(As per
SOR Item No-7.21P-151 of WRD Karnataka
for 2013-14)

Design
and
providing
electrification
including required capacity, cable wiring and
street/flood light etc. complete. Lump Sump
rate

Providing DG Set 750 HP + 365 HP Capacity


etc.

Providing 11 KVA electrict line with charge,


substation, transformer etc from Navetha to
Bhadbhut Barrage Site Rates
as per
DGVCL, Bharuch
Security Deposit for 11 KVA line at
Bhadbhut Barrage SiteRates as per DGVCL,
Bharuch

Total

Ton

1650

Nos.

90

L.S

L.S

L.S

Rs. In Cro

Deputy Executive Engineer


Project Implementation Unit-2
Vadodara

Executive Engineer
Project Implementation Unit-2
Vadodara

ELECTRIFICATION
Rate

Amount

85500

118075500

117100

1108702800

86700

67799400

110470

110249060

149115

1491150

149715

94380

28314000

145200

94380

169158

5135

17099550

7900

5135

9204

48279

685706637

50820

48279

60730

101840

168036000

50000

107200

101840

4500000

50000

55000

L.S

8500000

8500000

L.S

15913431

15913431 17504774 19255251

L.S

10907158

10907158 11997874 13197661

In Rs.
Rs. In Crore

2345294686
234.60

60500

9350000 10285000

e Engineer
mentation Unit-2

110470 1.355255

SUB-ESTIMATE NO.:6 :
VERTICAL LIFT GATE WITH HOISTING AND ELECTRIFICATION

Item No. :1:

Design, fabrication, supply, erection and commissioning of embedded parts consis


wheel tracks, seal seats, guide rails for both side roller system etc., with all access
barrage gate including cost of all materials, machinery, labour, cutting, aligning,
finishing, cleaning, applying one coat of zinc rich epoxy primer and four coats o
complete as per specifications and approved drawings with all leads and lifts. (
IMC-2 Ahmedabad SOR- 2013-14)

Item

Sr. No.
(a)
(b)
(c)

Upstream
Normal block
Sluice block and navigation lock
fish ladder
Total
Say

Nos
80
10

Weight
(MT)
15.1
17.12

1.82

Item No. :2:

Design, fabrication, supply, erection, testing and commissioning of fixed wheel t


consisting of skin plate, vertical and horizontal girders, wheels assembly with bot
stiffeners, lifting brackets, guide shoes, rubber seals, etc., with all accessories fo
cost of all materials, machinery, labour, cutting, aligning, welding, finishing, cleanin
of zinc rich epoxy primer and three coats of marine paint, seal fixing, etc
specifications and approved drawings with all leads and lifts. (As per RA based o
SOR- 2013-14)

Item

Sr. No.
(a)
(b)
(c)

Upstream
Normal block
Sluice block and navigation lock
fish ladder
Total
Say

Nos

Weight
(MT)

80
10

103.55
116.96

14.5

Item No. :3:

Design, fabrication, supply, erection and commissioning of embedded parts con


slide tracks, seal seats, guide rails, etc., with all accessories for spillway stop
including cost of all materials, machinery, labour, cutting, welding, aligning, a
cleaning, applying one coat of zinc rich epoxy primer and four coats of marine pa
complete as per specifications and approved drawings with all leads and lifts. (As p
2 Ahmedabad SOR- 2013-14)

Item

Nos

Weight
(MT)

80
10

4.29
4.86

4.86

80
10

4.22
4.31

4.31

Sr. No.
(a)
(b)
(c)

Upstream of U/s gate


Upstream
Normal block
Sluice block and navigation lock
fish ladder
Downstream of U/s gate

(a)
(b)
(c)

Upstream
Normal block
Sluice block and navigation lock
fish ladder
Total
Say

Item No. :4:

Design, fabrication, supply, erection, testing and commissioning of Radia


interchangeable (except bottom element) stop log elements consisting of skin p
vertical girders, stiffeners, lifting pins, bronze padded slide blocks, guide shoes, r
dogging sets etc., with all accessories for spillway including cost of all materials
cutting, aligning, welding, finishing, cleaning, applying one coat of zinc rich epo
coats of marine paint, seal fixing, etc., complete as per specifications and approv
leads and lifts. (As per SOR Item No-7.6 P-145 of WRD Karnataka for 2013-14)

Sr. No.
(a)

Item
Upstream of U/s gate
Upstream

Nos

Weight
(MT)

94.94

(b)
(c)

Normal block
Sluice block and navigation lock
fish ladder
Total
Say

107.59

23.19

Item No. :5:

Design, fabrication, supply, erection, testing and commissioning of automatic l


accessories for handling, lowering and lifting of spillway stop log gate elements
materials, machinery, labour, cutting, aligning, welding, finishing, cleaning, apply
rich epoxy primer and three coats of marine paint etc., complete as per specific
with all leads and lifts. (As per RA based on IMC-2 Ahmedabad SOR- 2013-14)

Item

Sr. No.

(a)
(b)

Automatic lifting Beam with all


Accessories
Upstream of U/s gate
Normal and sluice block
navigation lock
Fish ladder

Nos

Weight
(MT)

2
2

3.5
0.8

Total
Say
Item No. :6:

Design, fabrication, supply, erection, testing and commissioning of adequate cap


moving gantry crane consisting of rail mounted gantry frame, top platform
long/ cross travel arrangements, rope drums, gear systems, electric motors, ele
system, cabin,
control panel, wire rope, ladder, motorised cable reeling d
accessories for operating spillway stop log gate elements and river sluice/ can
gates including cost of all materials, machinery, labour, cutting, bending, aligning,
finishing, cleaning, applying two coats of zinc chromate red oxide primer and thre
synthetic enamel paint etc., complete with all leads and lifts. (Market Rate )

Item

Sr. No.

Moving Gantry Crane


Upstream of U/s gate
Say
Item No. :7:

Nos

Weight
(MT)

150

Design, fabrication, supply, erection and commissioning of rail track using 45 kg/
spillway bridge for movement of gantry crane for handling and operating spillw
elements/ river
sluice/ canal sluice emergency gate including cost of all m
labour, aligning, anchoring, welding, cleaning etc., complete as per specifica
drawings with all leads and lifts. (As per SOR Item No-7.9 P-146 of WRD Karnataka

Sr. No.

Item

Nos

Spill Way Bridge

2
Say

Length
(m)
1663

Item No. :8:

Design, fabrication, supply, erection, testing and


commissioning of adequate
hoist consisting of rope drum hoist consisting of hoist platform, rope drum, pully,
motor, electro magnetic break system, manual operation assembly, wire rope
control panel, etc., with all accessories for operating vertical lift roller gates for ba
of all materials, machinery, labour, gates for barrage including cost of all
m
labour, cutting, bending, aligning, anchoring, welding, finishing, cleaning, applyin
chromate red oxide primer and three coats of approved synthetic enamel paint et
leads and lifts. (As per RA based on IMC-2 Ahmedabad SOR- 2013-14)

Sr. No.

Item

(a)
(b)
(c)

Upstream of U/s gate


Upstream
Normal block
Sluice block and navigation lock
fish ladder

Nos

Weight
(MT)

80
10

155.32
175.44

22.97

Total
Say
Item No. :9:

Design, fabrication, supply, erection and commissioning of structural steel hoist


columns, beams, bracings, stiffeners, ties, chequered plate covering, hand railing
all other accessories for supporting rope drum hoist for opening barrage gates inc
materials, machinery, labour, cutting, aligning, anchoring, welding, finishing, cle
coats of zinc chromate red oxide primer and three coats of synthetic enamel pain
all leads and lifts. (As per SOR Item No-7.21P-151 of WRD Karnataka for 2013-14)

Sr. No.

Item
Structural
steel
Hoist
Upstream of U/s gate

(a)
(b)

Nos

Weight
(MT)

91
1

18
7.5

Bridge

Normal and sluice block navigation


lock
Fish ladder
Total
Say

Item No. :10:


Design and providing electrification including required capacity, cable wiring and s
complete. Lump Sump rate
Sr. No.

Item
electrification including
capacity DG set

Nos
required
90
Say

Item No. :11:


Providing DG Set 750 HP + 365 HP Capacity etc.
Item
Sr. No.

Nos
1

Say
Item No. :12:

Providing 11 KVA electrict line with charge, substation, transformer etc from Naveth
Barrage Site Rates as per DGVCL, Bharuch
Sr. No.

Item

Nos
1

Say
Item No. :13:

Security Deposit for 11 KVA line at Bhadbhut Barrage SiteRates as per DGVCL, Bha
Sr. No.

Item

Nos
1
Say

Refered Drawing No. 3.1,3.2,3.3,3.7,3.11,3.12

Estimate prepared by: Sh. P.S.Bathawar A.E.

ECTRIFICATION

edded parts consisting of sill beam,


etc., with all accessories for vertical lift
, cutting, aligning, anchoring, welding,
er and four coats of marine paint etc.,
ll leads and lifts. (As per RA based on

Quantity
(MT)
1208
171.2

1.82
1381.02
1381

ng of fixed wheel type vertical lift gate


assembly with both side roller system,
h all accessories for barrage including
g, finishing, cleaning, applying one coat
t, seal fixing, etc., complete as per
As per RA based on IMC-2 Ahmedabad

Quantity
(MT)
8284
1169.6

14.5
9468.1
9468

mbedded parts consisting of sill beam,


s for spillway stop log gate elements
welding, aligning, anchoring, finishing,
coats of marine paint, seal fixing, etc.,
ads and lifts. (As per RA based on IMC-

Quantity
(MT)
343.2
48.6

4.86

337.6
43.1

4.31
781.67
782

ssioning of Radial sliding type all


onsisting of skin plate, horizontal and
cks, guide shoes, rubber seals, clamps,
ost of all materials, machinery, labour,
at of zinc rich epoxy primer and three
cations and approved drawings with all
ka for 2013-14)

Quantity
(MT)
759.52

215.18

23.19
997.89
998

ing of automatic lifting beam with all


log gate elements including cost of all
ng, cleaning, applying one coat of zinc
ete as per specifications and drawings
SOR- 2013-14)

Quantity
(MT)

7
1.6
8.6
10

ng of adequate capacity Class-II type


ame, top platform with hand railing,
electric motors, electromagnetic brake
d cable reeling drum etc., with all
nd river sluice/ canal sluice emergency
, bending, aligning, anchoring, welding,
ide primer and three coats of approved
arket Rate )

Quantity
(MT)
300
300

track using 45 kg/m standard rails on


nd operating spillway stop log gate
ng cost of all materials, machinery,
as per specifications and approved
6 of WRD Karnataka for 2013-14)

Quantity
(Rmt)
3326
3330

oning of adequate capacity hydraulic


rope drum, pully, gear system, electric
sembly, wire rope, position indicator,
roller gates for barrage including cost
ng cost of all
materials, machinery,
g, cleaning, applying two coats of zinc
etic enamel paint etc., complete with all
13-14)

Quantity
(MT)
12425.6
1754.4

22.97
14202.97
14203

tructural steel hoist bridge consisting of


vering, hand railing, ladder etc., with
barrage gates including cost of all
ding, finishing, cleaning, applying two
nthetic enamel paint etc., complete with
ataka for 2013-14)

Quantity
(MT)

1638
7.50
1645.5
1650

cable wiring and street/flood light etc.


Quantity
(Nos)

90
90

Quantity
(Nos)
1
1

mer etc from Navetha to Bhadbhut


Quantity
(Nos)
1
1

as per DGVCL, Bharuch


Quantity
(Nos)
1
1

SUB-ESTIMATE NO.: 13 :
LEFT BANK FLOOD PROTECTION EMBANKMENT WIT
Sr. No.

Description of Item

Unit

Clearing the seat of earthen dam including seat of spillway


and HR including removing the trees, shrubs bushes etc
and depositing the materials outside the seat of dam
beyond 50mt from the toe line and unto 200mt lead as
directed (SIPC-SOR year 2013-14, Chapt-1 ED I-2)

ha

Stripping the seat of dam in all sorts of soils including soft


murrum and hard murrum, and including depositing the
materials as & where directed for dam seat & inspection
road etc with lead upto 1.0km and all lifts etc complete
(SIPC-SOR 2013-14,Chapt-1 ED I-3)

Excavation in all sort of strata and formations incl.


depositing the unuseful excavated stuff as and where
directed incl sorting and stacking useful materials in
measurable conditions as directed upto 200mt lead and all
lift etc. complete incl. dewatering. (A)In overburden incl.
hard murrum.
(SIPC-SOR year 2013-14, Chapt-1 ED I-4A)

Quaring, transporting & spreading selected materials from


borrow area for raising of embankment work in
homogenous section in uniform layers of specified
thickness as directed incl dressing breaking clods and
rolling at requisite moisture contents to required dry
density with roller of suitable type and watering at OMC for
lead upto 1.0 km and all lifts etc complete.
(SIPC-SOR
2013-14, Chapt-1 ED I-6,P-2)

Cum

Cum

Cum

4a

Extra lead charges for transporting the borrow area


materials for earthen dam beyond the basic lead of 1.0 Km
upto 5.0 Km for each additional Km or part there of
inclusive of all lift etc complete. (For 4 km: 4 x 15.40 = Rs.
63.60)
(SIPC-SOR 2013-14, Km/ Cum
Chapt-1 ED I-9)P-2

Providing and laying dry rubble stone pitching without base


of inverted filter and header stone but with 10 cms thick
murrum layer including hand packing & trimming &
dressing slopes etc complete 30 cms thick stone pitching
with pointing CM 1:2 (SIPC-SOR 2013-14, Chapt-1 ED I-17
(c)P-3)

Quarring,transporting and laying rock fill for ROCK TOE


using hard stone in layers directed including graded
filter,necessary hand packing of stones for adjusting sides
to correct design slopes etc using light hammer driven
wedges between rubble on exposed face for lead upto 1.0
km and all lifts etc comp. (SIPC-SOR year 2013-14, Chapt1 ED I-25, P-4)

Supplying and laying Mechanically woven double twisted


Hexagonal Zn + PVC Coated box wire mesh sebin 1 m x
1m x 1m filled with 10+40 kg trap rubble stone (approx. to
5t) interleveling of simes and fusing top gabian of tying to
each other laying to the lime, level slock with all loads lists
as directed etc. compl. (Considening lead of 75 km for
rubble material) As per RA Rate 2718/-

Sqm

Cum

No

10

11

Providing and laying geo-fabric filter (GWF-40-200


category) over the excavated surface as per specification
including stitching with overlap to design profile as directed
in tidal range etc. complete.
(On slopping surface of embankment berm and slopping
surface of bank)
(SIC-SOR South Zone 2013-14, Chap.6 I-1)

Cross drainage on embankment side slope and longitudinal


catch water drain along the embankment toe etc complete
For 24.051Km.x 2 sides =48.102 Km. Rate Rs.2.0 Lac/Km

Inverted choke (Construction of inverted choke filter by


providing laying, spreading B-type coarse sand of specified
grade in uniform layers on a prepared surface with motor
grader and compacting with power roller etc (SOR-NHC2013-14, I-4.8, P-22)

Construction of granular sub base with coarse graded


material, spreading in uniform layers with motor grader on
prepared surface mixing by mix in place method with
rotavator at OMC and compacting with vibratory roller to
achieve the desired density, etc complete
SOR-NHC-2013-14, I-4.2 (ii) P-20(2012-13, 633/cum. enhanced by 10%)

Sqm

Rmt

cum

cum

12

13

14

Providing, laying, spreading and compacting graded stone


aggregate to wet mix macadam specification including
premixing the material with water at OMC in mechanical
mix plant carriage of mixed material by tipper to site laying
in uniform layers with paver in sub base/base course on
well prepared surface and compacting with vibratory roller
to achieve the desired density (SOR-NHC-2013-14 I- 4.12 P
24)(2012-13, Rs. 715/-/cum)

Providing and applying primer coat with bitumen emulsion


on prepared surface of granular base including cleaning of
road surface and spraying primer at the rate of 0.6 kg/sq.
m using mechanical means.(SOR-NHC I-5.1, P-27, 201314)(2012-13, Rs. 18/-/sq.m)

Providing & laying Dense graded bituminous macadam in


two layers with 100-120 TPH batch type HMP producing an
average output of 75 tones per hour/DMP 60-90 THP
capacity 80-100 capacity using crushed aggregate of
specified grading premixed with bituminous binder @ 4.5
% by weight of total mix and filler, transporting the hot mix
to work site laying with hydrostatic paver finisher with
sensor control to the required grade, level and alignment,
rolling with smooth wheeled vibratory and tandam roller to
achieve the desired compaction as per MORTH specification
clause No. 507 complete in all respect.(SOR-NHC I-5.6A ii,
P-28-2013-14)(2012-13, Rs. 5503/- cum)

cum

sqm

cum

15

16

17

18

Providing & laying Bituminous concrete with 100-120 TPH


batch type hot mix plant producing an average output of 75
tons per hour/DMP 60-90 TPH capacity 80-100 capacity
using crushed aggregate of specified grading, premixed
with bituminous binders @ 5% of mix and filler transporting
the hot mix to work site, laying with hydrostatic paver
finisher with sensor control to the required grade, level,
and alignment, rolling with smooth wheeled, vibratory and
tandem rollers to achieve the desired compaction as per
MORTH specification clause 509 (grading -1) complete in all
respect (SOR-R&B-NHC I-5.8 I, P 31, 2013-14)(2012-13,
Rs. 6768/cum)

Road marking with hot applied thermoplast compound


reflecting glass bends on bitumenious surface. Providing
and laying Hot applied thermoplastic compound 2.5 CM
thick including reflectorising glass bends @ 250 gms/sq.mt.
Area, thickness of surface applied glass bends as per IRC
35 the finished surface to be level uniform and free from
streaks and holes. (SOR-R&B Zone II-2013-14 Item 93A
Pg 105)

Providing and Fixing Guard stone as per IRC type design


including white washing etc complete including fixing in
1:5:10 c.c (13007/4 x 2sides) (SOR-R&B-Zone II, I-45, P99-2013-14)

Providing and Fixing Ordinary Kilometer Stone of precast


CC 1:2:4 (kilometer stones of standard design as per IRC:
8-1980,
fixing
in
position)
including
necessary
reinforcement as per IRC type design in cc 1:4:8 including
letters and paints etc. complete.(SOR-R&B-Zone II, I-48, P99, 2013-14)

cum

sqm

No.

No.

19

20

Providing and Fixing 5th Kilometer stone of precast CC


1:2:4 including necessary reinformcement as per IRC type
design in CC 1:4:8 including painting, lettering etc.
complete.( SOR-R&B-Zone II, I-50, P-99, 2013-14)

Miscellaneous items viz. direction signboards, Kerb,


guard, metalbeam, crash barrer, delineators, side drains
near toe of embankment etc. 10% of total cost of items 1
to 10

No.

Lumpsum

Total
Say

Deputy Executive Engineer


Project Implementation Unit-2
Vadodara

Executive E
Project Implemen

STIMATE NO.: 13 :
TION EMBANKMENT WITH ROAD AT TOP
Quantity

Rate

Amount

295

3403

1003885

528532

41

21669812

192408

48

9235584

7691327

69

530701563

7691327

64

492244928

430504

263

113222552

42089

484

20371076

1524213

2718

4142810934

1043193

78

81369054

48102

200

9620400

432920

404

174899680

144306

697

100581282

180383

787

721530

20

122660

6053

141961421

14430600

742460980

36077

7445

268593265

19241

480

9235680

12000

322

3864000

24

1159

27816

2203

11015

446008657

Rs.
Rs. In Crore

Executive Engineer
Project Implementation Unit-2
Vadodara

7324324184
732.50