DATA CENTER IMPLEMENTATION ROADMAP

System / Application Layer

AODBS

RMS

EVIDS

BRS

CUSS

I2BS

CPGS

PRCS

Installing BRS Platform, Applications & Services

Installing CUS Platform, Applications & Services

Install SQL with Clustering

Installation of Cirpark Scada / Test Park Applications

Installation of Lince Parking Management / APNR Applications

Install SACS application on servers

EPGS

Add field equipments and configure it in

Add field equipments and configure it in Lince Application

Assign Address for Field Equipments space

Create tariff for payments and items/groups for employee access

Configure dynamic displays counting

Configure intercom subscriber units

Configure system reports

Configure credit card payment mode and System reports

Integrate with AODB / Master

Integrate with AODB / Master

Integration with DB
Installing AODB Platform, Applications & Services

Installing RMS Platform, Applications & Services

Installing EVIDS Platform, Applications & Services


Installing and Configuring Airlines Applications for BRS

Installing and Configuring Airlines Applications for CUS

Add field equipments & configure other features into app servers

MCS

IPTV

Delivery of Servers

Delivery of Servers

Delivery of servers

Equipments assembly & Delivery of Servers

Delivery of servers

Delivery of Servers

HP DL 380P QTY. 2

Servers Qty. 4

Server Installation

Server Installation / Credit card gate way

Installion Windows Application Server on virtual

Server Installation

Server Installation

Server Installation

Server Installation

Server Installation

Server Installation

Server Installation

Installation in Racks

CPGS Servers configuration (OS, Scripts etc)

PRCS / ANPR Servers / CC Workstation

Basic Installation server installation

IPTV Servers configuration (OS, Scriptsetc)

MCS Servers configuration (OS, Scriptsetc)

AODB Servers configuration (OS, Scripts ..etc)

RMS Servers configuration (OS, Scripts ..etc)

EVIDS Servers configuration (OS, Scripts ..etc)

BRS Servers configuration (OS, Scripts ..etc)

CUS Servers configuration (OS, Scripts ..etc)

Connection to Power and LAN

Configure RMS Servers on KAIA Network

Configure EVIDS Servers on KAIA Network

Configure BRS Servers on KAIA Network

Configure CUS Servers on KAIA Network

Cisco UCS 5108 Blade Server ANPB Servers


QTY. 2

Cisco UCS 5108 Blade Server EPGS Server QTY. 2

ANEVIA Servers QTY. 2

Configure IPTV Servers on KAIA network

Configure PRCS AND ANPR Servers / CC Workstation on KAIA network

Integrate with FAS

Integrate with FAS

Integrate with VSS

Integrate with I2BS

SMA 3000 Servers QTY. 2

Installation in racks

Installation in racks

Installation in racks

Connection to Power

SACS

Server Configuration

Install OS

Install OS

Configure PA Zones and do Zone Mapping

Configure SAN

WAV files Stored Locally on Virtual Server as history of LOGS

Configure MCS Servers on KAIA network

Install OS

Storage
Layer

Installing Routing Server

Configure SAN and assign LUNs


Configure AODB Servers on KAIA SAN storage

Configure RMS Servers on KAIA SAN storage

Configure EVIDS Servers on KAIA SAN storage

Configure BRS Servers on KAIA SAN storage

Configure CUS Servers on KAIA SAN storage

Configure SAN

Configure CPGS Servers on KAIA SAN Storage

Configure PRCS and ANPR Servers on KAIA SAN storage

Configuring Switches

Configuring Switches

Configure EPGS Servers on KAIA SAN storage

Configure IPTV Servers on KAIA SAN network

Configure MCS Servers on KAIA SAN network

Management LAN Configuration ( VLAN & Interface)

Equipments Assembly

Equipments Assembly

Cisco MDS 9710 QTY. 2

Delivery of Firewalls QTY. 2 and Switches Qty. 4

Network

Delivery of servers
Cisco UCS 5108 Blade Server Chassis 2

Installing InfoGate Admin Clients (Core AdminClient, IGMS Admin,


UltraVNC server
Configure CPGS Servers on KAIA network

Configure AODB Servers on KAIA Network

Cisco UCS 5108 Blade Server PRCS


Servers QTY.2

Install Prayer Application on Blade Server 2

Add field equipments & configure other features into app servers

Integrate with IVAS


Integrate with SACS
Equipments Assembly

HP DL 380P QTY. 2

HP DL 320e QTY. 2

Install Duran intellivox WINCONTROLL application on blade server


1

Add field equipments & configure other features into app servers

Delivery of servers

Delivery of Servers

Cisco UCS 5108 Blade Server CPGS Servers QTY. 2

Computer Layer

Delivery of servers

HP DL 380P QTY. 2

HP DL 380p QTY. 5

Install Simplevox Application on Virtual Server


Integration with DB

Installing MCS Platform, Applications & Services

Delivery of Servers

HP DL 320e QTY. 2

PAS

Install BIAMP-VOCIA Application on Virtual Server

Integration with DB
Installing IPTV Platform, Application & Services

Integrate with FAS

HP DL 380p QTY. 5

SACS

Install SQL with clustering

Install VMS application on servers

Installing EPGS Platform, InfoGate-WCF-Service & InfoGate


Maintenance System - IGMS

Integrate with VSS

Delivery of servers

VMS - VSS

Install SQL with clustering

APH - WAN Readiness

APH - WAN Readiness

Configuring SITA firewalls and switches

APH - WAN Readiness

Configuring SITA firewalls and switches

Equipments assembly

APH - WAN Readiness, Airlines WAN Connectivity for BRS

Configuring SITA firewalls and switches

APH - WAN Readiness, Airlines WAN Connectivity for CUS

Configuring SITA firewalls and switches

Configuring SITA firewalls and switches

Establish communication to Field Equipment

Equipment Assembly

Establish communication to Field Equipment

Installation VMWare physical hosts in data centers

Installion in racks

Installion in racks

Configuring switches & Establish communication

Connection to Power and LAN

Connection to Power and LAN

Connection to LAN

Connection to LAN

Installation of racks

Installation in Racks
Connect to Power and LAN

Connection to Power and LAN

Equipment and Material Delivery

Physical Installation

Configuration

SAN Storage Components & Accessories (TIER 1 and TIER 3)


Perform Common / Initial Storage Volume Management, Partitioning, Formatting, etc. Activitites

Storage Layer ( Common )

Component Pre-Installation Assembly


VNX 8000 QTY. 6 Racks

Physical fitting into the racks / Assembling the storage racks

Set Up Security and Access Control Permissions

MDS SAN Switch ( Fiber Interconnect, MDS)

Perform Redundant Power Connectivity


Fiber Interconnect UCS 6248 QTY. 4

MDS 9710 QTY. 4


Set Up Back-Up Policies ad Archiving Retention Policies

Blade Chassis Server (All Systems)


Perform Redundant Fiber Connectivity
Cisco UCS 5108 Qty. 10

Physical Installation

Materials Delivery

Active Network Components (Common)

Cisco 6500 (C6513-E) QTY: 4

Component pre-installation assembly


MPLS configuration "P & PE" (Routing Protocols)

Distribution Layer (Cisco 6500 & Nexus 7K)


Cisco 6500 (C6513-E) Qty: 6

Nexus 7K Qty:10
Access Layer (Cisco 3850 & Nexus 5K

Physical fitting into the racks

Cisco 3850 Qty: 20

Nexus 5K Qty:10
MPLS configuration "P & PE" (VRF's) MPLS configuration "CE" (VLAN ID's)
Security Layer (Firewalls & IPS, Web Security Proxy)

Firewalls & IPS Qty: 4

Web Security Proxy Qty: 4

Perform Redundant Power Connectivity

WAN Layer (Routers & Router Reflector)


Routers Qty: 8

Router Reflector Qty: 4


Security configuration " Access Lists, VPN connection"
Service Layer (Load Balancer, NMS, DHCP, DNS & Active Directory)

Load Balancer Qty: 8

Passive Cabling / Containment (Common)

Configuration

Core Layer (Cisco 6500)

NMS Qty: 2

Network Management Service "Monitoring"

Internet Connection configuration

Services "DHCP, DNS & Active Directory"

Perform Redundant Fiber Connectivity

Blade Chassis Qty: 2

DHCP, DNS & Active Directory

Design

Material Supply and Delivery

realignment of fibre patching and connectivity infrastructure

Cable and Cable Accessories Delivery

Cabling

Perform Patching
Accommodate space for the Copper connectivity infrastructure (if needed in the future)

Power Strips (PDU)

Cable Management

Physical Fitting to the Racks

Cable Management System component/material delivery

Connection to ground Commando Sockets

Physical Fitting

Cable Pulling, Management and Termination

Power Strips (PDUs)


Build Patch Cabinet PoC

Updated Single Line Diagram for the Fiber Cabling

Build Network Cabinet PoC


Patch Panels & Patch Cables
Build Server Cabinet PoC

Updated Network Design with latest Diagram


Simulate Cable Density of MoR using 2 x EoR Cabinets in KAIA Staging Data Center & Test Lab

Convert cable runner MoR setup in KAIA Staging Data Center & Test Lab / DC2 to EoR

Identify solutions options (e.g. Fiber / Microwave) for connecting the KAIA Staging Data Center & Test Lab to the KAIA PTB
Pulling Fiber Cabling (single mode)
Rack Accessories

Verify feasibility of moving the cabinets if needed with Nayeem (for passive cabling and power under raised floor )

Structural

MRF for the (Fiber / Microwave) connectivity between the KAIA Staging Data Center & Test Lab and KAIA PTB

Electrical
Revised Electric / Power Design for the KAIA Staging Data Center & Test Lab Facility

Cover holes/ dust-proofing


- UPS installation and operation and resolving current issue with UPS

HVAC & CRAC

Access Control

Fire Alarm & Fire Fighting

Mitigate risk of dripping water over the servers AC units or AC Air conduits, ducts, etc. \ Suggested option is to install a roof on top of each row of Racks to
maintain air flow

Decide on access path for Personnel into and out of the Facility

- Install and configure Fire Alarm and Fire Fighting (Co2 based) equipment

Facility Maintenance

Pest Control

Facility Readiness

Electrical Surge Protection and Failover Setup


Seal door thresholds (saddles) for air locking and dust proofing

Calculate cooling capacity for full density rack elevation for DC1, DC2, and 2 x MCRs

Policies (No Food or Drinks inside KAIA Staging Data Center & Test Lab, Facility Usage, Access Control, Incident management protocols, etc.)

Fix issues with Main Electrical Power Feed Cords behind UPS and FDR (below concrete floor level)
Generator supply and installation
Seal windows for air locking and dust proofing

Install and Configure Access Control to Authorized Personnel only


Identify Cooling solution and budget and design a phased approach for implementation

Pest Control Contract to be finalized with comments raised by KAIA Staging Data Center & Test Lab Facility

Reach a resolution to the PDU issue or find an alternate supplier for the KAIA Staging Data Center & Test Lab purpose
Identify required PDU quantities for the KAIA Staging Data Center & Test Lab facility
Install 4 x air curtains on top rails of entrance/exit doors and rolling doors

Contract to be signed by Service Provider and ICAD

- Implement solution for cooling equipment when full density racks is reached or right before A/C unit cooling capacity is reached
Identify supplier for PDUs

Reverse Installation of the door for proper magnetic lock position

Civil works for Dedicated Power Generator

Issue MRF for PDUs

Find out the estimated pricing for an adequate data center grade solution (e.g. CRACs of InRow Cooling)

Inspect KAIA Staging Data Center & Test Lab with Hassan Dajani's team to walk them through the new layout and map to the facility layout for further clarify

Issue MRF for electrical components

Perform Thermal Load calculations to evaluate the feasibility of using the A/C Units available for cooling the IT Equipment

Train 2 - 3 Fire Marshalls who are residents of this facility

Identify and select a free (or low cost) DCIM software solution

Fix and Power SACS components to the main entrance door of the KAIA Staging Data Center & Test Lab
Allocate a web server for the selected DCIM solution