Professional Documents
Culture Documents
AODBS
RMS
EVIDS
BRS
CUSS
I2BS
CPGS
PRCS
EPGS
Integration with DB
Installing AODB Platform, Applications & Services
Add field equipments & configure other features into app servers
MCS
IPTV
Delivery of Servers
Delivery of Servers
Delivery of servers
Delivery of servers
Delivery of Servers
HP DL 380P QTY. 2
Servers Qty. 4
Server Installation
Server Installation
Server Installation
Server Installation
Server Installation
Server Installation
Server Installation
Server Installation
Installation in Racks
Installation in racks
Installation in racks
Installation in racks
Connection to Power
SACS
Server Configuration
Install OS
Install OS
Configure SAN
Install OS
Storage
Layer
Configure SAN
Configuring Switches
Configuring Switches
Equipments Assembly
Equipments Assembly
Network
Delivery of servers
Cisco UCS 5108 Blade Server Chassis 2
Add field equipments & configure other features into app servers
HP DL 380P QTY. 2
HP DL 320e QTY. 2
Add field equipments & configure other features into app servers
Delivery of servers
Delivery of Servers
Computer Layer
Delivery of servers
HP DL 380P QTY. 2
HP DL 380p QTY. 5
Delivery of Servers
HP DL 320e QTY. 2
PAS
Integration with DB
Installing IPTV Platform, Application & Services
HP DL 380p QTY. 5
SACS
Delivery of servers
VMS - VSS
Equipments assembly
Equipment Assembly
Installion in racks
Installion in racks
Connection to LAN
Connection to LAN
Installation of racks
Installation in Racks
Connect to Power and LAN
Physical Installation
Configuration
Physical Installation
Materials Delivery
Nexus 7K Qty:10
Access Layer (Cisco 3850 & Nexus 5K
Nexus 5K Qty:10
MPLS configuration "P & PE" (VRF's) MPLS configuration "CE" (VLAN ID's)
Security Layer (Firewalls & IPS, Web Security Proxy)
Configuration
NMS Qty: 2
Design
Cabling
Perform Patching
Accommodate space for the Copper connectivity infrastructure (if needed in the future)
Cable Management
Physical Fitting
Convert cable runner MoR setup in KAIA Staging Data Center & Test Lab / DC2 to EoR
Identify solutions options (e.g. Fiber / Microwave) for connecting the KAIA Staging Data Center & Test Lab to the KAIA PTB
Pulling Fiber Cabling (single mode)
Rack Accessories
Verify feasibility of moving the cabinets if needed with Nayeem (for passive cabling and power under raised floor )
Structural
MRF for the (Fiber / Microwave) connectivity between the KAIA Staging Data Center & Test Lab and KAIA PTB
Electrical
Revised Electric / Power Design for the KAIA Staging Data Center & Test Lab Facility
Access Control
Mitigate risk of dripping water over the servers AC units or AC Air conduits, ducts, etc. \ Suggested option is to install a roof on top of each row of Racks to
maintain air flow
Decide on access path for Personnel into and out of the Facility
- Install and configure Fire Alarm and Fire Fighting (Co2 based) equipment
Facility Maintenance
Pest Control
Facility Readiness
Calculate cooling capacity for full density rack elevation for DC1, DC2, and 2 x MCRs
Policies (No Food or Drinks inside KAIA Staging Data Center & Test Lab, Facility Usage, Access Control, Incident management protocols, etc.)
Fix issues with Main Electrical Power Feed Cords behind UPS and FDR (below concrete floor level)
Generator supply and installation
Seal windows for air locking and dust proofing
Pest Control Contract to be finalized with comments raised by KAIA Staging Data Center & Test Lab Facility
Reach a resolution to the PDU issue or find an alternate supplier for the KAIA Staging Data Center & Test Lab purpose
Identify required PDU quantities for the KAIA Staging Data Center & Test Lab facility
Install 4 x air curtains on top rails of entrance/exit doors and rolling doors
- Implement solution for cooling equipment when full density racks is reached or right before A/C unit cooling capacity is reached
Identify supplier for PDUs
Find out the estimated pricing for an adequate data center grade solution (e.g. CRACs of InRow Cooling)
Inspect KAIA Staging Data Center & Test Lab with Hassan Dajani's team to walk them through the new layout and map to the facility layout for further clarify
Perform Thermal Load calculations to evaluate the feasibility of using the A/C Units available for cooling the IT Equipment
Identify and select a free (or low cost) DCIM software solution
Fix and Power SACS components to the main entrance door of the KAIA Staging Data Center & Test Lab
Allocate a web server for the selected DCIM solution