Professional Documents
Culture Documents
International Journal of Project Management Vol. 14, No. 2, pp. 103-110, 1996
Copyright 1996 Elsevier Science Ltd and IPMA
Printed in Great Britain. All rights reserved
0263-7863/96 $15.00 + 0.00
0263-7863(95)00067-4
This paper illustrates the dangers of trying to implement high technology projects, without
sufficient technical research and development, adequate management organisation and due
regard to social factors. The London Ambulance Service is the largest in the world. During the
early 1990s, it attempted to introduce a computer-aided despatch system. This system was
finally commissioned in October 1992, about 9 months late and failed within 2 weeks. This case
study traces the history of the project and identifies the flaws that led to its failure. Copyright
Elsevier Science Ltd and IPMA
Keywords:hightechnologyprojects, LondonAmbulanceService, computer-aideddespatch, cultural change, business process
re-engineering, information technology
*Entrant for the Sir Monty Finniston Award 1995 sponsored by IBM
Performance requirements
The nationally recognised standards of performance for
ambulance services issued by the Operational Research
Consultancy (ORCON) call for the time taken from receipt
of an emergency call to the issue of instructions to an
ambulance station or crew to be no more than 3 min. An
ambulance is required to arrive at the scene within 14 rain.
This is an onerous requirement that could not be met by
LAS with its existing manual system o f activating the
Numbers
Ratio %
1400
560
200
115
100
100
115
54
22
8
4
4
4
4
was
LAS
trying
to achieve?
What
Number
Ratio %
305
445
2
4
9
8
2
39
57
999
H
Call
Received
,.~
~oou,~e,o
Mobilise H
Determined
__
FomaMoved N
to Resource
Despatcher
Call
Recorded
onForm
~o~ov,~
toResource H
Allocator
Detemlines
ifResource
isMobile
Reference
Added
toCentral
Point
DCalls
upcilate~
Resource H
Allocator
Determined
Eliminated
FormMoved H
to Radio
Operator
Resource
Despatched
byRadio
Resource I
Despatched
by Telephone
Figure 1 Operation of the manual system
giving the status and location of their resources. This
information is provided continuously by a radio operator.
The allocator examines the forms for his/her own area and
decides which resource should be mobilised. He/she notes
this on the form and then passes it to a despatcher who then
telephones the relevant ambulance station or passes mobilisation instructions to the radio operator if the ambulance
is already mobile. There are some obvious problems with
a totally manual system:
At times a caller gives incomplete or inaccurate details;
the identification of the precise location can be difficult
and a number of alternatives have to be explored in the
book of maps.
The physical movement of paper forms around the
control room is inefficient.
Maintaining up-to-date vehicle status and location data is
slow and laborious, relying on allocators' intuition and
reports from ambulances as relayed through the radio
operators.
Voice communication with ambulances is time consuming, leading to mobilisation queues at peak times.
Identification of duplicate calls is prone to error relying
on human judgement and memory.
Call-backs are not handled efficiently, with call administrators leaving their posts to talk to allocators.
The identification of special incidents requiring a rapid
response unit, a major incident team or a helicopter,
relies totally on human judgement.
However, there are situations where human brain power
is superior to computer logic. These are where the human
operator knows other unrelated information (such as the
existence of a local football match or a major road works)
and can apply it effectively to the current situation. The
Datatrak
]
AutomaticVehicle
Location
Mo ech I--
Radio ~ " - p ~ l
Network I I
Sites
(5 ofO
Station
Printers
Public
Telephone
Network
Automatic
I D' trib tr I
Servers I
Radio
Interface
System
Call
Taker
Emergency
Call
Time scale
The LAS was under significant pressure from all directions
to achieve a rapid improvement in their service. Accordingly, the target programme dictated by their senior
management was as shown in Table 3. With this short time
scale it was inevitable that the programmes for policy
making, planning and implementation would overlap. We
shall review how this programme evolved in the next
section.
Table 3
Milestone
Date
February 1991
July 1991
8 January 1992
Invitations to participate were given to union representatives but there was little involvement from ambulance
crews as there were problems with the staff consultation
process at the time. The contract analyst did most of the
work with direct assistance from the systems manager.
As part of the development of the system requirements
specification a companion paper containing a revised operational method of working was produced. This was aimed at
both the Central Ambulance Control staff and ambulance
crews but although it would impact seriously on the way
they worked there was little consultation with the latter.
A small sub-team consisting of the contract analyst and
the systems manager was set up to handle the contract
placement with additional help from a supplies manager
from regional recruitment. The prime responsibility for the
technical evaluation of the tenders fell on the contract
analyst and the systems manager. The experience of the
representative from regional supplies was in procurement
in its most general sense rather than specific IT procurement. The systems manager was a career ambulance man
who had taken over responsibility for LAS systems and
communications some years before. Thus, a contractor and
a systems manager (who incidentally, was arguably unsuitably qualified and knew that he was to be replaced and
made redundant) were put in charge of the procurement of
an extremely complex and high-risk computer system.
An audit of the selection process was carried out by the
systems manager of the Scottish Ambulance Service. The
technical aspects of the tenders should have been adequately covered, however there was no one with specific
project management or contract management experience involved in the process. This gave rise to serious deficiencies:
Choice of a small IT contractor to manage a major
programme.
Acceptance of a programme which proved unachievable.
Lack of definition of contractors' responsibilities.
Acceptance of a contract price which, although close to
the available budget, was unrealistic in comparison with
the other quotations.
When the project moved into the development stage, the
project team was changed to:
administrator. Other departments appear to be well represented but in the face of the major deficiencies inherent
in the technical solution, they were powerless to prevent the
problems soon to be revealed.
The computer-aided despatch system and its software
development were to be carried out using the PRINCE
project management methodology. No clarification was
made as to how this was to be applied and there were no
personnel in the LAS team experienced in its application.
A short training course was carried out but this proved to
be insufficient and the disciplines of PRINCE were not
adhered to or enforced.
Throughout the contractor selection process, there had
been ambiguity over the managerial role of the contractor.
LAS had intended that the contractor's associate in the
consortium, a large hardware manufacturer, would take the
role of prime contractor and lead the project. In the event,
the contract was placed with a small software house who
subcontracted the hardware back to the other party. The
contractor was therefore not prepared or set up to execute
a prime contractor role and rapidly withdrew from activities of this nature. Responsibility for the overall coordination therefore reverted to the Director of Support
Services who found himself spending more and more of his
own time doing low level co-ordination and progress
chasing. He had no middle management level personnel to
do this for him. The Director of Support Services found his
time increasingly under pressure as he had to carry out his
normal duties as well as managing the project. With a more
experienced professional project manager, many of the
problems would have been identified earlier.
Technical development
Work on the preparation of the system's requirements
specification (SRS) went ahead in 1990 against a background
of the recent abandonment of a previous computer-aided
despatch system dating from the 1980s which could not
technically handle the demands placed on it. It was an
ambitious document, the functionality of the proposed
system being greater than that available from any existing
system. There was no evidence of any formal sign-off of the
SRS. Other ambulance services do have systems support,
but none of them could meet the LAS requirement. They
were therefore discounted.
The SRS was very detailed and contained a high degree
of precision on how the system was intended to operate,
being quite prescriptive, reflecting the culture of the
organisation and providing little scope for additional ideas
to be incorporated from prospective suppliers. However, as
is normal in any SRS, there were areas not fully defined;
notably details on the relationship and interfaces to other
LAS systems such as:
Radio interface system
Communication system
Patient transport system
The full systems design specification (SDS) was prepared
by the contractor during June and July 1991.
The computer hardware was considered to be very
powerful and generally resilient. The LAS network was not
large in comparison with those of other organisations. The
workstations were 486-based, running at 25 MHz using a
Microsoft Windows environment that allowed an attractive
and friendly graphical user interface and simultaneous
107
The programme
It is clear that neither the computer-aided despatch team,
the users nor the hardware were ready for commissioning
of the system on the due date of 8 January 1992 or on the
revised date for full implementation of 26 October 1992.
Significant facts, dates and activities were as follows:
(a) Work on a previous system that had been on-going
since the early 1980s was abandoned in 1990 due to its
lack of capacity for dealing with the anticipated
workload.
(b) The new management team was formed in 1990 and
the system requirement specification was completed in
February 1991.
(c) The system development and procurement contract
was first advertised in the European Journal on 7
February 1991. The recommendation to award the
contract was endorsed by the LAS Board on 28 May
1991. The contract for the radio interface system was
placed on 16 September 1991.
(d) The contractor prepared the full system specification
during June and July 1991. He then had 5 months to
achieve full system implementation by the due date of
8 January 1992.
(e) By mid-December 1991 it was clear that this date could
not be achieved. At that point the computer-aided
despatch software was incomplete and largely untested.
The radio interface system hardware and software
were not fully delivered and tested. The installation of
the ambulance tracking equipment (Datatrak) was
incomplete and its reporting accuracy under question.
(f) In January 1992 attempts were made at functional and
load testing of the system. These tests were inconclusive
and, over the next few months, various system elements
were tested, but never as a fully integrated whole.
(g) During the first 9 months of 1992 the system was
implemented piecemeal across different London
Ambulance divisions.
(h) The system was fully implemented at 07:00 hours on
26 October 1992. As the day wore on the system
became overloaded and it was necessary to revert to
semi-manual operation. This solution worked with
reasonable success up to the early hours of 4 November
at which time it slowed significantly and then locked up
altogether.
The enquiry
An enquiry team was set up by the South West Thames
Regional Health Authority in November 1992:
'To examine the operation of the computer-aided despatch
system, including:
the circumstances of its failures on Monday 26 October
and Wednesday 4 November 1992;
the process of its procurement;
and to identify lessons to be learned for operation and
management of the LAS against the imperatives of delivering service at the required standard, demonstrating good
working relationships and restoring public confidence.'
The team comprised:
The Chief Executive of South Yorkshire Metropolitan
Ambulance and Paramedic Service NHS Trust.
A senior computer audit partner from a reputable firm
of consultants.
110
Bibliography
The material used in the preparation of this case study was
taken from the report of the Inquiry into the London
Ambulance Service dated February 1993.
Michael Hougham 's early career was
in military electronics with GEC. He
moved into construction engineering
project management in 1977 and
worked with both John Brown E & C
and Stone & Webster Ltd on a wide
variety o f projects in the north sea,
on land in the UK and overseas. His
specialisation is project management
controls. For the past three years he
has managed Greenlands Management
& Engineering Consultants Ltd. He
has recently accepted the position of
Executive Officer with the Association
of Project Managers.