PRODUCTIVITY RATES FOR ALL PROJECT WORKS:

(Rev 0, May 2000)

Item No.

CREW SIZE

Hourly

Production

Production Rate

Per 10 hrs.
SM

FW

FORMWORK

FW01

Formwork to footings

2 CARPENTERS, 1 HELPER

1.2

12

FW02

Formwork to isolated footings

2 CARPENTERS, 1 HELPER

1.6

16

FW03

Formwork to rafts

2 CARPENTERS, 1 HELPER

1.4

14

FW04

Formwork to rafts D>0.75m

2 CARPENTERS, 1 HELPER

1.8

18

FW05

Formwork to tie beams

2 CARPENTERS, 1 HELPER

10

FW06

Formwork to high level tie beams D>0.45M

2 CARPENTERS, 1 HELPER

1.2

12

FW07

Formwork to Neck Columns

2 CARPENTERS, 1 HELPER

FW08

Formwork to U/G Water tank

2 CARPENTERS, 1 HELPER

FW09

Formwork to basement retaining walls

2 CARPENTERS, 1 HELPER

FW10

Formwork to columns (small size)

2 CARPENTERS, 1 HELPER

FW11

Formwork to Columns (large size)

2 CARPENTERS, 1 HELPER

FW12

Formwork to D/S beam internal (shallow)

2 CARPENTERS, 1 HELPER

FW13

Formwork to D/S beam external (Deep)

2 CARPENTERS, 1 HELPER

FW14

Formwork to D/S beam external (Shallow)

2 CARPENTERS, 1 HELPER

FW15

Formwork to D/S beam external (Deep)

2 CARPENTERS, 1 HELPER

FW16

Formwork to lift walls single core

2 CARPENTERS, 1 HELPER

FW17

Formwork to lift walls multi core

2 CARPENTERS, 1 HELPER

FW18

Formwork to slab decking (10ft) hourdi

2 CARPENTERS, 1 HELPER

1.6

16

FW19

Formwork to slab decking (>10ft) hourdi D/S beams

2 CARPENTERS, 1 HELPER

1.2

12

FW20

Formwork to slab decking (>10ft) hourdi

2 CARPENTERS, 1 HELPER

1.2

12

FW21

Formwork to slab decking (>10ft) hourdi

2 CARPENTERS, 1 HELPER

10

FW22

Formwork to staircase (non spiral)

2 CARPENTERS, 1 HELPER

FW23

Formwork to balcony parapets

2 CARPENTERS, 1 HELPER

FW24

Formwork to roof parapets

2 CARPENTERS, 1 HELPER

D
= DEPTH
U. GR. = UNDERGROUND
D/S
= DECK - SLAB
>
= GREATER THAN
<
= LESS THAN

Page 1 of 7

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:


(Rev 0, May 2000)
Item No.

CREW SIZE

Hourly

Production

Production Rate

Per 10 hrs.

FW 25

shutter Manufacture for pile caps

1 CARPENTER + 1 HELPER

2.00

20

FW 26

shutter Fix for pile caps

I CARPENTER + 1 HELPER

1.50

30

FW 27

Deshutter footings/pile caps

1 HELPER

6.00

60

FW 28

Shutter make column necks

1 CARPENTER + 1 HELPER

1.50

15

FW 29

Shutter fix column necks

1 CARPENTER + 1 HELPER

1.20

12

FW 30

Deshutter Column necks

1 HELPER

4.80

48

FW 31

Shutter make tie beams

1 CARPENTER + 1 HELPER

1.20

12

FW 32

shutter fix tie beams

1 CARPENTER + 1 HELPER

1.00

10

FW 33

Column shutter making

1 CARPENTER + 1 HELPER

1.20

12

FW 34

Column shutter fixing

1 CARPENTER + 1 HELPER

1.00

10

FW 35

Column deshuttering

1 HELPER

4.00

40

FW 36

Walls shutter making

1 CARPENTER + 1 HELPER

1.50

15

FW 37

Walls shutter fixing

1 CARPENTER + 1 HELPER

0.80

80

FW 38

De shutter Tie beam shutter

1 HELPER

4.00

40

FW 39

Wall formwork deshuttering

1 HELPER

3.20

32

FW 40

Staircase formwork making

1 CARPENTER + 1 HELPER

0.80

FW 41

staircase formwork fixing

1 CARPENTER + 1 HELPER

0,8

FW 42

Staircase formwork deshuttering

1 HELPER

1,6

16

FW 43

Drop beams formwork making

1 CARPENTER + 1 HELPER

1.00

10

FW 44

Drop beams formwork fixing

1 CARPENTER + 1 HELPER

0.80

FW 45

Drop beams formwork stipping

1 HELPER

3.20

32

FW 46

suspended slab formwork fixing

1 CARPENTER + 1 HELPER

1.20

12

FW 47

suspended slab formwork deshutter

1 HELPER

5.00

50

FW 48

Formwork fixing for sunshades

1 CARPENTER + 1 HELPER

0.70

FW 49

Parapet formwork making

1 CARPENTER + 1 HELPER

1.20

12

FW 50

Parapets formwork fixing

1 CARPENTER + 1 HELPER

1.00

10

FW 51

Parapets formwork stripping

1 HELPER

4.00

40

FW 53

Fixing of lintle formwork

1 CARPENTER + 1 HELPER

0.50

FW 54

Deshutter lintle formwork

1 HELPER

2.00

20

FW 55

Deck formwork fixing

1 CARPENTER + 1 HELPER

1.50

15

FW 56

Deck Formwork deshuttering

1 HELPER

6.00

60

FW 57

Pipe scaffolding erection for slab

1 SCAFFOLDER

0.85

85

FW 58

inverted beam shutter fixing

1 CARPENTER + 1 HELPER

1.00

10

FW 59

De-Shuttering Manholes, square - circular (Timber)

1 CARPENTER + 1 HELPER

4m2

40m2

FW 60

Manhole Shutter erection - square or circular(Timber)

1 CARPENTER + 1 HELPER

1,5 m2

15m2

FW 61

Metal Shutter for Manholes

1 CARPENTER + 1 HELPER

1m

10m2

FW 62

Metal Shutter for Precast Beams

2 CARPENTERS + 2 HELPERS

FW 63

Metal Shutter for Pile caps

FW 64

Metal Shutters for Pile cap Beams

3M

30M2

2 CARPENTERS + 2 HELPERS

3M

27M2

2 CARPENTERS + 2 HELPERS

3M2

30M2

Page 2 of 7

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:


(Rev 0, May 2000)
Item No.

CREW SIZE

Hourly

Production

Production Rate

Per 10 hrs.
Per Unit

MASONARY WORKS

MBW 01

Hollow Blockwork (100, 150 & 200 mm)

1 MASON, 1 HELPER

12 Nos

120 NR

MBW 02

Hollow Blockwork (large panels)

1 MASON, 1 HELPER

14 Nos.

140 NR

MBW 03

Solid blockwork

1 MASON, 1 HELPER

9,5

95 NR

MBW 04

Solid Blockwork as Raft forms

1 MASON, 1 HELPER

11

110 NR

MPL

PLASTERWORK

MPL 01

Plaster (internal), walls final coat

1 MASON, 1 HELPER

1.6

16 SM

MPL 02

Plaster (internal), walls rush coat

2 HELPER

1.4

150 SM

MPL 03

Plaster (internal), walls mesh

1 HELPER

1.8

100 SM

MPL 04

Plaster (internal), walls hacking

1 HELPER

100 SM

MPL 05

Plaster (internal), walls guide point

1 MASON, 1 HELPER

1.2

100 SM

MPL 06

Plaster (internal), walls corner beads

1 MASON, 1 HELPER

10 SM

100 SM

MPL 07

Plaster (external), walls with grooves

1 MASON, 1 HELPER

10 SM

10 SM

MPL 08

Plaster (external), walls without grooves

1 MASON, 1 HELPER

1,2

12 SM

MPL 09

Plaster (external), walls rush coat

2 HELPER

15 SM

150 SM

MPL 10

Plaster (external), walls mesh

1 HELPER

10 SM

100 SM

MPL 11

Plaster (external), walls hacking

1 HELPER

10 SM

100 SM

MPL 12

Plaster (external), walls guide points

1 MASON, 1 HELPER

10 SM

100 SM

MPL 13

Plaster (external), walls corner beads

1 MASON, 1 HELPER

10 SM

100 SM

MPL 14

Plastering of Arches/Mullians

1 MASON, 1 HELPER

0.8

80

MPL 15

Floor screed 50mm thick

1 MASON, 1 HELPER

20

MPL 16

Roof screed 100 mm thick

1 MASON, 1 HELPER

1.5

15

MPL 17

Mosiac floor Tiles fixing

1 MASON, 1 HELPER

1.6

1.5

MPL 18

Floor Screed 25mm thick

1 Mason + 1 Helper

0,6

MCR

CERAMIC WORKS

MCR 01

Ceramic tiles to walls by mortar

1 MASON, 1 HELPER

1.2

8 SM

MCR 02

Ceramic tiles to walls, mortar to corridors

1 MASON, 1 HELPER

9 SM

MCR 03

Ceramic tiles to walls, cut pieces

1 MASON

20 SM

MCR 04

Ceramic tiles to walls grouting

1 HELPER

50 SM

MCR 05

Ceramic tiles to walls, by glue

1 MASON, 1 HELPER

1,2

12 SM

MCR 06

Ceramic tiles to walls, corridors, by glue

1 MASON, 1 HELPER

1,3

13 SM

MCR 07

Ceramic tiles to walls, by glue, cut pieces

1 MASON

20 SM

MCR 08

Ceramic tiles to walls, by glue, grouting

1HELPER

50 SM

MCR 09

Ceramic tiles to floors

1 MASON, 1 HELPER

10 SM

MCR 10

Ceramic tiles to floors in halls

1 MASON, 1 HELPER

1,2

12 SM

MCR 11

Ceramic tiles to floors, cut pieces

1 MASON

20 SM

MCR 12

Ceramic tiles to floors, grouting

1 HELPER

50 SM

MCR 13

Marble flooring

1 MASON + 1 HELPER

0.60

60

1.2

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:


(Rev 0, May 2000)
Item No.

CREW SIZE

Hourly

Production

Production Rate

Per 10 hrs.
Per Unit

MCR 11

Ceramic tiles to floors, cut pieces

1 MASON

20 SM

MCR 12

Ceramic tiles to floors, grouting

1 HELPER

50 SM

MCR 13

Marble flooring

1 MASON + 1 HELPER

0.60

60

Page 3 of 7

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:


(Rev 0, May 2000)
Item No.

CREW SIZE

Hourly

Production

Production Rate

Per 10 hrs.
Per Unit

MCR

CERAMIC WORKS

MCR 13

Ceramic skirting by glue

1 MASON, 1 HELPER

2,5 M

25 METRE

MCR 14

Ceramic skirting by glue to halls, corridors

1 MASON, 1 HELPER

3M

30 METRE

MTW

TILING WORKS

MTW 01

Mosiac / Terrazo tiles to roofs

1 MASON, 1 HELPER

1,6

16 SM

MTW 02

Mosiac / Terrazo tiles to floors

1 MASON, 1 HELPER

1,4

14 SM

MTW 03

Mosiac skirting to halls

1 MASON, 1 HELPER

2,5

25 METRE

MTW 04

Mosiac skirting flush / recessed

1 MASON, 1 HELPER

1,4

14 METRE

MTW 05

Grouting / sealing to roof / floor tiles

1 HELPER

2,5

25 METRE

MKP

KERBING / BLOCK PAVING WORKS

MKP00

P.C.C. Curve kerb base (to curves)

1 MASON, 1 HELPER

2,5

25 METRE

MKP01

PCC to kerb base (Straight line)

1 MASON, 1 HELPER

3,0

30 METRE

MKP02

Haunching to kerb base (Dumpes)

1 MASON, 1 HELPER

40 METRE

MKP03

kerbstonse (Without PCC)

1 MASON, 1 HELPER

1,5

15 METRE

MKP04

Interlock paving on pre prepared sub - base

1 MASON, 1 HELPER

MKP05

Screed works including preparation

1 MASON, 1 HELPER

1,5

15 SM

MKP06

Haunching ot Kerb Base (Mixing Truck)

1 MASON, 1 HELPER

10 M

100M

DRW

MANHOLE/ DRAINAGE CONSTRUCTION

DRW 01

Excavation for drains / manholes

1 HELPER

5 CM

DRW 02

Backfill to drains / manholes

1 HELPER

10 CM

DRW 03

Blockwork to manholes

1 MASON, 1 HELPER

2 NOS

DRW 04

Plaster to manholes

1 MASON, 1 HELPER

2 NOS

DRW 05

Benching to manholes

1 MASON, 1 HELPER

4 NOS

DRW 06

Fix covers to manholes

1 MASON, 1 HELPER

2 NOS

DRW 07

Fix gulley traps

1 MASON, 1 HELPER

DRW 08

Laying of P.V.C. sleeves 4" - 12"

4 HELPER

MLW

MISCELLANEOUS LABOUR WORKS

MLW01

Bitumen paint to concrete blockwork surfaces

MLW02

Bitumin painting Bases / piles

MLW03

2 SM

1 NO
24M

240M

1 HELPER

40 SM

1 HELPER

7.00

70

Hacking of concrete surfaces

1 HELPER

50 SM

MLW04

fixing of flexcell sheets

1 HELPER

MLW05

pile cutting/dressing

1 HELPER

1 NO

MLW06

pile cutting/dressing (small diameter)

1 HELPER

2 NOS

MLW07

Vertical sealant (12 mm)

1 HELPER

2,5

25 METRE

MLW08

Horizontal sealant (12 mm)

1 HELPER

50 EMTRE

MLW09

Roof preparation for lw concrete

1 MASON, 1 HELPER

50 SM

MLW10

Angle fillet fixing

1 MASON, 1 HELPER

40 EMTE

MLW11

Hourdi block shifting and fixing to slab

2 HELPER

20

200 NOS

MLW12

Polythene sheet fixing

1 HELPER

3m

30

MLW13

Shaping of Soil Blinding

1 MASON + 1 HELPER

1M

10M

MLW14

Protection Board installation

1 CARPENTER + 1 HELPER

8M2

80M2

MCW

MISCELLANEOUS CARPENTARY WORKS

MCW 01

A/C subframe manufacture / fixing

1 CARPENTER

MCW 02

Door subframe manufacture / fixing

1 CARPENTER

MCW 03

Water bar fixing

1 CARPENTER

6 SM

5 NOS
4 NOS
2M

20 METRE
Page 4 0f 7

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:


(Rev 0, May 2000)
Item No.

CREW SIZE

Hourly

Production

Production Rate

Per 10 hrs.
Per Unit

CPW

CONCRETE PLACEMENT WORKS

CPW01

Concrete to pile caps by pump

6 MASONS, 18 HELPERS, 1 CARPENTER

Standard rate 1 man

180 CM
1 hr.

10m3

CPW02

Concrete to PCC blinding (100 mm thick)

1 MASON, 10 HELPERS

27 CM

CPW03

Concrete to slabs/beams, by pump

6 MASONS, 18 HELPERS, 1 CARPENTER

CPW04

Concrete to slabs / beams by crane

1 MASON, 6 HELPERS, 0.5 OPERATOR

8,10

27 CM

CPW05

Concrete to walls / columns, by pump

4 MASONS, 16 HELPERS, 2 CARPENTERS

1.2

81 CM

CPW06

Concrete by site mix

1 MASON, 12 HELPERS , 0.5 CARPENTER

1.6

9 CM

CPW07

Concrete Columns

8 HELPERS

1.40

10

CPW08

Concrete suspended slab (pump)

3 MASONS + 6 HELPERS

1.80

150

CPW09

Concrete parapets/staircases

8 HELPERS

1.00

CPW10

Blinding concrete 50 mm (readymix)

1 MASON + 4 HELPER

8,0

80

CPW11

Blinding concrete 50 mm (sitemix)

1 MASON + 8 HELPER

1.00

10

CPW12

Concrete footings & pile caps

1 MASON + 4 HELPER

12.00

120

CPW13

Concrete tiebeams, ground beams

1 MASON + 5 HELPER

6.00

60

CPW14

Concrete column necks

8 HELPER

1.50

15

CPW15

Concrete Ground slab

3 MASONS + 6 HELPER

1,5

15

CPW16

Concrete to precast slabs, beams

2 MASONS + 1 HELPER

3m3

30 M3

GLW

GENERAL LABOUR WORKS

GLW01

Unloading reinforcement ((Flat Bed Truck)

4 HELPERS

GLW02

Loading reinforcement to slab (With Crane)

4 HELPERS (Flat Bed Truck loads)

GLW03

Loading blockwork to site (with Wheel Burrow)

1 HELPER

GLW04

Loading mortar to site location

GLW05

Mixing mortar for distribution 0, 3 L mixer

GLW06

Site mixing of ready mix for distribution Hand mix

GLW07

Loading ready mix to site location

NTRA

NON TARGET RELATED ACTIVITES

NTRA01

Stacking of formwork

2 HELPERS

NTRA02

Curing of Substructure works

2 HELPERS

NTRA03

Curing of beams / slabs Hessiant Water

2 HELPERS

NTRA04

Curing of columns (Hessiant Water)

1 MASON + 2 HELPERS

NTRA05

Builders work make good chases

NTRA06
NTRA07

Site cleaning
Repairs to finished works

180 CM

2 Nos
40 Nos.

2 Nos
400 Nos.

4 HELPER

6M3
3M3

1.6 (L.M)

36 M

1.2 (L.M)
1 HELPER

25
1

250 M2

Page 5 of 7

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:


(Rev 0, May 2000)
Item No.

CREW SIZE

NTRA08

Maintenance of site services

2 HELPERS

NTRA09

Operators for mixers

2/MIXER

NTRA10

Operators for compaction equipment

1 UNIT

NTRA11

Office boy

ARABTEC 1 / CONSULTANT 1

NTRA12

Watchman

2 MIN

NTRA13

Storekeeper

1/SHIFT

NON MEASURABLE

Page 6 of 7

PRODUCTIVITY RATES FOR ALL PROJECT WORKS:


(Rev 0, May 2000)
Item No.

CREW SIZE

Hourly
Production Rate

RF

REINFORCEMENT

RF 01

Fix Rebar to footings & tie beams

1 STEEL FIXER

25

RF 02

Fix Rebar to walls, columns, beams, solid slabs

1 STEEL FIXER

20

RF 03

Fix rebar to ribs of hourdi slab

1 STEEL FIXER

18

RF 04

Fix rebar to mesh reinforcement

1 STEEL FIXER

15

RF 05

Fix rebar to hidden beams

1 STEEL FIXER

20

RF 01

Fix Rebar to footings & tie beams

1 STEEL FIXER

78

RF 02

Fix Rebar to walls, columns, beams, solid slabs

1 STEEL FIXER

38

RF 03

Fix rebar to ribs of hourdi slab

1 STEEL FIXER

35

RF 04

Fix rebar to mesh reinforcement

1 STEEL FIXER

15

RF 05

Fix rebar to hidden beams

1 STEEL FIXER

RFC 01

Steel cutting and bending 18.25 mm

1 STEEL FIXER

50.00

RFC 02

Steel cutting and bending 8 - 16 mm

1 STEEL FIXER

40.00

EXCAVATION
EX 1

Manual Excavation

1 HELPER

EX 2

Backfill + levelling

1HELPER

EX 3

Shaping of sloped earth for blinding for bases including compaction

1 MASON + 2 HELPER

PRODUCTIVITY RATES
(Rev 0, May 2000)
Productivity Rates for Tilling
Size. (Cms)

Location

Area

Manpower

Production Rate

Remarks

(Sqm. Per day)

30 X 30

Floor

Kitchen

1 Mason, 1 Helper

14

Residential Area by Sub-Contractor

30 X 30

Floor with pattern

Corridor

1 Helper, 2 Masons

10

Residential Area by Sub-Contractor

40 X 40

Floor

Bed room

1 Mason, 1 Helper

22-25

Residential Area by Sub-Contractor

20 X 20

Floor

Store (small area)

1 Mason, 1 Helper

10

Residential Area by Sub-Contractor

30 X 60

Floor

Bathroom

2 Mason, 1 Helper

Residential Area by Sub-Contractor

30 X 30

Floor + Wall

Bathroom

2 Mason, 1 Helper

10 X 10

Wall

Kitchen

1 Mason, 1 Helper

8-9

Residential Area by Sub-Contractor

30 X 60

Wall

Corridor

1 Mason, 1 Helper

14-15

Residential Area by Sub-Contractor

30 X 30

Wall

Bathroom

2 Mason, 1 Helper

Residential Area by Sub-Contractor


Residential Area by Sub-Contractor

Notes:
1. 1 Day = 10 hrs.
2. Gang Size:
1 Mason + 1 Helper for Kitchen and Bedroom.
2 Mason + 1 Helper for Bathroom.