Professional Documents
Culture Documents
July 2, 2012
Nav igant Reference: 157082
Disclaimer
Content of Report
This presentation was prepared by Navigant Consulting, Inc. exclusively for the benefit and internal use
of Salt River Project (SRP) and/or its affiliates or subsidiaries. No part of it may be circulated, quoted, or
reproduced for distribution outside these organization(s) without prior written approval from Navigant
Consulting, Inc. The work presented in this report represents our best efforts and judgments based on the
information available at the time this report was prepared. Navigant Consulting, Inc. is not responsible
for the readers use of, or reliance upon, the report, nor any decisions based on the report.
NAVIGANT CONSULTING, INC. MAKES NO REPRESENTATIONS OR WARRANTIES, EXPRESSED
OR IMPLIED.
Readers of the report are advised that they assume all liabilities incurred by them, or third parties, as a
result of their reliance on the report, or the data, information, findings and opinions contained in the
report.
July 2012
1
EN ER GY
List of Acronyms
Acronym
BOP
CGS
CI
CMMS
CT
EAF
EBH
EFOR
EPRI
ES
FD
FFH
FS
GKS
GT
HGP
HRSG
MI
Description
Acronym
Balance of Plant
Coronado Generating Station
Combustor Inspection
Computerized Maintenance Management System
Combustion Turbine
Equivalent Availability Factor
Equivalent Based Hours
Equivalent Forced Outage Rate
Electric Power Research Institute
Total Equivalent Starts
Forced Draft
Factor Fired Hours
Factored Starts
Generation Knowledge Service
Gas Turbine
Hot Gas Path
Heat Recovery Steam Generator
Major Inspection
MWh
NCF
NDE
NFOM
NGS
O&M
OEM
PdM
PM
POF
PRB
QA
RCA
RCM
RTF
SRP
TPC
Description
Megawatt hour
Net Capacity Factor
Non-Destructive Examination
Non-Fuel Operations and Maintenance
Navajo Generating Station
Operations and Maintenance
Original Equipment Manufacturer
Predictive Maintenance
Preventive Maintenance
Planned Outage Factor
Powder River Basin
Quality Assurance
Root Cause Analysis
Reliability Centered Maintenance
Run To Failure
Salt River Project
Total Production Cost
2
EN ER GY
Table of Contents
Executive Summary
Project Background
Maintenance Management Practices
Cost and Performance Benchmarks
Summary of Findings and Conclusions
Recommendations
4
EN ER GY
5
EN ER GY
6
EN ER GY
7
EN ER GY
8
EN ER GY
9%
10%
<1%
30%
33%
Coal
Combined Cycle
Gas Steam
Combustion Turbine
66%
51%
2%
49%
40%
* Percentages are representative of the SRP plants (including SRPs 21.7% ownership share of Navajo
Generating Station) reviewed in this report only and not inclusive of SRPs total generation capability.
2012 Nav igant Consulting, Inc.
Confidential and proprietary . SRP use only .
9
EN ER GY
Equivalent
Availability
Factor
Equivalent
Forced
Outage Rate
Net Capacity
Factor
Total
Production
Cost
Non-Fuel
O&M Cost
Coal
Coal plants are operating at a very high level of Availability and Reliability
with below median NFOM cost.
Trends in Availability, Reliability and NFOM cost are consistent with or better
than peers.
Achieving elite status (top quartile in both availability and NFOM cost)
would require reductions in NFOM cost without compromising current
availability and reliability performance.
Plant maintenance practices are above average and conform to both OEM and
industry standard guidelines.
Legend:
Top quartile
Second quartile
Third quartile
Fourth quartile
Note: Quartile rankings reflect the capacity weighted performance of all units in the group.
2012 Nav igant Consulting, Inc.
Confidential and proprietary . SRP use only .
10
EN ER GY
Equivalent
Availability
Factor
Equivalent
Forced
Outage Rate
Net Capacity
Factor
Total
Production
Cost
Non-Fuel
O&M Cost
Combined Cycle
Legend:
Top quartile
Second quartile
Third quartile
Fourth quartile
Note: Quartile rankings reflect the capacity weighted performance of all units in the group.
2012 Nav igant Consulting, Inc.
Confidential and proprietary . SRP use only .
11
EN ER GY
Equivalent
Availability
Factor
Equivalent
Forced
Outage
Rate
Net Capacity
Factor
Starting
Reliability
Total
Production
Cost
Non-Fuel
O&M Cost
Gas Steam
Top quartile
Second quartile
Third quartile
Fourth quartile
Note: Quartile rankings reflect the capacity weighted performance of all units in the group.
2012 Nav igant Consulting, Inc.
Confidential and proprietary . SRP use only .
12
EN ER GY
Equivalent
Availability
Factor
Equivalent
Forced
Outage
Rate
Net Capacity
Factor
Starting
Reliability
Total
Production
Cost
Non-Fuel
O&M Cost
CT
Top quartile
Second quartile
Third quartile
Fourth quartile
Note: Quartile rankings reflect the capacity weighted performance of all units in the group.
2012 Nav igant Consulting, Inc.
Confidential and proprietary . SRP use only .
13
EN ER GY
Table of Contents
Executive Summary
Project Background
Maintenance Management Practices
Cost and Performance Benchmarks
Summary of Findings and Conclusions
Recommendations
14
EN ER GY
Project Background
SRP engaged Navigant in April 2012 to benchmark and review major outage
maintenance practices for six fossil generation sites:
Coronado (coal)
Navajo (coal)
Agua Fria (gas)
Desert Basin (gas)
Kyrene (gas)
Santan (gas)
15
EN ER GY
Project Background
Scatter and trend charts were developed for the cost and performance
measures.
Scatter charts display two parameters on a single chart for comparison purposes, with
peer group median, top quartile and top decile lines for each variable.
Trend charts display a single variable plotted with annual data over the specific
evaluation period ( 10 years or 6 years), showing either group average or individual
SRP unit data along with peer group median and top quartile values.
o Individual unit trend plots often exhibit significant variability from year to year compared to
the median and top quartile trend lines which tend to be smoothed due to the larger number
of peer units being evaluated.
o This high year to year variability occurs most often when plotting NFOM cost due to the large
impact of major outages during a given year.
Relevant charts were selected for each peer group and included in the Cost and
Performance section of the report.
Notes:
1. All trend charts shown in the Cost and Performance section of the report show SRP unit data as an average
of the SRP units in the particular peer group.
2. A full set of both average and individual unit trend charts is included in the supplemental reference report.
2012 Nav igant Consulting, Inc.
Confidential and proprietary . SRP use only .
16
EN ER GY
Project Approach
Navigants project approach included four steps.
1: Kickoff Project
Kickoff
meeting
3: Extract Peer
Data
2: Collect Data
Verify data is
comparable to
GKS database
Finalize peer
group criteria
Finalize data
analysis
Extract peer
group data
from GKS
database
Prepare draft
report
SRP reviews
draft report
Implement
SRP comments
into final
report
17
EN ER GY
Cost and performance data for peer units is from Navigants Generation
Knowledge Service (GKS) data base
All data is validated through a rigorous QA process.
Cost and performance data for SRP units is supplied by SRP in accordance with
Navigants GKS data input guidelines.
18
EN ER GY
Table of Contents
Executive Summary
Project Background
Maintenance Management Practices
Cost and Performance Benchmarks
Summary of Findings and Conclusions
Recommendations
19
EN ER GY
Outage management
o Planning practices
o Outage record management
Conduct of maintenance
o Periodic preventive maintenance
o Condition based / predictive maintenance
o Corrective Maintenance
20
EN ER GY
Table of Contents
Maintenance Management Practices
Coronado (coal)
Navajo (coal)
Agua Fria (gas)
21
EN ER GY
22
EN ER GY
Observations at Coronado
23
EN ER GY
Observations at Coronado
24
EN ER GY
Observations at Coronado
Post outage critique meeting held with both SRP staff and
contractors.
CGS does not utilize a post-outage reliability indicator.
25
EN ER GY
Observations at Coronado
26
EN ER GY
Observations at Coronado
27
EN ER GY
28
EN ER GY
Table of Contents
Maintenance Management Practices
Coronado (coal)
Navajo (coal)
Agua Fria (gas)
29
EN ER GY
30
EN ER GY
Observations at Navajo
31
EN ER GY
Observations at Navajo
32
EN ER GY
Post outage critique meeting held with both SRP staff and
contractors.
NGS does not currently utilize a post-outage reliability
indicator (planned for current Fiscal Year) and post-outage
reliability was poor during the last three outages reviewed.
Observations at Navajo
33
EN ER GY
Observations at Navajo
34
EN ER GY
Observations at Navajo
35
EN ER GY
36
EN ER GY
Table of Contents
Maintenance Management Practices
Coronado (coal)
Navajo (coal)
37
EN ER GY
38
EN ER GY
39
EN ER GY
40
EN ER GY
The planned outage scope defines high level tasks until visual
inspection determines actual work scope, because work is bid
out based on actual wear and tear.
Main component outage reports are used and acted upon for
long term planning.
41
EN ER GY
All repair reports are maintained and used to plan the long
term maintenance scope.
42
EN ER GY
43
EN ER GY
44
EN ER GY
Table of Contents
Maintenance Management Practices
Coronado (coal)
Navajo (coal)
Agua Fria (gas)
45
EN ER GY
46
EN ER GY
47
EN ER GY
Ten year outage plan maintained that synchs with six year
corporate financial plan.
Purchase Orders are placed around 2 years in advance.
Outage scope is frozen around 6 months before the outage.
48
EN ER GY
Main component outage reports are used and acted upon for
long term planning.
49
EN ER GY
All repair reports are maintained and used to plan long term
maintenance scope.
50
EN ER GY
51
EN ER GY
52
EN ER GY
Table of Contents
Maintenance Management Practices
Coronado (coal)
Navajo (coal)
Desert Basin (gas)
53
EN ER GY
54
EN ER GY
55
EN ER GY
Observations at Santan/Kyrene
Current mix is about 1/3 preventive and 1/3 predictive and 1/3
corrective maintenance.
Moving to more condition based and predictive maintenance.
56
EN ER GY
Observations at Santan/Kyrene
57
EN ER GY
Every repair report is used and acted upon for long term
planning.
Observations at Santan/Kyrene
58
EN ER GY
All repair reports are maintained and used for long term
maintenance.
Observations at Santan/Kyrene
59
EN ER GY
Observations at Santan/Kyrene
60
EN ER GY
The Santan plant is in a well maintained state, all areas are clean without any debris
The Santan gas turbines are visually in good condition and have been well maintained
Plant Management is very engaged in the maintenance program
Plant management shows pride in
o Dedication and level of experience in workforce
o Breadth and depth of workforce talent, which provides the plant with many in-house
capabilities
o Excellent collaboration between operations, maintenance and engineering
Note that Navigant did not tour the Kyrene plant due to scheduling conflicts.
61
EN ER GY
Table of Contents
Maintenance Management Practices
Coronado (coal)
Navajo (coal)
Desert Basin (gas)
62
EN ER GY
Siemens / Westinghouse
Service Bulletin 36803 Rev. 10
7241 FA+e
Santan (SA) 5a, 5b and 6 - Kyrene 7
W501F
Desert Basin CT 1 and CT2
Combustion
Inspection
(CI)
Major
Inspection
(MI)
Factored
Starts
(FS)
450
900
2,400
Total
Equivalent
Starts (ES)
Factored
Fired Hours
(FFH)
12,000
24,000
48,000
Equivalent
Base Hours
(EBH)
7 E/EA
Santan (SA) 1, 2, 3, 4 - Kyrene 5, 6
Major
Inspection
(MI)
400 /
900 (with
uprate)
800 /
900 (with
uprate)
1,600 /
1,800 (with
uprate)
8,000 /
12,500 (with
uprate)
24,000 /
25,000 (with
uprate)
48,000 /
50,000 (with
uprate)
W501B
Agua Fria Unit 4, 5 and 6 Kyrene 4
Combustion
Inspection
(CI)
Major
Inspection
(MI)
Factored
Fired Hours
(FFH)
450
1,200
2,400
Factored
Starts
(FS)
12,000
24,000
48,000
Combustion
Inspection
Major (CI)*
Combustion
Inspection
Major (CI)*
Major
Inspection
(MI)
Total
Equivalent
Starts (ES)
400
800
1,600
Equivalent
Base Hours
(EBH)
8,000
16,000
32,000
SA5b
SA6
K7
CI
CI
Current Data
Comment
Date
Total FS
Incremental FS
Total FFH
Incremental FFH
12/12/2006
511
511
11,017
11,017
4/18/2008
929
418
19,048
8,031
1/3/2011
1,379
450
31,300
12,252
5/1/2012
1,609
230
35,657
4,357
Date
Total FS
Incremental FS
Total FFH
Incremental FFH
12/20/2006
521
521
9,468
9,468
4/18/2008
837
316
17,178
7,710
5/2/2010
1,159
322
29,248
12,070
5/1/2012
1,540
381
35,620
6,372
Date
Total FS
Incremental FS
Total FFH
Incremental FFH
9/30/2007
476
476
9,634
9,634
10/27/2009
844
368
23,357
13,723
1/3/2012
1,267
423
30,231
6,874
5/1/2012
1,315
48
32,155
1,924
Date
Total FS
Incremental FS
Total FFH
Incremental FFH
No
Previous
History
11/10/2007
1572
Unknown
25,000
Unknown
3/1/2009
1,946
374
30,724
5,724
5/1/2012
2,368
422
40,233
9,509
The gas turbines have historically been maintained in accordance with manufacturer recommended
intervals and appropriate prudent industry practices.
Yellow highlighted cells show variances from manufacturer recommended intervals. All of these are
within prudent industry practices.
64
EN ER GY
SA2
SA3
Outage Sequence
Current Data
Comment
Outage Event
Date
Total FS
Incremental FS
Total FFH
Incremental FFH
CI
3/31/2008
254
Not available
2,069
Not available
CI
2/2/2011
4,024
437
81,213
3,499
5/1/2012
4,178
154
82,532
1,319
Outage Event
Date
Total FS
Incremental FS
Total FFH
Incremental FFH
CI
12/5/2008
1,636
364
17,531
3,034
HGP
11/1/2011
3,803
315
90,778
2,589
5/1/2012
3,846
43
91,144
366
Outage Event
Date
Total FS
Incremental FS
Total FFH
Incremental FFH
CI
12/1/2007
1,286
Not available
14,144
Not available
CI
11/30/2010
3,701
480
82,914
3,808
5/1/2012
3,881
180
84,469
1,555
The gas turbines have historically been maintained in accordance with manufacturer recommended
intervals and appropriate prudent industry practices.
Yellow highlighted cells show variances from manufacturer recommended intervals. All of these are
within prudent industry practices.
65
EN ER GY
Outage Sequence
SA4
Outage Event
Date
Total FS
Incremental FS
Total FFH
Incremental FFH
K4, K5
K6
CI
2/11/2008
818
Not available
7,376
Not available
CI
4/1/2011
3,885
449
90,615
3,502
Current Data
MI
4/3/2012
4,023
138
91,829
1,214
Comment
Controls upgrade in April 2010 with hours/starts counter update
5/1/2012
4,036
13
91,945
116
Outage Event
Date
Total FS
Incremental FS
Total FFH
Incremental FFH
The gas turbines have historically been maintained in accordance with manufacturer recommended
intervals and appropriate prudent industry practices.
Due to low run times for K4, K5 and K6 no planned gas turbine outages have been performed since
2001.
66
EN ER GY
CT2
Outage Sequence
Current
Data
Event
Date
Total ES
Incremental ES
Total EBH
Incremental EBH
CI
1/14/02
CI
6/13/02
CI
1/24/03
HGP
1/25/04
HGP
4/23/04
CI
4/2/05
MI
10/15/06
398
398
124
124
465
67
250
127
637
172
459
209
806
169
713
254
855
49
760
47
1,069
214
986
226
1,487
418
1,299
312
CI
3/8/08
1,917
430
1,504
205
Event
Date
Total ES
Incremental ES
Total EBH
Incremental EBH
CI
3/1/02
CI
1/25/03
HGP
1/8/04
CI
4/8/05
MI
3/4/06
CI
4/6/07
HGP
10/2/08
306
306
155
155
506
200
432
277
708
202
651
219
1,135
427
950
298
1,457
322
1,111
162
1,791
334
1,220
109
2,262
471
1,482
262
CI
11/5/09
HGP
5/1/09
2,161
244
1,656
152
Upgrade
HGP
2/5/11
HGP
7/2/11
2/28/12
2,484
222
1,602
120
2,668
184
1,710
108
2,690
22
1,723
13
2,750
60
1,765
43
2/3/12
2,610
449
1,957
301
The gas turbines have historically been maintained in accordance with manufacturer recommended
intervals and appropriate prudent industry practices.
67
EN ER GY
68
EN ER GY
Table of Contents
Executive Summary
Project Background
Maintenance Management Practices
Cost and Performance Benchmarks
Summary of Findings and Conclusions
Recommendations
133
EN ER GY
EFOR
NFOM
($/MWh)
Unit
Technology
Comment
Coal
91.6%
3.5%
$8.84
Coal
91.1%
4.4%
$8.62
Legend:
Top quartile
Second quartile
Third quartile
Fourth quartile
EAF: Equivalent Availability Factor, EFOR: Equivalent Forced Outage Rate, NFOM: Non-Fuel Operations and Maintenance
134
EN ER GY
EFOR
NFOM
($/MWh)
Unit
Technology
Comment
Coal
90.3%
3.1%
$7.66
Coal
89.8%
4.6%
$7.62
Coal
90.2%
4.3%
$7.40
Top quartile
Second quartile
Third quartile
Fourth quartile
EAF: Equivalent Availability Factor, EFOR: Equivalent Forced Outage Rate, NFOM: Non-Fuel Operations and Maintenance
135
EN ER GY
Technology
SR
EFORd
NFOM ($/kW)
Comment
Gas Steam
100%
1.01%
$32.01
Gas Steam
100%
7.04%
$33.92
Gas Steam
100%
1.86%
$34.03
CT
99%
9.71%
$12.93
CT
99%
6.30%
$12.56
CT
100%
6.79%
$11.74
Top quartile
Second quartile
Third quartile
Fourth quartile
SR: Starting Reliability, EFORd: Equivalent Forced Outage Rate demand, NFOM: Non-Fuel Operations and Maintenance
Note that SRP counts a start as successful once a unit is ready for dispatch. This is considered more stringent than other industry measures.
2012 Nav igant Consulting, Inc.
Confidential and proprietary . SRP use only .
136
EN ER GY
Technology
DB
Combined
Cycle
SR
97%
EFOR
NFOM
($/kW)
20.49%
Comment
$32.26
Legend:
Top quartile
Second quartile
Third quartile
Fourth quartile
SR: Starting Reliability, EFOR: Equivalent Forced Outage Rate, NFOM: Non-Fuel Operations and Maintenance
Note that SRP counts a start as successful once a unit is ready for dispatch. This is considered more stringent than other industry measures.
Peer statistics for combined cycle starting reliability are unavailable.
2012 Nav igant Consulting, Inc.
Confidential and proprietary . SRP use only .
137
EN ER GY
EFOR
NFOM
($/kW)
Unit
Technology
Comment
Combined
Cycle
95%
7.30%
$28.32
Combined
Cycle
92%
11.94%
$27.84
Combined
Cycle
96%
2.85%
$18.75
Combined
Cycle
97%
10.38%
$25.02
Combined
Cycle
98%
6.46%
$30.24
Combined
Cycle
98%
8.12%
$22.55
Top quartile
Second quartile
Third quartile
Fourth quartile
SR: Starting Reliability, EFOR: Equivalent Forced Outage Rate, NFOM: Non-Fuel Operations and Maintenance
Note that SRP counts a start as successful once a unit is ready for dispatch. This is considered more stringent than other industry measures.
Peer statistics for combined cycle starting reliability are unavailable .
2012 Nav igant Consulting, Inc.
Confidential and proprietary . SRP use only .
138
EN ER GY
EFORd
NFOM
($/kW)
Unit
Technology
Comment
CT
91%
27.51%
$6.74
CT
97%
10.12%
$9.35
CT
97%
12.94%
$7.35
Combined
Cycle
99%
14.24%
(EFOR)
$33.60
Top quartile
Second quartile
Third quartile
Fourth quartile
SR: Starting Reliability, EFOR: Equivalent Forced Outage Rate demand, NFOM: Non-Fuel Operations and Maintenance
Note that SRP counts a start as successful once a unit is ready for dispatch. This is considered more stringent than other industry measures.
2012 Nav igant Consulting, Inc.
Confidential and proprietary . SRP use only .
139
EN ER GY
Table of Contents
Executive Summary
Project Background
Maintenance Management Practices
Cost and Performance Benchmarks
Summary of Findings and Conclusions
Recommendations
140
EN ER GY
2.
3.
SRP should consider the potential benefit of standardizing critical processes between the two coal
plants, such as the pre-outage planning process, post-outage critique process, etc. Other best
performing companies have realized the benefit of leveraging best practices across their fleet,
especially when it comes to critical processes.
Continual (dynamic) optimization of a PM program is a hallmark of an outstanding maintenance
program, along with strong craft involvement and ownership. SRP should consider implementing a
PM specific craft feedback process to encourage both continual optimization of the PM program and
craft ownership. See the next slide titled Example PM Craft Feedback Form.
SRP should consider implementing a post-outage reliability indicator as another means to assess the
effectiveness of a planned outage. Typical characteristics of these indicators are:
A. They measure reliability (i.e. EFOR, EUOF, etc.) for some period after breaker closed and the
outage is officially declared over. Usually this period is anywhere from one to three months.
B. Targets are established.
C. Events resulting in reliability loss during the evaluation period are evaluated in the context of
1. Was this an item worked on during the outage? If so, does this represent a quality of
work issue?
2. If this item was not worked on during the outage, does this represent a failure of our
condition assessment or outage planning process?
3. Etc.
141
EN ER GY
Category Grade
5
Above Average: The PM condition is between good(5) and average (3). There
is very minor degradation.
Below Average: PM condition is between poor (1) and average (3). More
degradation than expected.
142
EN ER GY
2.
3.
4.
5.
6.
7.
SRP should perform an in depth review of maintenance cost drivers for its gas plants. While all plants
interviewed demonstrated a well established maintenance program, maintenance costs are generally
higher than peers. Navigant recommends a detailed cost review to identify causes and devise suitable
next steps to improve the cost position.
Recommend implementation of post-outage reliability performance success measure as another
means to determine outage effectiveness.
The maintenance process should be documented and readily available for personnel, despite the deep
experience of the existing (graying) workforce.
Outage scope planning appeared lax at most locations, especially for long lead time items.
Recommend to evaluate benefits of structured outage scope planning approaches.
Outage cost tracking appears slow. Recommend to review the outage cost tracking process and
determine if faster cost tracking during outages would identify trends earlier and mitigate potential
cost overruns.
The sites did not follow a formal cost / benefit analysis process for planned upgrades. Recommend to
evaluate the benefit of formal cost / benefit analysis.
All sites should follow a documented set of criteria that determines when a RCA is conducted.
143
EN ER GY
Key
C ON TACTS
EN ER GY
EN ER GY
EN ER GY
144
EN ER GY