Saudi Aramco 2616-ENG (11/2010)

NOTES:
1- THESE ARE EXISTING PUMPS IN VACUUM UNIT-3. RATED DUTY IS CHANGED AS PART OF RIYADH REFINERY REVAMP PROJECT. VENDOR SHALL
RERATE THE PUMP TO MEET THE NEW DUTY REQUIREMENT. VENDOR SHALL SUPPLY IMPELLER, MOTOR DRIVER, COUPLING, COUPLING GUARD,
SEAL, SEAL FLUSH PLAN, SEAL LEAKAGE DETECTION PLAN, SEAL QUENCH PLAN AND BEARINGS. VENDOR SHALL MODIFY THE SEAL CHAMBER
AND MODIFY OR REPLACE THE BEARING HOUSING IF REQUIRED. VENDOR SHALL ALSO SEE THE POSSIBLITY OF REUSING THE EXISTING BASEPLATE.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

THIS REVISION IS NOT TO BE


USED FOR CONSTRUCTION
UNTIL CERTIFIED AND DATED

REVISION DESCRIPTION

ISSUED FOR 30% PACKAGE REVIEW

SAUDI ARABIAN OIL COMPANY

VENDOR SHALL SUPPLY NEW BASEPLATE IF IT IS NOT POSSIBLE TO REUSE THE EXISTING ONE. REST OF COMPONENTS SHALL BE REUSED. VENDOR
SHALL SPECIFY IN QUOTATION IF ANY OTHER COMPONENT NEEDS TO BE REPLACED TO MEET THE NEW DUTY REQUIREMENT. VENDOR SHALL
PERFORM ALL TESTING SPECIFIED IN 'INSPECTION AND TESTING' SECTION AND PROVIDE PERFORMANCE GUARANTEE. ALL MODIFICATIONS SHALL
COMPLY WITH THE LATEST ARAMCO SPECIFICATION 31-SAMSS-004.

JOB ORDER/EWO NO.

- PT:

REV. NO.

DATE

10-SEP-13

2- EXISTING AS-BUILT PUMP DATA IS GIVEN AS FOLLOWS:


291C

- S.G:

0.733 @PT

- RATED CAPACITY:

483.5m3/hr

- RATED HEAD:

163.4m

- NPSHR(water):

13m

- MAWP:

20kg/cm2 (g)@350C

- PUMP CASING/TRIM CLASS:

API 610 C-1

3- EXISTING MOTOR DATA IS GIVEN AS FOLLOWS:

OTHER

BY/DATE

- MANUFACTURER:

MITSUBISHI ELECTRIC CO.

- NAMEPLATE RATING:

298kW FOR Z09-P0013A; 255kW FOR Z09-P0013B

- SPEED:

3600

- FRAME:

687T

OPERATIONS/DATE

- PERFORMANCE CURVE (DOC.# 36G-4165)


- OUTLINE DRAWING (DOC.# P2-A0678)
- MECHANICAL SEAL DATA SHEET AND DRAWING (DOC.# 36G-3730)
- SECTIONAL ASSEMBLY DRAWING ( DOC.# P2-B0645)
- COUPLING DRAWING (DOC.# 36G-3729)

CONST. AGENCY/DATE

- MOTOR SPECIFICATION (DOC.# 3H1081W07-2)


- MOTOR OUTLINE (DOC.# CN71807)

5- NPSHR SHALL NOT EXCEED THE SPECIFIED NPSHA OVER THE RANGE OF MINIMUM CONTINUOUS STABLE CAPACITY TO 120% OF THE RATED
CAPACITY. AT RATED CAPACITY, THE NPSHA SHALL ALSO EXCEED THE NPSHR BY A MINIMUM MARGIN OF ONE(1) METER .

6- VISCOSITY CORRECTION FACTORS SHALL BE AS PER HI 9.6.7.

CERTIFIED/DATE

REVIEW FOR KEY DRAWINGS

- EXISTING AS-BUILT DATA SHEET (DOC.# 36G-3727)

7- PUMP SHALL HAVE A CONTINUOUS HEAD RISE FROM THE RATED HEAD TO SHUTOFF. THE HEAD RISE SHALL NOT BE LESS THAN 10% OF THE
RATED HEAD. SYSTEM IS DESIGNED TO 20.3KG/CM2.G@343C. VENDOR SHALL CONFIRM THE DESIGN TEMPERATURE AND PRESSURE ARE CONSISTANT
WITH THESE VALUES.

9- PUMP SHALL BE DISMANTLED TO INVESTIGATE THE CAUSE OF ANY UNSATISFACTORY PUMPS RUNNING TEST.

10- EXISTING INSTALLED PUMP IS EQUIPED WITH CONTROLLED SPILL BACK VIA A CONTROL VALVE. VENDOR SHALL CONFIRM THE MINIMUM

ENGG./DATE

(DESIGN AGENCY)

DESIGN CERTIFICATION

REQUIRED (SAUDI ARAMCO)

4- REFER FOLLOWING DOCUMENTS (PART OF REQUISITION)

CONTINUOUS FLOW.

11- VENDOR SHALL COMPLY WITH ADDITIONAL REQUIREMENTS PROVIDED IN THE REQUISTION.

12- EXISTING MATERIALS DESIGNATION ARE PER JIS STANDARD. UPGRADED COMPONENT MATERIALS SHALL COMPLY WITH LATEST ARAMCO STD.
MATERIAL CODE HKA2. VENDOR SHALL CONFIRM THE SUITABILITY.

13- VENDOR SHALL SELECT SUB-VENDOR FOR EQUIPMENT AND MATERIALS FROM ARAMCO REGULATED SUPPLIER LISTS.

15- PUMP SHALL BE RE-PAINTED PER ARAMCO STANDARD SAES-H-001.


16- ALL PROCESS WETTED METAL COMPONENTS OF SEAL SHALL BE 316L SS EXCEPT FOR BELLOWS. BELLOWS MATERIAL SHALL BE INCONEL 625 OR
718. METAL PARTS NOT IN CONTACT WITH THE MEDIUM PUMPED SHALL BE 316 SS. THE SURFACE OF SHAFT SLEEVES SHALL BE OVERLAID UNDER
THE DYNAMIC SECONDRY SEALING ELASTOMERS IN CONTACT WITH THE PUMPED LIQUID. THE OVERLAY SHALL BE OF A WEAR RESISTANT MATERIAL
SUCH AS STELLITE AND TUNGSTEN CARBIDE.
DRAWING COMPLETION CERTIFICATE NO.

AND CERTIFICATION REQUIREMENTS, PER SAEP-334, UNDER

IS COVERED, FOR ALL APPROVAL


THIS REVISION NO.

REVISION VALIDATION

14- EXPECTED MINIMUM MOTOR POWER RATING FOR NEW PROCESS CONDITIONS IS 350 kW. VENDOR SHALL CONFIRM.

17- BEARING HOUSING , IF SUPPLIED, OF THE OIL LUBRICATED PUMPS SHALL BE INSTALLED WITH THE FOLLOWING:
- CONSTANT LEVEL OILER
- LEVEL SIGHT GLASS
- DRAINABLE SIGHT GLASS(INSTALLED UNDER THE BEARING HOUSING TO DRAIN CONDENSED WATER FROM HE BEARING HOUSING
VENDOR SHALL ALSO PROVIDE PROVISIONS FOR PURGE OIL MIST LUBRICATION.
18- ALL SEAL SYSTEMS SHALL COMPLY WITH ARAMCO SPECIFICATION 31-SAMSS-12.
19- VENDOR SHALL PROVIDE THE COOLING WATER REQUIREMENT BASED ON NEW PROCESS CONDITIONS.
20-REFER PROJECT SPECIFICATION "PP-E01706 BASIC ENGINEERING DESIGN DATA" APPENDED WITH REQUISITION.

DATA SHEET FOR API CENTRIFUGAL PUMPS

DWG. TYPE

HEAVY VACUUM GAS OIL(HVGO) PUMPS (Z09-P13A/B)


AREA H- VACUUM UNIT-3, RIYADH REFINERY
RIYADH

PLANT NO.

INDEX

DRAWING NO.

SHT.NO

REV.NO.

Z09

VE-XXXXXX

6 OF
6

DAT

SAUDI ARABIA

EKRD/2616-1110.XLS