Professional Documents
Culture Documents
Version:
Issue Date:
Review By Date:
Owned By:
Authorised By:
1.1
August 2006
June 2008
Engineering Manager D & P
Executive Manager D & P
DESIGN OF STRUCTURES
REVISION TABLE
Version No
Date of Revision
1.0
June 2006
1.1
August 2006
Details of Amendment
Initial Release
Numbering Changed to represent previous system used
The above table lists in summary the amendments which have been made with most recent issues of this standard.
The table is updated with each re-issue. The latest amendments within the documents are marked with a change
indicator (|) in the outer margin.
CONTACT
This standard is the responsibility of the
Development and Projects Division, ElectraNet.
Please contact the indicated owner of the standard
with any inquiries.
ElectraNet
52-55 East Terrace, Adelaide, South Australia 5000
PO Box 7096, Hutt Street Post Office,
Adelaide, South Australia 5000
Ph (08) 8404 7966, Fx (08) 8404 7104
LI M I T AT I O N O F L I A B I LI T Y A N D
D I S C LA I M E R O F W A R R AN TY
ElectraNet makes no representation or warranty as
to the accuracy, reliability, completeness or
suitability for particular purposes of the information
in this document. ElectraNet and its employees,
agents and consultants shall have no liability
(including liability to any person by reason of
negligence or negligent misstatement) for any
statements, opinions, information or matter
(expressed or implied) arising out of, contained in or
derived from or for any omissions from the
information in this document, except in so far as
liability under any statute cannot be excluded.
2006 ElectraNet Pty Limited trading as ElectraNet. No part of this document may be reproduced
or copied in any form or by any means (graphic, electronic, mechanical, including photocopying,
recording, taping or information retrieval systems) without the prior written permission of ElectraNet.
LCM04
ElectraNet
TABLE OF CONTENTS
4.1
SCOPE ........................................................................................................................................................3
4.2
GENERAL..................................................................................................................................................3
4.3
4.4
DESIGN CERTIFICATION.....................................................................................................................3
4.5
TOWER DESIGN......................................................................................................................................4
4.6
POLE STRUCTURES...............................................................................................................................4
4.7
FOUNDATION DESIGN..........................................................................................................................4
4.8
Version: 1.1
Page 2 of 5
ElectraNet
LCM04
4.1 SCOPE
This section provides for the design of structures to be used on this contract.
4.2 GENERAL
Notwithstanding any approval given by the Superintendents, the Contractor shall be responsible for
all aspects of strength and functionality of structures and foundations for which they have carried out
the design.
The Contractor shall supply copies of all calculations and drawings to the Superintendents three (3)
weeks before commencement of manufacture. Manufacture shall only proceed after approval by the
Superintendent.
The Superintendent retains the right to halt the manufacture and/or construction process at any time
without penalty to the Superintendent, to require the Contractor to rectify the design and any
manufacture or construction, if the submitted design is found at any time not to comply with this
Specification.
The Contractor is responsible to ensure the structures comply with the Specification. The approval of
any design by the Superintendents does not imply that the design complies in all requirements and
shall not relieve the Contractor of design responsibility.
Contractor shall adhere to the electrical and climbing requirements shown on any drawing or text in
the Specification as well as the structural requirements.
The structures designed by the Contractor shall be designed for a service life of at least 50 years with
no required maintenance. The Contractor may be required to provide supportive evidence of this
regarding any feature the Contractor is responsible for.
Where this Specification is in contradiction with the Australian Standards, this Specification shall
prevail.
For details on the design of structures refer to the Line Design Manual documents (LDM230 series
documents).
Version: 1.1
Page 3 of 5
LCM04
ElectraNet
If tie-beams are utilised within the design, they are required to be self-supporting and shall be
positioned so as not to pond water;
The foundations should be designed for the tower to be loaded in any direction and hence the
foundation under any leg should be capable of resisting both the maximum uplift and the
maximum compression;
The foundation design shall be such that no concrete construction joints exist below ground
level unless provision is made to be able to clean and scabble the joint and maintain the joint
free of soil and water during construction;
The ability of the pile system and soil interaction to resist lateral loads shall not be assumed
without justification from the soil tests;
The design needs to consider that structures are sensitive to differential horizontal and vertical
movement between the tower legs. The combined long term and ultimate load differential
movement between any tower leg foundation shall be limited to a maximum of 20mm
horizontally and 12mm vertically. At the request of the Contractor, the Superintendent is
Version: 1.1
Page 4 of 5
ElectraNet
LCM04
willing to discuss this limitation. It shall remain the Contractors responsibility to achieve
fitness for purpose for any footing design provided by the Contractor.
For details on foundation design refer to the Line Design Manual documents (LDM230 series
documents).
Geotechnical investigations have been carried out at random sites in the area and details are
contained in the report appended to this Specification.
Pile foundation systems have been designed by the Superintendent. Design loadings are
provided to enable alternative designs to be prepared by the Contractor. These designs may be
of any pile type suitable for the varying site conditions. It should be noted that piling in
mangrove areas is required to provide minimum disturbance of mangroves and the surrounding
vegetation and any excavated material will need to be removed from site and not discharged at
the pile location.
All piling designs shall be in accordance with the geotechnical consultant's recommendations
and comply with the requirements of Australian Standard AS2159-1995.
Version: 1.1
Page 5 of 5