General Requirements for a FEED study and PTE preparation

The purpose of a FEED study is to ensure that all main elements of the chosen design
solution are defined and that the scope of the whole job is understood sufficiently
such that a target cost estimate and schedule can be prepared.
The following list provides a guideline to discipline input required for a generic
modification including long lead equipment items. At the Kick-Off meeting,
deliverables, which are relevant to each specific modification, should be agreed.
Piping:

Input to BoD, equipment purchase specification and FEED report.

Produce P&IDs for FEED / HAZOP (Issued as HAZOP comments incorporated)

Offshore surveys

Produce piping layouts, composite ISOs and material estimates (Prelim based on
FEED P&IDs)

Produce valve schedules, line lists and tie-in schedules (Based on FEED P&IDs)

Preliminary stress ISOs and analysis (Critical lines only).

Technical bid evaluation of equipment.

Instruments:

Input to BOD, equipment purchase specification and FEED report.

Technical Bid evaluation of equipment

Prepare data sheets for new actuated valves and issue enquiries to obtain accurate
costs.
Prepare ESD, F&G and Control System Specification (Issued IDC/Comments
incorporated)
Prepare Instrument schedule (Based on FEED P&IDs)
Establish impacts on metering package (if applicable enquiry issued for budget
costing).

Prepare C&Es, Block diagrams and BOMs.(include HAZOP comments)

Attend HAZOP / SIL

Mechanical:

Input to BOD and FEED report.

Produce Mechanical data sheets and specifications for the equipment package(s).

Issue initial enquiries for the equipment to approved suppliers

Perform a technical bid evaluation and prepare formal recommendation.

Update data sheets and specifications for purchase

Process:

Input to equipment purchase specification and FEED report

Prepare Process BOD

Produce P&IDs and ESD Block Logics for FEED / HAZOP (Issued HAZOP
comments incorporated)
Resolve HAZOP actions.(Outstanding actions to be identified)
Provide Data sheet input for equipment and control valves, PSVs and general
Instrumentation.(Issued for enquiry)

Perform line Hydraulic checks

Prepare line lists including line sizing (Based on FEED P&IDs)

Produce a control and operating philosophy (Issued IDC/Comments incorporated)

Prepare Shutdown Philosophy.(Issued IDC/Comments incorporated)

Technical Bid evaluation of equipment.

Electrical:

Input to BOD, equipment purchase specification and FEED report.

Technical Bid evaluation of equipment

Perform reviews of load impact on switchboards

Perform a review of impacts on starting the equipment motors.

Establish modifications required to the existing switch gear and issue prelim
enquiries to establish delivery and cost. To include PDC modifications and
offshore installation and commissioning costs.
Review Lighting and trace heating requirements.
Perform an offshore Survey to establish cable routings and modifications required
(including instrument cables).

Produce prelim Block diagrams, Cable routings and BOM.

Review interface requirements with PDC, PCS & ESD

Weight estimate

Safety:

Input to BOD, equipment purchase specification and FEED report.

Technical Bid evaluation of equipment

Perform a review of active fire protection requirements and in particular deluge


studies to include Hydraulic analysis to assess impacts fire water supply.

Prepare prelim firewater P&ID

Perform ventilation reviews.

Prepare prelim Hazardous area drawings

Prepare Prelim F&G block logics

Perform review of escape route impacts.

F&G Philosophy

SCE check sheets

Attend HAZOP / SIL as required.

Structural:

Input to BOD, equipment purchase specification and FEED report.

Technical Bid evaluation of equipment

Perform an offshore survey to establish support and installation requirements for


the new equipment
Prepare preliminary layout drawings and installation schemes as required.
Perform structural integrity checks and identify any strengthening requirements.
Liaison with custodian of integrity models will be required
Prepare preliminary weight control sheets.

Construction:

Input to FEED report.


Review of the proposals made during FEED with a view to ensuring best practices
are adopted in the design solution for the benefit of reducing cost during the
construction phase of the project.
Prepare Pre-Commissioning Strategy

Maintenance :

Provide estimate for producing PMRs, spares lists and SAP input as part of detail
design deliverable.
Equipment maintainability reviews (if applicable).

All Disciplines :
In addition to the above all disciplines will produce CTRs (as per agreed WBS) and
input to costing as required to produce a level 4 cost estimate for the P phase of the
project.
Bidders lists for all major equipment packages to be agreed.