You are on page 1of 14

Data Sheet for work study

Mixing & Laying Gr. 20 Concrete for Drain, ST1-047


Name of Road Project: Kiriella -Nedurana-Eheliyagoda Road
Date: 10/01/2016

Contractor: RR Constructions

Location/ Chainage: 9+122- 9+138


Length of Concreting: 16X2
(Drain Length)
2 drain Walls
Width:

0.1

Starting time:

Height of concreting: 0.6

Sketch:

10.55 A.M

End time:
(At given Length)

Wether Condition:
Sunny
Labour & Equipments
Mason(Nos)

Labour S/Sk(Nos)
Labour(U/Sk)(Nos)

Cement(Bags)
Aggregate (19mm),(Cu.m)
Sand(Cu.m)
Hire of Concrete Mixer(Rs./day)
Hire of Poker vibrator(Rs./day)
If readymix Concrete Used,
Readymix Concrete(Rs./ Cu.m)
Hire for Lorry with Concrete Drum(Rs./day)
(If Applicable)

1.92

12.04PM

Time Study Sheet


Element

Rate

Clock Time

Observed Time

Concrete Laying
Mason-2

100%

10.55-12.04

69

Labor U/Sk-4

100%

10.55-12.04

69

11.01-12.04

63

Poker Vibrator

Consider the data taken at Kiriella-Eheliyagoda Road (9+122-9+138)


Skilled Labor A (Mason)
Observed Time
Performance Rate
By using Equation (1)
Normal Time

=
=
=
=
=
=
=
=
=

PFD Allowance
Standard Time
Total time for Mason 2Nos.

Unskilled Labor
Observed Time
Performance Rate
By using Equation (1)
Normal Time

=
=
=
=
=
=
=

PFD Allowance
Standard Time
Total time for U/Sk Labor 4Nos.

Length of Concreted drain (2 walls)


Average Height of walls
Thickness of walls
Concrete quantity

=
=
=
=
=
=
=
=

2
69
100%
69*1
69 min
13%
69x (1+0.13)
77.97 min
77.97x2
155.94 min
0.325 days
4
69 min
100%
69x1
69 min
14%
69x (1+0.14)
78.66 min
78.66x4
314.64 min
0.656 days
16*2
32
0.6
0.1
32x0.6x0.1
1.92 m3

Data for 1.92m3 of concrete


Mason (Sk/A)
Labor U/Sk
Allow 2.5% Labor for tools
Hire of Poker Vibrator
Ready Mix Concrete (G20)
Cost per 1.92 m3
Cost per 1 m3

Quantity Unit
0.325 Day
0.656 Day
1.05 Hr
1.92 m3

Rate
1350
1050
290
12970

Amount
438.58
688.28
28.17
304.50
24902.40
26361.93
13730.17

Data for 8.5m3 of concrete


Mason (Sk/A)

Quantity Unit
1.438 Day

Rate
1350

Amount
1941.64

Labor U/Sk
Allow 2.5% Labor for tools
Hire of Poker Vibrator
Ready Mix Concrete (G20)
Cost per 8.5 m3
Cost per 1 m3

2.902 Day

1050

4.648 Hr
8.5 m3

290
12970

3047.05
124.72
1348.05
110245.00
116706.45
13730.17

Data Sheet for work study


Mixing & Laying Gr. 20 Concrete for Drain, ST1-047
Name of Road Project: Eheliyagoda-Dehiowita Road
Date: 07/12/2015
Contractor: KD Ebert Silva Holdings
Location/ Chainage: 5+172- 5+186
Length of Concreting: 14X2
(Drain Length)
2 drain Walls
Width:

0.1

Starting time:

Height of concreting: 0.7

Sketch:

9.41 A.M

End time:
(At given Length)

Wether Condition:
Sunny
Labour & Equipments
Mason(Nos)

Labour S/Sk(Nos)
Labour(U/Sk)(Nos)

Cement(Bags)
Aggregate (19mm),(Cu.m)
Sand(Cu.m)
Hire of Concrete Mixer(Rs./day)
Hire of Poker vibrator(Rs./day)
If readymix Concrete Used,
Readymix Concrete(Rs./ Cu.m)
Hire for Lorry with Concrete Drum(Rs./day)
(If Applicable)

1.96

10.32AM

Time Study Sheet


Element

Rate

Clock Time

Observed Time

Concrete Laying
Mason-2

110%

9.41-10.32

51

Labor U/Sk-5

95%

9.41-10.32

51

9.50-10.32

42

Poker Vibrator

Consider the data taken at Eheliyagoda-Dehiowita Road (5+172-5+186)


Skilled Labor A (Mason)
Observed Time
Performance Rate
By using Equation (1)
Normal Time
PFD Allowance
Standard Time
Total time for Mason 2Nos.

Unskilled Labor
Observed Time
Performance Rate
By using Equation (1)
Normal Time

2
51
110%

=
=
=
=
=
=

51*1.1
56.1 min
14%
69x (1+0.14)
63.95 min
63.95x2
127.91 min
0.266 days
5
51 min
95%

=
=
=
=
=
=
=

PFD Allowance
Standard Time
Total time for U/Sk Labor 5Nos.

Length of Concreted drain (2 walls)


Average Height of walls
Thickness of walls
Concrete quantity

=
=
=

=
=
=
=
=
=
=
=

51x0.95
48.45 min
14%
48.5x (1+0.14)
55.233 min
55.23x5
220.932 min
0.460 days
14*2
28
0.7
0.1
28x0.6x0.1
1.96 m3

Data for 1.96m3 of concrete


Mason (Sk/A)
Labor U/Sk
Allow 2.5% Labor for tools
Hire of Poker Vibrator
Ready Mix Concrete (G20)

Quantity Unit
0.266 Day
0.460 Day
0.7 Hr
1.96 m3

Rate
1275
975
250
12200

Amount
339.76
448.77
19.71
175.00
23912.00

Cost per 1.96 m3


Cost per 1 m3

24895.24
12701.65

Data for 8.5m3 of concrete


Mason (Sk/A)
Labor U/Sk
Allow 2.5% Labor for tools
Hire of Poker Vibrator
Ready Mix Concrete (G20)
Cost per 8.5 m3
Cost per 1 m3

Quantity Unit
1.156 Day
1.996 Day
3.036 Hr
8.5 m3

Rate
1275
975
250
12200

Amount
1473.43
1946.19
85.49
758.93
103700.00
107964.04
12701.65

Observed Time

69
69
63

Observed Time

51
51
42

-5+186)

You might also like