TIMES

DIM

8.1
18.98

RESULT

Description
a) Excavation 200mm top soil (m2)
Width :
7500 + 600 = 8100mm
Length:
18375 + 0600 = 18975mm

[Excavation topsoil 200mm thick from


ground level transporting and dumping
153.74 surplus soil from soil.]

UNIT

m2

b) Excavation Trench (m3)


Length: 600mm
Width : 600mm
Depth :
875 + 450 + 50 - 200 = 1175mm
14

Trench excavation for pad foundation not


exceeding 1.5m deep, backfilling;
compacting; dumping surplus soil from site

0.6
0.6
1.18
5.95

m3

c) Excavation Ground Beam


i) Size Beam : 200 x 600
5

Length : 5800mm
Width : 200mm
Thickness : 600mm

5.8
0.2
0.6
3.48
4

m3
Length : 2900mm
Width : 200mm
Thickness : 600mm

2.9
0.2
0.6
1.74
2

m3
Length : 2400mm
Width : 200mm
Thickness : 600mm

2.4
0.2
0.6
0.576

m3

TIMES

DIM

RESULT

2
4.8
0.2
0.6

DESCRIPTION
Length: 4800mm
Width : 200mm
Thickness : 600mm

1.15
2

UNIT

m3
Length : 3825mm
Width : 200mm
Thickness: 600mm

3.83
0.2
0.6
0.92
2

m3
Length : 1500mm
Width: 200mm
Thickness : 600mm

1.5
0.2
0.6
0.36
2

m3
Length : 1425mm
Width : 200mm
Thickness: 600mm

1.43
0.2
0.6
0.34

m3
ii) Size beam: 200 x 500
Length : 15600mm
Width : 200mm
Thickness: 500mm

1
15.6
0.2
0.5

m3
1.56
iii) Size Beam : 200 x 450

Length: 2775mm
Width : 200mm
Thickness: 450mm

2.78
0.2
0.45
0.5
6
1.65
0.2

m3
Length : 1650mm
Width: 200mm
Thickness: 450mm

0.45
0.89

TIMES

DIM

RESULT

m3

DESCRIPTION
a) DPM: hardcore for ground slab,

UNIT

200mm thick of hardcore


area of slab= length x width
Thickness= 275mm
18.38
7.15
0.28

[Filling to make up level average 300mm


thickness with
hardcore of clean hard broken stones
36.8 obtained off site]
b) DPM for ground slab,

m3

length
2400+4800+3825+1500+1650+1425+2775
= 18375mm
width= 2900+2900+1350
=7150mm
depth of excavation= 200mm
18.38
7.15
131.42

m2

QTY

TIMES

DIM

RESULT

DESCRIPTION
1) Foundation
Length:
600+2(450)-(6X50)= 1200mm

2/14/12/
1.2
403.2
2) Stump
153.74
Stump C1

4/8/
2.61

Length:
875+450-50+600+275-(2x12)+280+200
83.52 2606mm
link:
125x4 - 8(25) = 300mm

11/8/

no of link =
(875+450-50-2(16))/125 + 1= 11 nos

0.3
5.95

26.4
Stump C2
2/6/

Length:2606mm
2.61
31.32
link:
(100x2) + (450x2) - (8x25) = 900mm

3.48 2/11/

no. of link:
875 + 450 - 50 - (2x12) / 125 + 1 = 11 nos

0.9
19.8

Stump C3
1.74 4/6/

Length: 2606mm
2.61
62.64
Link:
(125x2) + (230x2) - (8x25) = 510mm

0.576 4/11/

no. of link:

0.51
QTY

TIMES

DIM

875 + 450 -50 - (2x12)/ 125 +1 = 11 nos


22.44
RESULT

DESCRIPTION
3) Beam
Beam size : 200 x 600
Length : 5800 - (2x25x5) + (2x200) = 5950

4/5/
5.95
1.15

119
Link:
(200x2) + (600x2)-(8x25)= 1400
5/30/

0.92

no. of link:
5800/200 + 1 = 30 nos

1.4
210
4/4/

Length: 2900 - (2x25x4) + (2x200) = 3100


3.1
49.6

0.36
Link:
(200x2) + (600x2) - (8x25) = 1400
4/16/

no. of link:
2900/200 + 1 = 16 nos

1.4
0.34

89.6
4/2/

Length: 3820 - (2x25x2) - (8x25) = 3520


3.52
28.16

1.56 2/20/
1.4

Link = 1400
No. of Link:
56 3820/200 + 1 = 20 nos

4/2/

Length: 2400 - (2x25x2) - (8x25) = 2100


2.1
16
Link: 1400
No. of link :
2100/200 + 1 = 12 nos

0.5 2/12/
1.4
33.6

0.89

QTY

TIMES

DIM

RESULT

14

DESCRIPTION
a) Formwork for Footing
Length
600 x 4 = 2400 mm

2.4
0.45

15.12 Depth = 450 mm


b) Formwork for stump
36.8

Stump C1
8

Length:
125 x 4 = 500mm

0.5
0.88

3.52 Depth: 875mm


Stump C2
2

Length: 1100mm
Depth: 875mm

1.1
0.88
1.94
131.42

Stump C3
4

Length: 710mm
Depth: 875mm

0.71
0.88
2.5

a) Ground beam formwork


Beam size: 200 x 600
length = 5800 - 2(125) /2
= 5660mm
length = 5660 x 2
= 11320mm
depth = 600mm
5
11.32
0.6

33.96 [formwork for beam]


length = 2900 - 2(125)/2
= 2780mm
length = 2780 x 2
= 5560mm
depth = 600mm

UNIT

QTY

TIMES
2/4/

DIM

RESULT

4.5
36

403.2 2/25/
1.4
70
2/4/
1.2
9.6

83.52 2/9/
1.4
25.2
2/4/
1.13
9.04
26.4
2/8/
1.4
22.4

31.32
2/4/
2.48
19.84
19.8
2/15/
1.1
33
6/4/

62.64

1.35
32.4

6/10/

1.1
UNIT

22.44
QTY

TIMES

DIM

66
RESULT

4/1/
15.35
m

119

51.4
4/79/
0.51
155.04

2210

49.6

89.6

89.6

56

16

33.6

UNIT

QTY

TIMES

DIM

RESULT

4
5.56
0.6
13.34
m2

15.12

7.34
0.6
8.81

m2

3.52

2
4.56
0.6
m2

1.94

5.47

2
m2

2.5

9.36
0.6
11.23

2
2.76
0.6
3.31

m2

33.96

DESCRIPTION
Length: 4800 - (2x25x2) - (8x25) = 4500mm

UNIT

QTY

TIMES

DIM

36

Link: 1400mm
No. of link:
4800/200 + 1 = 25 nos

14/
70

0.36
0.45

Length:1500 - (2x25x2) - (8x25) = 1200mm


m

9.6

Link: 1400
No. of link:
1500/200 + 1 = 9 nos
25.2 14/

0.03
0.875

Length: 1425 - (2x25x2) -(8x25) = 1125mm


m

9.04

Link: 1400mm
No.of link:
1425/200 + 1 = 8 nos
22.4
Beam Size : 200x450
Length: 2775 - (2x25x2) - (8x25) = 2475mm
m

19.84

Link: 400+900 - (8x25) = 1100


no. of link:
2775/200 + 1 = 15

5.55
33

Length: 1650 - (6x25x2) - (8x25) = 1350mm


m
Link: 1100mm
No. of link:

32.4

1650/200 + 1 = 10
66
DESCRIPTION
Beam Size : 200x500

UNIT

QTY

TIMES

Length: 15600 - (1x25x2) - (8x25)=15350mm

4.93
m

Link: 510
No. of link:
15600/200 + 1 = 79

DIM

51.4

155.04
14
0.36

DESCRIPTION

UNIT

QTY

TIMES

DIM
2
2.6
0.6

[formwork for beam]


length = 3820 - 2(125)/2
= 3670mm
length = 3.67 x 2
= 7340mm
depth = 600mm

m2

3.34

2
5.3
0.45
[formwork for beam]
length = 2400 - 2(125)/2
= 2280mm
length = 2280 x 2
= 4560mm
depth = 600mm

m2

8.81

6
3.06
0.45
[formwork for beam]
length = 4800 - 2(125)/2
= 4680mm
length = 4800 x 2
= 9360
depth = 600mm

m2

5.47

30.96
0.5
[formwork for beam]
length = 1500 - 2(125)/2
= 1380mm
length = 1380 x 2
= 2760mm
depth = 600mm

m2

11.23

[formwork for beam]

m2

3.31

length = 1425 - 2(125)/2


= 1300mm
length = 1300 x 2
= 2600mm
depth = 600mm

RESULT

DESCRIPTION
a) concrete work foundation
Area of pad footing
length x width = 0.6 x 0.6
= 0.36m

[pouring the concrete grade 25 into the


formwork for pad
footing and curing 7-24 days until it
2.27 strengths]
b) concrete work stump

UNIT

QTY

m2

m3

2.27

m3

0.37

m3

5.55

area of stump
length x width = 0.125 x 0.23
= 0.03m
[pouring the concrete grade 25 into the
formwork of stump
0.37 and all the reinforcement in it]
c) concrete work ground beam
volume of horizontal beam
15.60 x 0.2 x 0.5 = 1.56 m
volume of horizontal beam
(15.6 + 15.6 ) x 0.2 x 0.6 = 3.74m
volume of horizontal beam
2.775 x 0.2 x 0.45 = 0.25m
Total length for horizontal beam
1.56 + 3.74 + 0.25 = 5.55m
[pouring the concrete grade 25 into the
formwork foe beam
5.55 not exceed the level of beam formwork]
c) concrete work ground beam
volume of vertical beam = 7.15 x 0.2 x 0.45
7.15 x 0.2 x 0.45 = 0.64 m
volume of vertical beam
(7.15 x 5) x 0.2 x 0.6 = 4.29 m

Total length of vertical beam


DESCRIPTION
0.64 + 4.29 = 4.93 m
[pouring the concrete grade 25 into the
formwork for beam
4.93 and not exceed the volume needed]
d) concrete work lean concrete

RESULT

UNIT

QTY

m3

4.93

m2

5.04

Area of lean concrete


0.6 x 0.6 = 0.36 m

5.04 50mm of lean concrete

RESULT

DESCRIPTION

UNIT

QTY

3.12 [formwork for beam]


Beam size : 200 x 450
length = 2775 - 2(125)/2
= 2650mm
length = 2650 x 2
= 5300mm
depth = 450mm

m2

3.12

4.77 [formwork for beam]

m2

4.77

m2

8.26

m2

15.48

length = 1650 - 2(125)/2


= 1530mm
length = 1530 x 2
= 3060mm
depth = 450mm

8.26 [formwork for beam]


Beam size: 200 x 500
length = 15600 - 2(125)/2
= 15480mm
length = 15480 x 2
= 30960mm
depth = 500mm

15.48 [formwork for beam]