Informe Final Proyecto: Construccin de Sistema de Agua y

Saneamiento El Achiote, Cdigo 19200


NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
INDICE

1. COMPONENTE DE AGUA POTABLE Y SANEAMIENTO.................................................................. 2


2. DESCRIPCIN DE LOS ESTUDIOS E INVESTIGACIONES REALIZADAS......................................... 7
3. CRITERIOS PARA EL DISEO HIDRULICO.................................................................................. 5
4. ESTUDIOS Y DISEOS FINALES DE LOS ELEMENTOS DEL SISTEMA......................................... 13
5. CONCEPTUALIZACIN DEL PROYECTO DE AGUA POTABLE..................................................... 24
6. COMPONENTE DE SANEAMIENTO................................................................................................ 2
7. DESCRIPCION DE LOS ESTUDIOS E INVESTIGACIONES REALIZADAS......................................... 3
8. CONCEPTUALIZACION DEL PROYECTO DE SANEAMIENTO....................................................... 14
9. TAKE OFF Y PRESUPUESTO......................................................................................................... 1
10. COSTOS DE INVERSIN, OPERACIN Y MANTENIMIENTO......................................................... 2
11.

PLANOS..................................................................................................................................... 3

12. ANEXOS..................................................................................................................................... 1

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe Final Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote, Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
1. COMPONENTE DE AGUA POTABLE Y SANEAMIENTO
1.1 INTRODUCCION GENERAL
El Gobierno de Reconciliacin y Unidad Nacional de Nicaragua, ha establecido la Poltica de
aumentar la cobertura efectiva de abastecimiento de agua y saneamiento 1, mejorar los servicios,
promoviendo el uso racional de este recurso tanto en las reas urbanas como en las rurales.
Estableciendo metas de manera comprometida y firme en su Programa de desarrollo Humano
Sostenible.
El Gobierno de Reconciliacin y Unidad Nacional de Nicaragua ha firmado un nuevo Convenio de
prstamo con el Banco Mundial para financiar el Proyecto de Abastecimiento de Agua y
Saneamiento Rural de Nicaragua. (PRASNICA) por un monto de US$ 20 millones de dlares,
dedicado exclusivamente al subsector de abastecimiento de agua y saneamiento rural en aras
beneficiar en dicha cobertura a la poblacin ms excluida como son las comunidades que vive en
extrema pobreza y comunidades indgenas, tnicas y afrodescendientes de todo el territorio
nacional. El Proyecto de Agua y Saneamiento (PRASNICA) incluye varios componentes, entre los
cuales se encuentra la preparacin de los estudios y diseos de los sub proyectos.
Actualmente este nuevo programa de PRASNICA, tiene como objetivo incrementar los servicios y
cobertura de agua y saneamiento rural en un 1 % anual durante los cinco aos de duracin del
proyecto. El proyecto financiara aproximadamente 233 sub proyectos distribuidos en todo el pas.
El proyecto con Cdigo 19200 Construccin de Sistema de agua y saneamiento El Achiote
forma parte del plan de Inversin Municipal de la Alcalda de Bocana de Paiwas y responde a la
necesidad planteada por las comunidades beneficiadas como una de las necesidades ms sentidas,
por lo que la alcalda Municipal ha solicitado al Fondo de Inversin Social de Emergencia (NUEVO
FISE), asistencia tcnica y financiera para resolver la problemtica del abastecimiento de agua. El
NUEVO FISE, atendiendo la peticin, ha asignado fondos de inversin, que permita llevar a cabo las
obras para resolver el problema en el marco del Proyecto PRASNICA.
En este contexto el Nuevo FISE ha contratado a la empresa CONDISA con el fin de que realice los
diseos finales del proyecto y el desarrollo del componente social del mismo.
1.2 OBJETIVOS DEL PROGRAMA PRASNICA
Desarrollar todos los estudios y actividades requeridos y proveer la documentacin necesaria y suficiente
para que los subproyectos del rea asignada (o municipio) puedan pasar a la etapa de ejecucin. Todo
esto en estrecha coordinacin con el facilitador social que acompaa a la comunidad durante el ciclo del
proyecto.

Programa Econmico-Financiero 2007-2010, Agosto 2007

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe Final Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote, Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
1.3 OBJETIVOS DEL ESTUDIO

Determinar la demanda de agua potable y saneamiento, capacidad y disposicin de pago en cada


comunidad con base en el estudio socioeconmico, censo poblacional, taller de autodiagnstico
participativo, diagnstico situacional y censo poblacional.

Definir la tasa de crecimiento demogrfico para realizar las proyecciones de poblacin, la oferta y
demanda de agua de conformidad con las dotaciones normadas para el dimensionamiento del
sistema.

Definir la necesidad de instalaciones de saneamiento y proponer las opciones tecnolgicas


adecuadas que sern presentadas a consideracin de la comunidad en asambleas de
concertacin.

Determinar la oferta de agua para cada comunidad mediante el estudio de fuentes potenciales.
(Capacidad de la fuente de abastecimiento).

Formular opciones tcnicas de solucin y nivel de servicio para cada sub proyecto, incluyendo
costos de inversin, operacin y mantenimiento de cada una, adems del clculo de tarifas por
prestacin del servicio, evaluacin ambiental de emplazamiento para las principales estructuras.
Se deber dimensionar el tipo y cantidad de instalaciones sanitarias de acuerdo a la demanda
determinada por la comunidad demandante considerando las condiciones tcnicas del sitio.

Adems deber incluir en los costos del proyecto la dotacin de agua y saneamiento en las
puestos de Salud y en caso de las Escuelas que existan en la comunidad, aplicando las Normas y
Criterios para el Diseo de Establecimientos Escolares, aplicando la norma de batera sanitaria
para educacin primaria, establecido por el Ministerio de Educacin MINED 2008.

Presentar y negociar alternativas con la comunidad en asamblea preliminar de concertacin


comunitaria convocada y dirigida por la firma consultora. En esta asamblea se presentarn a
consideracin de la poblacin al menos tres opciones de abastecimiento de agua y saneamiento
viables para su utilizacin en la comunidad, indicando los costos de ejecucin de cada opcin
tcnica y estimaciones de tarifa mensual para la operacin y mantenimiento del sistema.

Desarrollar los diseos finales de la opcin seleccionada (de soluciones de saneamiento, obras
hidrulicas, obras de captacin, sistemas de tratamiento y desinfeccin, almacenamiento y de
vulnerabilidad de los sistemas). En el caso del Saneamiento se dispondr del Men de Opciones
bsicos de Saneamiento (para eliminacin de excretas: letrinas VIP, tasa rural con cierre hidrulico,
inodoro ecolgico. Sistemas de tratamiento: tanque sptico, biodigestor, humedal o biojardinera.
Disposicin final del efluente: campo de infiltracin, foso de absorcin)

Elaborar presupuesto de obras, soluciones de saneamiento (letrinas, inodoros ecolgicos, duchas,


lavamanos, lavaderos, fosos de absorcin, campos de infiltracin), planos, especificaciones
tcnicas, manuales y planes de operacin y mantenimiento del sistema.
3
FIRMA CONSULTORA: CONDISA
Diseo: Ing. Mirta Violeta
Bravo M.

Informe Final Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote, Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

1.4 SITUACION ACTUAL DE ABASTECIMIENTO DE AGUA


1.4.1

SITUACION ACTUAL DE ABASTECIMIENTO DE AGUA POTABLE

La comunidad de El Achiote est formada por 22 viviendas, las cuales para abastecerse de agua
hacen uso de algunos criques existentes en las propiedades y un buen nmero de viviendas hacen
uso de un manantial ubicado a unos 40m de la iglesia evanglica.
Las fuentes de aguas utilizadas si bien satisfacen las demandas de agua de consumo, aseo
personal y limpieza, no es agua potable, debido a que las obras de captacin no cuentan con
ninguna proteccin y al agua no es clorada antes de su ingesta.
A continuacin se presentan algunas fotografas de las fuentes de agua de donde actualmente se
abastece la poblacin.
FOTOS DE FUENTE MANANTIAL DE IGLESIA EVANGELICA

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe Final Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote, Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Manantial de agua ubicado a 40m de la Iglesia Evanglica, propiedad de la Iglesia y de donde se


abastecen gran parte de la comunidad, fecha de toma Abril 2012, coordenadas UTM 726794.748 y
1415824.597, Elevacin 342.25msnm.

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe Final Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote, Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
1.5 JUSTIFICACION DEL PROYECTO DE AGUA Y SANEAMIENTO
Actualmente la comunidad se abastece de agua para consumo, limpieza y aseo personal de fuentes
de agua que no cuentan con proteccin sanitaria tales como: ojos de agua, pozo excavado y criques.
Estas pequeas fuentes de agua son de uso comunal y se localizan a distancias promedios de unos
200m a 300 m de las viviendas, es importante destacar que ninguna de las fuentes de agua
utilizadas es de bien comunal, existen solo dos fuentes de abastecimiento de propiedad privada de
algunos miembros de la comunidad, que comparten el vital lquido con otros miembros de la misma.
No existen conflictos en cuanto al uso de las fuentes de abastecimiento. Sin embargo, las fuentes
carecen de medidas de proteccin que garanticen la potabilizacin del agua, tambin el agua al ser
transportada en bidones sin tapa es manipulada inadecuadamente ocasionando la contaminacin de
la misma.
En la comunidad existe el fecalismo al aire libre, esta prctica es una fuente de contaminacin de las
aguas superficiales. El consumo de agua no potable por parte de los pobladores trae como
consecuencia la ocurrencia de enfermedades de origen hdrico como parasitosis y diarrea, siendo
los ms afectados la poblacin infantil.
Ante esta problemtica se considera necesaria la realizacin de un proyecto que garantice el
suministro de agua potable para la poblacin y la construccin de unidades sanitarias, para la
disposicin correcta de las excretas.
1.6 RESUMEN DE OBRAS PROPUESTAS DE AGUA POTABLE Y SANEAMIENTO
Para resolver la problemtica de agua y saneamiento en la comunidad se propone la construccin
de mini acueducto por gravedad
item
1
2
3
4
5
6
7
8

Descripcin de la obra
Captacin de concreto
Filtro lento
Aireador
Tanque de abastecimiento
Lnea de conduccin de 2pvc sdr 26
Red de distribucin de 2pvc sdr 26
Red de distribucin de 1 1/2pvc sdr 26
Conexiones domiciliares
Obras de Saneamiento

FIRMA CONSULTORA: CONDISA


Bravo M.

Unidad
c/u
c/u
c/u
Gal.
m
m
m
c/u
c/u

Cantidad
1
1
1
2,500 gal.
649.80
1,759.68
1,622.44
22
22

Diseo: Ing. Mirta Violeta

Informe Final Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote, Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
2. DESCRIPCIN DE LOS ESTUDIOS E INVESTIGACIONES REALIZADAS
2.1 GENERALIDADES
El proyecto se localiza en la comunidad de El Achiote, en el municipio de Bocana de Paiwas que se
ubica en la zona Atlntica Sur del pas, La cabecera municipal es el poblado de Ubu Norte localizado
a 291 km. al suroeste de la ciudad capital Managua, y a unos 43 kilmetros del poblado de Rio
Blanco.
La superficie del municipio es de 2,374.9 Km y se localiza entre las coordenadas geogrficas latitud
Norte 1247, longitud Oeste 8507, a una elevacin promedio de 145.88msnm.
La comunidad de El Achiote se localiza a aproximadamente 20km de la cabecera municipal Ubu
Norte, el acceso es por medio de trocha de verano hasta la comunidad.
2.2 DESCRIPCIN DEL REA EN ESTUDIO
2.2.1

CLIMA

En la zona del proyecto predomina el clima monznico tropical, caracterizado por una estacin seca
de corta duracin que va de 2 a 4 meses como mximo y un periodo lluvioso el resto del ao,
durante la poca de verano el clima es caluroso a diferencia de la estacin lluviosa, poca en la que
el clima es fresco y agradable.
La zona del municipio de Paiwas presenta una precipitacin promedio anual que oscila entre los
2,400 mm y los 3,000 mm con una buena distribucin durante todo el ao. Lo que se caracteriza
como una zona eminentemente lluviosa, por lo cual se pueden distinguir tres periodos de diferencias
marcadas en la precipitacin: poca de primera, Cancula, postrera y apante.
La temperatura promedio es de 25.6 C como mnimo en los meses de enero y febrero, las
temperaturas elevadas ocurren en los meses de abril y mayo. La humedad relativa del municipio de
Paiwas oscila entre los 75% 85 %.
2.2.2

TOPOGRAFIA

El rea del municipio de Paiwas se caracteriza por presentar un relieve muy accidentado que
muestra diferencias marcadas en altitud, las que varan desde los 130 msnm en Wasayamaba hasta
los 185 msnm en la parte montaosa. Las mayores elevaciones son el cerro Copalar con una altura
de 550 msnm y el cerro la sirena con 440 msnm El rea agrcola del municipio est caracterizada
por una llanura aluvial bien drenada que oscila entre los 130 - 140 msnm.

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe Final Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote, Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
La superficie del municipio se caracteriza por presentar pendientes que corresponde en su
fisiogrfica, variando desde pendientes suaves, en las planicies hasta pendientes fuertes, en las
montaas.
Las
reas planas son
muy pocas pues las
pendientes mnimas
son de 3%, solo en
un 10% del rea
presentan
pendientes
casi
planas o ligeramente
inclinadas,
son
predominantes las
pendientes
escarpadas
y
extremadamente
escarpadas, as, el
50%
del
rea
presenta pendientes
entre el 15 y 40% y
las reas ms del 40% representan tan cerca del 40% del territorio.
El municipio est asentado sobre una planicie volcnica terciaria, presentando un relieve en general
plano con una cota promedio de 150 msnm.
Presenta una topografa ligeramente ondulada. Sus puntos ms altos son el cerro Ubu con 615
metros y Las Minitas con 510 metros. Estas alturas corresponden a las serranas de Copalar,
localizada en la parte central del territorio. Adems se cuenta con los cerros Buena Vista con 422 m,
Picachos con 404 m, El Diablo con 401m y el cerro Copalar con 390m.
Un poco ms hacia el sur encontramos la cordillera de Wapi. En la parte este en la planicie de San
Pedro, el cerro La Sirena con 508 metros, El Chele con 408 metros y el cerro Tuma con 462 metros.
Pendientes de 0 a 15 %, terreno fuertemente ondulado y se localiza en Mulukuk, Wasayamba y
San Pedro del Norte.
Pendientes de 15 a 30 %, moderadamente escarpado y se encuentran en distintas localidades del
municipio.
Pendientes de 30 a 50 %, se localizan al sur y este de Bocana de Paiwas, al sur de cerro Copalar y
al este de Perro Mocho.
Pendientes mayores de 50 %, se localizan al este y oeste del cerro Copalar.

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe Final Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote, Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
2.2.3

UBICACIN DEL PROYECTO

La comunidad de El Achiote se localiza en el municipio de Bocana de Paiwas a aproximadamente


20km de la cabecera municipal Ubu Norte, el acceso es por medio de trocha de verano hasta la
comunidad.
Figura No.1- Macro localizacin del sitio de Proyecto

EL ACHIOTE
B.DE PAIWAS

RAAS

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe Final Proyecto: Construccin de Sistema de Agua y Saneamiento El Achiote, Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
Figura No.2- Mapa de Micro localizacin del proyecto

San Pedro
del Norte
Rio Blanco

El Achiote

FIRMA CONSULTORA: CONDISA

Diseo: Ing. Mirta Violeta Bravo M.

10

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

2.3 CARACTERIZACIN DEL REA DE ESTUDIO


2.3.1

DATOS SOCIOECONOMICOS

Conformacin de la poblacin por grupos etarios.

Poblacin de la comunidad: La poblacin beneficiaria del proyecto en las comunidades la


conforman 23 familias con 101 personas, los menores de 15 aos son 52 nias, nios y
adolescentes que representan el 51.5% de la poblacin total.
La poblacin de jvenes y adultos es de 49 personas que equivale al 48.5%. La poblacin
masculina es un 44.5% y la poblacin femenina es del 55.5% con un predominio de la poblacin
femenina. El menor porcentaje de la poblacin por grupo etareo, est en las edades de 36 aos
a ms con un 18%.
SEXO
M
45
44.5%

F
56
55.5%

POBLACIN BENEFICIARIA
RANGO DE EDADES
1a5
6a15
16a25
26a35
20
32
13
18
19.5 %
32 %
12.5 %
18%

TOTAL
36 a >
18
18%

101
100%

Rango de edad: La poblacin de El Achiote es relativamente joven, ya que los menores de 25


aos representan el 64% de la poblacin total, con un predominio en las edades entre 6 a 25
aos con un 44.5%
1

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Responsable del Hogar: La responsabilidad est a cargo del 82% de padres y 18% de madres.
Hogares

Padre

18

82%

Madre

18%

Total

22

100%

Nivel de escolaridad de la poblacin.

Nivel de escolaridad: El mayor peso de escolaridad radica en el nivel de primaria con el 60%
seguido de secundaria con el 2%, analfabeto con 24% y profesional con el 0%; el mayor
predominio est en primaria y secundaria que totalizan el 97.6%.
Analfabeto
24
28%

Nivel de escolaridad (N= 316)


Primaria
Secundaria
Profesional
60
2
0
70%
2%
0%

Total
86
100%

En la comunidad El Achiote existe una escuela estatal, la que cuenta con 1 docente, mujer quien
procede de la misma comunidad. Los estudiantes provienen de la misma localidad. La cantidad de
estudiantes es de 35 nias y nios de preescolar y primaria. En el nivel preescolar hay 10 alumnos,
7 son nias (70%) y 3 (30%) nios que son atendidos por una docente. En primaria hay 25
estudiantes, son nias 10(40%) y nios 15 (60%) atendidos por 1 maestra, los estudiantes no tienen
ningn nivel organizativo. En este centro de estudio nicamente se imparte preescolar, primero,
segundo y tercer grado,
Nivel
Preescolar
Primaria
Total

Estudiantes
M
F
3
7
15
10
18
17

Total
10
25
35

%
30%
70%
100

Docentes
M
-

F
1
1

Esta escuela cuenta con aulas, la pizarra est en buen estado, tiene pupitres, no tiene biblioteca,
comedor infantil, ni sala para maestros, no tiene cafetn, no tiene cancha, no tiene banda escolar, no
hay vivero, ni hay huerto.
La escuela cuenta con una letrina, la cual se encuentra en mal estado, necesitan 2 para darle
cobertura adecuada a la poblacin estudiantil que hay en el centro de estudio, No cuenta con una
unidad para el lavado de manos. No cuenta con servicio de agua potable, por lo que no existen
charcas en el patio y para tener agua en la escuela, los alumnos llevan su agua para tomar en
botellas, el agua la consideran de mala calidad. Los estudiantes se enferman de diarrea por el agua
que consumen y en perodo lluvioso les afecta la malaria.
2
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Principales ocupaciones de las personas.


En la comunidad de El Achiote personas mayores que trabajan y que son beneficiarias del proyecto
tienen las siguientes ocupaciones: el 19% como productor agrcola, 7% como jornalero en
agricultura, 25% como ama de casa, 43% como estudiantes, el 1% como docentes y el5% ejercen
otras ocupaciones.
Ocupacin
Productor agrcola
Jornaleros
Domestica
Ama de casa
Vigilante
Estudiante
Docentes
otros
total

N
15
6
0
20
0
35
1
4
81

%
.19%
7%
0%
25%
0%
43%
1%
5%
100

Situacin econmica de las familias

Ingresos mensuales del hogar: El ingreso promedio es de C$ 2,875.00 Crdobas, el mnimo


que ganan mensual es de C$ 500 y el mximo de C$12,000.
CATEGORA
Ingreso del hogar al mes (Crdobas)

MEDIA / HOGAR
C$ 2,875.00

De las instancias organizativas comunitarias.


En la comunidad la poblacin tiene diversos espacios de organizacin, de 22 hogares, 8(36%)
participan en una organizacin religiosa, 4(20%) una organizacin social, 5(23%) a productivas, un
1(5%) otras y el 16% a ninguna.
Afiliacin a organizaciones: Se presentan las siguientes afiliaciones a organizaciones:
CATEGORA
Religiosa
Social
Productiva
Otras
ninguna
FIRMA CONSULTORA:
CONDISA
Total
Bravo M.

N
%
8
36%
4
20%
5
23%
1
5%
4
16%
Diseo:
Ing.
Mirta Violeta
22
100%

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Participacin de mujeres y hombres:

Personas del hogar que participan organizadamente en la construccin del proyecto de


Agua Potable en la comunidad: De los 22 hogares participantes del proyecto, el 100% de los
hogares contestaron en la encuesta donde las mujeres participan en un 55.5% y los hombres
participan en un 44.5%, manifestndose una mayor participacin de los hombres en actividades
comunitarias, esta misma tendencia se manifiesta en las instancias de toma de decisiones como
son la Asamblea de Concertacin, Asamblea General Comunitaria y Comit de Administracin,
sin embargo aunque la mujer participa activamente en todas las actividades del proyecto.
Hombres

45

44.5%

Mujeres

56

55.5%

Total

101

100%

Situacin de Salud en los hogares.


Principales enfermedades:
Las principales enfermedades que prevalecen entre los diferentes grupos de edades del total de la
poblacin beneficiada con el proyecto de agua y saneamiento de El Achiote son: tos con 43%,
seguido de resfriado con un25.%, diarrea con el 13%, malaria con 6%, parasitosis con el 3%,
enfermedades drmicas con el 6%, malaria el 6% y otras con 4%.
El 100% de los nios se encuentran vacunados, segn el reporte de los encuestados, el 95%
practica hbitos de higiene con relacin al lavado de las manos, el 100% con el buen uso del agua y
mantienen tapados los recipientes de almacenamiento, el 65% expresa realizar un buen uso de la
letrina, el 35% de las familias no utiliza letrina porque no tiene en su casa, y sus necesidades la
hacen al aire libre, principalmente los nios. En general el grupo etreo mayor de 0-5 aos es el ms
afectado con las enfermedades principalmente con tos, resfriado y diarrea, el 89% de la poblacin
total ha padecido de estas enfermedades en el 2010.
2.3.2

SERVICIOS EXISTENTES

La comunidad nicamente cuenta con una escuela primaria, no cuenta con servicio de energa
elctrica, agua potable y recoleccin de desechos slidos, ni ningn otro tipo de servicio pblico.
2.3.3

INFRAESTRUCTURA

Condiciones de la vivienda.
4
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

El 86% de los entrevistados afirman que viven en casa propia, un 14% habita en viviendas
prestadas. En las viviendas prevalecen las paredes de madera, piso de tierra, techo de zinc, el 90%
tienen tres divisiones, el 64% se encuentran en regular estado, el 14% de las casas los habitantes
opinan que estn en mal estado y el otro 22% de las viviendas se encuentran en buen estado fsico
Propiedad de la vivienda: Propia 19(86%), prestadas 4(14%).

Tipo de pared: Bloque (0%), Madera 20 (90%), madera y palma (0%), ladrillo 1(5%) y otros
materiales 1 (5%)

Tipo de piso: Tierra 20 (90%), Ladrillo 1(5%), Madera (0%) y otros materiales 1(5%)

Tipo de techo: Zinc 16(72.5%), Teja (0%), Otro material 6 (27.5%)

Divisiones de la casa: Tres divisiones 20(90%), dos divisiones 2(10%), sin divisiones (0%).

Estado de la vivienda: Buena 5 (25.5%), Regular 14 (63.5%), Mala 3 (14%).

2.4 ESTUDIO HIDROGEOLGICO


En el informe de prefactibilidad se presento el estudio hidrogeolgico completo del proyecto, el cual
presenta las siguientes conclusiones y recomendaciones.
Conclusiones:
De acuerdo a la evaluacin de los recursos hdricos en la microcuenca del cao, se estim
que la recarga natural promedio al acufero local en las microcuenca Cerro Catorce, anda en
el orden del 9.35 % respecto a la precipitacin media anual, es decir 275.26 mm/ao.
5
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Para la Microcuenca Cerro Catorce, con un rea total de 0.13 Km2, la recarga total anual
para el rea de captacin en el sitio propuesto de fuente de agua, result de 0.0357838
MMCA, que equivale a 98 m3/da o 18 gpm (1.13 l/seg.)
Como resultado de la estimacin del caudal superficial en la microcuenca Cerro Catorce,
con el mtodo Precipitacin- Escurrimiento, se tiene que para el rea de contribucin del
sitio propuesto es igual a 0.244934 MMCA (Millones de metros cbicos anuales),
equivalentes a 671 m3/da o 123.1 gpm (7.76 l/seg).
Se obtuvo una capacidad de produccin especfica para el acufero local equivalente a 11.78
m3/da/m (0.0095) m3/min./m) o 2.16 gpm por metro abatimiento o descenso. Lo anterior
refleja una transmisividad aproximada de 14.37 m2/da, en tales condiciones se estima una
produccin u oferta natural de agua en el medio poroso de 7 gpm por cada 5 metros de
descenso.
Desde el punto de vista de hidroqumico, las aguas en la microcuenca Cerro Catorce, se
clasifican como bicarbonatadas clcicas, reflejando que son aguas de muy poco tiempo de
permanencia en la microcuenca, con incipiente o nulo intercambio catinico. Desde el punto
la ptica de la calidad fsico-qumica, dichas aguas cumplen con las normas de potabilidad
(CAPRE).
Las concentraciones de indicadores de contaminacin, presentan valores por debajo de las
normas indicadas de potabilidad. Desde el punto de vista de salinidad, tiene menos de 60
mg/l (norma CAPRE 1000 mg/l). Las concentraciones de Los nitratos, nitritos, cianuro,
arsnico, plomo y flor, as como el grado de acidez representado por el pH, igualmente se
encuentran por debajo de los lmites permisibles (CAPRE).
La concentracin de hierro es de 0.35 mg/l, lo cual es levemente superior a la norma
CAPRE de 0.3 mg/l y amerita un tratamiento bsico para reducir la concentracin del mismo.
Se observa presencia de coliformes totales y fecales por encima del valor mximo admisible.
Desde el punto de vista de las alternativas de fuentes de captacin de agua, se estima que
la fuente del manantial en el cerro Catorce y pozo perforado equipado con bomba de
mecate (PPBM), presentan un balance positivo en la relacin oferta vs demanda. Aunque
de las tres alternativas, la de pozo perforado, presenta el menor cuadal de 2.5 gpm, la
alternativa MAG con conexin intra domiciliar presenta 5 y la de MAG con conexin de patio
presenta un excedente de 5 gpm. La alternativa de pozo (PPBM), requiere al menos 3
pozos, debido a la dispersin de la poblacin, dicha condicin convierte a dicha alternativa
menos viable respecto a la captacin del manantial.
Considerando la oferta natural arriba indicada, tanto en cantidad como en calidad, desde el
punto de vista de la estabilidad de caudal, se concluye que la microcuenca cerro Catorce,
en el sitio propuesto para captacin de agua, tiene capacidad para cubrir la demanda para
el perodo de diseo del proyecto de agua potable.

Recomendaciones:
De acuerdo a las condiciones de potencial hdrico evaluadas, en cuanto a cantidad y calidad
del agua, se recomienda el aprovechamiento con sistema MAG el manantial de la
microcuenca del cerro Puntas para el de abastecimiento de agua potable a la comunidad de
6
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

El Achiote del municipio de Paiwas en cualquiera de las dos modalidades. Dicho sitio se
localiza en las coordenadas este 724087 y norte 1414605.
Se sugiere, establecer un monitoreo peridico de la calidad de agua y tratamiento bsico de
cloracin, as como de remocin de Hierro, hasta la concentracin aceptable por debajo de
0.3 mg/l (Norma CAPRE).
2.5 ESTUDIO DE FUENTES DE ABASTECIMIENTO (CANTIDAD Y CALIDAD)
Para identificar las posibles fuentes de agua potable para la comunidad, se realiz un inventario de fuentes
de agua en uso y potenciales. Estas se identificaron con el acompaamiento de los miembros del comit
de Agua Potable y Saneamiento. De este trabajo se pudo identificar tres fuentes de agua, a continuacin
se presentan los datos de las fuentes.
De este trabajo se pudo identificar tres fuentes de agua potenciales, a continuacin se presentan los
datos.
Cuadro No.3 Inventario de fuentes
Fuente
Dueo
Produccin
Coordenadas
Uso actual
UTM 726794.748 y
Manantial iglesia Iglesia
4gpm/abril 2012
Abastece
1415824.597, Elevacin
evanglica
alrededor
342.25msnm.
de 12 viviendas.
Manantial Cerro
Bonito
Manantial
Cerro 14

Sr. Jos
5gpm/abril 2012
Miguel
Robles
La comunidad 10gpm/abril 2012

UTM 725552.72 y 1390435.52,


Elevacin 420msnm.

Ninguno

UTM 724087.22 y 1414605.08,


Elevacin 387.05msnm.

Ninguno

Figura No.5 Ubicacin de las fuentes de agua identificadas

7
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

2.5.1

AFOROS DE FUENTES

Una vez que se identificaron las fuentes potenciales y en uso, se procedi a realizar los aforos de las
mismas. Los resultados se pueden observar en cuadro anterior.
2.5.1.1 DESCRIPCIN DE LA METODOLOGA
Los aforos se realizaron con el mtodo volumtrico que consiste en tomar el tiempo que demora en
llenarse un recipiente de volumen conocido. Posteriormente se divide el volumen en litros entre el tiempo
promedio en segundos, obtenindose el caudal en l/s
El resultado del aforo fue de 10gpm, esta capacidad supera la demanda esperada para el final del
periodo de diseo que es del orden de los 6gpm.
Aforo en Manantial Cerro El 14, abril 2012, Caudal 10gpm

8
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

2.5.1.2 INTERPRETACIN DE LOS RESULTADOS


El aforo de la fuente Cerro 14 fue realizado en el mes de Abril del 2012, al final del verano y sin ocurrencia
de lluvias. La fuente propuesta produce un caudal de 10.00gpm, esta oferta de agua supera la demanda
esperada al final del periodo de diseo de 20 aos.
2.5.1.3 CONCLUSIONES

El Cerro 14 tiene potencial de explotacin como fuente de agua potable


La produccin de la fuente al final del verano del 2012 fue de 10.00gpm
La fuente es propiedad de la comunidad de El Achiote
No Existe ningn tipo de conflicto en torno a la legalidad de la fuente

2.5.1.4 RECOMENDACIONES
Se recomienda explotar la fuente superficial comunitaria con caudal de 7gpm.
Se recomienda la construccin de una obra de captacin en la fuente a utilizar para abastecer al
sistema.
Se recomienda construir obras de proteccin para la fuente de agua
9
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

2.5.2

RESULTADOS DE LA CALIDAD DEL AGUA

El agua tiene una gran influencia en los procesos bioqumicos que ocurren en la naturaleza, se considera
que el agua es un solvente universal, debido a que es capaz de disolver o dispersar la mayora de
sustancias con las que tiene contacto, sean estas slidas, lquidas o gaseosas, y de formar con ellas iones,
complejos solubles e insolubles, coloides o simplemente partculas dispersas de diferente tamao y peso.
Desde el punto de vista de la salud humana, el agua ayuda a eliminar las sustancias resultantes de los
procesos bioqumicos que se desarrollan en el organismo humano. Sin embargo, por esta misma
propiedad, puede transportar una serie de txicos al organismo que pueden afectar a diferentes rganos,
de manera reversible o irreversible. Es por ello la importancia de conocer las propiedades de la misma.
Para conocer la calidad del agua de la fuente de abastecimiento que ser utilizado para abastecer de agua
potable a la comunidad, se tom una muestra de agua de la fuente superficial propuesta y se procedi a
realizar el anlisis fsico qumico y bacteriolgico de la misma.
El anlisis fsico qumico consider los parmetros que miden las caractersticas estticas del agua tales
como: Aspecto, olor, turbiedad, color verdadero, PH, hierro, manganeso, sodio y sulfato. Algunos de estos
parmetros tambin se consideran como componentes inorgnicos que en concentraciones altas afectan la
salud, tal como el sodio, adems en este grupo de componentes inorgnicos se analizaron los siguientes
parmetros: Dureza, nitratos y nitritos.
Ver resultados de calidad fsico qumica del agua se presenta en los anexos No.12.5 y 12.6
2.5.2.1 INTERPRETACIN DE LOS RESULTADOS
Los resultados del anlisis fsico qumico, indican que la gran mayora de las concentraciones de los
parmetros analizados son inferiores al valor lmite permisible, segn la norma CAPRE. Sin embargo, se
registra valores superiores a la norma para el parmetro de pH, turbiedad y hierro.
El pH tiene un valor de 6.31, siendo el rango recomendado de 6.5 a 8.5, este valor indica que el agua de la
fuente es un poco acida respecto al sabor deseado, sin embargo no ocasiona mayores problemas de
salud.
El valor de la turbidez resulto de 24 UTU, este valor es alto respecto al valor recomendado de 5 UTU, esta
turbidez muy probablemente se debe a la formacin cascajosa amarillenta de donde nace el manantial.
En los resultados se puede observar que el valor medido para el parmetro de hierro total es de 0.355mg/l,
lo cual es un poco superior al valor recomendado de 0.3mg/l, por lo cual se considera que la concentracin
de hierro esta levemente incrementada respecto al valor lmite.
Tambin se midi el parmetro de Arsnico y cianuro, para el arsnico se obtuvo un valor menor de
0.001mg/l, este valor es inferior al valor lmite permisible de 0.01mg/l. El nivel de cianuro se midi menor de
10
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

0.02mg/l, siendo el valor lmite permisible de 0.05mg/l. Por lo que se puede concluir que el agua est libre
de este tipo de contaminantes.
Adems se midi el nitrgeno amoniacal, resultando un valor de 0.093mg/l, que es bajo en relacin al
valor lmite permisible de 0.5mg/l.
Tambin se realiz anlisis bacteriolgico del agua de la fuente, ver anexos No.12.5 y 12.6, los resultados
indican que existe cierto grado de contaminacin bacteriolgico, por lo cual ser necesario dar tratamiento
de desinfeccin al agua mediante la aplicacin de cloro.
2.5.2.2 CONCLUSIONES
Los resultados del anlisis fsico qumico indican que el agua es de buena calidad fsico qumica y
sin embargo requiere tratamiento para bajar la concentracin de hierro y la turbidez.
Los resultados de anlisis especiales como Nitrgeno Amoniacal, Arsnico, Cianuro indican que
las concentraciones de estos contaminantes estn por debajo del lmite permisible de la norma
CAPRE, por lo cual no representan ninguna amenaza para la salud.
El resultado del anlisis bacteriolgico indica que el agua tiene cierto grado de contaminacin
bacteriolgica, sin embargo, con un buen tratamiento de cloracin el agua puede ser desinfectada
y libre de este tipo de contaminacin.
2.5.2.3 RECOMENDACIONES
Se recomienda el uso del agua de la fuente 14, para abastecer al proyecto de agua potable para beneficiar
a esta comunidad. Aplicando prefiltracion, aireacin y cloracin como medida profilctica.
2.6 ESTUDIO DE SUELOS Y CALICATAS
Se realiz estudio de suelos en el predio en donde se ubicar el tanque de almacenamiento con la
finalidad de conocer la estratigrafa del suelo y la capacidad de soporte del mismo y con esta informacin
definir el mejoramiento de suelo requerido para las fundaciones del tanque. Adems se efectuaro n
calicatas en las calles de la localidad con el fin de conocer las caractersticas del suelo natural de la zona y
en base a ello estimar los costos de excavacin para la instalacin de tuberas. Ver esquema de ubicacin
de sondeos en esquema siguiente.

11
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

2.7 ASPECTOS AMBIENTALES DEL PROYECTO


El Decreto 76-2006 establece 3 categoras ambientales que rigen el Sistema de Evaluacin Ambiental en
el pas, de acuerdo a las incidencias que tienen los proyectos. Es importante tomar en consideracin que
los proyectos de Agua y Saneamiento Rural, no estn dentro de las 3 categoras ambientales que
establece el Decreto, por consiguiente y debido a que son proyectos de Bajo Impacto Ambiental Potencial,
no requieren de Estudio de Impacto Ambiental, ni de Autorizacin Ambiental del MARENA.
Clasificacin Ambiental
La clasificacin ambiental de los proyectos es un instrumento de Gestin Ambiental que permite identificar
las acciones a seguir segn las incidencias que stos pudieran tener en el medio ambiente. Los proyectos
de Agua & Saneamiento la mayor parte se aglutinan en la categora IV del Cuadro de Clasificacin
Ambiental segn decreto 76-2006, y de la lista de proyectos contemplados en el SNIP (Sistema Nacional
de Inversin Pblica)
La Categora IV establece que "Agrupa algunos tipos de proyectos del Sistema Nacional de Inversin
Pblica (SNIP) que no estn sujetos a los procedimientos ambientales de Ley y que por su incidencia
ambiental deberan llevar durante su ciclo de vida un conjunto de instrumentos ambientales que incluyen:
evaluacin del emplazamiento, anlisis ambiental, evaluacin ambiental, seguimiento y monitoreo"
Existen un conjunto de instrumentos ambientales que se incorporan en diferentes momentos del ciclo del
proyecto con el propsito de prevenir y corregir la incidencia ambiental negativa que pudieran generar los
proyectos financiados por El Nuevo FISE.
En la etapa de formulacin de proyecto se utiliza el instrumento de evaluacin de emplazamiento, este
instrumento ambiental permite valorar las caractersticas generales del sitio donde se propone ubicar el
proyecto para evitar o prevenir potenciales riesgos e impactos ambientales que atentan contra la
sostenibilidad y la adaptabilidad del proyecto.
2.7.1

REQUISITOS AMBIENTALES

Establecer los requisitos mnimos fsico ambientales que servirn como Indicadores de Desempeo
Ambiental del Sistema de gestin Ambiental del (SISGA) del FISE
Todas las fuentes de captacin para los proyectos de agua debern ser debidamente protegidas
(cercadas), para evitar el acceso de personas no autorizadas y animales. Adems se reforestar el
rea comprendida en un radio de 50 metros, medidos desde el centro de la fuente de captacin.
La fuente de captacin contar con un sello sanitario para mejorar las condiciones higinicas en sus
alrededores. Adems, la fuente de captacin no puede quedar de forma superficial, para ello se
recomienda construir un filtro con piedras de ro o grava y el sitio debe quedar bien drenado.

12
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

El trazado de las redes de tubera para proyectos de agua debe hacerse evitando las zonas de
terrenos inestables. En los casos que no existan otras alternativas deben realizarse muros de
sostenimientos y anclajes de tuberas.
En zonas de alto riesgo smico debern usarse materiales flexibles para las tuberas y en tramos
cortos. Las uniones de los tubos tambin deben ser flexibles.
La plataforma o piso de las letrinas debe elevarse un mnimo de 0.20 metros sobre el nivel mximo
esperado de inundacin, construyndole rampas hacia los lados o gradas, segn el caso.
Si en la excavacin del foso para la letrina se encuentra roca agrietada o suelos calcreos, se
debern impermeabilizar las paredes y el fondo del foso con una lechada de cemento con arena,
para impedir la contaminacin del agua subterrnea.
Se deber usar letrinas aboneras o letrinas elevadas en los siguientes casos:
En suelos muy arenosos o con altos niveles freticos y/o consistencia rocosa, debido a que se
pueden producir derrumbes y contaminacin del agua subterrnea.
En reas poblacionales donde se hace gran uso de agua de pozos superficiales, debido a que
pueden contaminar el acufero.
Los proyectos de agua y saneamiento rural cumplirn con las especificaciones tcnicas establecidas
por la Empresa Nicaragense de Acueductos y Alcantarillados, a travs de las NORMAS Y
PROCEDIMIENTOS TCNICOS PARA LA IMPLEMENTACIN DE PROYECTOS DE AGUA
POTABLE Y SANEAMIENTO EN EL SECTOR RURAL DISPERSO DE NICARAGUA. (1999), as
como, las especificaciones de calidad establecidas por el FISE.
En los proyectos de agua potable no podrn utilizarse como sub base o rellenos o materiales de
construccin (arena, piedra y otros), tanto para la red de tuberas, as como para la construccin de
Plantas de Tratamientos y Tanques de Depsitos de los proyectos, materiales contaminados o de
residuos de cualquier proceso industrial o minero. Slo se podrn usar estos materiales, cuando
existan anlisis de laboratorio que evidencien la ausencia de contaminacin por metales pesados o
cualquier otra sustancia.
En los proyectos de agua, tanto urbano como rural, debern tomarse las medidas necesarias
durante los trabajos de construccin de zanjas para evitar accidentes de los trabajadores y la
poblacin en general.
Los proyectos de Agua que lleven el componente Planta de Tratamiento, debern seguir un plan de
manejo especial de los sedimentos producto del tratamiento del agua con el propsito de ser
debidamente secados en un rea dispuesta para ese fin y posteriormente sern dispuestos en sitios
autorizados por la Unidad de Gestin Ambiental municipal, segn la concentracin que estos
pudieran tener de sustancias txicas o contaminantes. En caso que los sedimentos contengan
concentraciones de metales pesados o sustancias txicas deber drsele a estos desechos el
tratamiento de Desechos Peligrosos, en cuyo caso la mejor prctica es consultar con la Direccin de
Calidad Ambiental del MARENA, sobre el procedimiento a seguir. Las especificaciones para el
13
FIRMA CONSULTORA: CONDISA
Diseo: Ing. Mirta Violeta
Bravo M.

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

tratamiento de las aguas deben ser dictaminadas por el MINSA y debe formar parte del manual de
operaciones de la planta.
Todos los proyectos de agua debern cumplir lo estipulado en cuanto a la CLASIFICACION DE LOS
RECURSOS HIDRICOS DE A CUERDO A SUS USOS, cuyo objeto es determinar la capacidad y
condiciones del aprovechamiento de los recursos hidrulicos y los niveles y calidad de vertimientos
tolerables para cada cuerpo de agua, se establecen seis tipos de cuerpos de agua: Normativa
ambiental INAA (1999).

Tipo 1. Aguas destinadas al uso domstico y al uso industrial que requiera de agua potable,
siempre que esta forme parte de un producto o subproducto destinado al consumo humano o que
entre en contacto con l. Las aguas de este tipo se desagregan en dos categoras:
Categora 1-A Aguas que desde el punto de vista sanitario pueden ser acondicionadas con la sola
adicin de desinfectantes; y
Categora 1-B Aguas que pueden ser acondicionadas por medio de tratamientos convencionales de
coagulacin, floculacin, sedimentacin, filtracin y/o cloracin.

2.7.2

EVALUACIN DEL EMPLAZAMIENTO

La evaluacin del emplazamiento permite valorar las caractersticas generales del sitio y el entorno
donde se propone ubicar el proyecto para evitar o prevenir potenciales riesgos e impactos
ambientales que atentan contra la sostenibilidad y la adaptabilidad del proyecto, tales como:
Peligrosidad del sitio debido a factores naturales o antrpicos que pueden daar el proyecto.
Evitar efectos ambientales negativos del proyecto.
Valorar e identificar aspectos legales, tcnicos y normativos del proyecto que entren en
contradiccin con el marco jurdico.
Evitar efectos sociales indeseables generados por el proyecto.
Buscar la mxima adaptabilidad entre el sitio y el tipo de proyecto.
A continuacin se muestra la evaluacin de emplazamiento del componente de agua potable.

14
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

FONDO DE
INVERSIN SOCIAL
DE EMERGENCIA

NUEVO FISE

SISTEMA DE GESTION
AMBIENTAL (SISGA)

INSTRUMENTO DE
EVALUACION DE
EMPLAZAMIENTO

TITULO: Construccin

de

Agua

ELABORADA:
Julio 2012

Actualizada:

VIGENTE
DESDE:
Julio 2012

CANTIDAD DE
PGINAS:
2

del Sistema de Agua y Saneamiento El Achiote

HISTOGRAMA DE EVALUACION DEL EMPLAZAMIENTO DEL PROYECTO


NOMBRE DEL PROYECTO: Construccin del Sistema de Agua y Saneamiento El Achiote
COMPONENTE A CONSIDERAR: Fuente de abastecimiento
CODIGO DEL PROYECTO: 19200
DEPARTAMENTO/REGION: RAAS
COMUNIDAD: El Achiote

15
FIRMA CONSULTORA: CONDISA

Diseo: Ing. Mirta Violeta Bravo M.

Informe de Factibilidad Proyecto: Construccin de Sistema


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

de

Agua

16
FIRMA CONSULTORA: CONDISA

Diseo: Ing. Mirta Violeta Bravo M.

Informe de Factibilidad Proyecto: Construccin de Sistema


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

FONDO DE
INVERSIN SOCIAL
DE EMERGENCIA

NUEVO FISE

SISTEMA DE GESTION
AMBIENTAL (SISGA)

INSTRUMENTO DE
EVALUACION DE
EMPLAZAMIENTO

TITULO: Construccin

de

Agua

ELABORADA:
Julio 2012

Actualizada:

VIGENTE
DESDE:
Julio 2012

CANTIDAD DE
PGINAS:
2

del Sistema de Agua y Saneamiento El Achiote

HISTOGRAMA DE EVALUACION DEL EMPLAZAMIENTO DEL PROYECTO


NOMBRE DEL PROYECTO: Construccin del Sistema de Agua y Saneamiento El Achiote
COMPONENTE A CONSIDERAR: Planta de Tratamiento
CODIGO DEL PROYECTO: 19200
DEPARTAMENTO/REGION: RAAS
COMUNIDAD: El Achiote

1
FIRMA CONSULTORA: CONDISA

Diseo: Ing. Mirta Violeta Bravo M.

Informe de Factibilidad Proyecto: Construccin de Sistema


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

de

Agua

2
FIRMA CONSULTORA: CONDISA

Diseo: Ing. Mirta Violeta Bravo M.

Informe de Factibilidad Proyecto: Construccin de Sistema


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

FONDO DE
INVERSIN SOCIAL
DE EMERGENCIA

NUEVO FISE

SISTEMA DE GESTION
AMBIENTAL (SISGA)

INSTRUMENTO DE
EVALUACION DE
EMPLAZAMIENTO

TITULO: Construccin

de

Agua

ELABORADA:
Julio 2012

Actualizada:

VIGENTE
DESDE:
Julio 2012

CANTIDAD DE
PGINAS:
2

del Sistema de Agua y Saneamiento El Achiote

HISTOGRAMA DE EVALUACION DEL EMPLAZAMIENTO DEL PROYECTO


NOMBRE DEL PROYECTO: Construccin del Sistema de Agua y Saneamiento El Achiote
COMPONENTE A CONSIDERAR: Tanque de almacenamiento
CODIGO DEL PROYECTO: 19200
DEPARTAMENTO/REGION: RAAS
COMUNIDAD: El Achiote

1
FIRMA CONSULTORA: CONDISA

Diseo: Ing. Mirta Violeta Bravo M.

Informe de Factibilidad Proyecto: Construccin de Sistema


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

de

Agua

2
FIRMA CONSULTORA: CONDISA

Diseo: Ing. Mirta Violeta Bravo M.

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

2.7.3

ANLISIS AMBIENTAL DEL SUBPROYECTO


IDENTIFICACIN DE LA PROBLEMTICA AMBIENTAL

ALTERACIONES AMBIENTALES
CAUSAS
EFECTOS
ESPECIFICAR LAS ACCIONES ESPECIFICAR LOS EFECTOS QUE
HUMANAS QUE GENERAN EL SE OBSERVAN EN EL MEDIO
FACTORES
DETERIORO DE LA CALIDAD AMBIENTE DEBIDO AL DETERIORO
AMBIENTALES
AMBIENTAL EN CASO QUE LA DE LA CALIDAD AMBIENTAL EN
VALORACIN SEA MALA
CASO QUE LA VALORACIN SEA
MALA
-Quema a cielo abierto
-Contaminacin del aire por la
CALIDAD DEL AIRE
emisin de humo y gases
CANTIDAD
Y -Deficiente higiene comunal
-Contaminacin de las aguas
CALIDAD DE LAS -Vertido desechos slidos en cauces, superficiales con repercusin en la
AGUAS
y fuentes de agua superficiales.
salud y el ecosistema
SUPERFICIALES
-Usos de plaguicidas utilizados en
las reas de cultivo
SUELOS

CUBIERTA
VEGETAL

MEDIO
CONSTRUIDO

CALIDAD DE VIDA

-Ausencia de rgimen de usos de -Afectacin a suelos de calidad


suelos
edfica, daos a la produccin
-Quema
agrcola
-Procesos de erosin, sedimentacin,
-Deforestacin
prdida de especies de alto valor,
dao al hbitat de la fauna, descenso
en la cantidad se precipitaciones y
aguas superficiales.
-Deficiente higiene comunal
-Ausencia o deficiente tratamiento
-Crecimiento
poblacional
no adecuado de los desechos slidos y
planificado,
lquidos.
ausencia
de
procesos
de
planificacin del suelo y el territorio
Afectaciones a la salud de la Las alteraciones sobre la salud
poblacin debido a:
dependen en gran medida de los
-Condiciones higinico sanitarias y niveles de contaminacin que se
epidemiolgicas no adecuadas para produzcan (medios o episdicos) y de
el buen desarrollo de la poblacin.
las caractersticas de la poblacin,
-Ausencia de justicia social
especialmente la estructura de
edades. Las afecciones sanitarias
que se producen son principalmente
respiratorias,
gastrointestinales,
enfermedades contagiosas o de
1

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

transmisin por vectores (dengue,


malaria, clera y otras) enfermedades
de
transmisin
sexual
cardiovasculares, as como efectos
sobre el rendimiento en el trabajo y
psicolgicas
Deterioro de la calidad de vida
-Inseguridad ciudadana, vandalismo
-Vulnerabilidad social, pobreza,
Litigios territoriales
-Vulnerabilidad social

2
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y Saneamiento El Achiote


Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

VALORACIN DE LA CALIDAD AMBIENTAL SIN EL PROYECTO.


CRITERIOS
CAUSA

EFECTO

Prome
dio

Poblaci
n
Afectada
2

2.4

2.2

2.4

2
2

2
2

2
2

1
1

2
1

1.8
1.6

2.2

2.8

Intensidad

Superfi
cie

Recuperac
in

Duraci
n

Vertido desechos slidos en cauces,


y fuentes de agua superficiales
Usos de plaguicidas utilizados en
las reas de cultivo

-Ausencia de rgimen de usos de Afectacin a suelos de calidad edfica, daos a


suelos
la produccin agrcola
-Quema
-Deforestacin
-Procesos de erosin, sedimentacin, prdida
de especies de alto valor, dao al hbitat de la
fauna, descenso en la cantidad se
precipitaciones y aguas superficiales.
-Crecimiento
poblacional
no -Ausencia o deficiente tratamiento adecuado de
planificado,
los desechos slidos y lquidos.
ausencia de procesos de
planificacin del suelo y el territorio
Las alteraciones sobre la salud dependen en
Condiciones higinico sanitarias y
gran medida de los niveles de contaminacin
epidemiolgicas no adecuadas para que se produzcan (medios o episdicos) y de

-Quema a cielo abierto


-Deficiente higiene comunal

Contaminacin del aire por la emisin de humo


y gases
Contaminacin de las aguas superficiales con
repercusin en la salud y el ecosistema

3
FIRMA CONSULTORA: CONDISA

Diseo: Ing. Mirta Violeta Bravo M.

2.2

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y Saneamiento El Achiote


Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

el buen desarrollo de la poblacin.

las caractersticas de la poblacin,


especialmente la estructura de edades. Las
afecciones sanitarias que se producen son
principalmente respiratorias, gastrointestinales,
enfermedades contagiosas o de transmisin
por vectores (dengue, malaria, clera y otras)
enfermedades
de
transmisin
sexual
cardiovasculares, as como efectos sobre el
rendimiento en el trabajo y psicolgicas
Deterioro de la calidad de vida
-Quema a cielo abierto
Contaminacin del aire por la emisin de humo
y gases
VALOR PROMEDIO DEL ESTADO ACTUAL DEL MEDIO
22.4/10=2.24

4
FIRMA CONSULTORA: CONDISA

Diseo: Ing. Mirta Violeta Bravo M.

2.8

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Los efectos de la deforestacin representan una situacin riesgosa para la ejecucin del proyecto, que
afecta el puntualmente el criterio de poblacin, por lo que se proponen las medidas de mitigacin
pertinentes.
IDENTIFICACION DE LOS IMPACTOS DEL PROYECTO
ESTADIO DEL
PROYECTO
Construccin

ACCIONES IMPACTANTES

EFECTOS

Trabajos preliminares (limpieza Produccin de polvo


y descapote)
Produccin de desechos
orgnicos e inorgnicos
Generacin de empleo
Trabajos de construccin de Produccin de polvo
redes, conexiones domiciliares, Produccin de ruidos
obras de proteccin y obra de
captacin.
Riesgo de inestabilidad de

FACTOR AMBIENTAL
AFECTADO
Calidad del aire
Calidad de vida
Calidad del aire
Ruidos
Geologa

tierras en zanjas
Trazados vulnerables a Suelo Calidad de vida
deslizamientos

Funcionamiento

Funcionamiento del Sistema

Produccin de excretas
Riesgo de dao a la
infraestructura pblica o
privada
Generacin de empleo
Riesgo de contaminacin
por falta de higiene en la
manipulacin
Riesgo de accidentes
Deterioro del servicio ante
deficiencias
de
funcionamiento del comit
de Agua potable lo que
afecta la sostenibilidad del
proyecto

Suelo Calidad de vida


Medio Construido

Calidad de vida
Salud Humana

Poblacin
Calidad de vida

5
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y Saneamiento El Achiote


Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

VALORACIN DE LOS IMPACTOS DEL PROYECTO


CRITERIOS
ACCION IMPACTANTE

EFECTO

Produccin de polvo
Produccin de desechos orgnicos e
inorgnicos
Produccin de polvo
Trabajos de construccin de redes, Produccin de ruidos
conexiones domiciliares, obras de Riesgo de inestabilidad de tierras en
proteccin y obra de captacin.
zanjas
Trazados
vulnerables
a
deslizamientos
Produccin de excretas
Riesgo de dao a la infraestructura
pblica o privada
Riesgo de accidentes
Funcionamiento del sistema
Riesgo de contaminacin
Deterioro
del
servicio
ante
deficiencias de funcionamiento del
comit de Agua potable lo que afecta
la sostenibilidad del proyecto
VALOR PROMEDIO DEL ESTADO DEL MEDIO CON PROYECTO
26.40/11=2.40
Trabajos preliminares
descapote)

(limpieza

Intensida
d

Superfi
cie

Recuperac
in

Duraci
n

2
2

2
3

3
3

3
2

Poblaci
n
Afectad
a
2
3

2
2
2

2
2
3

3
3
2

3
3
3

2
2
2

2.4
2.4
2.4

2.4

2
2

2
3

3
3

3
3

3
3

2.6
2.8

2
2
2

2
2
2

2
2
2

3
2
2

3
2
2

2.4
2
2.0

Promedio

2.4
2.6

El valor promedio del estado del medio con proyecto es de 2.40 lo que indica que el proyecto tiene poca incidencia o relevancia ambiental y
las afectaciones al medio son pocas y fciles de controlar.
6
FIRMA CONSULTORA: CONDISA

Diseo: Ing. Mirta Violeta Bravo M.

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

PRONOSTICO DE LA CALIDAD AMBIENTAL DEL MEDIO CON PROYECTO.


Interpretacin de los impactos en la fase de construccin
En la fase de construccin se dan muchos aspectos negativos y es de esperarse debido
principalmente al movimiento de tierra al momento del descapote y zanjeo, esto afecta negativamente
al suelo, ya que facilita la erosin y prdida de suelo frtil. En estas actividades se producen
tolvaneras que incrementan el nivel de partculas de polvo en el rea afectada. Adems por el
movimiento de la maquinaria que se usa en el proyecto principalmente para el acarreo de material, se
incrementan los nivele s de ruidos causando incomodidad en la poblacin aledaa al rea de trabajo.
Otros factores que son afectados por stas actividades de acuerdo al orden de importancia de los
impactos son la visibilidad y la esttica, ya que habr obstculos en el camino y se impedir o
dificultar el trfico vehicular.
Lo positivo del proyecto en esta etapa son los empleos a trabajadores y el beneficio a pequeos
comerciantes de los alrededores.
La duracin de esta fase del proyecto en cuanto a tiempo es reducida y eso hace que los efectos sean
considerados como temporales, implicando adems la reversibilidad a corto plazo para la mayora de
los factores impactados.
Interpretacin de los impactos en la fase de operacin
En esta fase desde el punto de vista positivo los factores ambientales que sern beneficiados son los
aspectos de salud, pues si la poblacin cuenta con agua potable, las condiciones ambientales del
sector mejoraran significativamente, incrementando el nivel de vida de sus pobladores y trayendo
consigo la reduccin de las enfermedades producidas por la ingesta de agua no segura, esto se
reflejar en la reduccin de los ndices de morbilidad y mortalidad de la infancia, as como tambin en
la disminucin de consultas en los centros de atencin mdica. Aunque este factor ambiental no es
cuantificable, es desde el punto de vista social y humano de mxima prioridad, ya que si se tiene
personas sanas, estas rendirn ms en los trabajos productivos e inciden directamente de manera
positiva en la economa nacional.
Otro factor importante que ser beneficiado con el proyecto es el saneamiento e higiene de la
comunidad, al dotar a la misma con letrinas mejorara en gran manera el nivel y calidad de vida de los
pobladores de la comunidad.
En conclusin se puede notar que aunque se observa bastante balanceado el peso de los impactos
positivos y negativos, el mayor peso corresponde a lo positivo, indicando esto que el proyecto es
viable desde el punto de vista de balance de impactos, es importante hacer notar que con las medidas
de mitigacin, los impactos negativos se atenan, por lo que la ventaja de los impactos positivos
aumenta considerablemente con el desarrollo del proyecto

1
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

PLAN DE MITIGACIN DE LOS IMPACTOS AMBIENTALES GENERADOS POR EL PROYECTO.


RESPONSABLE
COSTO
ACCIONES
MEDIDAS DE
POR EL
EFECTOS
DE LA
IMPACTANTES
MITIGACION
CUMPLIMIENTO
MEDIDA
DE LA MEDIDA
Produccin de polvo
Humedecimiento de
Trabajos
preliminares
la tierra
Indirecto
Contratista
(limpieza y descapote)
Seleccin del sitio
Produccin de desechos receptor de los
C$ 2,500
Contratista
orgnicos e inorgnicos desechos
Recoleccin,
transporte
y
disposicin de los
desechos
Produccin de polvo
Humedecimiento de
Trabajos de construccin
la tierra
Indirecto
Contratista
de pozos propuestos.
Produccin de ruidos
Coordinacin de
Indirecto
Contratista
horarios
Produccin de excretas Construccin letrinas
Costo de
Beneficiarios
provisionales
inversin
Riesgo de dao a la Reparacin de daos
infraestructura pblica o causados
a
la Indirecto
Contratista
privada
propiedad pblica y/o
privada.
Funcionamiento
del Riesgo
de Control sanitario
Trabajo
Miembros del CAPS
sistema
contaminacin
comunitario
Deterioro del servicio Velar por adecuado
ante deficiencias de funcionamiento del
Trabajo
Miembros del CAPS
funcionamiento
del comit de agua.
comunitario
comit de Agua potable Capacitacin
y
lo que afecta la reglamentos
sostenibilidad
del
proyecto
Reduccin del % de
Trabajo
Miembros del CAPS
beneficiarios
del
comunitario
proyecto calculados en
el diseo

2
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

2.8 TERRENOS Y SERVIDUMBRES DE PASE


Los terrenos en donde se construirn las obras propuestas fueron adquiridos por los miembros de la
comunidad, como parte del aporte al proyecto.
Los documentos de legalidad de terrenos que se requieren para la ejecucin del proyecto son:
Legalidad del terreno en donde se localiza la fuente de agua propuesta y prefiltro
Legalidad del terreno en donde se propone tanque de almacenamiento y aireador
Legalidad de Servidumbres de pase de lnea de conduccin de fuente a tanque
Los documentos de legalidad de los terrenos se presentan en el anexo No. 12.4
2.9 BANCO DE MATERIALES (DE PRSTAMO Y DESECHOS)
A continuacin se presentan los datos del banco de materiales existente en la comunidad.
Caractersticas de los Bancos
Nombre del Banco de Materiales

Banco 1
Las minas

Tipo de Tenencia (Pblica o Privada)

Privada

Nombre del Dueo


Estado de la va de Acceso al Banco de
Materiales (Buena, Regular, Mala)
Distancia entre el Banco de Materiales y el
Proyecto (Km)
Est en Explotacin?

Tipo de material (m. selecto, arena, boln)

Selecto

Mala
6km
Si

Plano de Localizacin de los Bancos

3
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Plano de Localizacin de Banco de Materiales

BOTADERO DE DESECHOS
En la comunidad no existe servicio de recoleccin de desechos slidos ni un sitio destinado para botar los
desechos slidos, por lo que el contratista deber de buscar un lote que pueda ser utilizada para este fin.

4
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

3. CRITERIOS PARA EL DISEO HIDRULICO


3.1 GENERALIDADES
Los criterios utilizados en el diseo del proyecto son los establecidos por el INAA en las normas tcnicas
de diseo de sistemas de abastecimiento de agua potable en el medio rural (NTON 09001-99).
3.2 PERODO DE DISEO
En los diseos de proyectos de Abastecimiento de Agua se recomienda fijar la vida til de cada uno de los
componentes del sistema, con el propsito de:
Determinar que perodos de estos componentes del sistema, debern satisfacer las demandas
futuras de la comunidad.
Qu elementos del sistema deben disearse por etapas
Cules sern las previsiones que deben de considerarse para incorporar los nuevos elementos al
sistema.
A continuacin se indican los perodos de diseos econmicos de los elementos componentes de un
sistema de abastecimiento de agua potable.
PERIODO DE DISEO DE COMPONENTES DE SISTEMAS DE AGUA
A continuacin se indican los perodos de diseos econmicos de los elementos componentes de un
sistema de abastecimiento de agua potable.
Tipos de Componentes
perodo de diseo
Pozos excavados
10 aos
Pozos perforados
15 aos
Captaciones superficiales y manantiales
20 aos
Lneas de Conduccin
15 aos
Tanque de almacenamiento
20 aos
Red de distribucin
15 aos
Sin embargo como los TDR establecen un perodo de diseo de 20 aos para los sistemas, se utilizar un
perodo de diseo de 20 aos para todos los elementos del sistema.
3.3 POBLACIN DE DISEO
Para el clculo de las poblaciones futuras se usar el mtodo geomtrico expresado por la frmula
siguiente:
Pn = Po (1+r) n
Dnde:
Pn = Poblacin del ao n
Po =Poblacin al inicio del perodo de diseo
r =Tasa de crecimiento en el periodo de diseo expresado en notacin decimal.
n =Nmero de aos que comprende el perodo de diseo.
5
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Si no se dispone de datos de poblacin al inicio del perodo de diseo, deber efectuarse un censo
poblacional por medio de los representantes comunitarios o promotores sociales, previamente entrenados.
3.4 TASA DE CRECIMIENTO
Es necesario determinar las demandas futuras de una poblacin para prever en el diseo las exigencias,
de las fuentes de abastecimiento, lneas de conduccin, redes de distribucin, equipos de bombeo, planta
de potabilizacin y futuras extensiones del servicio. Por lo tanto, es necesario predecir la poblacin futura
para un nmero de aos, que ser fijada por los perodos econmicos del diseo.
La informacin necesaria para seleccionar la tasa de crecimiento con la cual habr de proyectarse la
poblacin de la localidad en estudio, se realizara con los datos de El Instituto Nicaragense de
Estadsticas y Censos (INEC), el cual maneja toda la informacin relacionada con las poblaciones del pas.
All se pueden encontrar los datos de los ltimos censos nacionales realizados en los aos 1,906, 1920,
1940, 1950, 1963, 1995 y 2005 El INEC.
Para estimar la tasa de crecimiento de cada localidad se utilizara el mtodo geomtrico. Este mtodo es
ms aplicable a localidades que no han alcanzado su desarrollo y que se mantienen creciendo a una tasa
fija y es el de mayor uso en Nicaragua. Se recomienda usar las siguientes tasas en base al crecimiento
histrico.
1) Ninguna de las localidades tendr una tasa de crecimiento mayor de 4%
2) Ninguna de las localidades tendr una tasa de crecimiento menor del 2.5%
En el caso del proyecto la tasa de crecimiento utilizada es de 3.20%
3.5 DOTACIN DE AGUA
Para definir la dotacin a utilizar en cada una de las alternativas planteadas se tomo en cuenta los criterios
establecido en las normas tcnicas de diseo de sistemas de abastecimiento de agua potable en el medio
rural NTON 09001-99 elaboradas por INAA. La cual expresa de forma textual.
La dotacin de agua, expresada como la cantidad de agua por persona por da est en dependencia de:
1- Nivel de Servicio adoptado
2- Factores geogrficos
3- Factores culturales
4- Uso del agua.
a) Para Sistemas de abastecimiento de agua potable, por medio de puestos pblicos, se asignar
un caudal de 30 a 40 lppd.
b) Para sistemas de abastecimiento de agua potable por medio de conexiones domiciliares de
patio, se asignar un caudal de 50 a 60 lppd.
c) Para los pozos excavados a mano y pozos perforados se asignar una dotacin de 20 a 30
lppd.
Adems de estas dotaciones se consideraron las recomendaciones del Nuevo FISE para las dotaciones
especiales tales como el caso de escuelas y centro de salud entre otros que se detallan a continuacin.
Dotacin de servicio
Mnima

Mxima
6

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Escuela
Puestos de salud
Centro de salud
Mataderos o centros de destace
Dotacin comercial
Dotacin pblica o institucional
Dotacin industrial

57 l/alumno/da
1,000 l/da
1,000 l/da + 50 l/cama/da
1,500 l/da
7% aplicable al consumo domiciliar
7% aplicable al consumo domiciliar
2% aplicable al consumo domiciliar

75 l/alumno/da

En el caso del proyecto se utilizo una dotacin de 60lppd, la dotacin especial de escuela de
57l/alumno/dia y dotacin comercial de 7%.
3.6 ESTUDIO DE OFERTA Y DEMANDA DE AGUA
El estudio de fuentes define la cantidad de agua disponible a explotar y la demanda se determina en base
a las proyecciones de poblacin, dotaciones de acuerdo al nivel de servicio y consumos especiales.
3.7 COBERTURA Y NIVEL DE SERVICIO DEL SISTEMA
La cobertura del sistema se determinara en base a las necesidades identificadas por el comit de
seguimiento del proyecto, quienes junto a los profesionales del NUEVO FISE han definido los alcances del
proyecto, siendo la meta el dar una cobertura del 100% de la poblacin.
Puestos Pblicos
Son tomas de agua que se implantan particularmente en el sector rural para abastecer dos a un mximo
de 20 casas.
Consideraciones
Deber instalarse en terreno comunal y si es privado garantizar que pase a ser comunal.
El puesto pblico no deber ser usado para el lavado de ropa, bao de personas o animales,
lavado de maz etc.
Se cercar el puesto de tal forma que se garantice su proteccin evitando el acceso de animales.
En cada puesto pblico se colocar como mximo 2 grifos, (ver detalle)
Ubicacin
El nmero de puestos a instalarse depender de la cantidad de casas, el nmero de personas y la
ubicacin de las casas, para su ubicacin deber abastecer como mnimo dos casas.
Se ubicarn puestos en las Escuelas, Centro de Salud, Centros Infantiles.
El puesto se ubicar centralizado a las casas a servir.
La distancia mxima entre puesto y casa ms alejada ser de 100 mts.
Conexiones Domiciliares de Patio
Ver tem 3.14
El nivel de servicio del proyecto ser conexin domiciliar de patio

7
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

3.8 PRODUCCIN DE LA FUENTE DE AGUA


La fuente de abastecimiento para el suministro de agua potable, constituye el elemento ms importante de
todo el sistema, por tanto: debe estar lo suficientemente protegida y debe cumplir dos propsitos
fundamentales. El caudal crtico de produccin de la fuente deber ser mayor o igual al consumo mximo
diario demandado por la poblacin al final del perodo de diseo, de lo contrario se desechar su
utilizacin, o se complementar con otra fuente disponible.
El caudal de la fuente propuesta es de 10gpm en tiempo de estiaje y la demanda es de 6.34gpm, lo que
indica que la oferta de agua supera a la demanda.
3.9 CRITERIOS PARA EL CLCULO DEL VOLUMEN DE ALMACENAMIENTO
Los depsitos para el almacenamiento en los sistemas de abastecimiento de agua, tienen como objetivos;
suplir la cantidad necesaria para compensar las mximas demandas que se presenten durante su vida til,
brindar presiones adecuadas en la red de distribucin y disponer de reserva ante eventualidades e
interrupciones en el suministro de agua.
La capacidad del tanque de almacenamiento deber de satisfacer las condiciones siguientes:
Volumen Compensador:
El volumen necesario para compensar las variaciones horarias del consumo, se estimar en 15% del
consumo promedio diario.
Volumen de reserva:
El volumen de reserva para atender eventualidades en caso de emergencia, reparaciones en lnea de
conduccin u obras de captacin, se estimar igual al 20 % del consumo promedio diario.
De tal manera que la capacidad del tanque de almacenamiento se estimar igual al 35% del consumo
promedio diario.
3.10 CRITERIOS PARA EL DISEO DE LAS OBRAS DE CAPTACIN
La fuente de abastecimiento para el suministro de agua potable, constituye el elemento ms
importante de todo el sistema, por tanto: debe estar lo suficientemente protegida y debe cumplir dos
propsitos fundamentales.
Suministrar agua en cantidad suficiente para abastecer la demanda de la poblacin
durante el perodo de diseo considerado.
Mantener las condiciones de calidad necesarias para garantizar la potabilidad de la
misma.
Manantiales:
Los manantiales son puntos localizados en la corteza terrestre por donde aflora el agua subterrnea,
generalmente este tipo de fuentes, sufre variaciones en su produccin, asociadas con el rgimen de
lluvia en la zona. En la mayora de los casos, es de esperar que el caudal mnimo del manantial
coincida con el final del perodo seco en la zona.

8
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Los criterios para considerar un manantial como fuente de suministro de agua potable son los
siguientes:
a) El dato o datos de aforo, debern corresponder al final del perodo seco de la zona y se
tomar como base para el diseo, el mnimo valor obtenido.
b) El caudal crtico de produccin de la fuente deber ser mayor o igual al consumo
mximo diario de la poblacin al final del perodo de diseo, de lo contrario se
desechar su utilizacin, o se complementar con otra fuente disponible.
3.11 CRITERIOS PARA LA SELECCIN DE LOS DIMETROS Y TUBERAS DE LAS LNEA DE
CONDUCCIN
La lnea de conduccin es el conjunto de ductos, obras de arte y accesorios destinados a transportar el
agua procedente de la fuente de abastecimiento, desde la captacin hasta la comunidad, formando el
enlace entre la obra de captacin y la red de distribucin. Su capacidad deber ser suficiente para
transportar el gasto de mximo da. Se le deber proveer de los accesorios y obras de arte necesarios
para su buen funcionamiento, conforme a las presiones de trabajo especificadas para las tuberas,
tomndose en consideracin la proteccin y mantenimiento de las mismas. Cuando la topografa del
terreno as lo exija se debern instalar vlvulas de aire y vaco en las cimas y vlvulas de limpieza en
los columpios.
Conduccin por gravedad.
Una lnea de conduccin por gravedad es la que dispone para transportar el caudal requerido aguas abajo,
de una carga potencial entre sus extremos que puede utilizarse para vencer las prdidas por friccin,
originadas en el conducto al producirse el flujo. Debe tenerse en cuenta los siguientes aspectos
fundamentales:
La capacidad deber ser suficiente para transportar el consumo mximo diario del diseo.
La seleccin de la clase de los materiales y las dimensiones de los conductos a emplearse debern
ajustarse a la mxima economa.
La lnea de conduccin deber dotarse de los accesorios y obras de arte necesarios para su correcto
funcionamiento, conforme a las presiones de trabajo especificadas para las tuberas. Deber tomarse
en cuenta adems su proteccin y su mantenimiento.
Para el dimensionamiento de la tubera de las lneas de conduccin se aplicar la formula
exponencial de Hazen Williams, ampliamente utilizada, donde se despeja la gradiente hidrulica.
H
10.549Q
S
L
C D
Dnde:
H=
Prdida de carga en metros
L=
Longitud en metros
S=
Prdida de carga en m/m
Q=
Gasto en m3/seg
D=
Dimetro en metros
C=
Coeficiente de Hazen-Williams, cuyo valor depende del tipo de tubera utilizada.
1.85

1.85

4.87

9
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Accesorios y vlvulas.
Las lneas de conduccin por gravedad requerirn de accesorios y vlvulas para su debida operacin,
proteccin y mantenimiento. Debern tomarse en cuenta las observaciones siguientes:
Instalar cajas rompe-presin cuando las presiones estticas sobrepasen las presiones de trabajo.
En el caso de tuberas de acero, debern instalarse juntas de dilatacin, tipos flexibles, debidamente
soportados y atracados.
Cuando la topografa sea accidentada se localizarn vlvulas de aire y vaco en las cimas del perfil.
En el caso de la topografa regular o plana, estas vlvulas estarn localizadas cada 2.5 kilmetro
como mximo y en las partes ms altas de perfil.
En caso de topografa plana se provocarn pendientes del 3% en el sentido positivo y 6% en el
sentido negativo de la direccin del flujo y se ubicarn vlvulas de aire en los puntos de inflexin.
El dimetro de las vlvulas de aire y vaco se determinar en funcin del dimetro de la lnea de
conduccin. Los fabricantes generalmente recomiendan el uso de vlvulas cuyo dimetro es 1 por
pie de dimetro de la lnea de conduccin.
En los puntos ms bajos de la lnea se instalarn vlvulas de limpieza con dimetro mnimo
equivalente a del dimetro de la lnea de conduccin.
Al inicio y al final de la lnea de conduccin, debern instalarse vlvulas de compuerta para regular o
cortar el flujo cuando sea necesario.
3.12 CRITERIOS PARA LA SELECCIN DE LOS DIMETROS Y TUBERAS DE LA RED DE
DISTRIBUCIN
La red de distribucin es el sistema de conductos cerrados, que permite distribuir el agua bajo presin a
los diversos puntos de consumo, que pueden ser conexiones domiciliares o puestos pblicos; para su
diseo deber considerarse los aspectos siguientes:
Se deber disear para la condicin del consumo de hora mxima al final del periodo de diseo, el
cual resulta al aplicar el factor de 2.5 al consumo promedio diario (CHM=2.5CPD, ms las prdidas).
El sistema de distribucin puede ser de red abierta, de malla cerrada o una combinacin de ambos.
La red se deber proveer de vlvulas, accesorios y obras de arte necesarias, para asegurar su buen
funcionamiento y facilitar su mantenimiento.
Coeficiente de capacidad hidrulica (C) en la frmula de hazen Williams. Segn material de tubera
Material del conducto
Nuevos C
Inciertos C
Cloruro de polivinilo (PVC)
150
130
Asbesto cemento
140
130
Hierro fundido cubierto
130
100
Dimetro mnimo: El dimetro mnimo de la tubera de la red de distribucin ser de 1 1/2 pulgadas
Cobertura sobre tuberas: Se mantendr una cobertura mnima de 1.20 m, sobre la corona del
conducto en toda su longitud.

10
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

CRITERIOS PARA LA SELECCIN DEL SISTEMA DE DESINFECCIN


El cloro se presenta puro en forma lquida, o compuesta como hipoclorito de calcio el cual se obtiene en
forma de polvo blanco y en pastillas, y el hipoclorito de sodio de configuracin lquida.
En el caso de Acueductos Rurales se utilizara para la desinfeccin el cloro en forma de hipocloritos, debido
a su facilidad de manejo y aplicacin. Se deber tener el debido cuidado para el transporte, manipuleo del
equipo requerido, disponibilidad suficiente y seguridad en cuanto al almacenamiento. El tiempo de
almacenamiento para el hipoclorito de sodio no debe ser mayor de un mes y para el de calcio no mayor de
tres meses.
Se recomienda que el tiempo de contacto entre el cloro y el agua sea de 30 minutos antes de que llegue al
primer consumidor; en situaciones adversas se puede aceptar un mnimo de 10 minutos. La
concentracin de cloro residual que debe permanecer en los puntos ms alejados de la red de distribucin
deber ser 0.2-0.5 mg/l despus del perodo de contacto antes sealado.
3.13 CRITERIOS PARA EL DISEO DE LAS CONEXIONES DE PATIO
Son tomas de agua que se aplican en el sector rural, pero en ocasiones espordicas y sujetas a ciertas
condiciones, tales como disponibilidad suficiente de agua, bajos costos de operaciones, capacidad de
pago de la poblacin, y nmero de usuarios del servicio.
Las condiciones sociales y tcnicas son las siguientes:
Condiciones Sociales
Deber realizarse un estudio cuidadoso para considerar las posibilidades econmicas de la
comunidad para construir un sistema con tomas domiciliares.
Deber realizarse una campaa educativa a la comunidad en cuanto al uso y ahorro del agua y
proteccin del Sistema, ya que cada llave quedar dentro de cada casa.
Condiciones Tcnicas
La comunidad deber aportar parte de la tubera a utilizarse en las tomas domiciliares. La conexin
domiciliar llegar hasta el lindero de la propiedad, a partir de ah la conexin correr por cuenta del
propietario.
El flujo de un grifo deber ser de 0.10 lps mnimo y 0.30 lps mximo.
Se recomienda usar un flujo menor para no desgastar los empaques en muy corto tiempo. Se puede
controlar el flujo con una vlvula de tapn (globo de en la entrada del puesto). Al instalar la vlvula,
tiene que ajustarse, para que se obtenga el flujo deseado.
La carga residual mnima deber ser de 5 mts y mxima 50 mts. Se recomienda cargas menores que
la mxima permisible, porque se controla mejor el sistema y se presenta menor desgaste de los
empaques y accesorios.
El dimetro de las conexiones y de los grifos ser de (12 mm.)
Toda conexin domiciliar deber estar siempre controlada por su medidor correspondiente o por un
regulador de flujos.

11
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

3.14 PRESIONES DE TRABAJO PERMITIDAS


Para brindar presiones adecuadas en el funcionamiento del sistema de abastecimiento se recomienda que
stas se cumplan dentro de un rango permisible, en los valores siguientes:
La presin mnima residual en la red principal ser de 14.00 m.
la carga esttica mxima ser de 50.00 m.
Se permitirn en puntos aislados, presiones estticas hasta de 70.00 m., cuando el rea de servicio
sea de topografa muy irregular.
3.15 VELOCIDADES PERMITIDAS
Se recomienda fijar valores de las velocidades del flujo en los conductos en un rango para evitar erosin
interna o sedimentacin en las tuberas. Los valores permisibles son los siguientes:
Velocidad mnima = 0.6 m/s
Velocidad mxima = 2.0 m/s

12
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

4. ESTUDIOS Y DISEOS FINALES DE LOS ELEMENTOS DEL SISTEMA


4.1

MEMORIA TCNICA

En este tem se describe toda la memoria de diseo hidrulico de cada uno de los elementos del sistema,
utilizando para ello los resultados de los estudios de campo y gabinete realizados, tales como: poblacin,
tasas de crecimiento, dotaciones, topografa, estudio de fuente y otros.
4.1.1

HIDRULICA OPERACIONAL

Los estudios realizados indican que la fuente ms ptima para abastecer a la comunidad es una fuente
superficial, localizada en la comunidad, por lo que se propone un mini acueducto por gravedad, conocido
como MAG.
El sistema estar conformado por una obra de captacin de agua superficial propuesta a construirse; la
cual contara con dispositivos de limpieza y mantenimiento como malla en la tubera de salida, vlvulas de
pase, vlvula de salida etc. que permitan un buen funcionamiento de la misma. De esta caja de captacin
saldr la lnea de conduccin por gravedad de 382 ml tubera PVC-SDR-26, de 2, que tambin contara
con dispositivos que permitan su buen funcionamiento, tales como vlvulas de limpieza, vlvulas de aire
etc. las cuales sern ubicadas de acuerdo lo demande la topografa del terreno, en la lnea de distribucin
estarn ubicadas dos obras de tratamiento de agua ( filtro dinmico y aireador), la lnea de conduccin
descargara en el tanque de concreto ciclpeo, desde donde el agua se distribuir por gravedad a la red de
distribucin, se propone construir toda la red de distribucin para garantizar el abastecimiento a todas al
mayor nmero de viviendas posible, adems se propone construir conexiones domiciliares.
4.1.1.1 DATOS PARA EL MODELAJE EN EPANET V.2.0
A continuacin se procede a la, con el fin de obtener el diseo final de los elementos que conformaran el
sistema.
Para realizar la modelacin hidrulica y dimensionamiento del sistema propuesto se har uso del
programa EPANET V.2.0, los datos de entrada al programa con son dimetro, material y longitud de las
tuberas se propusieron en base a criterios tcnicos.
A continuacin se presentan los datos por nodo y por tubera introducidos al programa para efectuar la
modulacin del sistema:

13
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

En la red propuesta se propone un tanque de almacenamiento, a continuacin se detallan los datos


utilizados en el tanque propuestos.

14
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Datos de tanque
Tanques
Tanque No.1

Cod.
EPANET
TQ1

Cota de
Dimetro
solera
390.50

2.59

N. mx.

N. mini.

1.85

0.2

N. Inicial
0.3

Donde:
Cota de solera (m): Cota en metros del fondo del depsito, respecto a un nivel de referencia
comn. .
Nivel Inicial (m): Nivel del agua en el depsito respecto al fondo del tanque, al comienzo de
la simulacin, en este caso ser de 0.3 m.
Nivel Mnimo (m): Nivel mnimo del agua respecto al fondo del tanque a mantener en el
depsito, durante la simulacin no se permitir que el agua descienda por debajo de dicho
nivel, ser de 0.20 m.
Nivel Mximo (m): Nivel de rebose del tanque.
Dimetro (m): Dimetro del depsito, en metros para depsitos cuadrados o rectangulares,
se calcula un dimetro equivalente con la siguiente frmula 1,128 A del tanque.
RESULTADOS DEL ANLISIS HIDRULICO (ESTTICO Y DINMICO)
A continuacin se presenta el anlisis hidrulico de la red de distribucin, analizando las siguientes
condiciones de trabajo.
a) 1ra. condicin, consumo mxima hora en la red de distribucin, para un periodo de
diseo de 20 aos.
b) 2da. Condicin, consumo mximo da en la red de distribucin, para un periodo de
diseo de 20 aos.
c) 3ra. Condicin, sin consumo en la red.

15
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Para realizar el anlisis hidrulico se estimo la demanda por nodos, a continuacin se presenta un
cuadro con el clculo de las demandas por nodos.
Carga por nodos

A continuacin se presenta el grafico con los nodos, tuberas, tanque propuesto y sentido del flujo en
las tuberas.
ESQUEMA HIDRAULICO DEL SISTEMA
La red est constituida 3 ramales, con una extensin de total de 3, 382.11 ml, conformada con
tubera PVC SDR-26 de dimetros de 2 y 1 pulgadas.
ESQUEMA HIDRAULICO PARTE 1

16
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

A continuacin se presentan las tablas de resultados hidrulicos de la condicin ms crtica como es


la condicin de consumo de mxima hora.

17
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

1ra. condicin, consumo mxima hora en la red de distribucin, para un periodo de diseo de
20 aos.
Esta condicin de anlisis simula a la red de distribucin trabajando con los caudales mximos
esperados en la red, que corresponden a la condicin de consumo de mximo da, para conocer las
presiones ms bajas esperadas en la red.
Se propone una red conformada por tuberas PVC SDR-26 de 2 y 1 de acuerdo a los estudios de
investigacin de tipo de suelo en la zona los suelos son tierras sueltas, fciles de excavar por lo que
se recomienda instalar las tuberas a la profundidad recomendada en las normas de 1.20m.
La red estar conformada por unos 1,759.68 m de tubera PVC SDR-26 de 2 y 1, 622.43 m de
tubera PVC SDR-26 de 1 .

Cuadro Estado de los nodos de la red

18
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

19
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Cuadro Estado de las lneas de la red

En los anlisis realizados se pueden observar que las velocidades en las tuberas son bajas aun
cuando se usa el dimetro mnimo de 1 , en algunos puntos de la red, esto no implica un mal
funcionamiento del sistema, simplemente la velocidad mnima garantiza la autolimpieza de las
tuberas, para garantizar la misma se proponen vlvulas de limpieza en los puntos crticos de la red
(ver planos de obras propuestas). Las presiones estn dentro del rango deseado, siendo la presin
mnima de 11.82 m en el nodo No.15 y la presin mxima de 28.86 en el nodo No.24.

20
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

2da. Condicin, consumo mximo da en la red de distribucin, para un periodo de diseo de


20 aos.
Cuadro Estado de los nodos de la red

21
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Cuadro Estado de las lneas de la red

Las presiones estn dentro del rango deseado, la presin mnima es de 17.66 m en el nodo No.15 y
la presin mxima es de 35.40 en el nodo No.24.

22
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

3ra. Condicin, sin consumo en la red.


Esta condicin de anlisis simula a la red de distribucin trabajando con los caudales cero, La
condicin sin consumo es donde se presentan las presiones ms altas en la red y nos permite prever
la capacidad que tienen que tener las tuberas para soportar las presiones esperadas o bien los
cambios requeridos en el sistema para reducir las presiones de trabajo en la red.
Cuadro Estado de los nodos de la red

Podemos observar que las presiones en la red estn dentro del rango deseado, la presin mnima es
de 20.27 m en el nodo No.2 y la presin mxima es de 39.55 en el nodo No.24, la presin mxima
del sistema es menor que la mxima que soporta las tuberas PVC-SDR 26 que es de 110 m.c.a.
23
FIRMA CONSULTORA: CONDISA
Diseo: Ing. Mirta Violeta
Bravo M.

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

4.1.1.2 CONCLUSIONES
En todas las condiciones de anlisis las presiones estn dentro de los rangos mnimos y
mximos recomendados, por lo que se puede concluir que la tubera propuesta PVC-SDR-26 es
idnea para estas condiciones de trabajo.
La red estar conformada por unos 1,759.68 m de tubera PVC SDR-26 de 2 y 1, 622.43 m de
tubera PVC SDR-26 de 1 .
4.1.1.3 RECOMENDACIONES
Se recomienda la construccin de la red de distribucin con tuberas PVC-SDR-26 de 2 y 1 .
Se recomienda la construccin de tanque de almacenamiento de 2,500 galones, ubicado sobre
la cota 390.50 msnm, para garantizar las presiones mnimas y mximas requeridas para el
funcionamiento de la red.
4.1.2

DISEO ESTRUCTURAL DEL TANQUE

Ver memoria de diseo estructural de tanque en anexo No.12.8

24
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

5. CONCEPTUALIZACIN DEL PROYECTO DE AGUA POTABLE


5.1 GENERALIDADES
El proyecto a ejecutar ser un MAG (Mini acueducto por gravedad). El abastecimiento de agua a la
comunidad de El Achiote se realizara mediante un sistema que opera totalmente por gravedad. Como
fuente de abastecimiento se propone un manantial que se localiza en el Cerro 14, localizado al oeste de la
comunidad.
El caudal que esta fuente produce en verano que es el periodo crtico debido a la ausencia de lluvias,
segn aforo realizado es de 10gpm, esta oferta de agua supera la demanda del proyecto. El caudal a
servir ser captado mediante una caja recolectora, desde donde saldr la lnea de conduccin por
gravedad hasta el tanque de almacenamiento propuesto.
Para mejorar la calidad fsica qumica y bacteriolgica del agua se propone un prefiltro grueso y un
aireador de bandejas.
5.2 PROYECCIN DE OFERTA Y DEMANDA DE AGUA
Los clculos de la oferta y demanda de agua del proyecto se realizaron los criterios citados en el captulo 3
de este informe. A continuacin se presentan las tablas de clculo de las proyecciones de oferta y
demanda, como tambin las proyecciones de poblacin.

25
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

26
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

27
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

28
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

29
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

30
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

31
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

32
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

33
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

5.3 CAUDALES DE DISEO


De acuerdo a las proyecciones de demanda el caudal de diseo para la fuente y la lnea de conduccin
para un periodo de 20 aos es de 0.40l/s, que corresponde al caudal de mximo da al final del periodo.
El caudal de diseo para la red de distribucin corresponde a la demanda de consumo de mxima hora al
final del periodo que es de 0.67l/s.
5.4 CAPACIDAD DE LA FUENTE
De acuerdo a aforo realizado en tiempo de estiaje el caudal de la fuente es de alrededor de 10gpm unos
0.63l/s, este caudal es superior a la demanda de consumo de mximo da al final del periodo que es de
0.40l/s. Por lo que se puede decir que la fuente propuesta tiene capacidad suficiente para suplir al
proyecto durante la vida til proyectada.
5.5 DESCRIPCIN DETALLADA DEL SISTEMA
El sistema propuesto para abastecer de agua potable a la comunidad de El Achiote consiste en la
construccin de un mini acueducto por gravedad (MAG).
5.5.1

FUENTE Y OBRA DE TOMA

Para el abastecimiento del sistema se har uso de la fuente Cerro 14, que se encuentra en predios
propiedad de la comunidad, para captar el agua se propone una caja de concreto, a continuacin se
muestra esquema de la captacin propuesta;

34
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
403

402

401

400

35
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

PLANTA - CAPTACION

36
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

5.5.2

CONFIGURACIN DE LA LNEA DE CONDUCCIN

La lnea de conduccin propuesta estar formada por tuberas de 2 PVC SDR-26, y tendr una
longitud de 649.80 ml.
Estn ubicados en la lnea distintas obras de tratamiento como es el filtro grueso dinmico y el
aireador. Debido a la topografa de la zona y que el sistema trabaja totalmente por gravedad, la
obras de tratamiento no se pueden ubicar en el mismo predio, las misma se propusieron a la largo
de la lnea de conduccin para garantizar las presiones mnimas en los diferentes punto.
Del punto 1 -2 la tubera tendr que profundizarse esto debido el pto 2 esta 2.85 m ms alto que la
obra de captacin, por lo cual no podra servirse la lnea de conduccin por gravedad, para pasar
este punto se deber de profundizar la tubera 3.60 m. (ver plano constructivo).
El filtro grueso dinmico se ubico en la estacin 0+190, se ubico el filtro en este punto donde se
garantiza un presin en la entrada del mismo de 1.69m, y en este punto la presin se hace cero, y es
este dispositivo el que garantiza la presin de la lnea de conduccin aguas abajo, por lo cual
garantiza una presin de entrada en el aireador de 3.18m, presin suficiente para el funcionamiento
del aireador, el mismo se ubico en la Est. 0+400.
Se garantizo una presin de entrada al tanque de almacenamiento de 4.93 m.c.a. Las normas de
INAA indican que la presin mnima de la lnea de conduccin deber de ser de 5 m.c.a. debido a la
topografa de la zona, esto no puedo garantizar en la lnea, pero si se tienen presiones de trabajo
que garanticen que las obras propuestas trabajen eficientemente.
En los puntos bajos de la lnea de conduccin se propone vlvulas de limpieza de 2 y en los puntos
altos se proponen vlvulas de aire de . Ver planos constructivos.
A continuacin se muestra el clculo de la lnea de conduccin:

1
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y Saneamiento El Achiote Cdigo


19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

1
FIRMA CONSULTORA: CONDISA

Diseo: Ing. Mirta Violeta Bravo M.

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

5.5.3

OBRAS DE TRATAMIENTO

FITRO GRUESO DIMANICO


Debido a los niveles de turbiedad que presenta la fuente de abastecimiento estn un poco elevados
en relacin al valor mximo recomendado en la norma CAPRE, se propone un filtro grueso dinmico
para mejorar la calidad del agua.
Se proponen dos unidades de filtracin y as garantizar el funcionamiento del sistema an cuando se
le de mantenimiento al mismo.
A continuacin se muestra el clculo del filtro, el clculo indica que ser necesario un filtro de dos
unidades, que garanticen un rea superficial de 0.37 m 2 por unidad.

Se requieren dos unidades de pre filtracin cada una de 0.80m de ancho y 2.40m de largo.
1
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

2
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

AIREADOR DE BANDEJAS
Para la remocin del hierro presente en el agua se propone un aireador, el dimensionamiento resulta
que es necesario un aireador con un altura de 2.1m, de 4 bandejas de 1x1m, a continuacin se
muestra tabla donde se dimensiona el mismo:

3
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

DESINFECCION
Para la desinfeccin del agua como medida profilctica, se recomienda la aplicacin de cloro. La
caracterstica principal del cloro para su uso como desinfectante es su presencia continua en el agua
como cloro residual. Adems, el cloro no solo acta como desinfectante, sino que tambin reacciona
con otros elementos presentes en el agua, como amoniaco, hierro, manganeso y otras sustancias
productoras de olores y sabores, mejorando la calidad del agua.
4
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

El sistema propuesto para la cloracin es un dosificador sencillo, que consiste en un recipiente


plstico con una benoclipsis para regular goteo, protegidos con pequea caseta, que se instalara
sobre la losa del tanque de almacenamiento sobre suelo. Similar al del esquema que se presenta a
continuacin.
CLAVADOR DE
2"x2" CORRIDA
CON 2 MANOS DE
PINTURA

LAM. DE 4'
ZINC ONDULADO
CAL.26.

PIEZA DE MADERA
DE 4"x2"VERTICAL
H=1.10m, PROTEGIDA
CON 2 MANOS DE PINTURA

CLAVOS DE 4"
PARA FIJAR
PIEZA DE MADERA

1
.1
0

SIN FORRO

PIEZA DE MADERA
DE 4"x2"CORRIDA
PROTEGIDA CON 2
MANOS DE PINTURA

BIDON
PLASTICO
DE 5Gls.
ESPICHE DE
MADERA

CLAVOS DE 4" PARA


FIJAR PIEZA DE
MADERA A TANQUE

LOSA DE CONCRETO
REFORZADA.
SECC. A DE CASETA DE PROTECCION
DE HIPOCLORADOR

DET. DE HIPOCLORADOR

5
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Caudal de agua
a clorar
en GPM en LPS
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

0.06
0.13
0.19
0.25
0.32
0.38
0.44
0.50
0.57
0.63
0.69
0.76
0.82
0.88
0.95
1.01
1.07
1.14
1.20
1.26

Caudal de mezcla de cloro


Al 1%
ml/hora gotas/min
45.42
15
90.84
30
136.26
45
181.68
60
227.10
76
272.52
91
317.94
106
363.36
121
408.78
136
454.20
151
499.62
166
545.04
181
590.46
196
635.88
211
681.30
227
726.72
242
772.14
257
817.56
272
862.98
287
908.40
302

Al 0.5% (**)
ml/hora gotas/min
90.8
30
181.7
61
272.5
91
363.4
121
454.2
151
545.0
182
635.9
212
726.7
242
817.6
273
908.40
303
999.2
333
1090.1
364
1180.9
394
1271.8
424
1362.6
454
1453.4
485
1544.3
515
1635.1
545
1726.0
576
1816.8
606

(**) Esta es la concentracin que se obtiene de los equipos que producen cloro por electrolisis

En Tabla se presenta el clculo para la dosificacin de cloro que se le debe agregar al equipo de
cloracin hidrulico. Una vez preparada la mezcla, se vierte en el equipo de cloracin, se regula de
acuerdo al caudal que llega al tanque y se deja dos das como mximo, que es el tiempo adecuado
de duracin de la mezcla.
El caudal que llegar al tanque de esta comunidad es de 6.50 gpm.
5.5.4

TANQUE DE ALMACENAMIENTO

De acuerdo a los clculos de proyecciones de demanda de almacenamiento, en la comunidad se requiere


construir un tanque con capacidad de almacenamiento de 8.10m aproximadamente 2,141.00 galones, se
propone un tanque de 2,500 galones, las dimensiones del tanque propuesto son las siguientes:
Ancho interno = Largo interno = 2.40m
Ancho externo = Largo externo = 6.20m
Altura de agua = 1.85m
Altura Total = 2.40m
6
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

El tanque se localizara en un predio con un rea de 4,234.78 ml, estar totalmente protegido por un cerco
de alambre de pas de 7 hiladas y un portn de acceso tambin de alambre de pas.
A continuacin se presenta un esquema de tanque propuesto.
2.80

LOSA SUPERIOR
DE CONCRETO

VIGA VC-1

0.25
TUBERIA DE ENTRADA
=1 1/2" HG

NIVEL DE REBOSE

PELDAOS VAR. # 6
GALVANIZADA
@ 0.30 m A/C

1.00

2.15

1.85
LOSA DE CIMENTACION
DE CONCRETO
MALLA DE VAR. # 4
@ 0.20 m A/D

TUBERIA DE LIMPIEZA
3" HG

0.90
P=1%

5.5.5

0.10

CONFIGURACIN DE LA RED DE DISTRIBUCIN

La red de distribucin propuesta estar conformada por tuberas de 2 y 1 , PVC SDR-26, la red estar
formada por 3,382.12 ml de tuberas, distribuidas de la siguiente manera: 1,759.68 ml de tuberas PVC
SDR-26 de 2 y 1,622.44 de tuberas PVC SDR-26 de 1
A continuacin se muestra esquema de la configuracin de la redes.

7
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

8
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y Saneamiento El Achiote Cdigo


19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

1
FIRMA CONSULTORA: CONDISA

Diseo: Ing. Mirta Violeta Bravo M.

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

5.5.6

CONEXIONES

Se proponen 22 conexiones domiciliares para abastecer a toda la comunidad.


5.5.7

CONCLUSIONES Y RECOMENDACIONES

CONCLUSIONES
La demanda para el final del periodo de diseo es para CPD de 0.27 l/s, CMD 0.40 l/s y CMH de 0.67
l/s.
Se propone construir una obra de captacin.
La lnea de conduccin ser de 383.0 ml de PVC SDR-26 de 2 pulg.
Se propone un filtro lento dinmico, aireador de bandeja y cloracin como tratamiento de potabilizacin
de la fuente de agua.
Se propone un tanque de almacenamiento de concreto ciclpeo sobre suelo de 2,500 gal.
La red de distribucin estar formada por 3,382.12 ml de tuberas, distribuidas de la siguiente manera:
1,759.68 ml de tuberas PVC SDR-26 de 2 y 1,622.44 de tuberas PVC SDR-26 de 1
RECOMENDACIONES
La falta de un sistema de agua sanitariamente segura, ha causado en la comunidad muchos
problemas de salud a la poblacin, evitando adems su desarrollo como comunidad, por lo que se
recomienda dar atencin a esta problemtica, construyendo el sistema de abastecimiento tipo MAG
propuesto, esto causara un gran impacto en la calidad de vida de los comunitarios.
5.6 CRONOGRAMA DE EJECUCIN

1
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

6. COMPONENTE DE SANEAMIENTO
6.1 SITUACION ACTUAL DEL SANEAMIENTO
En la visita a la comunidad se pudo observar que las letrinas que predominan en la comunidad son
letrinas sencillas con caseta de madera, banco de madera y techo de zinc.

Letrinas existentes en la comunidad de El Achiote, en algunas viviendas que cuentan con


este tipo de instalacin, fecha: abril 2012.

2
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

En el trabajo de campo se investig que las letrinas existentes son de madera y estn construidas a
nivel del suelo, a pesar de que la zona es bastante lluviosa, observando que alrededor de algunas
de ellas hay presencia de charcos y reas lodosas.
Tambin se determin que los suelos de la zona son suelos arcillosos y que el nivel fretico se
encuentra en el invierno a unos 15m.
Con las condiciones encontradas en la zona del proyecto, se recomienda que en caso de
construccin de letrinas se construyan letrinas semi elevadas y a nivel de suelo, segn las
condiciones del lote y que las fosas sean totalmente revestidas.
6.2 JUSTIFICACION DEL PROYECTO
La cobertura del saneamiento en el medio rural segn estimaciones realizadas a partir de los resultados
del censo 2005 est por el orden del 69.6 %. En estos datos se incluyen a todas las personas que estn
recibiendo diferentes niveles de atencin por medio de diversos tipos de sistemas de disposicin de
excretas. Esta informacin nos revela el gran dficit existente de servicios de saneamiento, lo que trae
consigo el deterioro en los niveles de vida de residentes y usuarios de las comunidades y reduce
drsticamente las condiciones higinico-sanitarias a niveles crticos, creando peligros latentes de
contaminacin y enfermedades.
Actualmente este nuevo programa de PRASNICA, tiene como objetivo incrementar la cobertura de
saneamiento rural en un 1 % anual durante los cinco aos de duracin del proyecto.
7. DESCRIPCION DE LOS ESTUDIOS E INVESTIGACIONES REALIZADAS
7.1 CATASTRO Y DIAGNOSTICO DE LOS DISPOSITIVOS DE SANEAMIENTO EXISTENTE
La encuesta realizada indica que en la comunidad existen 14 letrinas de las cuales 2 letrinas en
buen estado, 7 en regular estado y 5 en mal estado. De las 22 viviendas de la comunidad 8 no
cuentan con letrinas, por lo que estas familias tienen que defecar al aire libre. Esta informacin nos
permiti determinar que existe una demanda de 20 unidades de saneamiento en la comunidad, ms
2 unidades de saneamiento que se proyectan en las escuelas de la comunidad.
De la poblacin beneficiada con el proyecto, el 65% tiene letrina, siendo la diferencia el 35% los que
no poseen este servicio. Las letrinas que poseen las personas se encuentran en mal estado en un
36% y son utilizadas por los nios, adultos, por lo que Se requiere un proyecto urgente para el
manejo adecuado de las excretas a fin de evitar la contaminacin del ambiente con heces fecales.

Tenencia de letrina: El 65% de las viviendas tienen letrina.

Estado de la letrina: En 14 hogares que tienen letrina se presenta el siguiente estado de las
letrinas:
CATEGORA

Buena
Regular
FIRMA CONSULTORA:
CONDISA
Bravo M. Mala
Total

N
%
2
14%
7Diseo: Ing. Mirta
50% Violeta
5
36%
14
100%

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Tipo de suelo donde se construy letrina: En 14 hogares se presenta la siguiente situacin:

7.2 ASPECTOS AMBIENTALES DEL SUBPROYECTO


7.2.1

REQUISITOS AMBIENTALES

De los diferentes tipos de letrinas que existen se consideran apropiadas para el sector rural disperso: la
letrina tradicional o sanitaria, la abonera y la de hoyo seco ventilado. Para la seleccin de cualquiera de los
tipos anteriores deber considerarse lo siguiente:
Ubicacin con respecto a la vivienda: La vivienda debe de disponer terrenos suficientes que permita la
ubicacin de la letrina como mnimo a 5 metros de la vivienda.

4
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Tipo de suelo: Debe valorarse tanto la permeabilidad como la estabilidad. As los suelos permeables
facilitan la infiltracin de los lquidos dispuestos en los hoyos y por lo tanto son aptos para todo tipo de
letrinas Mientras que los suelos rocosos son difciles de excavar y para estos casos se recomienda la
letrina abonera. La estabilidad del suelo define la necesidad de recubrimiento de las paredes del hoyo. De
esta manera cuanto ms inestable sea el suelo, ser necesario el empleo de materiales resistentes.
Nivel del agua subterrnea: En ocasiones, el nivel de las aguas subterrnea limita la excavacin de los
hoyos. Dependiendo del nivel del manto fretico se podrn construir cmaras sobre el nivel del suelo o
excavar hoyos hasta donde lo permita el nivel mximo de las aguas.
Costo del sistema de disposicin: el costo de la letrina tradicional o la seca ventilada es inferior a la
letrina abonera, por lo que este ser otro de los factores a considerar para la toma de decisin en la
seleccin.
Para evitar la contaminacin por coliformes fecales de pozos excavados a mano o perforados, y malos
olores, se establece una distancia mnima entre las letrinas y las siguientes estructuras:
Letrina - Pozo excavado
20.0 metros
Letrina- Vivienda
5.0 metros
Letrina- Linderos de propiedad
5.0 metros
Letrina-Tanque de Agua sobre suelo
10.0 metros
Letrina-Tanque de Agua Sobre torre
8.00 metros
Letrina- tubo de A. Potable
3.0 metros
Letrina Pozo Perforado
300.0 metros
As mismo la letrina se orientar de acuerdo al rgimen de vientos predominantes de forma tal que el
arrastre de malos olores no se produzca hacia las viviendas.
En el caso de terrenos con fuertes pendientes se procurar que la letrina se ubique en la parte ms baja
de la pendiente.
La distancia vertical mnima entre el fondo del foso y el nivel fretico de las aguas, se establece en 3.0
metros, en el caso que no se pueda cumplir con esta disposicin, usar Letrina Elevada.
Para la instalacin de letrinas en reas de desarrollo de viviendas, debe de tratarse que stas se ubiquen
en una misma direccin o lnea, previendo siempre que no se contaminen los pozos de agua, los que
tambin deben localizarse en una misma direccin y a los mismos retiros de las letrinas.
Cuando se disponga informacin sobre la direccin del movimiento del agua subterrnea, la letrina se
ubicar aguas debajo de cualquier fuente de abastecimiento.
7.2.2

EVALUACION DEL EMPLAZAMIENTO

La evaluacin del emplazamiento permite valorar las caractersticas generales del sitio y el entorno
donde se propone ubicar el proyecto para evitar o prevenir potenciales riesgos e impactos
ambientales que atentan contra la sostenibilidad y la adaptabilidad del proyecto, tales como:
Peligrosidad del sitio debido a factores naturales o antrpicos que pueden daar el proyecto.
Evitar efectos ambientales negativos del proyecto.
5
FIRMA CONSULTORA: CONDISA
Diseo: Ing. Mirta Violeta
Bravo M.

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Valorar e identificar aspectos legales, tcnicos y normativos del proyecto que entren en
contradiccin con el marco jurdico.
Evitar efectos sociales indeseables generados por el proyecto.
Buscar la mxima adaptabilidad entre el sitio y el tipo de proyecto.

A continuacin se muestra la evaluacin de emplazamiento del componente de saneamiento.

6
FIRMA CONSULTORA: CONDISA
Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

FONDO DE
INVERSIN SOCIAL
DE EMERGENCIA

NUEVO FISE

SISTEMA DE GESTION
AMBIENTAL (SISGA)

INSTRUMENTO DE
EVALUACION DE
EMPLAZAMIENTO

TITULO: Construccin

ELABORADA:
Julio 2012

Actualizada:

VIGENTE
DESDE:
Julio 2012

CANTIDAD DE
PGINAS:
2

del Sistema de Agua y Saneamiento El Achiote

HISTOGRAMA DE EVALUACION DEL EMPLAZAMIENTO DEL PROYECTO


NOMBRE DEL PROYECTO: Construccin del Sistema de Agua y Saneamiento El Achiote
COMPONENTE A CONSIDERAR: Saneamiento
CODIGO DEL PROYECTO: 19200
DEPARTAMENTO/REGION: RAAS
COMUNIDAD: El Achiote

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

La evaluacin de emplazamiento de saneamiento indica lo siguiente:


Dado que el Valor Total (ExPxF / PxF) result de 2.33 el sitio de emplazamiento de esta obra es poco
peligroso, tiene muy bajo riesgo y bajo deterioro de la calidad ambiental por lo que se considera un sitio
elegible para el desarrollo de la inversin.

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y Saneamiento El Achiote


Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

7.2.3

ANLISIS AMBIENTAL DEL SUBPROYECTO


VALORACIN DE LA CALIDAD AMBIENTAL SIN EL PROYECTO.
CRITERIOS
CAUSA

-Quema a cielo abierto

EFECTO
Contaminacin del aire por la emisin
de humo y gases
Contaminacin de las aguas
superficiales con repercusin en la
salud y el ecosistema

-Deficiente higiene comunal


-Vertido desechos slidos en
cauces, y fuentes de agua
superficiales
Usos de plaguicidas utilizados en
las reas de cultivo
Mal estado de las letrinas, o
inexistencia de las misma
-Ausencia de rgimen de usos de Afectacin a suelos de calidad edfica,
suelos
daos a la produccin agrcola
-Deforestacin
-Procesos de erosin, sedimentacin,
prdida de especies de alto valor, dao
al hbitat de la fauna, descenso en la
cantidad se precipitaciones y aguas
superficiales.
-Deforestacin
Disminucin de la capacidad de
almacenamiento de la cuenca.
-Crecimiento
poblacional
no -Ausencia o deficiente tratamiento
planificado.
adecuado de los desechos slidos y
lquidos.

Promedio

Poblaci
n
Afectada
3

2
2

2
2

2
3

2.4
2.4

2.0

2.4

1.8

1.6

2.2

Intensidad

Superfi
cie

Recuperac
in

Duraci
n

3
2

3
3

2.2

10

FIRMA CONSULTORA: CONDISA

Diseo: Ing. Mirta Violeta Bravo M.

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y Saneamiento El Achiote


Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Ausencia de justicia social

Deterioro de la calidad de vida


-Inseguridad ciudadana, vandalismo
-Vulnerabilidad social, pobreza, Litigios
territoriales
-Vulnerabilidad social
Las alteraciones sobre la salud dependen en
gran medida de los niveles de inmisin que
Deficiente acceso a la educacin y
se produzcan (medios o episdicos) y de las
otros servicios bsicos
caractersticas de la poblacin,
especialmente la estructura de edades.
VALOR PROMEDIO DEL ESTADO ACTUAL DEL MEDIO
24.60/11=2.23

2.8

2.8

11

FIRMA CONSULTORA: CONDISA

Diseo: Ing. Mirta Violeta Bravo M.

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Los efectos de la deforestacin representan una situacin riesgosa para la ejecucin del proyecto, que
afecta el puntualmente el criterio de poblacin, por lo que se proponen las medidas de mitigacin
pertinentes.
IDENTIFICACION DE LOS IMPACTOS DEL PROYECTO
ESTADIO DEL
PROYECTO
Construccin

ACCIONES IMPACTANTES

EFECTOS

Trabajos preliminares (limpieza


y descapote)

Produccin de polvo
Produccin de desechos
orgnicos e inorgnicos
Generacin de empleo
Produccin de polvo
Produccin de ruidos

Trabajos
letrinas

Funcionamiento

de

construccin

Funcionamiento del Sistema

Riesgo de inestabilidad
de tierras en excavacin
de fosas.
Produccin de excretas
Riesgo de dao a la
infraestructura pblica o
privada
Riesgo de contaminacin
por falta de higiene en la
manipulacin
Deterioro del servicio ante
deficiencias
de
funcionamiento del comit
de Agua potable lo que
afecta la sostenibilidad
del proyecto
Reduccin del % de
beneficiarios del proyecto
calculados en el diseo

FACTOR AMBIENTAL
AFECTADO
Calidad del aire
Calidad de vida
Calidad del aire
Ruidos
Geologa

Suelo Calidad de vida


Medio Construido

Salud Humana

Calidad de vida

Economa

12

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y Saneamiento El Achiote


Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

VALORACIN DE LOS IMPACTOS DEL PROYECTO


CRITERIOS
ACCION IMPACTANTE

EFECTO

Produccin de polvo
Produccin de desechos orgnicos e
inorgnicos
Produccin de polvo
Trabajos de construccin de pozos de Produccin de ruidos
letrinas
Riesgo de inestabilidad de tierras en
excavaciones.
Produccin de excretas
Riesgo de dao a la infraestructura
pblica o privada
Funcionamiento del sistema
Riesgo de contaminacin
Deterioro
del
servicio
ante
deficiencias de funcionamiento del
comit de Agua potable lo que afecta
la sostenibilidad del proyecto
Reduccin del % de beneficiarios del
proyecto calculados en el diseo
VALOR PROMEDIO DEL ESTADO DEL MEDIO CON PROYECTO
26.8/10=2.68
Trabajos preliminares
descapote)

(limpieza

Intensida
d

Superfi
cie

Recuperac
in

Duraci
n

3
2

3
3

3
3

3
3

Poblaci
n
Afectad
a
3
3

3
2
2

3
3
2

3
3
3

3
3
3

2
2
2

2.8
2.6
2.4

2
3

2
3

3
3

3
3

3
3

2.6
3

2
2

3
2

3
2

3
2

3
2

2.8
2

2.8

Promedio

3
2.8

El valor promedio del estado del medio con proyecto es de 2.68 lo que indica que el proyecto tiene poca incidencia o relevancia ambiental y
las afectaciones al medio son pocas y fciles de controlar.
13

FIRMA CONSULTORA: CONDISA

Diseo: Ing. Mirta Violeta Bravo M.

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

PRONOSTICO DE LA CALIDAD AMBIENTAL DEL MEDIO CON PROYECTO.


Interpretacin de los impactos en la fase de construccin
En la fase de construccin se dan muchos aspectos negativos y es de esperarse debido a las
excavaciones para la instalacin de las unidades de saneamiento se producen tolvaneras que
incrementan el nivel de partculas de polvo en el rea afectada adems de los peligros de derrumbe
de las fosas spticas.
La duracin de esta fase del proyecto en cuanto a tiempo es reducida y eso hace que los efectos sean
considerados como temporales, implicando adems la reversibilidad a corto plazo para la mayora de
los factores impactados.
Interpretacin de los impactos en la fase de operacin
En esta fase desde el punto de vista positivo los factores ambientales que sern beneficiados son los
aspectos de salud, pues si la poblacin cuenta con saneamiento, las condiciones ambientales del
sector mejoraran significativamente, incrementando el nivel de vida de sus pobladores y trayendo
consigo la reduccin de las enfermedades producidas por la contaminacin de excretas, esto se
reflejar en la reduccin de los ndices de morbilidad y mortalidad de la infancia, as como tambin en
la disminucin de las enfermedades diarreicas.
En conclusin se puede notar que aunque se observa bastante balanceado el peso de los impactos
positivos y negativos, el mayor peso corresponde a lo positivo, indicando esto que el proyecto es
viable desde el punto de vista de balance de impactos.

14

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

PLAN DE MITIGACIN DE LOS IMPACTOS AMBIENTALES GENERADOS POR EL PROYECTO.

ACCIONES
IMPACTANTES

EFECTOS

Trabajos
preliminares Produccin de polvo
(limpieza y descapote)

MEDIDAS DE
MITIGACION

Humedecimiento de
la tierra
Seleccin del sitio
Produccin de desechos receptor de los
orgnicos e inorgnicos desechos
Recoleccin,
transporte
y
disposicin de los
desechos

Trabajos de construccin Produccin de polvo


de obras de saneamiento.
Riesgo de dao a la
infraestructura pblica o
privada

Funcionamiento
sistema

COSTO
DE LA
MEDIDA

RESPONSABLE
POR EL
CUMPLIMIENTO
DE LA MEDIDA

Indirecto

Contratista

C$ 2,500

Contratista

Humedecimiento de
Indirecto
la tierra
Reparacin de daos
causados
a
la Indirecto
propiedad pblica y/o
privada.
Riesgo de inestabilidad Proporcionar el corte
de
tierras
en de taludes acorde Indirecto
excavaciones.
ngulo de reposo o
reforzar las reas de
corte.
del Riesgo
de
Trabajo
contaminacin
Control sanitario
comunitario
Deterioro del servicio Velar por adecuado
ante deficiencias de funcionamiento del
Trabajo
funcionamiento
del comit de agua.
comunitario
comit de Agua potable Capacitacin
y
lo que afecta la reglamentos
sostenibilidad
del
proyecto
Reduccin del % de
Trabajo
beneficiarios
del
comunitario
proyecto calculados en
el diseo

Contratista

Contratista

Contratista

Miembros del CAPS

Miembros del CAPS

Miembros del CAPS

15

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

8. CONCEPTUALIZACION DEL PROYECTO DE SANEAMIENTO


8.1 CONCEPTUALIZACION DEL SANEAMIENTO
La alternativa a ejecutar en el componente de saneamiento fue seleccionada por la comunidad de El
Achiote en asamblea de concertacin realizada el da 19 de Junio en la alcalda de Bocana de
Paiwas, esta asamblea conto con la participacin de los miembros de CAPS, beneficiarios,
autoridades municipales, Ing. Territorial del Nuevo FISE y profesionales de CONDISA.
En cuanto al componente de saneamiento la comunidad selecciono el uso de inodoros ecolgicos y
donde esta tecnologa no pueda ser aplicada por restricciones de tipo de suelo y/o espacio se
construirn letrinas ventiladas dobles. Se debe de tomar muy en cuenta que en la comunidad los
suelos son arcillosos lo que restringue el uso de inodoros ecolgicos, sin embargo los lotes de las
viviendas son amplios, lo que representa una ventaja en este tipo de solucin de saneamiento.
En total se propone la construccion de 22 unidades de saneamiento, para beneficiar a las viviendas que
actualmente tienen su letrina en regular o mal estado, las que tienen las letrinas llenas o no tienen,
adems de dos unidades sanitarias para la escuela.
INODOROS ECOLOGICOS
Se podr implementar esta nueva tecnologa de saneamiento siempre y cuando las condiciones del
lote de la vivienda en donde se propone la obra de saneamiento tengan las condiciones debida de
tipo de suelo y espacio. Por ello en las asambleas de concertacin se presentara claramente los
requerimientos de esta opcin, para que los beneficiarios valoren entre las opciones presentadas y
seleccionen lo que a su conveniencia y condiciones de su lote se adecue mejor.
El inodoro ecolgico presenta algunas ventajas que pueden ayudar a que se convierta en una
solucin ambiental y socialmente idnea para diferentes condiciones que presentan las
comunidades rurales. Algunas de las ventajas que presenta esta tecnologa son:
El asiento de esta letrina es ms confortable debido a que est construido de cermica y
est libre de imperfecciones o rugosidades. Adems, esta tasa se puede lavar fcilmente y
mantenerse limpia durante mucho tiempo de uso. Por tanto se espera que hay una mayor
limpieza en comparacin con las tradicionales.
Al depositarse las excretas en un tanque que est un poco alejado de la taza, elimina los
riesgos de que las personas o la caseta caigan dentro de l, adems, el usuario no est
expuesto a los gases de la materia en descomposicin.
La disposicin de las excretas tratadas en un campo de infiltracin de poca profundidad,
posibilita la absorcin y descomposicin de compuestos de nitrgeno (desnitrificacin),
reduciendo el riesgo de contaminacin de stos al agua subterrnea.
Una de las caractersticas de los inodoros ecolgicas, es que no requieren de mucha
cantidad de agua para su funcionamiento, pues cuentan con una taza diseada para permitir
la fcil lavada de las excretas, impide el paso de insectos y olores desagradables del pozo
16

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

sptico al interior de la caseta y necesita de 1 litro de agua para el arrastre. Esto hace que
sean una buena alternativa en zonas con poca agua.

17

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y Saneamiento El Achiote


Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
A continuacin se presenta esquema del diseo del mismo.

18

FIRMA CONSULTORA: CONDISA

Diseo: Ing. Mirta Violeta Bravo M.

LETRINA VENTILADA DE FOSO DOBLE

El VIP Doble tiene casi el mismo diseo que el VIP Simple con la ventaja adicional de un segundo
pozo que permite que la tecnologa sea usada continuamente y permite un vaciado ms seguro y
fcil. Al usar dos pozos, un pozo puede ser usado mientras el contenido del segundo pozo reposa
para posteriormente ser drenado, se reduce en volumen y se degrada. Cuando el segundo pozo est
casi lleno, (las excretas estn a 50 cm de la superficie) se cubre, y el contenido del primer pozo se
extrae. Debido al extendido tiempo de reposo (por lo menos 1 ao de relleno/reposo) el material
debe estar saneado y puede ser extrado manualmente.
La caseta, plancha y banco pueden ser cambiadas de un pozo al otro. En cualquier caso, el pozo
que no est siendo llenado debe estar completamente cubierto y sellado para evitar que agua,
basura y animales (y/o gente) caigan en el pozo. La ventilacin de los dos pozos puede ser por
medio de un tubo cambiado de uno al otro o bien cada pozo puede estar equipado con su propio
tubo. Los pozos en el VIP Doble son continuamente usados y deben estar bien recubiertos y tener
un buen soporte para asegurar su longevidad.
La tecnologa slo funcionar adecuadamente si los pozos son usados uno despus del otro y no al
mismo tiempo. Por lo tanto, se requiere una cubierta para el pozo fuera de servicio. Una de las
grandes ventajas es que los dos pozos pueden ser usados de manera alterna por tiempo indefinido.

19

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

La letrina VIP Es una letrina mejora sobre el Pozo Simple porque el flujo continuo de aire por la
tubera de ventilacin alivia los olores y acta como una trampa para las moscas ya que escapan
hacia la luz.
Las moscas que se cran en el pozo son atradas por la luz en la parte alta del tubo de ventilacin.
Cuando vuelan hacia la luz y tratan de escapar son atrapadas por la pantalla de moscas y mueren.
La ventilacin tambin permite que escapen los olores y minimiza la atraccin para las moscas.
El tubo de ventilacin debe tener un dimetro interno de 100 mm hasta un mximo de 150 mm y
estar por encima del punto ms alto de la superestructura de la letrina. La ventilacin funciona mejor
en reas con viento pero donde hay poco viento, su efectividad se puede mejorar pintando el tubo de
negro; la diferencia de calor entre el pozo (fro) y la ventila (tibia) crea una corriente que jala el aire y
los olores hacia arriba y hacia el exterior del pozo.
El tamao de la malla de la pantalla para moscas debe ser suficientemente grande para prevenir el
taponamiento con polvo y permitir que circule el aire libremente.
Al filtrarse el efluente del VIP Simple y migrar por el terreno no saturado, se eliminan los organismos
fecales. El grado de eliminacin de organismos fecales vara con el tipo de terreno, la distancia
viajada, la humedad y otros factores ambientales y, por lo tanto, es difcil estimar la distancia
necesaria entre un pozo y una fuente de agua. Se recomienda una distancia de al menos 30 m entre
el pozo y una fuente de agua para limitar la exposicin a contaminacin qumica y biolgica.
Adecuacin Los procesos de tratamiento en el VIP Simple (aerbico, anaerbico, deshidratacin,
compostaje u otros) son limitados y, por lo tanto, la reduccin de patgenos y la degradacin
orgnica no son significativas. Sin embargo, como las excretas estn contenidas en el foso, la
transmisin de patgenos es limitada.
Dependiendo de la profundidad del pozo, la profundidad de los mantos freticos, el nmero de
usuarios, y las condiciones del terreno, algunos pozos pueden ser usados durante 20 aos sin ser
vaciados.
Los VIP son especialmente apropiados cuando el agua es escasa y donde hay un bajo nivel fretico.
Deben ser ubicados en un rea con buena ventilacin. No son adecuados para terrenos rocosos o
compactos (que son difciles de excavar) o para reas que se inundan frecuentemente.
Algunos de los inconvenientes de esta solucin son:
La infiltracin de la letrina puede contaminar los mantos freticos; por lo tanto no se recomienda en
comunidades que se abastecen de aguas sub superficiales.
Los pozos son susceptibles de falla/derrame durante las inundaciones;
Hay riesgos para la salud por las moscas que no son completamente eliminadas por la ventilacin.
8.2 CONCLUSIONES
Solo el 65% de las viviendas cuentan con letrinas y un 35% no tienen letrinas
Solo el 14% de las letrinas existentes se encuentra en buen estado
El 50% de las letrinas existentes se encuentra en buen estado
20

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

El 36% de las letrinas existentes se encuentra en buen estado


Se propone la construccin de unidades de saneamiento en aquellas viviendas que tienen sus
letrinas en regular estado, en mal estado, que las tienen llenas o que no tienen letrinas. Mas dos
unidades de saneamiento en la escuela de la localidad, en total 22 unidades.

8.3 RECOMENDACIONES
Se recomienda que a la ejecucin del proyecto se priorice a las viviendas que no cuentan con
unidades de saneamiento y las que las tienen en mal estado.
Se deber de capacitar a la poblacin respecto al uso adecuado de las unidades de saneamiento.

21

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

9. TAKE OFF Y PRESUPUESTO

9.1 CUANTIFICACIN DE OBRAS PARA LA CONSTRUCCIN DEL SISTEMA DE AGUA POTABLE


[SI EL CASO LO AMERITA]

9.2 CUANTIFICACIN DE OBRAS PARA LA CONSTRUCCIN DEL SISTEMA DE SANEAMIENTO [SI


EL CASO LO AMERITA]

9.3 PRESUPUESTO PARA LA CONSTRUCCIN DEL SISTEMA DE AGUA POTABLE Y


SANEAMIENTO

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

10. COSTOS DE INVERSIN, OPERACIN Y MANTENIMIENTO


10.1 RESUMEN DE COSTOS DE INVERSIN

10.2 COSTOS DE OPERACIN Y MANTENIMIENTO

10.3 SISTEMA TARIFARIO

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

11. PLANOS
Incluir lista de planos

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

12.

ANEXOS

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

12.1 LEVANTAMIENTO TOPOGRFICO


A continuacin se incluye datos del levantamiento de la comunidad y predios de obras propuestas
2,724136.9250,1414561.5650,401.6420,
50,724140.5477,1414534.0099,404.4200,1
51,724172.6055,1414494.4178,401.0990,1
52,724233.6493,1414459.3394,400.1881,1
53,724385.3475,1414367.6265,395.9314,1
54,724455.2244,1414366.8468,394.0819,1
55,724633.1193,1414268.6121,390.6470,1
4,724600.6610,1414191.0504,392.3759,3
3,724612.1635,1414273.0618,392.4823,3
56,724818.4858,1414543.9560,371.1561,1
57,724899.9653,1414625.4660,369.5861,1
5,724993.9937,1414719.7669,364.3926,3
6,725132.7159,1414835.0989,364.9292,3
58,725257.3827,1414902.6028,363.2331,1
59,725424.5252,1414984.4223,361.5247,1
B1,725418.8076,1414999.1114,361.9249,
7,725608.4137,1415080.7341,364.8761,3
8,725705.9353,1415135.3287,363.6330,3
60,725957.6149,1415312.9880,360.5010,1
9,726210.8510,1415502.1083,362.0019,3
10,726300.5969,1415584.8843,364.5798,3
11,726532.8014,1415857.1969,369.5503,3

5068,724127.012,1414561.472,396.33
8,6
5069,724130.875,1414551.735,396.87
1,6
5070,724133.393,1414554.216,396.57
9,6
5071,724136.35,1414559.395,400.236,
6
5072,724135.969,1414554.97,397.105,
6
5073,724139.236,1414558.46,400.388,
6
5074,724136.571,1414557.692,398.98
9,6
5075,724141.131,1414557.079,400.17
1,6
5076,724136.644,1414547.865,401.71
8,6
5077,724144.744,1414555.99,400.62,6
5078,724136.609,1414550.234,400.53,
6
5079,724144.239,1414537.142,405.37
9,6
5080,724138.192,1414535.69,404.103,
6
5081,724146.832,1414539.768,405.81,
6
5082,724134.668,1414535.445,402.09
7,6
5083,724130.536,1414536.061,399.96
3,6
5084,724128.014,1414536.237,398.45
2,6
5085,724152.701,1414542.216,406.28,
6
5086,724152.552,1414529.635,404.91
3,6
5087,724140.082,1414531.746,404.13
2,6
5088,724149.87,1414530.61,405.035,6
5089,724137.852,1414528.511,401.49
1,6
1

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
12,726569.5918,1415818.2131,368.4630,3
61,726735.2284,1415639.7309,359.8688,1
62,726856.0540,1415681.1590,359.7417,1
13,726863.7466,1415693.6074,359.5817,3
14,726929.9840,1415641.3433,357.7296,3
63,727039.1365,1415707.4096,355.8847,1
64,727140.2520,1415756.2408,355.3426,1
300,726921.3915,1415698.3506,357.5814,8
301,726927.0448,1415699.3990,357.3812,8
302,726925.0152,1415711.5782,357.7515,8
303,726950.9329,1415709.2368,357.2086,8
304,726951.8651,1415704.0134,356.9635,8
305,726941.4738,1415701.9138,357.1172,8
306,727174.2035,1415782.3779,358.0789,8
307,727177.2087,1415777.6765,358.1072,8
308,727180.6312,1415779.1657,358.3447,8
309,727182.1408,1415763.7090,359.1575,7
310,727168.5974,1415785.2428,357.6741,7
311,727174.7441,1415775.4407,357.9983,4
312,727170.3974,1415782.4871,357.8388,6
313,727178.5591,1415769.5534,358.5088,6
314,727160.2878,1415764.4654,357.3804,4
315,727168.6234,1415736.5122,358.7239,7
316,727153.4925,1415776.1885,356.4906,6

5090,724144.986,1414532.107,404.94
5,6
5091,724135.292,1414524.455,399.48
7,6
5092,724134.43,1414522.491,398.308,
6
5093,724149.88,1414522.481,403.748,
20
5094,724157.171,1414513.476,400.89
5,20
5095,724149.332,1414519.374,402.77
3,6
5096,724153.869,1414522.255,403.65
1,6
5097,724159.268,1414525.402,404.07,
6
5098,724173.44,1414500.537,402.356,
6
5099,724175.063,1414504.924,403.85
9,6
51,724172.606,1414494.41,401.099,PI
5100,724168.963,1414496.36,400.855,
6
5101,724165.999,1414496.374,399.49
8,6
5102,724179.325,1414495.611,402.49
1,6
5103,724182.695,1414498.028,402.93
5,6
5104,724172.735,1414488.343,399.23
4,6
5105,724158.959,1414497.305,397.51
4,6
5106,724169.456,1414483.259,397.00
7,6
5107,724167.389,1414479.675,395.07
5,6
5108,724161.898,1414485.921,395.74
9,6
5109,724157.152,1414482.501,393.25
8,6
5110,724170.515,1414492.701,400.14,
6
5111,724166.781,1414489.501,397.80
8,6
5112,724194.213,1414483.905,400.19
2

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

317,727157.8399,1415769.5410,357.0700,6
318,727163.2274,1415756.9101,358.0434,6
319,727165.8420,1415750.4421,358.5015,6
320,727144.0310,1415755.2436,356.0262,4
321,727148.2017,1415740.9527,356.8999,6
322,727146.2242,1415749.3892,356.5939,6
323,727140.0704,1415759.7715,354.7328,6
324,727135.7415,1415762.8448,354.1482,6
325,727129.3144,1415744.5659,353.7545,4
326,727132.0881,1415738.0010,354.6820,6
327,727132.8925,1415731.0183,355.4692,6
328,727126.9723,1415747.8875,353.7145,6
329,727122.0496,1415755.1420,352.0610,6
330,727113.8400,1415734.3018,351.9206,4
331,727115.2770,1415729.8475,353.4831,6
332,727110.7094,1415739.1855,351.6818,6
333,727106.2175,1415745.8398,350.2242,6
334,727115.8770,1415723.8909,353.7961,7
335,727096.3901,1415726.7972,351.2481,4
336,727091.3744,1415736.7799,349.3230,6
337,727094.8527,1415730.9379,350.7856,6
338,727097.8237,1415723.3797,351.9402,6
339,727097.7191,1415719.4984,352.6266,7

6,6
5113,724192.224,1414479.464,398.89
9,6
5114,724188.392,1414472.972,397.46
1,6
5115,724184.158,1414466.311,395.74
4,6
5116,724199.387,1414487.821,401.70
6,6
5117,724197.354,1414485.641,400.87
3,6
5118,724201.17,1414490.831,402.443,
6
5119,724196.083,1414480.919,399.50
7,20
5120,724228.672,1414462.193,400.94
7,20
5121,724208.039,1414474.049,400.16
7,20
5122,724216.092,1414472.992,400.80
2,6
5123,724212.834,1414469.77,400.276,
6
5124,724210.119,1414465.709,399.60
8,6
5125,724219.302,1414477.951,401.65
6,6
5126,724208.09,1414461.85,398.941,6
5127,724204.442,1414458.453,398.12
9,6
5128,724248.287,1414453.367,396.16
9,AUX
5129,724231.764,1414456.452,399.74
1,6
5130,724229.054,1414452.16,398.776,
6
5131,724226.161,1414446.889,398.12
6,6
5132,724225.113,1414442.473,397.62
7,6
5133,724234.967,1414462.042,400.51
8,6
5134,724236.724,1414466.983,400.89
2,6
5135,724238.063,1414470.592,401.94
4,6
3

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
340,727098.6135,1415718.9359,352.9224,6
341,727078.7034,1415723.4323,351.7126,4
342,727075.3885,1415735.4834,351.3993,6
343,727075.6546,1415730.7506,351.8880,6
344,727080.8848,1415711.8635,353.1920,6
345,727079.6015,1415715.2287,352.9803,7
346,727061.7980,1415719.1180,353.0849,4
347,727059.9041,1415723.5113,352.9011,6
348,727057.5708,1415729.3796,352.0063,6
349,727067.2746,1415706.3394,354.6010,6
350,727064.6772,1415711.8917,354.0672,7
351,727044.2795,1415714.0496,354.8319,4
352,727043.6820,1415718.4266,354.7555,6
353,727042.1639,1415724.7573,353.9214,6
354,727049.7099,1415704.5710,355.3834,6
355,727048.3276,1415707.9147,355.2592,7
356,727024.9011,1415720.2151,354.8049,6
357,727026.1057,1415714.4555,355.3329,6
358,727026.8369,1415709.5648,355.6149,4
359,727028.5924,1415703.2747,356.2485,7
360,727029.3257,1415701.4218,356.4090,6
361,727008.8620,1415705.8127,355.4530,4
362,727007.5746,1415710.9559,354.9823,6
363,727006.5329,1415716.0685,354.4362,6

5136,724266.83,1414440.38,391.289,
AUX
5137,724247.363,1414450.916,395.29
9,AUX
5138,724245.843,1414447.706,394.68
1,AUX
5139,724243.769,1414444.775,394.14
8,AUX
5140,724250.435,1414455.666,396.56
3,6
5141,724252.649,1414458.568,397.24
6,6
5142,724254.38,1414462.421,396.723,
6
5143,724280.818,1414433.767,390.10
2,AUX
5144,724267.477,1414442.124,391.72
5,6
5145,724269.258,1414445.012,393.46
1,6
5146,724270.43,1414448.521,393.98,6
5147,724264.979,1414436.381,389.65,
6
5148,724262.973,1414432.544,388.71,
6
5149,724261.296,1414428.66,388.016,
6
5150,724294.473,1414424.773,386.84
8,AUX
5151,724281.948,1414436.008,390.64
1,6
5152,724283.235,1414438.574,391.52
7,6
5153,724285.298,1414440.798,391.92
4,6
5154,724279.127,1414430.786,388.78
1,6
5155,724277.139,1414428.06,387.078,
6
5156,724309.055,1414415.502,385.77
1,AUX
5157,724296.907,1414427.137,387.45
9,6
5158,724298.181,1414429.143,388.01
7,6
5159,724299.821,1414431.516,387.98
4

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

364,727010.7314,1415699.0232,356.1537,7
365,727011.8859,1415693.7583,356.6211,6
366,726990.2149,1415701.3054,355.2444,4
367,726988.2018,1415705.7473,354.8868,6
368,726986.3000,1415713.4656,355.3312,6
369,726993.5573,1415688.6316,356.4052,6
370,726991.6952,1415694.6425,355.8986,7
371,726971.5760,1415696.8959,355.9367,4
372,726968.6645,1415707.5672,356.6002,6
373,726969.7472,1415702.1501,356.3046,6
374,726974.7133,1415681.9449,356.5700,6
375,726972.3684,1415690.3646,356.0308,7
376,726953.0289,1415693.1937,356.4039,4
377,726952.1143,1415698.4574,356.7077,6
378,726951.4793,1415702.4422,356.8524,6
379,726954.3179,1415686.0041,356.5187,7
380,726954.4999,1415681.9277,356.5259,7
381,726935.3012,1415688.0143,356.6987,4
382,726933.9736,1415692.9981,357.0304,6
383,726933.2780,1415698.8697,357.1844,6
384,726937.2859,1415676.7263,356.8522,6
385,726937.2296,1415676.8987,356.8474,6
386,726936.1127,1415681.7826,356.9236,7
200,726823.7139,1415760.2172,358.4547,2

9,6
5160,724293.024,1414422.108,386.03
2,6
5161,724291.411,1414417.951,385.09
2,6
5162,724290.129,1414413.445,384.14,
6
5163,724350.042,1414392.991,391.47
6,6
5164,724307.997,1414412.593,384.94
3,6
5165,724306.563,1414409.842,384.15
4,6
5166,724305.544,1414407.2,383.452,6
5167,724310.68,1414418.002,386.419,
6
5168,724312.186,1414420.457,387.18,
6
5169,724312.761,1414422.764,387.86
6,6
5170,724304.194,1414419.383,384.74
6,6
5171,724301.476,1414421.28,382.967,
6
5172,724299.103,1414421.508,384.45
5,6
5173,724330.94,1414403.364,383.705,
6
5174,724333.078,1414407.048,384.70
5,6
5175,724334.992,1414414.607,386.39
2,6
5176,724327.924,1414398.162,382.50
2,6
5177,724334.916,1414384.121,383.97
6,6
5178,724346.315,1414399.19,390.64,6
5179,724346.435,1414405.282,391.58
1,6
5180,724341.719,1414389.674,387.85
7,6
5181,724343.867,1414395.08,389.22,6
5182,724346.318,1414399.194,390.64
7,6
5183,724349.849,1414403.614,392.38
9,6
5

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
387,726831.0638,1415759.9087,358.4398,8
388,726830.1533,1415765.2583,358.4172,8
389,726841.9690,1415769.6635,358.1361,8
390,726843.2935,1415772.5988,358.0814,8
391,726833.6661,1415771.2440,358.0906,8
392,726832.9434,1415776.6488,357.8620,8
393,726821.3290,1415772.4133,358.3292,8
394,726822.0519,1415768.1332,358.3690,8
395,726813.6909,1415766.7548,358.2972,8
396,726788.9044,1415705.0111,359.1271,8
397,726803.4052,1415712.4923,359.1079,8
398,726806.5464,1415706.9668,359.1195,8
399,726833.1251,1415739.9774,358.6810,7
400,726828.9277,1415736.6656,358.7010,7
401,726812.9309,1415730.7007,358.5966,7
402,726845.6438,1415749.8207,358.3598,7
403,726851.9570,1415754.1594,358.2605,7
404,726834.1561,1415730.5019,358.8025,4
405,726832.0757,1415729.3894,358.8989,7
406,726836.2711,1415730.9436,358.8382,7
407,726840.5031,1415720.8412,359.2176,7
408,726836.3841,1415718.1915,359.3299,7
409,726838.5719,1415719.5326,359.2572,4

5184,724353.733,1414408.575,394.43
9,6
5185,724358.81,1414366.235,390.458,
6
5186,724367.616,1414390.426,396.46
9,6
5187,724362.083,1414374.682,392.81,
6
5188,724369.355,1414397.216,397.67
5,6
5189,724365.821,1414384.258,395.35
6,6
5190,724371.615,1414404.607,399.44
7,6
5191,724379.843,1414371.043,396.05
5,AUX
5193,724383.957,1414363.863,394.79,
6
5194,724384.712,1414370.162,396.26
7,6
5195,724383.981,1414361.508,393.32
3,6
5196,724385.251,1414376.209,397.17,
6
5197,724386.469,1414382.08,398.137,
6
5198,724384.157,1414360.032,392.50
4,6
5199,724424.513,1414367.73,396.176,
AUX
52,724233.649,1414459.339,400.188,P
I
5200,724396.339,1414379.69,398.285,
PILA
5201,724395.154,1414380.749,398.57
6,PILA
5202,724402.679,1414379.486,398.95
9,6
5203,724402.988,1414382.767,400.26,
6
5204,724402.97,1414373.637,396.682,
6
5205,724403.554,1414369.505,394.09,
6
5206,724455.209,1414366.833,394.26,
PI
6

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
410,726844.5558,1415703.9983,360.0208,4
411,726842.3278,1415703.2359,360.0731,7
412,726846.5715,1415705.0984,359.9310,7
413,726847.3542,1415690.1101,360.0219,7
414,726851.8512,1415691.7264,359.9380,7
415,726849.5914,1415690.6687,359.9324,4
416,726863.0844,1415625.5334,359.8593,8
417,726864.2666,1415620.5747,359.8887,8
418,726848.3087,1415622.6109,360.1719,8
419,726867.6100,1415618.4522,359.9233,7
420,726863.7191,1415641.4310,359.9025,7
421,726859.2882,1415666.5811,359.4866,7
422,726836.4404,1415698.7295,360.3804,8
423,726840.0840,1415687.6730,360.2681,8
424,726829.7176,1415684.0958,360.5015,8
425,726874.0715,1415699.0441,359.1012,7
201,726832.4094,1415673.6952,360.2038,2
426,726822.8902,1415704.0969,359.6932,7
427,726820.6204,1415702.9205,359.7706,7
428,726827.2043,1415683.4308,360.4891,7
429,726823.9545,1415697.1411,359.9887,4
430,726826.2287,1415690.3805,360.3562,4
431,726825.8642,1415695.3446,360.1734,8

5207,724404.171,1414364.946,390.53,
6
5208,724424.16,1414363.411,393.743,
6
5209,724423.696,1414359.671,391.70
8,6
5210,724425.159,1414373.413,397.81
8,6
5211,724425.625,1414379.337,399.59
4,6
5212,724427.106,1414385.515,400.79
6,7
5213,724438.304,1414361.793,393.23
8,7
5214,724436.001,1414366.622,395.38
8,7
5215,724433.363,1414372.597,396.96
1,7
5216,724448.749,1414367.01,394.46,2
0
5217,724437.222,1414367.346,395.38
8,20
5218,724451.566,1414381.799,399.22
3,6
5219,724453.093,1414375.761,396.75
9,6
5220,724453.965,1414371.837,395.72
2,6
5221,724456.458,1414362.073,392.72
4,7
5222,724457.742,1414356.032,390.65
8,6
5223,724458.211,1414352.791,388.83
3,6
5224,724519.102,1414333.627,384.30
4,AUX
5225,724467.641,1414360.372,391.20
2,20
5226,724480.813,1414353.526,387.63
6,20
5227,724501.982,1414342.524,384.20
8,20
5228,724480.692,1414367.869,389.37
9,6
5229,724479.663,1414362.722,388.79
5,6
7

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
432,726848.5556,1415661.9146,359.8844,8
433,726841.0440,1415660.2144,359.9945,8
434,726829.4944,1415659.8620,360.3453,7
435,726822.9001,1415657.9170,360.5889,8
436,726815.0929,1415656.0667,360.7432,8
437,726811.1881,1415655.7442,360.8416,7
438,726800.7890,1415653.1436,361.0468,7
439,726798.4833,1415650.3761,360.7766,8
440,726789.7669,1415648.2228,360.6814,8
441,726786.1930,1415650.2247,360.7210,7
442,726770.0394,1415646.3567,360.0722,7
443,726769.1735,1415645.0406,360.0802,8
444,726762.2865,1415643.7665,359.8102,8
445,726753.2802,1415642.6333,359.8460,7
446,726796.1604,1415682.6687,359.7083,8
447,726805.6622,1415688.1506,359.8633,8
448,726803.3038,1415692.4226,359.5707,8
449,726809.5314,1415676.0555,360.5466,8
450,726812.1512,1415668.2336,360.4691,8
451,726804.3265,1415665.4155,360.5847,8
452,726813.4247,1415666.1580,360.5839,7
453,726794.4592,1415662.1109,360.7711,7
454,726809.5809,1415677.1284,360.5290,7
455,726784.8222,1415684.4429,358.6301,7

5230,724478.516,1414357.31,388.584,
6
5231,724476.53,1414351.038,386.292,
6
5232,724475.517,1414348.674,385.19
1,6
5233,724578.05,1414299.343,386.719,
AUX
5234,724495.723,1414341.905,383.63
6,6
5235,724501.465,1414350.646,385.30
6,6
5236,724492.239,1414337.266,382.66
9,6
5237,724501.966,1414355.697,386.08
4,6
5238,724516.694,1414330.177,383.80
6,6
5239,724521.197,1414337.23,384.444,
6
5240,724523.84,1414341.52,384.482,6
5241,724513.342,1414325.582,382.91
2,6
5242,724510.98,1414321.509,381.887,
6
5243,724541.503,1414322.951,382.97
1,7
5244,724542.314,1414327.54,383.478,
7
5245,724540.406,1414316.911,382.12
4,7
5246,724558.777,1414317.5,383.969,6
5247,724556.799,1414311.519,383.48
7,6
5248,724560.418,1414323.896,384.47
6,6
5249,724555.139,1414300.055,383.30
5,6
5250,724578.773,1414304.542,386.25
9,6
5251,724576.371,1414286.63,387.847,
6
5252,724579.817,1414312.391,385.99
5,6
5253,724597.142,1414287.121,389.29
5,6
8

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
456,726925.2548,1415678.9763,357.1252,7
457,726926.7099,1415669.8081,357.3608,7
458,726918.3083,1415687.6942,357.5400,4
459,726917.0991,1415695.0955,357.6758,6
460,726917.3344,1415691.0524,357.6523,6
461,726919.3890,1415681.3768,357.4707,6
462,726899.5750,1415683.4282,358.2207,4
463,726901.6157,1415670.1239,358.1819,4
464,726901.0500,1415675.7630,358.2403,4
465,726897.8155,1415687.8530,358.3922,4
466,726896.7063,1415695.1119,358.4917,4
467,726882.0959,1415678.7641,358.8244,4
468,726884.0434,1415666.8076,359.1292,6
469,726883.9536,1415671.8136,359.1069,6
470,726880.3893,1415683.4921,358.9921,6
471,726880.2256,1415690.5474,359.0771,6
472,726864.1467,1415674.6180,359.4184,4
473,726867.0343,1415662.1549,359.6253,6
474,726866.0026,1415667.7625,359.5818,6
475,726862.7767,1415683.3486,359.5629,6
476,726860.3575,1415694.0879,359.6185,7
477,726846.1754,1415669.9879,359.8076,4
478,726848.1092,1415664.3410,359.9210,7

5254,724600.727,1414293.429,388.28,
6
5255,724593.72,1414281.619,389.744,
6
5256,724590.386,1414276.119,390.52
8,6
5257,724603.028,1414297.926,387.44
5,6
5259,724614.6,1414288.377,390.47,TA
NQUE
5260,724610.915,1414283.956,391.26
5,TANQUE
5261,724606.776,1414279.401,391.72
9,TANQUE
5262,724602.22,1414274.26,391.947,T
ANQUE
5263,724598.348,1414268.874,391.82
4,TANQUE
5264,724595.036,1414265.422,392.03
6,TANQUE
5265,724590.594,1414260.563,391.90
6,TANQUE
5266,724592.829,1414252.237,392.51
3,TANQUE
5267,724600.46,1414256.354,392.697,
TANQUE
5268,724601.051,1414263.607,392.65
6,TANQUE
5269,724601.047,1414263.606,392.65
7,TANQUE
5270,724606.363,1414270.007,392.41,
TANQUE
5271,724611.866,1414276.44,392.234,
TANQUE
5272,724617.561,1414282.03,391.43,T
ANQUE
5273,724622.48,1414286.505,390.696,
TANQUE
5274,724627.174,1414291.293,389.32
7,TANQUE
5275,724633.133,1414292.122,388.79
8,TANQUE
5276,724640.279,1414296.301,386.86
6,TANQUE
5277,724633.167,1414277.284,390.41,
TANQUE
9

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
479,726843.6106,1415688.7789,360.1661,7
480,726844.3602,1415684.1736,360.1377,6
481,726844.4533,1415677.4309,359.9519,6
482,726823.4065,1415681.7948,360.5794,7
483,726829.2717,1415659.8692,360.3805,7
484,726828.2899,1415664.8650,360.3526,4
485,726826.4880,1415671.6804,360.3064,6
486,726824.8099,1415677.0799,360.4357,6
487,726810.1505,1415660.1447,360.9065,4
488,726811.0409,1415655.7237,360.8512,6
489,726808.9310,1415665.0660,360.5422,6
490,726790.3767,1415656.6041,360.5098,4
491,726794.3394,1415662.0506,360.7767,7
492,726791.8557,1415651.3828,361.1805,7
493,726959.7844,1415442.0470,365.8511,8
494,726947.6936,1415436.6376,365.6604,8
495,726793.0544,1415664.4176,360.5617,7
496,726790.3812,1415670.1905,360.1350,7
497,726788.6126,1415662.9092,360.4371,7
498,726772.8773,1415652.4785,360.0449,4
499,726774.2872,1415647.5395,360.2919,7
500,726771.5505,1415657.2892,360.1502,7
501,726758.1908,1415653.3171,359.8386,7

5278,724629.377,1414273.813,390.93
2,TANQUE
5279,724626.688,1414268.834,391.25
5,TANQUE
5280,724642.389,1414282.649,388.79
4,TANQUE
5281,724638.48,1414277.131,389.69,T
ANQUE
5282,724627.1,1414261.674,390.984,T
ANQUE
5283,724634.84,1414264.696,390.188,
TANQUE
5284,724636.473,1414271.72,390.192,
TANQUE
5285,724623.217,1414253.958,391.28
7,TANQUE
5286,724633.264,1414258.865,390.19
4,TANQUE
5287,724631.721,1414252.318,390.31
5,TANQUE
5288,724618.965,1414246.437,391.27,
TANQUE
5289,724630.038,1414247.084,390.43,
TANQUE
5290,724627.739,1414238.579,390.06
7,TANQUE
5291,724615.025,1414240.571,391.07
3,TANQUE
5292,724624.458,1414232.21,389.929,
TANQUE
5293,724629.08,1414230.245,389.622,
TANQUE
5294,724632.489,1414226.698,389.32
3,TANQUE
5295,724632.013,1414237.446,389.62
9,TANQUE
5296,724636.453,1414232.438,389.14
1,TANQUE
5297,724635.309,1414242.506,389.58
5,TANQUE
5298,724643.021,1414245.102,389.12
4,TANQUE
5299,724639.409,1414238.138,389.15
5,TANQUE
53,724385.331,1414367.627,396.099,P
I
10

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
502,726752.2870,1415667.2331,359.8197,7
503,726749.1381,1415677.0527,359.7074,7
504,726755.9670,1415647.9323,359.7722,4
505,726757.4698,1415643.3929,359.8608,7
506,726754.2194,1415651.9930,359.8960,6
507,726747.9798,1415656.5572,359.9739,6
508,726744.2567,1415665.1427,359.9249,7
509,726739.9244,1415647.2823,359.9378,4
510,726741.4410,1415636.2424,359.6120,6
511,726741.2388,1415626.6471,359.0561,6
512,726732.0558,1415624.2843,358.7753,6
513,726733.6346,1415631.0348,359.1844,6
514,726727.9724,1415635.8180,359.2593,6
515,726721.8079,1415629.2111,358.6122,6
516,726726.7345,1415640.2607,359.3485,6
517,726719.4136,1415635.7428,358.7997,6
518,726736.1741,1415648.0444,359.5591,6
519,726741.7564,1415652.9453,359.9833,6
520,726736.3801,1415655.1566,360.0399,6
521,726733.0704,1415650.0286,359.6500,6
522,726728.7399,1415645.6221,359.3809,6
523,726718.5348,1415642.7910,358.9602,6
524,726780.5725,1415605.4759,358.6545,8
525,726781.8074,1415600.0579,358.5438,8

5300,724653.077,1414261.229,387.73
4,TANQUE
5301,724648.003,1414253.273,388.43
7,TANQUE
5302,724641.741,1414255.708,389.08
2,TANQUE
5303,724656.742,1414270.327,387.63
5,TANQUE
5304,724645.587,1414264.314,388.59
6,TANQUE
5305,724660.413,1414276.018,386.67
8,TANQUE
5306,724649.063,1414272.213,388.58,
TANQUE
5307,724661.993,1414283.029,385.22
5,TANQUE
5308,724651.405,1414279.765,387.70
8,TANQUE
5309,724655.049,1414287.27,385.313,
TANQUE
5310,724632.352,1414261.385,390.41
3,TANQUE
5311,724626.726,1414249.783,390.79,
TANQUE
5312,724626.735,1414249.779,390.79,
TANQUE
5313,724623.559,1414243.901,390.75
8,TANQUE
5314,724708.571,1414381.573,372.08,
AUX
5315,724585.949,1414105.039,394.89
6,8
5316,724575.802,1414103.057,394.56
6,8
5317,724508.7,1414130.898,390.533,8
5318,724512.351,1414125.712,390.09
9,8
5319,724604.715,1414291.597,388.94,
6
5320,724598.336,1414282.423,390.11
7,TANQUE
5321,724595.789,1414278.067,390.54
2,TANQUE
5322,724593.503,1414273.987,391.02
6,TANQUE
5323,724591.223,1414269.844,391.23
11

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

526,726773.6627,1415599.2341,358.2594,7
527,726771.0443,1415618.7718,359.4990,7
528,726755.1478,1415616.8402,358.9044,7
529,726690.5620,1415650.5268,357.9427,7
530,726718.2893,1415658.1195,359.2854,4
531,726701.5184,1415653.5900,358.4369,6
532,726709.6238,1415655.6614,358.8147,6
533,726733.3058,1415662.1422,359.8961,6
534,726726.5637,1415660.1201,359.7799,6
535,726704.9782,1415672.1790,358.6616,4
536,726688.9654,1415664.6691,357.8689,6
537,726698.4226,1415668.0599,358.3762,6
538,726710.5576,1415675.3330,358.9049,6
539,726718.5131,1415680.6551,359.0624,6
540,726692.3977,1415686.1439,358.1299,4
541,726676.0848,1415676.4717,357.9999,6
542,726706.9764,1415694.6524,358.3814,6
543,726696.6329,1415690.1574,358.3231,6
544,726681.0565,1415698.2346,358.0917,4
545,726674.8321,1415693.3764,358.1321,6
546,726668.7613,1415687.1927,358.1399,6
547,726686.5268,1415703.2539,358.1993,6
548,726694.4920,1415710.2480,358.0206,6

2,TANQUE
5324,724587.943,1414263.443,391.31
4,TANQUE
5325,724585.812,1414256.797,391.19
1,TANQUE
5326,724582.562,1414249.397,391.01
5,TANQUE
5327,724580.294,1414242.186,390.91
2,TANQUE
5328,724596.907,1414294.476,387.52
5,TANQUE
5329,724594.252,1414290.012,388.31
4,TANQUE
5330,724591.608,1414285.849,388.57
9,TANQUE
5331,724587.405,1414279.556,389.40
1,TANQUE
5332,724595.987,1414263.648,392.34
9,TANQUE
5333,724583.967,1414275.065,389.65
7,TANQUE
5334,724581.658,1414271.399,389.76
7,TANQUE
5335,724578.208,1414265.086,389.07
7,TANQUE
5336,724574.813,1414261.456,388.53
8,TANQUE
5337,724632.744,1414268.616,390.62
1,TANQUE
5338,724636.155,1414262.281,389.91
1,TANQUE
5339,724639.07,1414255.949,389.504,
TANQUE
5340,724629.215,1414276.124,390.92
2,TANQUE
5341,724631.636,1414271.707,390.70
4,TANQUE
5342,724626.869,1414280.253,390.96
9,TANQUE
5343,724624.572,1414284.379,390.73
3,TANQUE
5344,724594.629,1414297.914,386.85
5,TANQUE
5345,724600.431,1414301.224,386.44
5,TANQUE
5346,724629.157,1414298.438,387.39
12

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

549,726667.7360,1415712.8831,358.9059,4
550,726660.5769,1415707.2365,358.9286,6
551,726653.9281,1415702.0143,359.0437,6
552,726672.9222,1415717.7020,359.1084,6
553,726678.6765,1415723.6329,359.0452,6
554,726652.9614,1415728.4874,360.6684,4
555,726642.5163,1415716.3574,360.5711,6
556,726666.9934,1415737.9976,360.2080,6
557,726660.7004,1415731.9138,360.2458,6
558,726650.3781,1415722.4943,360.2428,6
559,726640.2263,1415742.4003,361.5374,4
560,726653.6824,1415752.5168,361.0311,6
561,726646.5474,1415747.9364,361.3335,6
562,726634.0482,1415737.7926,361.5865,6
563,726627.3370,1415733.1243,361.6420,6
564,726627.3629,1415756.3648,362.5931,4
565,726614.9069,1415745.7952,362.3674,6
566,726619.8842,1415749.2642,362.4357,6
567,726632.8103,1415762.9717,362.5210,6
568,726639.6710,1415768.8627,362.1445,6
569,726614.0532,1415770.4650,363.2984,4
570,726605.0982,1415761.5575,363.0616,6
571,726599.6151,1415757.3093,363.0230,6
572,726620.1018,1415774.5915,363.2989,6

4,TANQUE
5347,724608.159,1414304.772,385.76
5,TANQUE
5348,724639.059,1414292.71,387.873,
TANQUE
5349,724626.343,1414300.067,387.29,
TANQUE
5350,724614.655,1414306.2,385.673,T
ANQUE
5351,724622.759,1414302.214,386.75
1,TANQUE
5352,724618.994,1414305.945,385.71
6,TANQUE
5353,724645.967,1414288.243,387.26
8,TANQUE
5354,724649.331,1414283.774,387.25,
6
5355,724655.35,1414279.01,387.216,6
5356,724659.665,1414275.38,386.88,6
5357,724645.989,1414287.833,387.35
4,20
5358,724655.918,1414302.362,382.26
7,20
5359,724669.927,1414323.527,378.30
3,20
5360,724682.517,1414342.768,375.01
3,20
5361,724697.633,1414364.96,372.585,
20
5362,724657.928,1414301.665,382.08
4,6
5363,724663.325,1414298.032,382.12
2,6
5364,724667.931,1414294.867,382.08
8,6
5365,724653.38,1414304.961,382.59,6
5366,724650.097,1414307.864,382.58
2,6
5367,724674.819,1414319.048,378.34
6,6
5368,724665.411,1414325.016,378.74
4,6
5369,724660.552,1414327.882,379.22
6,6
5370,724669.196,1414322.36,378.483,
6
13

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
573,726629.1532,1415783.8138,363.0767,6
202,726859.7336,1415603.9563,360.1273,2
574,726789.8717,1415609.4401,358.8745,7
575,726790.8425,1415599.0315,358.2358,7
576,726799.1249,1415608.3189,359.5544,7
577,726830.2631,1415612.7413,360.0900,7
578,726600.4133,1415784.4814,364.8117,4
579,726592.5309,1415778.4374,364.6873,6
580,726585.5444,1415774.0861,364.1542,6
581,726603.7389,1415789.1899,364.9410,6
582,726611.2751,1415792.9704,364.5443,6
583,726587.6091,1415798.1461,366.7752,4
584,726582.2165,1415794.5881,366.9685,6
585,726574.2884,1415789.5684,366.1661,6
586,726592.7743,1415803.0662,366.5313,6
587,726600.6614,1415807.7401,365.6979,6
588,726575.5022,1415811.3390,368.2104,4
589,726573.2858,1415809.5874,368.2608,6
590,726566.9924,1415802.4271,367.7004,6
591,726579.9674,1415816.6711,367.6857,6
592,726586.3219,1415823.6672,367.0141,6
593,726561.9297,1415825.9952,368.3516,4
594,726557.5811,1415821.9433,368.7662,6
595,726552.8840,1415817.3734,368.7481,6

5371,724678.353,1414316.106,378.47,
6
5372,724678.151,1414344.599,375.93
9,6
5373,724683.693,1414338.545,374.91
2,6
5374,724688.616,1414334.265,374.86
6,6
5375,724678.094,1414344.567,375.95
1,6
5376,724672.864,1414349.29,376.692,
6
5377,724692.41,1414331.672,374.887,
6
5378,724691.88,1414362.953,373.321,
6
5379,724696.269,1414358.245,372.66
3,6
5380,724687.766,1414367.506,373.83
5,6
5381,724682.151,1414372.805,373.95,
6
5382,724700.932,1414354.834,372.06
4,6
5383,724706.587,1414383.03,372.171,
6
5384,724700.82,1414387.458,372.404,
6
5385,724694.94,1414391.97,372.549,6
5386,724713.025,1414377.917,371.77
6,6
5387,724718.407,1414374.036,371.32
9,6
5388,724722.831,1414392.552,370.87
3,7
5389,724719.876,1414396.527,370.67,
7
5390,724717.548,1414399.362,370.03
8,7
5391,724713.423,1414404.315,370.12
7,7
5392,724729.993,1414412.604,369.77
2,AUX
5393,724716.981,1414423.973,370.07,
AUX
5394,724749.095,1414389.425,368.98
14

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

596,726565.6861,1415830.1519,368.1701,6
597,726569.9883,1415834.8463,367.8274,6
598,726548.5105,1415840.4936,368.4712,4
599,726534.7539,1415829.5611,368.2447,6
600,726541.5650,1415834.3094,368.6038,6
601,726555.0473,1415847.2594,368.4255,6
602,726562.7475,1415853.5444,368.2760,6
603,726524.1018,1415839.7744,368.2524,6
604,726529.5536,1415845.5625,369.0251,6
605,726544.3906,1415860.4291,369.1202,6
606,726553.5614,1415867.8613,368.9402,6
607,726536.0273,1415853.9965,369.3915,4
203,726576.2111,1415815.8754,368.0679,2
608,726675.7398,1415907.8827,361.1750,8
609,726678.7040,1415905.6564,360.7752,8
610,726687.0654,1415912.8657,360.0236,8
611,726531.4108,1415858.5254,369.3889,6
612,726529.7324,1415855.5240,369.3980,6
613,726533.3159,1415861.9436,369.3664,6
614,726530.6251,1415866.3088,369.2061,6
615,726527.9987,1415860.6893,369.1751,6
616,726525.8567,1415857.2301,369.1266,6
617,726524.3993,1415854.0505,369.0826,6

3,AUX
5395,724732.481,1414415.72,368.023,
6
5396,724735.167,1414418.861,365.16
9,22
5397,724735.736,1414419.818,361.88,
17
5398,724741.256,1414424.51,366.369,
22
5399,724743.816,1414427.883,368.49
5,6
54,724455.224,1414366.847,394.082,P
I
5400,724748.461,1414440.154,370.57
7,6
5401,724807.703,1414527.683,371.19
1,20
5402,724756.983,1414452.745,370.49
7,20
5403,724794.517,1414508.202,370.96
6,20
5404,724766.548,1414466.878,370.54
2,20
5405,724779.642,1414486.224,370.52
7,20
5406,724759.519,1414457.03,370.534,
6
5407,724763.738,1414452.892,370.19
8,6
5408,724755.246,1414460.312,370.76
4,6
5409,724766.842,1414448.315,370.00
1,6
5410,724770.751,1414475.101,370.51
1,6
5411,724765.999,1414479.841,370.97
9,6
5412,724777.209,1414472.41,370.062,
6
5413,724781.063,1414468.659,369.94
2,6
5414,724786.878,1414490.824,370.57
5,6
5415,724782.88,1414494.095,370.708,
6
5416,724794.079,1414483.962,370.24
15

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

618,726525.0187,1415863.1819,368.8835,6
619,726533.0488,1415870.5631,369.0363,6
620,726527.3066,1415868.2969,368.7858,6
621,726525.0604,1415863.1336,368.8868,6
622,726522.3176,1415859.2573,368.8153,6
623,726519.7255,1415856.1709,368.5723,6
624,726521.6656,1415865.5530,368.4311,6
625,726526.8355,1415869.0062,368.7204,6
626,726529.5026,1415873.3187,368.8625,6
627,726516.5054,1415860.0545,368.0268,6
628,726519.7912,1415863.8960,368.3467,6
629,726517.8858,1415868.8784,367.8394,6
630,726512.7635,1415863.1647,367.3409,6
631,726514.8374,1415865.9318,367.5422,6
632,726523.7244,1415870.8233,368.4565,6
633,726525.6926,1415875.5997,368.4596,6
634,726515.2628,1415872.8767,367.3793,6
635,726509.9621,1415867.3897,366.7525,6
636,726511.8671,1415869.8290,367.0001,6
637,726519.1648,1415877.1624,367.7690,6
638,726522.7106,1415881.2180,367.9288,6
639,726506.8868,1415871.3199,366.1002,6
640,726515.5750,1415880.9745,366.9469,6

9,6
5417,724779.016,1414497.228,370.81
4,6
5418,724797.582,1414514.399,371.07
4,6
5419,724801.939,1414511.004,371.05
3,6
5420,724797.6,1414514.433,371.064,6
5421,724809.641,1414504.266,370.97
9,6
5422,724792.216,1414517.341,371.08
1,6
5423,724787.645,1414520.307,371.17,
6
5424,724816.921,1414525.179,371.02
5,6
5425,724820.893,1414521.781,370.98
8,6
5426,724824.837,1414518.182,370.94
5,6
5427,724808.648,1414531.158,371.24
7,6
5428,724804.998,1414534.088,371.38
2,6
5429,724796.127,1414537.12,371.537,
6
5430,724824.589,1414539.196,371.02
1,6
5431,724828.086,1414535.937,370.89
5,6
5432,724816.225,1414546.059,371.43
4,6
5433,724834.127,1414529.665,370.74
1,6
5434,724813.727,1414548.598,371.56,
6
5435,724805.41,1414555.825,372.045,
6
5436,724828.706,1414560.027,371.34
1,6
5437,724835.365,1414552.445,370.81
3,6
5438,724824.817,1414564.594,371.62
9,6
5439,724837.628,1414549.37,370.659,
6
16

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
641,726518.3757,1415884.5554,367.2257,6
642,726507.5846,1415871.7291,366.2870,6
643,726506.8877,1415871.3798,366.1110,6
644,726529.5414,1415873.2378,368.8437,6
645,726527.9974,1415880.0025,368.5155,6
646,726526.8772,1415883.8789,368.2650,6
647,726526.1095,1415887.7545,368.0450,6
648,726537.5854,1415887.8695,368.4995,6
649,726537.4677,1415882.7435,368.7246,6
650,726536.8736,1415871.1123,369.1754,6
651,726536.5626,1415863.9322,369.4345,6
652,726541.6243,1415882.1852,368.7498,6
653,726543.1574,1415886.3441,368.6011,6
654,726545.4155,1415880.2323,368.8323,6
655,726541.0359,1415868.6597,369.2169,6
656,726547.4319,1415884.0194,368.7114,6
657,726552.2602,1415881.0854,368.8164,6
658,726548.6483,1415877.1842,368.9683,6
659,726551.0918,1415873.3638,368.9476,6
660,726539.3167,1415860.5808,369.3602,6
661,726554.5743,1415877.1827,368.9336,6
662,726553.0299,1415868.9608,368.9217,6
663,726553.0202,1415869.0024,368.9239,6

5440,724814.338,1414574.173,372.31
5,6
5441,724843.61,1414542.889,370.394,
6
5442,724728.995,1414388.374,370.68
4,6
5443,724741.112,1414399.611,368.47
9,22
5444,724745.803,1414412.465,361.81,
17
5445,724748.313,1414412.945,361.92
6,22
5446,724751.32,1414412.852,363.307,
22
5447,724757.118,1414414.144,365.15
4,6
5448,724764.841,1414414.859,367.81
9,6
5449,724766.987,1414412.585,368.07
6,6
5450,724754.804,1414420.658,367.81
8,6
5451,724755.717,1414423.86,369.582,
6
5452,724753.097,1414397.077,367.43
1,6
5453,724765.258,1414410.175,366.60
5,6
5454,724755.487,1414399.535,365.35
4,22
5455,724763.641,1414409.132,365.41
4,22
5456,724760.412,1414405.586,361.58
5,17
5457,724778.771,1414389.737,366.09
3,6
5458,724759.449,1414374.039,367.30
3,6
5459,724774.414,1414387.527,364.89,
6
5460,724752.489,1414368.01,368.837,
6
5461,724771.215,1414385.625,362.34
5,22
5462,724767.257,1414383.702,361.15
8,17
17

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
664,726558.5698,1415872.1207,368.9624,6
665,726553.7086,1415864.1549,368.7923,6
666,726561.3014,1415867.3295,368.7932,6
667,726548.3120,1415862.9544,369.0217,6
668,726547.9367,1415858.9356,368.8710,6
669,726553.4913,1415859.7609,368.6754,6
670,726562.7141,1415861.9006,368.6034,6
671,726538.9849,1415857.7095,369.3519,6
672,726562.4148,1415855.9774,368.4062,6
673,726552.5728,1415855.0911,368.5777,6
674,726546.6123,1415856.1397,368.8553,6
675,726537.1054,1415854.3140,369.4316,6
676,726561.7295,1415850.5842,368.2879,6
677,726544.6675,1415852.9744,368.8390,6
678,726550.7703,1415850.8679,368.5092,6
679,726536.9791,1415854.2734,369.4260,6
680,726525.1778,1415857.5019,369.0595,6
681,726517.9563,1415857.5243,368.2834,6
682,726509.3469,1415857.7690,366.8287,6
683,726503.6994,1415857.6358,366.0466,6
684,726510.0361,1415852.4953,366.9689,6
685,726525.7028,1415854.5943,369.1355,6
686,726503.4082,1415850.7084,365.9197,6

5463,724764.897,1414379.642,362.59,
22
5464,724708.013,1414440.947,370.46
3,AUX
5465,724739.109,1414438.583,370.25
8,6
5466,724733.071,1414434.811,368.33
4,6
5467,724727.781,1414432.692,366.72
2,22
5468,724723.046,1414430.397,361.93
5,17
5469,724720.442,1414427.505,365.88
3,22
5470,724718.355,1414425.315,368.61
2,6
5471,724715.538,1414422.042,370.93
1,6
5472,724733.777,1414454.843,371.71
2,6
5473,724725.352,1414449.506,369.03
4,6
5474,724719.657,1414446.895,366.75
2,6
5475,724705.034,1414439.383,371.56
4,6
5476,724710.848,1414443.179,368.32
2,6
5477,724712.324,1414443.96,366.958,
22
5478,724716.55,1414446.861,365.13,2
2
5479,724715.328,1414445.983,362.88
8,17
5480,724893.625,1414619.184,370.05
6,20
5481,724836.202,1414561.694,370.96
6,20
5482,724885.046,1414610.594,370.57
7,20
5483,724876.082,1414601.62,370.841,
20
5484,724850.669,1414576.178,370.86
5,20
5485,724867.39,1414593.129,370.907,
7
18

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
687,726510.1327,1415852.4326,366.9536,6
688,726620.3698,1416500.2003,391.2965,8
689,726609.3796,1416495.3795,391.5167,8
690,726605.0432,1416500.8030,391.1709,8
691,726406.2402,1415983.6758,368.4888,8
692,726423.1831,1415988.0155,367.7420,8
693,726520.8683,1415843.2256,368.1782,4
694,726517.3818,1415847.0841,367.9971,6
695,726508.6712,1415829.0937,366.7695,4
696,726502.8389,1415835.6491,366.0576,6
697,726498.0118,1415839.9225,365.5558,6
698,726514.0368,1415824.6750,367.1849,6
699,726520.9148,1415822.5320,367.5676,6
700,726496.7231,1415815.1624,365.7904,4
701,726490.1566,1415825.5095,365.5692,6
702,726483.8342,1415831.2160,365.0144,6
703,726500.2084,1415811.2842,365.9247,6
704,726506.9990,1415804.0700,366.3092,6
705,726484.4288,1415800.7789,365.0539,4
706,726479.8983,1415807.1431,364.9801,6
707,726473.9644,1415816.3502,364.7002,6
708,726488.0106,1415794.1211,365.2228,6
709,726490.3108,1415787.8329,365.3004,6
710,726471.5131,1415786.1230,364.3308,4

5486,724863.677,1414598.611,371.40
9,7
5487,724859.473,1414605.194,371.94
4,7
5488,724869.203,1414590.047,370.56
6,7
5489,724874.41,1414582.029,370.009,
7
5490,724843.175,1414577.139,371.07,
6
5491,724847.083,1414573.122,370.79
7,6
5492,724852.015,1414569.351,370.57
5,6
5493,724856.687,1414565.086,370.23
6,6
5494,724836.276,1414583.509,371.71
8,6
5495,724980.688,1414706.546,365.14
7,20
5496,724914.296,1414639.914,368.37
5,20
5497,724969.374,1414695.191,365.56
9,20
5498,724929.995,1414655.669,367.43
3,20
5499,724958.338,1414684.115,366.16
2,20
55,724633.119,1414268.612,390.647,P
I
5500,724941.346,1414667.062,366.95
7,20
5501,724958.317,1414684.139,366.19
7,AUX
5502,724895.38,1414601.044,369.06,6
5503,724890.412,1414606.048,369.81
9,6
5504,724887.075,1414610.009,370.34
6,6
5505,724882.459,1414614.928,370.89
1,6
5506,724910.477,1414617.812,367.96
6,6
5507,724906.309,1414621.056,368.59
3,6
5508,724895.599,1414629.608,369.98
19

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

711,726466.0859,1415793.5148,364.3202,6
712,726457.7895,1415803.7446,364.0111,6
713,726476.2365,1415781.3911,364.4365,6
714,726481.4302,1415775.2692,364.5074,6
715,726459.2266,1415771.8593,363.7728,4
716,726452.1170,1415778.1171,363.7034,6
717,726442.6145,1415787.3281,363.4993,6
718,726465.5429,1415766.3996,363.9347,6
719,726471.4723,1415762.0236,364.1786,6
720,726446.8254,1415757.2330,363.6826,4
721,726437.7629,1415765.6369,363.5662,6
722,726428.5617,1415772.6826,363.4900,6
723,726453.6865,1415751.2080,363.9828,6
724,726460.6040,1415745.6636,363.9788,6
725,726434.5460,1415743.3791,363.7432,4
726,726423.2914,1415752.4210,363.6827,6
727,726414.6336,1415760.2193,363.6669,6
728,726441.6097,1415736.3492,363.8338,6
729,726448.6557,1415731.5676,364.1598,6
730,726422.4150,1415729.2253,364.3323,4
731,726414.5735,1415736.0558,364.0054,6
732,726405.5396,1415743.2450,363.8789,6
733,726436.0773,1415717.4187,364.1871,6

8,6
5509,724892.595,1414633.834,370.20
3,6
5510,724914.293,1414633.572,368.13
7,6
5511,724919.194,1414628.37,367.314,
6
5512,724910.675,1414637.879,368.68
7,6
5513,724906.976,1414643.703,369.09,
6
5514,724928.847,1414647.677,367.25
7,6
5515,724931.941,1414644.874,366.94
2,6
5516,724920.386,1414655.709,368.18
7,6
5517,724923.992,1414652.965,367.77
6,6
5518,724945.773,1414670.879,366.70
1,6
5519,724948.956,1414667.926,366.42
7,6
5520,724954.217,1414662.804,366.12
1,6
5521,724939.852,1414675.774,367.08
4,6
5522,724950.522,1414690.403,366.69
6,6
5523,724957.618,1414684.553,366.18
8,6
5524,724947.845,1414692.405,367.01
1,6
5525,724974.539,1414693.092,363.78
1,6
5526,724970.681,1414697.472,365.63
1,6
5527,724973.875,1414696.303,365.03,
6
5528,724966.613,1414700.991,366.12
7,6
5529,724963.282,1414704.214,366.30
4,6
5530,724988.611,1414714.24,364.607,
6
5531,724985.519,1414717.207,364.86
20

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

734,726428.6456,1415723.5770,364.2564,6
735,726410.6959,1415715.3769,365.1373,4
736,726401.4281,1415724.2547,364.3620,6
737,726394.8307,1415730.3248,363.8692,6
738,726415.8225,1415709.1846,364.8389,6
739,726419.3989,1415706.5103,364.6117,6
740,726424.1383,1415701.9785,364.3938,6
741,726398.1340,1415701.1022,365.5543,4
742,726405.8333,1415693.2022,365.4924,6
743,726411.5307,1415687.6216,365.2450,6
744,726388.4765,1415708.6425,364.9567,6
745,726380.6687,1415714.7481,364.2902,6
746,726387.2864,1415686.5391,365.4748,4
747,726381.0562,1415693.9198,365.2100,6
748,726371.7411,1415703.9968,364.9198,6
749,726400.2261,1415674.1015,366.1221,6
750,726394.6253,1415678.5089,365.9380,6
751,726375.1439,1415672.3366,365.2676,4
752,726381.0314,1415667.2117,365.8439,6
753,726385.9787,1415662.3681,366.0359,6
754,726367.9442,1415678.5263,364.6117,6
755,726363.4172,1415682.2917,364.4000,6
756,726362.9535,1415657.8995,363.7745,4
757,726367.8412,1415652.5565,364.0129,6

7,6
5532,724982.609,1414719.402,365.05
5,6
5533,724991.338,1414709.964,364.54
2,6
5534,724994.352,1414706.663,363.72
1,6
5535,724957.561,1414771.581,363.70
6,AUX
5536,724940.929,1414735.013,363.68
3,20
5537,724949.274,1414753.362,363.92
2,20
5538,724947.501,1414731.606,363.69
9,6
5539,724951.085,1414729.913,363.59
4,6
5540,724938.179,1414737.639,363.48
2,6
5541,724936,1414738.786,363.315,6
5542,724950.921,1414757.625,363.9,6
5543,724948.156,1414758.562,363.92
3,6
5544,724946.547,1414758.818,363.81
4,6
5545,724968.287,1414794.441,363.06
5,AUX
5546,724977.973,1414815.475,362.49
5,AUX
5547,724954.35,1414755.696,363.846,
AUX
5548,724956.641,1414754.77,363.498,
6
5549,724975.26,1414756.614,358.327,
17
5550,724961.744,1414767.862,363.46
9,6
5551,724987.659,1414746.272,360.52
7,7
5552,724966.728,1414763.098,360.53,
7
5553,724961.545,1414767.522,363.57
3,7
5554,724984.603,1414748.512,359.84
3,7
5555,724952.755,1414774.59,363.765,
21

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

758,726372.6800,1415647.8760,364.2747,6
759,726357.5249,1415664.0248,363.6594,6
760,726351.5505,1415669.8640,363.0666,6
761,726350.3159,1415643.3488,361.9751,4
762,726347.0162,1415651.1924,361.9008,6
763,726343.9347,1415659.1793,361.9836,6
764,726354.9424,1415635.9417,362.0329,6
765,726358.0353,1415630.5519,362.5142,6
766,726340.9689,1415667.8128,362.0222,7
767,726360.9737,1415612.3253,363.0531,7
768,726348.9737,1415604.9675,362.9524,7
769,726329.3709,1415660.5512,361.1650,7
770,726339.7276,1415630.8394,361.4750,4
771,726343.8251,1415618.6577,361.7827,6
772,726336.7379,1415638.8213,361.4727,6
773,726333.9288,1415646.0600,361.5007,6
774,726346.2955,1415612.4136,362.5041,6
775,726328.2058,1415617.0889,362.6391,4
776,726333.5180,1415609.3421,363.3111,6
777,726336.6627,1415604.6794,363.5476,6
778,726323.1442,1415623.8418,362.0303,6
779,726318.7409,1415630.6466,361.4606,6
780,726320.4862,1415608.4913,364.2865,4

7
5556,724947.291,1414779.082,363.40
9,7
5557,724941.405,1414783.836,361.28
8,22
5558,724925.326,1414797.403,361.38
3,22
5559,724928.616,1414795.026,360.36
2,22
5560,724930.866,1414792.846,358.8,1
7
5561,725000.521,1414784.45,360.836,
6
5562,724996.051,1414786.094,360.07
2,6
5563,724991.556,1414787.203,358.27
9,22
5564,724988.754,1414788.417,358.16
7,17
5565,724980.641,1414790.819,359.78
6,22
5566,724976.011,1414790.793,362.57
3,6
5567,724971.827,1414792.552,362.87
6,6
5568,724962.766,1414796.698,363.03
7,6
5569,724940.268,1414805.31,360.806,
6
5570,724956.715,1414798.586,361.38
9,22
5571,724945.388,1414803.186,359.35
7,22
5572,724947.298,1414802.373,358.77
3,17
5573,725014.008,1414795.069,361.23
9,6
5574,725009.923,1414796.782,360.24
4,6
5575,725005.858,1414799.262,359.42
6,22
5576,725001.023,1414802.055,358.70
5,17
5577,724997.072,1414804.306,358.65
8,22
5578,724993.507,1414806.328,360.39
22

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

781,726326.1761,1415600.5559,364.4779,6
782,726330.2698,1415593.7093,364.3687,6
783,726315.0111,1415616.3939,363.2174,6
784,726309.6243,1415623.2963,363.0145,6
785,726308.9630,1415594.6883,364.5203,4
786,726314.1771,1415588.5249,364.3864,6
787,726318.0728,1415581.7023,364.2959,6
788,726303.9975,1415601.4681,364.5697,6
789,726298.5111,1415609.0789,364.3686,6
790,726295.1271,1415590.2158,364.4979,6
791,726288.2449,1415595.1729,364.3879,6
792,726306.0707,1415578.6282,364.5125,6
793,726310.2247,1415571.7655,364.5106,6
794,726288.8892,1415572.8791,364.3979,4
795,726283.7680,1415577.8905,364.6137,6
796,726277.4448,1415583.4397,364.8003,6
797,726293.9759,1415567.2699,364.5059,6
798,726298.4301,1415561.1284,364.5920,6
799,726273.6316,1415560.0117,363.4492,4
800,726267.6208,1415565.3104,363.2115,6
801,726260.5062,1415571.4510,363.3909,6
802,726279.4368,1415553.7195,363.8109,6
803,726284.8618,1415549.0535,364.1209,6
804,726259.8325,1415547.2658,363.1111,4

6,6
5579,724989.683,1414808.291,362.07
7,6
5580,724982.384,1414812.51,362.559,
6
5581,724973.725,1414816.93,361.92,6
5582,724967.841,1414820.291,359.87
9,22
5583,724954.161,1414828.618,360.44
5,6
5584,724959.073,1414825.514,359.32
2,22
5585,724964.233,1414823.063,359.05,
17
5586,724980.527,1414819.908,361.46
3,6
5587,724984.28,1414826.913,358.844,
22
5588,724984.857,1414829.464,359.00
2,17
5589,724999.417,1414859.379,363.65
5,6
5590,724995.273,1414851.176,360.47
2,22
5591,724994.593,1414848.017,358.98
8,22
5592,725180.552,1414860.994,363.71,
BM
5593,725142.483,1414840.382,365.25
1,20
5594,725155.641,1414847.506,365.00
3,20
5595,725168.061,1414854.23,364.438,
20
5596,725179.185,1414860.254,363.79
3,20
5597,725182.449,1414862.021,363.27
3,20
5598,725186.104,1414864,362.305,20
5599,725191.228,1414866.774,362.35
6,20
56,724818.485,1414543.956,371.156,P
I
5600,725197.277,1414870.05,363.309,
20
5601,725207.221,1414875.434,363.37
23

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

805,726252.8793,1415553.4572,362.0959,6
806,726244.7578,1415559.8290,361.4485,6
807,726264.7471,1415542.6595,363.7596,6
808,726270.9796,1415537.9339,364.4753,6
809,726246.0928,1415534.5954,363.1388,4
810,726233.3128,1415547.0294,360.9751,6
811,726239.6900,1415540.2494,362.1700,6
812,726251.0459,1415528.4104,364.2352,6
813,726254.9967,1415523.9856,365.1969,6
814,726231.6406,1415521.1628,362.5686,4
815,726226.5919,1415526.9259,361.6944,6
816,726221.0502,1415532.7042,360.8944,6
817,726235.4729,1415516.6175,363.6256,6
818,726239.0634,1415512.8451,364.6982,6
819,726218.2418,1415508.9958,362.4032,4
820,726213.8944,1415513.3024,361.5246,6
821,726209.1854,1415518.6480,360.8128,6
822,726222.6764,1415503.6209,363.4386,6
823,726226.8324,1415499.3976,364.6547,6
825,726199.4197,1415501.3986,360.3075,6
826,726195.0110,1415506.3714,359.5509,6
827,726208.5232,1415491.0727,362.5415,6
828,726213.2364,1415485.2688,364.0667,6

8,20
5602,725220.258,1414882.492,363.31
3,20
5603,725230.86,1414888.233,363.71,2
0
5604,725235.011,1414890.48,363.958,
20
5605,725132.131,1414823.857,364.18
4,6
5606,725130.121,1414828.138,364.53
5,6
5607,725128.3,1414832.723,364.786,6
5608,725125.829,1414837.424,365.23
2,6
5609,725123.798,1414842.002,365.51
4,6
5610,725147.528,1414844.554,365.35
7,6
5611,725149.817,1414840.567,364.96
3,6
5612,725151.568,1414837.189,364.58
4,6
5613,725145.544,1414848.185,365.55
2,6
5614,725143.464,1414850.86,365.736,
6
5615,725168.055,1414853.781,364.43
8,6
5616,725166.471,1414859.464,364.52
6,6
5617,725169.148,1414850.011,364.26
3,6
5618,725162.571,1414865.474,364.61
6,6
5619,725169.808,1414846.849,364.15
7,6
5620,725179.878,1414860.334,363.77
5,6
5621,725176.718,1414864.075,363.51
8,6
5622,725170.339,1414869.945,363.55
3,6
5623,725186.316,1414854.277,363.59
7,6
5624,725252.705,1414900.055,363.65
1,20
24

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
824,726203.7132,1415496.7782,361.2177,4
829,726205.3126,1415509.1631,360.8591,6
830,726200.8845,1415515.6639,360.0900,6
831,726217.1427,1415492.7275,363.9362,6
832,726221.7680,1415486.1620,365.5164,6
833,726188.7459,1415485.5586,359.5567,4
834,726184.8923,1415491.4981,358.4615,6
835,726180.9747,1415497.0273,355.5227,6
836,726193.0041,1415478.2871,360.8519,6
837,726196.3851,1415472.1232,362.4355,6
838,726175.0186,1415475.2700,358.3527,4
839,726172.7802,1415480.6183,357.3417,6
840,726169.4472,1415487.5803,355.0474,6
841,726178.1409,1415467.7603,360.3819,6
842,726180.8852,1415462.4260,361.7701,6
843,726160.8824,1415464.7783,358.3304,4
844,726157.5517,1415469.9817,356.8733,6
845,726153.8632,1415476.1778,355.3070,6
846,726164.6638,1415459.6442,359.9829,6
847,726168.5428,1415454.3485,361.7124,6
848,726147.9038,1415455.0760,357.9787,4
849,726144.4686,1415460.1593,356.1750,6
850,726139.9493,1415465.7072,354.4091,6

5625,725241.792,1414894.111,363.99
1,20
5626,725199.229,1414874.358,363.72
7,6
5627,725201.674,1414870.457,363.23
1,6
5628,725196.914,1414878.546,363.74
5,6
5629,725194.616,1414882.648,364.03
7,6
5630,725203.118,1414866.818,362.62
6,6
5631,725220.899,1414879.986,363.17
9,6
5632,725219.069,1414884.526,363.47
1,6
5633,725217.303,1414888.53,363.803,
6
5634,725222.434,1414876.43,362.934,
6
5635,725240.131,1414887.941,363.35
9,6
5636,725237.609,1414891.485,363.84
7,6
5637,725236.085,1414894.455,364.25
2,6
5638,725241.923,1414883.897,363.00
4,6
5639,725316.151,1414931.329,361.64
7,AUX
5640,725307.255,1414926.978,362.26
7,20
5641,725298.247,1414922.573,362.65
3,20
5642,725285.192,1414916.188,363.09
1,20
5643,725271.323,1414909.406,362.95
6,20
5644,725232.989,1414890.797,364.05
8,7
5645,725239.145,1414890.153,363.61
2,7
5646,725246.386,1414889.826,363.24
1,7
5647,725258.092,1414888.605,362.33
7,7
25

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
851,726150.7958,1415451.1420,359.3366,6
852,726153.5776,1415447.1905,360.2229,6
853,726133.5167,1415444.4784,358.0146,4
854,726130.4203,1415450.8092,356.0417,6
855,726127.6805,1415455.5792,354.6063,6
856,726135.6591,1415439.5457,359.5925,6
857,726139.2139,1415434.4838,361.1661,6
858,726138.7400,1415433.7072,361.5446,7
859,726119.4846,1415433.9519,359.0184,4
860,726122.4369,1415427.9797,360.5715,7
861,726125.1455,1415423.4991,361.6227,6
862,726116.3744,1415439.6421,357.8351,6
863,726112.0541,1415446.4139,355.8827,6
864,726105.3234,1415423.3866,360.1913,4
865,726108.7051,1415418.2931,360.9936,6
866,726113.6477,1415410.2993,362.2560,6
867,726116.2375,1415411.5793,362.2857,7
868,726101.0037,1415428.1616,359.0834,6
869,726096.1436,1415433.2481,357.2209,6
870,726100.7190,1415420.0727,360.1216,7
871,726094.1811,1415414.8362,360.3481,4
872,726095.6483,1415410.9196,360.8877,6
873,726099.7804,1415405.0865,361.7404,7

5648,725271.692,1414910.129,362.97,
6
5649,725269.799,1414914.073,363.19
9,6
5650,725267.098,1414919.125,363.72
6,6
5651,725263.907,1414924.648,364.31
8,6
5652,725275.021,1414904.451,362.41
4,6
5653,725277.293,1414900.871,362.09,
6
5654,725291.793,1414919.494,363.10
9,6
5655,725289.494,1414923.53,363.348,
6
5656,725286.895,1414928.276,363.67
6,6
5657,725283.212,1414933.887,364.01
2,6
5658,725294.172,1414914.558,362.66,
6
5659,725313.526,1414930.248,361.73
3,6
5660,725316.177,1414925.633,361.44
6,6
5661,725312.164,1414935.375,361.92
1,6
5662,725309.803,1414940.604,362.26
4,6
5663,725333.487,1414943.585,360.69
2,6
5664,725329.658,1414948.921,361.22
8,6
5665,725336.31,1414939.799,360.309,
6
5666,725338.746,1414934.019,360.11
3,6
5667,725417.921,1414981.17,361.599,
20
5668,725347.028,1414946.451,360.11
2,20
5669,725402.375,1414973.558,361.62
3,20
5670,725365.903,1414955.695,360.24,
20
26

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
874,726101.0431,1415401.8838,362.2105,6
875,726092.2608,1415416.7305,359.9640,7
876,726088.8248,1415421.1191,359.3212,6
877,726085.9675,1415428.7012,357.8393,6
204,726071.6811,1415398.1587,361.7949,2
878,726033.0074,1415380.1745,359.2180,7
879,726015.6439,1415375.3099,357.9456,7
880,726031.2134,1415395.0487,357.6328,7
881,726079.6536,1415404.2172,361.4455,4
882,726081.5097,1415398.3085,362.1316,7
883,726076.8243,1415411.3098,360.5729,7
884,726083.3166,1415394.1715,362.5106,6
885,726072.8376,1415418.7631,359.8127,6
886,726065.1232,1415393.2961,361.4962,4
887,726065.5319,1415392.3518,361.5905,7
888,726069.4904,1415386.0499,362.1924,6
889,726071.3387,1415382.4699,362.0101,6
890,726061.5030,1415400.1118,360.5961,6
891,726058.8476,1415404.9671,359.7462,7
892,725796.5830,1416204.3619,378.3706,8
893,725782.7828,1416201.9763,378.9557,8
894,726049.1964,1415381.3738,360.0793,4
895,726045.2379,1415388.1334,359.5827,6
896,726042.0597,1415395.1621,358.8112,6

5671,725387.55,1414966.296,361.101,
20
5672,725362.423,1414938.897,359.30
8,6
5673,725359.516,1414944.866,359.51
1,6
5674,725357.504,1414948.893,359.77
3,6
5675,725354.269,1414955.538,360.36
6,6
5676,725352.566,1414958.5,360.712,6
5677,725385.076,1414946.327,359.00
6,6
5678,725383.031,1414951.384,359.61
3,6
5679,725380.795,1414957.008,360.17
2,6
5680,725377.227,1414962.634,360.73
6,6
5681,725375.031,1414965.629,361.09
2,6
5682,725434.571,1414989.683,361.35
9,20
5683,725601.111,1415076.898,364.48
9,20
5684,725454.583,1415000.163,360.71
7,20
5685,725583.036,1415067.432,363.86
4,20
5686,725477.528,1415012.179,359.68
6,20
5687,725566.06,1415058.542,363.126,
20
5688,725501.94,1415024.964,359.856,
20
5689,725548.16,1415049.168,362.37,2
0
5690,725517.129,1415032.918,361.06
9,20
5691,725537.589,1415043.633,362.12
5,20
5692,725405.941,1414959.993,360.45
5,6
5693,725403.871,1414964.919,360.83
3,6
5694,725401.441,1414970.748,361.22
27

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

897,726052.5407,1415375.2338,360.5485,6
898,726055.3686,1415370.6665,360.6525,6
899,725653.3138,1416096.4592,358.1457,8
900,725649.2149,1416093.7050,358.0106,8
901,725646.0565,1416097.0818,358.0992,8
902,726034.6808,1415370.5221,359.6055,4
903,726028.5349,1415378.7882,358.9144,6
904,726024.6222,1415385.3617,358.0836,6
905,726038.3724,1415364.3748,359.8999,6
906,726041.8089,1415358.0453,360.1444,6
907,726019.5588,1415359.2254,359.2676,4
908,726013.9099,1415365.9677,358.8555,6
909,726007.6312,1415373.3663,357.9797,7
910,726023.9543,1415353.2398,359.7703,6
911,726027.6662,1415347.7283,359.7811,6
912,726004.4186,1415347.9219,359.4016,4
913,725998.5295,1415353.9920,359.0682,6
914,725990.8962,1415362.5040,358.5498,6
915,726008.1795,1415342.7193,359.3922,6
916,726012.7478,1415336.1819,359.2512,6
917,725916.5413,1415945.8013,363.0404,8
918,725907.6396,1415940.2006,362.6029,8
919,725904.7575,1415944.1787,362.7585,8
921,725983.4344,1415343.9864,359.3739,6

6,6
5695,725399.594,1414976.133,361.75
7,6
5696,725432.913,1414990.709,361.41
2,7
5697,725432.164,1414995.807,361.59
3,7
5698,725434.202,1414980.428,361.04
4,7
5699,725433.735,1414984.613,361.23
2,7
57,724899.965,1414625.466,369.586,P
I
5700,725457.33,1414992.198,360.521,
6
5701,725455.633,1414997.041,360.62
8,6
5702,725453.973,1415001.893,360.71
9,6
5703,725452.753,1415005.71,360.795,
6
5704,725476.138,1415020.992,359.95
2,6
5705,725477.74,1415016.033,359.749,
6
5706,725479.648,1415011,359.515,6
5707,725481.773,1415006.809,359.42
1,6
5708,725503.171,1415020.901,359.73
5,6
5709,725496.336,1415033.727,360.20
8,6
5710,725500.748,1415024.794,359.85
1,6
5711,725499.178,1415029.042,360.04
4,6
5712,725521.262,1415041.773,361.63
8,6
5713,725523.979,1415037.211,361.49
5,6
5714,725525.759,1415032.639,361.34
5,6
5715,725527.218,1415029.454,361.33
3,6
5716,725547.651,1415041.503,362.3,6
5717,725545.509,1415046.205,362.27
28

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

922,725977.1180,1415350.4013,358.8893,6
923,725994.5918,1415330.2466,359.3481,6
924,725998.7605,1415325.0112,359.1518,6
925,725989.5947,1415336.8608,359.4289,4
926,725974.6073,1415325.6703,359.6498,4
927,725969.1677,1415332.0539,359.2477,6
928,725964.3034,1415338.3802,359.2351,6
929,725979.4544,1415319.5651,359.4471,6
930,725982.6741,1415315.2176,359.3087,6
931,725960.7620,1415315.3069,360.3159,4
932,725955.9267,1415320.6297,360.3774,6
933,725951.8931,1415326.2877,359.6555,6
934,725968.1040,1415304.3214,359.5890,6
935,725963.1775,1415310.9673,360.0609,6
936,725946.0883,1415304.8989,360.4512,4
937,725949.3364,1415299.7316,360.3027,6
938,725953.0035,1415294.8270,360.1188,6
939,725941.0522,1415311.2027,360.6505,6
940,725937.3009,1415315.6479,360.6202,6
941,725931.3167,1415294.3636,360.3940,4
942,725936.4570,1415287.0536,360.2117,6
943,725940.8544,1415280.0579,359.8242,6
944,725921.7950,1415304.5313,360.8367,6

2,6
5718,725542.187,1415052.598,362.33
6,6
5719,725539.265,1415057.893,362.42
3,6
5720,725566.516,1415052.365,363.16
5,6
5721,725563.684,1415058.501,363.01
9,6
5722,725561.172,1415064.518,363.07
1,6
5723,725559.675,1415068.153,362.96
2,6
5724,725584.908,1415061.437,363.96,
6
5725,725582.758,1415067.265,363.88
9,6
5726,725580.139,1415073.314,364.02
7,6
5727,725578.288,1415078.507,364.33
1,6
5728,725693.302,1415128.219,364.03
6,20
5729,725676.695,1415118.928,364.72
2,20
5730,725660.583,1415109.912,364.84
2,20
5731,725643.959,1415100.611,364.75
1,20
5732,725627.421,1415091.358,364.69
3,20
5733,725630.648,1415088.127,364.39
5,6
5734,725627.324,1415091.019,364.62
4,6
5735,725621.77,1415096.23,365.148,6
5736,725633.727,1415084.727,364.15,
6
5737,725644.729,1415102.441,364.85
7,6
5738,725647.471,1415097.672,364.61
1,6
5739,725650.235,1415093.359,364.42
7,6
5740,725641.874,1415105.338,364.95,
6
29

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
945,725926.7097,1415299.7237,360.7045,6
946,725894.5501,1415312.1035,361.5653,8
947,725898.1227,1415319.1860,361.5602,8
948,725892.2801,1415325.5937,361.5076,8
206,727224.3849,1415828.8513,357.4970,2
949,727508.2915,1416116.0312,340.4507,8
950,727507.1317,1416117.7709,340.4445,8
1,724094.0000,1414597.0000,403.0000
2,724136.9250,1414561.5650,401.6420
960,724612.8300,1414276.3900,A
961,726952.4900,1416154.1610,,B
55,724633.1190,1414268.6120,390.6490,
56,724818.4850,1414543.9560,371.1560,
1,724094,1414597,403,
2,724136.925,1414561.565,401.642,BM
50,724140.548,1414534.01,404.42,PI
5000,724104.742,1414603.436,403.358,FUENTE
5001,724107.879,1414597.52,402.848,6
5002,724112.415,1414597.209,403.877,6
5003,724107.545,1414603.127,404.139,6
5004,724116.318,1414597.443,405.942,6
5005,724120.619,1414598.114,407.75,6
5006,724104.591,1414606.354,404.766,6
5007,724115.377,1414605.227,407.005,6

5741,725665.306,1415113.294,364.8,6
5742,725668.867,1415109.122,364.54
5,6
5743,725660.432,1415117.778,365.09
9,6
5744,725671.414,1415104.567,364.35
4,6
5745,725687.482,1415124.766,364.47,
6
5746,725683.237,1415129.107,364.59
8,6
5747,725690.75,1415121.046,364.108,
6
5748,725943.095,1415302.567,360.67
1,20
5749,725717.992,1415143.789,363.34
1,20
5750,725928.786,1415292.475,360.54
4,20
5751,725738.179,1415158.028,363.09
9,20
5752,725912.881,1415281.255,360.64
6,20
5753,725762.792,1415175.389,362.27
6,20
5754,725892.674,1415267.004,360.35
2,20
5755,725787.89,1415193.092,361.524,
20
5756,725871.726,1415252.227,360.91
8,20
5757,725809.491,1415208.329,361.19
3,20
5758,725852.192,1415238.449,360.79
7,20
5759,725827.107,1415220.754,360.94
5,20
5760,725842.58,1415231.669,360.722,
20
5761,725842.606,1415231.651,360.75
3,AUX
5762,725706.069,1415136.698,363.73
3,7
5763,725702.694,1415139.29,363.997,
7
5764,725710.099,1415133.663,363.39
30

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

5008,724100.338,1414609.186,406.41,6
5009,724118.654,1414606.601,408.405,6
5010,724107.864,1414611.366,407.172,6
5011,724110.038,1414615.442,409.283,6
5012,724111.771,1414617.361,410.04,6
5013,724096.347,1414612.293,406.882,6
5014,724101.779,1414613.354,407.875,6
5015,724103.785,1414617.419,409.667,6
5016,724105.266,1414620.07,410.771,6
5017,724083.987,1414620.57,407.599,6
5018,724087.421,1414602.397,403.928,6
5019,724089.114,1414594.844,403.426,6
5020,724085.173,1414605.961,403.969,6
5021,724082.437,1414608.967,404.236,6
5022,724085.794,1414594.315,402.972,6
5023,724079.495,1414611.177,404.324,6
5024,724084.276,1414593.852,402.202,6
5025,724088.384,1414598.45,403.793,6
5026,724084.543,1414599.585,404.167,6
5027,724080.983,1414600.655,403.266,6
5028,724092.412,1414590.633,402.908,6
5029,724094.28,1414590.123,402.925,6
5030,724090.565,1414586.251,402.342,6

7,7
5765,725714.728,1415130.254,363.22
6,7
5766,725728.319,1415153.484,363.18
7,6
5767,725724.662,1415156.578,363.53
5,6
5768,725731.408,1415150.254,362.94
5,6
5769,725735.509,1415146.246,362.77,
6
5770,725749.617,1415169.33,362.781,
6
5771,725745.374,1415172.607,362.93
4,6
5772,725752.774,1415166.391,362.61
9,6
5773,725758.148,1415159.638,362.44
7,6
5774,725770.91,1415184.336,361.879,
6
5775,725766.718,1415188.387,362.15,
6
5776,725773.654,1415180.276,361.79
1,6
5777,725776.152,1415177.16,361.672,
6
5778,725792.633,1415197.895,361.37
7,6
5779,725788.158,1415202.361,361.56
3,6
5780,725795.651,1415191.691,361.09,
6
5781,725797.847,1415188.28,361.001,
6
5782,725816.156,1415219.713,361.32
5,6
5783,725818.88,1415216.54,361.115,6
5784,725838.875,1415229.422,360.69
8,6
5785,725823.279,1415209.669,360.59
4,6
5786,725835.601,1415232.76,360.942,
6
5787,725825.853,1415206.153,360.45
9,6
31

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012
5031,724094.785,1414587.714,402.823,6
5032,724095.195,1414584.202,402.863,7
5033,724098.362,1414590.699,403.107,7
5034,724100.271,1414587.336,403.306,6
5035,724100.212,1414600.539,402.908,6
5036,724101.142,1414584.466,402.848,7
5037,724107.769,1414585.351,402.268,7
5038,724108.008,1414598.574,403.053,7
5039,724106.754,1414604.574,404.005,7
5040,724096.392,1414612.219,406.891,7
5041,724095.311,1414604.683,403.613,6
5042,724096.384,1414597.171,402.612,6
5043,724099.368,1414599.339,402.682,6
5044,724099.364,1414595.143,402.404,6
5045,724094.406,1414593.844,403.08,6
5046,724103.823,1414599.735,402.712,6
5047,724098.054,1414591.325,402.995,6
5048,724100.929,1414595.861,402.181,6
5049,724104.964,1414594.77,402.361,6
5050,724090.898,1414598.953,403.367,6
5051,724093.164,1414598.874,403.102,15
5052,724092.375,1414595.047,403.319,15
5053,724091.59,1414596.886,403.346,6
5054,724115.761,1414578.579,402.077,AUX

5788,725832.692,1415235.811,361.28
4,6
5789,725844.989,1415223.085,360.30
8,6
5790,725848.363,1415219.375,359.96
9,6
5791,725844.93,1415233.347,360.771,
6
5792,725848.62,1415229.992,360.367,
6
5793,725841.23,1415237.152,361.144,
6
5794,725851.989,1415227.007,360.06
3,6
5795,725837.41,1415240.969,361.538,
6
5796,725864.426,1415247.024,360.76
8,6
5797,725867.65,1415243.525,360.375,
6
5798,725870.227,1415239.979,359.94
2,6
5799,725857.797,1415250.291,361.22
2,6
58,725257.383,1414902.603,363.233,P
I
5800,725854.471,1415253.457,361.63
5,6
5801,725883.274,1415260.4,360.643,6
5802,725885.482,1415256.926,360.27
4,6
5803,725884.059,1415263.763,360.68
7,6
5804,725887.024,1415252.762,359.96,
6
5805,725881.656,1415267.514,360.88
8,6
5806,725902.572,1415273.936,360.65
3,6
5807,725905.583,1415269.743,360.44
9,6
5808,725900.332,1415278.056,360.72
5,6
5809,725908.098,1415265.297,360.02
2,6
5810,725896.704,1415281.311,360.79
32

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

5055,724118.462,1414580.91,400.928,6
5056,724119.671,1414584.204,401.379,6
5057,724121.418,1414585.477,403.008,6
5058,724123.447,1414588.436,405.723,6
5059,724124.778,1414589.731,406.401,6
5060,724114.963,1414576.288,402.617,6
5061,724113.348,1414573.493,402.256,6
5062,724112.358,1414570.958,401.641,6
5063,724136.427,1414563.578,402.579,6
5064,724136.22,1414565.617,403.614,6
5065,724136.27,1414568.028,404.71,6
5066,724135.299,1414561.674,400.726,6
5067,724132.706,1414561.724,398.589,6
5068,724127.012,1414561.472,396.338,6

1,6
5811,725917.289,1415289.496,360.78
9,6
5812,725918.172,1415288.641,360.76
4,6
5813,725920.477,1415286.448,360.60
2,6
5814,725923.227,1415284.502,360.49
5,6
5815,725927.351,1415281.752,360.30
3,6
5816,725929.479,1415279.099,360.27,
6
59,725424.525,1414984.422,361.525,
BM
60,725957.702,1415312.871,360.607,P
I
5817,724612.161,1414273.062,392.48
5,BM3
5818,724600.661,1414191.052,392.40
1,BM4
5819,724993.999,1414719.758,364.42
5,BM5
5820,725132.717,1414835.094,365.00
2,BM6
5821,725608.418,1415080.725,364.91,
BM7
5822,725705.954,1415135.298,363.68
6,BM8

33

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

12.2 ESPECIFICACIONES TCNICAS


12.2.1 ESPECIFICACIONES AMBIENTALES GENERALES
INDICE DE CONTENIDO
00000 ESPECIFICACIONES TECNICAS GENERALES:2
00001 ESPECIFICACIONES AMBIENTALES GENERALES
2
00002 NOTAS GENERALES A LAS ESPECIFICACIONES TECNICAS 3
00003 LIMITACIONES DE TRABAJO : 4
00004 DOCUMENTOS DE CONTRATO :
4
00005 PROTECCION Y REEMPLAZO DE ESTRUCTURAS : 4
00006 PROTECCION DE LA PROPIEDAD PUBLICA Y PRIVADA : 4
00007 FACILIDADES PARA TRANSITO DE VEHICULOS Y PEATONES :
00008 BARRICADAS, AVISOS PREVENTIVOS Y LUCES : 5
00009 MATERIALES EQUIPO Y HERRAMIENTAS A SUMINISTRAR 5
00010 PRIORIDAD DEL TRABAJO : 6
00011 LIMPIEZA PERIODICA: 6
00012 ROTULO :
6
00013 CONDICIONES GENERALES 6
00014 CERTIFICADOS 7
00015 APROBACION DE MATERIALES 8
00016 RECHAZO DE MATERIALES
8
00017 FORMA PARA SOMETER MUESTRAS 8
00018 CAMBIOS EN LAS ESPECIFICACIONES8
00019 MATERIALES NO ESPECIFICADOS POR MARCA O SIMILITUD 8
00020 MATERIALES ESPECIFICADOS POR MARCA O SIMILITUD
9

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

00000 ESPECIFICACIONES TECNICAS GENERALES:


Estas especificaciones tcnicas son generales y se refieren a todos los aspectos de la construccin,
en el caso que algn tipo de actividad no est incluida en estas especificaciones, es deber del
contratista hacer la obra de manera tcnicamente correcta y sin ninguna mala intencin, es decir no
debe valerse del hecho que no est incluida en las especificaciones.
Se recomienda a todos los contratistas, que visiten los proyectos antes de participar en las
licitaciones. El contratista debe incluir todos los costos que sean necesarios, sin omitir ninguna
actividad, para evitar que sus costos presenten errores y sean los ms correctos.
Asimismo se consideraran como especificaciones tcnicas generales, las especificaciones
ambientales generales.
00001 ESPECIFICACIONES AMBIENTALES GENERALES
La reparacin, reemplazo, ampliacin y construccin de cualquier infraestructura financiada por el
FISE, pueden producir efectos adversos sobre el medio ambiente si no se toman en consideracin
las medidas de mitigacin necesarias.
Los impactos ambientales comnmente asociados a los proyectos FISE son la contaminacin del
aire por generacin de polvo, contaminacin de cuerpos de agua por arrastre de sedimentos y mala
disposicin de excretas del personal y produccin de desechos slidos de construccin.
Estos efectos son generalmente de carcter temporal, con un rea de influencia puntual o local, de
intensidad variable, mitigables y prevenibles con la aplicacin de normas y medidas sencillas.
El contratista debe tomar todas las precauciones necesarias para evitar la contaminacin ambiental
durante la ejecucin del contrato.
La violacin de las siguientes normas es causa suficiente para la cancelacin del contrato y el retiro
o descalificacin del contratista de la lista del FISE.
Disposicin de Excretas. Si el sitio de las obras, no dispone de sistema sanitario que pueda ser
utilizado por los trabajadores del contratista, el contratista deber construir una letrina para este fin.
El tipo de letrina a construir depender de la zona donde se ubicar.
Disposicin de materiales y residuos slidos. Se entienden por materiales y residuos slidos, los
residuos de construccin o fabricacin, materiales removidos, los escombros, sobrantes de
materiales, empaques de cemento, plsticos, madera, latas de pintura, varillas de hierro, ladrillos,
bolsines fracturados, solventes de pintura, tejas y lminas de zinc, colochos y serrn.
Para disponer adecuadamente de los materiales y residuos slidos, se seguirn los siguientes
pasos: Se recomienda en separar el papel y la madera, que puedan ser utilizados como combustible,
la tierra sobrante de excavacin que se pueda disponer como relleno, los metales y los plsticos que
se puedan reciclar.
2

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Los materiales y escombros no reciclables deben ser enviados a botaderos municipales, donde
existan. De no existir botadero autorizado, los desechos slidos deben ser enterrados en sitios
aprobados por el ingeniero supervisor o quemados con autorizacin previa del supervisor. Los
residuos de asbesto cemento no se deben fracturar.
El contratista no podr directamente o a travs de terceras personas, disponer estos residuos en
sitios diferentes que los establecidos para ello y autorizados por el supervisor.
Por ningn motivo se permitir botar los residuos en ros o quebradas, calzadas, canales de aguas
pluviales o cauces, cuerpos de agua o cualquier otro sitio donde puedan ser causa de contaminacin
del ambiente o deterioro del paisaje.
Residuos lquidos. Los residuos lquidos como grasas, aceites y pintura con base de aceite, se les
deber dar una disposicin final de acuerdo a las siguientes recomendaciones: las grasas y aceites
se debern almacenaren recipientes apropiados y podrn quemarse utilizndolos como combustible.
Esto produce emisiones de partculas como xidos de azufre e hidrocarburos en forma temporal,
pero es preferible que enterrarlas porque pueden contaminar los acuferos y fuentes de agua
potable. Las pinturas con base de agua se pueden botar sobre los escombros y dejar evaporar el
agua.
Por ningn motivo se permitir verter los residuos lquidos en ros o quebradas, calzadas pblicas,
canales de aguas pluviales, cauces, cuerpos de agua o cualquier otro sitio donde puedan ser causa
de contaminacin del ambiente o deterioro del paisaje.
Residuos de tierra sobrante. Los residuos de tierra sobrante deben utilizarse, cuando sea posible
como relleno, de lo contrario deber disponerse como material slido. Por ningn motivo, se
permitir botar los residuos en ros o quebradas, calzadas pblicas, canales de aguas pluviales o
cauces, cuerpos de agua o cualquier otro sitio donde puedan ser causa de contaminacin del
ambiente o deterioro del paisaje. Apertura de zanjas. Las zanjas que se excaven para la instalacin
de las tuberas de agua potable o servida, tanques spticos y pozos de absorcin, debern dializares
con cinta de color naranja internacional, para evitar accidentes.
El material excavado se deber depositar al lado de la misma y cubrir con plstico durante la poca
lluviosa, para evitar el arrastre de material por la escorrenta. En poca de sequa, se deber
humedecerse el material para minimizar la produccin de polvo. Si el material excavado es inestable,
se deber entibar las zanjas independientemente de la altura. Si el material es estable, se entibara a
partir de 2.50 metros. Aguas residuales y servidas.
Por ningn motivo se permite el estancamiento deliberado de aguas o el vertido de estas
directamente a cuerpos de agua.
Tala de rboles y reemplazo de estos. Si la tala de rboles es requerida para la construccin del
proyecto, el contratista deber contar con el permiso respectivo de MARENA. Para cada rbol
derribado, se extraer el tronco y la raz. Se rellenara el hueco provocado por la eliminacin del
3

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

rbol. De acuerdo a la reglamentacin de MARENA, por cada ao que tenga el rbol derribado, se
debern sembrar tres arboles hasta un mximo de25. Si el contratista, da negligencia en la ejecucin
del proyecto, tala ms rboles diferentes a los contemplados en los planos y diseos del proyecto,
deber asumir la reposicin dichos rboles y cumplir con la normativa establecida por MARENA. Si
las condiciones del terreno, no permiten la siembra del nmero de rboles requeridos el contratista
podr disminuir el nmero de estos con previa autorizacin del supervisor. Productos con plomo
No ser permitido, bajo ningn motivo, la utilizacin de productos que contengan plomo en los
interiores de las infraestructuras verticales (pintura, etc.).
00002 NOTAS GENERALES A LAS ESPECIFICACIONES TECNICAS
1.- Cada contratista antes de presentar su oferta, tiene la obligacin de visitar el sitio y lugar del
proyecto, para considerar todos los factores que influyan tanto en los costos, como en la calidad de
las obras. Una vez abiertas las ofertas deben estar solventadas todo tipo de dificultades.
2.- Toda contratista considerara las especificaciones que competan a cada proyecto especfico, ya
que estas abarcan a la generalidad de los proyectos.
3.- En caso de que existan contradicciones en los planos y especificaciones tcnicas, el Ingeniero
supervisor decidir tal incongruencia, dejando por escrito en el libro de Bitcora del proyecto, la
solucin correcta. El contratista debe solicitar por escrito tal decisin antes de empezar cualquier
actividad, ya que si ocurre en obra defectuosa, que castiguen la calidad y seguridad estructural y se
compruebe mal intencin de su parte, ser responsabilidad suya demoler y construir sin costo
adicional para el dueo.
4.- En vista que se requiere la generacin de empleados; no tratamos de maltratar las utilidades de
los contratistas, por lo que esperamos que estos no maltraten la calidad de las obras, ni los ingresos
de los obreros, por lo que tanto: Especificaciones Tcnicas, Planos y Bitcora tienen el mismo peso,
el punto 3 aclara toda contradiccin.
5.- Todos los materiales sobrantes (producidos como escombros) capaces de ser reutilizados, en
otro tipo de obra, no son propiedad del contratista, los que tienen que disponer de estos, son las
entidades dueas de la obra, o sea las entidades que administren la obra una vez concluida.
Cabe aclarar que este acpite se refiere solo a los materiales que fueron quitados de las estructuras
existentes, no a los materiales nuevos que los contratistas adquieren en el comercio para construir y
reparar las infraestructuras.
El contratista no tomara ventaja con cualquier contradiccin que hubiere en los planos y en las
especificaciones, en este caso el supervisor decidir la manera ms tcnica de resolver el caso a
favor de la buena ejecucin de la obra.
00003 LIMITACIONES DE TRABAJO:
El supervisor har entrega oficial al contratista del sitio donde se efectuara la obra, motivo del
contrato, y lo dejara asentado en el libro de Bitcora y a partir de esa fecha empieza a contarse el
tiempo calendario de ejecucin de la obra.
Segn sea el proyecto proveer el derecho de va o servidumbre necesario para el trabajo
especificado, el contratista no entrara ni ocupara con personal, herramientas o materiales ninguna
propiedad privada fuera del derecho de va sin el consentimiento del propietario. Se entiende que el
derecho de va aqu referido significa solamente permiso de usar o pasar a travs de cierto local o
4

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

espacios de calles, carreteras o a travs de propiedades pblicas o privadas, en las cuales el


contratista va a llevar a efecto el trabajo.
00004 DOCUMENTOS DE CONTRATO:
Forman parte del contrato los siguientes documentos: Planos (que incluyen detalles, estructurales,
arquitectnicos, elctricos e hidra sanitarios, esquemas de obras exteriores, mobiliario, pupitres as
como todo adendum que se refiera al sistema constructivo). Especificaciones Tcnicas: Estas
complementan lo indicado en los planos.
El libro de Bitcora: Se indicara el registro pormenorizado de las actividades que se ejecutan en el
proyecto, indicndose lo relativo a toda actividad que no est clara en los planos y especificaciones.
As como el registro de visitas de la supervisin, cambios o aclaraciones solicitados por el
contratista. Las consideraciones generales. Todas las aclaraciones hechas a las preguntas que
hacen los contratistas, para presentar su oferta en las licitaciones.
00005 PROTECCION Y REEMPLAZO DE ESTRUCTURAS:
Los planos muestran ciertas estructuras subterrneas, tuberas y cables que se supone existen en el
rea de trabajo, la localizacin de las cuales puede variar algo de lo indicado. Particularmente se
informa al Contratista de que pueden existir tubos o estructuras subterrneas y tuberas cruzadas
que no figuran en los planos y que la responsabilidad del contratista es proceder con cautela en la
ejecucin del trabajo a fin de prevenir daos a dichas estructuras o tuberas. El contratista ser
responsable por todos los daos que ocasione a todas las tuberas y cables existentes, pavimentos,
aceras y estructuras sobre o bajo tierra, sea que estn o no indicadas en los planos del contrato;
adems deber por su cuenta asumir los gastos de proteccin de las mismas o repararlas y/o
reemplazarlas si estas son daadas.
00006 PROTECCION DE LA PROPIEDAD PBLICA Y PRIVADA:
El contratista deber tomar todas las precauciones necesarias para prevenir daos a las estructuras
sobre o bajo la tierra y para proteger y preservar la propiedad dentro y adyacente al trabajo. Todo
dao causado a terceros e infraestructuras que sea ocasionado por el contratista cuando efecta los
trabajos corrern por cuenta de l. Para evitar estos daos, debe prevenirlos con seales
adecuadas, en zanjaos con seales luminosas (sean con iluminacin mecnica o mechones) estas
se encendern cuando no haya personal trabajando, y cuando no haya visibilidad por oscuridad
apangndolas cuando se inicien los trabajos o cuando sea de da.
Adems pondrn seales de prevencin con rtulos y letreros que indiquen que hay obreros
trabajando. En el caso de la construccin sean edificios se protegern con cercas provisionales los
frentes de las areas de los predios, para proteccin de los peatones que transiten por el lugar.
Estas cercas deben de construirse antes de empezar los trabajos y dar seguridad tanto a los obreros
como a los peatones.
00007 FACILIDADES PARA TRANSITO DE VEHICULOS Y PEATONES:
Los trabajos se realizaran con la menor interrupcin posible del trfico. Antes de empezar los
trabajos en las calles el contratista deber obtener de la Oficina Nacional del Trnsito y del Ministerio
del Distrito Nacional el permiso correspondiente para trabajar en las calles y mantener el trfico
5

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

abierto a los vehculos. Las alcantarillas ubicadas en calles pavimentadas no sern construidas
hasta que el Contratista haya presentado y recibido aprobacin del Ingeniero supervisor, por escrito,
del programa de trabajo que indicar la fecha de comienzo y terminacin de la construccin de las
alcantarillas. Dicho programa incluir el tiempo estimado para la excavacin, preparacin del lecho,
colocacin del tubo principal y accesorios, conexiones domiciliares, pruebas, relleno, compactacin y
reparacin del pavimento. El Ingeniero supervisor dar su aprobacin o rechazo (si en su opinin el
tiempo asignado es excesivamente largo) del programa de trabajo dentro de un periodo mximo de
tres das despus de haber recibido los documentos del contratista. Toda la basura esparcida por los
camiones del Contratista a su paso sobre los pavimentos existentes o que de cualquier otra manera
ha sido depositada sobre los mismos, deber ser retirada por el Contratista cuando en la opinin del
Ingeniero supervisor la acumulacin es suficiente para causar la formacin de lodo, polvo,
interferencia con el trfico o para convertirse en un peligro para el trfico. El Contratista deber
construir y mantener, sin costo adicional, puentes adecuados y seguros sobre las excavaciones, en
los sitios donde se considere necesario o sea ordenado por el Ingeniero, con el propsito de facilitar
el trfico de peatones o vehculos. Todas las estructuras temporales construidas con este propsito
debern ser removidas al terminar el trabajo, a menos que el Ingeniero lo especifique de otra
manera, y todo dao causado a la propiedad pblica o privada deber ser reparado por el
Contratista.
00008 BARRICADAS, AVISOS PREVENTIVOS Y LUCES:
El contratista deber proveer y mantener avisos preventivos luminosos y seales de desvo
adecuadas en todos los cierres e intersecciones ya lo largo de todos los desvos, dirigiendo el trfico
alrededor de los tramos cerrados de carretera, de manera que las rutas temporales de desvo estn
claramente sealadas a travs de toda su longitud. Todas las barricadas debern estar provistas de
luces espaciadas a distancias no mayores de dos metros no debiendo usarse menos de tres (3)
luces. En los sitios donde cambien las lneas de trfico, las barricadas debern tener luces
adicionales que sealen sus extremos finales. Las obstrucciones tales como materiales
almacenados equipo y excavaciones debern ser sealadas con no menos de dos (2) luces que
debern estar espaciadas a distancias no mayores de 1.5 metros. Las luces debern ser visibles a
no menos de 150 metros en todas las direcciones de trfico y debern estar colocadas no menos de
0.60 metros por encima de la carretera adyacente abierta al trfico. Las luces podrn ser de batera
o combustible, resistentes al viento y la lluvia, aprobadas por el Ingeniero. Todas las luces debern
permanecer encendidas desde media hora antes de la puesta del sol, hasta media hora despus de
la salida del mismo. Los vigilantes debern efectuar el patrullaje que sea requerido y debern
reemplazar las luces que hagan falta. Ninguna va pblica podr ser cerrada sin el consentimiento
por escrito de la autoridad competente.
00009 MATERIALES EQUIPO Y HERRAMIENTAS A SUMINISTRAR
Todos los materiales y equipos requeridos para los trabajos comprendidos por este contrato sern
suministrados por cuenta del contratista. As como los equipos y herramientas que se necesiten
para la completa ejecucin de la obra. Salvo que se indique que material ser suministrado por
terceros, los que sern puestos en la obra cuando el contratista lo requiera, avisando con 15 das de
anticipacin, en caso que el material u otro accesorio atrase la obre se le tiene que dar prorroga de
tiempo al contratista.
6

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

00010 PRIORIDAD DEL TRABAJO:


El Duelo se reserva el derecho de establecer la secuencia o prioridad del trabajo de construccin en
los diferentes captulos contemplados en el presente contrato y el contratista deber dar prioridad a
los requerimientos especficos del Dueo, siempre y cuando no atrase la obra ni en tiempo contra
actual del contratista.
00011 LIMPIEZA PERIODICA:
A medida que el trabajo progresa, el Contratista deber quitar del lugar del trabajo toda clase de
desperdicios y materiales sobrantes con la finalidad de mantener el rea limpia y en condiciones
originales. En dicha limpieza el contratista dar prioridad a los requerimientos que el supervisor
decida. Al hacer la limpieza y haya que botar materiales de desecho estos se tienen que botar en los
botaderos municipales, siempre y cuando no queden en la orilla de caminos y carreteras, en este
caso el lugar lo decidir el supervisor tomando el consentimiento de la alcalda municipal.
00012 ROTULO:
El contratista deber erigir en los lugares de trabajo dos rtulos de acuerdo a planos constructivos.
00013 CONDICIONES GENERALES
A. Modo de manejo. El manejo de los materiales y almacenamiento debe efectuarse en tal
forma que se les prevenga de toda mancha, daos, deterioros y mezcla con materias
extraas. Los materiales que vengan en sus empaques originales, deben ser guardados en
ellos sin abrirlos. Cualquier violacin a este respecto podr causar el rechazo de los
materiales.
B. Coordinacin. Sera responsabilidad de esta divisin la debida coordinacin de los trabajos
de mampostera con el de las otras artes tal como se expresa en las divisiones de Plomera,
Electricidad, Aire Acondicionado, Ventanales, Puertas, Cielos, etc.
C. Toda mencin hecha en estas especificaciones o indicada en los planos obliga al contratista
a suplir e instalar cada artculo, material o equipo con el proceso o mtodo indicado y de la
calidad requerida o sujeta a calificacin y suplir toda la mano de obra, equipo y
complementarios necesarios para la terminacin de la obra.
D. Los documentos del contrato, que incluyen planos y Especificaciones, son complementarios
los unos con los otros, de modo que lo dicho en uno se entender como dicho en todos.
Si se detectan contradicciones en los documentos se tendr presente que las
especificaciones no son excluyentes con los planos sin que prevalezca uno sobre el otro,
debe prevalecer la manera tcnica de concluir la obra, en estos casos el supervisor indicara
en la bitcora, como debe de construirse la obra, los dibujos a escala mayor prevalecen
sobre los dibujos a escala menor y las dimensiones en cifras sobre las dimensiones a
escala. Si la contradiccin fuere de orden mayor, deber ser consultado al diseador por
medio del supervisor para la debida aclaracin. Para lo que el FISE se encargara de
solucionar este caso en un plazo no mayor de 10 das.
E. Trabajo Requerido: El trabajo consiste en la preparacin del sitio, excavacin, relleno,
terrapln, nivelacin, como esta descrito en las especificaciones o indicado en los planos o
razonablemente implicado en ellos.
F. Se removern tambin del sitio de la obra todas las piedras y a cualquier obstculo que
7

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

G.
H.
I.

J.

K.

pueda resultar para los trabajos de construccin. El contratista tomara todas las
precauciones necesarias para no causar dao a terceros en la remocin de escombros u
otros materiales de esta naturaleza del terreno.
rboles y arbustos localizados en el
rea de construccin debern ser derribados, se extraern troncos y races y sern
rellenados los huecos. Escarbar o raspar a fin de quitar la maleza, races, grama suelta,
capa vegetal en general.
Elevaciones Los planos indican las elevaciones del terreno existente y elevaciones finales
requeridas. Cualquier excavacin, relleno o nivelacin adicional requeridos para la completa
terminacin del trabajo ser efectuado por el contratista sin ningn recargo extra.
Banco de Nivel: El contratista levantara todos los bancos de nivel, puntos de coordinacin y
estacas, las cuales deben ser preservados y mantenidas por cuenta del contratista; hasta
que el supervisor crea conveniente mantenerlos.
Responsabilidad por el terreno: El contratista tiene la obligacin de examinar los planos,
estudios geolgicos y de suelos, efectuados en el sitio de la obra y asumir completa
responsabilidad en el uso y disponibilidad del suelo desde el punto de vista constructivo. J.
Trazado de la obra: El contratista comprobara las medidas indicadas en los planos,
localizando la construccin con precisin en el sitio, de acuerdo con los documentos del
Contrato. Niveletas y estacas de nivelacin permanecern en su posicin hasta que todas
las esquinas y alturas de la edificacin hayan sido establecidas permanentemente.
EL CONTRATISTA ser responsable de proteger de daos todas las lneas, niveles y puntos
de referencia y si se destruyen debern ser reparados y repuestos por su cuenta. Se
notificara a el supervisor, cuando el trazo este sustancialmente terminado y se proceder a
la construccin hasta que haya sido aprobado.
Nivelacin: Toda la edificacin se proyecta a un solo nivel interior. Por tanto, una vez
ubicado el proyecto, se asumir el nivel promedio entre lados opuestos del rea de
construccin y se proceder a recortar el terreno alto y rellenar el terreno bajo en capas de
20 cms, compactadas hasta superar o igualar el grado 90% proctor. La nivelacin se
extender alrededor de la construccin un ancho mnimo de 1 mt. La diferencia entre el nivel
de piso interior y el nivel del terreno circundante no podr ser mayor de 10 cms. Los taludes
formaran con los horizontales ngulos no mayores de 45 grados. El contratista no tomara
ventaja de cualquier contradiccin que exista en los planos y las especificaciones, en este
caso el supervisor dar por escrito en el libro de bitcora la solucin ms tcnica y adecuada
para la ejecucin de la obra.

00014 CERTIFICADOS
Envo de las muestras. El CONTRATISTA someter al supervisor en triplicado un certificado
describiendo cada muestra sometida para su aprobacin, certificando que el material, equipo o
accesorio llena los requisitos del Contrato. El Certificado deber incluir la siguiente informacion: 1.Nombre y marca del producto y del manufacturero.2.Descripcin de propiedades qumicas y
fsicas del material y nombre del laboratorio o autoridad donde se obtuvo el dato.3.- Fecha de la
prueba. Si la declaracin es original del manufacturero, El CONTRATISTA endosara a su nombre
todo reclamo y someter la declaracin bajo su propio nombre.
00015 APROBACION DE MATERIALES
Todo material, equipo, mtodos y accesorios que fueren parte del trabajo quedaran sujetos a la
8

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

aprobacin o desaprobacin del INSPECTOR. El INSPECTOR tiene la opcin de requerir pruebas


de Laboratorio demuestras sometidas para su aprobacin o a su discrecin, aprobar materiales
basndose en el dato y muestras sometidas. La aprobacin de cualquier material o producto no
constituir renuncia del derecho del INSPECTOR para demandar el completo incumplimiento de los
requisitos del Contrato. La aprobacin de una muestra se entiende que es solamente su
caracterstica y no deber interpretarse como cambio o modificacin a los requisitos del Contrato. No
se enviara material alguno al trabajo hasta que las muestras representativas del hayan sido
aprobadas por escrito por el INSPECTOR.
00016 RECHAZO DE MATERIALES
Falla en las muestras ser suficiente causa para que se rehse considerar cualquier otra muestra del
mismo manufacturero cuyos materiales hayan fallado. En caso que los materiales, equipos o
accesorios que han sido rechazados por el INSPECTOR se incorporen en la obra, el INSPECTOR
tendr derecho de ordenar que se remuevan y se repongan por otros aprobados o demandar al
CONTRATISTA todas las reparaciones que crea conveniente. Los materiales que no cumplan con
las especificaciones en cuanto a la resistencia, esfuerzos y otros como dimensiones y calidad, ser
desechados de la obra en caso que hayan sido integrados a la obra, esta ser demolida asumiendo
los nuevos costos el contratista.
00017 FORMA PARA SOMETER MUESTRAS
Si no se indicara en otra forma EL CONTRATISTA someter al INSPECTOR dos muestras de cada
material, con un Certificado relacionado a ellas. EL CONTRATISTA pagara todo gasto de transporte.
Las muestras debern presentarse debidamente marcadas, indicando claramente el nombre de
productos, lugar de origen, nombre del manufacturero, nombre del CONTRATISTA y nombre del
Proyecto. El material cuyas muestras sean as presentadas, si son satisfactorias, podr ser
incorporado en el trabajo del CONTRATISTA.
00018 CAMBIOS EN LAS ESPECIFICACIONES
Todo lo aqu indicado en las especificaciones tcnicas, y los contratistas cambien o por cualquier
error involuntario, o mal intencin de estos, sern objetos de paralizar las obras por el Ingeniero
supervisor, corregir las obras siguiendo las especificaciones, sin costo alguno para el dueo, as
como obra adicional que el error del contratista cauce. Todo el costo que incurra correr por cuenta
del contratista.
00019 MATERIALES NO ESPECIFICADOS POR MARCA O SIMILITUD
Debern ser de primera calidad y debern ser acompaadas por certificados de laboratorios,
recomendaciones escritas de otras empresas o entidades que las hayan usado, y sern
acompaadas por garantas escritas en cuanto a su calidad, duracin y responsabilidad econmica
para respaldar daos ulteriores causados por defectos en el material.
00020 MATERIALES ESPECIFICADOS POR MARCA O SIMILITUD
Se especificara por marca o similitud aprobado, se requiere que la similitud sede mediante
certificados, folletos y garantas que demuestren igualdad en cuanto a durabilidad y acabado de
materiales, dimensiones, rendimientos mecnicos, eficiencia y actuacin, operaciones y controles.
9

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

12.2.2 ESPECIFICACIONES TCNICAS GENERALES


12.2.2.1DEFINICIONES
En cualquier parte de estos documentos que se usen los trminos que se describen a continuacin,
su intencin y significacin debern ser interpretadas de la manera siguiente:
Propietario:

Alcalda Municipal de Bocana de Paiwas

Ingeniero:

El ingeniero supervisor designado por la Alcalda, para la supervisin tcnica de la


obra, actuando dentro del marco de las atribuciones que le sern confiadas.

Contratista:

El Oferente a quien este contrato es adjudicado por la Alcalda.

Sub-Contratista:
Cualquier empresa constructora, persona natural o jurdica seleccionada por el
Contratista y aprobado por la Alcalda para efectuar una obra en particular o suplir
bienes demandados por el trabajo.
Fiador:

La compaa debida y legalmente autorizada para operar en Nicaragua, la cual


adquiere obligacin con y por el Contratista por el pago de todas las obligaciones
para el desarrollo aceptable del trabajo requerido por este Contrato.

Laboratorio:

Cualquier laboratorio aprobado por el Supervisor para efectuar pruebas en los


materiales que sern incorporados a la obra.

Planos:

Los dibujos, planos, perfiles, cortes, esquemas suplementarios o reproducciones


exactas de ellos, suplidos por la Alcalda y/o aprobados por el Supervisor, que
muestren la ubicacin, carcter, dimensiones y detalles del trabajo que se ha de
hacer.
Especificaciones:
Las direcciones, disposiciones y estipulaciones comprendidas en los Documentos de
Contrato que establecen los mtodos constructivos, calidad de insumos, bienes y
servicios que sern suministrados por el Contratista.
Orden de Cambio:
Un convenio escrito entre la Alcalda y el Contratista, aprobado por el Supervisor, el
cual una vez debidamente ejecutado pasa a formar parte del Contrato. Ordenes de
cambio pueden comprender un aumento o disminucin de obras, cambios en la
ubicacin de los elementos del sistema y/o en los pagos que se harn bajo el
Contrato.
Aprobado, Dirigido, Requerido:

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

En cualquier parte de las especificaciones o planos donde se usen las palabras


"Aprobado", "Dirigido", u otras palabras que tengan el mismo significado, deber ser
entendido que se necesita la aprobacin, direccin o requerimiento del Supervisor.
12.2.2.2PRELIMINARES
Una vez pasada la entrega del sitio del proyecto por el ingeniero encargado del seguimiento, al
contratista, este ser el encargado de la limpieza inicial, trazo y nivelacin, construcciones
temporales (si las requiere), demoliciones (si las requiere), fabricacin de obras de madera (para
la ejecucin de la obra), instalacin de servicios temporales (si se requirieran) y otros trabajos
preliminares.
Esta etapa de la construccin es la que da inicio al proyecto, una vez recibido el sitio, dando
adems apertura al libro de bitcora. El contratista, antes de iniciar la obra, deber examinar
cuidadosamente todos los trabajos adyacentes, de los cuales depende esta obra, de acuerdo a
las intenciones de estas especificaciones informando por escrito al inspector de la obra cualquier
condicin que evite al contratista realizar un trabajo de primera calidad.
No se eximir al contratista de ninguna responsabilidad por trabajos adyacentes incompletos o
defectuosos, a menos que tales hayan sido notificados al supervisor por escrito y este los haya
aceptado antes de que el contratista inicie cualquier parte de la obra.
LIMPIEZA INICIAL
El contratista debe ubicar el sitio del proyecto, los planos sealan los lmites de la obra y
especifican los rboles, arbustos plantas y objeto que deben conservarse.
En caso contrario debern ser indicados por el supervisor y por escrito en el libro de bitcora.
Todos los objetos de la superficie y todos los rboles, troncos, races y fundaciones viejas de
concreto, y cualquier obstruccin saliente, debern ser quitados.
Todos los escombros no flamables como trozos de bloque, tejas, cubiertas de techo sern
botados en el botadero municipal o donde el supervisor lo indique, no as trozos de materiales de
asbesto cemento el que ser enterrado a una profundidad de 1.20 metros previamente
quebrando en trozos no mayores de 25 centmetros de dimetro; en caso que el nivel de aguas
sub-superficiales sea menor a 1.20 metros de profundidad, el contratista los enterrara en un sitio
donde el manto fretico sea ms profundo de 1.20 metros.
TRAZADO Y NIVELACION:
Las lneas bases, puntos topogrficos de referencia, y los elementos de control necesarios para
determinar la indicacin y elevacin del trabajo en el terreno, estn mostrados en los planos o
sern suministrados por el Ingeniero.
El contratista trazara su trabajo partiendo de las lneas bases y bancos de nivel o puntos
2

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

topogrficos de referencia establecidos en el terreno y de las elevaciones indicadas en los


planos, siendo responsable por todas las medidas que as tome.
El Contratista ser responsable por la ejecucin del trabajo en conformidad con las lneas y cotas
de elevacin indicadas en los planos o establecidas por el Ingeniero.
El Contratista tendr la responsabilidad de mantener y preservar todas las estacas y otras
marcas hasta cuando el Ingeniero supervisor lo autorice para removerlas.
En caso de negligencia del Contratista o de sus empleados que resultare en la destruccin de
dichas estacas, antes de su remocin autorizada, el contratista las reemplazara si as lo exigiere
el Ingeniero supervisor.
Los bancos de nivel y las niveletas debern ser cuidadosamente conservados por el contratista
hasta la aceptacin final del trabajo, y si son destruidos o aterrados, su relocalizacin o
construccin ser hecha por cuenta del contratista.
Cualquier trazado errneo ser corregido por el contratista por su cuenta, en caso que haya
obras construidas, errneamente ser perdida para el contratista.
Para evitar errores en el trazado de las obras el contratista colocara las suficientes niveletas
sencillas as como dobles en los lugares donde se formen vrtices en la construccin, indicando
los niveles tomando como referencia los puntos indicados en el plano o indicados por el
ingeniero supervisor.
En caso que el contratista, encontrare errores en el nivel del punto de referencia, lo indicara por
escrito en el libro de bitcora, antes de comenzar cualquier obra; el supervisor contestara de la
misma manera indicando el nivel correcto; en caso que el contratista haya incurrido en avances
de obras con niveles incorrecto de las terrazas correr por cuenta de la correccin de la obra.
Para el trazado de las obras el contratista usara niveletas de madera o metlicas, de cuartones
de 2"x2" y 0.50 metros de alto con reglas de1"x3" debidamente acepillada el canto superior
donde se referir el nivel. Las niveletas sencillas llevaran dos cuartones de apoyo de la regla del
nivel espaciados a 1.10 metros, para niveletas dobles sern tres cuartones espaciados a 1.10
metros pero formando ngulo recto, la madera podr ser de pino o madera blanca.
El contratista ser responsable de proteger de daos todas las lneas, niveles y puntos de
referencia y si se destruyen debern ser reparados y repuestos por su cuenta, notificando al
supervisor, cuando el trazo este sustancialmente terminado se solicitara si puede eliminarlos.
El contratista para hacer el trazo y nivelacin, antes tiene que verlas condiciones del terreno.
Es igualmente obligacin del contratista notificar al dueo por medio del supervisor, sobre las
condiciones inesperadas o sospechosas que se detecten en el terreno durante el proceso de la
construccin.
3

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

12.2.2.3SUMINISTRO E INSTALACION DE TUBERIAS DE PVC Y ACCESORIOS


Esta seccin comprende el suministro de todo el material, herramientas, equipo y mano de obra
necesarios para instalar tuberas de PVC, con vlvulas y accesorios, de acuerdo con lo aqu
especificado e indicado en los planos correspondientes.
Las actividades constructivas incluyen: excavacin, relleno y compactacin, encofrado y arriostramiento
de zanjas, remocin de agua, instalacin de tubera y accesorios.
MATERIALES
El Contratista suministrar todos los otros materiales tales como tuberas y accesorios de PVC, vlvulas
y dems materiales necesarios para efectuar los trabajos estipulados en este Contrato.
CALIDAD DE TUBOS Y ACCESORIOS.
Todos los tubos y accesorios cloruro de polivinilo (P.V.C.) y de hierro Galvanizado y debern ajustarse a
las especificaciones siguientes:
MATERIALES
TUBERIA Y ACCESORIOS
Tuberas de P.V.C.
(Cloruro de Polivinilo)
SDR - 26 para las tuberas de agua potable
Accesorios de PVC
Hierro Galvanizado

ESPECIFICACION
A.W.W.A.
A.S.T.M.
D2241-73
Schedule 40 - ASTM 2466
ASTM A72 45 A90 35

Los requerimientos fsicos y dimensiones de todos los tubos debern ajustarse a lo especificado por las
entidades antes sealados.
Las juntas entre tubos de dimetros iguales y mayores de 2 sern del tipo espiga y campana y se
unirn con junta rpida provista de empaque de hule. Para uniones especiales o dimetros menores de
2 se usar cemento solvente, consistente en una solucin de PVC clase 1254-B, el cual deber cumplir
con la norma ASTM-D-2564-72.
Los accesorios de PVC sern cdula 40 y debern cumplir con las normas ASTM-D-2466-69. La unin
entre los accesorios y las tuberas debern hacerse con el mismo cemento que se utilizar para unir los
tubos.
Tuberas HG
Las tuberas de HG sern del tipo estndar (cdula 40) y debern ajustarse a las especificaciones
siguientes:
Que se ajuste en todos los aspectos con la especificacin ASTM-120-65 y que cumpla con el
proceso de Galvanizacin de acuerdo a la especificacin ASTM A-90-39.
4

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

La tubera de HG. deber ser suministrada en longitudes de 20 pies con rosca Standard en
cada extremo.

Un acoplamiento deber ser suministrado con cada longitud Standard. El acoplamiento consistir en
una camisa de Hierro Galvanizado con Rosca Standard para roscarse en el extremo del tubo.
Los accesorios de hierro galvanizado debern ajustarse a las especificaciones ASTM, tendrn rosca
hembra del tipo Iron Pipe (I.P) y debern ser diseados para acoplarse a la tubera de HF a ser
suministrada.
Vlvulas
Las vlvulas de pase de 2" y menores sern fabricadas de hierro fundido con asientos paralelos de
bronce y doble disco, vstago de bronce no levadizo con cierre en el sentido de las manecillas del reloj,
provistas de tuerca de operacin de 2"x 2", conforme normas AWWA C-500-71, para una presin de
trabajo de 150 psi.
Las partes ferrosas de las vlvulas, excepto las superficies pulidas, debern recibir dos capas de
pintura asfltica aprobada por el Ingeniero.
Las vlvulas con dimetros iguales o mayores de 3" debern estar provistas de bridas en los extremos,
segn normas ANSI-B-16.1-60, debindose acompaar con sus respectivos compaeros de brida de
hierro fundido y rosca hembra, que se unirn mediante adaptadores a las tuberas de PVC.
Las vlvulas de 2" de dimetro o menores sern similares a las fabricadas por Mueller, modelo H 10201
y tendrn extremos de rosca hembra, que se unirn mediante adaptadores a las tuberas de PVC. Las
vlvulas de limpieza sern de bronce y de 2 de dimetro.
CAJAS PROTECTORES DE VLVULAS
Las vlvulas ubicadas en la lnea de conduccin y red de distribucin sern protegidas mediante una
pequea estructura consistente en un tubo de concreto simple tipo PROCON de 6 de dimetro de
altura variable (entre 1.0 a 1.5 m) que cubrir la vlvula.
En la parte superior el tubo estar cubierto por un bloque de concreto simple de 3,000 psi y
dimensiones de 0.6 m x 0.6 x 0.1 m, con tapa de forma tronco cnica para 6.
ACTIVIDADES CONSTRUCTIVAS
Excavacin
Las excavaciones de zanja se efectuarn de acuerdo con la alineacin, niveles y dimensiones indicados
en los planos. El fondo de la zanja ser conformado a mano, de tal manera que se obtenga un apoyo
uniforme y continuo para la superficie inferior del tubo sobre un suelo firme y uniformemente planos
entre las depresiones excavadas para acomodar las campanas o juntas.
5

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

El ancho de zanjas no ser mayor que el dimetro nominal de la tubera ms 0.45 metros, ni menor de
0.60 metros. Se requiere una cubierta de 1.20 metros sobre el tubo, salvo que sea necesario evitar
obstculos en cuyo caso se excavar a la profundidad indicada en los planos u ordenada por el
Ingeniero.
Cuando en el fondo de la zanja se encuentren materiales inestables, basura o materiales orgnicos que
en opinin del Ingeniero deban ser removidos, se excavar y se removern dichos materiales hasta la
profundidad que ordene el Ingeniero.
Cuando sean removidos los materiales inaceptables como apoyo de la tubera y antes de colocar la
tubera se rellenar la zanja hasta la sub-rasante con material granular que ser apisonado en capas
que no excedan 15 centmetros hasta un nivel que corresponda a 1/4 del rea del tubo.
Instalacin de Tubera y Accesorios
Los tubos se colocarn de conformidad con la alineacin y cortes aqu estipulados e indicados en los
planos o designados por el Ingeniero, quien podr ordenar cambios en alineacin y nivel de la tubera,
cuando lo considere necesario.
La instalacin de la tubera se efectuar con herramientas y equipos apropiados para este fin.
La instalacin de tuberas y accesorios de PVC ser de acuerdo con especificaciones recomendadas
por el fabricante.
Salvo que se indique lo contrario en los planos, el tendido de tubera en curvas se har flexionando la
tubera en las juntas. La deflexin mxima de cada junta no deber exceder la recomendada por el
fabricante.
Instalacin de Vlvulas
Las vlvulas se instalarn en las tuberas y en los sitios indicados en los planos.
Las vlvulas debern instalarse sobre bases de concreto con varillas de anclaje de acuerdo con los
detalles indicados en los planos. Toda vlvula deber instalarse de tal manera que la tuerca para operar
la vlvula quede en una posicin vertical. Las cajas de vlvulas se instalarn al ras con la superficie del
terreno.
Encofrado y Arriostramiento
Cuando se consideren necesarias las zanjas y otras excavaciones, debern ser encofradas y
arriostradas a fin de prevenir cualquier movimiento de tierra, evitar a los tubos cualquier dao y proteger
a los trabajadores en la zanja. El Contratista asume responsabilidad por todo encofrado efectuado
defectuosamente y que pueda causar dao a terceros.
6

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Remocin de Agua
El Contratista utilizar bombas y todo otro equipo necesario para remover el agua de las zanjas y otras
excavaciones. Se requiere que toda zanja se mantenga seca y no se permitir que algn tubo o
estructura sea colocado en una zanja con agua. El Contratista deber disponer el agua de tal forma que
no ocasione dao a la propiedad o inconveniencia al pblico.
Relleno y Compactacin
Salvo que el Ingeniero indique lo contrario, las zanjas no se rellenarn hasta que la tubera sea
sometida a una prueba hidrosttica. Solamente materiales seleccionados provenientes de las
excavaciones deben usarse para relleno a los costados y hasta 30 centmetros sobre la parte superior
de la tubera.
El relleno ser colocado y apisonado en capas que no excedan 10 centmetros. Si los materiales de la
excavacin no se consideran apropiados para relleno, en opinin del Ingeniero, el Contratista obtendr
por su cuenta en otro sitio, los materiales requeridos.
No se permitirn piedras en el relleno alrededor del tubo y piedras de ms de O.10 centmetros sern
excluidas de todo relleno, lo mismo que madera, basura y materia orgnica.
Colocacin y disposicin de Materiales Excavados
Materiales extrados de la zanja sern colocados y dispuestos de tal manera que no obstruyan
indebidamente el trfico de vehculos y peatones en las calles, aceras y entradas a casas.
El Contratista podr levantar el relleno sobre zanja hasta una altura de O.2O cms. sobre el nivel del
terreno natural con el material de relleno sobrante. Si sobrara an despus de ste algn material o
ste a juicio del Ingeniero no fuera adecuado para este fin, estos materiales debern ser removidos del
sitio de la obra por el Contratista a un lugar adecuado sealado o aprobado por el Ingeniero.
Prueba de tubera
Despus de instalar el tubo antes de rellenar la zanja, el Contratista someter a prueba secciones de
tubera que no exceda 300 metros salvo que el Ingeniero permita probar secciones ms largas.
Salvo casos especiales aprobado por el Ingeniero, la tubera debe probarse a una presin hidrosttica
de no menos de 160 libras por pulgada cuadrada y se mantendr esta presin durante no menos de
una hora. El Contratista instalar los bloques de empuje temporales; tapones y todo aparato necesario
para el ensayo.
Se requiere que todo aire sea expulsado del tubo antes de elevar la presin de prueba a lo aqu
estipulado y con este fin se instalarn llaves maestras donde el Ingeniero lo considere necesario, por
cuenta del Contratista.
7

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Los tubos y accesorios sern revisados cuidadosamente durante el ensayo a presin y todos esos que
se encuentren rajados o daados sern removidos y reemplazados por cuenta del Contratista.
Toda junta ser revisada durante la prueba y donde se manifieste exfiltracin o derrame el Contratista
reparar las juntas hasta que stas queden impermeables. La prdida de agua de los tubos no debe
exceder los siguientes lmites por cada 100 juntas:
Mxima Fuga Permitida en
Dimetro de Tubera Galones /Hora/100 Juntas
----------------------------------------------------------2" y menos
0.8
3"
1.2
4"
1.6
6"
2.3
----------------------------------------------------Desinfeccin
Despus del ensayo la tubera ser baldeada. La desinfeccin se efectuar llenando la tubera con
agua e introduciendo una solucin de cloro en suficiente cantidad para obtener en el agua un mnimo de
10 ppm de cloro residual despus de 24 horas.
El Contratista deber suministrar todo aparato, equipo y cloro necesario para efectuar la desinfeccin
de la tubera, adems de los tubos y equipos que sean necesarios para remover el agua durante el
baldeo de la tubera.
Bloques de Reaccin
Bloques de reaccin de concreto deben colocarse en los sitios designados por el Ingeniero incluyendo
tees, codos, reductores, tapones, etc. Todo bloque de reaccin se colocar contra tierra firme y las
dimensiones de estos debern estar de acuerdo con lo indicado en los planos.
Restauracin de la Superficie
El Contratista deber restaurar a su condicin original, toda superficie removida o perturbada por l
durante la ejecucin de la obra.
12.2.2.4INSTALACION DE CONEXIONES DE PATIO
Comprende el suministro de todos los materiales, herramientas, equipo, transporte y mano de obra
necesaria para instalar las conexiones de patio, segn esquema mostrado en los planos. El Contratista
deber realizar por su propia cuentas las excavacin y relleno, compactacin, remocin de agua,
instalacin de la conexin de patio, restauracin de la superficie a su estado original y todo lo necesario
para dejar un trabajo completamente terminado a satisfaccin del dueo.
8

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

MATERIALES
La tubera a utilizarse en las conexiones ser de cloruro de polivinilo (PVC) el cual deber ajustarse a
las normas ASTM D-2241-73, Cedula SDR-13.5 para una presin de trabajo de 315 psi. El tipo de unin
para la tubera de 1/2" ser con extremo acampanado para hacer uniones cementadas.
Los accesorios de PVC de la conexin sern Cdula 40.
Las abrazaderas para la unin de la conexin con la tubera matriz principal sern de PVC y tendrn
pernos de acero de 1/2" y tuercas hexagonales.
El dimetro interno de las abrazaderas deber ser adaptable al dimetro externo de la tubera matriz, no
debiendo existir protuberancias en la superficie interior del cuerpo de la abrazadera que pueda
obstaculizar el apoyo uniforme de la misma sobre el tubo de alimentacin de la conexin.

ACTIVIDADES CONSTRUCTIVAS
Excavacin
El trazado de las conexiones ser a 90 respecto a la tubera de alimentacin de la conexin. Las
excavaciones se realizarn con este alineamiento, variando la profundidad de 1.20 metros en el punto
de conexin de la tubera principal y 1.0 metros en el final de la misma. Los costados de la zanja
debern ser verticales y el fondo conformado a mano de tal manera que se obtenga un apoyo uniforme,
continuo en toda su longitud, El ancho de la zanja no deber exceder de 0.60 metros.
Cuando en el fondo de la zanja se encuentren materiales inestables, basura o materiales orgnicos,
debern ser removidos y reemplazados por material granular.
El Contratista remover toda agua que se colecte en las zanjas mientras se estn haciendo las
conexiones. No se permitir la entrada de agua a las tuberas.
El agua encontrada ser eliminada de una manera satisfactoria para el Ingeniero.
Instalacin de tuberas
La perforacin de tubera de servicios de agua potable se har en un costado del tubo en un ngulo de
45 grados respecto al eje horizontal.
Antes de colocar la abrazadera, el tubo debe limpiarse con un cepillo hasta dejar la superficie uniforme
y lisa donde se ajuste completamente la abrazadera. Las tuercas de la abrazadera deben apretarse
uniformemente y lo suficiente para proveer una conexin hermtica, pero que no llegue a ocasionar
ruptura de la tubera.
9

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Despus de efectuada la perforacin, al agujero debe introducirse un punzn para remover las virutas
de material que pueda haber quedado.
El tapn hembra de la conexin de puesto pblico deber quedar a 0.40 metros de la lnea de derecho
de va. Antes de colocar el tapn, la tubera debe drenarse durante unos minutos, para lavarlas y
eliminar cualquier suciedad que pueda encontrarse dentro.
Relleno y compactacin.
Se cumplir con lo dispuesto en lo concerniente a relleno y compactacin de tuberas.
12.2.2.5PORTONES Y CERCADO GENERAL
ALCANCES
Se construirn conforme a lo indicado en los planos de predios de pozos.
El trabajo a ejecutarse bajo este rubro comprende el suministro de equipo, herramientas, mano de obra,
transporte y materiales necesarios para llevar a cabo la construccin e instalacin de cercas
perimetrales y portones, en los sitios y dimensiones indicadas en los planos y de acuerdo con lo
estipulado en estas especificaciones.
MATERIALES
En los predios de pozos y tanque los cercos sern de alambre de pas de 66lbs, en rollos de 12.5 x
300vrs, Se deber utilizar # 13 galvanizado.
En todos los predios los postes sern de Concreto pretensado de 2.50m de alto, irn enterrado 0.8m
en bloques de concreto simple de 210 kg/cm 2y sobresaldr 1.7m, el cerco se compondr de 7 hileras
de alambres de pas distanciadas a cada 0.30m, los postes estarn ubicados a cada 2.50m uno del
otro.
INSTALACION
La cerca quedar conformada segn el alineamiento y dimensiones mostradas en los planos.
Las columnas debern quedar perfectamente verticales y el alambre bien tenso.
Todas las columnas irn separadas a 2.50m y enterradas por lo menos 0.8m
El portn de acceso ser de 2 metros, y su construccin se har de acuerdo con lo indicado en los
planos.
12.2.2.6 TANQUE DE ALMACENAMIENTO
A continuacin se listan los principales requerimientos a cumplir para la realizacin de estas obras.
10

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Consiste en suministro de los materiales, mano de obra, equipo, herramientas y dems complementos
para suplir el concreto reforzado para esta obra de acuerdo a las Especificaciones subsiguientes y con los
detalles que aparecen en los planos.
Excepto cuando se especifique de otra forma, el concreto tendr una resistencia a la compresin a los 28
das de 3,000 libras de compresin por pulgada cuadrada.
Para todo concreto, la proporcin de cemento, rido y agua necesarios para obtener la plasticidad y
resistencia requerida, estar de acuerdo con las Normas 6I3-54 del ACI. No se permitir cambios en las
proporciones sin la aprobacin del Ingeniero.
El Cemento a emplearse en las mezclas de concreto ser Cemento Portland Tipo 1, sujeto a las
Especificaciones ASTM C-150.
El Agregado Fino ser Arena natural o manufacturada, dura, limpia y libre de todo material vegetal, mica
detrito de conchas marinas, sujeta a las Especificaciones ATM-C-33-59.
El Agregado Grueso ser Piedra triturada grava limpia, dura, durable y libre de todo recubrimiento, sujeta
a Especificaciones ASTM-C-33-6IT.
El tamao ms grande permitido del agregado ser un quinto (1/5) de la dimensin mnima de la formaleta
de los elementos de concreto, tres cuarto (3/4) del espaciamiento libre mnimo entre varillas de refuerzo
segn lo recomendado por la Norma 6I3-54 del ACI.
El agua que a emplear en la mezcla del concreto deber ser limpia, libre de aceite, cido cantidades
perjudiciales de material vegetal, lcalis y otras impurezas.
El acero de refuerzo deber cumplir la especificacin ASTM A-305 con un lmite de fluencia de 40,000 lbs
por pulgada cuadrada, de acuerdo a las especificaciones ASTM A-615-68, Grado 40. Todas las varillas
debern estar limpias y libres de escamas, trazas de oxidacin avanzada, grasas y otras impurezas e
imperfecciones que afecten sus propiedades fsicas, resistencia o su adherencia al concreto.
El cemento se almacenar en bodegas secas sobre tarimas de madera en estibas de no ms de 10 sacos.
El cemento debe llegar al sitio de la construccin en sus envases originales y enteros. No se utilizar
cemento daado ya endurecido.
Los ridos finos y gruesos se manejarn y almacenarn separadamente de manera tal que se evite la
mezcla con materias extraas. Todas las varillas de acero de refuerzo se debern proteger hasta el
momento de usarse.
La limpieza, doblado, colocacin y empalme del acero de refuerzo se harn de acuerdo con las normas y
recomendaciones 318-71 y 315-65 del ACI, y las especificaciones del CRSI.
El acero de refuerzo se limpiar de toda suciedad y xido no adherente. Las barras se doblarn en fro,
ajustndolas a los planos y especificaciones del Proyecto, sin errores mayores de un centmetro.
11

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Los dobleces de las armaduras, salvo indicacin especial en los planos, se harn con radios superiores a
siete y medio (7.50) veces su dimetro.
Las barras se sujetarn a la fortaleza con alambre tacos de concreto piedra, y entre s con ataduras de
alambre de hierro dulce N 16, de modo que no puedan desplazarse durante la llena y que ste pueda
envolverlos completamente.
El Ingeniero podr autorizar la mezcla a mano en las partes de la obra de escasa importancia debiendo
hacerse entonces sobre una superficie impermeable mezclndose los materiales en seco hasta que
presente un aspecto uniforme, agregando a continuacin el agua en pequeas cantidades hasta obtener
un producto homogneo y cuidando que durante la operacin no se mezcle con tierra ni impureza alguna.
La colocacin vertida de todo el concreto se har de acuerdo con las Normas 3I8-7I, 605-59 y 6I4-59 del
ACI y en la forma que aqu se modifica. El transporte y vertida del concreto se har de modo que no se
disgreguen sus elementos, volviendo a mezclar al menos con una vuelta de pala, las que acusen seales
de segregacin.
No se permitir la colocacin de mezclas que acusen un principio de fraguado, prohibindose la adicin de
agua lechada durante la llena. Todo el concreto se colocar sobre superficies hmedas, libres de agua y
nunca sobre lodo suave tierra seca o porosa.
El concreto debe ser colocado con la ayuda de equipo de vibracin mecnica. La vibracin deber ser
aplicada directamente al concreto a menos que el Ingeniero lo apruebe de otra manera. La intensidad de
la vibracin ser lo suficiente como para causar el flujo y asentamiento del concreto en su lugar.
El Contratista prestar cuidadosamente atencin al curado apropiado de todo el concreto. Una vez
desencofrado cualquier miembro estructuras, se mantendr hmedo todo el da por un perodo de 7 das.
En caso de la fundacin masiva para el tanque, se esparcir una capa de arena en toda la superficie, la
cual se mantendr hmeda todo el da y teniendo el cuidado de humedecerla por las noches durante los
siete das del curado.
Se har una prueba de impermeabilidad al tanque la cual consiste en llenar el tanque hasta la altura del
rebosadero durante un periodo de 48 horas, reponiendo continuamente el agua que sea consumida por la
saturacin de los materiales que forman las partes del tanque. A continuacin se dejar lleno el tanque por
72 horas ms, no debiendo rebajar el nivel del agua ms de 9 cms. Cualquier fuga deber ser revisada por
el Ingeniero y recomendar su reparacin.
En la parte interior de las paredes se aplicar un repello de 1.50 cms, con una proporcin de una parte de
cemento por tres partes de arena. Posterior al repello, se aplicar un fino tipo espejo de cemento con
textura lisa. Se tendr especial cuidado con el curado de estos acabados, evitando agrietamiento por la
falta de humedad.

12

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Este tipo de tanque, tendr como accesorios complementarios: Tubera de entrada y salida, tubera de
limpieza y ventilacin y tubera de rebose. Todo de acuerdo a lo indicado en planos y secciones
anteriores.
CONCRETO CICLOPEO
El concreto ciclpeo consistir de un 70 porciento de concreto de (140 kg/cm2) y un 30 porciento de piedra
grande bruta por volumen slido de la mezcla. La piedra para esta clase de obras tendr un tamao que
pueda ser manejado por un hombre o por medio de un tecle, ser dura y sana.
Preferiblemente, la piedra deber ser angulosa y con superficie spera que le permita ligarse
completamente con la masa de concreto a su alrededor.
La piedra deber ser colocada sin daar la formaleta o el concreto ya colocado y parcialmente fraguado.
La piedra que tenga estratificaciones ser colocada sobre su cara natural. Las piedras debern ser
lavadas y saturadas con agua antes de ser colocadas.
En muros o pilas cuyo espesor sea mayor de 60 cms se usarn piedras de tamao manejable por un
hombre y cada piedra deber quedar rodeada por una capa de concreto de no menos de 15 cms de
espesor, a no menos de 30 cms de la cara superior ni a menos de 15 cms de un coronamiento.
Todo el interior del tanque ser repellado y afinado y luego se cubrir con un impermeabilizante.

ACCESORIOS DEL TANQUE


Para cada tanque, el Contratista deber suministrar los accesorios que se muestran en los planos y que
aqu se especifican:
Respiradero
El techo de cada tanque deber estar provisto de una abertura de ventilacin de conformidad al detalle
mostrado en los planos. Consiste en tubera de material PVC o HoGo del dimetro indicado, formando
con codos del mismo material, una U invertida. La entrada ser protegida con cedazo fino. Este tubo de
ventilacin ser colocado al centro de la tapa superior del tanque.
Tubo de entrada
Cada tanque deber estar provisto de un tubo de entrada. La tubera de entrada es de HoGo del dimetro
especificado, que anterior a su entrada est provista de una vlvula de compuerta de bronce y posterior a
su entrada, de una vlvula de boya de igual material y dimetro.
Tubo de salida
13

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Consiste en tubera de HoGo del dimetro especificado, situada a 0.05 mts sobre el fondo y provista de
una vlvula de pase de bronce del mismo dimetro del tubo.
Tubo de limpieza
Es de hierro galvanizado del dimetro especificado, ubicada en el fondo con una pendiente del 2% hacia
la salida. Su operacin se efectuar mediante una vlvula de bronce del mismo dimetro.
Rebosadero
Cada tanque deber tener un rebosadero de conformidad a los detalles y dimensiones que se indican en
los planos. Consiste en tubera de HoGo del dimetro especificado, unida a la tubera de limpieza a travs
de un codo de 90 grados y una tee del mismo dimetro y material.
12.2.2.7 OBRAS DE CAPTACIN Y PREFILTRO
La construccin de la obra de captacin, prefiltro y aireador debern ser construidas conforme a lo indicado
en la seccin tanque de almacenamiento de concreto reforzado, relativo a la fabricacin y colocacin de
concreto reforzado.
Para las actividades de trazado y nivelacin, movimiento de tierra, tubera y accesorios, etc., se debern
remitir a las especificaciones contenidas en las secciones correspondientes a estas actividades. Adems
se deber cumplir con todo lo especificado en los planos.

14

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

ESPECIFICACIONES DE OBRAS DE SANEAMIENTO


LETRINAS
1.- Disposiciones Generales
Estas especificaciones cubren los aspectos relevantes para el suministro de materiales y la
preparacin de los servicios que se consideran necesarios para llevar a cabo la construccin de
Letrinas.
Los Contratistas no podrn alegar omisiones en su oferta debido a desconocimiento e interpretacin
errnea de los documentos relacionados al proyecto.
Los Oferentes debern inspeccionar por sus propios medios el lugar de la construccin y sus
vecindades con el objeto de familiarizarse con todas las condiciones topogrficas, suelo, vas de
acceso, as como de las condiciones generales que puedan afectar el costo de los trabajos.
2.- Alcances de obra
La construccin de letrinas involucra las siguientes actividades:

Excavacin de fosa conforme la seccin especificada en planos.

Construccin de paredes para revestimiento.

Construccin de brocal.

Colocacin de losa inferior y banco.

Construccin de caseta.

Tubo de ventilacin.

Rotulacin en puerta.

Limpieza final y entrega.


3.-

Localizacin de sitios donde se construirn las letrinas

Estas obras se realizarn en los predios de cada una de las viviendas que integran el proyecto y
para lo cual se debern tomar los aspectos generales siguientes:

Localizacin y ubicacin del terreno, el cual debe tener las condiciones de permanecer seco y/o
libres de inundaciones.

En terrenos con pendientes altas, las letrinas se localizarn en las partes ms bajas.

La distancia mnima entre la letrina y cualquier fuente de abastecimiento de agua ser de 20.00
mts dentro o fuera del predio donde se construir.

La distancia mnima vertical entre el fondo de la fosa y el nivel fretico ser de 1.50 mts.
15

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

La distancia entre la casa y la letrina ser entre 5.00 y 10.00 mts.


Deber considerarse la direccin del viento al ubicar la letrina a sotavento de la vivienda.

En terrenos inestables, para evitar derrumbes durante la excavacin, ser necesario ademar las
paredes de la fosa con material local.

4.- Materiales
a) El forro de las paredes ser de zinc liso calibre 28 standard fijado con tornillos golosos de buena
calidad cabeza plana ranurada.
b) La cubierta de techo ser de zinc corrugado calibre 28 standard, fijado con tornillo goloso para
zinc con arandela de neopreno.
c) Las estructuras de las casetas y la estructura de techo sern de acuerdo a dimensiones
reflejadas en planos.
d) En los casos que el proyecto indique losa, asiento y tapa prefabricadas a base de resinas de
polister reforzadas o fibra de vidrio de alta densidad y/o de concreto reforzado; las medidas son
estndar, como se refleja en los planos constructivos. Cada una debe llevar agujero para la
colocacin del tubo de ventilacin.
e) El ladrillo cuartern slido de barro cocido clase A se deber utilizar para la construccin de
paredes con las medidas de 2x6x10. Se colocarn presionndolos firmemente sobre una
camada de mortero 1:4 que cubra la superficie de la hilera inferior. No se permitirn ladrillos
quebrados ni de medidas diferentes excepto previa autorizacin del Ingeniero.
f) Los bloques que se utilizarn para revestimiento de fosas deben tener una resistencia mnima
del 80% a la norma standard del cdigo de la construccin. Se colocarn presionndolos
firmemente sobre una camada de mortero 1:4 que cubra la superficie de la hilera inferior.
g) Los elementos estructurales de acero se pintarn con anticorrosivo de color rojo, aplicada sobre
la estructura, a dos manos de acuerdo a las recomendaciones del fabricante.
h) Se podr utilizar arena de ro que no est contaminada, que tenga la granulometra adecuada,
debe estar limpia y tamizada, antes de usarla debe estar autorizada por el Ingeniero.
5.- Excavacin
En general, a menos que el Ingeniero indique lo contrario, la profundidad del foso ser conforme lo
indican los planos, tomando como nivel el terreno natural. Cuando el suelo es inestable debe ser
totalmente revestido con ladrillo cuartern, bloque, piedra cantera o el material que se indique en los
planos.
El fondo de la fosa deber quedar perfectamente nivelado, sin la presencia de bolones que se
pudiesen encontrar durante la excavacin.
En ningn caso se permitir al Contratista excavar menos de la profundidad estipulada en los
planos, cualquier situacin que impida esta disposicin deber ser solicitado por escrito al Ingeniero.
16

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

El Contratista deber tomar las precauciones necesarias durante el proceso de excavacin para
evitar acumulacin de aguas, inundaciones por escorrentas, lluvias o fuentes de agua internas que
se puedan sellar.
Las dimensiones de la fosa estn indicadas en los planos, las que podrn ser para letrinas standard,
semi elevadas o elevadas, las medidas del rea son standard para todos los casos, excepto cuando
la letrina no es revestida, en la cual se considerar la excavacin adicional en el rea
correspondiente al brocal.
Cuando el foso es revestido, las medidas de la fosa son las indicadas en los planos ms 0.15 mts
correspondiente al ancho del material a colocar como paredes.
En terrenos flojos que se indique la construccin de letrinas estndar, es responsabilidad del
contratista tomar las medidas de precaucin para evitar derrumbes, por lo que habr necesidad de
ademar las paredes de la fosa, utilizando materiales existentes en la regin. El costo de la actividad
de ademado lo debe considerar el Oferente en los indirectos de su oferta.
El Contratista deber someter la metodologa y programa de construccin al Ingeniero para cumplir
en tiempo y forma con sus obligaciones contractuales.
6.- Restricciones y Calidad del Trabajo
a) No se permitirn fosas abiertas por perodos mayores de tres (3) das, previo al inicio de las
obras de revestimiento de paredes y/o a la colocacin de la losa y banco.
b) Los materiales de excavacin y de construccin de la fosa debern ser colocados donde no
obstaculice el trnsito de los miembros de la familia a beneficiar. Los materiales de excavacin
deben ser esparcidos convenientemente en el predio previa autorizacin y disposicin del
beneficiario.
c) El Contratista deber prever que durante el periodo de construccin las fosas no recolecten
agua pluvial o de cualquier otra fuente. El contratista remover por su cuenta toda el agua que
se colecte en las fosas por accidentes, negligencia o casos fortuitos.
7.- Construccin de Paredes del Foso y Brocal
De acuerdo a la prctica constructiva que se exige para la construccin de paredes de bloque,
ladrillo cuartern, piedra cantera u otro material indicado, esta deber presentar aplomo y escuadra
en todos sus lados.
Las paredes deben estar cimentadas segn el caso: para las letrinas semi elevadas y elevadas
deben llevar una losa de concreto simple en toda el rea del fondo del foso con un espesor de 0.05
mts. En el caso de las letrinas standard, las paredes de revestimiento (brocal) deben montarse sobre
17

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

un cordn perimetral de mortero 1:4 de 0.05 mts de espesor por el ancho correspondiente al ladrillo
de revestimiento. Todas las paredes debern tener un espesor mnimo de 0.15 mts.
Al concluir la construccin del brocal y la caseta de la letrina, se debe forjar un talud entre el terreno
natural con el pie de pared, en los costados y la parte posterior para evitar la penetracin de agua
pluvial.

18

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

8.- Construccin y Colocacin de Plancha y Banco


La plancha y banco de la letrina ser construida e instalada segn se indique en los planos, las que
podrn ser de fibra, plstico o de concreto reforzado, estas debern ser colocadas a nivel y a
escuadra en funcin del brocal. Debe observarse que las aristas superiores de los bancos deben ser
biselados, sin escorias o puntas.
9.- Construccin y Colocacin de Caseta
La estructura de paredes ir fijada a las anclas que se han empotrado de previo en las bases de
concreto correspondientes al brocal. La estructura para las paredes podr ser:
a) De madera blanca, la que debe estar seca, sana, sin nudos, sin defectos, debe ser aserrada de
forma pareja y a escuadra en todas sus caras, la seccin para cada una de las piezas ser de 2x2
con una tolerancia mxima de 1-7/8. Las piezas para la estructura de paredes como para el techo
sern de una sola pieza, con la longitud indicada en los planos.
En la estructura de madera se podr utilizar variedades de reconocido uso en la construccin, que
tengan durabilidad mayor a 4 aos, entre estas maderas estn: Pino, Guanacaste, Cedro macho,
Rosita o Manteco, Carolillo, Genzaro, Gaviln entre otras. Todas las piezas debern estar secas y
tratadas con productos qumicos contra comejen. El acabado de la madera deber ser repasada
(acepillada y/o eliminar lo rstico y mechudo) en las caras expuestas.
Entre las maderas que se consideran no utilizables por la falta de durabilidad o por su condicin
fsica al exponerse a la intemperie son: Palo de Agua, Panam, Sebo, Helequeme, Javillo, Manga
Larga, Alcanfor, Sangregrado, Talalate, Ceiba, Espavel, Acetuno, entre otras.
Los herrajes para madera se fijarn con 3 bisagras de 2x2 galvanizada, fijadas con tornillos
golosos ranurados. Los tornillos deben quedar a tope y planos a la placa de bisagra.
b) La estructura metlica, estar formada por angulares de hierro industrial nuevo de buena calidad,
estar empotrado en las base de concreto correspondientes al brocal y fijadas entre si por medio de
pernos de hierro con arandelas y tuercas.
Los Herrajes para estructura metlica se fijarn con una bisagra artesanal formada por ejes de
hierro de y tubo cuadrado negro soldado a la estructura.
El forro o cerramiento de la caseta para todos los casos ser de zinc liso calibre 28 standard,
estar fijado a la estructura por medio de tornillos golosos para metal con cabeza. La colocacin
del forro de zinc no debe presentar bordes salientes, puntas corto punzantes, virutas que puedan
ocasionar cortaduras a los usuarios.
Al colocar el tubo de ventilacin debe quedar sellado entre la cubierta de techo, de igual forma en
la unin con el piso.
19

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

En la puerta se pintar un letrero con el nombre y logotipo del FISE, con tamao de 4x3. Las
letras para el N de Contrato y del cdigo es de 2. La pintura debe ser de aceite brillante
conforme los colores establecidos en el detalle de planos.
10.- Proteccin de Propiedades y Estructuras
El Contratista deber asumir todos los riesgos inherentes a la presencia o proximidad de paredes,
viviendas, cercos, estructuras, servicios pblicos y propiedades situadas en la vecindad de su
trabajo. Ser responsable por todos los daos y deber asumir los gastos por perjuicios directos e
indirectos, de acuerdo a lo requerido por la persona propietaria de la estructura o de la que est a
cargo de la misma, ya sea que dichas estructuras estn o no mostradas en los planos.
11.- Medicin de los trabajos y forma de pago
Todos los trabajos a ejecutarse dentro de los alcances estimados de obra se pagarn conforme
avance de ejecucin del proyecto y conforme las unidades totalmente terminadas.
Trabajo defectuoso.- Todo trabajo que ha sido rechazado deber ser remediado satisfactoriamente
por el Contratista de modo aceptable y sin ninguna compensacin adicional por el FISE.
12.- Limpieza final
El Contratista una vez terminado el trabajo, eliminar toda basura, material sobrante de la
construccin, dejando en condiciones originales y limpio el terreno y la letrina.
INODORO ECOLOGICO
A continuacin se describen las partes del inodoro, algunas de ellas deben ser elaboradas en el
taller antes de ser trasladadas al destino final donde se instalar el inodoro ecolgico popular.
Taza-sanitaria con asiento:
Una taza sanitaria (inodoro) de porcelana como las que se usan en los barrios residenciales, la que
descansa sobre un pequeo pedestal cuyo tamao es un poco ms grande que la taza. Esta tazasanitaria no tiene tanque de agua ni trampa o sifn, de manera que no requiere tanta agua para
descargarse, pues se descargar con el orn y la gravedad, requiriendo a lo sumo un litro de agua,
pero solamente en caso de defecacin, no as cuando se usa para orinar. Este sistema es el ms
ahorrativo de agua de los que hemos ensayado con sello hidrulico, algo muy importante sabiendo
que hay muchos lugares donde escasea el agua potable o no hay servicio del alcantarillado. El
hecho de no tener la trampa en el propio inodoro, evita el congestionamiento de las heces al interior
de la taza, lo que de acuerdo a la experiencia desestimula su uso por parte de la familia.
El pedestal que sostiene la taza-sanitaria se construye de Covintec enchapado con cemento, a fin de
facilitar su traslado y abaratar los costos frente a una construccin de concreto. El soporte del
20

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

asiento se construye con tubos y codos de PVC con el objetivo de fijar el asiento de la taza sanitaria
al pedestal. El pedestal se elabora cortando un trozo de Covintec de 46 cm. cuadrado, (parte plana
superior), dos trozos de 46 cm. de largo por 16 cm. de ancho y dos trozos de 31 cm. De largo por 16
cm. de ancho (cuatro lados del pedestal), estos se unen a la parte de 46 cm. fijndose con alambre
de amarre, tomando la forma de un cubo, se cubre con un pedazo de malla gallinero de 1 m.
cuadrado amarrado siempre con alambre de amarre, en el centro del pedestal a 16 cm. de uno de
los costados se abre un hoyo de 3 de dimetro por donde se introduce el tubo de 3 por 28 cm. de
largo que une el inodoro con el tubo de acarreo a travs de un codo de 3 y en un molde de madera
de 50 cm. cuadrado por 28 cm. de alto se reviste de mezcla de arena y cemento, dejndose secar
por dos das. El pedestal ya terminado debe tener una medida de 28 cm. De alto por 50 cm. De lado
en la parte plana superior.
El soporte del asiento que se confecciona de tubo y codos PVC de , 32 cm. de alto por 22 cm. De
ancho y se llena de cemento y arena, sirve para fijar el asiento al pedestal.
Tubo de acarreo:
El tubo de acarreo es un tubo de PVC de 3 de dimetro y est compuesto por dos partes: una parte
horizontal de 40 cm. De largo y una parte vertical de 1.5 m. de largo. Dicho tubo une y acarrea las
excretas (orina y heces) hacia el depsito de descomposicin o barril; este tubo de acarreo penetra
al depsito de tratamiento por un orificio de 3 de dimetro en la parte superior y a travs de un codo
se inclina verticalmente hacia el fondo del barril, el transporte del material se logra inclinando
ligeramente el tubo.
El tubo que acarrea las excretas se coloca con una ligera pendiente (1.5% en dos metros), la cual no
debe ser tan pronunciada (1 pulgada es suficiente); una inclinacin mayor provoca un arrastre ms
rpido del lquido u orina, dejando retrasados los slidos, mientras que una inclinacin leve permite
que los slidos se encaminen casi flotando. Al llegar al barril entra por la tapadera del mismo,
inclinndose por medio de un codo de 90 grados. Este tubo penetra hasta la mitad del barril, de
manera que una vez inundado por el material acuoso que entra al barril sirve como sello de agua.
Tanque sptico o depsito de descomposicin.
El tanque sptico o depsito de descomposicin est compuesto por un barril de plstico que mide
81 cm. de alto y 49 cm. de dimetro, y con una capacidad de 33 galones. Tiene como objetivo recibir
las excretas (heces y orina), liquificarlas y eliminar un buen porcentaje de las bacterias pues las
mismas se encontrarn en un ambiente anaerbico. Este barril se encuentra enterrado en una fosa,
procurando que quede holgado y que la parte superior se site a ras del suelo. El barril queda
cubierto con su tapa plstica y se le pone una brida para sellarlo.
El barril plstico es donde se lleva a cabo la biodigestin est enterrado en el suelo y est destinado
a recibir el material que llega desde la taza a travs del tubo de acarreo. Aqu se realiza la
descomposicin de la materia orgnica y la mineralizacin o transformacin de materiales orgnicos
en inorgnicos.

21

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Cuando el depsito empieza a funcionar tendremos cuatro niveles: un fondo o lodillo generado por la
sedimentacin, un rea de lquido con algunas partes slidas, una nata en la superficie y una
cmara o vaco que almacena y expulsa el gas generado por la biodigestin.
Al barril plstico se le hacen dos perforaciones con un molde metlico caliente de 3 de dimetro
(como los fierros para herrar ganado): una perforacin en la tapadera a 5 cm. Del borde, por donde
entrar el tubo de acarreo a travs de un codo PVC de 3, la otra perforacin, en el costado opuesto
del barril, a 10 cm. debajo del borde, por donde saldr el tubo de drenaje a travs de un codo PVC
de 3.

Tapadera y tubo-respiradero:
La tapadera sirve para tapar la fosa del tanque sptico y sellar el brocal de la misma. Esta tapadera
se elabora igualmente con material Covintec enchapado con cemento. A esta tapadera se le abre un
orificio por donde entrar el tubo respiradero que expulsar los gases y el mal olor hacia la
atmsfera. El tubo respiradero se elabora cortando un pedazo de tubo de PVC de de dimetro
por 2 m. de alto y se coloca una T de en el extremo superior. En la tapadera plstica del barril y a
15 cm., de uno de los bordes, se hace una perforacin con un metal caliente de de dimetro por
donde saldr el tubo respiradero. Un extremo del tubo penetra la tapadera de la fosa y la tapa del
barril, situndose en la cmara que queda entre el nivel del lquido del barril y la tapa del mismo; la
otra parte del tubo sale sobre el nivel de la tapadera de la fosa con el objetivo de dejar salir el gas y
el mal olor. A la tapadera se le hace un orificio de de dimetro, por el cual saldr el
tuborespiradero.

Tubo de drenaje:
El tubo de drenaje es un tubo de PVC de 3 de dimetro y est compuesto por dos partes: una parte
vertical que va dentro del barril, y una parte horizontal que descansa sobre la zanja de infiltracin. La
parte vertical que mide 40 cm. de longitud sube del fondo del barril, dejando una rendija de entrada a
6 pulgadas del plan por donde subirn los slidos una vez liquificados. Este tubo-dreno sube hasta
llegar a un orificio de salida en el costado del barril coronado por un codo de 90 grados que gira
hacia la zanja de descarga final del efluente. La parte horizontal del tubo de drenaje tiene una
longitud de 3 o 4 m. dependiendo de la capacidad de absorcin del suelo donde se coloca el inodoro
ecolgico. La altura del orificio de salida debe estar a 10 cm. debajo de la tapa del barril, pero por
debajo del nivel del primer tubo de entrada o de acarreo. A la parte del tubo de drenaje que se coloca
en la zanja de infiltracin deben hacrsele varias ranuras con un metabo o circular. Las ranuras de
de ancho y 3 de largo deben hacerse en la parte media de ambos costados, ni muy arriba, ni
muy abajo, por donde el efluente bastante descontaminado que sale del barril se esparcir a lo largo
de la zanja que le sirve de lecho.

Zanja de infiltracin:
La zanja de infiltracin mide 3 o 4 m. de largo y al menos 50 cm. de profundidad. En el lecho de la
zanja se esparce una delgada capa de arena de 10 cm., encima se adicionan otros 20 cm. de piedra
boln u hormign para terminar de filtrar el efluente o material acuoso que sale de la fosa de
descomposicin. Debido a su drenaje constante, el barril no se llena nunca y debido al proceso de
hidrlisis constante, mantiene una sedimentacin muy baja. Esta zanja de infiltracin es el lugar
22

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

donde se realiza la evaporacin y la infiltracin o depuracin por filtrosuelo de los efluentes; la zanja
est cubierta por un camelln de tierra y sobre este lecho caern los rayos solares que volvern ms
agresivo el ambiente para los patgenos.

rea de races:
En la superficie y a ambos lados de la zanja de infiltracin y del tubo de drenaje se encuentra
finalmente el rea de races, las que terminarn de depurar las aguas o efluentes finales. Encima de
esta zanja se siembran arbustos de races pequeas, tales como flores, zacate, arbustos, grama o
simple monte, con el fin de conformar un rea de races, tambin pueden sembrarse frutos altos
como el pltano; lo que no se recomienda son plantas comestibles de topologa rastrera, pues son
contaminables (tomate, lechuga, otras). Estas races competirn por agua, aire y nutrientes con los
microorganismos patgenos que todava no han sido destruidos por el tratamiento anterior.
SELECCIN DEL TERRENO Y CAVADO DE FOSA Y ZANJA
Se selecciona el terreno y se lleva a cabo la medicin donde se cavarn las fosas y la zanja de
infiltracin. El hoyo donde se coloca el tanque sptico tiene 1 m. de hondo por 56 cm. De dimetro,
la zanja de infiltracin tiene 50 cm. de hondo, 30 cm. de ancho por 3 m. de largo, la fosa donde
desemboca el tubo de drenaje tiene 50 cm2 por 60 cm. de hondo. Esta ltima tarea deber hacerla
la familia beneficiaria.
La hechura del pozo es la parte de la instalacin que requiere ms cuidado en la instalacin es la
hechura de la fosa donde se colocar el depsito o barril. Primero se hace un crculo, utilizando un
comps de campo, es decir, una soga o manila unida por dos clavos, uno clavado suavemente en el
centro del crculo y sostenido por una mano, y el otro suelto y manejado por la otra mano, de manera
que permita girarlo alrededor del centro, tal como aparece en la foto. El permetro del crculo deber
ser cuatro pulgadas ms ancho que el dimetro del barril que se utilizar, con el fin de que las
paredes del barril no estn pegadas a las paredes de la fosa, evitando as la presin de la tierra,
sobre todo cuando est mojada por el invierno, presione o apachurre el barril. Una vez que se ha
rayado el crculo se procede a rayar dos cuadros sucesivos que rodeen el crculo y a colocar dos
moldes que facilitarn la tarea; el primer cuadro que besa la tangente del crculo se hace con el fin
de dejar los cuatro angulares que quedarn una vez que se cav la fosa, en estos angulares es
donde descansar la tapadera de la fosa. Esto se hacer para dejar establecido los soportes cuatro
soportes sobre los que se colocar la tapadera. Recordemos que la tapadera es cuadrara y el crculo
redondo para que penetre el barril. Si el orificio se hace cuadrado, la tapadera caera sobre el barril,
pues no habra nada que la detenga, lo mismo pasara si hacemos la tapadera redonda.
En el segundo cuadro, dos pulgadas ms grande que el primero, se coloca el segundo molde; entre
ambos cuadros quedar un espacio que servir para construir una cadena o brocal de contencin
para proteger la entrada de la fosa.
Vase el espacio triangular que se forma entre el crculo y el cuadro que besa la tangente del
crculo, el que tiene que dejarse para usarlo como soporte para que la tapadera o loza superior no
caiga adentro de la fosa.
23

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Dependiendo de las condiciones, es recomendable utilizar un depsito o barril de mayor capacidad


con el fin de conseguir un mayor tiempo de retencin de los agentes patgenos al interior del agua,
aunque como dijimos, el proceso ms efectivo de descontaminacin es el efectuado una vez que el
efluente haya salido a la superficie (evaporacin, infiltracin, rayos solares y competencia de las
races).
COMO SE INSTALA EL INODORO ECOLOGICO
Una vez que se han trasladado las piezas y herramientas en el campo y se hayan hecho las
excavaciones necesarias procedemos a la instalacin del sistema.
Primer paso: Pegar los terminales de los tubos de entrada y salida en los extremos internos de
los codos, colocando papel peridico en los enlaces para no sellar definitivamente los goznes, pues
a veces se necesita desarmar todo el andamiaje. Poner la tapadera y ajustar brida (en caso que
exista); esta ltima se debe pintar con anticorrosivo en sus partes metlicas para protegerla de la
humedad y la corrosin.

Segundo paso: Ubicar el tanque sptico en el hoyo, conectar tubos de acarreo y drenaje,
colocar la tapa de caja de registro y hacerle anillo de cemento y arena, colocar el tubo respiradero,
cubrir la tapadera con un pliego de plstico negro de 1.20 m.1/2, colocar tierra en el borde del
plstico, a fin de proteger la caja de registro de la entrada de aguas pluviales o escorrentas.
Tercer paso: Colocar una capa de 20 cm. de piedra boln mediana en la zanja de infiltracin,
rellenar la fosa ubicada al final de la zanja con piedra boln mediana.
Cuarto paso: Instalar el pedestal conectando al tanque sptico a travs de un codo y tubo de
acarreo, fijar el inodoro al pedestal con pernos y cemento, fijar asiento del inodoro al pedestal.
Quinto paso: Cubrir el tubo de infiltracin con una cinta de plstico negro de 30 cm. De ancho
y 3 m. de largo, colocar una capa de piedras de 10 cm. y rellenar de tierra formando un camelln
sobre la zanja de infiltracin, colocar un codo de PVC de 3 en la desembocadura del tubo de
infiltracin, llenar la fosa con piedra boln mediana 10 cm. Por encima de la altura del codo, colocar
un pedazo de plstico negro de 50 cm2, finalmente poner una capa de tierra en forma de
promontorio.
Sexto paso: La caseta (opcional) se ensambla en el terreno fijando las piezas de angulares con
pernos de 5/16 de 1, enterrando 30 cm. en el suelo con una base de cemento y arena, el techo se
confecciona con tres platinas de 1 y 1.46 m. de largo empernadas con pernos 5/16 de 1 y dos
lminas de zinc de 6 pies fijadas con pernos punta de broca para techo, el forro de lona se coloca
metiendo dos pedazos de tubos PVC de en los ojales y empernando en la estructura con pernos
3/16 de 1.5, se colocan tres venas de tubos PVC en los cantos de los angulares para proteccin de
la lona. La puerta se confecciona en un marco de tubos PVC de y lona ojaleada de 1.6 m. de alto
por 59 cm. de ancho, se cuelga con bisagras de 1 x 2 y pernos de 3/16 de 11/2.
24

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

Piezas de la caseta opcional. La caseta diseada por CIPRES para albergar el inodoro
ecolgico est compuesta por 4 angulares de 1 1/2 de ancho y de 2.35 m. de largo, 4 angulares de
11/2 y de 1 m. de largo, 4 angulares de 11/2 y de 1.30 m. de largo, 1 angular de 11/2 y de 2 m. de
largo, 2 lminas de zinc de 6 pies, 3 platinas de 1 y de 1.46 m. de largo, 1 lona ojaleada de 1.6 m.
de ancho por 4.16 m. de largo, 2 tubos PVC de y 1.60 mts de largo, 3 venas de tubos PVC de
1/2, 1puerta de tubo PVC y lona de 1.60 m. de alto por 59cm. de ancho, 3 bisagras de 1 x 2, 24
pernos de 5/16 de 1, 21 pernos de 3/16 de 1, 6 pernos de 3/16 de 11/2 ,9 pernos punta de broca
para techo.
ADVERTENCIAS Y RECOMENDACIONES
a) Es preferible y ms barato construir en serie el Inodoro Ecolgico Popular y despus llevarlo en
piezas al lugar donde se instalar. Asimismo, se recomienda comprar las piezas al por mayor, de lo
contrario sale ms caro.
b) Aunque puede estar dentro de la casa, es ms recomendable colocarlo fuera de ella, pues estar
ms aireado. Una vez que se ha decidido ponerlo fuera de la casa, habr que escoger el terreno
donde se instalar el Inodoro Ecolgico Popular. Aunque est diseado para descontaminar in situ el
suelo, es preferible instalarlo en un terreno plano y lo ms alejado que se pueda de alguna fuente de
agua o pozo. Asimismo, hay que tomar en cuenta tanto el grado de permeabilidad del suelo como de
anegamiento o saturacin del mismo. Nosotros pensamos que 50 centmetros para la zanja de
infiltracin y contemplar terrenos que tengan al menos un metro de profundidad antes de llegar al
manto fretico.
c) Evitar el exceso de agua que se vierte o eche al interior de la taza, pues mientras menos agua se
use ms lenta es la circulacin y ms tiempo de retencin obtenemos del material al interior del
depsito o barril. Esto no es difcil de conseguir, pues aunque la gente tiene por costumbre echar
bastante agua, es este caso no tiene sentido hacerlo al momento de orinar, sino slo al momento de
defecar. En otras localidades donde hay escasez de agua, esta recomendacin se logra mucho ms
fcilmente. Recordemos que el mayor nivel de depuracin se logra cuando el efluente se lleva a
cabo por infiltracin y competencia con las plantas. En caso de que se quiera limpiar se recomienda
no hacerlo con cloro ni creolina, sino con un poquito de alcohol mezclado con agua, para no interferir
el proceso de descomposicin.
d) En relacin al tubo vertical que entra al depsito o barril, se recomienda dejarlo a una altura media
entre el fondo y la parte superior del mismo. Ni muy alto para evitar que las burbujas de gas salgan
con facilidad regresando a la taza. Ni muy bajo para evitar que la cada del agua remueva el lodillo,
acelerando as la salida prematura del mismo antes de que el medio acuoso haga su efecto sobre
los patgenos.
e) En relacin al tubo de ascensin, es decir, el tubo que va del fondo del depsito hacia el orificio
superior de salida, es recomendable que est suspendido a una altura de tres pulgadas del fondo. Ni
ms bajo, porque mientras ms pequea es la ranura, ms rpido circula el agua y menos tiempo
tendramos de retencin. Ni ms alto, porque mientras ms separado se encuentre del fondo, ms
fcilmente entrarn los slidos y menos tiempo de retencin de los mismos tendramos para el
proceso de descomposicin.
25

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

f) En relacin al rea de races generado por las plantas que deben sembrarse sobre la superficie
del tubo de drenaje final, recomendamos que se planten arbustos pequeos como el limn criollo o
algunas variedades de chile, pues as aprovecharamos el bioabono y la humedad para aumentar la
fertilidad. La advertencia para no sembrar plantas que puedan contaminarse, slo se refiere a los
tubrculos o races que puedan entrar en contacto con los patgenos (lechuga, rbano, yuca,
malanga, remolacha, papas y otros), los frutos que no entran en contacto directo no tienen mayor
problema, ya que la contaminacin de las bacterias no se hace por la cadena molecular de la planta,
sino por contacto directo con el fruto o con las personas. Los arbustos no deben estar encima del
tubo de drenaje, ni deben ser muy frondosos, para no quitarle luz solar al rea de absorcin.
g) No se debe echar en la taza del inodoro ningn tipo de papel u otros objetos ya que estos tardan
en degradarse, obstaculizando el proceso de descomposicin e infiltracin subterrnea de los
desechos.
h) La cantidad de agua que debe echarse al inodoro cada vez que se usa es lo que alcanza en el
pichel que se les ha proporcionado para este fin, un litro en total.
i) Es recomendable sembrar a los lados del tubo de drenaje plantas de jardn de races pequeas o
de frutos altos como el pltano para que contribuyan al proceso de descomposicin absorbiendo el
aire, agua y nutrientes que se acumulan en el rea de ferti -irrigacin aledaa al tubo de drenaje.
Recordemos que no se deben sembrar rboles de races grandes y profundas que puedan daar las
instalaciones, tampoco plantas rastreras como ayote, sandas meln, etc. en el rea de fertiirrigacin aledaa al inodoro y tubo de drenaje.
j) Se debe construir una caseta alrededor de la taza del inodoro y una capa de cemento en el piso
dentro de la caseta a fin de garantizar confort y privacidad.
k) Cuando se requiera hacer limpieza general de la taza del inodoro, no se debe utilizar mucha agua,
para evitar la saturacin del sistema por exceso de agua.
l) Mantener la taza del inodoro siempre tapada para evitar la introduccin de objetos extraos.

26

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

12.3

PLAN DE OPERACIN Y MANTENIMIENTO (POM) DEL SISTEMA

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

12.4

LISTA DE RESULTADOS, MEMORIAS, FICHAS, AVALES, DOCUMENTOS LEGALES,


ACTAS DE COMPROMISO

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

12.5 RESULTADO DE CALIDAD DEL AGUA FSICO-QUMICO

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

12.6 RESULTADO DE CALIDAD DEL AGUA MICROBIOLGICO

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

12.7 RESULTADO DE LABORATORIO DE SUELOS

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta

Informe de Factibilidad Proyecto: Construccin de Sistema de Agua y


Saneamiento El Achiote Cdigo 19200
NUEVO FISE - Alcalda Municipal de Bocana de Paiwas 2012

12.8 MEMORIA DE CLCULO DEL DISEO ESTRUCTURAL

FIRMA CONSULTORA: CONDISA


Bravo M.

Diseo: Ing. Mirta Violeta