You are on page 1of 2

SAUDI ARAMCO ID/PID FORM REV 1 - 310811

Rev 4

31-Mar-11
SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


PORTABLE FIRE PROTECTION EQUIPMENT INSTALLATION

SATIP-B-019-01

PROJECT TITLE:

ITEM
NO.

PROJECT PHASE &


ACTIVITY CODE

1.0

DOCUMENT REVIEW

1.1
2.0

APPROVED DATE

WBS/BI/JO/NO.

TASK / ACTIVITY

QUALITY
PROCEDURE

QUALITY
RECORD

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

SAUDI
ARAMCO

REMARKS

NONE
MATERIAL RECEIVING

2.1

SAIC-B-2011

2.2

Storage, Handling & Preservation

SAIC-B-2012

SAIC-B-2012

3.1

Portable Extinguishers

SAIC-B-2013

SAIC-B-2013

3.2

Foam Generating Equipment

SAIC-B-2014

SAIC-B-2014

3.3

Special Fixed Extinguishing equipment

SAIC-B-2015

SAIC-B-2015

3.4

Structural Welding for supports

3.5

Access and Platforms

3.6

Painting works and Safety color coding

4.0

MECHANICAL

31-Aug-11
CONTRACTOR/SUBCONTRACTOR

Material Verification & Inspection


a) Portable Fire Extinguishers
b) Mobile Foam Apparatus
c) Carbon Dioxide Extinguishing Systems
d) Halon 1301 Fire Extinguishing Systems SAIC-B-2011
e) Dry Chemical Fire Extinguishing
Systems
f) Fire Hose Including Connections and
Nozzles

3.0

DISCIPLINE:

S. Aramco will inspect the first batch of delivery for each


type of equipment.

INSTALLATION

Refer to SATIP-M-001-04

SAIC-B-2016

SAIC-B-2016

Refer to SATIP-H-100-01

PRE-COMMISSIONING

4.1

Re-instatement/Final Inspection of
Portable Fire Protection System

SAIC-B-2017

SAIC-B-2017

4.2

Mech Completion Punch listing


(Partial or Final MCC)

SATR-A-6133

SATR-A-6133

Page 1 of 2

USE SATR-A-2011

Utilize SAIC-B-2017 to accumulate any FEIL items.

SAUDI ARAMCO ID/PID FORM REV 1 - 310811

Rev 4

31-Mar-11
SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


PORTABLE FIRE PROTECTION EQUIPMENT INSTALLATION

APPROVED DATE

SATIP-B-019-01

PROJECT TITLE:

WBS/BI/JO/NO.

ITEM
NO.

PROJECT PHASE &


ACTIVITY CODE

1.0

DOCUMENT REVIEW

TASK / ACTIVITY

QUALITY
PROCEDURE

QUALITY
RECORD

DISCIPLINE:

31-Aug-11

MECHANICAL

CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

REMARKS

SAUDI
ARAMCO

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
of Saudi Aramco participation based upon the Contractors performance.

Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization

Witness:
QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is
not present.

Hold:

If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

100% Hold Point for QC Inspection or Test.

Witness Inspection/Test

QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.

LEGEND
R
RH

Review of Documents
Review and Approval of Documents

Page 2 of 2